Upload
duongtuyen
View
224
Download
0
Embed Size (px)
Citation preview
EPWP Large Projects GuidelinesScaling Up Service Delivery
and Contributing to Job Creation
Version 1: August 2012
index Page
Glossary of Terms 5
List of Abbreviations 8
Executive Summary 9
1. Introduction 10 1.1 Purpose of the Guidelines 10 1.2 Scope of the Guidelines 10 1.3 Application of the Guidelines 12 1.4 Overview of Expanded Public Works Programme (EPWP) 12 1.4.1 EPWP Phase 1 (April 2004 to March 2009) 13 1.4.2 EPWP Phase 2 (April 2004 to March 2014) 13
2. Definition of an EPWP Large Project 14 2.1 EPWP Large Projects defined 2.2 Rationale for Large Projects 14 2.2.1 Addressing socio-economic imperatives 14 2.2.2 Development support to emerging enterprises 15
3. Implementation approaches for EPWP Large Projects 16 3.1 Labour intensification in an EPWP Large Project 16 3.1.1 Large contractor using large-intensive construction methods 16 3.1.2 Subcontractor implements the labour-intensive components of the project 17 3.2 Bundling of smaller contracts to form a large project 19
4. Identification of Suitable Large Projects for Implementation using Labour-Intensive Methods 20 4.1 Types of activites than can be implemented labour-intensively in EPWP Large Projects 21 4.1.1 Road works 21 4.1.2 Stormwater works 21 4.1.3 Sewers 21 4.1.4 Water 22 4.1.5 Haul of materials 22 4.1.6 Electricity 22 4.1.7 Houses, School and Clinics 22
2
Page 4.2 Possible Contracting Arrangements 22 4.2.1 Option 1: Programme management approach (design by employer) using labour-intensive methods 22 4.2.2 Option 2: Programme management approach (develop and construct) for large projects using labour-intensive methods 26 4.2.3 Option 3: Management contracts for large projects using labour-intensive construction methods 27 4.3 Determine contracting arrangements strategy 28 4.3.1 Forms of Contracts for an EPWP Large Project 29 4.3.2 Decision criteria for the selection of a suitable form of contract for construction works 30 4.3.3 Determine procurement arrangements (Decide on Quality strategy) 32 4.4 Design and Documentation for EPWP Large Projects 33 4.4.1 Design and documentation compliance to EPWP guidelines 33 4.4.2 Labour-intensive compliance for Built-Environment Professionals 33 4.4.3 Labour-intensive construction compliance for contractors 33 4.4.4 Construction Industry Development Board compliance requirements 34
5. Monitoring and Reporting Requirements of EPWP Large Projects 36 5.1 Monitoring Indicators 36 5.2 EPWP reporting Templates 37 5.3 Progress Monitoring 37 References 38
3
EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation4
List of Figures, Tables and Annexures
Figure 1 Overview of the EPWP Large Projects Guidelines
Figure 2 Proposed Service Delivery model: Programme Management (Design by Employer)
Figure 3 Stages of Delivery of an EPWP Large Project
Figure 4 Management Contract of an EPWP Large Project
Figure 5 Decision criteria for the selection of a Form of Contract for Construction and
Maintenance
Figure 6 Deciding on procurement arrangements for EPWP Large Projects
Figure 7 Single Volume Approach to the packaging of construction procurement documents
Figure 8 Three Volume Approach to the packaging of construction procurement documents
Table 1 Recommended combinations of Forms of Contract and Forms of Subcontract
Table 2 Decision criteria for the selection of the Form of Contract for Construction Works
Annexure A An Overview of Contracting Strategies for Construction and Engineering Projects
Annexure B Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model -
An example of an EPWP Large Project Case Study
Annexure C Municipality Reporting Template
Annexure D Provincial Reporting Template
List of Figures
List of Tables
List of Annexures
5
Glossary of Terms
Actual Expenditure Actual expenditure = (the expenditure on the project by the contractor) + (the expenditure by the professional service provider appointed to design and supervise the project). The actual expenditure excludes expenditure on government management and administration.
Code of Good Practice for employment and conditions of work for Expanded Public Works Programmes The Minister of Labour periodically issues a Ministerial Determination in terms of the Basic Conditions of Employment Act of 1997 and Gazetted a Code of Good Practice for employment and conditions of work for Expanded Public Works Programmes which allows for special conditions to facilitate greater employment on Expanded Public Works Programmes (EPWP).
Contractor A person, trading entity or group of persons who is contracted to carry out the work on the Expanded Public Works Programme for the relevant public body or client body.
Construction costs This is a combined cost of labour, plant and materials, excluding professional fees.
Cost per FTE Cost per FTE is calculated by: dividing the total budget for an EPWP project by the number of full time equivalent jobs (FTEs) planned to be created.
Daily Rate A worker is paid a fixed sum each day in return for (i) working a fixed number of hours during that day, or (ii) completing a fixed task for that day.
Demographic Characteristics of Workers The number of workers that fall within the following categories must be recorded: • Youth (i.e.16 to 35 of age) (youth who are still at school shall not be employed on EPWP projects); • Women; • People with Disabilities. The definitions contained in the Preferential Procurement Regulations of 2001 for these categories of beneficiaries will be utilised.
EPWP Large Project A large project could either be one big project or a grouping of a number of related small initiatives (various mini-projects) managed in a coordinated way to obtain benefits and control not available from managing them individually. For the purpose of these guidelines, the budgetary threshold of an EPWP Large Project is R30 million (Including Value Added Tax) and above.
EPWP Target Group Unemployed, local, low skilled South Africans willing to work on EPWP projects and programmes for a minimum wage rate.
EPWP Worker A person employed to work in an EPWP project under the Code of Good Practice for Expanded Public Works Programmes or the Learnership Determination for unemployed learners, whether they are employed directly by a government department, an implementing agent, a contractor or a sub-contractor.
Full Time Equivalent (FTE) FTE refers to one person-year of employment. One person year is equivalent to 230 per- son days of work. Person-years of employment = total number of person days of employment created for targeted labour during the year divided by 230. For task-rated workers, tasks completed should be used as a proxy for 8 hours of work per day.
FTE Target “FTE Target” means the targeted number of Full Time Equivalent an employment programme required to create using funding received by a public body within a stipulated financial year.
EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
6 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
Implementing Agent (IA) A business, institution or person who is contracted to implement the Expanded Public Works Programme on the relevant department’s behalf. An implementing agent is bound by the same terms and conditions governing the implementation of Expanded Public Works Programme as a department.
Incentive Grant / Amount The Incentive Grant / Amount earned is calculated as follows = Number of FTEs reported [by the end of a quarter] x Incentive subsidy per FTE.
Job Creation Targets The number of full time equivalent jobs and work opportunities that a public body must create.
Job Opportunity 1 job opportunity = paid work created for an individual on an EPWP project for any period of time. In the case of social sector projects, Learnerships will also constitute job opportunities. The same individual can be employed on different projects and each period of employment will be counted as a job opportunity.
Key Performance Indicators (KPIs) Indicators are qualitative and/or quantitative measure/markers that define how performance toward the achievement of the programme, project or activity objective will be measured. Labour Intensity Labour intensity refers to the labour component of a project and is calculated as the percentage of unskilled labour wages against the total expenditure.
Labour-Intensive Construction Methods of construction involving a mix of machines and labour, where labour, utilising hand tools and light plant and equipment, is preferred to the use of heavy machines, where technically and economically feasible.
Main Contractor A person or firm undertaking a major contract and employing one or several subcontractors to carry out specific parts of the work or provide services, labour or materials.
Managing Contractor An experienced (main) contractor who is contracted to be responsible for the construction of a project through an agreement that he / she manages one or a number of smaller subcontractors for different parts of the works.
Mentorship Provision of guidance, advice, technical and management support to emerging contractors or professionals to enable them to implement infrastructure projects successfully and eventually establish themselves in a competitive environment.
Monitoring Monitoring is a process that involves measuring and tracking progress according to the planned outputs / outcomes including: resources, activities, quality, costs, timeframes, etc.
Person-Days of Employment created The number of people who worked on a project x the number of days each person worked.
Programme A programme is a coordinated approach to explore a specific area related to an organisation’s mission. It usually includes a plan of action or events which identifies staff and related activities or projects leading towards defined and funded goals.
7EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
Project A specific intervention with a beginning and an end, with a number of distinct phases in between. A project is designed to achieve specific objectives within predetermined implementation timeframes, with a budget with an associated cash-flow, and has a single point of responsibility (project manager).
Project Budget The project budget = (the price tendered by the contractor) + (the professional fees for the professional service provider appointed to design and supervise the project). The project budget excludes govern- ment management and administration costs.
Project Wage Minimum Daily Wage Rate = daily wage (whether task-rated or time-rated) per individual project. This wage rate must be inserted in the Project tender document as per the EPWP guidelines.
Public Body A provincial or national department, national or provincial public entity or constitutional institution within the meaning of the Public Finance Management Act, 1999, a municipality and municipal public entity within the meaning of the Municpal Finance Management Act, 2003. Reporting Reporting is a process of recording EPWP project data/information from sites and uploaded into the EPWP reporting system on a frequency determined by the EPWP Monitoring and Evaluation (M&E) Unit (e.g. monthly and quarterly reporting frequency), using the reporting templates developed by the EPWP.
Subcontractor A person or trading entity being contracted by a main contractor or employer to carry out work or deliver services, labour or materials as part of a larger project. Subcontracting could take any one form, including:
• Domestic subcontractor: subcontractor appointed by the main contractor at his discretion;
• Nominated subcontractor: a subcontractor nominated by the employer which the contractor is obliged to appoint as a subcontractor (the nominated subcontractor has to be registered with the CIDB, in accordance with the CIDB Register of Contractors, Act. 38 of 2000); and
• Selected subcontractor: a subcontractor selected by the contractor in consultation with the employer in terms of the requirements of the contract (the selected subcontractor has to be registered with the CIDB, in accordance with the CIDB Register of Contractors, Act. 38 of 2000).
Targeted procurement Procurement of construction services specifying objectives other than purely technical or financial (e.g. socio-economic). These may include labour-based technology for the optimum employment of labour, maximum use of local resources, training, and contractor or community development components.
Task-based work A worker is paid a fixed wage in return for a fixed quantity of work, to a specified quality, or a task. The task set should be possible for a worker (or group of workers for a group task) to complete within 8 hours.
Training Person-Days The number of Training Person Days is the number of people who attended training x the number of days of training.
8
B-BBEE Broad-Based Black Economic Empowerment
BIFSA Building Industries Federation of South Africa
CIDB Construction Industry Development Board
CLO Community Liaison Officer
DPW Department of Public Works (national)
EPWP Expanded Public Works Programme
FA Framework Agreements
FIDIC Fédération Internationale Des Ingénieurs-Conseils (International Federation of Consulting Engineers)
FTE Full Time Equivalent
GCC General Conditions of Contract
IDP Integrated Development Plan
IDIP Infrastructure Delivery Improvement Programme
JBCC Joint Building Contracts Committee
KPIs Key Performance Indicators
MTEF Medium Term Expenditure Framework
NEC New Engineering Contract
PIC Project Implementation Committee
SAFCEC South African Federation of Civil Engineering Contractors
SANS South African National Standards
SMME Small Micro and Medium Enterprises
MFMA Municipal Finance Management Act
PFMA Public Finance Management Act
PPP Public Private Partnerships
EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
List of Abbreviations
The Department of Public Works, through its Large Projects Directorate of the EPWP Unit identified the need to develop guidelines that will assist the various client bodies with regard to the conceptualization, planning, design, implementation and management of large infrastructure projects which are to be implemented in accordance with the EPWP principles.
In the infrastructure sector the emphasis is on creating additional work opportunities through the use of labour-inten-sive construction and maintenance methods, which, involve the use of an appropriate mix of labour and machines, with a preference for labour where technically feasible and economically viable, without compromising the quality of the product.
All public bodies involved in infrastructure provision are required to participate in the EPWP. This involvement re-quires them to identify, plan, design, implement, manage, monitor and report their EPWP large projects in accord-ance with the EPWP protocols.
In terms of these guidelines a large project is defined as one with a budget threshold of R30 million or more (includ-ing Value Added Tax). The guidelines also identify a number of projects that have potential of being implemented using labour-intensive methods of construction.
In order to increase the job creation potential of large projects, the guidelines propose a number of approaches that could be considered by public bodies in the planning, implementation and management of infrastructure projects. These include established contractors implementing large projects using labour-intensive construction methods, subcontractors implementing large projects using labour-intensive construction methods and lastly the bundling of smaller projects to form large contracts. Such large contracts could be implemented using either big and established contractors or the subcontractors or a combination of the two models.
On the basis of the delivery approaches adopted, the public bodies have to choose a possible contracting strategy that meets their requirements. This could either be design by employer, develop and construct and also manage-ment contract strategies, taking into account the labour-intensive construction methods and technologies.
The implementation of large projects follows the choice of contracting strategies. The implementation of large projects must take into account the following factors, namely:
• Design & Documentation - EPWP Labour-Intensive Construction skills for built environment professionals (both client sideandtheconsultants’sideaswell);
• CIDB Compliance - StandardforUniformity; - RegisterofContractors;and - RegisterofProjects.
• EPWP Labour-Intensive Construction Guidelines - LICSkillsforContractors
The public bodies have to monitor the progress of the implementation of large projects and report the implementa-tion, making use of reporting templates and in accordance with the monitoring and reporting indicators, as deter-mined by the National Department of Public Works.
Executive Summary
9EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
10 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
1.1 Purpose of the Guidelines Document The guidelines are intended to give guidance to public bodies including decision makers, project managers and
built environment private sector consultants to enable them to plan, implement, manage, monitor and report the
delivery of large projects using labour-intensive methods of construction.
1.2 Scope of the GuidelinesThe Guidelines comprise five core components, namely:
• Defining EPWP Large Projects;
• Identification of suitable projects that
could be implemented using labour-intens-
ive construction methods;
• Intensification of labour intensive construction
methods on large projects;
• Deciding on contracting strategies for large
projects;
• Implementation of large projects using labour-
intensive construction methods;
• Monitoring and Reporting of EPWP Large projects using labour-intensive construction methods.
It must be noted that the scope of these guidelines does not include manual description of work methods and
design standards, rather it is a reference document to be used for all types of large infrastructure works us-
ing labour-intensive construction methods. These guidelines also do not attempt to give guidance on how to
“labour-intensify” current works, but focus more on the strategic level, especially from the Infrastructure plan-
ning, funding, implementation, monitoring and reporting of large infrastructure projects. References are made
to the other manuals that were previously published by the National Department of Public Works and the CIDB.
Introduction1.
EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation 11
AN OVERVIEW OF EPWP LARGE PROJECTS GUIDELINES
Figure 1: An Overview of EPWP Large Projects
Define an EPWP Large
Project
Identify suitable EPWP Projects for
LIC Methods
Decide on LIC Methods and Delivery Approaches
for Large Projects
Decide onContracting
Arrangements
Implement Large Projects using LIC methods
Implementation Considerations:
• Procurement of
Service Providers
• Design & Documentation - EPWP LIC skills for professionals
• CIDB Compliance - Standard for Uniformity - Register of Contractors - Register of Projects
• EPWP Labour- Intensive Construction Guidelines - LIC Skills for Contractors
Monitoring and Reporting of EPWP
Large Projects
• Monitoring Indicators
• Reporting Templates
• Data Collection Processes from Project Level to Programme Level
Monitoring&
Reporting
Design by Employer
Develop & Construct
Management Contract
Subcontractors Imple-menting
large projects using LIC methods
Bundling of Small Projects into large
projects (Implemented by large contractor,
Subcontractors or both)
Large Contractor imple-menting large projects
using LIC methods
Overview of Large Projects Guide-lines
Intensifica-tion of LIC methods on Large Projects
Suitable projects for LIC
methods
Definitionof EPWP
Large Projects
For the programme approach to be realized, public bodies have to ensure that there is a long-term view to
infrastructure delivery (by starting with long-term infrastructure plans for provincial and national departments
and the integrated development plans of municipalities) and the medium-term infrastructure funding model. The
programme approach also affords the public bodies an opportunity to address socio-economic imperatives.
12 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
1.3 Application of the guidelinesThe guidelines are aimed at the public bodies, in particular decision makers and the private sector built environ-
ment professionals who normally provide an extension of capacity for public sector public bodies.
It is recommended that the users of these guidelines must have a fair understanding of the framework govern-
ing the implementation of the Expanded Public Works Programme (EPWP), and also a good understanding
of the Construction Industry Procurement prescripts, as regulated by the Construction Industry Development
Board, in terms of CIDB Act No. 38 of 2000 and the framework governing public sector procurement in South Af-
rica, especially the Public Finance Management Act (1999) and the Municipal Finance Management Act (2003).
These guidelines do not replace the CIDB Prescripts or the National Treasury Practice Notes or regulations
that are issued by the respective institutions from time to time, rather must be understood to be interpreted as
offering guidance regarding the planning, preparation and implementation of EPWP Large Projects, within the
context of scaling up delivery and maximising the creation of work opportunities.
