Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report Quarterly Report January–March 2017
Sri Lanka: Green Power Development and Energy
Efficiency Improvement Investment Program
(Tranche 1)-Moragolla Hydropower Project
Prepared by Ceylon Electricity Board of the Ministry of Power and Renewable Energy for the
Asian Development Bank
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Environmental Safeguard Monitoring Report
Reporting Period : January 2017 to March 2017
Date : April 03, 2017
Loan No. : 3147 / 3146 (SF) - SRI
SRI: Green Power Development and Energy Efficiency
Improvement Investment Program (Tranche-01)
Moragolla Hydropower Project
Prepared by Ceylon Electricity Board of the Ministry of Power and Renewable Energy for the Asian
Development Bank
This environmental safeguard monitoring report is a document of the borrower and made publicly
a aila le i a orda e ith ADB’s Pu li Co u i atio s Poli y a d the “afeguard poli y “tate e t 2009.The views expressed herein do not necessarily represent those of ADB’s Board of Dire tors,
Management, or staff.
1
TABLE OF CONTENTS
Page
Abbreviations 02
Executive Summary 03
1.0 Introduction 04
1.1. Brief Project Description 04
1.2. Project Progress Status and Implementation Schedule 05
2.0 Compliance to National Regulations 09
3.0 Compliance to Environmental Covenants from the ADB Loan Agreement 11
4.0 Compliance to Environmental Management Plan 13
5.0 Safeguards Monitoring Results and Unanticipated Impacts 15
6.0 Implementation of Grievance Redress Mechanism and Complaints Received from
Stakeholders 17
7.0 Supplementary Environment Impact Assessment Report 18
8.0 Fish Surveying, Translocation and Monitoring of the Labeo fisheri along the
Mahaweli River 19
9.0 River Flow Data on the Mahaweli River Downstream of the Moragolla Hydropower
Plant 21
10.0 Conclusions and Recommendations 21
Annexure 1 - River Flow Data on the Mahaweli River Downstream of the Moragolla Hydropower
Plant 23
Annexure 2 - Letter received from Mr. Prashan De Silva 36
LIST OF TABLES
1.1 Summary of Environmental Compliance Status 03
2.1 Status of the Main Activities of the Project funded by ADB 05
2.2 Status of the Preliminary Activities of the Project funded by CEB 06
3.1 Activities related to Aquatic Ecology 07
3.2 Activities related to Terrestrial Ecology 08
4.1 Applicable Acts and Legislation to the project 09
5.1 Environmental Covenants 11
6.1 Compliance Status on Pre-Construction Environmental Issues in Moragolla Hydropower
Project 14
7.1 Environmental Monitoring Plan for the Moragolla Hydropower Project: Special Issues 16
8.1 Key activities of the SEIA approval process 18
9.1 Key activities of the Fish Surveying, Translocation and Monitoring of the Labeo fisheri 20
2
ABBREVIATIONS
ADB Asian Development Bank
APs Affected Persons
CEB
Ceylon Electricity Board
CEA Central Environmental Authority
GoSL Government of Sri Lanka
GRC Grievance Redress Committee
DS Divisional Secretariat
DWC Department of Wild Life Conservation
EARF Environmental Assessment and Review Framework
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMoP Environmental Monitoring Plan
EPL Environmental Protection License
FSL Full Supply Level
FD Forest Department
IA Implementing Agency
IUCN International Union for Conservation of Nature
IEE Initial Environmental Examination
LAA Land Acquisition Act
NEA National Environment Act
NZG National Zoological Gardens
MASL Mahaweli Authority of Sri Lanka
MCM Million Cubic Meter
MFF Multi Financing Facility
MHP Moragolla Hydropower Project
MoPE Ministry of Power and Renewable Energy
MV Medium Voltage
MPC
Ministry Procurement Committee NBRO
PD Project Director
PMO Project Management Office
PMU Project Management Unit
PPC Project Procurement Committee
Rsp Responsibility
SCAPC Standard Cabinet Appointed Procurement Committee
SPS Safeguard Policy Statement
TL Transmission Line
Electrical Terminology V Volt Unit of Voltage
kV Kilovolt 1000 volts
W Watt Unit of active power
kW Kilowatt 1000 watts
MW Megawatt 1000kW
MWh Megawatt hour Unit of energy
VA Volt ampere Unit of apparent power
MVA Million volt ampere 106VA
3
Executive Summary
Moragolla Hydropower Project (MHP) is one of several hydropower projects identified by the
Government of Sri Lanka (GoSL) to reduce the role of fossil-fuel power generation, which has outstripped
hydropower over the past 30 years as readily exploitable locations have been utilized. The Executing
Agency of The project is the Ministry of Power and Renewable Energy (MoPE) and the Implementing
Agency is the Ceylon Electricity Board (CEB). Financial assistance is given by the Asian Development Bank
(ADB) under the Tranch 1 of Green Power Development and Energy Efficiency Improvement Investment
Program.
The Project involves construction of a 37m high, 236 m long concrete gravity dam (crest at 550 masl), to
create a 38.5ha, 1.98 MCM reservoir with a Full Supply Level (FSL) at 548 masl. The concrete spillway
contains 5 radial gates (13x15m) designed to pass a 10,000 year flood (6,700m3/s) with no increase in
FSL, or with a 2m increase if one gate was non-operational and closed. Water will be diverted by an intake
just upstream of the dam, into a 2.7km, 4.7m ø underground headrace tunnel, surge tank and penstock
on the left bank, to an above-ground powerhouse and 28m open-channel tailrace outfall, through which
water will return to the river. Existing 132 kVA transmission line (TL) from Polpitiya to Kiribathkumbura
will have an in and out connection to the Moragolla 132kV switchyard.
The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main
practical tools employed during the project implementation to provide the environmental protection
measures. The purpose of the Environmental Management Plan (EMP) is to set out clearly the required
mitigation measures and allocate responsibility for each, and to provide additional information to assist in
planning and implementing the various activities.
The impacts and mitigation for this project fall into four distinct categories, based on the phase in which
the mitigation will be provided and the parties who will take the necessary action. For this reason the
EMP as well as EMoP for this project is subdivided into the equivalent four parts. These are as follows:
a) Construction Phase EMP;
b) Operation Phase EMP;
c) Special Issues EMP: Aquatic Ecology;
d) Special Issues EMP: Terrestrial Ecology.
Since at the moment project is at preconstruction stage, this report mainly addressed relevant
environmental issues and their mitigation measures for preconstruction stage of the project as mentioned
in the following table and forth coming chapters.
Summary of Environmental compliance during the period of January 01, 2017 to March 31, 2017.
Table No. 1.1 : Summary of Environmental Compliance Status
Environmental Mitigation Measures Compliance Status
Preventing Poaching To be commenced
Confirmation of Fish Distributions (Fish Survey) Commenced
Catch- and- Haul (Fish Translocation) To be commenced
Animal Rescue Program To be commenced
Afforestation/Habitat Enhancement To be commenced
4
1.0 Introduction:
1.1 Brief Project Description
Green Power Development and Energy Efficiency Improvement Investment Program is intended to finance
a series of investments via Multi-tranche Financing Facility (MFF) of Asian Development Bank (ADB).
Tranche-01 consists of several development projects in generation, transmission and distribution sectors,
including Moragolla Hydropower Project.
Moragolla Hydropower Project (MHP) is one of several hydropower projects identified by the Government
of Sri Lanka (GoSL) to reduce the role of fossil-fueled power generation, which has outstripped
hydropower over the past 30 years as readily exploitable locations have been utilized. Returning
hydropower to greater prominence would promote sustainable development and reduce greenhouse gas
emissions in line with the National Climate Change Policy, and limit exposure to fluctuating international
fuel prices. The Executing Agency is the Ministry of Power and Renewable Energy (MoPE) and the
Implementing Agency is the Ceylon Electricity Board (CEB).
The project will be located in the upper reaches of the Mahaweli Ganga in the Central Highlands of Sri
Lanka, approximately 22 km south of Kandy City and 130 km north-east of Colombo.
The project involves construction of a 37 m high, 236 m long concrete gravity dam (crest at 550 masl), to
create a 38.5 ha, 1.98 MCM reservoir with a Full Supply Level (FSL) at 548 masl. The concrete spillway
contains 5 radial gates (13 x 15 m) designed to pass a 10,000 year flood (6,700 m3/s) with no increase in
FSL, or with a 2 m increase if one gate was non-operational and closed. Water will be diverted by an intake
just upstream of the dam, into a 2.7 km , 4.7 m Ø underground headrace tunnel, surge tank and penstock
on the left bank, to an above-ground powerhouse and 28 m open-channel tailrace outfall, through which
water will return to the river. Existing 132 kVA transmission line (TL) from Polpitiya to Kiribathkumbura will
have an in and out connection to the Moragolla 132kV switchyard.
MHP is designed as a run-of-river scheme, with an installed capacity of 30.2 MW (2 x 15.1 MW); and it will
operate as a peaki g statio , ge erati g po er i the daily peak de a d period (5-9 pm), and at other
times if there is sufficient water (mainly in the monsoon season). The dam includes a pipe to discharge a
o sta t E iro e tal Flo (E-flow) of 1.5 m3/s, which will pass through a micro-hydro plant on the
right bank, generating an additional 360 kW.
5
1.2 Project Progress Status and Implementation Schedule:
A. Progress Status
The updated status of Moragolla Hydropower Project from January 2017 to March 2017 is given below
in Table 2.1 and Table 2.2 respectively.
Table -2.1: Status of the Main Activities of the Project funded by ADB
Se. No Work Description Status
1.0 Lot 1 - Civil Works
Part A – Preparatory Works consists of construction of Base
camp for the Employer and Engineer, upgrading and
construction of irrigation facilities, and construction and
improvement of permanent access roads.
Part B – Main work consists of construction of a dam, intake,
headrace tunnel, surge tank, penstock shaft, power house,
tailrace, and switchyard and all related works.
ADB has approved the Lot 1
(Civil Works) bidding
document and SCAPC has
approved the same on May
21, 2015. Bid calling was
delayed due to non-
appointment of the
Consultant who should
review the bidding
document before calling for
bids. Consultant has
completed the review of Lot
1 bidding document without
the Dam section, since MASL
has requested to
incorporate a Bottom outlet
and to widen Dam Crest by
3m for an additional
carriage way.
2.0 Lot 2 – Mechanical and Electrical Facilities
Part A – Hydro Mechanical Facilities consists of dam gates, stop
logs, trash racks, steel lining of penstock and all hydro
mechanical facilities.
Part B – Electro Mechanical Facilities consist of turbine,
generators, switchyard equipment, control and protection
systems, connection to the existing transmission line, micro
hydro power plant and all other electro mechanical facilities.
Lot 2 CEB Consultants have
commenced scrutinizing the
bidding document with the
PMU and expect to
complete by May 31, 2017.
3.0 Lot 3- Consultancy Service
Consultancy Supervision Services for the project.
After Cabinet approval and
ADB concurrence the
contract for the Consultancy
Services was signed
between CEB and Ms.
Nippon Koei Co. Ltd. (Japan)
in joint venture with
Fitchner GmbH & Co. KG
(Germany) on October 24,
2016. Consultant has
completed the review of Lot
1 bidding document on
March 31, 2017, without the
dam section.
6
Table -2.2: Status of the Preliminary Activities of the Project funded by CEB
Se. No Work Description Status
1 Land Acquisition
Udapaltha DS Division - Under Section 9, title inquiries were
completed for all lands under Uda Palatha DS Division. Section 10
decision on title notice was sent to Valuation Department for
valuation for the lands which has clear title. For other lands DS
(Udapalatha) has requested clarification from Ministry of Lands for
the issues aroused in title inquiry.
Ganga Ihala Korale DS division – Under Section 9, title inquiries
were completed for all lands under Ganga Ihala Korale DS Division,
except for Ulapane South. After title inquiries errors on some PPs
were complained by PAPs. Site investigations on those issues were
completed and PPs to be corrected. Survey request for PP
correction was sent to Survey Superintendent-Kandy by DS (Ganga
Ihala Korale).
Section-38 Direction was received for Ulapane South in Ganga lhala
Korale DS Division. Section 5 Direction was received and Survey
order was given to prepare PP. Plan preparation work was
completed and PP is pending.
2 Resettlement Land Possession of the resettlement land was taken over by CEB after
Section 38 - direction. Section 9 title inquiries were completed and
Section 10 decision on title notice is pending.
3 Construction of
Resettlement Village
Contract was awarded to Ms. Sierra Construction Co. Ltd. on March
21, 2016. Preliminary design work is ongoing. But physical
construction work is delayed until approval for the Supplementary
EIA is received.
4 Environmental
activities
Contract was awarded to Ms. Access Energy (Pvt) Ltd. to obtain the
river flow measurement along the Mahaweli river. Flow
measurements work were commenced and ongoing.
Contract was awarded to Ms. National Aquatic Resources Research
& Development Agency to carry out a fish survey along Mahaweli
River. A Technical Committee was appointed to oversee the
implementation of fish survey and translocation process. A request
letter was sent to Director General of Wild Life Dept. for approval
to commence the work. After approvals from Department of
Wildlife NARA has completed the fish surveying work. It was
observed that Labeo fisheri was present in the vicinity of the project
area and awaiting for their report.
7
B. Implementation Schedule for Environmental Activities of Moragolla Hydropower Project
B.1 Aquatic Ecology
Table No. 3.1: Activities related to Aquatic Ecology
Note 1: Pre construction activities was delayed due to delay in appointing the Consultancy Service to commence work.
Activities 2016 2017 2018 2019 2020 2021 2022 2023
Pre-construction Construction Operation
Preventing Poaching
Worker dissemination sessions. X1 X X
Monitoring (spot checks) of worksites adjacent to the river.
X X X X X X X X X
Confirmation of Fish Distributions (Fish Survey)
Logistics preparation for survey
(equipment procurement; maps,
boat).
X
Fish survey. X X
Linkage to fish translocation
program.
X
Fish Survey / Monitoring X X X X X X X X X X X X
Catch- and- Haul (Fish Translocation)
Review of fish survey data. X
Survey and selection of
translocation sites.
X
Undertake catch-and-haul. X
Public awareness-raising at target
sites to support fish conservation.
X X X
8
B.2 Terrestrial Ecology
Table No. 3.2: Activities related to Terrestrial Ecology
Activities 2016 2017 2018 2019 2020 2021 2022 2023
Pre-construction Construction Operation
Afforestation/Habitat Enhancement
Final selection of afforestation sites.
X2
Survey and demarcation of planting sites.
X2
Final site-specific selection of species.
X2
Preparation of detailed afforestation plan.
x
Preparation of detailed planting maps.
x
Establishment and maintenance of nurseries.
x x
Land preparation for planting. x
Supply of planting material. x
Afforestation planting. x
Post-planting maintenance and management.
x x x x x
Weeding. x x
Fire protection. x x x
Application of fertilizer. x x
Cutting of climbers and creepers.
x x x
Pest and diseases control. x x x x x x
Vacancy planting. x
Monitoring. x x x x x x x x x
Animal Rescue Program
Animal rescue program. X2 X X
Note 2: Pre construction activities are delayed due to delay in some local approvals and approval for Supplementary EIA.
9
2.0 Compliance to National Regulations:
The relevant applicable Acts and Legislations to the project are given in the Table No. 4.1.
