ENVIRONMENTAL QUALITY ACT 1974(SECTION 34A)

ENVIRONMENTAL QUALITY(PRESCRIBED ACTIVITIES)(ENVIRONMENTAL IMPACTASSESSMENT) ORDER 2015

GAZZETTEMENT :28 AUG 2015

DEPARTMENT OF ENVIRONMENT MALAYSIA

TABLE OF CONTENTS

HISTORY

EIA ORDER 2015

CONCLUSION

2

HISTORY

3

4

LEGAL REQUIREMENTENVIRONMENTAL

QUALITY ACT (EQA) 1974 (AMENDMENT)

2012

Section 34ASection 34AA

Environmental Quality (Prescribed

Activities) (Environmental

Impact Assessment) Order 1987

5

(1) Unit Perancang Ekonomi, Jabatan Perdana Menteri(2) Bahagian Konservasi Alam Sekitar, NRE(3) PUU, NRE(4) PUU, JAS(5) Jabatan Pengairan dan Saliran (JPS)(6) Jabatan Perhutanan Semenanjung Malaysia (JPSM)(7) Jabatan Ketua Pengarah Tanah dan Galian (JKPTG)(8) Jabatan Mineral dan Geosains (JMG)(9) Jabatan Taman Laut (JTL)(10) Kementerian Pertanian Industri Asas Tani (MOA)(11) Jabatan Pertanian (DOA)(12) Jabatan Perikanan (DOF)(13) Jabatan Veterinar (DOV)(14) Kementerian Kerja Raya (KKR)(15) Jabatan Kerja Raya (JKR)(16) Kementerian Pengangkutan (MOT)- Bahagian Darat(17) Kementerian Pengangkutan (MOT)- Bahagian Udara

INPUT AND COMMENTS FROM GOVERNMENT AGENCIES (FEBRUARY 2009):-

6

• sambungan...

(18) Kementerian Pengangkutan (MOT)- Bahagian Maritim(19) Jabatan Penerbangan Awam (DCA)(20) Jabatan Laut Semenanjung Malaysia(21) Jabatan Keretapi(22) Kementerian Perumahan dan Kerajaan Tempatan (KPKT)(23) Jabatan Kerajaan Tempatan(24) Jabatan Pengurusan Sisa Pepejal Negara(25) Jabatan Perancang Bandar dan Desa (JPBD)(26) Kementerian Tenaga, Air dan Komunikasi (KTAK)(27) Kementerian Pelancongan (28) Kementerian Perdagangan Antarabangsa dan Industri

(MITI)(29) Malaysian Industrial Development Authority (MIDA)(30) Kementerian Kesihatan (MOH)(31) Jabatan Kesihatan (32) Jabatan Perlindungan Alam Sekitar Sabah (JPAS)(33) Lembaga Sumber Asli dan Alam Sekitar Sarawak

(NREB)

7

(1) Federation of Malaysia Manufacturers (FMM)(2) Malaysian International Chamber of Commerce of

Industry (MICCI)(3) Chemical Industries Council of Malaysia (CICM)(4) Malaysian Pulp & Paper Mill Association(5) Malaysian Petrochemicals Association(6) Federation of Livestock Farmer Association Malaysia (FLFAM)(7) Construction Industry Development Board Malaysia

(CIDB)(8) Malaysia Quarry Association (MQA)(9) Malaysian Chamber of Mines (MCM) (10) Real Estate and Housing Developers’ Association

Malaysia (REHDA)

INPUT AND COMMENTS FROM PRIVATE STAKEHOLDERS:-

8

1. Malaysian Environmental NGOs (MENGO)

2.ENSEARCH

3. World Wide Fund for Nature (WWF)

4. Malaysian Nature Society (MNS)

5. FOMCA

INPUT AND COMMENTS FROM (NGO):

10

PRINSIP ASAS DALAM PINDAAN

1. Elakkan “ambiguity”

2. Fokus kepada aktiviti yang mempunyai impak ketara terhadap alam sekitar dan yang terletak di kawasan sensitif alam sekitar