These guidelines are also not replacing the “EPWPInfrastructureImplementationManual”(DPW2008)orthe
“Guidelines for the implementationof theLabour-IntensiveProjectsunder theExpandedPublicWorksPro-
gramme”(DPW,2005).The guidelines are also to be read in conjunction with these documents or their latest
versions.
1.4 Overview of Expanded Public Works Programme (EPWP)The EPWP is a nation-wide programme that is aimed at the reorientation of existing public sector expenditure
to draw significant numbers of the unemployed into productive work, so that workers gain skills while they work,
and also increase their capacity to earn an income.
The EPWP is a strategic intervention that was designed to make a significant contribution to reducing unem-
ployment and providing livelihoods for the poor, women, youth and people with disabilities in the country. The
EPWP emphasizes the need to focus our investment on social infrastructure in a manner that addresses severe
conditions of underdevelopment and entrenched poverty. The EPWP is being implemented in a phased ap-
proach as described below.
13EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
1.4.1 EPWPPhase1(April2004toMarch2009)EPWP Phase 1 was from April 2004 to March 2009, and its stated target of one (1) million work opportunities
was met one (1) year earlier than envisaged, which paved the way for the planning and implementation of
EPWP Phase 2.
1.4.2 EPWPPhase2(April2009toMarch2014)The objective of EPWP Phase 2 is to create 4.5 million work opportunities for poor and unemployed people
in South Africa so as to contribute to halving unemployment by 2014, through the delivery of public works
and community services. The intention is to ensure that EPWP enables government to act as an employer
of last resort as part of the Anti-Poverty Strategy. The EPWP Phase 2 has three strategic features, namely:
• Introduction and setting of targets and Accountability across government
• Introduction of a Fiscal Incentive
• Introduction of the non-state sector
14 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
2.1 EPWP Large Projects definedAn EPWP Large Project is defined as an infrastructure
project with a value of more than R30 million (includ-
ing Value Added Tax) that involves the use of labour-
intensive methods on a significant scope of work to
maximise the creation of work opportunities.
The EPWP Large Project could either be one big
project or a grouping of a number of related small ini-
tiatives (various mini-projects) managed in a coordi-
nated way to obtain benefits and control not available
from managing them individually.
An EPWP Large Project can also be defined as a publicly funded infrastructure project or activity, whose
implementation:
• Has a significant portions of the scope of work that can be implemented labour-intensively;
• Ultimately provides public goods and services to prescribed good standard.
2.2 Rationale for Large ProjectsThe July 2005 Cabinet Lekgotla raised concerns regarding the size, impact and visibility of EPWP initiatives.
On the basis of these concerns, it was recommended that options for structuring Large Projects involving large
contractors be investigated to accelerate capital expenditure and increase the size of EPWP projects. It is
also thought that bigger projects will have greater job creation impact in an area and also makes it easier for
public bodies to project manage, instead of having many small projects to manage. If properly planned, large
infrastructure projects can yield a number of benefits, some of which include, but not limited to the following:
2.2.1 Addressingsocio-economicimperativesThe awarding of contracts to a large contractor, due to economy of scale and the expertise residing in such com-panies, presents an excellent opportunity to cost effectively provide work opportunities and to develop targeted enterprises. A large contractor can provide work opportunities to and be able to contribute to the development of
targeted enterprises
Definition of an EPWP Large Project2.
15EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
2.2.2 DevelopmentsupporttoemergingenterprisesDevelopment support may, however, be provided in a much more targeted, focused and measurable manner should Key Performance Indicators (KPI) be established for large projects and bonus incentives be paid if the Contractor equals or exceeds the performance targets set. For example, KPIs can be established in respect of:
• training outcomes, e.g. number of persons attending and passing specified training courses; • contractor development outcomes such as the number of contractors improving their CIDB contractor grading designations over the duration of the contract; • new enterprise formation in classes of works where there is a scarcity of black owned businesses; • number of persons employed in terms of the EPWP requirements; • Value of work subcontracted to emerging contractors which could be implemented using labour- intensive methods of construction; • the attainment of contract participation goals measured in terms of the SANS 1914 families of standards for targeted construction procurement; • number of experiential opportunities offered to those who have completed specific learnerships; and • number of employees who are learners at a university and who are undergoing experiential training so that they may complete their qualification in fulfilment of requirements for registration with the Engineering Council of South Africa; etc.
16 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
There are a number of ways in which large projects can
enhance labour intensity and these include, but not lim-
ited to the following:
• labour intensification in an EPWP large
project; and
• labour intensification in a number of smaller
EPWP projects that have been clustered
together to form a large project.
There are cases where the public bodies might have
large projects to implement as EPWP projects, and also
cases where the public bodies might not have large
projects, but a number of smaller projects that could be
implemented using labour-intensive construction meth-
ods. In both instances, the public bodies might have budgets that could be stretched over a period of three to five
years, with specific socio-economic deliverables built into the specifications of such infrastructure projects. The
two possible approaches to labour intensification are elucidated in detail in the following section of the guidelines.
3.1 Labour intensification in an EPWP Large Project
3.1.1 LargeContractorusinglabour-intensiveconstructionmethodsIn this approach, the intension is to get the large contractors to implement labour-intensive methods in large projects.
These are ideally projects with large budgets of R30 million and above (including VAT) with components which could
be conceptualised, designed, planned, tendered, implemented and managed using labour-intensive methods.
The adoption of this approach requires the public bodies to balance a number of factors, including making large
projects to be more attractive for medium-sized and large contractors, and simultaneously being more developmen-
tal for small enterprises. There are a number of ways in which this can be done.
One of the ways involves the “carrot approach”, whereby public bodies can offer incentives to large contractors to
implement projects in a labour intensive manner by introducing or allowing them additional preference points during
the tender evaluation stage for the highest labour content.
Implementation Approaches for EPWP Large Projects
3.
17EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
Another method could be the “stick approach”, whereby large contractors could be penalised if they do not meet
the minimum labour content prescribed in the tender specifications. This could be quantified in terms of the
amount that could be deducted from the payment certificates should the specified labour-intensity / content not
be realised.
One of the prerequisites for this model is that the public bodies must stipulate the labour-intensive skills require-
ments and capabilities of potential large contractors interested in this model. The large contractors must have in
their employ personnel who have the required labour-intensive construction training in accordance with the re-
quirements of the “Guidelines for the implementation of Labour-Intensive Infrastructure projects under the EPWP”
(DPW, 2005).
3.1.2 Subcontractor implements the labour-intensive components of theproject
3.1.2.1 Subcontractingpracticesintheconstructionindustry Subcontracting is a well established practice within the construction industry, since it is an
effective means of involving small, medium and micro enterprises in the construction works
contracts The reasons for subcontracting vary between the different types of construction works
contracts. In some contracts there may be a need to acquire specialist capabilities to perform
certain aspects of the work, e.g. there might be scope for labour-intensive construction work
within a Large Project (CIDBPracticeNoteNo.7,May2007).
In others, there may be a need to subcontract portions of the work to increase the contracting
capacity of the contractors or to satisfy client requirements relating to the engagement of small
and micro enterprises or local enterprises in a contract, in accordance with a targeted procure-
ment strategy of a public body. Subcontracting may also be used as a means of addressing
racial and gender imbalances in the ownership of contracting entities, through the different
types of subcontracting arrangements,namely: Domestic, Nominated and Selected subcontractor
(Refer to Glossary of Terms for definitions of various subcontracting arrangements).
The subcontractors should be engaged in fair conditions of contract which are recorded in
writing. The NEC3 and the JBCC Series 2000 Agreements contain principal (prime or main)
contracts and subcontracts, whereas FIDIC and GCC 2010 only provide the principal contracts
(Table 1).
18 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
The South African Federation of Civil Engineering Contractors (SAFCEC), the Building Industries Federation of
South Africa (BIFSA) and the CIDB have developed forms of subcontract which may be used with any approved
forms of contract.
3.1.2.2 Labour-intensiveconstructionscopeasaspecialistcategoryofworks There are also cases where the public bodies might have identified the appropriate EPWP large
projects that could be implemented using labour-intensive construction methods, in a manner
involving the use of small and emerging contractors. In this case, the various components or work
packages can be isolated and the main contractor could be informed, through the specifications
and the pricing instructions to have such packages implemented using small and emerging
contractors.
The same principle could be applied with regard to the skills requirements of the subcontractors,
i.e. only those subcontractors with personnel who possess the relevant labour-intensive
construction skills and qualification could be allowed to submit tender offers. The main contractors
could make use of nominated, domestic or selected subcontractors.
The subcontracting model for the labour-intensive scope requires a contractor who has adequate
and strong supervisory capacity in labour intensive construction. The implication is that even if
the main contractor subcontracts the identified labour-intensive scope of work, there will still be a
need for the main contractor to have personnel in his / her employ who have the required labour-
Table 1: Recommended combinations of forms of contract and forms of subcontract
Source: CIDB Practice Note No. 7, May 2007: Subcontracting arrangements
Series of Contract Recommended forms of subcontract
FIDIC • BIFSA Standard Subcontract Agreement 1995 Edition (Amended 2000), for use with Principal Building Agreements other than the JBCC Principal GCC 2004 Building Agreement • BIFSA Labour-only subcontract • SAFCEC General conditions of subcontract (2003 edition)
JBCC Series 2000 • BIFSA Non-Nominated Subcontract for use with the JBCC Series 2000 Principal Building Agreement • JBCC 2000 Nominated / Selected Subcontract Agreement
NEC3 • NEC3 Engineering and Construction Subcontract • NEC3 Engineering and Construction Short Subcontract
19EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
intensive construction qualification (either at NQF Level 5 of 7), provided that such a person will
assist the sub-contractors otherwise the subcontractors must hire somebody with such skills.
3.2 Bundling of smaller contracts to form a large projectThis approach involves the grouping of smaller similar projects into packages and also ensuring that these are
planned and coordinated at a programme level. This approach might require the public body to appoint a Pro-
gramme Manager to coordinate the planning and implementation of the programme. These might be projects that
are identified and prioritised on a yearly basis and programmed for implementation on an MTEF basis.
20 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
Labour-intensive refers to the methods of construction
involving a mix of machines and labour, where labour,
utilising hand tools and light plant and equipment, is
preferred to the use of heavy machines, where tech-
nically and economically feasible (EPWP Guidelines,
DPW 2005).
The infrastructure sector was identified as the largest
employment generator, targeting the creation of ap-
proximately 900, 000 out of 1 million work opportunities
during the first phase of the programme (2004 to 2009).
In terms of Phase 2 (2009 to 2014), it was envisaged
that this component would be a large-scale expansion
of the use of labour-intensive construction methods to
build, upgrade and maintain the social and economic infrastructure in the underdeveloped rural and urban areas
of the country where such infrastructure is lacking. At the same time, local people would be employed and given
basic training and skills development.
The bulk of funding for large infrastructure projects is from the Infrastructure Grants to Provinces and the Munici-
pal Infrastructure Grant (MIG). Conditions were introduced through the 2004 Division of Revenue Act (DORA),
which required the municipalities and the provinces to execute public works such as low-volume roads, storm wa-
ter drains and trenching work using labour-intensive methods in accordance with the EPWP Guidelines produced
by the Department of Public Works, and as approved by the South Africa Local Government Association (SALGA)
and the National Treasury.
In a study conducted by the ILO, titled “Enhancing Labour Intensity in the Expanded Public Works Programme,
Road Infrastructure Projects, South Africa” (ILO, 2012) confirmed that overall labour intensity rate is lower for new
construction projects than for maintenance projects. The implication is that for public bodies to make a difference
in the implementation of large projects, from a job creation point of view, all large projects must be implemented
in accordance with these guidelines.
Identification of Suitable Large Projects forImplementation using Labour-Intensive Methods
4.
21EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.1 Types of activities that can be implemented labour-intensively in EPWP Large ProjectsThe Guidelines for the implementation of labour-intensive infrastructure projects under the Expanded Public Works
Programme (DPW July 2005) provides guidance on what types of works can be carried out using labour-intensive
work methods. The guidelines also deal with how additional clauses can be included in tender documents to en-
able the contractors to price those items that would have been identified and isolated as labour-intensive items.
The types of activities that can be implemented using labour-intensive construction methods include, but not
limited to the following:
4.1.1 Roadsworks • Site clearance
• Layer work construction including loading, hauling and spreading
• In-site concrete roads
• Segmented block paved roads
• Cast in-situ block pavements
• Road Markings
• Fencing;
• Erection of road signs;
• Grass maintenance;
• Road reserve maintenance;
• Rubble masonry bridges, culverts and retaining walls
4.1.2 Stormwaterworks • Gabions and reno mattresses
• Small diameter pre-cast concrete elements (pipes and arches)
• Grassed or lined water channels
4.1.3 Sewers • Sewer manholes
• Sewer manhole covers and lids
• Maturation or flocculation ponds
22 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.1.4 Water • Laying of water pipes, fittings and house connections in all materials
• Construction of ferro-cement reservoirs
• Excavation for membrane lined and floating roof reservoirs
• Construction of small masonry reservoirs
• Spring and well protection measures
4.1.5 Haulageofmaterials
4.1.6 Electricity • Excavation of trenches for reticulation of all voltages
• Excavation for and erection of poles for overhead lines
• Installation of all electricity cables (joints and terminations by qualified persons)
4.1.7 Houses,SchoolsandClinics • Manufacture of masonry elements on site
• Excavation of all foundation trenches by hand
• Manufacture of roof trusses on site
4.2 Possible Contracting Arrangements
4.2.1 Option1:Programmemanagementapproach(designbyemployer)using labour-intensivemethods
a) Definition of Design by Employer
The contractor only undertakes construction on the basis of full designs issued by the employer.
This contracting strategy requires that the design and specifications be adequately developed
before tenders are invited (CIDB Inform Practice Note No. 1, August 2006: Scaling up delivery
and accelerating empowerment) (See attached Annexure A).
Design is a separate function to construction and is managed by the client or his agent. The
Employer has the capability and capacity to make decisions during the design process
(Delivery Management Guidelines: Practice Guide 2: Construction Procurement Strategy,
2011-04-20)
23EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
b) What the Model entails
The service delivery model adopted for the multi-year programme (between 3 and 5 years) for
this option is as shown in Figure 2. The Employer will procure the services of a Programme
Manager to manage the delivery of the works, a Design Consultant to design the works and to
monitor the quality of the constructed works and a Contractor to construct the works.
A competitive selection process is followed to appoint these participants, primarily based on quality (functionality
criteria). The Contractor will be selected on the basis of quality (functionality) parameters and fee percentages for
overheads and profit and related financial parameters (Watermeyer, et al, 2010).
The Programme Manager acts as the “Employer” in the professional service contract with the Design Consultant,
save for making the payments due, and as the Project Manager / Principal Agent in the construction works con-
tract with the Contractor. The Department (Employer) only interfaces with the Contractor and Design Consultant
through the appointed Programme Manager (either public or private sector employee).
Figure 2: Proposed service delivery model: programme management (design by employer) Source: Watermeyer et al, 2010.
Legend for NEC3 ContractsPSC: Professional Services ContractECC: Engineering and Construction ContractECSC: Engineering and Construction Short ContractECS: Engineering and Construction SubcontractECSS: Engineering and Construction Short SubcontractSC: Supply ContractSSC: Supply Short ContractTSSC: Term Service Short Contract
Service Provider(TSSC)
Subcontractor(ECSC, ECSS or ECS)
Supplier(SC or SSC)
Contractor(ECC - option C & D)
Programme Manager(PSC)
Employer
Supervisor
Employer’sRepresentative
ProjectManager
Project Steering Committee
Design Consultant(PSC)
24 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
The Programme Manager is responsible for converting the business plan into work packages for the Design Con-
sultant who will develop the scope of work for the Contractor and provide the drawings and specifications for each
work package which will involve a single identified site where facilities are to be constructed. The Programme
Manager and Design Consultant will provide services in accordance with the stages outlined in Figure 3.
Figure 3: Stages of delivery of a project
Stage 1: PreparationDevelopment of strategic brief which defines project objectives business need, acceptance criteria and client priorities and aspirations.
Stage 2: ConceptDevelopment of initial design which establishes the detailed brief, scope, scale, form, social development goals and budget for the project (Concept report).
Stage 3.: Design DevelopmentDetailed development of approved concept to establish detailed form, character, function, cost plan and social development targets for the project.
Stage 4: Production InformationFinal detailing, performance definition, specification, sizing and positioning of all systems and components enabling either construction or the production of manufacturing and instal-lation.
Stage 5: Manufacture, Installation and ConstructionDefinition of the fabrication, manufacturing details and installation of all the components.
Stage 6: Post Practical CompletionDealing with outstanding issues and feedback and assisting with familiarising Project users with the design of the Works.