Table No. 4.1: Applicable Acts and Legislations to the project
Act /Rule/Notification Year Objectives Compliance Status
National Environment Act (NEA) No
47 of 1980 as amended by act No
56 of 1988 and act No 53 of 2000
1980
1988
2000
Sri Lanka national basic
charter for protection and
management of environment.
Being Complied
EIA regulations gazetted under NEA
(Government Gazette Extraordinary
No.772/72 dated 24 June 1993 and
in several subsequent
amendments)
1993 Schedule of State agencies as
the project approving
agencies under NEA.
Mahaweli Authority
of Sri Lanka is the
Project Approving
Authority for the
Moragolla
Hydropower Project
Environmental Protection License
(EPL) regulations gazetted under
NEA (Government Gazette
Extraordinary No. 1533/16 dated 25
January 2008)
2008 Schedule of activities for
which a EPL is required under
NEA
To be obtained at
construction stage
Wastewater Discharge Standards-
Gazette Notification No. 1534/18
dated 01/02/2008
2008 General standards and
criteria for the discharge of
industrial effluents into inland
surface waters
To be incorporated
at Construction stage
National Environmental (Noise
Control) Regulations 1996 -
Gazette Notification no. 924/12
dated 23.05.1996
1996 To regulate and control noise
generating sources with the
objective of maintaining the
standards (Under NEA)
Base line study will
be done once the
contract is awarded
with the
participation of the
contractor, before
commencement of
work.
Sri Lanka Electricity Act, No. 20 of
2009
2009 The Act does not explicitly
deal with environmental
implications of activities
related to power generation,
transmission and distribution.
However, CEB
Integrates environment
protection as a part of its
project activities.
Being Complied to
CEB standards.
Mines and Minerals Act No. 33 of
1992
1992 Provide for the establishment
of the Geological survey and
mines Bureau to regulate the
exploration for mining,
transportation, processing,
trading in or export of
minerals.
Necessary approvals
will be taken at pre-
construction stage.
10
Act /Rule/Notification Year Objectives Compliance Status
Mahaweli Authority of Sri Lanka Act
No. 23 of 1979
1979 To plan and implement the
Mahaweli Ganga
Development Scheme
including the construction
and operation of reservoirs,
irrigation distribution system
and installations for the
generation and supply of
electrical energy.
Being Complied
Soil Conservation Act No. 25 of
1951 and No. 29 of 1953 and
amended by Act No. 24 of 1996
1951
1953
1996
To make provision for the
enhancement and substance
of productive capacity of the
Soil; to restore degraded land
for the prevention and
mitigation of soil erosion; for
the Conservation of soil
resources and protection of
land against damage by
floods, salinity, alkalinity
water clogging, and to
provide for matters
connected therewith or
incidental thereto.
To be incorporated
at Construction stage
Irrigation Ordinance No. 32 of 1946,
Act No.1 of 1951 and No. 48 of
1968, Law No. 37 of 1973
1946
1951
1968
1973
Construction and
Maintenance of Irrigation
Works, Protection of
Irrigation Works and
Conservation of Water
To be incorporated
at Construction stage
Fauna and Flora Protection
Ordinance as amended by Act No.
49 of 1993 and subsequent
amends.
1993 To provide for the protection,
conservation and
preservation of the fauna and
flora of Sri Lanka
Being Complied
The Antiquities Ordinance, No.9 of
1940 (now Act) and the subsequent
amendments, particularly the
Antiquities (Amendment) Act No.
24 of 1998 is the primary Act.
1940
1998
This Ordinance provides for
the preservation of the
antiquities of Sri Lanka
At present project
area does ’t i ol e
with any antiquities.
The Urban Development Authority
Act No. 41 of 1978
1948 Minister in-charge of the
subject of Urban
Development declares the
areas suitable for
development.
Being Complied
11
3.0 Compliance to Environmental Covenants from the ADB Loan Agreement:
The Table 5.1 shows the applicable Environmental Covenants from the ADB Loan Agreement.
Table No.5.1: Environmental Covenants
Product Schedule Para
No.
Description Remarks
Loan
3146-SRI
5 5 The Borrower and CEB shall ensure that
the preparation, design, construction,
implementation, operation and
decommissioning of the project and all
project facilities comply with (a) all
applicable laws and regulations of the
Borrower relating to environment,
health, and safety; (b) the
Environmental safeguards; (c) the EARF;
and (d) all measures and requirements
set forth in a respective IEE or EIA and
EMP, and any corrective or preventive
actions set forth in a Safeguards
Monitoring Report.
It is being complied as per ADB
Safeguard Policy Statement (SPS) (2009)
as set out in the EARF.
EMP is being implemented in
accordance with applicable laws and
regulations of GOSL and ADB guide
lines.
Further an Environmental Management
Office of the MHP will carry out the
regular environmental monitoring as set
out in the EMP.
The Environmental Monitoring actions
has been planned and will be carried
out in all three phases of
preconstruction, during construction,
and post construction phase.
Loan
3146-SRI
5 6 By 2015, CEB shall undertake, to the
satisfaction of ADB, (a) dry and wet
season fisheries surveys for the
endangered Green Labeo fish on the
stretch of Mahaweli River from around
the site of the Moragolla Hydropower
plant tailrace and the confluence with
the Atabage Oya to appropriate point
downstream on the Mahaweli river and
(b) collect hourly, daily and monthly
flow data on the Mahaweli river
downstream of the Moragolla
Hydropower Plant tailrace and the
confluence with the Atabage Oya over
the period of January 2015 to
December to Identify the minimum
required downstream environmental
river flows during the dry and wet
seasons to satisfy the critical habitat
requirements of the safeguard Policy
Statement. CEB shall ensure that such
minimum required downstream
environmental river flows are
maintained following completion of the
Moragolla Hydropower plant to avoid
any measurable adverse impacts on the
habitat of the endangered Green Labeo
fish.
Being complied.
Contract was awarded to Ms. National
Aquatic Resources Research &
Development Agency (NARA) to
commence fish survey and translocation
of Labeo fisheri along Mahaweli River.
A Technical Committee was appointed
to oversee the implementation of fish
survey and translocation process.
Meetings were held with Department of
Wild Life on April 2016. Approval was
received and NARA has commenced the
fish surveying work. Surveying was
carried out for 04 days and temporarily
suspended due to turbid water. NARA
has requested for permission from
Dept. of Wildlife (DWC) to use different
trapping system due to fast flowing rate
and less transparency.
After approvals received for the same
from the DWC, NARA has completed
the fish surveying work. It was observed
that the Labeo fisheri was present in
the vicinity of the project area and
awaiting for their report.
12
Product Schedule Para
No.
Description Remarks
Contract was awarded to Ms. Access
Energy (Pvt) Ltd to obtain river flow
measurements along Mahaweli River.
Mahaweli Authority approval was
received for a location to carry out the
flow measurements. Flow
measurements were commenced and
ongoing.
Loan
3146-SRI
5 7 CEB shall enter into an agreement with
Mahaweli Authority, acceptable to
ADB, which shall, inter alia, set out(a)
to the extent possible, the minimum
hourly, daily and monthly
environmental river flows downstream
of the Moragolla Hydropower Plant
tailrace during the dry and wet seasons;
and (b) a regulatory mechanism for the
coordinated operation of the Moragolla
Hydropower Plant following its
construction and the existing Kotmale
hydropower plant to ensure that, at all
times, adequate downstream flows are
released to avoid any measurable
adverse impacts on the Labeo fisheri
and maintain the population of the
endangered Green Labeo fish inhabiting
the Mahaweli River downstream of the
tail race of the proposed Moragolla
Hydropower Plant and the confluence
of the Atabage Oya with the Mahaweli
River.
To be carried out
A project modification report was
submitted to the project approving
authority for approvals due to some
changes in EIA. A Supplementary
Environmental Impact Assessment
report is prepared and submitted for
approvals. Once this is approved the
agreement between CEB and Mahaweli
Authority is expected to be reached.
Loan
3146-SRI
5 8 Within 180 days of the effective date
CEB shall established an Environment
Management office, acceptable to ADB,
which shall be responsible for (a) the
environmental monitoring of
construction activities of the Moragolla
Hydropower plant; and (b)
implementation of the relevant EMP for
the Moragolla Hydropower plant
including monitoring of the Labeo fisheri
and downstream minimum
environmental river flows during
operations of the Moragolla
Hydropower plant.
Complied.
Environment Management Office was
established in June 2015 with one
Engineer and Supervisor to take care
the Resettlement, Environmental and
Social issues. Environmental Officer is
also recruited to oversee the
environmental issues.
13
4.0 Compliance to Environmental Management Plan:
The Environmental impacts and mitigation for this project fall into four distinct categories, based on the
phase in which the mitigation will be provided and the parties who will take the necessary action. For this
reason the EMP for this project has subdivided into the equivalent four parts. These are as follows:
1. Construction Phase EMP
2. Operation Phase EMP
3. Special Issues EMP: Aquatic Ecology
4. Special Issues EMP: Terrestrial Ecology
Following the Feasibility study (2009-2012), EIA approval was received from MASL (Project Approving
Agency) in August 2013. Subsequently, Detailed Engineering Design was conducted by the Consultant
with ample amount of studies and investigations. Consequently, certain features of the proposed projects
were substantially altered to optimize the project implementation with respect to environmental, social
and economic perspectives. Thus, the major two entities in this regard are;
1. Shifting the dam 100m downstream from the original location of feasibility study followed by
shortening of tunnel etc.
2. Recording of existence of "Labeo Fisheri" in the project affected area as per the additional
environmental studies of Detailed design phase.
Considering all these changes and environmental implications identified in the detailed design phase
Environmental Submission to ADB was made in 2014 including the Environmental Management Plan and
approval from ADB was received.
At the meantime, due to design changes in the Detailed Engineering Design, MASL (Mahaweli Authority
of Sri Lanka) as the Project Approving Agency claimed for a supplementary EIA. Moreover, they have
recommended for inclusion of bottom outlet which was again a substantial design change. Thus, Volume
2: Environmental Management Plan of 2014 has to be revised again.
First review of the EMP has been completed by the Consultants and the PMU and necessary changes to
the EMP was identified. Based on the survey results of the endangered Labeo fisheri conducted by NARA
and on the recommendations of the Department of Wild life, necessary changes will be done to the EMP.
In addition, the conditions given when providing the approval for Supplementary EIA by the Project
Approving Authority, will be included to the EMP. Final review of the EMP will be done based on the
above recommendations and this will be submitted for necessary approvals and concurrence.
Since this project is in pre-construction stage, special issues of EMP; Aquatic Ecology and Terrestrial
Ecology and relevant environmental issues and their mitigation measures for pre-construction stage of
the Project are being carried out and addressed in this report.
Based on the present Environmental Management Plan the Compliance Status on Environmental Issues
in Moragolla Hydropower Project for pre-construction stage is presented in Table No.6.1. It is to be
noted that since no physical construction work has yet being commenced, only some activities related
to Environmental issues has commenced and some are yet to be implemented.
14
Table No.6.1: Compliance Status on Pre-Construction Environmental Issues of Moragolla Hydropower Project
Potential Root
Cause
Environmental
Issues
Management/
Mitigation Measures
Responsibility Compliance
Status/Remarks Planning Implementation Monitoring Supervision Review
Agency
Fish Poaching by
Project workers
Adverse impacts
on local fish
population
Preventing fish Poaching
Dissemination session for
all project workers and
Monitoring (spot checks)
of work sites adjacent to
the river
CEB CEB CEB CEB CEB To be implemented as
per the EMP
Blasting and
Excavation
Adverse impacts
on Labeo fisheri
distribution in
the Mahaweli
Ganga Section
near project
Confirmation of Fish
Distributions
(Fish Survey)
Fish survey of all the
pools above and below
the dam site
CEB CEB/Consultant CEB CEB CEB The fish survey work
was completed by the
Contractor Ms.
National Aquatic
Resources Research &
Development Agency
(NARA). Awaiting for
their report
Adverse impacts
on local fish
population
Catch-and- Haul
(Fish Translocation)
CEB CEB/Consultant CEB/FD/D
WC/NZG/
CEB/FD/DW
C/NZG/
CEB/FD/
DWC/NZ
G
To be implemented as
per the EMP based on
the fish survey results.
Site Clearance and
Inundation
Adverse impacts
on animals at
project site
Animal Rescue Program
Vulnerable animals will
be captured and moved
to adjacent habitat, if
possible or allowed to
move away from the land
clearing work sites.
CEB CEB/Consultant CEB/
Consultant CEB/IUCN/C
EA
CEB/IUC
N/CEA
To be implemented as
per the EMP
Losing habitats
of wildlife due
to land clearing
and inundation
Afforestation/Habitat
Enhancement Enhancing
habitat for wild life to
compensate lost habitats
by afforestation of 100m
buffer strip around the
reservoir
CEB CEB/Consultant CEB/
Consultant FD CEB/FD To be implemented as
per the EMP and the
preliminary work was
commenced.
15
5.0 Safeguards Monitoring Results and Unanticipated Impacts:
Environmental Monitoring Schedule
The individual environmental monitoring measures are identified in the EIA/Main Report and in the EMP and
relate primarily to those activities in which there are measurable environmental emissions (e.g. air quality, water
quality, noise, etc.). These activities are drawn together in the Environmental Monitoring Plan (EMoP), which
describes in detail the purpose of each monitoring activity and the methodology to be employed (including the
approach, parameters to be measured, survey locations, frequency, and other information). It also recommends
thresholds that will signal the need for corrective actions.
EMoP for this project is divided into four parts, equivalent to the different parts of the EMP such as Construction
Phase, Operation Phase, Special Issues - Aquatic Ecology, and Special Issues - Terrestrial Ecology. Construction
Phase shows that some quite extensive monitoring is required in relation to the three main fields in which there is
the most risk of impacts from the construction work (water quality, air quality and noise and vibration). This
involves monitoring at and around all of the main construction sites and several of the ancillary sites (quarry,
disposal sites and main transportation route), and before construction begins (baseline) and regularly throughout
the construction period. This monitoring is assigned to the contractor to raise awareness of the environmental
risks and impacts associated with the construction work and the way they need to be mitigated.
The remainder of this EMoP involves: small-scale monitoring to confirm the requisite E-flow is provided during
reservoir impoundment; regular monitoring of water levels in domestic wells during tunnel construction; and
checking the structural condition of buildings that may be at risk of structural damage throughout the
construction period. These activities are assigned to CEB because they involve contact with the public regarding
some quite sensitive issues, and because provision of a continuous E-flow is one of the main conditions of the
Environmental Approval for the project, granted by MASL. CEB will probably appoint specialized consultants and
contractors to conduct this work, but it is important that the responsibility for the monitoring and any resulting
remedial action remains with CEB as the Project Proponent.
EMoP for the operation stage of the project are not expected to be major environmental impacts during this
stage, so there is no need for extensive environmental monitoring. Monitoring in relation to the hydrological
changes downstream of the tailrace only requires simple checks, because if CEB mitigates these impacts by
operating the Moragolla and Kotmale stations out-of-phase in the dry season it is very unlikely that there will be
noticeable changes in flow when one station begins to operate.