3. Aktiviti yang bukan di kawasan sensitif alam sekitar boleh dikawal melalui pelan kerja tanah dan Erosion and Sedimentation Control Plan (ESCP) yang lengkap yang akan diluluskan oleh Pihak Berkuasa Tempatan dan JPS

4. Hanya terminologi EIA digunakan. Tiada terminologi PEIA, DEIA, Comprehensive EIA etc . Jadual 1 (Tak perlu pameran awam) dan Jadual 2 (Kelulusan TOR dan Pameran Awam diperlukan)

11

BASIC PRINCIPLE IN EIA ORDER

2015

1. NO “AMBIGUITY”

2. FOCUS ON ADVERSE SIGNIFICANT IMPACT ACTIVITIES AND DEVELOPMENT AT OR NEAR TO OR ADJACENT TO SENSITIVE AREAS

3. DEVELOPMENT OF ACTIVITIES OUTSIDE SENSITIVE AREAS CAN BE CONTROL UNDER LOCAL GOVERNMENT AGENCIES AND APPROVED SEDIMENTATION CONTROL PLAN (ESCP)

4. NO MORE TERMINOLOGY OF PEIA, DEIA, COMPREHENSIVE EIA ETC .

FIRST SCHEDULE (NO PUBLIC DISPLAY AND PUBLIC COMMENTS) AND SECOND SCHEDULE (PUBLIC DISPLAY AND PUBLIC COMMENTS)

12

EIA ORDER 1987

SHEDULE: 19

ACTIVITIES (57 SUB

ACTIVITIES)

EIA ORDER 2015

FIRST SCHEDULE: 21

ACTIVITIES (45 SUB

ACTIVITIES)

SECOND SCHEDULE: 17

ACTIVITIES (42 SUB

AKTIVITIES)

DIFFERENCES BETWEEN EIA ORDER 1987

AND EIA ORDER 2015

13

EIA ORDER 2015

FIRST SCHEDULE

• N0 PUBLIC DISPLAY AND PUBLIC COMMENTS

• CLIENT CHARTER 5 WEEKS OR 3 WEEKS

SECOND SCHEDULE

• PUBLIC DISPLAY AND PUBLIC COMMENTS

• CLIENT CHARTER 12 WEEKS

The changes and key elements in the new EIA Order 2015 covered :

a. Reduce of quantum/sizes in development area that need EIA study;

b. Prescribed activities in slope area;

c. Scope of EIA order considering sensitive area that include Peninsula Malaysia, Sabah and Sarawak; and

d. Consider the protection of ecology in project development

e. No more using the term PEIA or DEIA 14

KEY ELEMENTS IN EIA ORDER 2015

15

NEW PRECRIBED ACTIVITIES IN EIA ORDER 2015

• DEVELOPMENT IN COASTAL AND HILL AREA.

• DEVELOPMENT IN SLOPE AREA.

• DREDGING.

• RADIOACTIVE MATERIALS AND RADIOACTIVE WASTES.

NEW ACTIVITIES

16

NEW SUB-ACTIVITIES

• AGRICULTURE: - New pig farming area of 2,000 or

more standing pig population.

• AERODROME:

• FORESTRY:

• INDUSTRY:- Recycle paper industry: Production

capacity of 50 tonnes per day or more.

NEW PRECRIBED SUB- ACTIVITIES IN EIA ORDER

2015

17

NEW SUB-ACTIVITIES

• MINING:- River, coastal or offshore sand mining.

• WASTE TREATMENT AND DISPOSAL:

- Construction of off-site recovery plant or treatment facility that generates significant amount of wastewater which is located upstream of public water supply intake.

- Construction of transfer station. - Construction of sewerage network.- Sludge treatment facilities.

NEW PRECRIBED SUB- ACTIVITIES IN EIA ORDER

2015

18

NEW SUB-ACTIVITIES

• ROAD:- Construction of road, tunnel or bridge

traversing or adjacent to environmentally sensitive areas.

• RADIOACTIVE MATERIALS AND RADIOACTIVE WASTE:

- Any activity specified in this Schedule and the First Schedule using radioactive materials and generating radioactive wastes.

