Upload
erkegroup
View
232
Download
0
Embed Size (px)
Citation preview
7/30/2019 ERKE Group,Trio 3x200HD PTC Vibrodriving monopiles in the Anholt Offshore wind farm, Denmark
1/2
The Anholt windarm will become Denmarks largest oshore wind arm with an
overall capacity o 400MW and will cover 4% o Denmarks total power consumption.
THE PROJECT
Dong Energy wanted to test Vibrodrivers technology as an alternative solution to
impact hammers, or driving monopile oundations in oshore windarm projects
while reducing noise emissions under water.
The job required driving monopiles o conical shape with a bottom diameter
exceeding 5m and weighing 275 t. The complexity o this job with harsh oshore
weather conditions and heavy piles, required a customised solution that PTC had
the capability to provide in a very short time delivery.
The pile driving equipment proposed by PTC was a Trio o 2OOHD Vibrodrivers
perectly synchronized to get an eccentric moment o 600 m.kg. These
Vibrodrivers were powered by 3 PTC power packs 1200C model, supplying
a tota l power o 2418 kW. A PTC Vibmaster monitoring system was used to
display and registered important piling data, such as depth, vibration amplitude and
power.
DONG Energy, which has erected half of the worlds majoroffshore wind farms, is currently building Denmarks large-scale offshore wind farm, which includes an area of 88kmbetween Grenaa and the island of Anholt.
Trio 3x200HD driving monopiles
in the Anholt Offshore wind farm,Danemark
KEY FACTS
Patented
synchronisation
technology
275 t conical
shaped monopile
600 m.kg
eccentric moment
2418 kW
7/30/2019 ERKE Group,Trio 3x200HD PTC Vibrodriving monopiles in the Anholt Offshore wind farm, Denmark
2/2
FIRST PHASE: ONSHORE TEST, SYNCHRONISATION IS THE KEY
The synchronisation o the 3 Vibrodrivers as well as the 3 power packs was a complex task. PTC studies
in this matter, resulted in a patented synchronization technology based in PTCs long time know how in
mastering vibration and producing high-end power packs.
In order to adjust the synchronisation o the PTC equipment beore taken it to the barge, the jobsite begun
with a onshore test. In this inital phase taken place in the Aalborg harbour, the Trio o PTC 200HD drove
into the ground a shorter test pile, which was then extracted with the same equipment. PTCs technological
approach was confrmed and the equipment was then taken to the barge.
SECOND PHASE: OFFSHORE PILE DRIVING
The next phase o the project was oshore in the waters o Kattegat between the North and the Baltic seas,
and just a ew kilometers away rom the Anholt island.
The PTC pile driving equipment was
installed in the SVANEN barge owned by
the company Ballast-Nedam. PTC servicetechnicians qualifed or oshore operations
were on board as well, and assured the
operations and the equipment installation,
commissioning and support until the end o
the jobsite.
The driving o the 275 ton piles started as
soon as the weather conditions were
avourable . The piles were driven to
the stipulated depth in less than 30 min
in a soil consisting o dense sand and
compact silty sand.
In addition o an excellent driving speed
o the pile, PTC Vibrodrivers proved a
signifcant environmental advantage, as
these vibrators can drive the pile respecting
the most recent German regulations in
noise emissions under water. Dong Energy
perormed several sound measurements
and confrmed its satisaction in the PTC
driving solution or oshore windarms.
On the Svanen barge,
during the driving of the
conical shape monopiles.
During the test phase,
the Trio of 200HD Vibrodrivers
with six 250 t clamps
at the Aalborg Harbour.