EMoP for the Special Issues on Aquatic ecology and Terrestrial Ecology is shown in Table No. 7.1. Since the project
is at pre-construction stage, relevant activities in this table are planned to be carried out.
16
Table No. 7.1: Environmental Monitoring Plan for the Moragolla Hydropower Project: Special Issues
Impact Mitigation Monitoring Parameters Method Rsp Frequency Location
1. Aquatic Ecology: The project area supports 8 nationally threatened fish species, including Labeo fisheri, which is of high conservation priority. These species may be affected by disturbance, poaching, turbidity, blasting, etc.
Special measures to protect the rare fish include catch and haul (translocation) to the nearby Kelani River; and cutting channels in the river bed downstream of the dam to improve connections between pools in dry season
Catch and haul requires a prior survey to determine the presence and distribution of Labeo fisheri and other large species; and this should then be repeated during MHPP operation to assess changes in the populations
Monitor: Locations of river bed pools above and below the dam site; fish species present, their distributions and approximate numbers in pools in the river bed; locations of pools
Use an inflatable raft and portable electronic fish finder to determine depth of riverbed, numbers and depth of fish, & locations (GPS coordinates). Use small mesh nets to catch fish samples for species identification; release the captured specimens upstream or downstream
CEB
Two surveys: one pre-construction and one after one year of MHPP operation. Pre-construction survey has already commenced.
In all major pools in the river bed, at the sites of the reservoir and dam, down to Atabage Oya.
The translocation area in Kelani River should then be surveyed annually for the first four years after translocation to monitor survival and population expansion
Monitor: Fish species present and their distributions. Estimate population densities and record other features, such as breeding status
Use similar netting techniques to capture samples of fish in the translocation area
Five surveys: one baseline before translocation and then annually post-translocation
Kelani River, over around 5 km upstream and downstream
2. Terrestrial Ecology: The project will remove >900 trees, none of which are endangered. Terrestrial fauna includes 41 endemic or endangered species of which 5 are high priority1. These are not at risk from the project but their habitat will be enhanced
CEB will reforest a 100 m buffer around the reservoir to reduce soil erosion and planting will incorporate measures to provide habitat for the 5 priority faunal species
The planted area will need to be regularly monitored so that dead seedlings can be replaced and other remedial action (weed removal, disease treatment, etc.) planned and implemented as necessary
Monitor: seedling deaths, indications and presence of pests and disease, invasive species, human encroachment, farming and other unauthorized activities
Conduct walkover surveys of features that can be recognized visually (seedling survival, encroachment) and smaller scale investigations of other aspects (pests, disease). Record locations on maps to plan remediation
CEB
Surveys every 3 months for the first year, then every six months for the next four years
Cover the whole planted buffer zone
When the MHPP is operating the main mitigation will be to protect the reservoir catchment from human impacts by implementing a Watershed Management Plan to improve vegetative cover, stabilise soil and enhance faunal habitat
Once the WMP is underway there needs to be regular monitoring of the key expected improvements in order to record progress and plan refocusing if needed
Monitor: the key parameters in which improvements are needed: soil conservation, vegetation cover and the presence of the key faunal species (reservoir and river water quality will also be monitored as described above)
Monitoring methodologies will be developed in detail during the planning stage for the WMP
Surveys every six months, plus shorter-term records of aspects like faunal sightings when appropriate
The overall WMP area, and in particular those locations targeted for specific activities
Note 1: Complete detail is included Volume 4 – Additional Environmental & Social Studies; Report 12 – Expert Report on Habitat Creation and Management to enhance Terrestrial
Biodiversity by IUCN in Environmental and Social Studies submission of February 2014.
17
6.0 Implementation of Grievance Redress Mechanism and Complaints Received from Stakeholders
Construction activities of hydropower projects, especially where Involuntary Resettlement is involved, might
give rise to grievances among Affected Persons (APs), however much the potential sources of conflict have
been addressed in Environmental Management Plans and Resettlement Plans and Policies. Grievances may
be related to social issues such as eligibility criteria and entitlements, location of resettlement sites, quality
of services at those sites, allocation of houses, livelihoods and social and cultural issues, etc. Grievances may
also be related to environmental issues such as dust generated due to clearing and grubbing works,
vibration and damages to structures, noise, traffic congestion, decrease in water level and water pollution in
private and public wells due to blasting and tunneling, damage to tea plantations and agricultural lands, etc.
Social grievances occur mostly at the time of implementation of the Resettlement Action Plan; and
complaints on environmental issues and public nuisances generally occur during the construction period.
Both types of grievances are different in nature. However, it is imperative to have a mechanism in place to
examine each and find solutions in a transparent manner, to demonstrate to the people that their
grievances are examined carefully.
The Moragolla Hydropower Project, in keeping with the ADB and national safeguard policies, will set up a
Grievance Redress Committee (GRC), which will function as an independent body to find solutions to
grievances and disputes among the affected and concerned parties.
The tentative nominations for the GRC was received by the PMO and formal setting up of the committee
was done. Formation of the GRC was notified to the general public by publication of a notice in national
newspapers in three languages i.e., Sinhala, Tamil and English. The local community was also informed
about the grievance handling procedures of the project through Grama Niladharis1of the area and displaying
notices at important public places within the Divisional Secretariat Divisions of Udapalatha and Ganga Ihala
Korale.
The following members to the GRC was appointed. Mr. J C Ranepura - Additional District Secretary (Lands)
of the Kandy District will function as the Chairperson of the GRC. Ven. Bowala Wimaladhamma and P G
Wijethunga from Udapalatha DS Division and Ven. Mawathure Chandima and K M A Illangakoon from Ganga
Ihala Korale DS Division will represent the Members from the Affected Persons (AP). Mr. H M C D Herath -
Civil Engineer of the PMO, nominated by the Project Director of the MHP will serve as the Secretary to the
GRC. An honorarium will be paid to the members of the GRC; the required funds for operation of the GRC
will be borne by CEB.
During this reporting period, only effective social activity in progress is the land acquisition process, and no
requests and grievances received to PMU.
Meanwhile Mr. Prashan De Silva, owner of the Aqua Dunhinda luxury retreat, has raised his concern over
the impact/effect on the reduced water flow and the sediment flushing through a bottom outlet of the
Moragolla reservoir dam, by his letter dated December 21, 2016. PMU has discussed with him in detail in
connection with his concern and explained the remedial measures taken for the protection of ecological
environment in the immediate downstream of the reservoir. Also, the proposal given for the sediment
flushing from the bottom outlet in an environmentally friendly manner was explained in detail. Finally, he
agreed with the proposal given by the project to protect the environment.
1Grama Niladhari (Village leader) is a Sri Lankan public official appointed by the central government to carryout administrative duties
in a Grama Niladhari division, which is a sub unit of a Divisional Secretariat. The duties of a Grama Niladhari include the reporting of
issuing of permits, gathering statistics, maintaining the voter registry and keeping the peace by settlement of personal disputes. They
are responsible for keeping track of any criminal activity in their area and issuing character certificates on behalf of residents when
requested.
18
7.0 Supplementary Environmental Impact Assessment Report
The feasibility study for the project was carried out by the Central Engineering Consultancy Bureau (CECB)
during 2009-2012. Environmental Impact Assessment (EIA) was also carried out in parallel with feasibility
study. EIA approval was obtained in August 2013 from Mahaweli Authority of Sri Lanka (MASL), the Project
Approving Agency (PAA) for the project.
Subsequently Detailed Engineering Design (DED) was carried out. During DED, the consultant reviewed the
Feasibility Study Reports (FSR) and carried out additional investigations, surveys and studies to ascertain the
suitability of proposed components in the project layout as proposed in the FSR. Based on this information,
the consultant carried out the optimization of the project, in a sustainable manner on social, environmental
and economic aspects. Accordingly, certain Project features were altered than that in the feasibility study
report. Some of the Project alterations are as follows.
1. A bottom outlet to be added
2. Shifting of the dam axis by 100m downstream
3. Environmental flow release through a micro Hydropower plant at the toe of the dam instead of
direct releasing to the downstream
4. Proposing diversion tunnel as an additional alternative for river diversion
5. Underground penstock instead of surface penstock
6. Shifting of Switchyard location
7. Power station access through causeway across Mahaweli river
8. Use of new disposal area
9. Use of new quarry site
10. Co tra tor’s orki g area-3 sites
11. Location change Resettlement village
In order to address the above alterations of the project features, MASL has requested to prepare and send a
Supplementary Environmental Impact Assessment Report (SEIAR) for approval.
A report was prepared by external Consultants and sent to Mahaweli Authority for approvals in May 2016.
After several discussions with the appointed Technical Committee, revised SEIAR was submitted. SEIAR was
opened for public comments from October 27, 2016 to December 8, 2016. Public comments were received
by CEB on December 19, 2016 and reply to them was sent on early January 2017. Meanwhile the EIA
approval already given expired on August 2016, and upon request for extension the PAA informed that it
will be given along with the approval for the SEIAR. Final approval is pending.
Some of the key dates on the activities of the Supplementary EIA approval process is given below.
Table No 8.1: Key activities of the SEIA approval process
No Activity Date
1 TEC meeting for Project Modifications @ MASL Head Office
and Decided to go for SEIAR
February 05, 2015
2 Requested to NBRO for Proposal and Cost Estimate March 06, 2015
3 TOR for SEIAR Received March 23, 2015
4 NBRO Proposal and Cost Estimate received March 26, 2015
5 Request for CEB General Ma ager’s Approval for obtaining
consultancy service from NBRO. However, GM did not grant
the approval and advised to get consultancy service from
individual consultants for each Environmental field and
prepare SEIAR
April 07, 2015
19
6 Requested to CEB, AGM(P) for approval and appointment of
TEC
May 05, 2015
7 TEC Appointment May 11, 2015
8 Preparing RFP and TEC report and submission to
Procurement Committee for obtaining consultancy service
from individual Consultants, directly
June 15, 2015
9 Procurement Committee approval obtained subjected to the
approval of Secretary (MOPE)
July 10, 2015
10 Approval of Secretary (MOPE) received July 29, 2015
11 Proposals called from individual consultants Aug. 04, 2015 to Aug. 20, 2015
12 All consultants responded except for the field of Socio
Economy Aspects. TEC report submitted to Procurement
Committee after evaluation above received RFP. In addition,
it is requested for approval to get another Consultant for
Socio Economic Aspects
September 18, 2015
13 Procurement Committee Approval received subjected to the
approval of Secretary (MOPE) for Socio Economic Consultant
September 29, 2015
14 Approval of Secretary (MOPE) received for Socio Economic
Consultant
October 13, 2015
15 Proposals called from Socio Economic Consultant Oct 13, 2015 to Oct 20, 2015
16 TEC Report submission to DPC (For Socio Economic
Consultant)
October 28, 2015
17 Awarding of Consultants including NBRO October 01, 2015
18 Awarding to Socio Economic Consultant December 01, 2015
19 SEIAR submission to MASL May 18, 2016
20 TEC meeting @MASL June 14, 2016
21 Meeting minutes of TEC meeting July 18, 2016
22 Revised SEIAR Submission Aug 12, 2016
23 TEC Meeting Sep 13, 2016
24 TEC comments Sep 26, 2016
25 Revised SEIAR Submission to Publish in 3 languages Oct 24, 2016
27 Publish in Local Newspapers Oct 27, 2016 to Dec 08, 2016
28 Public comments submitted to MHP December 19, 2016
29 Reply to Public Comments December 29, 2016
30 TEC meeting January 19, 2017
31 Special meeting for technical issues on bottom outlet and
dam crest
February 02, 2017
32 MASL decided to grant approval and subject to concurrence
of Central Environment Authority (CEA)
(CEA waiting for DWC recommendation on Labeo fisheri and
DWC waiting for NARA report on fish survey)
February 21, 2017
8.0 Fish Surveying, Translocation and Monitoring of the Labeo fisheri along the Mahaweli River
EIA of the proposed Moragolla hydropower project has been approved in year 2013. But at the time of EIA
studies, it has not identified the endangered Labeo fisheri fish species which is present in the Mahaweli river.
Nonetheless the fish was identified with the detail design stage and it was mentioned In the Volume 1 of the
Environmental and Social Study Report (Environmental Main Report) of Moragolla Hydropower Project. As
per the Environmental Main Report it was a mandatory requirement to do the Fish Surveying, Translocating
(catch-and-haul) and Monitoring of the Labeo fisheri within the affected area in the Mahaweli River (clause
20
307, page 129). In line with the above requirement a Technical Evaluation Committee (TEC) was appointed
by CEB to prepare Terms of Reference (TOR) and to proceed with the tender to select a contractor to carry
out the work.
According to the approved TOR, proposals were requested by CEB by publishing a paper advertisement and
bids were closed January 06, 2016.
Contract was awarded to Ms. National Aquatic Resources Research & Development Agency (NARA) to carry
out a fish survey along Mahaweli River. A Technical Committee was also appointed to oversee the
implementation of fish survey and translocation process. After approvals from Department of Wildlife
Conservation (DWC), NARA has commenced the fish surveying work. Initial fish surveying was carried out and
temporarily suspended due to turbid water. NARA has requested for permission from DWC to use different
trapping system due to fast flowing rate and less transparency. After approvals from DWC, NARA has
completed the fish surveying work. It was observed that Labeo fisheri was present in the vicinity of the
project area and awaiting for their report.
The important triggers in this process were listed below.
Table No. 9.1: Key activities of the Fish Surveying, Translocation and Monitoring of the Labeo fisheri
No Activity Date
1 CEB requested to appoint a TEC to oversee the implementation of
Fish surveying and translocation of Labeo fisheri from IUCN, Forest
Department, National Zoological garden, and Department of Wild
Life Conservation
November 18, 2015
2 Pre-Bid meeting and site visit. December 18, 2016
3 EML Consultants (Pvt.) Ltd has request for an extension of date of
proposal submission on surveying and translocation of Labeo fisheri.
January 01, 2016
4 BID opening and two bids were received at the closing time January 06, 2016
5 TEC recommends to award the contract for carrying out Surveying,
Translocating, Monitoring and Relocating of Labeo fisheri to National
Aquatic Resources Research & Development Agency (NARA)
January 19, 2016
6 Latter of Award had been issued to NARA February 8, 2016
7 Letter of Acceptance by NARA February 18, 2016
8 CEB requested to appoint a Technical Committee comprising
representative from Mahaweli Authority, NAQDA, CEA, etc. to
oversee the implementation of Surveying, Translocating, Monitoring
and Relocating of Labeo fisheri
March 28, 2016
9 Awareness programme on Surveying, Translocating, Monitoring and
Relocating of Labeo fisheri
April 11, 2016
10 Permission request from Wild Life for Surveying, Translocation,
Monitoring and Relocating of Labeo fisheri
April 11, 2016
11 Permission granted by Wild life Department only for Surveying the
Labeo fisheri
June 30, 2016
12 First Extension on Bank Guarantee up to 2017/01/16 from
2016/07/16
August 03, 2016
13 First surveying work plan submitted by NARA August 2016
14 Fish surveying started and subsequently the program was postponed. September 27, 2016
to October 24, 2016
15 CEB requested to obtain a report on Effects on Labeo fisheri due to
sediment flushing through the bottom outlet
November 09, 2016
16 Requested permission from Wildlife Department to use non-harmful
fish traps and electro fishing technique
December 10, 2016
21
17 Second surveying work schedule submitted and commenced by
NARA- No fish being recorded
December 19, 2016
to January 13, 2017
18 Third Extension on Bank Guarantee for another six months January 03, 2017
19 Submission of new work schedule by NARA February 7, 2017
20 Permission granted by Department of Wild Life for using non-harmful
fish traps and electro fishing technique
January 16, 2017
21 Rescheduled the surveys dates by NARA, Feb 16,2017 to March
11,2017
February 14, 2017
22 Surveying started with using non-harmful fish traps and electro
fishing technique
Feb 16, 2017 to
March 24, 2017
23 Survey completed, Labeo fisheri found in the river, and the final
survey report yet to submitted
March 31, 2017
Even though the total contract for the Surveying, Translocation, Monitoring and Relocating of Labeo fisheri had being
awarded to NARA, the remaining activities will depend upon the survey findings and with the recommendations of the
Department of Wild life and other stake holders.