Instruct contractor toproceed with a project orcall for tenders from SMME contractors
25EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
Projects (work packages) identified by the Programme Manager and developed to stage 4: Production Information
will be:
a) constructed by the Contractor on the basis of:
i). a target price for the project being fixed before commencing with construction, i.e. a guaranteed
maximum price, which comprises a forecast of the probable cost of the constructing and
commissioning of the works and is agreed with the Employer and the Programme Manager
including all risks for construction and commissioning and the Contractor’s fee (mark-up);
ii). the target price being amended whenever a change in the scope of the work occurs which has an effect
(upwards or downwards) on the price;
iii). the total project cost being maintained within a margin of 10% affordability so that if the target
exceeds the affordability limit, the Programme Manager, Design Consultant and Contractor
provide an economic solution without prejudicing the functionality or design of the scheme to
reduce the total project cost within the affordability margin; and
iv). the Contractor being paid his direct costs of employing people, the actual incurred cost of
equipment, plant and materials and actual payments to subcontractors plus a fee for overheads
and profits, provided that this amount does not exceed the target price; and
v). the final amount paid to the contractor being the lesser of the contract price and his cost plus
his fee together with an agreed portion of the difference between the target price and this latter
amount; or
b). constructed by an SMME contractor who is contracted on a “one-off” basis by the Employer, based
on a priced contract with bill of quantities following a competitive tendering process.
The major portion of the works, however, will be carried out by the Contractor. The abovementioned target con-
tract is a development of cost reimbursable contracts, the idea being that a target is set jointly by the parties to
serve as a motivation to decrease and control costs. Financial risks are shared, proportionally through the Con-
tractor’s share percentages, between the Employer and the Contractor. The Contractor develops and prices either
an activity schedule or bills of quantities for each project (site), based on the documentation (production informa-
tion) submitted by the Design Consultant and Programme Manager, in order to arrive at a target cost.
26 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
The Programme Manager advises the Employer on the reasonableness of the price for the works and finalises
the target price for the package with the Contractor. Thereafter the Programme Manager provides cost control
services and acts as the Project Manager / Principal Agent in the construction contract with the Contractor. The
Contractor maintains records of all:
• goods received notes;
• amounts paid to subcontractors together with details of how the amounts were calculated; and
• daily allocation records for his staff and usage of equipment and plant.
4.2.2 Option2:Programmemanagementapproach(developandconstruct)for largeprojectsusinglabour-intensivemethods
4.2.2.1 DescriptionofDevelopandConstructcontractingstrategy The Develop and Construct strategy is similar to the Design and Build strategy, except that the
Employer issues a concept design on which tenders are based. The strategy is based on a
scheme design prepared by the Employer under which a contractor finalises the production
information and constructs it.
The final design details are integrated with construction and are managed by the contractor. The
Employer prepares the Design Development Report setting out the integrated developed
design for the project. The report is then used to develop the scope of work for the contract
(See Annexure A).
a) What this strategy entails
This option is very similar in approach to option 1, the main difference being that the Design Consultant appointed
by the Employer performs the services associated with Stage 1 (Preparation) and Stage 2 (Concept) and the
Contractor appoints a Design Consultant to perform the services associated with Stage 3 (Design Development),
Stage 4 (Product Information) and Stage 5 (Manufacture, Installation and Construction Information).
The Employer retains the services of his appointed Design Consultant to review the Contractor’s outputs of Stages
3 to 5 for consistency with the Concept Report that was developed in Stage 2, to act as the Supervisor, in terms of
the contract with the Contractor and to perform services associated with the Stage 6 (Post Practical Completion).
27EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.2.3 Option 3: Management contracts for large projects using Labour- IntensiveConstructionMethods
4.2.3.1 DescriptionoftheManagementContractingStrategy This is a contracting strategy under which a contractor is responsible for planning and managing
all post-contract activities, including, if required, any design of the works or portion thereof, and
for the performance of the whole contract (See Annexure A).
4.2.3.2 WhattheManagementContractingStrategyentails In this option, the Employer outsources the entire programme to a Management Contractor whose
responsibilities in essence are to translate the business plan into work packages and to man-
age the work packages. The Employer only interfaces with the Contractor through the appoin-
ed Project Manager. The Employer also appoints a Supervisor to ensure that the quality of the
works is in accordance with the requirements of the Contract.
The Management Contractor’s responsibilities for construction work are the same as those
undertaken by a contractor responsible for designing and constructing construction works in terms
of options 1 and 2. The Management Contractor, however, only manages the project and is
required to subcontract the design, the provision of site services and the construction and
installation of works to others (See Figure 4).
A competitive selection process is followed to appoint the Management Contractor, primarily
based on quality (functionality criteria). The scope of work establishes the procedures which the
Management Contractor has to follow to procure the services of the Design Consultant,
Contractors and others. These procedures can be framed around the requirements of the CIDB
Standard for Uniformity in Construction Procurement and SANS 294, Construction Procurement
Processes, Procedures and Methods.
The Contractor is paid the amount due to Subcontractors for work which the Contractor has
subcontracted, plus the cost of any work carried out by the Contractor himself, less any
disallowed cost, plus a fee. The Contractor is required to keep records of accounts of payment
of costs, proof that payment has been made, communications about and assessment of amounts
due to Subcontractors, etc.
28 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
The Management Contractor’s Fee will increase as Subcontractors’ prices increase due to changes in the scope
of work. However, he will not receive separate payment for his work in dealing with changes in the scope of work
and he will not receive any additional fee for work on changes in the scope of work which does not lead to an
increase in Subcontractors’ prices.
4.3 Determine contracting arrangements strategy The three main functions are work transfer (to define the work that one paryt will undertake), risk transfer (to define
how the risks inherent in doing the work will be allocated between the parties) and also motive transfer (to implant
motives in the contractor that match those of the client)(CIDBDeliveryManagementGuidelines:PracticeGuid
2-ConstructionProcurementStrategy,April2011).
Figure 4: Management contract of an EPWP Large Project
Legend for NEC3 ContractsPSC: Professional Services ContractECC: Engineering and Construction ContractECS: Engineering and Construction SubcontractECSC: Engineering and Construction Short ContractSC: Supply ContractTSSC: Term Service Short Contract
Project Manager(PSC)
Supervisor(PSC)
Employer
Management Contractor(ECC - option F)
Designer(PSC)
Supplier(SC or SCC)
Service Provider(TSSC)
Subcontractors(ECC, ECSC, ECS or ECSS)
29EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.3.1 FormsofContractsforanEPWPLargeProjectThe complier should identify suitable forms of contract for the package and suitable pricing strategies for the
selected forms of contract (See Figure 5) (Watermeyer, 2011). Because of the diversity of both construction and
client’s requirements, no single uniform approach to contractual arrangements can be specified or advocated.
A number of alternative strategies are available to the client and each contract should be formulated with a specific
job in mind. There are a number of appropriate contracting strategies that could be considered include, namely:
Design by Employer, Design and Build, Develop and Construct, Construction Management model, Management
Contracting and Community-Based model.
Figure 5: Decision criteria for the Selection of a Form of Contract for Construction and Maintenance Projects (Watermeyer, et al, 2011).
Building and InfrastructureFIDIC Short Form (Green Book)NEC3 Engineering and Construction Short ContractBuildings OnlyJBCC Minor Works Agreement
Does the works satisfy all of the following statements? a. the works: i) are straightforward or repetitive in nature ii) are of short duration; iii) have almost no requirement for sophisticated management techniques; and iv) impose only low risks on both employer and the contractor; and
b. the design of the works is almost complete when construction starts?
Building and InfrastructureFIDIC Red BookGCC 2010NEC3 Engineering and Construction ContractBuildings OnlyJBCC Principal Building Agreement
Building and InfrastructureFIDIC Yellow Book or FIDIC Silver BookGCC 2010NEC3 Engineering and Construction Contract
Building and InfrastructureFIDIC Silver BookNEC3 Engineering and Constructiion Contract
What are the contractual arrangement?
Design by Employer
Design and Build / Develop and Construct
Management Contract
YES
NO
30 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
The CIDB Standard for Uniformity of construction procurement documents requires that construction works be
performed using one of the following forms of contract (Figure 5):
i) General Conditions of Contract for Construction Works (GCC 2004);
ii) Conditions of Contract for Construction, Conditions of Contract for Plant and Design-Build,
Conditions of Contract for FIDIC EPC/Turnkey Projects or Short Form of Contract
iii) JBCC series 2000 Principal Building Agreement or Minor Works Agreement; or
iv) NEC3 Engineering and Construction Short Contract or NEC3 Engineering and Construction
Contract.
The Standard further requires that the CIDB Standard Professional Services Contract or the NEC3 Professional
Service Contracts be used for the appointment of professional service providers. The standard requires that
these forms of contract “beusedwithminimalprojectspecificvariationsandadditionswhichdonotchangetheir
intendedusage.”
4.3.2 Decision criteria for the selection of a suitable formof contract for constructionworksThere are a number of factors that influence the client bodies to choose one form of contract over another. Where
several forms of contract satisfy requirements, consider the need for the following in the final selection of a form
of contract (see Table 2 below):
4.3.2.1 Back-to-backcontract Eliminate FIDIC and GCC 2010 Forms of Contract as they currently do not make provision fo
subcontracts (FIDIC has a test version available).
4.3.2.2 Riskassessmentandallocation Changes to the price arising from the Employer’s Risk are assessed as the cost to the
contractor without reference to tendered rates and prices, the philosophy being that the
contractor should not be in a better or worse position than before the change. Use only NEC
contracts if this is a consideration.
The proactive management of risks and the assessment of events leading to changes in the
time for delivery or the cost of works to be assessed soon after the event triggering such
changes occurs. Use only NEC contracts if this is a consideration.
4.3.2.3 Incentivisingtheprojectteamtoperformbetter If it is also the intention of the client to incentivise the supply team to perform better, you
must use only NEC contracts if this is a consideration.
31EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.3.2.4 Familiaritywithaparticularformofcontract If the organisation is only familiar with a particular form of contract and the kind of projects
are once off in nature, then the client can consider the use of the form of contract that is most
familiar to the organisation and their professional team.
Form of Contract
FIDIC Conditions of Contract for Construction for Building and Engineering Works designed by the Em-ployer (Red Book)
FIDIC Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant and for Building and Engineering Works, designed by the Contractor (Yellow Book)
FIDIC Conditions of Contract for EPC Turnkey Projects (Silver Book)
FIDIC Short Form of Contract (Green Book) as pub-lished by the International Federation of Consulting Engineers (Green Book)
General Conditions of Contract for Construction Work (GCC 2010)
JBCC Principal Building Agreement
JBCC Principal Building Agreement - Minor Works Building Agreement
NEC3 Engineering and Construction Contract (ECC)
NEC3 Engineering and Construction Short Contract (ECSC)
Decision Criteria Building or Engineering works designed by the Employ-er. The works may include some elements of contractor designed works.
The provision of electrical or mechanical plant and the design and construction of building or engineering works.
The provision on a turnkey basis of a process or power plant, of a factory or similar facility, or an infrastructure project or other type of development.
Building or Engineering works of relatively small capital value or for relatively simple or repetitive work or work of short duration. Use for Design by Employer or contrac-tor designed works.
Construction and Building works contracts, and con-tracting strategy. Although its focal point is on the con-tracting strategy of Design by Employer, it is also suit-able for the Design and Construct.
Building works where the contractor is not responsible for design of the permanent works or the co-ordination of design elements.
Minor building works of simple content where:• The contractor is not responsible for the design of the works;• The Employer appoints direct contractors for spe- cialised work or the installation of items not under taken by the contractor• The construction period is not more than 9 months
Engineering and Construction works, including any level of design responsibility.
Engineering and Construction works which do not re-quire sophisticated management techniques, comprise straightforward work and impose only low risk on both the Employer and contractor.
Table 2: Decision criteria for the selection of the form of contract for construction works
32 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.3.3 Determineprocurementarrangements(DecideonQualitystrategy)The compiler is to determine the strategies to ensure quality in the procurement in addition to the full and unam-
biguous specification of requirements in the scope of work, based on the decision criteria contained in Figure 6
(Selecting suitable quality strategies).
1. Decide on Quality Strategy
2. Decide on Procurement Procedure
3. Decide on Targeted Procurement Strategy
4. Decide on a Tender Evaluation Procedure
Figure 6: Deciding criteria for procurement arrangements for EPWP Large Projects
Note: A public body procurement policy may limit or place certain restriction on the use of some options
Description OutputDetermine quality strategy Suitable quality strategies
Description OutputDetermine procurement procedure A suitable procurement procedure
Description OutputDetermine targeted procurement Suitable targeted procurementstrategy procedures
Description OutputIdentify the appropriate tender A suitable tender evaluationevaluation procedure procedure
Quality Strategy Options• Life cycle costing• Prequalification• Evaluation criteria• Undertakings at tender stage• Preference• Eligibility criteria
Targeted Procurement Procedure Options• Preferencing• Incentives for KPI’s• Mandatory subcontracting• Contractual obligations
Tender Evaluation Procedure Options• Method 1: Financial offer• Method 2: Financial offer and preferences• Method 3: Financial offer and quality• Method 4: Financial offer, quality and preferences
Procurement Procedure Options• Competitive selection procedure • Nominated • Open • Qualified • Quotation • Proposal procedure using the - two envelope system • Proposal procedure using the - two stage tendering system• Negotiation procedure • Competitive negotiations procedure • Open • RestrictedEligibility criteria, if applicable
33EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.4 Design and Documentation for EPWP Large Projects
4.4.1 DesignanddocumentationcompliancetoEPWPguidelinesIt is expected that the design and documentation of EPWP large projects have to comply with the “Guidelines for
the implementation of labour-intensive infrastructure projects under the EPWP” (DPW, 2005). The Guidelines
were developed by the National Department of Public Works, with the aim of providing provinces and munici-
palities with the necessary tools to successfully tender the infrastructure projects as labour-intensive projects.
The guidelines were designed with the aim of minimising the additional work required from provincial and munici-
pal officials by providing instructions on how additional clauses can be included in contractors for consultants and
contractors involved in planning and implementation of labour-intensive infrastructure projects.
The compiler of construction procurement documents is also to ensure that the tender documents do identify the
types of projects that have potential for being implemented labour-intensively and simultaneously incorporate the
relevant clauses in the various sections of the tender documents, especially the tender data, pricing instructions,
specifications, Bill of Quantities / Schedule of Activities and the scope of works sections of the tender documents.
The aim of incorporating the clauses is to ensure that the specific scope of work targeted for labour-intensive
construction must yield more work opportunities in comparison to the conventional approach.
4.4.2 Labour-intensivecomplianceforBuilt-EnvironmentProfessionalsThe public bodies are to ensure that the Built-Environment Professionals responsible for the design and the docu-
mentation of large projects must have the required labour-intensive construction qualification, at NQF level 5 or 7.
4.4.3 Labour-intensiveconstructioncomplianceforcontractorsThe public sector client body to ensure that works contracts for large projects are awarded to contractors who
have in their employ managers who have completed the necessary skills training in terms of the“Guidelinesfor
theImplementationofLabour-IntensiveInfrastructureProjectsundertheEPWP”.
34 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.4.4 ConstructionIndustryDevelopmentBoardcompliancerequirements
4.4.4.1 StandardforUniformityofConstructionProcurementDocuments The compiler to prepare the tender documents in accordance with the CIDB Standard for
Uniformity in construction procurement documentation. The complier might consider using the
single volume approach or the three volume approach in the compilation of construction procure-
ment documents. In the single volume approach, the procurement document consists of two
parts compiled in a single volume. The first part comprises “The Tender” and the second
part comprises “The Contract” (See Figure 7). In the three volume approach, the standard
headings of the document are kept the same (as the single volume headings), but they are
divided into three volumes. Only the tender returnable documents (Volume 2) are returned as
part of the Tender submission (See Figure 8).
Figure 7: Single Volume approach to the packaging of construction procurement documentation Source: CIDB SFU (Standard for Uniformity, 8 August 2005)
Tender
Contract
Part 1 Tendering Procedures T1.1 Tender Notice and Invitation to Tender T1.2 Tender DataPart 2 Returnable Documents T2.1 List of Returnable Documents T2.2 Returnable Schedules
Part 1 Agreements and Contract Data C1.1 Offer and Acceptance C1.2 Contract DataPart 2 Pricing Data C2.1 Pricing Assumptions C2.2 Activity Schedule / Bill of QuantitiesPart 3 Scope of Work (C3)Part 4 Site Information (C4) (For Works only)
35EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
4.4.4.2 CompliancewiththeCIDBRegisterofContractors(RoC)
The CIDB Act (No. 38 of 2000) requires the CIDB to establish and maintain a Register of Contrac-
tors (RoC) to regulate those persons who contract with the public sector to provide construction
works. The RoC is not mandatory for private sector contractors. Public sector client bodies
implementing EPWP Large projects can only make use of CIDB registered contractors, with the
correct grading designations.
4.4.4.3 CompliancewiththeCIDBRegisterofProjects(RoP) The CIDB Act (No. 38 of 2000) also permits the CIDB to establish and maintain a Register of
Projects (i.e. RoP). The RoP is aimed at registering construction projects with a minimum
value as determined by the CIDB Regulations in order to capture the size, distribution and profile
of construction projects that are being implemented by the both the public and the private sector
client bodies.
Once the successful contractors have been selected for the award of contracts, all the construc-
tion projects with a value in excess of R200, 000 must also be registered with the CIDB Register
of Projects (RoP). The registration with the RoP must be complied with during the advertising,
award and cancellation / termination stages of the project.
