37
Dr. Anamaria Popescu,PE,PMP,PSP McLachlan Lister - Hill International Australia May 23, 2012 EOTs? Avoiding the Traps or Taking Advantage of Them

EOT Tricks and Traps

Embed Size (px)

DESCRIPTION

EOT Tricks and Traps

Citation preview

  • Dr. Anamaria Popescu,PE,PMP,PSP

    McLachlan Lister - Hill International Australia

    May 23, 2012

    EOTs? Avoiding the Traps or Taking

    Advantage of Them

  • Presentation Objectives

    EOT Triggers

    Contractual Completion Date(s)

    Primary Ingredients

    Schedule Integrity

    Documentation of Causation

    Responsibility Assignment

    Concurrency of Delays

    Schedule Analysis

    Presentation is Everything!

    Recap

  • EOT Triggers

    1. An Event Occurred or Will Occur that Causes Delay

    2. 3 Possible EOT Event Types:

    Owner driven events Os risk (Time & money)

    Neutral events risk shared (Time only)

    Concurrent events-risk allocated (Time only)

    3. Causes Delay to the Critical Path

    .But, Critical Path to What?

  • Dealt with in Contract 2 ways: By stating a date By stating a works period

    Types of Contractual Completion Dates: Practical Completion Date Substantial Completion Date Mechanical Completion Date Handover Date Separable Portion Date

    May apply to a Section, or the Entire Project Each Section is treated separately

    Multiple EOT Claims and LD Assessments May Apply

    Contractual Completion Date(s)

  • Primary Ingredients

  • No Open Ends Limited Constraints All Scope Captured Majority of Tie Types: FS No Large Lags: Float Hoarding No Redundant Logic Ties Critical Path Makes Sense Critical Path is Continuous Longest Path Filter Confirmation

    Schedule Integrity: What is It?

  • Obligation of Both the Owner and Contractor

    Contract Must State Schedule Requirements Diligence Must not Stop after Baseline is Accepted Schedule Updates Are Contractual Too! Key Tools to EOTs

    Schedule Integrity

  • Ask for the Electronic Version (Not a PDF) Run a Schedule Diagnostic on Baseline & Updates Primavera: Schedule Log and Claim Digger Others: Acumen Fuse, Schedule Analyser Pro Also look for..

    Added and/or Deleted Activities Increase or Decrease in OD Calendar Changes Schedule Calculation Changes Etc

    Schedule Integrity: How do you Know?

  • Schedule Integrity: Diagnostic Tools

    P6: Schedule Log

  • Schedule Integrity: Diagnostic Tools

    Claim Digger

  • Schedule Integrity: Diagnostic Tools

    Acumen Fuse

  • Documentation of Causation

    The need for evidence: He who Asserts Must Prove

    1st: Demonstrate Cause (Documentation)

    2nd: Demonstrate Effect (Schedule Analysis)

    The 3 Rs Records, Records, and Records

    Record Type Important but Record Content Key!

  • Letters and Emails RFIs Hold Registers Transmittal Logs Progress photographs Variation Notices Daily Field Reports Weekly Progress Reports Meeting Minutes Drawing Revision Logs

    Documentation of Causation: Record Types

  • Instructions given & received Conflicts in plans/specifications Weather conditions: Not Just Rain Work Stoppage: Time Stopped and Why Number of Workers/Trade Type Subcontractors Equipment Type Utilised and Number Daily Activity of Crews Specific Location: Station Number, Area Delays Encountered: Specific Activity Material Shortages

    Documentation of Causation: Record Content

    Create a Standardised Daily Report Form

  • Documentation of Causation:

    Delay Examples

    Weather

  • Documentation of Causation:

    Delay Examples

    Equipment & Material Problems

  • Documentation of Causation:

    Delay Examples

    Design Issues

    Environmental

    HSSE Issues

  • What Does the Contract Say? Owner Caused Delays Force Majeure Delays Neutral Delays-Weather Non-Excusable Delays

    Allocate Responsibility to Individual Delay Events

    Responsibility Assignment

    Code Delay

    Split Activities

    Code Resp.

    Allocate Actual

    Duration

  • Concurrent Delay: Otherwise Known As.