9.0 River Flow Data on the Mahaweli River Downstream of the Moragolla Hydropower Plant
As per the Schedule No. 5 of the loan agreement No 3146-SRI between Democratic Socialist Republic Of Sri Lanka
and Asian Development Bank, dated November 20, 2014 it is a mandatory requirement to collect hourly, daily
and monthly flow data on the Mahaweli river downstream of the Moragolla Hydropower Plant tailrace and
the confluence with the Atabage oya for a period of one year to identify the minimum required downstream
environmental river flows during the dry and wet seasons to satisfy the critical habitat requirement of the
Safeguard Policy Statement.
Accordingly, a contract was awarded to Ms. Access Energy (Pvt) Ltd to obtain river flow measurements along
Mahaweli River. Flow measurements were commenced from June 2016 and ongoing. A detail report in
connection with the above is attached in Annexure 1.
10.0 Conclusion and Recommendations
EMP provides the framework for implementing the environmental mitigation, enhancement and
compensation. It is in four parts, comprising EMPs for construction and operation phases, and EMPs for the
two special issues (aquatic and terrestrial ecology) where mitigation is more complex and requires action in
all phases. Each part deals with specific environmental issues, in turn, summarizes the potential impacts and
mitigation to be applied, and assigns responsibility for each action.
At present, the Project is in pre-construction stage due to some unavoidable reasons. In this stage, special
consideration has to be given for the conservation of Labeo fisheri in which fish surveys for identifying their
baseline and establishing control points for monitoring before resuming construction and thereafter surveys
for annual monitoring should be conducted. A contract was awarded to carry out fish survey and
translocation process and the survey work was completed. In addition, another contract was awarded to
obtain river flow data along the Mahaweli River at the location recommended in Loan Agreement.
Mitigation in the construction phase is mainly the responsibility of the contractors and action in the
operational phase is mainly allocated to CEB; but some action is required of both parties, and the design
consultant, in all phases. Construction contracts will require contractors to provide all mitigation and conduct
all monitoring work assigned to them in the EMP and EMoP.
The EMoP provides the mechanism to ensure that: a) all of the actions to provide the mitigation are taken as
set out in the EMP; b) the actions mitigate impacts and protect the environment as intended; and c) residual
impacts of the project are recorded, so that additional mitigation can be provided if any unexpected impacts
occur. The EMoP is in the same four parts as in the EMP and includes: physical and chemical monitoring of
22
emissions; biological surveys of fish, planted vegetation and other features; and social surveys of river users.
In each case the approach to the monitoring is described, including the method, parameters, location,
frequency, and responsibility; plus guidance on threshold levels that would trigger corrective action.
Emissions monitoring is mainly the responsibility of the contractor, to raise awareness of the impacts of
construction activities and the mitigation needed. The remainder of the monitoring is assigned to CEB as the
Project Proponent, although this may be outsourced to specialist consultants and contractors if necessary.
CEB has established a Grievance Redress Mechanism (GRM), to ensure that any concerns, complaints and
grie a es a out the proje t’s e iro e tal perfor a e are re ei ed a d resol ed. This ill ha e t o levels: a) initial complaints received by the contractor or client on site will be resolved in situ where possible
by discussion with the complainant and subsequent agreed action; b) any issues that cannot be resolved
locally will be referred to a Grievance Redress Committee (GRC), comprising senior representatives of local
government and the project agencies (client, contractor, supervision consultant), the local community and
Affe ted Perso s. A o plai ts register ill e ai tai ed i the lie t’s site offi e a d by the GRC. CEB will
inform complainants in writing of decisions made, action to be taken and the program. Decisions by the GRC
will be deemed final, although complainants may take further action through a court of law if they wish.
Implementing EMP for the project was delayed by a few months. However, since commencement of the
construction phase had been shifted, these lapses can be recovered with the immediate startup of relevant
activities of EMP in this phase.
23
Annexure 1
CONSTRUCTION OF MORAGOLLA HYDROPOWER PLANT
ADB LOAN NO. 3146 SRI
River Flow Data on the Mahaweli River Downstream of the
Moragolla Hydropower Plant
24
1. Introduction
1.1 General
Moragolla Hydropower Project (MHP) is one of several hydropower projects identified by the Government of
Sri Lanka (GoSL) to reduce the role of fossil-fuelled power generation, which has outstripped hydropower over
the past 30 years. Returning hydropower to greater prominence would promote sustainable development and
reduce greenhouse gas emissions in line with the National Climate Change Policy, and limit exposure to
fluctuating international fuel prices. The Executing Agency is the Ministry of Power and Renewable Energy
(MoPE) and the Implementing Agency is the Ceylon Electricity Board (CEB).
The project will be located in the upper reaches of the Mahaweli Ganga in the Central Highlands of Sri Lanka,
approximately 22 km south of Kandy City and 130 km north-east of Colombo.
The project involves construction of a 37 m high, 236 m long concrete gravity dam (crest at 550 masl), to
create a 38.5 ha, 1.98 MCM reservoir with a Full Supply Level (FSL) at 548 masl. The concrete spillway
contains 5 radial gates (13m x 15m) designed to pass a 10,000 year flood (6,700 m3/s) with no increase in
FSL. Water will be diverted by an intake just upstream of the dam, into a 2.7 km , 4.7 m Ø underground
headrace tunnel, surge tank and penstock on the left bank, to an above-ground powerhouse and 28 m open-
channel tailrace outfall, through which water will return to the river.
The Project is a daily peak generation power station with an installed capacity of 30.2 MW (2 x 15.1 MW),
having a rated head of 69.0 m and discharge of 50 m3/s. The dam includes a pipe to discharge a constant
“Environmental Flow” (E-flow) of 1.5 m3/s, which will pass through a micro-hydro plant on the right bank,
generating an additional 360 kW.
1.2 River flow measurement
Schedule No. 5 of loan agreement No 3146-SRI between DEMOCRATIC SOCIALIST REPUBLIC OF SRI
LANKA and ASIAN DEVELOPMENT BANK, dated November 20, 2014 has specified that CEB shall
undertake, to the satisfaction of ADB, to collect hourly, daily and monthly flow data on the Mahaweli river
downstream of the Moragolla Hydropower Plant tailrace and the confluence with the Atabage oya for a period
of one year to identify the minimum required downstream environmental river flows during the dry and wet
seasons to satisfy the critical habitat requirement of the Safeguard Policy Statement.
CEB shall also ensure that such minimum required downstream environmental river flows are maintained
following the completion of the Moragolla Hydropower Plant to avoid any measurable adverse impact on the
habitat of the endangered Green Labeo fish.
In order to meet the above requirement, a contract was awarded to Access Energy (Pvt) Ltd. No. 278, Union
Place, Colombo 02, Sri Lanka to measure the hourly river flow on the Mahaweli river downstream of the
Moragolla Hydropower Plant tailrace and the confluence with the Atabage oya for a period of one year starting
from June 2016 to May 2017.
1.3 The river flow measurement location
Access Energy (Pvt) Ltd. No. 278, Union Place, Colombo 02, Sri Lanka was awarded the contract to measure
the hourly river flow on the Mahaweli river downstream of the Moragolla Hydropower Plant tailrace and the
confluence with the Atabage oya for a period of one year starting from June 2016 to May 2017.
Fig 1.1 shows the location at the Mahaweli river where flow measurement were carried out by the contactor.
25
Fig 1.1 River flow measurement location
Fig 1.2 and 1.3 shows the location of the data logger and pressure transducer installed underwater
respectively by Access Energy Pvt(Ltd) for the measurement of the river flow.
Fig 1.2 Data logger Fig 1.3 Pressure Transducer location
The flow measuring system is based on the indirect discharge measurement technology. In this indirect
method only the water level is recorded and the discharge is computed by reference to a rating curve relating
the water level with the discharge across the section. A hand held current meter which works on magneto-
induction principle and having no moving parts was used to develop a rating curve for discharge
measurement.
Data
Logger
26
2.0 Flow Data
2.1 Hourly Flow Data
As shown in fig 1.1, the Kotmale power station discharge is released to the Mahaweli River upstream of the
flow measuring location. In addition the water from the Atabage Oya also connected to the Mahaweli River
upstream of this measuring location. The water discharge from the Kotmale Power Station when in operation,
is an additional discharge to the natural flow of the Mahaweli River. Therefore this flow rate need to be
deducted from the measured river flow data in order to identify the natural flow rate of the river.