NEW PRECRIBED SUB- ACTIVITIES IN EIA ORDER

2015

19

• AGRICULTURE• DRAINAGE AND IRRIGATION• LAND RECLAMATION• FISHERIES• FORESTRY• INDUSTRY• PORTS• MINING• PETROLEUM• POWER GENERATION AND TRANSMISSION• QUARRIES• TRANSPORTATION• RESORT, RECREATIONAL AND INSTITUTIONAL DEVELOPMENT• WASTE TREATMENT AND DISPOSAL

PRECRIBED SUB- ACTIVITIES IN EIA ORDER 2015

REMAIN ACTIVITIES

20

REMAIN ACTIVITIES (NEW TITLE)

REMAIN PRECRIBED ACTIVITIES IN EIA ORDER

2015

•CONSTRUCTION OF DAM From sub-activity of : -Drainage and Irrigation.-Power Generation and

Transmission.-Water Supply.

• INDUSTRIAL ESTATE DEVELOPMENT -From sub-activity Infrastructure.

• ROAD-From sub-activity Infrastructure.

• NEW TOWNSHIPS -From sub-activity Infrastructure.

• AERODROME-From activity Airport.

21

• DELETED

INFRASTRUCTURE: 9(a) Construction of hospitals with outfall into beachfronts used for

recreational purposes.

AGRICULTURE1 (b) Agricultural programmes

necessitating the resettlement of 100 families or more

DELETED PRECRIBED SUB- ACTIVITIES IN EIA

ORDER 2015

EIA ORDER 2015

22

2. In this Order—

“environmentally sensitive area” means—

(a) any area specified as such in the development plan or national physical plan under the Town and Country Planning Act 1976 [Act 172]; or

(b) any area specified as enviromental protection area or enviromental conservation area under any Enactment in the State of Sabah or any Ordinance in the State of Sarawak;

“report” means a report of an environmental impact assessment.

INTERPRETATION

3. (1) The activities specified in the First Scheduleand the Second Schedule are prescribedactivities.

(2) The activities specified in the First Schedule do not require public display and public comment unless otherwise instructed, in writing, by the Director General.

(3) The activities specified in the Second Schedule require public display and public comment.

24

PRESCRIBED ACTIVITIES

25

[Subparagraph 3(2)]

List of Prescribed Activities that Does NotRequire Public Display and public

comments according to the Procedure as in the Environmental Impact Assessment

Guidelines

FIRST SCHEDULE

26

[Subparagraph 3(3)]

List of Prescribed Activities that Require Public Display and public

comments according to the Procedure as in the Environmental

Impact Assessment Guidelines

SECOND SCHEDULE

3. (4)Notwithstanding subparagraph (1), the followingactivities are also prescribed activities:

(a) any prescribed activity which has beendivided into a size or quantum smaller thanthe size or quantum specified in the FirstSchedule and the Second Schedule; or

(b) any activity involving the increase in sizeor quantum resulting such activity to becategorized as prescribed activities.

REDUCE OR INCREASE SIZE

(5) Public display and public commentreferred to in subparagraphs (2) and (3) are adisplay of a report, at a place and withinthe time determined by the DirectorGeneral, to obtain public comment inrelation to that report.

PUCLIC DISPLAY

29

APPLICATION TO THE STATE OF SARAWAK

4. (1) This Order* shall apply to the State of Sarawak inrespect of the prescribed activities specified in the followingitems:

(a) items 2, 6, 9, 10, 11 (a,b), and 14 (a) ofthe First Schedule;

and

(b) items 2, 6, 9, 10,11, 16 and 17 and sub-item 14 (a) of the Second Schedule.

* The EIA Report is process by DOE Sarawak

30

EIA Activities processed by NREB, Sarawak

SCHEDULE 1 SCHEDULE 1

1 Agriculture 13 Development in Slope Area

3 Drainage & Irrigation 14 Waste Treatment and Disposal (Solid Waste, Sewage)

4 Fisheries 15 Dredging

5 Forestry 16 Housing

7 Land Reclamation 17 Industrial Estate Development

8 Mining 18 Construction of New Townships

10 Ports (State ports) 19 Quarry

11(c) Construction of transmission line in environmentally sensitive area.