  • Concurrent Delay - Requirements

    Two or more delays during the same time

    There can only be one unit of delay during the same unit of time, regardless of the number of delaying

    events

    Delays unrelated and independent

    Must delay the critical path

    Responsibility of different parties

    Each party bears its own expenses for that delay

    Involuntary (i.e., not pacing)

    Substantial and not easily curable

  • Concurrency: Net Affect Matrix

    Have a Matrix As Part of Your Contract

  • Literal vs. Functional Concurrency

    Literal Concurrency

    Delays have to be literally concurrent in time, as in happening at the same time

    Functional Concurrency

    Delays need only occur in the same analysis period or window

  • Schedule Analysis: Choose Your Weapon

    3.TIA

    1.As-Planned vs. As-Built

    2.Windows

    Analysis

  • As-Planned vs. As-Built

    Comparison of start/finish dates between two schedule updates

    Purely mathematical-Variance between dates

  • As-Planned vs. As-Built

    Delayed Completion

    Early Start

    Early Completion

    Overall Delay

    Delayed Start

    As-Planned

    As-Built

    Delayed Completion

    Early Start

    Early Completion

    Overall Delay

    Delayed Start

    As-Planned

    As-Built

    1

    4

    2 3

    1 2

    3

  • As-Planned vs. As-Built

    When should it be used? Limited time and money

    No electronic schedules

    Inadequate schedule logic

    Quick and dirty 1st pass

    What does the Schedule Analysis Method Best Prove?

    Excusable non-compensable delay

  • As-Planned vs. As-Built

    Not Good For: Concurrent delays or acceleration

    Critical path changes between updates

    Multiple critical or near-critical paths per update

    Recovering extended overhead costs

    Arbitration or Litigation

    Pros: Easy to understand, explain, and graphically depict

    Technically simple to perform

    Data Required: Baseline schedule

    As-built schedule

  • Windows Analysis

    Quantify loss or gain of time along a float path

    Loss and gains tallied by window

    A window is the time period framed between two revisions:

    The as-planned schedule for the beginning of the window

    The as-built schedule for the end of the window

    As-

    Planned As-

    Built

  • Windows Analysis: Example

    ID Task Name DurJan 2006

    9 10 11 12 13 14 15 16 17 18 19 20 21 22

    1 2dExcavate

    2 1d

    3 3dForm / Rebar

    6 4d

    4

    5 3dConcrete

    7 1dStrip Forms

    4d

    8

    9 1dInspect

    23 24 25 26 27

    10

    1d

    1d

    Gain

    Null

    Delay

    Net

    1

    -1 -1 -1 -1 -1 -1

    2

    0

    -7

    1

    -1

    -51 1

    0

    -1 -1 -1 -1 -1 -1-1

    Gain = +

    Delay = --

    Planned

    As-Built

  • Windows Analysis

    When Should the Schedule Analysis Method be Used? Complex schedules with large critical paths Very high delay damages Concurrent delays Client has the time and budget Need graphical depiction of concurrency

    What does the Schedule Analysis Method Best Prove? Excusable non-compensable delay Excusable compensable delay Concurrent delay: Literal Concurrency Non-excusable delay

  • Impacted As-Planned (A.K.A TIA)

    Insertion of impact activities into a baseline or update schedule

    Integrated into the network logic before, in-between, or after the activity it affected

    Additive model that simulates the possible effect of actual delay events to the schedule completion date

    Comparison of IAP schedule and succeeding update to determine possible acceleration or non-excusable delays

    Comparison of IAP schedule and planned schedule to determine time extension

  • Impacted As-Planned:(Acceleration)

    IAP Schedule

    As-Built Schedule

    6/20

    6/25

    Acc

    5

  • Impacted As-Planned:(Time Extension Example)

    IAP Schedule

    6/20

    6/18

    (2 Days)

  • Impacted As-Planned

    When Should the Schedule Analysis Method be Used?

    Indemnification of liquidated damages

    For preliminary negotiations between owner and contractor

    While the Job is Ongoing

    What does the Schedule Analysis Method Best Prove?

    Requests for Time Extension or LD Waivers

    Acceleration Claims

  • Presentation

    1. Attach Source Documentation

    2. Graphical Representation

    Schedule Updates: Prior to Impact and After Impact

    Critical Path in Gantt Chart Format with Logic

    Concurrency

    3. Write Up

    Keep it Short and Sweet

    Explanation of Impact Event: Timing,Activities,Duration

    4. Cost Impact

    Stand-By Costs of Equipment and Crews Affected

    Dont Claim Costs on Crews That Were Working!

    5. Executive Summary at the Beginning

    6. Submit Once Impact Event Is Known

    7. Submit Again Once Full Impact Understood

  • Recap

    Documentation is Key: Content Must be Consistent

    Schedules Must Be Sound and Accurate

    Dont Ignore Updates

    Choose Your Technique Wisely

    Consider Concurrency

    Present Claim as a Concise Package

    Dont Throw the Kitchen Sink into the Claim

    Resolution Inversely Proportional to Submittal Time

  • Contact Information

    Brisbane Office

    2/19 Musgrave Street

    West End, QLD, 4101

    Email: [email protected]

    Phone: 61 07 3255 0223

    Sydney Office

    Level 1, 1 Hickson Road

    Phone: 61 02 9241 7328

    Perth Office

    189 Colin Place

    Phone: 61 08 9480 0647