In order to calculate the natural flow of the river, the hourly flow rates from Kotmale discharge was obtained in
parallel to the hourly flow measurement data. Table 2.1.1 to 2.1.9 shows the hourly natural flow rate of the
Mahaweli River, after deducting Kotmale discharge, for the period from June 2016 to February 2017.
27
Table 2.1.1 Hourly Flow Data - June 2016
Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 50.80 46.88 45.60 44.60 40.20 39.40 53.95 52.80 57.50 51.52 65.00 56.56 55.52 55.40 48.10 42.40 49.36 47.51 43.35 46.44 46.50 38.69 50.66 37.40
2 53.20 27.20 32.00 34.80 33.24 31.44 35.36 35.28 32.64 27.44 40.43 33.00 28.37 37.10 33.80 27.00 28.40 26.40 34.00 12.80 21.09 12.46 31.68 41.00
3 33.40 30.40 25.95 31.90 30.40 30.40 24.00 23.00 22.16 18.60 23.44 12.52 26.00 24.40 21.08 24.32 16.60 29.64 24.40 16.36 32.60 33.00 27.16 32.56
4 56.40 29.24 28.36 30.60 21.00 24.96 21.60 30.00 20.24 18.29 27.28 30.56 29.90 42.30 31.93 42.86 36.20 62.40 52.75 46.80 59.80 65.88 91.68 106.80
5 90.20 80.30 74.45 62.80 54.60 50.20 43.20 40.56 44.00 42.40 38.40 33.60 31.80 29.16 33.04 33.00 31.36 32.96 33.96 12.16 32.40 41.30 24.96 48.40
6 37.52 38.56 36.16 35.65 35.65 28.40 24.01 35.20 29.24 20.60 23.13 27.74 30.12 30.03 32.51 24.76 33.00 35.72 32.04 12.20 24.14 20.49 22.35 24.16
7 53.60 21.44 24.20 22.08 22.60 20.16 24.40 31.72 23.60 56.87 22.76 30.90 28.99 37.40 23.84 29.30 14.45 24.45 20.00 10.36 31.20 13.60 49.75 30.43
8 29.70 31.16 31.89 30.43 31.16 28.92 29.70 28.14 28.14 13.32 23.75 23.00 28.36 29.76 36.27 28.66 28.36 31.20 22.65 29.20 33.16 28.64 34.15 29.18
9 46.00 32.62 32.62 31.16 29.70 28.14 24.21 25.20 29.70 18.20 23.98 23.69 20.34 26.41 24.04 17.48 24.00 30.04 15.36 27.80 22.36 29.00 33.44 45.20
10 37.00 32.62 31.89 31.16 29.70 19.30 25.60 31.15 37.75 27.86 21.90 19.30 24.50 28.90 17.80 26.41 27.91 31.90 30.40 21.20 33.00 50.50 37.00 35.54
11 35.54 35.54 31.89 32.62 30.43 31.16 14.10 28.15 29.65 35.40 30.40 28.20 25.78 25.55 24.33 24.97 20.86 24.80 24.16 10.92 33.16 20.12 22.71 25.90
12 27.36 24.24 25.02 23.46 25.80 24.24 25.80 25.80 27.36 26.58 26.58 25.80 25.02 24.24 24.24 24.24 22.68 24.24 11.19 18.84 29.24 24.97 34.08 30.43
13 35.54 45.25 56.00 60.80 58.40 71.20 42.64 49.76 48.25 41.60 38.48 38.15 42.08 44.96 48.68 40.75 36.60 57.50 50.16 42.35 63.00 54.40 54.80 64.00
14 51.25 47.50 47.50 46.00 43.75 33.11 33.16 37.60 38.88 31.16 37.40 33.96 36.40 33.60 30.56 39.60 29.76 29.00 33.05 17.64 30.20 19.28 30.45 28.90
15 32.62 30.43 32.62 33.35 31.89 33.35 20.80 33.40 34.90 20.84 32.56 24.64 30.16 31.72 26.00 22.24 27.96 32.60 23.20 20.76 16.00 17.60 32.36 33.05
16 17.24 28.14 26.58 27.36 28.14 25.80 28.14 27.36 26.58 19.65 16.64 13.96 24.04 10.96 20.64 24.92 18.20 24.40 17.60 40.20 21.24 18.56 38.60 22.20
17 44.50 25.02 23.46 22.68 24.24 17.75 18.40 19.16 22.56 17.40 15.80 15.08 23.28 25.80 11.44 10.96 18.00 23.60 24.40 22.20 25.00 53.00 20.40 31.89
18 27.36 28.14 29.70 28.14 26.58 27.36 16.20 19.52 11.00 16.80 26.20 24.20 21.80 25.60 28.90 38.00 44.40 44.40 54.00 89.71 99.20 81.20 54.00 48.25
19 42.25 40.00 37.75 35.54 34.08 31.89 33.35 31.89 31.16 29.70 30.43 28.92 27.36 28.14 28.14 26.58 27.36 27.36 26.58 17.76 27.60 23.46 28.15 29.65
20 29.70 30.43 31.89 30.43 30.43 26.36 28.20 31.20 26.80 32.92 22.76 14.88 24.20 14.56 16.68 25.92 31.32 27.05 28.55 30.11 29.59 26.20 27.80 33.04
21 28.40 28.20 28.66 26.64 27.56 29.64 15.96 32.36 18.40 33.24 39.84 39.16 43.00 44.04 45.20 39.84 41.08 41.80 37.04 24.84 36.52 41.24 47.52 47.84
22 80.79 76.00 100.16 94.00 83.52 84.76 103.76 85.55 79.29 91.76 100.16 103.76 101.36 101.36 91.24 97.24 104.64 97.24 92.40 88.60 97.60 82.95 66.96 34.15
23 12.54 25.02 25.80 25.80 24.24 25.02 24.24 24.24 20.30 24.88 24.96 15.36 19.56 22.64 21.04 23.68 23.00 21.57 19.49 23.40 18.56 21.20 26.70 22.15
24 37.75 36.27 37.00 37.75 46.75 21.40 15.50 13.30 11.45 10.41 21.40 11.00 17.35 22.90 19.95 20.35 16.31 21.40 21.40 21.40 31.89 21.90 21.90 23.46
25 20.72 22.68 20.72 20.72 22.68 20.72 21.90 22.15 12.55 22.15 19.20 17.00 18.50 18.50 25.02 20.72 20.72 18.36 20.72 19.30 10.24 21.80 20.16 19.94
26 34.81 18.38 20.36 17.86 22.15 19.21 14.95 20.01 16.66 16.95 19.21 19.21 19.94 17.02 19.94 18.48 18.48 19.21 18.48 20.67 17.02 19.21 19.54 15.50
27 18.36 16.00 15.50 18.36 16.00 16.00 18.36 19.89 17.81 11.16 11.80 13.65 13.41 25.02 15.50 16.00 15.50 15.00 16.00 16.29 11.44 14.60 12.96 13.28
28 25.15 18.48 17.18 14.50 15.50 17.18 14.64 36.24 19.21 18.17 17.46 16.65 17.96 29.65 22.68 24.24 23.46 21.90 22.68 14.10 25.36 23.36 22.68 24.24
29 22.68 23.46 25.02 23.46 24.24 37.00 20.00 25.44 19.94 21.39 20.67 19.94 19.95 15.55 14.16 14.45 18.15 23.70 12.50 22.00 22.00 24.00 36.20 22.68
30 17.18 15.50 15.50 17.18 15.50 15.00 13.28 16.50 15.78 13.80 14.40 16.20 15.20 15.50 27.33 23.08 20.52 28.59 19.36 27.28 16.72 19.48 19.80 28.90
Day
Flow Rate m3/sec
Time in Hours
28
Table 2.1.2 Hourly Flow Data - July 2016Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 25.80 15.50 15.00 14.50 15.00 15.00 12.88 16.30 16.24 13.29 14.96 7.60 17.16 11.83 16.29 14.83 14.83 17.02 16.29 14.64 18.55 15.56 14.83 14.10
2 14.50 12.80 14.00 13.50 13.50 14.50 13.18 13.56 9.52 7.40 17.16 7.60 14.85 19.95 16.29 12.55 12.55 12.55 11.82 22.90 41.60 34.15 29.70 12.10
3 11.40 13.50 12.10 12.80 12.80 12.80 5.07 10.88 11.11 10.41 9.95 9.66 9.95 7.70 17.02 11.50 11.50 13.27 11.24 12.80 20.16 11.80 20.44 25.02
4 11.40 11.40 13.50 11.40 11.40 7.86 11.28 11.73 5.15 19.30 9.64 8.40 14.84 16.40 8.91 9.36 12.20 15.20 10.46 10.96 7.32 17.80 13.50 12.80
5 11.40 10.70 12.10 11.40 10.00 10.70 10.20 11.76 11.76 5.45 9.60 11.56 10.88 18.12 10.41 11.20 12.26 11.05 8.45 7.35 10.30 11.76 11.76 11.76
6 10.98 13.06 11.09 7.86 11.91 9.65 6.00 11.80 11.05 11.05 5.80 6.60 12.60 13.32 11.76 10.98 12.54 16.29 9.42 9.55 11.00 10.52 13.35 5.07
7 8.12 8.91 8.90 11.76 13.32 9.54 14.85 11.80 7.81 8.76 14.16 9.14 9.77 14.05 9.25 5.49 6.80 15.37 8.56 9.25 6.94 11.33 11.24 9.30
8 9.30 8.60 9.30 7.90 7.90 8.60 8.63 13.32 9.16 8.38 11.50 9.94 6.40 5.56 6.16 8.90 11.05 11.80 9.55 9.14 9.44 8.90 12.55 11.76
9 10.20 8.90 12.23 6.30 6.62 17.75 12.54 10.20 14.10 8.90 8.90 5.51 12.14 13.06 8.59 8.91 12.54 15.56 12.23 12.14 15.88 17.33 12.87 18.36
10 19.54 22.68 25.80 30.43 31.16 31.89 35.54 40.75 40.00 37.75 37.75 39.25 40.00 45.25 51.25 53.60 50.50 48.25 50.50 43.76 49.20 46.24 45.20 40.75
11 37.75 34.08 32.62 29.70 28.92 26.58 25.80 25.80 24.24 24.24 14.10 20.67 18.45 19.94 21.40 13.41 15.95 13.70 18.17 7.00 10.40 14.08 17.80 16.19
12 20.36 18.90 16.60 19.20 10.65 25.14 15.92 18.55 16.18 16.24 10.32 14.80 16.40 15.60 17.80 20.00 20.67 15.15 17.02 10.18 15.20 15.95 25.95 17.03
13 19.20 16.20 15.47 14.81 18.10 9.95 15.56 15.37 13.35 7.20 21.60 9.25 13.81 20.56 9.20 17.97 14.40 14.80 14.05 15.67 22.20 14.52 14.42 16.00
14 15.00 14.50 16.00 18.36 16.00 16.00 7.70 17.02 16.92 8.91 14.20 8.84 7.60 15.40 20.67 13.79 15.25 14.83 11.50 14.88 23.20 14.05 25.28 13.32
15 16.29 14.10 11.51 13.60 13.60 16.95 17.70 16.40 9.90 9.90 12.79 12.04 17.75 15.36 10.65 14.00 15.56 14.83 14.01 17.70 16.61 15.15 15.88 12.96
16 15.36 13.69 9.74 7.59 9.12 17.34 20.05 17.05 14.22 7.24 6.64 8.96 6.96 5.20 12.08 11.75 12.50 22.49 8.91 17.16 19.52 22.80 14.74 13.28
17 14.84 15.91 6.55 12.66 10.68 9.15 5.80 13.28 17.75 6.11 10.00 6.80 7.68 17.44 5.07 10.13 13.28 12.50 6.84 9.15 10.99 18.48 13.27 14.42
18 14.42 13.08 18.48 14.01 11.75 13.60 12.40 11.85 5.15 11.56 16.20 8.90 18.00 8.50 13.12 6.12 9.40 9.20 13.00 10.75 12.76 13.56 23.76 9.42
19 10.68 33.60 7.35 9.54 8.90 12.87 17.02 11.51 10.58 15.16 15.33 15.76 5.80 5.49 6.40 6.52 10.00 8.64 12.64 14.16 13.60 11.20 9.43 14.21
20 6.56 9.95 9.95 11.51 8.18 15.36 5.96 13.01 15.12 5.80 14.04 9.52 8.72 12.36 14.85 8.96 13.64 13.64 15.95 7.60 9.60 8.10 14.73 8.90
21 7.34 15.15 9.32 9.94 8.91 12.25 6.36 13.76 9.16 10.64 10.20 7.80 11.27 10.52 13.18 22.25 9.54 10.20 13.32 9.42 8.64 8.64 7.08 8.64
22 8.80 6.56 14.10 7.34 10.36 7.03 9.16 9.94 7.77 4.43 5.27 17.04 7.41 8.80 4.51 7.56 8.44 14.05 9.90 15.08 10.58 7.41 8.16 8.90
23 9.94 7.66 9.16 7.08 6.30 14.82 14.20 8.44 6.89 13.80 5.50 5.20 9.42 13.76 6.00 9.25 5.84 12.60 5.44 7.36 5.20 14.80 11.50 5.78
24 8.07 10.20 7.34 8.49 7.34 14.86 5.52 16.76 5.50 11.45 12.95 4.16 8.72 15.89 15.26 9.90 11.82 5.48 8.96 14.64 14.64 8.40 5.76 19.30
25 14.75 17.75 13.69 18.16 14.01 6.94 7.76 15.56 9.90 20.80 16.04 21.91 15.47 17.75 11.82 6.73 19.03 16.82 17.75 14.63 8.73 16.71 15.56 7.03
26 14.74 10.16 11.82 8.81 5.89 7.45 7.40 11.05 5.90 8.24 9.44 7.56 16.60 15.60 16.44 12.13 11.82 10.68 7.76 15.14 9.77 29.65 8.90 14.83
27 12.54 13.32 13.32 9.22 9.95 8.71 8.24 13.80 6.01 14.40 6.54 5.04 5.08 16.01 6.65 15.20 15.55 18.26 9.16 11.04 9.66 8.91 8.90 7.08
28 7.76 11.51 13.32 9.22 11.10 16.70 9.64 8.12 8.81 6.62 10.05 15.60 6.08 9.71 5.20 7.84 7.60 15.49 6.08 5.20 14.56 15.12 10.67 9.94
29 13.06 7.86 12.28 9.63 8.08 15.03 10.06 12.55 10.16 14.96 7.05 6.30 4.52 6.60 5.55 6.84 6.00 8.32 6.94 15.36 11.62 16.41 5.55 14.10
30 5.89 7.55 15.46 9.94 16.29 11.09 13.28 16.29 10.68 16.29 17.34 26.00 41.20 50.20 50.00 44.40 41.20 34.90 34.61 27.64 41.20 33.11 28.90 28.92
31 25.80 24.24 22.68 21.90 21.90 19.54 14.40 19.94 19.21 19.94 18.36 17.75 15.50 15.78 20.36 17.46 20.99 16.54 17.69 13.48 10.92 23.20 31.15 21.81
Day
Flow Rate m3/sec
Time in Hours
29
Table 2.1.3 Hourly Flow Data - August 2016Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 17.18 15.00 14.50 15.00 14.50 14.50 11.31 17.55 7.77 17.02 15.47 9.67 9.96 14.01 13.59 11.82 12.55 13.59 12.54 7.06 17.20 15.56 14.83 6.72
2 36.27 8.07 10.67 13.38 9.54 13.91 11.51 10.88 5.80 6.55 13.18 6.55 12.44 5.26 7.35 9.95 6.62 10.78 5.90 7.88 15.55 13.47 12.04 15.50