20 Road

12 Development in Coastal and Hill Area

21 Water Supply

APPLICATION TO THE STATE OF SARAWAK

31

EIA Activities processed by NREB, Sarawak

SCHEDULE 2

1 Agriculture

3 Drainage & Irrigation

4 Fisheries

5 Forestry

7 Land Reclamation

8 Mining

10 Ports (State ports)

12 Development in Coastal and Hill Area

13 Development in Slope Area

14 Waste Treatment and Disposal (Solid Waste)

15 Construction of Dam

APPLICATION TO THE STATE OF SARAWAK

32

4. (2) This Order* shall apply to the State of Sabah in respect of the prescribed activities specified in the following items:

(a) items 2, 6, 9, and 14 and sub-item 11 (a,b) of the First Schedule; and

(b) items 2, 6, 9, 11, 14 and 17 of the Second Schedule.

* The EIA Report is process by DOE Sabah

APPLICATION TO THE STATE OF SABAH

33

EIA Activities processed by EPD SABAH

SCHEDULE 1 SCHEDULE 1

1 Agriculture 13 Development in Slope Area

3 Drainage & Irrigation 15 Dredging

4 Fisheries 16 Housing

5 Forestry 17 Industrial Estate Development

7 Land Reclamation 18 Construction of New Townships

8 Mining 19 Quarry

9(b) Petroleum (on-shore pipeline) 20 Road

11(c) Construction of transmission line in environmentally sensitive area.

21 Water Supply

12 Development in Coastal and Hill Area

APPLICATION TO THE STATE OF SARAWAK

34

EIA Activities processed by EPD SABAH

SCHEDULE 2

1 Agriculture

3 Drainage & Irrigation

4 Fisheries

5 Forestry

7 Land Reclamation

8 Mining

10 Ports

12 Development in Coastal and Hill Area

13 Development in Slope Area

15 Construction of Dam

APPLICATION TO THE STATE OF SARAWAK

35

FIRST SCHEDULE[Subparagraph 3(1)]

List of Prescribed Activities that does not require

Public Display according to the Procedure as in the Environmental Impact Assessment Guidelines

EIA ORDER 2015

43

6. INDUSTRY

(a) Chemical:

Production capacity of each product or combined products of 100 tonnes or more per day.

(b) Cement:

Cement grinding plant with cement production capacity of 200 tonnes or more per day.

(c) Lime:

Production of 100 tonnes or more per day of burnt lime using rotary kiln or 50 tonnes or more per day of burnt lime using vertical kiln.

FIRST SCHEDULE

EIA ORDER 2015

45

7.LANDRECLAMATION

Coastal reclamation or land reclamation along river banks involving an area of less than 50 hectares.

FIRST SCHEDULE

EIA ORDER 2015

46

8. MINING

(a) Ore processing outside mineral tenement area, including concentrating of aluminium, copper, gold, iron, tantalum or rare earth element.

(b) Sand mining on land or river, or in coastal area or in territorial waters not exceeding 3 nautical miles measured from the low-water line, involving an area of 20 hectares or more.

(c) Sand mining in continental shelf area.FIRST SCHEDULE

EIA ORDER 2015

9. PETROLEUM:

(c) Construction of—

(i) oil separation, processing, handling and storage facilities;

(ii) gas separation, processing, handling and storage facilities; or

(iii) oil and gas separation, processing, handling and storage facilities;

(d) Construction of product depot for the storage of petrol, gas or diesel which has the combined storage capacity of 60,000 barrels or more (excluding service station) within 3 kilometres from any commercial, industrial or residential area.

EIA ORDER 2015

49

10. PORTS

(a) Expansion of portinvolving an increase of 50percent or more in handlingcapacity per annum.

(b) Expansion of fishingport involving an increase of50 percent or more in fishlanding capacity per annum.

FIRST SCHEDULE

EIA ORDER 2015

51

12. DEVELOPMENT IN COASTAL AND HILL AREA:

(a) Construction of building or facilities with 80 rooms or more in coastal area.

