17
EOR: The Economic Alternative for CCS Denbury Resources Inc. Gasification Technology Conference October 2007

EOR: The Economic Alternative for CCS · EOR Projects Require Total Delivered CO 2 Costs < $0.50/Mcf at Oil Prices of $30/Bbl to Ensure Its Ability to Continually Take and Sequester

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

EOR: The Economic Alternative for CCSDenbury Resources Inc. Gasification Technology Conference October 2007

2Denbury Resources Inc.

Outline

Company Information

The CO2 Pipeline Dilemma

Carbon Capture and Storage

Issues and Potential Solutions

3Denbury Resources Inc.

Company SnapshotDenbury is the largest oil and gas producer in the State of Mississippi

Primarily as a result of CO2 enhanced oil recovery and Denbury’s efforts, Mississippi’s oil production has reversed its decline and is actually increasing

Denbury currently operates seven (7) active CO2 enhanced oil recovery projects in Mississippi and is in the process of initiating three (3) new floods during 2007

Denbury currently injects approximately 400 MMcf (23,000+ tons) of CO2 per day into the seven active floods

Based on our injection volumes we believe we are the largest injector of CO2 on a daily basis in the U.S.

Denbury currently operates approximately 270 miles of CO2 pipelines and is in the process of constructing an additional 400+ miles of CO2 pipelines.

Since 1999, Denbury has produced in excess of 15 MMBbls of oil from CO2Flooding

4Denbury Resources Inc.

Tinsley

Citronelle

Jackson Dome

NEJD

CO

2 P

ipel

ine

Free State Pipeline

Sonat MS Pipeline

Martinville

DavisQuitman

Heidelberg

Summerland Soso

Sandersville

EucuttaYellow Creek

Cypress Creek

BrookhavenMallalieu

Little Creek

Olive

Smithdale

McComb

Cranfield

LakeSt. John

LockhartCrossing

PortBarre

LakeChicot

IberiaThornwell S Lake Arthur SW

Hastings

T E X A S

L O U I S I A N A

M I S S I S S I P P I

Oyster Bayou

Fig Ridge

Delta Pipeline

Green Pipeline

Delhi

CO2 Projects ‐ Total Potential Tertiary Oil Reserves (1)

(1) Probable tertiary oil reserves as of 12/31/06 based on 10% to 17% recovery factors. Hastings Field is under contract but not owned.(2) Projected CO2 production of petroleum coke to ammonia plant expected to be completed during 2010.

Phase 341 MMBbls

Phase 277 MMBbls

Phase 536 MMBbls

Phase 431 MMBbls

Phase 182 MMBbls

Phase 626 MMBblsPhase 7

Hastings Field50 - 90 MMBbls (1)

Faustina Project190 - 225 MMcf/d of CO2

(2)

Phase 8Seabreeze Complex

30 - 40 MMBbls (1)

5Denbury Resources Inc.

CO2 Business Model – Projected Net Oil Production

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

55,000

60,000

65,000

70,00020

02

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

NET

BOPD

Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 Phase 7 Phase 8

Note: Forecast based on internal management estimates. Actual results may vary.

(SW MS) (E MS) (Tinsley) (Cranfield/St. John) (Delhi) (Citronelle) (Hastings) (Seabreeze)

6Denbury Resources Inc.

CO2 Business Model

Note: Forecast based on internal management estimates. Actual results may vary.

0

100

200

300

400

500

600

700

800

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

Cap

ital (

MM

$ / Y

EAR

)

0

200

400

600

800

1000

1200

1400

1600

MM

CFP

D

Capital Jackson Dome Pipeline CO2 Req

7Denbury Resources Inc.

WATER INJECTOR WELLS

Phase I

Phase VPilot

Phase II

Phase I

Phase IV

Phase IIPhase III

Mallalieu, West Unit: 3,574 Acres Mallalieu, East

Phase I

Phase IIPhase IV

Phase III

Pilot

Phase V

Mallalieu Area

8Denbury Resources Inc.

Mallalieu AreaMallalieu Area Net Oil Production vs. Total CO2 Injection

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Jan-01 Jul-01 Jan-02 Jul-02 Jan-03 Jul-03 Jan-04 Jul-04 Jan-05 Jul-05 Jan-06 Jul-06 Jan-07

Net B

OP

D

0

100

200

300

MM

CFP

D C

O2

Net Daily Production vs. Total CO2 Injection

Temperature Issues

EMU BOPD (Net)

WMU BOPD (Net)CO2 INJECTION MMCPD

WMU current production 5200 BOPD

EMU current production 700 BOPD

Denbury Resources Inc.

US CO2 Pipelines vs Gasification Projects

Gasification Projects

Existing CO2 Pipelines

“The Dilemma”

10Denbury Resources Inc.