3 9.30 9.30 9.30 8.60 8.60 8.60 11.40 14.63 5.22 5.16 4.70 5.45 6.03 7.53 7.04 5.58 4.70 6.20 9.42 10.78 10.05 9.30 7.90 7.20
4 6.50 7.20 8.60 7.90 7.20 7.20 8.60 7.86 7.86 6.21 6.55 5.80 5.07 16.51 9.42 7.34 7.45 13.69 8.64 9.54 11.75 17.34 31.89 25.80
5 27.36 9.94 5.58 8.90 5.16 6.10 6.52 5.52 8.38 5.80 7.30 8.05 6.55 14.83 7.20 6.50 5.99 5.99 5.99 14.00 9.23 7.08 6.24 6.24
6 7.20 6.24 5.99 4.04 7.86 5.26 7.08 7.08 7.86 6.82 8.64 8.64 6.30 7.08 8.90 5.16 6.30 7.08 7.60 5.52 6.04 6.56 8.64 9.42
7 10.30 5.78 7.08 5.12 7.60 13.69 9.16 10.98 7.86 4.74 6.30 4.74 3.44 3.44 5.00 8.38 7.60 10.72 9.42 5.69 7.88 9.64 5.78 7.86
8 13.50 5.47 5.22 5.22 5.47 5.47 5.22 5.22 5.47 6.30 4.75 5.48 5.33 6.26 5.26 5.52 6.04 1.58 5.12 5.33 5.55 10.72 6.30 7.86
9 4.22 21.90 5.99 4.96 4.96 5.22 1.58 2.76 6.30 6.83 4.72 6.92 4.80 5.48 5.00 5.78 4.22 3.94 4.98 5.78 7.86 7.08 10.00 5.99
10 5.99 5.99 6.24 5.99 5.99 5.99 5.73 6.24 5.73 2.14 7.08 5.16 5.06 4.43 6.04 3.70 5.26 5.26 2.14 5.50 11.80 10.20 10.70 5.22
11 4.96 4.96 5.22 4.96 5.22 4.96 4.96 4.96 4.70 10.98 5.26 4.48 4.43 5.52 6.40 4.00 5.52 4.75 4.58 4.80 5.04 4.72 11.76 5.47
12 4.70 4.70 4.70 4.44 4.70 4.70 4.44 4.44 4.44 4.22 5.78 5.26 5.26 5.12 5.26 6.82 5.52 5.26 5.12 3.29 6.14 6.14 4.22 6.56
13 6.21 4.74 3.56 6.30 1.58 6.56 6.56 5.26 5.52 3.44 5.52 4.48 6.04 3.70 4.74 4.74 4.22 5.26 5.99 5.85 8.05 8.64 11.76 18.36
14 5.22 5.22 4.96 5.22 5.47 5.47 5.12 4.34 6.30 4.74 6.04 6.04 6.30 7.08 8.90 6.30 8.64 6.30 8.64 8.32 10.32 6.52 5.32 16.00
15 9.30 7.90 10.00 10.00 11.40 10.70 10.00 10.70 9.30 11.76 9.42 9.42 9.95 8.91 9.42 9.68 10.98 10.20 18.36 9.90 11.28 14.97 23.20 34.15
16 39.25 27.36 25.02 22.68 20.72 19.54 17.18 15.50 17.18 17.44 18.17 16.92 9.40 18.12 21.00 22.16 14.35 17.75 15.46 13.69 16.71 13.50 12.10 12.10
17 13.50 11.40 11.40 12.10 12.80 10.70 12.54 7.03 7.76 13.32 10.20 10.36 9.54 28.14 8.12 9.95 9.32 9.22 11.72 10.68 11.41 12.14 8.64 7.90
18 7.90 8.60 7.20 7.20 7.20 6.50 7.90 6.50 6.50 15.15 10.68 13.69 9.42 7.86 6.30 7.08 7.08 6.30 7.08 6.51 6.65 10.20 8.60 7.90
19 7.90 7.90 7.90 6.50 6.50 7.86 7.76 14.11 6.30 4.43 5.16 5.16 6.20 6.56 6.82 8.60 7.08 7.86 5.00 5.16 8.38 6.82 6.56 6.30
20 3.70 26.58 5.99 5.99 5.73 1.58 6.30 4.08 5.78 5.16 10.98 3.96 4.74 6.82 7.60 8.12 7.03 10.20 5.26 5.89 13.65 7.86 9.42 5.73
21 5.47 3.60 4.22 6.82 3.18 3.96 7.60 7.08 5.26 5.99 5.73 5.22 5.22 17.18 22.68 35.54 34.81 36.27 31.16 51.25 44.50 31.16 20.72 5.73
22 5.99 5.99 5.99 5.47 5.47 5.47 5.99 5.47 5.47 4.75 4.02 5.48 4.02 5.00 5.73 5.99 50.50 62.40 58.40 37.20 44.40 38.80 35.54 29.70
23 25.02 22.68 19.54 18.36 16.00 15.00 15.50 15.50 15.50 15.50 17.18 39.60 54.80 52.80 48.25 52.00 61.60 68.00 72.00 77.48 79.16 72.50 60.76 56.44
24 45.80 28.68 48.56 43.45 36.80 43.04 33.96 27.33 23.44 12.96 17.20 19.40 19.20 16.20 23.32 19.52 12.36 13.64 12.92 22.80 20.92 7.05 19.84 25.90
25 16.31 16.66 19.63 11.82 15.88 16.91 18.10 22.54 21.16 12.56 11.32 10.20 10.36 27.44 19.20 20.60 17.76 19.56 11.76 20.80 19.80 15.88 22.15 8.45
26 10.71 14.00 15.50 15.47 16.71 17.02 8.40 11.82 15.91 7.36 17.20 6.20 8.96 6.82 9.44 22.72 7.46 14.80 13.12 17.80 18.90 20.64 13.64 17.04
27 15.85 33.35 37.75 38.50 38.50 37.00 5.80 17.02 15.15 20.76 8.80 12.87 11.31 14.42 9.85 11.41 10.27 13.48 11.30 29.40 28.37 35.65 35.96 33.60
28 28.15 17.75 16.29 16.29 17.58 22.61 14.12 16.80 15.52 19.16 12.00 9.96 10.80 9.71 11.20 9.60 6.64 5.64 12.88 14.48 16.28 8.60 15.55 18.24
29 10.00 8.49 10.68 9.63 10.30 11.74 10.75 10.08 9.96 11.32 18.80 4.22 5.60 11.85 9.96 8.36 11.79 11.28 14.85 13.96 14.45 10.41 11.40 10.12
30 16.29 11.92 17.43 5.52 16.29 9.42 9.63 5.16 5.84 10.64 8.15 5.90 5.04 5.32 11.05 8.61 7.44 7.00 13.76 12.56 13.70 11.04 15.20 10.76
31 16.92 19.21 16.09 15.15 20.67 18.48 14.74 10.98 18.48 8.16 6.94 10.48 12.49 14.40 7.67 7.03 11.41 9.22 9.95 22.20 16.76 16.01 9.95 10.68
Day
Flow Rate m3/sec
Time in Hours
30
Table 2.1.4 Hourly Flow Data - September 2016Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 17.75 9.95 13.32 10.68 12.87 14.75 10.27 20.67 15.85 13.54 21.80 14.00 15.57 16.71 15.88 13.04 10.04 5.04 2.40 9.80 7.11 15.60 13.70 12.60
2 10.68 5.99 14.11 11.50 4.02 14.10 13.80 14.22 4.45 7.40 8.20 6.40 11.80 12.60 6.16 22.24 34.56 96.52 135.53 131.70 114.48 94.80 80.56 64.15
3 39.60 44.56 35.00 42.80 27.36 76.00 23.20 32.60 16.56 16.56 18.20 12.40 16.40 26.56 12.60 24.00 7.72 18.80 23.60 13.84 12.60 16.92 16.28 20.48
4 9.48 16.88 18.10 19.20 13.60 7.99 3.76 16.24 16.41 21.40 10.04 9.20 11.72 9.65 16.60 6.76 17.16 15.24 7.20 6.56 8.40 17.16 20.36 24.80
5 21.84 22.66 18.51 16.37 19.20 10.64 10.80 15.80 8.20 4.96 11.20 17.00 13.44 10.48 12.40 17.60 40.20 14.10 10.00 14.52 10.96 14.20 21.36 5.36
6 10.35 9.63 10.47 10.98 4.02 5.27 8.36 16.61 8.08 5.20 2.60 14.72 3.92 4.72 9.60 3.12 3.60 4.80 12.16 3.64 6.19 13.00 3.01 3.16
7 7.98 7.59 5.26 5.99 5.89 14.04 23.69 4.87 4.96 5.20 2.04 5.76 16.36 13.64 6.01 7.56 5.36 11.92 6.64 12.00 2.90 2.08 29.68 23.65
8 10.46 25.80 29.70 26.58 32.62 31.89 61.60 25.02 31.89 7.20 6.50 7.20 6.24 6.24 6.24 6.24 6.50 6.24 6.24 5.99 6.24 5.99 6.24 6.50
9 6.50 5.99 6.24 6.24 7.20 6.24 6.24 5.99 6.24 5.73 6.24 5.73 5.73 5.73 5.47 6.24 5.99 5.99 5.99 5.99 5.99 6.24 5.99 5.99
10 5.73 5.99 5.73 5.73 5.73 5.73 5.99 5.99 6.24 5.99 5.73 5.99 5.47 5.99 5.47 5.22 5.47 5.47 5.73 5.99 5.73 5.47 5.47 5.22
11 4.96 5.73 5.22 5.22 5.22 4.96 5.22 5.73 5.22 5.22 5.47 5.47 5.22 5.22 4.96 4.96 5.22 4.70 4.96 5.47 4.96 4.70 4.96 4.96
12 4.96 4.70 5.22 4.70 4.96 4.70 4.96 4.70 5.47 4.96 4.70 4.44 4.44 4.70 4.96 4.70 5.22 4.70 4.70 4.70 5.22 4.70 4.70 4.70
13 4.70 4.44 4.70 4.70 4.70 4.70 4.70 4.70 4.96 4.96 4.44 4.44 4.44 4.70 5.22 4.44 4.70 4.70 4.96 4.96 5.47 4.96 4.96 4.70
14 4.70 4.70 4.70 4.96 4.70 4.70 4.70 4.70 4.44 4.70 4.70 4.70 4.70 4.70 4.70 4.44 4.70 9.30 12.10 12.10 12.10 11.40 13.50 12.80
15 12.80 12.80 12.80 12.10 12.80 13.50 12.80 12.80 12.80 12.80 12.80 12.10 12.80 12.80 12.80 12.10 12.10 10.00 9.30 9.30 9.30 9.30 11.40 11.40
16 12.80 13.50 12.80 12.10 12.10 12.10 10.70 10.70 10.00 10.70 10.00 8.60 8.60 8.60 7.90 8.60 7.90 8.60 7.90 7.90 7.90 7.20 7.90 8.60
17 8.60 7.90 7.20 7.90 7.90 8.60 9.30 9.30 8.60 8.60 8.60 7.90 8.60 7.90 7.90 7.90 9.30 8.60 9.30 8.60 8.60 8.60 8.60 9.30
18 9.30 8.60 8.60 8.60 7.90 8.60 8.60 8.60 7.90 7.20 7.20 7.20 7.20 8.60 7.90 8.60 8.60 9.30 10.70 11.40 12.80 15.00 15.50 15.00
19 15.00 14.00 13.50 12.80 12.10 11.40 10.70 10.70 10.00 11.40 10.00 9.30 9.30 9.30 8.60 8.60 8.60 7.90 7.90 7.90 8.60 8.60 7.90 8.60
20 8.60 7.90 7.90 7.90 7.90 8.60 7.90 7.90 7.90 7.20 8.60 7.20 7.90 7.20 7.20 6.50 7.90 6.50 6.50 7.20 6.50 6.50 6.50 7.90
21 7.20 6.50 6.50 7.20 6.50 6.50 6.50 7.20 7.20 6.50 6.50 6.50 6.50 6.50 6.50 6.50 6.24 6.50 6.50 6.50 6.50 6.50 7.20 6.50
22 6.24 6.24 6.50 7.20 6.50 6.24 7.20 6.50 6.50 6.24 6.50 5.99 6.24 6.24 6.24 6.24 6.24 6.50 6.50 6.24 6.50 6.24 6.24 6.24
23 6.24 6.24 5.99 6.24 5.99 6.24 6.24 5.99 7.20 6.24 6.24 5.99 6.24 6.24 5.99 6.24 6.24 6.24 5.99 5.99 5.99 5.99 5.99 6.50
24 6.24 5.99 5.99 6.24 6.24 5.99 5.99 6.24 6.24 6.24 5.99 5.73 5.73 5.73 6.50 5.73 5.73 5.99 5.73 5.73 5.73 5.47 6.50 5.99
25 5.99 5.99 5.99 5.73 5.99 5.99 5.99 6.50 5.99 5.73 5.73 5.47 5.47 5.47 5.47 6.24 5.47 5.47 5.73 5.99 5.73 5.73 5.73 5.73
26 5.73 6.24 5.47 5.47 5.47 5.73 5.73 5.73 5.73 5.73 5.47 5.73 5.73 5.73 5.73 5.73 5.47 5.99 5.99 5.47 5.47 5.47 5.47 5.22
27 5.22 5.47 5.22 5.22 5.47 5.99 5.47 5.47 5.47 5.47 5.47 5.73 5.47 5.47 5.47 5.99 5.47 5.47 5.22 5.22 5.47 5.73 5.47 5.47
28 5.73 5.47 5.47 5.73 5.73 5.73 5.47 5.99 5.47 5.73 5.47 5.47 5.99 5.73 5.99 5.73 5.73 5.99 5.73 5.73 5.73 5.99 5.73 5.73
29 5.99 5.73 5.99 5.99 5.99 5.99 5.99 6.24 5.99 5.99 5.99 5.99 5.73 5.99 5.73 6.24 5.99 5.99 6.24 6.24 6.24 6.50 6.50 7.20
30 7.20 7.20 7.20 7.90 9.30 14.00 14.00 13.50 15.50 18.36 19.54 19.54 23.46 24.24 23.46 21.90 20.72 19.54 18.36 16.00 15.50 15.00 15.00 14.50
Day
Flow Rate m3/sec
Time in Hours
31
Table 2.1.5 Hourly Flow Data - October 2016
Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 17.18 16.00 15.00 16.00 17.18 16.00 15.50 15.50 16.00 15.00 14.50 14.00 14.00 14.00 15.00 13.50 13.50 13.50 13.50 12.10 12.80 12.10 12.80 12.80
2 13.50 12.10 12.10 11.40 11.40 12.10 12.80 12.10 13.50 12.10 11.40 11.40 11.40 12.10 11.40 11.40 12.10 10.70 10.70 11.40 10.70 10.70 10.70 10.70
3 10.70 12.10 11.40 11.40 10.70 10.70 11.40 11.40 11.40 10.70 11.40 10.70 10.70 10.70 10.00 10.70 10.00 10.00 10.00 10.00 10.70 10.00 10.00 10.00
4 9.30 10.00 10.00 9.30 9.30 9.30 9.30 10.00 10.00 9.30 10.00 9.30 10.00 9.30 9.30 9.30 10.00 9.30 12.80 7.70 8.97 9.72 5.91 3.20
5 7.08 21.90 5.99 5.22 5.22 5.47 4.96 4.70 4.44 4.19 4.44 4.44 4.19 10.00 4.96 4.19 4.19 4.19 4.19 4.54 3.18 4.70 4.19 4.19
6 3.93 4.19 3.79 3.93 3.93 3.79 5.73 9.30 4.44 4.19 3.93 3.93 4.19 4.96 4.19 4.19 4.44 4.19 3.93 4.35 3.60 3.60 19.54 4.44
7 3.93 3.79 3.93 3.79 3.79 3.93 4.19 4.19 3.93 3.79 3.79 3.79 3.64 3.64 3.36 3.50 3.64 3.64 3.79 4.43 2.15 2.15 1.58 4.44
8 3.79 3.64 3.79 3.79 3.79 3.93 3.79 3.93 3.79 3.79 3.64 3.64 3.64 3.50 3.50 3.64 3.50 3.36 3.50 3.70 6.50 3.79 3.64 3.50
9 3.50 3.50 3.64 3.64 3.64 3.64 3.64 3.64 4.44 3.93 3.79 3.79 3.79 3.79 3.93 3.93 4.19 4.19 4.19 4.96 4.70 4.70 4.70 4.70
10 4.70 4.44 4.70 4.19 4.44 4.44 4.19 4.70 4.19 3.93 4.19 3.93 3.93 3.79 1.48 4.40 3.20 3.99 5.15 3.65 5.10 5.90 5.90 5.90
11 4.41 5.91 4.74 4.74 6.04 3.70 7.04 4.22 12.10 4.70 4.70 4.19 4.19 3.93 3.79 3.93 3.93 3.93 3.79 6.30 1.58 7.08 6.56 4.60
12 3.70 3.70 4.48 6.30 15.26 14.10 8.07 6.30 5.26 5.99 4.70 4.44 4.19 4.19 3.93 3.93 2.50 5.89 5.12 6.36 6.82 5.99 4.44 4.19