Figure 8: Three Volume Approach to compilation of construction procurement documents Source: CIDB SFU (Standard for Uniformity, 8 August 2005)
Volume 1:Tendering Procedures
Volume 2:Returnable Documents
Volume 3:Draft Contract
Part 1 Tendering Procedures T1.1 Tender Notice and Invitation to Tender T1.2 Tender DataPart 2 Returnable Documents T2.1 List of Returnable Documents T2.2 Returnable Schedules
Part 1 Returnable Documents T2.1 List of Returnable Documents T2.2 Returnable Schedules C1.1 Form of Offer and Acceptance C1.2 Contract Data (Part 2 by Contractor) C2.2 Activity Schedule / Bill of Quantities
Part 1 Agreements and Contract Data C2.2 Contract Data (Part 1: Data by Employer)Part 2 Pricing Data C2.1 Pricing AssumptionsPart 3 Scope of Work (C3)Part 4 Site Information (C4) (For Works only)
FinalContractdocumentcompliedafterevaluation
36 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
The Contractor is obliged to produce a work schedule
(programme) as indication of the forecast progress of
the works to completion. The Project Manager shall
have to monitor the actual work against the planned
progress and the ability of the contractor to complete
the works within the contractually stipulated time.
In addition to the above, there are additional EPWP re-
porting requirements that have to be met by the contrac-
tors and the Project Managers. The EPWP has already
developed the core monitoring indicators that are used
to monitor and report progress on the implementation of
EPWP initiatives across the various sectors.
5.1 Monitoring IndicatorsThe EPWP indicators referred to above include:
• Person-days of Employment created;
• Person Years of Employment / Full Time Equivalents (FTE’s);
• Job Opportunities;
• Project Wage;
• Training Person-days;
• Project Budget;
• Actual Expenditure; and
• Demographic targets
- Women;
- Youth; and
- People with Disabilities
Monitoring and Reporting Requirements of EPWP Large Projects
5.
37EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
5.2 EPWP reporting templatesThe reporting templates and the definitions of the above monitoring indicators have also been developed by the
EPWP Unit of the National Department of Public Works. The public body has to collect performance related data
on a monthly basis and ensure that such reports are captured in the EPWP reporting system. The Reporting tem-
plates are attached to these Guidelines as Annexures C and D.
5.3 Progress monitoring Progress monitoring and reporting must be done on a project basis. The Project Implementing Body must collect
information from the Project Manager, who will in turn collect such information from the Contractor at a project
level, using the project reporting templates developed by the EPWP Unit. The Daily Attendance Demographic
reports are to be consolidated into monthly and then quarterly reports for submission to the public body.
38 EPWP Large Projects Guidelines - Scaling Up Delivery and Job Creation
Bentall, P., Beusch, A., and De Veen J., (1999): Employment-Intensive Infrastructure Programmes: Capacity Building for Contracting in the Construction Sector, Development Policies Department, International Labour Office (ILO), Geneva.
Constitution of the Republic of South Africa (Act No. 108 of 1996), Parliament of the Republic of South Africa, Government Printers, 1996.
Construction Industry Development Board Act (No. 38 of 2000), Government Printers, Republic of South Africa, 2000.
Construction Industry Development Board Inform Practice Note No. 229: CIDB Infrastructure Gateway System- an overview, September 2010.
Construction Industry Development Board Practice Note No. 10: Attaining social and economic deliverables, February 2008.
Construction Industry Development Board Practice Note No. 11: Programme Management Approach to delivery, February 2008.
Construction Industry Development Board Practice Note No. 23: Construction Procurement Strategy, September 2010.
Construction Industry Development Board Practice Note No. 24: Managing construction procurement processes, September 2010.
Construction Industry Development Board Inform Practice Notes No’s: 22, 22a and 22b – CIDB Infrastructure Gateway System, September 2010.
Construction Industry Development Board Practice Note No. 7: Subcontracting Arrangements, May 2007.
Construction Industry Development Board: Standard for Uniformity in Construction Procurement, Board Notice No. 94 of 2006, Government Gazette No. 29138 of 18 August 2006.
Construction Industry Development Board Inform Practice Note No. 1, Scaling up delivery and accelerating empowerment, August 2008.
Construction Industry Development Board Management Guidelines: Practice Guide 2- Construction Procurement Strategy, April 2011.
Construction Industry Development Board: Labour-Based methods and technologies for employment intensive construction works, March 2005.
Expanded Public Works Programme (EPWP) Phase 2 Business Plan: 2009-2014, National Department of Public Works, Republic of South Africa, 2009.
EPWP Guidelines for the implementation of labour-intensive construction infrastructure projects, EPWP Unit, National Depart-ment of Public Works, 2006.
ILO (2012): Study on Enhancing Labour-Intensity in the Expanded Public Works Programme Road Infrastructure Projects, International Labour Organisation (ILO), Pretoria September 2011.
Local Government Municipal Systems Act (No. 32 of 2000), Department of Cooperative Governance and Traditional Affairs, GovernmentPrinters, 2000.
Municipal Finance Management Act (No. 56 of 2003), National Treasury, Government Printers, Republic of South Africa, 2003.
National Department of Public Works: Guidelines for enhancing employment opportunities in the delivery of infrastructure projects: A National Public Works Programme Initiative, Republic of South Africa, July 1999.
National Treasury and CIDB (2006 & 2010): Infrastructure Delivery Improvement Programme (IDIP) Toolkit.
Preferential Procurement Policy Framework Act (No. 5 of 2000), National Treasury, Government Printers, Republic of South Africa, 2000.
Public Finance Management Act (No. 1 of 1999, as amended), National Treasury, Government Printers, Republic of South Africa, 1999.
Tajgman, D. and De Veen, J. (1998): Employment-Intensive Infrastructure Programmes: Labour policies and practices, Development Policies Department, International Labour Office, Geneva. Watermeyer, R. B. and Thumbiran, I. (May 2009): Delivering infrastructure at scale in developing countries: Numbers or Systems? – The Fourth Built Environment Conference hosted by SOCSA, Livingstone, Zambia.
Watermeyer, R. B., Nevin, G., Amod, S. A. and Hallet, R.A. (1995): An Evaluation of projects within the Soweto’s Contractor Develop-ment Programme, Journal of the South African Institution of Civil Engineers, Vol. No. 26, No. 2, pp. 17 – 26.
Watermeyer, R. B., Larkin, D. and Van Huysteen, S. (2007): A model for the delivery of large scale employment-intensive works using a programme management approach. Prioritising Employment creation in Government Policies, Programmes and Investments, 12th ILO Regional Seminar for Labour Based Practitioners, Durban, South Africa, 8-12 October 2007.
Watermeyer, R. B. Larkin, D., Kee, A. and Thumbiran, I. (2008): Delivering Infrastructure at scale: eThekwini Water and Sanitation experience in a Pilot project.
Watermeyer, R. B. et al (March 2001): Delivering infrastructure at scale: eThekwini Water and Sanitation experience in a pilot project, Civil Engineering Journal. Watermeyer, R. B. (September 2006): Accelerating the EPWP – the engagement of large contractors in public sector projects.
References
Annexure AAn Overview of Contracting Strategies for
Construction and Engineering Projects
index
List of Figures
Figure A1 Design by Employer Strategy
Figure A2 Design and Build Strategy
Figure A3 Develop and Construct Strategy
Figure A4 Construction Management Strategy
Figure A5 Management Contracting Strategy
List of Figures
40
Page
1. Design by Employer 41
2. Design and Build 41
3. Develop and Construct 42
4. Construction Management Strategy 42
5. Management Contracting Strategy 43
Design by Employer
Design and Build
The historic approach to delivery in the civil and building sector has been the Design by Employer Strategy, whereby the contractor only undertakes construction on the basis of full designs issued by the employer (See Figure A1). This contracting strategy requires that the design and specifications be adequately devel-oped before tenders are invited (CIDBInformPracticeNoteNo.1,August2006:Scalingupdeliveryandacceleratingempowerment).
In the Design and Build strategy, the contractor undertakes most of the design and all construction in ac-cordance with the Employer’s brief and his detailed tender submission, usually for a lump sum price (See Figure A2).
The contractor undertakes only construc-tion on the basis of full designs issued by the employer. Design is a separate func-tion to construction and is managed by the client or his agent. The Employer has the capability and capacity to make de-cisions during the design process.
The design is integrated with construction and is managed by the contractor. In this case the client has approved a Concept Report setting out the integrated concept. This is then used by the contractor to de-velop the scope of work for the contract.
1.
2.
Figure A1: Design by Employer
Figure A2: Design and Build
Employer
Consultant(Designer)
Contractor(Constructor)
41Annexure A: An Overview of Contracting Strategies for Construction and Engineering Projects
Source: Delivery Management Guidelines, (CIDB: 2011)
Source: Delivery Management Guidelines, (CIDB: 2011)
Consultant(Designer andConstructor)
Employer
42
Develop and Construct3.
Construction Management Strategy
The Develop and Construct strategy is similar to the design and build strategy, except that the Employer issues a concept design on which tenders are based (See Figure A3). The strategy is based on a scheme design prepared by the Employer under which a contractor finalises the production information and con-structs it. The final design details are integrated with construction and are managed by the contractor.
This is a contracting strategy under which a third party (professional service provider) provides consulta-tion during the design stage and is responsible for planning and managing all post-contracting activities for a group of contractors appointed by the employers (See Figure A4) (CIDBDeliveryManagementGuidelines:PracticeGuide2–ConstructionProcurementStrategy,2011-04-20).
4.
Employer
Construct ionManager
Contractors(Constructors)
Subcontractor(Construction Works
Subcontract)
Subcontractor(Construction Works
Subcontract)
Subcontractor(Construction Works
Subcontract)
Subcontractor(Construction Works
Subcontract)
Consultants(Professional Services)
Annexure A: An Overview of Contracting Strategies for Construction and Engineering Projects
The Employer prepares the Design Devel-opment Report setting out the integrated developed design for the project. The re-port is then used to develop the scope of work for the contract.
In the construction Management Strategy a construction manager can accept responsi-bility for delivering the completed project by a date set for a target or fixed price.
Accordingly, a construction manager may provide management services from the time that the design process is initiated to the commissioning and hand over of the completed works which relate to the con-trol of time and cost (PracticeNoteNo.1,August 2006:Scaling up delivery and ac-celeratingempowerment).
Source: Delivery Management Guidelines, (CIDB: 2011)
Source: Delivery Management Guidelines, (CIDB: 2011)
Figure A3: Design and Construct
Figure A4: Construction Management Strategy
Consultant(Conceptual
Design)
Employer
Contractors(Constructors)
43
Management Contracting Strategy
This is usually ideal where there is a need for the third party support to ensure the successful delivery of a project usually through a design by employer contracting strategy. This strategy is also ideal where the programme involves the participation of small or emerging contracting entities. Such enterprises may require third party support in order to complete their contracts satisfactory. Such support may take the form of construction or materials management support. Third party management, which is in the form of construction management, is required where there is a significant risk that small contractors may fail to timeously and satisfactorily complete their contracts.
The strength of this strategy lies in the high level of supervision and support that can be extended to emerging contractors. As a result, the Construction Manager’s staff should consist of people with exten-sive contracting experience to be able to support and mentor emerging contractors (DepartmentofPublicWorks,NPWPBranch,June1999).
5.
Employer
Design Consultant(Professional Service Contract)
Subcontractor(Construction Works
Subcontract)
Subcontractor(Construction Works
Subcontract)
Subcontractor(Construction Works
Subcontract)
Subcontractor(Professional Serv-
ice Contract)
Annexure A: An Overview of Contracting Strategies for Construction and Engineering Projects
This is a contracting strategy under which a contractor is responsible for planning and managing all post-contract activities, including, if required, any design of works or portion thereof, and for the performance of the whole contract (See Figure A5)
Source: Delivery Management Guidelines, (CIDB: 2011)
Figure A5: Management Contracting Strategy
ManagementConstructor
44 Annexure A: An Overview of Contracting Strategies for Construction and Engineering Projects
Annexure BReview of eThekwini Metropolitan Municipality Infrastructure
Delivery Model - an example of an EPWP Large Project Case Study
Case Study Review in Collaboration with the City of eThekwini Metropolitan Municipality Water and Sanitation Business Unit
46
index Page
1. List of Abbreviations 49
2. Introduction 50
3. eThekwini Metropolitan Municipality Infrastructure Delivery Model 51 3.1 Background to the Delivery Model 51 3.2 Mobilization of the Project Team 51 3.2.1 Appointment of the Design Consultants. 51 3.2.2 Appointment of the Programme Manager 51 3.3 Mobilization of the Construction Team 51 3.3.1 Appointment of Contractors 51 3.3.2 Appointment of Subcontractors 52 3.4 Roles and Responsibilities 53 3.4.1 Client (eThekwini Municipality) 53 3.4.2 Design Consultants 53 3.4.3 Programme Manager 53 3.4.4 Technical Mentorship support consultants 53 3.4.5 Training Service Providers 54 3.4.6 Material Suppliers 54 3.5 The Unique Features of the eThekwini Infrastructure Delivery Model 54 3.5.1 Grouping of similar projects into a programme 54 3.5.2 Contractors were on a medium to long-term duration 54 (say 3 years) 3.5.3 Introduction of a single point of accountability 54 3.5.4 Introduction of risk and project management practices 55 3.5.5 Implementation of projects with a broad scope of work 55 3.5.6 Maximum use of local resources 55 3.5.7 Partnership opportunities 55 3.6 Construction Procurement Strategy of the Municipality 56 3.6.1 Delivery management strategy 56 3.6.2 Contracting Arrangements 56
47
Page
3.6.3 Procurement arrangements for the programme 60 a) Accommodating the Social and Economic Agenda b) SMME Development and Job creation achievements of the project c) Allocation of Work between Contractors d) Role of Subcontractors in the model 3.7 Enterprise development opportunities 67 3.7.1 Targeting strategy of participants 67 3.7.2 Subcontracting within the eThekwini Delivery Model 67 3.7.3 Entry level of subcontractors. 68 3.7.4 Standard forms of subcontract 68 3.7.5 CIDB Registration Requirements 69 3.8 Training and skills development issues of the model 69 3.8.1 Training and capacity building opportunities for the subcontractors 69 3.8.2 Technical training for workers 70 3.8.3 Workplace experience for Built Environment Students and young professionals 70 3.9 Job Creation potential of eThekwini infrastructure delivery model 70 3.9.1 Targets set for employment opportunities 70 3.9.2 Actual job creation actual 70 3.9.3 Quality of work opportunities created 70 3.9.4 Conditions of employment of the local labour 71 3.10 Monitoring, Reporting and Evaluation of the model 71 3.11 Funding model of the programme 71 4. Observations and Lessons Emanating from the Review of the Case Study 72 4.1 Early buy-in and commitment of key decision makers 72 4.2 Change management processes 72 4.3 Mobilization workshops 72 4.4 Value of social facilitation in infrastructure development programmes 73 4.5 Procurement in the absence of detailed scope of work 73 4.6 Mobilization of the Project Team at short notice 73 4.7 Long-term large contracts can be implemented by public bodies 73 4.8 Addressing socio-economic opportunities through large-scale infrastructure delivery 74 4.9 Advancement of the contractor development agenda / targeted procurement 74 4.10 Addressing capacity constraints of public sector client bodies 74 4.11 Ability to harness the capability and capacity of the private sector 75 4.12 Political Commitment 75
5. References 76
48
List of Figures and Tables
Figure B1 Organizational structure of eThekwini Infrastructure Delivery Model
Figure B2 Contracting Strategy for eThekwini Metropolitan Municipality’s Delivery Model
Table B1 Summary of the generic contracting strategies
Table B2 Summary of costs
Table B3 Selecting suitable quality strategies
Table B4 Summary of basic competitive selection procedures
Table B5 Summary of generic procurement strategies
Table B6 Recommended combinations of forms of contract and forms of sub-contract
List of Figures
List of Tables
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
49
1.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
List of Abbreviations1.
CE Civil Engineering
CETA Construction and Engineering Training Authority
CIDB Construction Industry Development Board
CPG Contract Participation Goals
DPW Department of Public Works
ECC Engineering and Construction Contract
ECS Engineering and Construction Subcontract
ECSS Engineering and Construction Short Subcontract
EPWP Expanded Public Works Programme
FTE Full Time Equivalent
GCC General Conditions of Contract
JBCC Joint Building Contracts Committee
MFMA Municipal Finance Management Act
MTEF Medium-Term Expenditure Framework
NEC New Engineering Contract
PSC Professional Services Contract
50
Introduction2.
The EPWP Large Projects Directorate of the National Department of Public Works support Public Bodies
with the implementation of labour intensive infrastructure projects with a value exceeding R30 million. The
objective of the Directorate is to improve the impact on poverty alleviation by large capital projects through
the increase of labour intensity of such projects. The two support strategies currently in place for imple-
mentation are:
• Increase of labour intensive components of projects with a budget exceeding R30 million; and
• Bundling of similar projects to create a single large project of a value exceeding R30 million.
The above strategies were piloted by a number of public and private sector client bodies. The unfortunate
issue is that there were no elaborate user-friendly guidelines to guide the officials or the private sector with
regard to the rollout of these kinds of projects. It is in the light of the above that the National Department
of Public Works decided to document the implementation model of the eThekwini Metropolitan Municipality.