Scoping Economics of a 450 Mile CO2 Pipeline**

30” Pipeline● Free Flow Capacity – 650 MMcf/d● Capacity w/ 1 Pump Station – 880 MMcf/d● Annual Pump Station Expense (w/o repl. costs or power substation) - $7 MM

26” Pipeline● Free Flow Capacity – 450 MMcf/d● Capacity w/ 3 Pump Stations – 800 MMcf/d● Annual Pump Station Expense (w/o repl. costs or power substation) - $19 MM

24” Pipeline● Free Flow Capacity – 370 MMcf/d● Capacity w/ 5 Pump Stations – 800 MMcf/d● Annual Pump Station Expense (w/o repl. costs or power substation) - $31 MM

**All Cases Used Pipeline Construction Costs for CO2 Pipelines in Mississippi

11Denbury Resources Inc.

Compression Capital Costs

Stated Conditions● 15 psig Suction to 2100 psig Discharge● 3 - 5800 T/d Compressors● Purchase Cost - $30 MM● Installation Cost - $30 MM (based on general construction and installation costs)● Total Cost - $60 MM● Total Power Requirement – 82.8 MW

Higher Suction Pressure● 50 psig Suction to 2100 psig Discharge● Purchase Costs - $22.5 MM ● Total Costs - $45 MM● Total Power Requirement – 45 MW

CO2 Capture Pressure is a Major Factor on Costs for CCS

12Denbury Resources Inc.

Total Amortized Cost ($/Mcf)

Amortization Schedule ● 20 and 30 Years

● Solved for Lowest Cost per Mcf Delivered to the EOR Project

● Attempting to Achieve a Utility Type ROR - 30 Year Schedule

● 800 MMcf/d from Day 1

● Two Year Construction Timetable

● Total Capital - $750 M – (24” Pipeline)

Components of Costs – Stated Conditions (15 psig)● Capital Recovery - $0.475/Mcf

● Operating Costs of Pipeline and Booster Stations - $0.146/Mcf

● Total Costs - $0.621/Mcf

● Excludes Costs of Power to Compress CO2

● Excludes Cost for CO2

13Denbury Resources Inc.

Carbon Capture and Storage

Basic Assumption: Everyone will be Required to Deal with CO2 Emissions

The Costs of Capture is the same whether the Emitter Chooses to Ultimately Inject into a Pipeline or Inject into Saline Reservoirs.

CO2 Pipelines Operate at Pressures > 2000 psi

Injection Pressures for Saline Reservoir Injection will most likely be > 2000 psi

14Denbury Resources Inc.

Carbon Capture and Storage – Geologic Example

Single Gasification Project Emitting 200 MMcf/d of CO2

30 Year Life

Total CO2 Emissions – 2.2 Tcf of CO2

Denbury’s DRI Ice Field

16,000’ Underground

Reservoir Pressure - +/- 11,000 psi

Areal Extent - 5,500 acres to spill point (Approx: 9 sq. miles)

Average Thickness - 300’

Storage Capacity - Approx. – 3 Tcf

Thus, the areal extent of a single plant’s CO2 emissions will cover a very large area, much greater than the most likely plant site area.

if thickness = 125’, Area would be the size of Manhattan (22+ sq. miles)

if thickness = 60’, Area would be the size of San Francisco (47+ sq miles)

15Denbury Resources Inc.

Carbon Capture and Storage

Enhanced Oil Recovery Operations Can Provide the “Costs” of Transportation, Sequestration and Liability

Saline Reservoir Injection - All “Costs” for Transportation, Sequestration and Liability will Remain with the Emitter

Therefore;

Enhanced Oil Recovery is the Lowest Cost Option for Sequestering CO2

Emissions Today and for the Foreseeable Future

Provides an Economic Solution for CCS and Provides Additional Quantities of Domestic Oil Production

The Only CCS Method that Produces an Economic Benefit and Social Benefits

The Only CCS Method that can be Utilized Now

16Denbury Resources Inc.

Issues

EOR Projects Require Total Delivered CO2 Costs < $0.50/Mcf at Oil Prices of $30/Bbl to Ensure Its Ability to Continually Take and Sequester the CO2. Higher Oil Prices will allow CO2 to be Transported Longer Distances

CO2 Located Closer to Existing CO2 Pipeline Infrastructure will have a Considerable Cost Advantage

No Different than Natural Gas Production

The Closer Natural Gas is to the User the Higher the Price it Receives (Gulf Coast vs Rockies)

17Denbury Resources Inc.

Solutions

Potential Solutions

● Greenhouse Gas Emissions Credits – “Carbon Value”● Estimated 2010 Values - 100% VER @ $3/ton = $0.17/Mcf @$5/ton = $0.285/Mcf

● State or Federal Subsidies to Offset Costs (Capital and Operating)

● Is there the Possibility that CO2 Capture is Valued by the Community Whereby the Sale Price of the Gasification Product Can Be Increased to Cover a Portion of the Costs of CCS?