(b) Construction of hill-station resort or hotel at 300 meters or more above mean sea level covering an area of 20 hectares or more.

FIRST SCHEDULE

EIA ORDER 2015

53

14. WASTE TREATMENT ANDDISPOSAL

(a) Scheduled waste:

(i) Construction of recovery plant (off-site);

(ii) Construction of wastewater treatment plant (off-site);

(iii) Construction of storage facility (off-site).

FIRST SCHEDULE

EIA ORDER 2015

54

14. WASTE TREATMENT AND DISPOSAL

(b) Solid waste:

(i) Construction of composting plant;

(ii) Construction of recovery plant or recycling plant.

(c) Sewage:

(i) Construction of sewage treatment plant with 20,000 population equivalent or more;

(ii) Sludge treatment facilities.

FIRST SCHEDULE

EIA ORDER 2015

55

15. DREDGING

(a) Capital dredging.

(b) Disposal of waste dredged materials.

FIRST SCHEDULE

EIA ORDER 2015

62

SECOND SCHEDULE[Subparagraph 3(1)]

List of Prescribed Activities that require Public Display

according to the Procedure as in the

Environmental Impact Assessment Guidelines

EIA ORDER 2015

63

1. AGRICULTURE

(a) Land development schemescovering an area of 500hectares or more to bringforest into agriculturalproduction.

(b) New pig farming area of 2,000or more standing pigpopulation.

SECOND SCHEDULE

EIA ORDER 2015

64

2. AERODROME

(a) Construction of a new aerodrome involving a runway of 1,000 metres or longer.

(b) Construction of aerodrome in or adjacent or near to any state park, national park, national marine park, island surrounding marine park or environmentally sensitive area.

SECOND SCHEDULE

EIA ORDER 2015

65

3. DRAINAGE AND IRRIGATION

(a) Construction of man-made lakes and artificial enlargement of lakes with surface areas of 50 hectares or more in or adjacent or near to environmentally sensitive area.

(b) Any drainage of wetland, wild-life habitat or of dry inland forest covering an area of 20 hectares or more.

SECOND SCHEDULE

EIA ORDER 2015

66

4. FISHERIES

Land based aquaculture projects accompanied by clearing of mangrove swamp forest, peat swamp forest or fresh water swamp covering an area of 50 hectares or more.

SECOND SCHEDULE

EIA ORDER 2015

67

5. FORESTRY

(a) Conversion of forest at 300 meters or more above mean sea level to other land use covering an area of 100 hectares or more.

(b) Logging or conversion of forest to other land use within—

(i) a catchment area of reservoirs used for municipal water supply, irrigation or hydro-power;

(ii) an area adjacent or near to any state park, national park or national marine park;

(iii) any state park, national park or national marine park; or

(iv) an area gazetted as water catchment forest under the National Forestry Act 1984 [Act 313].

SECOND SCHEDULE

EIA ORDER 2015

68

5. FORESTRY

(c) Logging, or cutting or taking of timber from forest at 300 meters or more above mean sea level covering an area of 100 hectares or more, outside permanent reserved forest.

(d) Logging, or cutting or taking of timber covering an area of 500 hectares or more.

(e) Development of planted forest covering an area of 500 hectares or more.

SECOND SCHEDULE

EIA ORDER 2015

69

5. FORESTRY

(f) Conversion of an area of—

(i) mangrove forest;

(ii) peat swamp forest; or

(iii) fresh water swamp forest,

for industrial, housing or agricultural use covering an area of 50 hectares or more

(g) Clearing of mangrove forest, peat swamp forest or fresh water swamp forest, on islands adjacent to any national marine park.

SECOND SCHEDULE

EIA ORDER 2015

70

6. INDUSTRY

(a) Non-ferrous—

(i) Primary smelting aluminium (all sizes);

(ii) Primary smelting copper (all sizes);

(iii) Primary smelting other non-ferrous (producing 50 tonnes product or more per day).

(b) Cement:

With clinker production capacity of 30 tonnes or more per hour.