The purpose of documenting the eThekwini delivery model is also aimed at highlighting certain operational
and strategic lessons that the public sector client bodies have to consider in the planning, implementation
and management of large EPWP infrastructure projects. It is also expected that the results of the review
of the Case Study will set the tone for the preparation of user-friendly guidelines that will be workshopped
and eventually applied by the various public sector client bodies.
The guidelines for Large EPWP projects will have to take into account the three project management
aspects, i.e. quality, time, cost and any other socio-economic deliverables / objectives. The challenge in
developing and implementing a delivery model that enables allocated budgets to be spent is to do so in a
manner that results not only in construction works of an acceptable quality being delivered in response to
prioritized needs, but also contributes to the social and economic agenda including employment and skills
development.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
51
3.1 Background to the Delivery ModelThe eThekwini Water and Sanitation maintains some 13 000 km of water mains in the Durban area of which approximately 3,000 km were aging undiped asbestos cement pipes of 150 mm diameter or less. During the 2007/08 Financial Year, these old asbestos cement pipes were at the end of their useful life, and used to burst frequently and needed to be replaced. eThekwini adopted the delivery model outlined in this Case Study Report which allowed the target price associated with each work package within identified reservoir zones be established once the scope of work and socio-economic deliverables were finalized.
3.2 Mobilization of the Project Team
3.2.1 AppointmentoftheDesignConsultantsThe municipality appointed the Design Consultants through an open procurement process using the Ex-pression of Interest and then invited Tender option. The municipality appointed a total of four (4) success-ful professional service providers who later signed contracts with the municipality, in accordance with the NEC3 Engineering and Construction form of contracts.
3.2.2 AppointmentoftheProgrammeManagerThe Programme Manager was also appointed using the open process, with the Expression of Interest and invited tender option used. Only one (1) programme manager was appointed to manage the programme and to interface with the municipal executive manager.
3.3 Mobilization of the Construction Team
3.3.1 AppointmentofContractorsA total of four (4) main contractors were appointed by the municipality. These were contractors with cidb grading designations of 7 CE or higher. The intention was for the four main contractors to train and men-tor the sixteen subcontractors who were later appointed by the municipality, as nominated subcontractors (See Figure 2 below).
eThekwini Metropolitan MunicipalityInfrastructure Delivery Model
3.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
52
Figure B1: Organizational Structure of eThekwini Infrastructure Delivery Model
3.3.2 AppointmentofSubcontractorsA total of sixteen (16) subcontractors were eventually selected to be part of the programme. The selection process was also an open process, whereby the municipality issued an expression of interest calling upon interested contractors to apply and submit their credentials and corporate profiles. The subcontractors were grouped into four teams, with each team comprising of one Design Consultant, one Main Contractor, and four Subcontractors.These were selected subcontractors, i.e. a procurement process whereby the subcontractors are selected by the contractor in consultation with the employer in terms of the requirements of the contract. At the end the contractors had to sign the normal subcontract agreements with the subcontractors using the NEC Subcontract Agreements.
Employer(eThekwini Metro)
Programme Manager Ninham Shand (PSC3)
4 x Main Contractors(ECC3, ECSC3)
Design Consultant(4 Entities) (PSC3)
Icon Construction(Pty) Ltd
Stemele Bosch Africa(Pty) Ltd BKS (Pty) Ltd
CBI ConsultingEngineers (Pty) Ltd GOBA (Pty) Ltd
WBHO / INSITUPipelines JV
WK Construction(Pty) Ltd
Afriscan Construction
(Pty) Ltd SANYATI
4 x Subcontractors
4 x Subcontractors
4 x Subcontractors
4 x Subcontractors
Community LiaisonOfficer (CLO)
Community LiaisonOfficer (CLO)
Community LiaisonOfficer (CLO)
Community LiaisonOfficer (CLO)
Mentorship SupportService Provider
Risk AuditConsultant
Legend for NEC3 Contracts:
PSC: Professional Service ContractECC: Engineering and Construction ContractECS: Engineering and Construction SubcontractECSS: Engineering and Construction Short Subcontract
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
53
3.4 Roles and Responsibilities
3.4.1 Client(eThekwiniMunicipality)The Client was responsible for the conceptualization of the model and the appointment of the professional team and the four (4) construction teams (contractors).
3.4.2 DesignConsultantsThe four (4) design consultants appointed by the Municipality were allocated to the four (4) main contrac-tors to take responsibility for the detailed designs within the reservoir zones that were allocated to the four teams. The three stage scope of the Design Consultants included: • Identification of the scope of work; • Design of the works; and • Supervision of the works. The Design Consultants were also responsible for quality control and compliance of the contractors with the design specifications issued by the Client.
3.4.3 ProgrammeManagerThe main responsibility of the Programme Manager and Cost Consultants was to coordinate the work of the four teams and report to the municipality through the municipal senior executive who was tasked with the responsibility of delivering on this project. The Programme Manager was also the cost consultants who were responsible for the allocation of the budgets and ensuring that budgets were spent in accordance with the estimates and the approved scope of work.
3.4.4 TechnicalMentorshipSupportConsultantsA full time mentor was engaged to assist the co-contractors to establish business systems in order to im-prove their sustainability and to grow their businesses. Key performance assessments of these contractors were undertaken by the mentor at regular intervals to monitor their progress. The expected annual turno-vers of these co-contractors at the end of the contract was expected to be between R1, 000, 000.00 and R10, 000 000.00.
The technical mentorship support consultant was identified by the municipality but appointed by the Main Contractors to render mentorship support to all the appointed subcontractors. The one mentorship support consultant appointed by the Main Contractors was shared by the four teams, and was paid directly by the main contractors, on a proven cost basis.
With regard to the funding of the Mentors’ fees, these were taken care of by the municipality as part of the recoverable expenses that were claimed by the Main Contractors. Considering the total budget of the programme (R2 billion at the end of the programme), the costs of mentorship support services were ap-proximately 1% of the programme budget.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
54
3.4.5 TrainingServiceProvidersInitially the municipality had envisaged appointing a training provider to render training to all the subcon-
tractors and the workers. The lack of training budget and the delays from the Department of Labour and
the Construction Education and Training Authority (CETA) made it almost impossible for this dream to be
realized. The bulk of training was rendered on site for subcontractors by the appointed mentorship sup-
port consultants. The subcontractors were awarded the certificates of attendance, not the certificates of
competence. The main weakness of the programme was the lack of a coherent training programme for the
subcontractors.
3.4.6 MaterialSuppliersIn order to ensure that the required materials were always available for the duration of the project, the vari-
ous material suppliers were briefed on the materials required and all the main contractors had to buy the
materials from the identified suppliers. There were a total of five (5) materials suppliers who were engaged
by the municipality, on the basis of the supplier database that they had at the time.
What was of significance was that the Main Contractors purchased all the materials on their own and in
some cases they were able to get better prices for the materials from outside of the eThekwini Metropolitan
area of jurisdiction. In cases where the suppliers might have considered to collude and artificially raise the
prices, the Main Contractors had the latitude to source such materials elsewhere, at cheaper prices than
those offered by the eThekwini based suppliers.
3.5 The Unique Features of the eThekwini Infrastructure Delivery ModelThe delivery model of the eThekwini Water and Sanitation was informed by four strategic thrusts, namely:
3.5.1 GroupingofSimilarProjectsintoaProgrammeProjects of a similar nature were grouped together within a geographic region into a single programme.
5.5.2 ContractorswereonaMediumtoLong-TermDuration(say3years)Key contracts associated with a programme are placed with a limited number of service providers and /
or contractors for a period of not less than 3 years. The construction works contracts that were concluded
were for a three year period and were based on the NEC3 Engineering and Construction Target Contract
option (Option C).
3.5.3 IntroductionofaSinglePointofAccountabilitySingle point accountability was assigned to those who were contracted for developing and overseeing the
implementation of the programme. The Programme Manager was the main interface between the munici-
pality and the Team.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
55
3.5.4 IntroductionofRiskandProjectManagementPracticesEfficient and integrated risk management and project management practices were introduced in the pro-
gramme. The Programme Manager was required to introduce and maintain a risk register which was proc-
essed through the fortnightly project team meetings and also risk reduction meetings between the parties.
In addition, a Programme Manager was mandated to engage a separate company to carry out monthly risk
audits for all the sites.
3.5.5 ImplementationofProjectswithaBroadScopeofWorkTypically at the commencement of the programme (series of projects), the only “knowns” were the allocated
medium term budget, a list of short term priorities and possibly an indicative broad brush breakdown of the
budget into prioritized reservoir zones for the first year of the programme, based on eThekwini GIS and
burst records.
Individual projects within a programme were scoped, designed and documented so that construction could
take place. This cycle needs to be repeated so that as projects are identified, they can be scoped, designed
and documented so that construction occurs on a continuous basis over the period of the programme. Ac-
cordingly, the delivery model was capable of procuring services in the absence of a well defined scope of
work.
3.5.6 MaximumuseofLocalResourcesThe project was able to maximize the use of local resources, e.g. bedding sand, security, plant hire, amongst
others. All the labour for each of the Reservoir Zone was sourced locally in the respective community where
the work was to be carried out, using the labour rotational model.
3.5.7 PartnershipOpportunitiesThe programme also offered opportunities for the development of much needed technical skills that were
required by municipal staff and also by the students from the various Universities of Technology to enable
them to qualify and graduates from the various institutions. The programme also offered opportunities for
in-service training for a number of professional beneficiaries.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
56
3.6 Construction Procurement Strategy of the Municipality
3.6.1 DeliveryManagementStrategyDelivery management is the management of the process of public service delivery as applied to infrastruc-
ture and maintenance projects. On the basis of the analysis of the expenditure, organisational and market
analysis, and informed by the procurement objectives the client makes strategic delivery management de-
cisions. The client also decides on the delivery model, i.e. whether the delivery will be as a project or pro-
gramme and ultimately the packaging of works.
In terms of the eThekwini delivery model, the municipality decided on a programme approach to delivery.
The municipality identified a programme comprising a number of projects and obtained the necessary fund-
ing for it. The programme approach to delivery provided the municipality with an umbrella under which
several projects were planned, implemented and managed. The use of this model for the municipality had
a number of benefits, namely:
• Coordinating multiple projects which would not have been realised if the projects were managed
independently;
• Projects were linked to an overall client organisational strategy;
• Projects of a similar nature and these were linked together to obtain the advantages of repetition;
• Projects were grouped together because of their similar supporting service deliveries, similar
governance requirements, common stakeholder or change management or similar risk profiles;
• They had similar planning, procurement and implementation timelines; and
• The client was able to implement the programme with the active involvement of two senior
executives from the municipality, while the rest of the work was carried out by the appointed
programme management team.
In terms of the eThekwini delivery model, the municipality identified a programme as a grouping of indi-
vidual projects and obtained the necessary funding for it. The client thereafter procured the services of a
Programme Manager and one or more Design Consultants and Contractors in terms of a competitive pro-
curement process in the absence of any detailed scope of work using the NEC3 family of standard contracts
published by the Institution of Civil Engineers, London and the CIDB Standard for Uniformity in Construction
Procurement.
3.6.2ContractingArrangements 3.6.2.1 DefinitionofacontractingstrategyA contracting strategy is a strategy that governs the nature of the relationships which the employer wishes to
foster with the contractor, which in turn determines the risks and responsibilities between the parties to the
contract and the methodology by which the contractor is to be paid (ISO 10845-1- Construction Procurement).
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
57
Because of the diversity of the construction and the client’s requirements, no single uniform approach to
contractual arrangements can be advocated. The choice of any of a contracting strategy is informed by a
number of factors, namely:
• the type of work at hand;
• the allocation of risk;
• the programme management requirements;
• the design strategy; and
• the arrangements or the employment of programme manager, design consultants and the
contractors.
eThekwini municipality used a combination of the Construction Management and the Design and Construct
contracting strategies to deliver on this programme (See Figure B3).
Table B1: Summary of the Generic Contracting Strategies
Design by Employer
Contract under which a
contractor undertakes
only construction on
the basis of full designs
issued by the employ-
er. Design is a separate
function to construction
and is managed by the
client or his agent.
Develop and Con-
struct
Contract based on a
scheme design pre-
pared by the client un-
der which a contractor
finalises the production
information and con-
structs it.
Design and Construct
Contract in which a
contractor designs the
works based on a brief
provided by the client
and constructs it.
Construction
Management
Contract under which
a third party (profes-
sional service provider)
provides consultation
during the design stage
and is responsible for
planning and manag-
ing all post-contract
activities for a group of
contractors appointed
by the Employer.
Management
Contractor
Contract under which
a contractor is respon-
sible for planning and
managing all post -con-
tract activities, includ-
ing, if required, any
design of the works or
portion thereof, and for
the performance of the
whole of the contract.
3.6.2.2 TypicalcontractingstrategiesThere are various contracting strategies that are available in the industry. These include (See Table B4): • Design by Employer; • Develop and Construct; • Design and Construct; • Construction Management; and • Management contractor.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
58
3.6.2.3 PricingStrategiesFor the eThekwini case study, tenderers were competing on the basis of price and quality for the programme
management, design consultancy and construction services. They tendered for their staff rates and certain
cost parameters relating to expenses while contractors tendered a range of parameters associated with the
NEC3 Schedule of Cost Components, i.e.
• A direct fee percentage;
• A subcontracted fee percentage;
• Time related charges for equipment;
• A percentage for working areas overheads;
• A percentage for manufacture and fabrication overheads;
• A percentage for design overheads; and
• Hourly rates for specified personnel and equipment
Tender assessment schedules were used to develop a comparative price for evaluation purposes, based
on assumed quantities of hours and amounts and the tendered cost parameters (percentages and rates)
(See Table B5).
Table B2: Summary of costs
Item
No:
1
2
3
4
5
6
(Defined cost plus compensation events) x tendered direct fee percentage ……./ 100 = Rand …Fee 1
Subcontracted work x tendered subcontracted fee percentage ……100. = Rand… Fee 2
Total Comparative Figure = Defined Cost plus compensation events plus Fee 1 plus Fee 2.
Component
People
Equipment
Plants and Materials
Charges
Manufacture and Fabrication
Design
Subtotal
Subcontracted Work
Total Defined Cost
Compensation Events
Basis of assumed cost
Employer estimated amount
Employer estimated amount plus tendered amounts for identified
items or percentage of specific hire lists
Employer estimated amount
Employer estimated amount plus tendered percentage on people
for overhead costs in the working areas
Tendered hourly rates multiplied by employer estimate of hours
and overhead percentage for employer estimated hours
Employer estimated amounts
Employer estimated amounts plus tendered percentage for people
overheads and percentage adjustment on listed prices for equip-
ment
Assumed cost,
Rand
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
59
a) Programme ManagerThe Programme Manager converts the budget into a series of works packages, manages the delivery of
the works, acts as the Employer’ Agent in terms of the Design Consultant’s contracts, acts as the Project
Manager in terms of the Contractor’s contract and provides cost consultancy services.
b) Design ConsultantThe Design Consultant provides design services in relation to the identified work packages and monitors
the quality of the constructed works. The contractor constructs the works associated with an identified
works package.
c) ContractorThe Contractor, prior to commencing the work, agrees a target price with the Project Manager based on an
activity schedule developed from the specifications and drawings provided by the Design Consultant for the
identified package of work. During the course of the contract, the contractor is paid his costs as defined in
Option C of the NEC3 Engineering and Construction Contract, based on his tendered cost parameters and
at the end of the contract, the contract is paid his share of the difference between the target price and his
cost according to an agreed formula. If the final cost is greater than the target cost, the Contractor pays his
share of the difference. This motivates the Contractor to control costs.
The Design Consultant was typically paid on a time and cost basis (Option E of the NEC Professional Serv-
ice Contract) until such time as the precise scope of work was known and a target contract could be agreed
with the Design Consultant (Option C).
3.6.2.4 Cost-basedContractThe concept of the model using the Option C (Target Cost) NEC3 Engineering and Construction Contract
was introduced to the Design Branch of eThekwini Water and Sanitation in February 2007, taking into ac-
count the fact that the Branch had not previously used the NEC3 Form of Contract. The decision to pro-
ceed with the model was made during mid February 2007 after a briefing meeting which was attended by
selected officials, contractors and consultants.
3.6.2.5 FormsofContractsUsed(forcontractorsandconsultants)The NEC3 Professional Service Contract was used for the appointment of the consultants (Figure 3). Use
was made of the Construction Industry Development Board’s (CIDB) Specification for Social and Economic
Deliverables in Construction Works Contracts. The contracts with both the contractors and consultants
required that the project be delivered in terms of the generic project stages developed by the Construction
Industry Council (UK) outlined in Table 2 (Watermeyer et al, 2010).
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
60
3.6.3 ProcurementArrangementsfortheProgrammeThe procurement documents for the delivery model were developed in accordance with the requirements
of the CIDB Standard for Uniformity in Construction Procurement documentation.
