ERCOT Project Update
Commercial Operations SubcommitteeApril 10, 2007
Adam MartinezMarket Operations Division Projects Organization
Please Note: These slides are best viewed in Slideshow mode
2April 10, 2007 Page 2
2007 MO PPL
Unplanned 2006 Carry-over Projects(Green Shaded Area)
Projects ABOVE the Capability Line
(Orange Shaded Area)
Projects BELOW the Capability Line
(Yellow Shaded Area)
3April 10, 2007 Page 3
Unplanned 2006 Carry-Over Projects
• Only remaining active project is ERCOT.com Registered Access– Scope of project is presentation of Operations and System Planning Data (Tmaps) data on the ERCOT public website– This project was transferred from the RO PPL to the MO PPL in late March– RMS requested the transfer, COPS informed at March meeting
SourceCommi
tteeSource
DocProject Project No.
Current Status
2007 Priority2007 Rank
2007 Budget Range
2007 Running Range
Market MO PRR312Enhance ESIID Lookup Function
50025_01 Closing n/a
ERCOT MO Lodestar Extracts 40042_06 Closing n/a
Market MOPRR283 PIP204
EPS Meter Data 30026 Complete n/a
ERCOT MO Maestro Replacement 50137_01 Complete n/a
ERCOT MO Maestro Replacement - Phase 2 50137_02 Cancelled 0 - Carryover 0.1 <$50k <$1M
ERCOT MO ERCOT.com Registered Access 60077_01 Execution 0 - Carryover 0.3 $100k-$250k <$1M
4April 10, 2007 Page 4
Projects ABOVE the Capability Line
• New project added above the capability line – Collage Infrastructure Project– ERCOT source, Priority 1 – Critical, Rank 8.5, $250-$500K initial budget– Collage is the ERCOT’s content management tool for its public websites
• ERCOT.com, Texas Nodal Market Implementation website, Operations and System Planning Data, other smaller websites (Retail Testing Website, internal ERCOT employee sites)
– Project addresses potential limitations with Collage environments ability to manage and maintain websites’ content• Nightly content update process increased from 7 hrs to 12 hrs since last year. Expect trend to continue due to continued growth in
volume of content updated to websites• Options have been analyzed and remedial steps have been taken, but problem requires redesign of Collage architecture and nightly
process to mitigate risk of website content delays or failures
SourceCommi
tteeSource
DocProject Project No.
Current Status
2007 Priority2007 Rank
2007 Budget Range
2007 Running Range
Market RMS SCR740Enhancements to SCR727 - Market Access
50024_01 Execution 0 - Carryover 1 $100k-$250k <$1M
Market RMS SCR740Enhancements to SCR727 - Market Enhancements
50024_02 Execution 0 - Carryover 2 $100k-$250k <$1M
ERCOT MO SCR 727 Phase II 40007_01 Execution 0 - Carryover 3 <$50k <$1M
Market COPSTML Phase 3 - Wholesale Enhancements
40103_01 Cancelled 0 - Carryover 4 <$1M
ERCOT MO Lodestar 4.5 Upgrade 40066_04 On Hold 0 - Carryover 5 $250k-$500k <$1M
ERCOT MO EIS Lodestar Transition to ODS 50030_01 Execution 0 - Carryover 6 <$50k <$1M
PUCT MO REC Program Modifications 60027_01 Cancelled 0 - Carryover 7 $50k-$100k <$1M
ERCOT MO Upgrade to Load Profiling SW 60090_01 Execution 0 - Carryover 7.5 $100k-$250k <$1M
Market MO PRR598Extension of Credit Against OOM Start Up
60083_01 Cancelled 1 - Critical 8 <$1M
ERCOT MO Collage Infrastructure 70038_01Not Yet Started
1 - Critical 8.5 $250k-$500k $1M-$2M
Market WMS PRR661SCE Performance Enforcement Criteria
70001_01 Cancelled 2 - High 9 $1M-$2M
Market PRS PRR666Modification of RPRS Under-Scheduled Capacity Charge Calculation
60087_01 Cancelled 2 - High 10 <$50k $1M-$2M
Market PRS PRR565Calculation of Losses for Settlement
60068_01 Closing 2 - High 11 $1M-$2M
Market PRS PRR668Distribution Loss Factor Calculations
60068_01 Closing 2 - High 11 $50k-$100k $1M-$2M
Market COPS SCR743 QSE Dispute Extract 70002_01Not Yet Started
2 - High 12 $50k-$100k $1M-$2M
Market COPS LPGRR016Load Profile Transition Migration
60101_01Not Yet Started
2 - High 12.5 $50k-$100k $1M-$2M
ERCOT MO Siebel to L* 5 - Rewrite 70003_01 Cancelled 2 - High 13 $1M-$2M
ERCOT MOTransition of Production Reporting to EIS - Wholesale
70004_01 Cancelled 2 - High 14 $1M-$2M
5April 10, 2007 Page 5
SourceCommi
tteeSource
DocProject Project No.