13 3.93 4.44 4.19 4.19 3.93 4.06 4.97 18.36 4.70 4.44 4.44 4.19 3.93 3.93 3.93 3.93 4.70 3.93 3.93 4.34 8.12 10.00 4.96 4.96
14 5.47 7.20 7.90 10.70 15.00 17.18 17.04 43.00 20.72 18.36 18.36 16.00 15.50 16.00 14.50 14.00 13.50 12.80 12.80 16.50 11.93 14.00 13.17 11.09
15 11.40 10.00 8.60 8.60 8.60 9.30 19.84 12.54 15.00 9.30 9.30 8.60 1.40 19.20 10.08 14.85 17.18 7.90 2.52 17.36 11.16 13.60 17.18 11.40
16 10.70 9.30 12.10 11.76 14.10 12.14 12.23 27.36 10.70 8.60 7.90 8.60 7.20 6.24 6.50 6.50 5.27 6.55 4.99 4.92 6.44 6.20 13.30 17.02
17 12.02 9.42 10.98 10.72 9.94 8.08 1.44 32.65 9.30 7.20 6.50 5.80 5.40 5.28 12.05 13.24 15.36 20.53 12.92 22.20 8.00 15.40 26.56 16.47
18 12.20 13.06 9.94 8.38 8.38 7.06 11.53 17.52 4.12 15.26 15.81 16.90 20.36 16.00 12.15 14.75 18.95 18.16 14.78 38.32 23.00 13.80 22.56 6.60
19 18.50 12.43 17.81 14.01 4.96 7.92 7.00 12.92 4.55 16.37 21.54 8.31 19.47 19.76 5.68 13.24 23.80 16.60 1.96 22.20 11.20 20.72 15.00 19.21
20 12.54 13.32 12.54 12.28 13.06 5.16 13.79 15.00 10.00 18.90 13.27 1.86 4.76 24.72 17.22 9.40 13.52 13.04 14.52 12.46 8.20 11.44 27.36 10.00
21 7.20 7.20 7.90 7.20 7.20 6.50 3.70 13.50 8.60 7.20 5.16 10.29 12.60 8.49 13.69 8.49 15.10 14.10 11.20 16.80 18.55 13.64 13.80 8.81
22 12.54 12.28 12.54 12.54 14.10 1.52 14.01 15.14 5.80 4.85 11.51 5.80 13.28 6.30 11.51 11.09 12.54 13.32 6.62 14.20 21.60 11.50 10.00 14.00
23 22.68 23.46 21.90 21.90 18.36 14.10 19.65 19.03 10.65 16.19 14.00 14.00 12.76 18.79 20.67 11.72 15.85 18.50 17.80 18.48 17.96 19.80 24.24 22.68
24 22.68 21.90 20.72 19.54 18.36 19.54 10.20 23.46 17.18 15.50 16.00 16.00 16.00 19.54 37.00 47.50 52.00 56.80 67.20 95.45 184.30 245.50 229.00 193.00
25 151.48 117.00 91.40 73.60 61.60 56.00 50.50 44.50 43.75 40.00 37.00 36.27 33.35 32.62 32.62 34.90 28.92 28.14 29.70 40.75 27.36 28.14 27.36 27.36
26 31.89 33.35 35.54 37.00 34.08 31.89 31.16 29.70 27.36 25.80 25.02 23.46 22.68 23.46 20.72 20.72 20.72 20.72 20.72 19.54 18.36 20.72 18.36 20.72
27 18.36 18.36 19.54 22.68 20.72 19.54 21.90 19.54 18.36 19.54 18.36 16.00 16.00 18.36 17.18 16.00 15.50 15.50 5.07 26.65 9.54 16.61 16.00 14.50
28 15.50 16.00 17.18 16.00 17.18 17.18 14.91 32.62 16.00 16.00 15.00 15.00 14.50 14.50 14.00 14.00 14.00 15.00 14.50 14.00 14.00 14.00 14.50 13.50
29 12.80 7.86 12.96 17.75 31.16 14.50 13.50 13.50 7.60 14.21 15.56 15.56 14.69 15.56 13.50 12.10 12.10 12.80 12.80 10.70 24.86 10.58 13.50 12.10
30 12.10 12.10 11.40 13.50 12.80 12.80 12.44 20.75 28.92 12.80 11.40 4.74 9.20 29.70 11.40 10.70 11.40 12.80 13.50 31.89 33.35 17.18 18.36 20.72
31 17.18 18.36 20.72 18.36 19.54 18.36 18.36 16.00 15.50 15.00 15.50 14.00 13.50 13.50 14.00 13.50 13.50 13.50 2.76 15.79 22.15 24.40 40.40 45.25
Day
Flow Rate m3/sec
Time in Hours
32
Table 2.1.6 Hourly Flow Data - November 2016Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 47.50 48.25 45.25 43.00 40.00 37.75 35.54 34.81 31.89 28.92 28.14 25.02 25.02 25.02 21.90 22.68 21.90 28.14 51.25 44.50 37.75 19.25 35.71 35.54
2 28.92 28.14 27.36 28.14 28.14 27.36 25.80 25.02 23.46 24.24 22.68 19.54 22.68 19.54 17.18 19.54 17.18 19.54 16.00 16.41 28.15 56.00 62.40 50.50
3 51.25 51.25 46.75 44.50 43.75 41.50 38.50 34.81 33.35 29.70 29.70 27.36 27.36 25.80 25.02 24.24 23.46 25.02 21.08 92.04 105.80 80.00 72.00 61.60
4 57.60 52.80 49.00 47.50 47.50 43.75 42.25 40.00 37.75 35.54 34.81 33.35 31.89 30.43 29.70 29.70 31.16 33.35 12.45 44.72 29.48 46.80 48.25 34.81
5 32.62 33.35 31.16 30.43 30.43 28.92 28.14 28.14 28.14 28.92 30.43 32.62 33.35 33.35 31.89 30.43 31.16 30.43 23.40 27.65 31.70 36.06 43.12 28.84
6 28.92 26.58 26.58 25.80 25.80 25.02 25.02 24.24 23.46 25.02 23.46 22.68 23.46 22.68 22.68 21.90 21.90 23.46 11.22 9.40 21.52 25.26 32.08 26.58
7 22.68 18.17 22.09 22.84 18.20 22.48 23.52 24.24 22.68 19.54 19.54 20.72 19.54 17.18 18.36 18.36 16.00 18.36 17.34 15.00 26.40 30.43 18.36 18.36
8 16.00 16.00 16.00 16.00 18.36 16.00 18.04 41.50 15.00 15.50 16.00 15.00 16.00 15.50 15.50 15.00 14.50 15.00 9.42 10.44 12.80 32.00 15.36 18.36
9 19.54 19.54 20.72 18.36 19.54 19.54 16.76 28.92 18.36 16.00 17.18 15.00 16.00 17.18 15.00 17.18 15.50 15.50 15.88 18.00 16.56 18.60 34.40 27.80
10 34.08 32.62 30.43 29.70 26.58 24.24 24.24 20.72 21.90 18.36 18.36 14.10 20.67 16.25 16.31 14.45 14.00 16.31 13.40 20.80 18.45 3.95 20.80 17.75
11 15.50 14.50 15.00 18.36 18.36 15.56 12.00 40.75 18.36 12.14 5.26 24.80 22.25 23.65 14.75 16.24 15.20 15.20 16.08 37.68 16.25 17.81 18.36 16.00
12 18.36 15.50 17.18 15.50 15.00 16.00 13.01 15.26 16.00 15.50 15.00 12.66 14.05 11.80 18.48 14.83 15.00 13.50 13.50 15.16 7.64 19.84 13.40 15.96
13 21.60 18.48 16.00 18.48 19.94 19.56 21.96 24.00 21.40 21.90 17.18 14.50 15.50 15.00 14.50 15.00 14.00 14.50 14.01 10.92 12.00 15.52 38.24 16.00
14 14.00 14.00 13.50 14.00 13.50 13.50 14.00 13.50 14.00 13.50 13.50 14.00 16.00 15.98 15.56 14.50 12.80 10.70 12.80 9.66 12.26 32.62 14.00 15.50
15 15.00 15.50 17.18 18.36 21.90 20.72 13.41 17.51 16.95 12.66 15.20 18.10 17.75 17.02 16.29 14.10 10.13 15.16 6.66 11.76 16.53 14.73 14.50 12.80
16 13.50 15.50 15.00 15.50 15.50 9.66 3.68 25.15 10.99 10.71 13.71 12.55 20.76 13.56 16.60 22.15 13.32 13.27 14.40 16.76 16.29 19.54 12.10 14.00
17 12.80 13.50 12.80 12.10 14.00 5.07 10.01 34.08 12.80 12.80 13.50 7.30 10.30 16.61 12.65 17.34 15.00 15.50 9.92 9.92 41.60 22.44 15.00 17.18
18 18.36 17.18 19.54 17.18 15.00 17.18 15.28 34.90 18.07 15.16 13.47 13.70 12.26 13.24 12.26 12.20 11.45 16.61 17.16 15.20 19.21 28.14 12.80 14.00
19 13.50 14.50 15.50 16.00 20.72 19.54 22.68 28.14 28.14 28.14 26.58 27.36 27.36 26.58 24.24 25.02 24.24 21.90 19.54 20.72 46.00 40.75 31.89 18.36
20 15.00 16.00 17.18 15.50 16.00 16.00 14.50 17.02 24.45 14.83 17.02 16.29 17.02 28.92 13.50 14.50 14.00 13.50 13.70 45.20 46.20 45.24 43.75 14.50
21 13.50 14.00 13.32 14.74 17.02 14.83 11.75 19.54 13.50 14.00 14.50 12.80 14.00 12.10 12.10 13.50 12.10 14.00 13.50 13.47 16.01 14.01 14.50 12.80
22 11.40 13.50 12.80 12.80 1.58 12.15 11.45 10.70 13.50 12.80 11.50 10.27 7.30 16.20 8.97 10.70 14.42 13.28 13.24 15.78 5.37 24.24 30.43 58.40
23 58.40 54.40 45.25 39.25 34.08 28.92 18.55 27.40 23.30 28.49 9.90 15.04 25.43 12.20 7.28 16.28 20.30 19.55 21.12 23.52 16.24 39.60 61.60 44.50
24 35.54 32.62 31.89 29.70 28.92 27.36 18.55 28.15 22.68 20.72 10.71 15.20 17.97 17.51 15.26 15.95 14.97 16.65 17.05 16.60 20.67 18.79 15.00 15.50
25 15.00 14.50 15.00 14.00 14.00 7.08 15.21 17.18 15.00 14.50 15.00 7.41 12.43 9.95 13.18 12.95 13.70 7.41 5.92 8.00 14.80 12.60 8.81 13.50
26 12.80 14.00 13.50 12.80 14.50 13.50 8.91 13.01 14.87 6.63 13.13 9.72 11.45 23.71 9.12 10.71 11.75 11.31 10.65 13.92 21.16 15.68 20.36 20.72
27 13.50 12.10 12.10 12.10 12.10 15.39 11.45 20.35 15.47 11.75 12.45 12.24 19.03 14.01 15.98 16.71 15.15 9.64 13.68 11.00 9.40 12.00 19.31 9.12
28 15.47 17.65 14.01 9.61 14.06 5.48 13.44 18.50 17.02 7.75 12.96 19.64 7.60 19.76 11.50 26.12 16.29 7.76 12.27 13.00 12.08 23.36 15.00 10.70
29 11.40 10.70 11.40 10.70 11.40 10.70 34.08 31.16 31.16 15.00 11.40 10.70 10.00 10.70 10.70 10.00 10.00 10.00 10.70 14.32 15.84 13.91 12.80 10.70
30 10.00 10.00 10.00 10.70 10.70 10.00 9.54 9.90 11.19 10.65 15.00 10.00 10.00 9.30 10.00 10.70 10.70 9.30 11.50 14.16 25.80 10.70 10.00 10.00
Day
Flow Rate m3/sec
Time in Hours
33
Table 2.1.7 Hourly Flow Data - December 2016Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 9.30 9.30 9.30 9.30 9.30 10.00 13.30 13.71 12.23 11.40 9.30 8.60 9.30 8.60 9.30 9.30 8.60 9.30 10.00 11.76 9.42 9.68 19.54 10.00
2 8.60 8.60 7.90 7.90 8.60 6.30 3.56 14.40 15.47 15.78 9.63 5.47 7.14 7.45 24.24 11.61 12.23 9.63 9.63 9.88 9.42 8.90 8.60 7.20
3 9.30 7.90 7.90 7.20 8.60 7.90 9.63 16.20 10.00 8.60 7.90 8.90 6.20 28.92 7.20 6.50 7.90 6.50 6.50 6.26 6.20 11.09 19.54 7.20
4 9.30 7.90 7.20 7.20 7.90 7.20 5.51 8.72 8.97 7.35 8.38 9.63 9.22 6.56 8.90 7.34 9.63 11.40 4.23 1.40 17.00 8.36 18.48 8.60
5 7.20 7.90 10.70 8.60 8.60 8.60 7.72 9.55 6.95 35.36 40.88 38.64 40.36 38.60 40.36 39.80 40.08 50.24 11.91 39.00 41.76 40.40 36.16 30.80
6 27.36 12.13 6.30 15.14 5.89 9.22 14.73 18.07 8.90 8.70 12.08 7.36 11.76 11.81 11.09 16.52 20.56 14.84 13.20 53.80 12.76 15.96 14.83 13.28
7 24.24 6.50 6.24 7.90 5.99 6.24 4.43 14.52 13.79 13.28 7.30 3.95 14.00 8.38 25.49 35.76 36.00 34.90 29.36 30.36 32.65 35.20 8.60 5.99
8 5.99 6.50 6.50 6.24 8.60 7.20 7.20 13.32 8.16 13.30 5.15 8.84 23.16 17.64 16.30 13.30 12.55 11.80 11.22 14.72 7.57 17.80 25.44 12.80
9 11.40 10.00 11.40 10.70 11.40 6.62 3.66 10.30 11.51 10.68 9.20 8.51 9.26 7.99 6.95 7.99 8.45 6.20 6.20 7.80 26.24 20.05 11.40 7.20
10 8.60 9.30 8.60 10.00 12.10 1.72 12.66 12.43 14.73 14.94 9.54 1.22 10.59 17.75 10.78 10.58 11.41 11.09 8.39 16.30 17.02 8.60 6.50 7.90
11 7.90 7.20 7.20 8.60 7.20 7.20 7.20 18.48 14.83 12.02 6.31 8.70 10.46 7.03 13.70 11.09 8.49 10.78 17.34 5.20 13.52 12.50 25.80 7.90
12 6.50 6.50 6.50 7.20 7.20 6.24 10.36 11.51 10.72 8.38 5.38 7.03 10.99 10.36 11.19 6.94 9.32 3.70 1.83 8.18 9.30 6.50 6.24 7.20
13 6.24 6.24 5.99 6.24 6.50 6.24 5.99 4.12 7.66 8.81 14.42 9.95 7.34 7.76 15.56 7.76 4.65 8.49 17.75 28.16 5.07 23.65 7.20 6.24
14 5.99 5.99 6.24 5.99 6.24 5.73 10.00 14.32 6.94 7.03 12.64 11.44 6.56 14.12 6.13 5.04 6.00 8.00 25.96 33.56 17.35 28.92 6.50 5.73
15 6.24 5.99 5.99 5.99 6.24 6.50 7.35 13.31 8.81 5.04 6.20 8.08 7.28 10.20 7.80 13.00 9.96 8.96 5.55 9.64 33.40 17.02 11.40 6.50
16 5.99 5.47 5.47 5.73 6.24 7.08 6.25 19.07 24.00 12.55 5.28 5.28 12.40 16.40 7.84 13.93 14.92 5.26 6.80 29.70 26.58 5.99 5.47 5.47
17 5.73 6.24 5.73 5.73 5.47 5.47 6.24 4.43 11.82 8.08 18.48 15.50 9.08 8.76 18.74 9.22 11.92 7.35 7.35 10.20 10.00 15.20 19.54 5.73