Legend for NEC3 Contracts:
PSC: Professional Service ContractECC: Engineering and Construction ContractECS: Engineering and Construction SubcontractECSS: Engineering and Construction Short Subcontract
Figure B2: Contracting strategy for eThekwini Metropolitan Municipality’s Delivery Model
4 x Subcontractors(ECS3 or ECSS3)
4 x Subcontractors(ECS3 or ECSS3)
4 x Subcontractors(ECS3 or ECSS3)
4 x Subcontractors(ECS3 or ECSS3)
Employer(eThekwini Metro)
Programme Manager Ninham Shand (PSC3)
4 x Main Contractors(ECC3, ECSC3)
Design Consultant(4 Entities) (PSC3)
Icon Construction(Pty) Ltd
Stemele Bosch Africa(Pty) Ltd BKS (Pty) Ltd
CBI ConsultingEngineers (Pty) Ltd GOBA (Pty) Ltd
WBHO / INSITUPipelines JV
WK Construction(Pty) Ltd
Afriscan Construction
(Pty) Ltd SANYATI
Mentorship SupportService Provider
Risk AuditConsultant
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
61
3.6.3.1 QualityStrategyThe municipality determined the quality strategies that were used in the selection of consultants (Design
Consultants and the Programme Manager) and the four (4) Main contractors and the sixteen (16) subcon-
tractors.
There are a total of six (6) possible quality strategies that could be used by public sector client bodies (Ta-
ble 6 - Selecting suitable quality strategies). The municipality used the Evaluation Criteria strategy for the
programme and the preference mechanism in accordance with the ISO 9000 Standards.
3.6.3.2 ProcurementProcedureThere are three basic competitive selection procedures, namely: Negotiated Procedure, Competitive Se-
lection and Competitive Negotiations. Within the three basic competitive selection procedures, there are
a total of eight (8) potential procedures to choose from, namely: Nominated, Open, Qualified, Quotation,
Proposal procedure using the two-envelope system, Proposal procedure using the two-stage system, re-
stricted competitive negotiations and the Open competitive negotiations (See Table B7 below).
a) Pre-Qualified Approach (Competitive Selection)In the case of eThekwini municipality, Expressions of Interest were prepared in accordance with the CIDB’s
Standard for Uniformity in Construction Procurement, advertised on 9 March and closed on 23 March 2007.
Submissions were evaluated and the successful respondents were invited to proceed with the preparation
of a tender in accordance with the CIDB’s Standard Conditions of Tender on 7 May 2007. Tenders for the
Programme Manager and Design Consultants closed on 18 May 2007 and for the Contractors on 25 May
2007. From these tenders one Programme Manager, four Design Consultants and four Contractors were
selected.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
62
There are a total of six (6) possible quality strategies that could be used by public sector client bodies (Ta-ble 6 - Selecting suitable quality strategies). The municipality used the Evaluation Criteria strategy for the programme.
Table B3: Selecting Suitable Quality Strategies
Decision Criteria
Use if solution(s) to performance specifications offered by tenderers have an impact upon the life-cycle of the project, e.g. the solution offered impacts upon issues such as reliability, durability, running costs, after-sales service and technical assistance, etc.
Use where it is essential to ensure that only those tenderers who are capa-ble of providing a quality service are invited to submit tenders.
Use where the introduction of quality criteria in the eligibility criteria needs to be used to screen respondents in calls for expressions of interest or tenderers to ensure that submissions are only evaluated from those who are able to or are likely to satisfy the quality requirements for the contract.
Use where it is desirable and appropriate to have the opportunity to make inputs into quality management plans at tender stage and to finalise such plans before awarding the contract.
Use where it is desirable but not essential to meet stated quality criteria, e.g. be ISO 90000 Certified.
Use if criteria such as the following have profound or significant impact on the tenderer’s offer: • Technical merit; • Response to (ability to relate to) the proposed scope of work / project design; • Aesthetic and functional characteristics; • Safety and environmental characteristics; • Quality control practices and procedures which ensure compliance with stated employer’s requirements. • Organization, logistics and support resources relevant to the scope of work; • Qualifications and demonstrated experience of the key staff (assigned personnel) in relation to the scope of work; and • Demonstrated experience of tendering entity with respect to specific aspects of the project / comparable projects.
Description
Incorporates aspects of life cy-cle costing in the evaluation of tender offers (Link to Evaluation Methods 3 and 4).
Invite tender offers only from prequalified tenderers (link to Qualified procedure)
Evaluate only submissions and tenders received from respond-ents and tenderers, respective-ly, who satisfy eligibility criteria framed around quality.
Require tenderers to submit draft quality management plans with tender.
Award a preference for attain-ment of quality standards (Link to Evaluation Methods 2 and 4).
Incorporate objective and quan-tifiable aspects of quality in the evaluation of the financial offer (Link to Evaluation Methods 3 and 4).
Mechanism
Life-cycle Costing
Prequalifica-tion
Eligibility Criteria
Undertakings at Tender Stage
Preference
Evaluation Criteria
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
63
Table B4: Summary of Basic Competitive Selection Procedures
NegotiationProcedure
CompetitiveSelection
CompetitiveNegotiation
1
2
3
Procedure Description
A tender offer is solicited from a single tenderer.
The contract is usually awarded to the contrac-tor who submits the lowest finan-cial offer or ob-tains the highest number of tender evaluation points.
The number of tenderers com-peting for the contract is re-duced through a series of nego-tiations until the remaining ten-derers are invited to submit final offers.
Pre-requisites
In addition to satisfying the deci-sion criteria, the reason for fol-lowing this procedure is in ac-cordance with the Employer’s procurement policy.
None
The procedure is permitted in terms of the Employer’s procure-ment policy and the capability exists or can be put in place to execute the procedure.
Decision Criteria
The procurement satisfies one or more of the fol-lowing criteria: • Only one contractor is identified as possess- ing the necessary experience and qualifi- cations or product to provide the required service or goods • The required services or construction works cannot technically or economically be separat- ed from another contract previously per- formed by a specific contractor. • The service or construction works being pro- cured are largely identical to works previously executed by that contractor and it is not in the public interest to solicit other tenders; or • The services being procured have a very low ceiling value and it is not cost effective to en- gage in a competitive selection process.
The criteria for the negotiation procedure or the competitive negotiation procedures do not apply.
The procurement satisfies one or more of the fol-lowing criteria: • It is not feasible to formulate detailed specifi cations for the work or to identify the charac- teristics of construction works to obtain the most satisfactory solution to procurement needs. • There are various possible means of satisfy- ing procurement needs; • The technical character of the construction works or nature of the services warrants the use of competitive negotiations to realize the most satisfactory solution to procurement needs. • There is potential for obtaining better value for money through negotiations than through a competitive selection procedure.
These selections were ratified by the Bid Evaluation and Adjudication Committees and these were awarded during the last week of June 2007. Work commenced on 1 July 2007, i.e. the start of the new financial year.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
64
Table B5: Summary of Generic Procurement Strategies
Nominated Procedure
Open Procedure
Qualified Procedure
Quotation Procedure
Proposal Procedure Using the Two-Envelope System
Proposal Procedure Using the Two-Stage System
Shopping Procedure
PP1
PP3
PP2A
PP2B
PP2C
PP2D
PP2E
PP2F
PP2G
PP3A
PP3B
Procedure Decision Criteria
A tender offer is solicited from a single tenderer.
Any procurement procedure in which the contract is normally awarded to the contractor who submits the lowest financial offer or obtains the highest number of tender evaluation points.
Tenderers that satisfy prescribed criteria are admitted to an electronic data base. Tenderers are invited to submit tender offers based on search criteria and their position on the data base. Tenderers are repositioned on the data base upon ap-pointment or upon the submission of a tender offer.
Tenderers may submit tender offers in response to an advertisement by the or-ganization to do so.
A call for expressions of interest is advertised and thereafter only those tenderers who have expressed interest, satisfy objective criteria and who are selected to submit tender offers, are invited to do so.
Tender offers are solicited from not less than three tenders in any manner the or-ganization chooses, subject to the procedures being fair, equitable, transparent, competitive and cost-effective.
Tenderers submit technical and financial proposals in two envelopes. The finan-cial proposal is only opened should the technical proposal be found to be ac-ceptable.
Non-financial proposal are called for. Tender offers are then invited from those tenderers that submit acceptable proposals based on revised procurement docu-ments. Alternatively, a contract is negotiated with the tenderer scoring the highest number of evaluation points.
Written or verbal offers are solicited in respect of readily available supplies ob-tained from three sources. The supplies are purchased from the source providing the lowest price once it is confirmed in writing.
A procurement procedure which reduces the number of tenderers competing for the contract through a series of negotiations until the remaining tenderers are invited to submit final offers.
A call for expressions of interest is advertised and thereafter only those tenderers who have expressed interest, satisfy objective criteria and who are selected to submit tender offers, are invited to do so. The employer evaluates the offers and determines who may enter into competitive negotiations.
Tenderers may submit tender offers in response to an advertisement by the or-ganization to do so. The employer evaluates the offers and determines who may enter into competitive negotiations.
Negotiation Procedure
Competitive Selection Procedure
Competitive NegotiationProcedure
RestrictedCompetitiveNegotiations
OpenCompetitiveNegotiations
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
65
3.6.3.3 TargetedProcurementStrategy
a) Accommodating the Social and Economic AgendaThere are a number of techniques and mechanisms associated with targeted procurement procedures, all
of which are designed to promote or attain the participation of targeted enterprises and targeted labour in
contracts (CIDB Practice Note No. 10, February 2008). These procedures (also see SANS 10396, Implement-
ing preferential construction procurement policies using targeted procurement procedures) relate to the:
• measurement and quantification of the participation of target groups;
• definition and identification of target groups;
• unbundling of contracts;
• granting of preferences;
• provision of incentives for the attainment of key performance indicators in the performance of
contracts;
• creation of contractual obligations to engage target groups in the performance of the contract;
• provision of third party management contract;
• requirements for minimum prescribed levels of equity in the tendering entity;
• acceleration of targeted enterprises in rotating electronic databases; and
• evaluation of procurement outcomes.
Contract participation goals measure the participation of targeted enterprises and targeted labour, i.e. the
flows of money from the contract to the target groups. They provide a key performance indicator.
SANS 1914, Targeted Construction Procurement, provides a series of performance based specifications to
facilitate the establishment of a contract participation goal for a particular contract in respect of the partici-
pation of targeted enterprises, targeted partners in joint ventures, local resources and targeted labour, as
relevant. These specifications, upon award of the contract, form the basis for monitoring and verifying that
the contractor achieves the contract participation goals in the performance of the contract.
Contract participation goals (CPGs) may be used, in addition to measuring and reporting on a key perform-
ance indicator which reflects the quantum of business or employment generated in respect of targeted
enterprises or targeted labour through the performance of the contract, to:
• Reserve a portion of the contract work for specified target groups through the setting of minimum
contrast participation goals;
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
66
• Establish the basis for the awarding of preferences in proportion to the quantum of the CPG that is
tendered; or
• Establish performance targets for the payment of financial incentives relating to the attainment of
key performance indicators.
c) SMME Development and Job creation achievements of the projectApproximately 3,800 temporary workers (unemployed persons) were employed on the programme at any
one time to excavate trenches and were rotated every 4 months to allow others to financially benefit from
the construction activities. The total number of jobs created was approximately 46,000. The total amount of
money paid to workers was approximately 21% of the total project expenditure.
d) Allocation of Work between ContractorsThe Reservoir Zones were assigned to specific consultants and contractors. The target price was negoti-
ated with the contractor after the design of the water network was completed. The Reservoir Zones were
handed over to contractors who became responsible for the maintenance of the existing pipe work in the
district, including the repair of burst pipes, until such time that the new pipelines were installed, the old
pipes were decommissioned and the zones were handed back to eThekwini Water and Sanitation Division.
The target was for 80 km of water mains to be replaced each month.
e) Role of Subcontractors in the ModelA total of 16 subcontractors were also offered work opportunities. These contractors who had annual turno-
vers ranging from well below R750, 000.00 to R5, 500 000.00, started off by undertaking 10% of the con-
struction work and were being developed to undertake 20% of the construction work.
3.6.3.4 TenderEvaluationprocedure
There are four generic tender evaluation methods, namely:
• Method 1: Financial offer
• Method 2: Financial offer and preferences
• Method 3: Financial offer and quality
• Method 4: Financial offer, quality and preferences
In terms of the evaluation of the tender offers from the professional service providers and the construction
service providers, it appears that Method 2 was used in the evaluation of the Expression of Interest.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
67
3.7 Enterprise Development Opportunities
3.7.1 TargetingStrategyofParticipantsAn Expression of Interest was advertised by the municipality, calling all potential civil engineering contrac-
tors within the jurisdiction of the Metropolitan municipality to submit their corporate credentials and other re-
quirements. A total of 76 contractors responded to the Expression of Interest, of which 30 were shortlisted.
Of the 30 that were shortlisted, only 16 were successful with regard to accessing procurement opportunities
within the programme and they continued for the full duration of the implementation of the programme.
3.7.2SubcontractingwithintheeThekwiniDeliveryModelSubcontracting is a well established practice within the construction industry. It is an effective means of involving small, medium and micro enterprises in the construction works contracts. The reasons for sub-contracting vary between the different types of construction works contracts. In some contracts there may be a need to acquire specialist capabilities to perform certain aspects of the work.
In others, there may be a need to subcontract portions of the work to increase the contracting capacity of the contractor or to satisfy client requirements or expectations relating to the engagement of small and mi-cro enterprises or local enterprises in a contract (as part of its targeted procurement strategy / obligations). Subcontracting may also be used as a means of addressing racial and gender imbalances in the ownership of contracting companies (as part of the construction industry transformation agenda of public sector client bodies). There are three different types of subcontractors, name:
• Domestic subcontractor: subcontractor appointed by the main contractor at his discretion;
• Nominated subcontractor: a subcontractor nominated by the employer which the contractor is obliged to appoint as a subcontractor; and
• Selected subcontractor: a subcontractor selected by the contractor in consultation with the employer in terms of the requirements of the contract.
For the purpose of eThekwini Model, there were selected subcontractors. These were identified by the Municipality but appointed by the Main Contractors, through a competitive, open and transparent process.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
68
Table B6: Recommended combinations of Forms of Contract and Forms of Subcontract
Source: CIDB Practice Note No.7, May 2007: Subcontracting Arrangements
Series of Contract
FIDIC
GCC 2004
JBCC Series 2000
NEC3
Recommended Forms of Subcontract
BIFSA Standard Subcontract Agreement 1995 Edition (Amended 2000), for use with Principal Building Agreements other than the JBCC Principal Building Agreement
BIFSA Labour-only subcontract
SAFCEC General conditions of subcontract (2003 edition)
BIFSA Non-Nominated Subcontract for use with the JBCC Series 2000 Principal Build-ing Agreement
JJBCC 2000 Nominated / Selected Subcontract Agreement
NEC3 Engineering and Construction Subcontract
NEC3 Engineering and Construction Short Subcontract
3.7.3 EntrylevelofsubcontractorsIn terms of the development of small and emerging contractors, the municipality had appointed a total of
four (4) main contractors and sixteen (16) subcontractors who were appointed to be part of the programme.
With the exception of the main contractors, who had cidb grading designations of 7CE and above, the ma-
jority of subcontractors had cidb grading designations of 2CE PE or 3CE PE.
Working under the guidance of the main contractors and the mentors that were appointed by the main
contractors, the majority of subcontractors were able to improve their entry level grading designations by at
least two grading designations when they exited the programme.
3.7.4 StandardformsofsubcontractThe subcontractors should be engaged in fair conditions of contract which are recorded in writing. The
NEC3 and the JBCC Series 2000 Agreements contain principal (prime or main) contracts and subcontracts,
whereas FIDIC and GCC 2004 only provide the principal contracts.
The South African Federation of Civil Engineering Contractors (SAFCEC), the Building Industries Federa-
tion of South Africa (BIFSA) and the CIDB have developed forms of subcontract which may be used with
any approved forms of contract (See Table B9 below).
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
69
3.7.5 CIDBRegistrationRequirementsIn terms of the Construction Industry Development Regulations, prime or main contractors who contract
with an organ of state / public sector client bodies must be registered with the CIDB. Subcontractors need
not be registered, but nominated subcontractors must, however, be registered as they are nominated by an
organ of state in terms of the public procurement system.
The Regulations exempt from registration labour only contractors, and those contractors who are provided
with the bulk of the materials required for engineering and construction works by the employer or an agent
of the employer from registration. Given the fact that the subcontractors were selected subcontractors, all
of them were required to have been registered with the CIDB for them to participate in the eThekwini water
and sanitation programme.
3.8 Training and Skills Development Issues of the Model
3.8.1 TrainingandCapacityBuildingOpportunitiesforthe SubcontractorsThe beauty with the eThekwini infrastructure model was that the four (4) main contractors were very experi-
enced and skilled contractors in their own rights. They were able to impart valuable skills to the sixteen (16)
subcontractors that were engaged by the municipality. The municipality had initially submitted an applica-
tion for funding from the Department of Labour, through the Construction Education and Training Authority
(CETA). The funding for training never came through because the CETA took too long to respond and later
it was placed under administration.