SECOND SCHEDULE

EIA ORDER 2015

71

6. INDUSTRY

(c) Iron and steel:

(i) Using iron ore as raw materials for production of 100 tonnes or more per day; or

(ii) Using scrap iron as raw materials for production of 200 tonnes or more per day.

SECOND SCHEDULE

EIA ORDER 2015

72

6. INDUSTRY

(d) Petrochemicals:

Production capacity of each product or combined product of 50 tonnes or more per day.

(e) Pulp, or pulp and paper:

Production capacity of 50 tonnes or more per day.

(f) Recycle paper industry:

Production capacity of 50 tonnes or more per day.

SECOND SCHEDULE

EIA ORDER 2015

73

7. LAND RECLAMATION:

(a) Coastal reclamation or landreclamation along river banksinvolving an area of 50 hectares ormore.

(b) Coastal reclamation or landreclamation along river banks, withinor adjacent or near to environmentallysensitive areas.

(c) Reclamation for man-madeisland.

SECOND SCHEDULE

EIA ORDER 2015

74SECOND SCHEDULE

8. MINING

(a) Mining of minerals in newareas involving large scaleoperation.

(b) Mining of mineralswithin or adjacent or near toenvironmentally sensitivearea.

EIA ORDER 2015

75

9. PETROLEUM

(a) Construction of oil refineries;

(b) Construction of gas refineries;or

(c) Construction of oil and gasrefineries.

SECOND SCHEDULE

EIA ORDER 2015

76SECOND SCHEDULE

10. PORTS

(a) Construction of a new port.

(b) Construction of a new fishing port.

EIA ORDER 2015

77SECOND SCHEDULE

11. POWER GENERATION AND TRANSMISSION

(a) Construction of coal fired power station and having the capacity of 10 megawatts or more with or without transmission line.

(b) Construction of nuclear-fuel power station, with or without transmission line.

EIA ORDER 2015

78

12. DEVELOPMENT IN COASTAL AREA, NATIONALAND STATE PARK

Development of tourist facilities, recreational facilities or other facilities—

(a) in any national park or state park; or

(b) on any island in surrounding waters which has been gazetted as a national marine park or marine reserve under the Fisheries Act 1985 [Act 317].

SECOND SCHEDULE

EIA ORDER 2015

79SECOND SCHEDULE

EIA ORDER 2015

13. DEVELOPMENT IN SLOPE AREA:

(a)Development or land clearing of 50 per cent or

more of an area with slope greater than or equal

to 250 but less than 350.

(b)Construction of road, tunnel or bridge

traversing an area with slope greater than or

equal to 350.

80

14. WASTE TREATMENT AND DISPOSAL

(a) Scheduled waste:

(i) Construction of thermal treatment plant.

(ii) Construction of off-site recovery plant for lead acid battery wastes.

(iii) Construction of off-site recovery plant or treatment facility that generates significant amount of wastewater which is located at the upstream of public water supply intake.

(iv) Construction of secure landfill facility.SECOND SCHEDULE

EIA ORDER 2015

81

14. WASTE TREATMENT ANDDISPOSAL

(b) Solid waste:

(i) Construction of thermal treatment plant.

(ii) Construction of sanitary landfill facility.

(iii) Construction of transfer station.

SECOND SCHEDULE

EIA ORDER 2015

82

15. CONSTRUCTION OF DAM

(a) Construction of dam or impounding reservoir for the purpose of irrigation, flood mitigation, control of siltation, recreational, water supply or any other reason with a surface area of 100 hectares or more.

(b) Dam and hydro-electric power scheme with either or both of the following -

(i) dam of 15 metres or more in height and ancillary structures covering a total area of 40 hectares or more;

(ii) reservoir with a surface area of 100 hectares or more.

SECOND SCHEDULE

EIA ORDER 2015

84

17. RADIOACTIVE MATERIALS ANDRADIOACTIVE WASTE

Any activity specified in this Schedule and the First Schedule using radioactive materials and generating radioactive wastes.

SECOND SCHEDULE

EIA ORDER 2015

85

CONCLUSION

CONCLUSION

86

New EIA Order 2015, can further contribute and enhance the effectiveness of EIA towards achieving sustainable development in Malaysia.