18 5.73 5.22 5.22 5.47 5.99 5.73 5.47 5.47 5.73 5.47 5.99 5.47 5.22 4.96 5.22 5.47 5.22 4.96 5.22 5.22 5.22 5.47 5.47 5.47
19 5.22 4.96 5.22 7.90 2.56 5.16 7.34 9.63 5.52 7.12 17.48 6.88 6.08 5.96 21.56 8.08 12.76 12.80 6.00 7.40 15.66 14.83 19.54 5.73
20 5.22 5.99 5.47 5.47 4.96 5.22 4.03 7.76 7.00 3.92 9.96 7.60 10.36 9.44 8.08 13.36 6.80 11.20 12.28 7.56 7.44 9.13 11.40 5.99
21 5.47 5.22 5.47 5.47 5.47 3.00 7.35 9.42 8.64 2.96 14.60 4.60 7.80 8.44 8.56 8.44 13.32 5.48 3.70 9.84 16.76 10.72 16.00 5.73
22 5.22 5.22 5.22 4.96 5.22 5.22 5.22 5.00 7.34 10.36 5.52 5.48 6.21 4.43 9.64 8.64 7.86 7.90 4.96 13.58 24.24 5.99 4.70 4.70
23 4.96 4.70 4.70 5.73 4.96 4.96 6.82 9.30 5.22 5.47 4.96 4.96 4.44 5.22 4.96 4.70 4.44 4.44 4.44 4.44 4.70 5.73 4.96 4.70
24 4.96 4.96 4.70 4.70 5.73 5.22 4.96 4.96 4.96 4.96 5.73 5.22 4.70 4.19 4.19 3.93 4.70 4.44 4.44 3.94 26.58 5.22 4.96 4.44
25 4.70 5.47 4.96 4.70 4.96 4.96 4.70 5.47 4.70 4.70 4.70 4.70 4.44 4.96 4.70 4.19 4.19 4.44 4.70 4.43 6.20 10.98 5.47 4.70
26 4.70 4.70 4.70 4.70 4.96 4.44 5.47 4.96 4.70 4.70 4.44 4.44 4.44 4.70 4.19 3.93 3.93 3.93 4.19 4.02 8.08 4.43 25.02 4.96
27 4.44 4.70 4.44 4.44 5.22 4.70 4.44 4.70 4.70 4.44 4.44 4.44 4.70 3.93 3.79 3.93 3.93 3.79 3.93 5.00 14.50 4.70 4.19 4.19
28 4.19 4.19 4.44 4.19 4.19 4.44 4.70 5.99 4.96 4.70 4.70 4.44 4.96 4.44 3.93 4.19 4.44 5.22 4.70 4.43 4.74 7.34 5.52 7.90
29 5.22 4.96 4.96 4.96 5.22 5.47 5.47 5.22 4.96 4.96 4.96 5.22 5.22 4.96 4.96 4.44 4.44 4.96 4.70 14.42 6.50 4.96 4.70 4.70
30 5.22 5.22 5.22 5.22 4.96 5.22 4.96 5.47 5.22 4.96 4.70 4.70 4.70 4.70 4.44 4.19 4.44 4.19 4.19 9.63 10.46 5.52 14.36 5.22
31 4.70 4.70 4.44 4.70 4.44 4.44 4.44 4.44 4.44 5.22 4.44 4.19 4.19 3.93 3.93 3.93 4.44 4.19 4.19 5.89 5.78 5.16 6.24 5.22
Day
Flow Rate m3/sec
Time in Hours
34
Table 2.1.8 Hourly Flow Data - January 2017Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 4.19 4.19 4.19 3.93 4.19 4.19 4.19 4.96 4.70 4.44 3.93 3.93 3.79 3.64 3.93 3.93 3.79 3.64 3.79 5.15 6.04 6.50 4.19 4.44
2 4.70 4.44 3.93 4.19 4.19 3.93 4.19 4.19 4.70 4.19 3.93 3.93 3.79 3.79 3.79 4.44 3.93 3.79 3.79 5.52 7.08 5.00 8.64 21.90
3 4.70 4.19 3.93 3.93 4.96 4.19 3.93 4.19 3.79 3.93 3.93 3.93 4.19 4.19 3.93 3.79 2.66 9.42 5.26 7.03 8.12 8.64 7.86 8.12
4 25.80 5.26 9.42 5.12 5.52 4.22 8.05 7.08 3.94 5.16 7.41 4.48 7.08 2.40 6.82 7.08 8.38 7.08 10.20 14.83 5.73 4.44 3.93 3.79
5 3.79 3.93 3.93 3.79 3.79 3.93 3.79 4.70 4.19 3.93 3.93 3.79 3.64 3.50 3.50 3.93 3.64 3.64 3.64 5.00 5.78 12.28 7.90 3.93
6 4.44 3.93 3.79 3.79 3.64 3.79 3.79 3.79 3.79 3.79 4.44 3.79 3.64 3.50 3.36 3.64 3.64 18.36 17.02 12.40 11.34 10.70 3.93 3.79
7 3.79 3.79 3.64 3.79 4.44 4.19 3.64 3.79 3.79 3.79 3.93 3.79 3.64 3.79 3.50 3.50 3.36 3.22 3.50 2.92 6.30 6.30 4.70 4.19
8 3.64 3.36 3.64 3.64 3.64 3.64 3.64 3.64 3.79 3.93 3.79 3.50 3.50 3.36 3.36 3.22 3.22 3.50 3.79 3.94 5.26 6.56 7.86 5.73
9 3.79 3.50 3.50 3.64 3.64 4.44 3.79 3.79 3.79 3.79 3.79 3.79 3.50 3.50 3.64 3.36 3.36 3.22 1.58 4.44 13.28 10.70 3.79 3.64
10 3.50 4.19 3.79 3.50 3.64 3.64 3.64 3.50 3.50 3.64 3.64 3.64 3.50 3.36 3.22 3.94 2.66 6.82 6.82 7.35 11.10 24.40 20.72 20.72
11 27.36 20.72 18.36 27.36 26.58 27.36 10.98 5.78 3.18 4.74 6.04 4.74 5.52 5.78 3.70 5.26 4.12 6.30 6.30 7.34 6.30 8.64 8.64 8.20
12 23.46 8.12 3.18 4.74 4.48 5.26 5.26 5.52 4.70 3.50 3.93 3.64 3.36 3.22 3.07 3.07 3.07 3.07 1.70 6.04 5.26 9.42 5.99 3.64
13 3.50 3.36 3.22 3.50 3.36 3.36 3.36 3.36 3.36 3.36 3.36 3.36 3.64 3.36 3.22 3.07 2.93 3.07 3.22 3.44 5.52 6.30 7.20 4.70
14 3.50 3.79 3.50 3.36 3.36 3.36 3.50 3.50 3.50 3.36 3.50 3.22 3.22 3.07 3.50 3.22 3.22 3.07 2.93 3.18 3.96 5.52 2.76 5.73
15 3.36 3.36 3.22 3.36 3.79 3.50 3.36 3.36 3.36 3.36 3.36 3.22 3.22 3.22 2.93 2.93 2.93 3.50 3.22 4.74 3.70 3.96 4.74 4.70
16 3.36 3.22 3.07 3.22 3.22 3.22 3.18 3.56 3.70 5.00 3.72 4.80 6.95 6.56 2.76 3.00 5.52 5.52 3.96 3.96 3.00 6.54 4.18 2.50
17 5.36 4.74 3.94 3.00 5.26 5.26 4.74 4.18 2.76 5.60 3.70 5.26 5.36 6.04 5.52 4.22 3.18 2.90 3.70 4.22 6.30 6.30 3.94 5.52
18 5.60 4.82 5.52 5.00 5.78 4.74 4.22 2.76 2.92 4.48 4.48 3.96 4.48 3.44 1.88 2.66 5.52 2.66 2.18 2.18 5.12 4.48 3.18 2.40
19 5.52 3.96 3.18 3.96 4.22 1.62 3.96 2.76 3.96 7.20 3.44 5.26 5.30 6.30 2.76 3.18 4.48 7.86 6.56 4.56 5.52 5.36 5.78 6.30
20 26.58 3.00 2.66 2.66 2.38 5.00 5.26 3.18 3.18 3.18 2.76 3.44 4.74 3.96 2.76 2.40 4.22 3.44 5.00 2.92 2.92 3.94 3.00 4.44
21 3.36 3.22 3.50 3.36 3.79 3.64 3.36 3.22 3.07 2.93 2.93 3.50 3.07 2.93 2.93 2.93 2.93 2.93 3.07 3.00 1.62 2.76 3.00 4.18
22 3.79 3.36 3.22 3.36 3.36 3.22 3.36 3.50 3.50 3.22 3.22 3.07 3.07 3.07 3.07 3.07 2.93 3.07 3.36 3.18 3.96 5.52 4.96 3.36
23 3.22 3.22 3.22 3.36 3.79 3.50 3.36 3.36 3.22 3.36 3.36 3.22 3.22 3.36 3.64 3.50 3.96 3.92 3.70 3.18 3.00 3.00 2.38 8.60
24 3.79 3.50 4.44 3.93 3.79 4.19 4.44 4.44 4.19 4.19 3.93 4.19 4.19 3.93 3.93 3.93 3.93 3.93 4.44 4.85 5.89 4.70 4.96 5.73
25 5.99 6.24 7.20 9.30 9.30 8.60 7.20 7.20 7.20 6.24 7.20 5.99 5.47 4.96 4.96 5.47 4.70 4.19 4.44 4.19 4.96 3.93 3.93 4.19
26 4.44 4.70 3.93 4.19 4.19 3.93 3.93 4.44 4.19 3.93 3.93 3.79 3.79 4.19 3.93 3.79 3.64 3.79 4.44 4.19 4.70 4.96 4.96 4.10
27 5.00 5.12 9.30 3.93 4.19 4.70 3.61 3.00 5.22 4.96 4.44 4.96 5.99 4.96 5.22 4.96 4.44 5.99 7.08 3.70 14.42 13.32 11.76 5.99
28 5.47 5.99 5.47 5.47 5.47 5.47 6.24 5.73 5.47 5.47 5.47 5.22 5.47 4.96 5.22 4.70 4.96 5.47 5.22 4.43 7.08 7.20 5.73 5.22
29 5.22 5.22 4.96 5.73 4.96 5.22 4.96 4.96 5.73 4.96 4.96 4.44 4.44 4.70 4.19 4.19 4.19 4.19 4.96 11.40 8.12 6.56 3.44 8.60
30 5.73 4.96 4.96 4.70 4.44 4.44 4.44 5.47 4.70 4.70 4.70 4.44 4.70 4.44 4.44 4.44 4.19 4.19 4.19 4.43 7.76 15.00 4.96 4.70
31 4.19 4.44 4.44 4.96 4.96 4.96 4.70 4.44 4.70 4.70 5.22 4.96 4.70 4.44 3.93 3.93 3.93 3.93 3.79 14.10 12.54 9.16 20.72 4.96
Day
Flow Rate m3/sec
Time in Hours
35
Table 2.1.9 Hourly Flow Data - February 2017Location - On the Mahaweli River Downstream of the Moragolla Hydropower Plant Tail Race and the Confluence with the Atabage Oya
00:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
1 4.44 4.44 4.44 4.70 4.96 4.96 4.96 4.70 4.44 5.22 4.96 4.96 4.70 4.44 3.93 3.79 4.19 3.79 3.64 5.16 3.70 12.54 7.20 4.70
2 4.70 4.70 4.44 4.44 4.19 4.96 4.70 4.70 4.44 4.44 4.44 3.93 3.79 4.70 4.44 3.79 3.79 4.19 4.19 4.60 7.03 4.22 20.67 3.96
3 36.27 7.20 5.47 5.22 5.22 4.96 4.70 4.70 4.96 5.22 4.96 4.70 4.44 4.19 3.93 3.93 3.79 4.19 4.44 10.26 16.29 15.00 5.47 4.96
4 4.96 4.96 4.70 4.70 4.70 4.44 4.70 4.96 4.70 5.73 5.22 5.22 4.96 4.70 4.44 3.93 4.19 3.93 3.93 3.43 12.00 5.44 8.60 10.98
5 5.99 4.96 4.96 4.96 4.96 4.96 4.96 4.96 5.47 4.22 8.12 6.50 4.70 3.93 3.64 3.64 3.64 3.64 2.76 5.16 11.76 9.63 23.46 5.47
6 4.96 4.70 4.70 4.44 4.44 4.44 4.70 4.96 4.96 4.70 4.70 4.48 6.83 8.64 8.64 5.80 5.79 9.09 10.36 12.24 16.29 15.25 7.20 4.96
7 4.70 4.19 4.19 3.93 3.93 3.93 3.93 12.80 11.09 11.09 9.95 11.09 11.82 9.42 8.64 7.86 7.86 7.86 7.86 2.92 15.56 3.96 12.28 15.00
8 4.96 4.70 4.70 4.44 4.44 4.70 2.66 7.86 8.64 25.80 4.96 4.70 3.93 3.79 3.50 3.36 3.22 3.36 3.50 15.14 12.54 7.34 5.99 4.70
9 4.44 5.22 4.44 4.44 4.19 5.73 6.31 7.08 15.56 7.08 10.00 4.44 4.44 3.79 3.79 3.64 3.64 3.93 3.50 5.89 7.34 8.49 7.67 6.66
10 6.21 6.24 4.44 4.44 4.19 4.19 9.42 11.76 6.56 5.78 6.30 7.08 16.20 15.00 4.19 3.79 3.64 3.64 3.79 3.44 3.44 5.52 8.60 5.22
11 4.19 3.93 3.64 3.50 3.50 3.64 3.64 3.64 3.79 3.93 4.19 4.19 3.79 3.64 3.64 3.93 3.36 3.50 3.36 3.70 12.02 14.00 4.44 3.93
12 3.79 3.79 3.79 3.79 3.79 3.79 3.79 3.79 3.79 3.93 4.19 3.93 3.50 3.50 3.22 3.22 3.22 3.36 3.36 4.43 3.18 3.70 3.70 4.44
13 3.79 3.79 3.79 3.79 4.19 4.19 3.93 3.93 3.70 3.96 5.16 7.35 3.96 3.50 5.00 4.43 4.74 5.52 5.52 3.96 5.22 4.19 3.79 3.79
14 3.64 3.50 3.50 3.50 3.50 3.36 3.64 3.64 3.64 3.96 13.90 15.46 5.78 11.24 6.30 7.08 6.30 8.60 7.86 6.56 9.63 9.16 12.10 4.70
15 4.19 4.19 4.19 4.19 4.70 4.96 4.44 6.30 8.59 13.32 6.31 4.43 5.16 5.50 6.01 8.20 7.35 4.84 3.94 6.62 4.60 4.96 4.19 3.79
16 3.93 3.93 4.19 4.19 3.93 4.19 4.19 2.40 8.12 10.98 5.12 5.12 6.30 3.70 3.93 3.64 3.50 3.36 3.50 6.56 7.08 6.04 12.10 4.96
17 4.19 3.79 3.64 3.64 3.64 3.64 4.18 6.30 4.44 3.79 2.76 4.02 3.61 5.00 6.50 4.44 3.93 2.92 7.08 14.83 6.56 10.00 4.19 3.64
18 3.50 3.50 4.22 4.75 3.80 4.40 6.93 3.18 3.96 4.74 5.78 3.04 6.56 4.44 3.64 3.50 3.50 3.36 3.22 3.22 3.22 3.22 3.22 3.22
19 3.36 3.50 3.36 4.19 3.64 3.79 3.64 3.61 3.18 4.70 3.93 2.76 4.22 5.78 7.86 6.30 5.22 3.93 4.96 7.03 5.78 4.74 5.22 4.44
20 4.19 4.70 4.19 3.93 3.93 3.93 2.76 3.70 4.44 4.96 4.44 3.93 3.93 3.79 3.79 3.64 3.79 3.93 3.79 3.79 4.19 4.19 4.19 3.93
21 3.79 3.79 3.79 3.93 3.93 4.44 4.19 3.93 4.44 4.19 5.78 4.22 6.56 4.70 3.79 3.50 3.36 3.22 3.22 5.00 8.12 3.44 4.96 3.93
22 3.79 3.79 3.64 3.64 3.50 3.50 3.50 3.50 4.22 5.78 5.52 9.30 4.44 3.93 3.50 3.36 3.36 3.22 3.22 3.18 3.39 3.96 4.70 3.79
23 3.93 3.64 3.64 3.64 3.50 3.50 3.93 5.26 3.18 2.15 5.45 5.78 6.56 4.96 3.79 3.50 3.22 3.07 3.07 3.96 5.12 7.20 3.79 3.79
24 3.64 3.36 3.50 3.50 3.64 3.64 3.64 3.50 3.50 3.50 3.36 3.22 3.22 2.93 2.79 2.93 2.79 3.07 3.22 3.18 3.18 4.22 3.18 4.44
25 3.79 3.36 3.36 3.22 3.22 3.22 3.36 3.50 3.64 3.50 3.50 3.36 3.36 3.22 3.22 3.22 3.36 3.07 3.07 5.00 5.78 5.00 5.47 3.79
26 3.50 3.50 3.50 3.36 3.36 3.36 3.22 3.07 3.22 3.22 3.22 3.22 3.64 3.50 3.64 3.50 3.36 3.36 3.79 2.40 4.74 5.78 3.70 4.10
27 4.19 3.64 3.64 3.64 3.79 3.64 6.78 6.04 7.86 3.96 5.12 5.47 3.64 3.50 3.36 3.36 3.36 3.64 2.76 3.18 4.22 4.48 6.82 5.52
28 4.70 3.79 3.50 3.50 3.36 3.36 3.36 3.64 3.64 4.44 3.79 3.64 5.12 5.00 5.16 5.78 5.52 6.30 3.44 4.74 3.18 4.74 4.96 4.19
Day
Flow Rate m3/sec
Time in Hours
36
Annexure 2
Letter received from Mr. Prashan De Silva
37
38