Current Status
2007 Priority2007 Rank
2007 Budget Range
2007 Running Range
Market RMS SCR740Enhancements to SCR727 - Market Access
50024_01 Execution 0 - Carryover 1 $100k-$250k <$1M
Market RMS SCR740Enhancements to SCR727 - Market Enhancements
50024_02 Execution 0 - Carryover 2 $100k-$250k <$1M
ERCOT MO SCR 727 Phase II 40007_01 Execution 0 - Carryover 3 <$50k <$1M
Market COPSTML Phase 3 - Wholesale Enhancements
40103_01 Cancelled 0 - Carryover 4 <$1M
ERCOT MO Lodestar 4.5 Upgrade 40066_04 On Hold 0 - Carryover 5 $250k-$500k <$1M
ERCOT MO EIS Lodestar Transition to ODS 50030_01 Execution 0 - Carryover 6 <$50k <$1M
PUCT MO REC Program Modifications 60027_01 Cancelled 0 - Carryover 7 $50k-$100k <$1M
ERCOT MO Upgrade to Load Profiling SW 60090_01 Execution 0 - Carryover 7.5 $100k-$250k <$1M
Market MO PRR598Extension of Credit Against OOM Start Up
60083_01 Cancelled 1 - Critical 8 <$1M
ERCOT MO Collage Infrastructure 70038_01Not Yet Started
1 - Critical 8.5 $250k-$500k $1M-$2M
Market WMS PRR661SCE Performance Enforcement Criteria
70001_01 Cancelled 2 - High 9 $1M-$2M
Market PRS PRR666Modification of RPRS Under-Scheduled Capacity Charge Calculation
60087_01 Cancelled 2 - High 10 <$50k $1M-$2M
Market PRS PRR565Calculation of Losses for Settlement
60068_01 Closing 2 - High 11 $1M-$2M
Market PRS PRR668Distribution Loss Factor Calculations
60068_01 Closing 2 - High 11 $50k-$100k $1M-$2M
Market COPS SCR743 QSE Dispute Extract 70002_01Not Yet Started
2 - High 12 $50k-$100k $1M-$2M
Market COPS LPGRR016Load Profile Transition Migration
60101_01Not Yet Started
2 - High 12.5 $50k-$100k $1M-$2M
ERCOT MO Siebel to L* 5 - Rewrite 70003_01 Cancelled 2 - High 13 $1M-$2M
ERCOT MOTransition of Production Reporting to EIS - Wholesale
70004_01 Cancelled 2 - High 14 $1M-$2M
Projects ABOVE the Capability Line
• Several projects above the capability line have been cancelled– Extension of Credit Against OOM Start Up – Requirements fulfilled by ERCOT manual process; no Market impact– SCE Performance Enforcement Criteria – Requirements fulfilled by ERCOT manual process; no Market impact– Siebel to L* Rewrite – Scope addresses rewrite of internal ERCOT process using new TIBCO technology. Current process runs as
required and TIBCO resources are constrained so business has cancelled project and will revisit need under 2008 PPL Project Process; no Market impact
– Transition of Production Reporting to EIS-Wholesale – Scope addresses transition of internal ERCOT reports that use production as source data to using EIS/ODS as source. Delays with EIS/ODS environment stability and resource constraints for EIS resources resulted in business decision to cancel the project for this year and revisit need under 2008 PPL Planning process; no Market impact
6April 10, 2007 Page 6
Projects BELOW the Capability Line
• Several projects below the capability line have been cancelled– Lodestar Web Services – Scope addresses transition of Lodestar extracts/reports that are mass produced to production from the
EIS environment using web services; Delays with EIS/ODS environment stability; resource constraints for EIS resources; commitment to deliver Lodestar upgrade, and ability to provide one-off web services via other projects has resulted in business decision to cancel the project for this year and revisit need under 2008 PPL Planning process; potentially limits Market’s access to web services not already scoped in other projects or planned for Nodal
– URC for Uncontrollable Resources - Requirements fulfilled by ERCOT manual process; no Market impact
SourceCommi
tteeSource
DocProject Project No.
Current Status
2007 Priority2007 Rank
2007 Budget Range
2007 Running Range
ERCOT MO Lodestar Web Services 60030_01 Cancelled 2 - High 15 $1M-$2M
Market WMS PRR426URC for Uncontrollable Resources
40057_01 Cancelled 3 - High / Medium 17 $1M-$2M
ERCOT MO EIS Reporting Tool II 60021_01 Below Line 9 - Parking Lot $250k-$500k $1M-$2M
Market COPS PRR577 TDSP Load Extract 50150_01 Below Line 9 - Parking Lot <$50k $1M-$2M
Market COPSTCR Synchronization of Credit Payment with Settlement Invoices
30103_01 Below Line 9 - Parking Lot -$ $1M-$2M
Market COPS PRR385 DLC Implementation - Below Line 9 - Parking Lot -$ $1M-$2M
Market COPS PRR478Use of Lagged Dynamic Samples for New Load Profiles
40056_01 Below Line 9 - Parking Lot -$ $1M-$2M
7April 10, 2007 Page 7
Financial Overview
MO PPL Budget Activity Amount Notes/comments
Funds released by cancellation of project ABOVE the Capability Line
$619K • Extension of Credit Against OOM Start Up• Requirements fulfilled by ERCOT manual process; no Market
impact• Siebel to L* Rewrite• Transition of Production Reporting to EIS-Wholesale
Funds released by cancellation of project UNDER the Capability Line
$0 • Lodestar Web Services• URC for Uncontrollable Resources • No funds available to release since projects were not above the line
and allocated any of the $1.5M funding
Funds requested by addition of new project
$400K • Collage Infrastructure Project
Current Forecast Spend of projects above the Capability Line
$1.495K • Budget range of $1M – $2M
Approved MO Capability Line Budget Funding
$1.5M • Has not changed since initial allocation identified under 2007 PPL Planning process
Budget Variance $5k • Difference between budget allocation and forecast spend• All projects COPS and MOCART want for 2007 are currently funded• New projects and/or initiation of projects below the line (with change
in priority or rank) will require funding increase and/or impacts to current project budgets
8April 10, 2007 Page 8
Questions / Contacts
Adam D. MartinezManager, Market Operations Divisional Projects Organization
ERCOT(512) 248-3883