The lack of funding for training and support from the CETA forced the municipality to fund its own training,
hence the training that was offered was not accredited. The lesson is that the public sector client bodies
have to allocate their own funding if they are serious about enterprise development, because the state
entities (e.g. CETA) that have been mandated to address the training and skills development issues do not
seem to have their ducks in a row.
Another challenge is that if public sector client bodies initiate large EPWP initiatives with the hope that the
CETA or other appropriate institutions will come to the party, this might not necessarily be the case. This
also implies that before the plans for initiating such projects, client bodies must sign memoranda of under-
standing / agreements with the various potential partners to ensure that all the stakeholders are able to
come to the party.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
70
3.8.2 TechnicalTrainingforWorkersSelected workers were provided with training in pipe laying. All workers received HIV/Aids training. Work place experience was also provided by the design consultants to enable eThekwini staff members to gain suitable experience to facilitate their registration as built environment professionals. The only weakness with regard to training was that a lot of unaccredited training was rendered and unfortunately the beneficiar-ies will have nothing to show for it, with the exception of the certificates of attendance.
Trench excavation for the replacement of secondary water mains in pilot project was generally done by hand. It was also reported that a number of selected workers were trained in pipe laying. The training ren-dered was not accredited. All workers received training on HIV/AIDS. 3.8.3 WorkplaceExperience forBuiltEnvironmentStudentsandyoung professionalsWork place experience for municipal staff was provided by the design consultants to enable the young professionals to gain suitable experience to facilitate their registration as Built Environment Profession-als. A total of seventy-five (75) students were offered in-service training during the implementation of the programme. The in-service training enabled the students from the various Universities of Technology with KwaZulu-Natal to benefit in terms of completing their practical training obligations towards their Built Envi-ronment Qualifications. The students were divided between the four (4) Design Consultants, the four (4) Main Contractors and the Sixteen (16) Subcontractors.
3.9 Job Creation Potential of eThekwini Infrastructure Delivery Model
3.9.1 TargetssetforEmploymentOpportunitiesFrom the interviews with the management of the programme it became clear that there were no job creation targets set from the outset. The intention was that at least 10% of the programme budget was supposed to go to local labour, given the capital intensive nature of the programme.
3.9.2 ActualJobCreationActualOn the basis of the secondary data from the municipality, it was clear that the 10% target for funds that had to go to local labour was doubled to 21%. This was attributed to the successful incorporation of the EPWP guidelines in the procurement documents of the projects, whereby more construction activities were identi-fied to be implemented using hands, as opposed to using machines (EPWP guidelines, 2006).
3.9.3 QualityofWorkOpportunitiesCreatedThere was a total of over 300 work packages, with a budget of almost R2 billion. These work packages were grouped in accordance with the geographic areas and the reservoir networks of the municipality. For example, one reservoir could be servicing three or four wards, and the work packages would be spread in the three or four wards, not in an equal number, but in various proportions. There was a proportional al-location of labour based on the scope of work.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
71
The local labour was sourced with the participation of the ward committees and the Community Liaison Officers and also with the participation of the Ward Councillors. The wards where the work packages were implemented had to identify and engage their own local labour for the duration of the implementation of the work package. This implied that the quality of the work opportunities ranged on average between four and six months. The further implication was that the quality of any training that could have been offered to the local labour was compromised and could not be sustained. It was reported that the total number of work opportunities created for all the work packages amounted to 46 000, during the full duration of implementa-tion of the programme (i.e. over a period of three years).
3.9.4 ConditionsofEmploymentoftheLocalLabourThe local workers were appointed by the contractors and subcontractors in accordance with the standard industry conditions of employment. The feedback from the interview with the eThekwini senior executive involved in the programme revealed that the conditions of employment of local labour was not in accord-ance with the CodeofGoodPracticeforSpecialPublicWorksProgrammes,instead, these were based on the conventional conditions of employment.
3.10 Monitoring, Reporting and Evaluation of the modelThe Project Team had developed a monitoring and evaluation framework that was used as a basis for capturing the progress of the implementation of the programme. The subcontractors had to submit their reports to the main contractors, who would in turn consolidate their cluster report for submission to the Pro-gramme Manager. The Programme Manager would then consolidate all the Cluster Reports and submit to the Senior Executive of the Municipality.
Despite the fact that the templates and the reporting indicators were not necessarily those of the EPWP, an attempt was made to ensure that the EPWP data was collected and reported on, in accordance with the quarterly reporting requirements.
3.11 Funding Model of the ProgrammeThe municipality had a budget of over R2 billion, over a period of three years. The expenditure on this project up to 1 September 2008 was approximately R400 million, but to date almost R2 billion has been spent by the municipality.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
72
The review of the implementation of the model on the pilot project has demonstrated a number of lessons
that are to be used by decision makers and programme implementing agents in the planning and imple-
mentation of EPWP Large projects. The lessons emanating from the eThekwini Infrastructure Delivery
Model are summarized in the following section:
4.1 Early buy-in and commitment of key decision makersThe early buy-in and commitment of the key stakeholders was critical in ensuring that the programme was
implemented. The nature of support was reflected in the financial support that was given to the programme,
despite the other competing priorities of the municipality.
4.2 Change management processesThe adoption of the Programme Delivery Model implied that the Municipality had to ensure that the internal
business processes had to be streamlined to accommodate the new way of doing business. This implied
that the procurement processes had to be realigned with the model and also to ensure that the municipal
Supply Chain Personnel and the Built Environment Professionals within the Water and Sanitation business
unit had to be capacitated to implement the new infrastructure delivery model.
4.3 Mobilization workshopsWith the understanding of the complexity and the dynamism when it comes to community-based infrastruc-
ture developments, the municipality ensured that there was thorough stakeholder mobilization programme
involving the Political Office Bearers (Ward Councillors), Ward Committees, Material suppliers, amongst
others.
The aim of the mobilization programme was to ensure that there was minimal or no resistance on the part
of the key stakeholders when it came to the actual implementation of the programme. These consultative
sessions were also aimed at ensuring that there was commitment and buy-in from the various stakeholders
prior to the actual rollout of the programme. This was to ensure that all the stakeholders were on the same
platform when implementation kicked in, and this was one of the factors that contributed to the successful
rollout of the programme throughout the metropolitan municipality.
Observations and Lessons Emanating from the Review of the Case Study
4.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study 73
4.4 Value of social facilitation in infrastructure development programmesIn order to strengthen dialogue between the main contractor and the communities where the work was be-
ing carried out, a Community Liaison Officers (CLOs) were appointed by the Municipality (but paid for by
the main contractors). This proved to have been very successful because there were virtually no issues of
discontent that threatened the implementation of the programme because the CLOs were able to play their
part in terms of maintaining community dialogue not only with the community stakeholders, but with other
stakeholders as well.
The implication is that for successful implementation of Large EPWP Projects, the value of social facilita-
tion cannot be underestimated. This is also implies that the public sector client body has to ensure that the
Terms of Reference for social facilitation must be clearly developed to ease the implementation processes.
4.5 Procurement in the absence of detailed scope of workThe implementation of the eThekwini water and sanitation programme also revealed that it is possible to
procure a programme of works in the absence of a detailed scope of work within the current South African
public sector procurement regime.
4.6 Mobilization of the Project Team at short noticeThe success of the eThekwini infrastructure delivery model also highlights the fact that it is possible to
mobilize a project team to tackle a large infrastructure project within a relatively short period of time once a
decision is made to proceed with a project.
4.7 Long-term large contracts can be implemented by public bodiesThe eThekwini infrastructure delivery model also demonstrated that long-term, large contracts rather than
short-term small contracts permit service delivery to occur at scale.
74
4.8 Addressing socio-economic opportunities through large-scale infrastructure deliveryGiven the duration of implementation and the size of the budget of the eThekwini infrastructure delivery model, it became clear that large, long term contracts can effectively and efficiently deliver on a wide range of social and economic objectives (CIDB Practice Note No. 11, February 2008).
The approach addressing the social and economic agenda was very flexible, and unlike most other deliv-ery models, it allowed the client to change the deliverables over time in response to emerging needs and changing circumstances. This was of particular value where the contracts extend over a few years.
The learning curve on the project relating to the maintenance of the existing water network and the sup-plying of households with water while decommission the old pipes and commissioning the new ones was a steep one.
4.9 Advancement of the contractor development agenda / targeted procurementThe target contract approach whereby the target price is negotiated once the scope of work in a Reservoir Zone is known has provided the client with complete flexibility in deciding on priorities and has enabled a well structured and focussed contractor development programme to be implemented with clear and meas-ureable outcomes. The scale of the project has allowed a focussed mentorship programme to be imple-mented to ensure that the targeted construction businesses put in place business systems to ensure that they grow in a sustainable manner.
This delivery model using large well established contractors has been able to deliver jobs to the unem-ployed efficiently and effectively. The money paid to such workers which amount to 21 % of total project cost in the early stages of the project where the start up costs are high, compares very favourably with the achievements of Soweto’s Contractor Development Programme which ran from 1988 to 1998 (Watermeyer, R.B., Nevin, G., Amod, S. and Hallett, R.A., 1995).
The Soweto Contractor Development Programme, which replaced secondary water mains, involved small labour only contractors and third party management support in the form of construction and materials man-agement. This programme enabled 28 percent of the construction cost, excluding programme manage-ment and design and supervision costs, to be paid to small contractors.
4.10 Addressing capacity constraints of public sector client bodiesIt is a known fact that the public sector has lost its staff to the consulting sector. What is also apparent is that there are a large number of engineers and technologists in the industry and business sector which has proportionally remained approximately the same during this period.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
75Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
The current project approach that is employed in most government departments and municipalities works well where a knowledgeable client exists. With the loss of technical staff, many public sector clients have insufficient in-house capacity to get these projects up and running or to effectively oversee their imple-mentation. The shortage of qualified engineers in a number of public sector client bodies is a known fact (Lawless, 2005). What is interesting to note is that there are more engineers and technologists working for contractors than government or local authorities.
Given the fact that there was only one senior municipal executives dedicated to the implementation of the water and sanitation programme dramatically reduced the staffing requirements of the client and this can offer a solution to overcoming capacity constraints in the public sector. The clear and well defined project stages have allowed the project team to document the delivery process and to allow the client to control the project using only one staff member.
For the purpose of this programme, eThekwini had only assigned one of its senior project managers to in-terface with the project team through the appointed programme manager. From the review of the eThekwini Case Study, it has become clearer that there are two distinctly different strategies to address the current lack of service delivery and poor project outcomes:
• Significantly improve and dramatically increase the skills base of built environment professionals within government to effectively and efficiently manage and oversee the current delivery processes; and • Harness the capability and capacity of the private sector to delivery infrastructure using a radically different delivery process.
4.11 Ability to harness the capability and capacity of the private sectorThe model which eThekwini has implemented harnesses the capability and capacity of the private sector to deliver and provides an alternative delivery process which enables allocated budgets to be spent in a manner that results not only in construction works of an acceptable quality being delivered in response to prioritized needs, but also contributes to the regional social and economic agenda including employment and skills development.
4.12 Political CommitmentThe fact that the municipality had set aside a budget of R2 billion to be spent in a programme over a period of three financial years (within the MTEF) is a sign that there was a clear political commitment, reinforced by the funding commitment. This also made it possible for the municipality to conceptualise and plan a structured enterprise development programme.
76
References5.
Constitution of the Republic of South Africa (Act No. 108 of 1996), Parliament of the Republic of South Africa, Govern-ment Printers, 1996.
Construction Industry Development Board Act (No. 38 of 2000), Government Printers, Republic of South Africa, 2000.
Construction Industry Development Board Practice Note No. 10: Attaining social and economic deliverables, February 2008.
Construction Industry Development Board Practice Note No. 11: Programme Management Approach to delivery, Febru-ary 2008.
Construction Industry Development Board Practice Note No. 23: Construction Procurement Strategy, September 2010.
Construction Industry Development Board Practice Note No. 24: Managing construction procurement processes, Sep-tember 2010.
Construction Industry Development Board Inform Practice Notes No’s: 22, 22a and 22b – CIDB Infrastructure Gateway System,September 2010.
Construction Industry Development Board Practice Note No. 7: Subcontracting Arrangements, May 2007.
Construction Industry Development Board: Standard for Uniformity in Construction Procurement, Board Notice No. 94 of 2006, Government Gazette No. 29138 of 18 August 2006.
Construction Industry Development Board Inform Practice Note No. 1, Scaling up delivery and accelerating empower-ment, August 2008.
Construction Industry Development Board Management Guidelines: Practice Guide 2- Construction Procurement Strat-egy, April 2011,
Expanded Public Works Programme (EPWP) Phase 2 Business Plan: 2009-2014, National Department of Public Works, Republic of South Africa, 2009.
EPWP Guidelines for the implementation of labour-intensive construction infrastructure projects, EPWP Unit, Na-tional Department of Public Works, 2006.
Local Government Municipal Systems Act (No. 32 of 2000), Department of Cooperative Governance and Traditional Af-fairs, Government Printers, 2000.
Municipal Finance Management Act (No. 56 of 2003), National Treasury, Government Printers, Republic of South Africa, 2003.
National Treasury and CIDB (2006 & 2010): Infrastructure Delivery Improvement Programme (IDIP) Toolkit.
Preferential Procurement Policy Framework Act (No. 5 of 2000), National Treasury, Government Printers, Republic of South Africa, 2000.
Public Finance Management Act (No. 1 of 1999, as amended), National Treasury, Government Printers, Republic of South Africa, 1999.
Watermeyer, R. B. and Thumbiran, I. (May 2009): Delivering infrastructure at scale in developing countries: Numbers or Systems? – The Fourth Built Environment Conference hosted by SOCSA, Livingstone, Zambia.
Watermeyer, R. B., Larkin, D. and Van Huysteen, S. (2007): A model for the delivery of large scale employment-intensive works using a programme management approach. Prioritising Employment creation in Government Policies, Programmes and Investments, 12th ILO Regional Seminar for Labour Based Practitioners, Durban, South Africa, 8-12 October 2007.
Watermeyer, R. B. Larkin, D., Kee, A. and Thumbiran, I. (2008): Delivering Infrastructure at scale: eThekwini Water and Sanitation experience in a Pilot project.
Watermeyer, R. B. et al (March 2001): Delivering infrastructure at scale: eThekwini Water and Sanitation experience in a pilot project, Civil Engineering Journal.
Watermeyer, R. B. (September 2006): Accelerating the EPWP – the engagement of large contractors in public sector projects.
Annexure B: Review of eThekwini Metropolitan Municipality Infrastructure Delivery Model - An Example of an EPWP Large Project Case Study
Annexure CMunicipality Reporting Forms
78 Annexure C: Municipality Reporting Forms
index
Page
1. Registration Form 79
2. Submission Form 80
3. Progress Report 81
4. Beneficiary Information Form 82
79Annexure C: Municipality Reporting Forms
Field request Description if needed Please complete this sectionProject Name
Public Body (Province) Reference number Thenumberusedbythepublicbodytoidentifytheproject. ThisnumberhastobeuniqueforeveryprojectProject Name TheprojectnameneedstobeuniqueforprojectsProject Type Select one and mark with a X Municipal
Project LocationProvince IndicateinwhichProvincetheprojectwillbeimplemented District Municipality / Metro Indicateinwhichdistrict/MetroMunicipalitytheprojectwillbe implementedLocal Municipality / Metro region IndicateinwhichlocalmunicipalitytheprojectwillbeimplementedPrimary Ward Indicateinwhichwardtheprojectwillbeimplemented.Iftheproject isimplementedinmorethanoneward,thennamethewardsin “describeprojectlocation”Enter the name of the Municipal Area IndicateinwhichmunicipalareatheprojectwillbeimplementedDescribe the project location Shortdescription,includingtheareaorwardwithinthemunicipality
Project Ownership and LocationProject Ownership Public Body Type Select one and mark with a XProject owner (Who is funding the project)Department in the public body type (Implementer) ThisreferstothedepartmentwithinthemunicipalityImplementing public body type (Implementer) Thismustbeadistrict,localormetromunicipalityProject Implementer Thisreferstothedepartmentwithinthemunicipalitywhois responsiblefortheimplementationoftheprojectProject ImplementationSource of Reference number IndicatethesourceofreferencenumberIDP Reference Number allocated to the projectMIG Registered? Indicateyes/no
EPWP InformationChooses EPWP Programme Select one and mark with a X - Not part of a programme- Contractor Development Facilities & Infrastructure Housing Delivery Labour Based Construction Programme Labour Intensive Programme EPWP Provincial MIG NYS Provincial National Youth Service Subsidised Housing Vuk’uphile Vukuzakhe Zimbambele Community based NGOProject Priority Select one and mark with a X 1.Labourintensiveandtraining 2.Vuk’uphilelearnership 3.Labourintensive,notraining 4.Other 5.LargeProjectsSector InfrastructureProject Sub-Sector Pleasechoosefromthefollowing: Select one and mark with a X InfrastructureRoads If sub-sector is other, then Groundrehabilitation mark with an X and provide RoadsandStormwater name of “other” SettlementsandServices Housing ParkDevelopment WaterInfrastructureUpgrade Sewerupgrade Pipelines Stormwaterdrains Sidewalks Multipurpose Other LightsReticulation Pavingofparks ParkingLotsIf Other, describe
PROJECT ALLOCATEDEstimated project start date Providestartdateoftheproject.ThisistheconstructionstartdateEstimated project end date ProvideestimatedprojectanddatePlease give a short project description Shortdescription,nolongerthanoneline.Project type: InfrastructureProject Environment Select one and mark with a X Urban Rural BothUrbanandNon-Urban
BUDGET ALLOCATEDSource of funds Whichorganisationswillbecontributingtothefundingoftheproject. Pleasechoosethefollowing: DistrictMunicipality Donors EPWP IGP Loans LocalMunicipality MIG NationalDepartment ProvincialDepartmentTotal Amount of budget Providebudgetamount
PROJECT CONTRACT IN PUBLIC BODYName and ContractTitle: Provide informationSurname: Provide informationInitials: Provide informationE-mail address: Provide informationCellular: Provide informationTelephone (Office): Provide informationFax: Provide informationPhysical Address: Provide informationPostal Address: (if different from Physical) Provide information
THIS FORM REFERS TO THE PROJECT PLAN AS BEFORE THE START OF THE PROJECT, AND NOT TO THE ACTUAL INFORMATION.REGISTRATION FORM
80 Annexure C: Municipality Reporting Forms
Field request Description if needed CommentBUDGET
Source of funds Whichorganisationswillbecontributingtothefundingof Budget amounts theprojectandhowmuchwilleachorganisationcontribute? Pleasechoosefromthefollowing: District Municipality EPWP IGP Loans National Provincial Capital Budget Provincial Department Provincial Maintenance Budget Upscaling GrantWhat will be the annual budgets of the projects? Pernationalfinancialyear.Takeintoaccountall Annual budget amount financialyearsinwhichthisprojectwillbeactive. 09-Oct 09/10 10/11 11/12 12/13 13/14
MILESTONESMilestone Willthismilestonebemeasured(Yes/No) TargetDateProject approvedConsultant appointedDetailed Design specifications approvedTender report approved Construction startedImplementation complete
EPWP INDICATORSIndicator Indicate(Yes/No)Consultant contractContractor compliant with EPW requirementsExit StrategyBranding Compliant
Planned EPWP Infrastructure outputsOutput Tickifapplicable Measureinkm/sqm/noetc- Indicatevaluei.e.kmroadstobe constructed Km of roads constructed to standardKm of pipelines installed to standardKm of storm water drains constructed to standardKm of sidewalks constructed to standardNo of bridgesNo of erf connectionsNo of pipe / box culvertsNo of pump stationsNo of ReserviorsNo of retention damsNo of standpipesNo of transfer facilitiesNo of VIP’sSqm of bus ranksSqm of community hallsSqm of landfill siteSqm of taxi ranksSqm of treatment worksSqm of buildingsSqm of Grass cuttingKm of fencingSqm of Clinic Construction and RehabilitationNumber of classroom construction and rehabilitation
PLANNED TRAININGAccredited courses
Cost estimate ProvideinformationifavailableNumber of person training days ThetotalnumberofdaysforallpersonstoattendtrainingNumber of people to attend ThetotalnumberofpeoplethatwillattendtrainingNumber of women to attend ThisincludesadultwomenandyouthwomenNumber of youth to attend Allpersonsaged35andunder
Non-accreditedCost estimate ProvideinformationifavailableNumber of person training days ThetotalnumberofdaysforallpersonstoattendtrainingNumber of people to attend ThetotalnumberofpeoplethatwillattendtrainingNumber of women to attend ThisincludesadultwomenandyouthwomenNumber of youth to attend Allpersonsaged35andunder
PLANNED LABOUREmployment generation details Planned number of persons days of employment Planned persons to be employedAdult menAdult womenYouth menYouth womenDisabled
PLANNED LABOURMinimum daily wage Asperthecontractdocument RPlanned number of employees from Hasthispublicbodyspecifiedthatanumberofpersonsthe indigent list fromtheindigentlisthastobeemployed?Ifso,what numberofpersons?
THIS FORM REFERS TO THE PROJECT PLAN AS BEFORE THE START OF THE PROJECT, AND NOT TO THE ACTUAL INFORMATION.SUBMISSION FORM
DATA FOR A 12 MONTHS PERIOD (APRIL - MARCH)
81Annexure C: Municipality Reporting Forms
A
pril
May
Ju
ne
July
A
ugus
t Se
ptem
ber
Oct
ober
N
ovem
ber
Dec
embe
r Ja
nuar
y Fe
brua
ry
Mar
ch
Fina
ncia
l Rep
ort
Expe
nditu
re fo
r cur
rent
mon
th
EPW
P Ce
rtifie
d Co
ntra
ctor
s
Num
ber o
f con
tract
ors
Amou
nt S
pent
SMM
E C
ontr
acto
rs
Amou
nt S
pent
Mile
ston
es
Proj
ect A
ppro
ved
Con
sulta
nt a
ppoi
nted
Det
aile
d D
esig
n
spec
ifica
tions
app
rove
d
Tend
er re
port
appr
oved
Con
stru
ctio
n st
arte
d
Impl
emen
tatio
n co
mpl
ete
Act
ual O
utpu
ts
Type
of o
utpu
t
Qua
ntity
ach
ieve
d
Dat
e ac
hiev
ed
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
PROGRESS REPORT
82 Annexure C: Municipality Reporting Forms
BENEFICIARY INFORMATIONPLEASE PROVIDE BENEFICIARY INFORMATION ON THIS SHEET FOR EACH MONTH OF THE YEAR (APRIL - MARCH)
Fi
rst N
ame
Intia
ls
Last
Nam
e I.D
.Num
ber
DO
B
Gen
der
Has
Dis
abili
ty
Educ
atio
n Le
vel
Star
t Dat
e
dd/mm/yyyy
MorF
YorN
Seecodesat
dd/mm/yyyy
bottomoflist
No.
of
Labo
ur
days
for A
pril
Dai
ly
wag
era
te fo
rA
pril
Tota
l W
ages
pa
idA
pril
Tota
l N
o. o
f tr
aini
ng
days
Apr
il
AP
RIL
- M
AR
CH
ED
UC
ATIO
NA
L LE
VE
LS:
us
e th
e co
des
(1,2
,3) o
n th
e ab
ove
spre
adsh
eet
1 - U
nkno
wn
2 - N
o Sc
hool
ing
3 - G
rade
1-3
(Sub
A -S
td 1
)4
- Gra
de 4
(Std
2) A
BET
1
7 - G
rade
9 (S
td 7
) ABE
T 4
8 - G
rade
10
-11
(Std
8-9
)
5 - G
rade
5-6
(Std
3-4
) ABE
T 2
6 - G
rade
7-8
(Std
5-6
) ABE
T 3
9 -
Gra
de 1
2 (S
td 1
0)10
- Po
st M
atric
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTA
L (D
o no
t ent
er
data
in th
is li
ne)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
BENEFICIARY INFORMATIONPLEASE PROVIDE BENEFICIARY INFORMATION ON THIS SHEET FOR EACH MONTH OF THE YEAR (APRIL - MARCH)
Annexure DProvincial Reporting Forms
84 Annexure D: Provincial Reporting Forms
index
Page
1. Registration Form 85
2. Submission Form 86
3. Progress Report 87
4. Beneficiary Information Form 88
85Annexure D: Provincial Reporting Forms
Field request Description if needed Please complete this sectionProject Name
Public Body (Province) Reference number Thenumberusedbythepublicbodytoidentifytheproject. ThisnumberhastobeuniqueforeveryprojectProject Name TheprojectnameneedstobeuniqueforprojectsProject Type Select one and mark with a X Provincial National
Project LocationProvince IndicateinwhichProvincetheprojectwillbeimplemented District Municipality / Metro Indicateinwhichdistrict/MetroMunicipalitytheprojectwillbeimplementedLocal Municipality / Metro region IndicateinwhichlocalmunicipalitytheprojectwillbeimplementedPrimary Ward Indicateinwhichwardtheprojectwillbeimplemented.Iftheproject isimplementedinmorethanoneward,thennamethewardsin “describeprojectlocation”Enter the name of the Municipal Area IndicateinwhichmunicipalareatheprojectwillbeimplementedDescribe the project location Shortdescription,includingtheareaorwardwithinthemunicipality
Project Ownership and LocationProject Ownership Public Body Type ProvincialDepartment Select one and mark with a XProject owner (Who is funding the project) Thisreferstotheprovincialdepartmentwhoisprovidingthemoney (Itcannotbeametro,districtormunicipality)Department in the public body that is responsible for the project ThisreferstothedepartmentwithintheprovincialdepartmentImplementing public body type (Implementer) Thiscanbethesame/anotherprovincialdept,ametro,districtormunicipalityProject Implementer Thenameoftheprovincialdepartment,metrodistrictorprovinceImplementing department Thisreferstothedepartmentwithinthepublicbodywhoisresponsibleforthe implementationoftheprojectProject ImplementationSource of Reference number IndicatethesourceofreferencenumberIGP Registered? Indicateyes/noIf the project is IGP registered, what is the IGP reference number? ProvidetheIGPnumber
EPWP InformationChooses EPWP Programme Select one and mark with a X - Not part of a programme- Contractor Development Facilities & Infrastructure Development Programme Housing Delivery Labour Based Construction Programme Labour Intensive Programme EPWP Provincial MIG NYS Provincial National Youth Service Subsidised Housing Vuk’uphile Vukuzakhe Zimbambele Community based NGOProject Priority Select one and mark with a X 1.Labourintensiveandtraining 2.Vuk’uphilelearnership 3.Labourintensive,notraining 4.Other 5.LargeProjectsSector InfrastructureProject Sub-Sector Pleasechoosefromthefollowing: Select one and mark with a X InfrastructureRoads If sub-sector is other, then Groundrehabilitation mark with an X and provide RoadsandStormwater name of “other” SettlementsandServices Housing ParkDevelopment WaterInfrastructureUpgrade Sewerupgrade Pipelines Stormwaterdrains Sidewalks Multipurpose Other LightsReticulation Pavingofparks ParkingLotsIf Other, describe
PROJECT ALLOCATEDEstimated project start date Providestartdateoftheproject.ThisistheconstructionstartdateEstimated project end date ProvideestimatedprojectanddatePlease give a short project description Shortdescription,nolongerthanoneline.Project type: InfrastructureProject Environment Select one and mark with a X Urban Rural BothUrbanandNon-Urban
BUDGET ALLOCATEDSource of funds Whichorganisationswillbecontributingtothefundingoftheproject. Pleasechoosethefollowing: DistrictMunicipality Donors EPWP IGP Loans LocalMunicipality MIG NationalDepartment ProvincialDepartmentTotal Amount of budget Providebudgetamount
PROJECT CONTRACT IN PUBLIC BODYName and ContractTitle: Provide informationSurname: Provide informationInitials: Provide informationE-mail address: Provide informationCellular: Provide informationTelephone (Office): Provide informationFax: Provide informationPhysical Address: Provide informationPostal Address: (if different from Physical) Provide information
THIS FORM REFERS TO THE PROJECT PLAN AS BEFORE THE START OF THE PROJECT, AND NOT TO THE ACTUAL INFORMATION.REGISTRATION FORM
86 Annexure D: Provincial Reporting Forms
Field request Description if needed CommentBUDGET
Source of funds Whichorganisationswillbecontributingtothefundingof Budget amounts theprojectandhowmuchwilleachorganisationcontribute? Pleasechoosefromthefollowing: Donors EPWP IGP Loans National Provincial Capital Budget Provincial Department Provincial Maintenance Budget Upscaling GrantWhat will be the annual budgets of the projects? Pernationalfinancialyear.Takeintoaccountall Annual budget amount financialyearsinwhichthisprojectwillbeactive. 09/10 10/11 11/12 12/13 13/14
MILESTONESMilestone Willthismilestonebemeasured(Yes/No) TargetDateProject approvedConsultant appointedDetailed Design specifications approvedTender report approved Construction startedImplementation complete
EPWP INDICATORSIndicator Indicate(Yes/No)Consultant contract compliant with EPW guidelinesContractor compliant with EPW requirementsExit StrategyBranding Compliant
Planned EPWP Infrastructure outputsOutput Tickifapplicable Measureinkm/sqm/noetc- Indicatevaluei.e.kmroadstobe constructed Km of roads constructed to standardKm of pipelines installed to standardKm of storm water drains constructed to standardKm of sidewalks constructed to standardNo of bridgesNo of erf connectionsNo of pipe / box culvertsNo of pump stationsNo of ReservoirsNo of retention damsNo of standpipesNo of transfer facilitiesNo of VIP’sSqm of bus ranksSqm of community hallsSqm of landfill siteSqm of taxi ranksSqm of treatment worksSqm of buildingsSqm of Grass cuttingKm of fencingSqm of Clinic Construction and RehabilitationNumber of classroom construction and rehabilitation
PLANNED TRAININGAccredited courses
Cost estimate ProvideinformationifavailableNumber of person training days ThetotalnumberofdaysforallpersonstoattendtrainingNumber of people to attend ThetotalnumberofpeoplethatwillattendtrainingNumber of women to attend ThisincludesadultwomenandyouthwomenNumber of youth to attend Allpersonsaged35andunder
Non-accreditedCost estimate ProvideinformationifavailableNumber of person training days ThetotalnumberofdaysforallpersonstoattendtrainingNumber of people to attend ThetotalnumberofpeoplethatwillattendtrainingNumber of women to attend ThisincludesadultwomenandyouthwomenNumber of youth to attend Allpersonsaged35andunder
PLANNED LABOUREmployment generation details Planned number of persons days of employment Planned persons to be employedAdult menAdult womenYouth menYouth womenDisabled
PLANNED LABOURMinimum daily wage Asperthecontractdocument RPlanned number of employees from Hasthispublicbodyspecifiedthatanumberofpersonsthe indigent list fromtheindigentlisthastobeemployed?Ifso,what numberofpersons?
THIS FORM REFERS TO THE PROJECT PLAN AS BEFORE THE START OF THE PROJECT, AND NOT TO THE ACTUAL INFORMATION.SUBMISSION FORM
DATA FOR APRIL, MAY AND JUNE
87Annexure D: Provincial Reporting Forms
A
pril
May
Ju
ne
July
A
ugus
t Se
ptem
ber
Oct
ober
N
ovem
ber
Dec
embe
r Ja
nuar
y Fe
brua
ry
Mar
ch
Fina
ncia
l Rep
ort
Expe
nditu
re fo
r cur
rent
mon
th
EPW
P Ce
rtifie
d Co
ntra
ctor
s
Num
ber o
f con
tract
ors
Amou
nt S
pent
SMM
E C
ontr
acto
rs
Amou
nt S
pent
Mile
ston
es
Proj
ect A
ppro
ved
Con
sulta
nt a
ppoi
nted
Det
aile
d D
esig
n
spec
ifica
tions
app
rove
d
Tend
er re
port
appr
oved
Con
stru
ctio
n st
arte
d
Impl
emen
tatio
n co
mpl
ete
Act
ual O
utpu
ts
Type
of o
utpu
t
Qua
ntity
ach
ieve
d
Dat
e ac
hiev
ed
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
If mile
stone
has
been
achie
ved
prov
ide th
e ac
hieve
ment
date
other
wise
ind
icate
“NO”
for
each
mi
leston
e not
achie
ved.
PROGRESS REPORT
88 Annexure D: Provincial Reporting Forms
BENEFICIARY INFORMATIONPLEASE PROVIDE BENEFICIARY INFORMATION ON THIS SHEET FOR EACH MONTH OF THE YEAR (APRIL - MARCH)
Fi
rst N
ame
Intia
ls
Last
Nam
e I.D
.Num
ber
DO
B
Gen
der
Has
Dis
abili
ty
Educ
atio
n Le
vel
Star
t Dat
e
dd/mm/yyyy
MorF
YorN
Seecodesat
dd/mm/yyyy
bottomoflist
No.
of
Labo
ur
days
for A
pril
Dai
ly
wag
era
te fo
rA
pril
Tota
l W
ages
pa
idA
pril
Tota
l N
o. o
f tr
aini
ng
days
Apr
il
AP
RIL
- M
AR
CH
ED
UC
ATIO
NA
L LE
VE
LS:
us
e th
e co
des
(1,2
,3) o
n th
e ab
ove
spre
adsh
eet
1 - U
nkno
wn
2 - N
o Sc
hool
ing
3 - G
rade
1-3
(Sub
A -S
td 1
)4
- Gra
de 4
(Std
2) A
BET
1
7 - G
rade
9 (S
td 7
) ABE
T 4
8 - G
rade
10
-11
(Std
8-9
)
5 - G
rade
5-6
(Std
3-4
) ABE
T 2
6 - G
rade
7-8
(Std
5-6
) ABE
T 3
9 -
Gra
de 1
2 (S
td 1
0)10
- Po
st M
atric
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TOTA
L (D
o no
t ent
er
data
in th
is li
ne)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
BENEFICIARY INFORMATIONPLEASE PROVIDE BENEFICIARY INFORMATION ON THIS SHEET FOR EACH MONTH OF THE YEAR (APRIL - MARCH)