Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Environmental Management Plan __________________________________________
May 2020
Mongolia: Aimag and Soum Centers Green and Resilient Regional Development Investment Program
Ulgii and Deluun and Buyant Soums, Bayan-Ulgii Aimag
Prepared by the Ministry of Construction and Urban Development for the Asian Development Bank.
CURRENCY EQUIVALENTS (16 May 2020)
Currency Unit – Tugrik (MNT)
MNT 1.00 = $0.00035 $1.00 = MNT 2,792
ABBREVIATIONS
ADB - Asian Development Bank
ALAMGaC - Land Management, Geodesy and Cartography ASDIP
- Aimag and Soum Centers Green and Resilient Regional Development Investment Program
AMC - Asset Management Company CEMP - contractor environmental management plan
DoE - Aimag Department of Environment DBM - Development Bank of Mongolia
EIA - environmental impact assessment EMP - environment management plan EMR - environmental monitoring report GOM - Government of Mongolia GRM - grievance redress mechanism
IEE - initial environment examination MET - Ministry of Environment and Tourism
MCUD -
Ministry of Construction and Urban Development
MOFALI - Ministry of Agriculture and Light Industry NFPUG - National Federation of Pasture Users Group
TOSK - Provincial Housing Authority PIU - project implementation unit
TRTA - transaction technical assistance REA - rapid environmental assessment
RP - resettlement plan SPS - ADB Safeguard Policy Statement (2009)
WEIGHTS AND MEASURES
km - kilometer ha - hectare m - meter
m3 - cubic meter t - metric ton
NOTE
In this report, "$" refers to US dollars.
This environmental management plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Table of Contents
I. INTRODUCTION 1
A. Overview of ASDIP 1
II. INSTITUTIONAL ARRANGEMENTS AND RESPONSIBILITIES 3
A. Project level 3 B. Bayan-Ulgii Aimag 4
III. SUMMARY OF POTENTIAL IMPACTS 7
IV. PUBLIC CONSULTATION 10
V. MITIGATION PLAN 10
VI. MONITORING PLAN 30
A. Environmental Quality Standards for Tranche 1 of ASDIP 30 B. Performance Monitoring 30 C. Reporting 30 D. Estimated Cost of EMP 35 E. Emergency Response Plan 36
APPENDIX A: ENVIRONMENTAL QUALITY STANDARDS OF MONGOLIA 37
APPENDIX B: EXAMPLE ENVIRONMENTAL MONITORING REPORT FOR ASDIP 45
APPENDIX C: EMERGENCY RESPONSE PLAN 46
A. Alert Procedures 47 B. Emergency Response Situations 48
Table 1: Planned Investments in Ulgii Center and Deluun Soum Center .................................... 2 Table 2: Summary of Indicative Responsibilities for Uvs Aimag EMP ......................................... 6 Table 3: Summary of Potential Impacts of ASDIP ....................................................................... 8 Table 4: Mitigation Plan .............................................................................................................11 Table 5: Environmental Monitoring Plan ....................................................................................31 Table 6: Performance Monitoring Indicators for ASDIP ..............................................................34 Table 7: Indicative Costs for Bayan-Ulgii Aimag EMP ...............................................................35 Table 8: Roles and Responsibilities in Emergency Incident Response ......................................46 Table 9. Evacuation Procedure .................................................................................................48 Table 10: Response Procedure During Medical Emergency .....................................................49 Table 11: Response Procedure in Case of Fire .........................................................................49 Figure 1: Institutional Arrangements for ASDIP .......................................................................... 4
1
I. INTRODUCTION
1. Tranche 1 of the Aimag and Soum Development Investment Program (ASDIP) is located in the three western Aimags of Uvs, Bayan-Ulgii, and Khovd of Mongolia. The environmental management plan (EMP) reported herein was prepared for the project areas in Bayan-Ulgii Aimag which are located Ulgii – the Aimag center, and the soum centers of Deluun Buyant. The two EMPs for the project areas in Bayan-Ulgii Aimag and Khovd Aimag were prepared separately. 2. The EMP will guide the implementation of the urban infrastructure and agribusiness components of Tranche 1 of ASDIP in Ulgii, and Deluun and Buyant soums through the pre-construction, construction, and post-construction operation phases to ensure that unnecessary environmental and social impacts identified in the separate IEE do not occur, and to also measure and document any unexpected impacts of the project components. 3. The EMP provided here will guide contractors to develop their contractor EMPs (CEMP) for their construction package bidding documents. Similar to the EMPs of the other two Aimags, the EMP of the feasibility designs of Tranche 1 in Bayan-Ulgii Aimag is decidedly comprehensive and developed as a stand-alone management tool that will be updated during the later detailed design stage of Tranche 1. A. Overview of ASDIP
4. Tranche 1 of the ASDIP will promote local economic development and improve basic urban services in priority Aimags of Mongolia1. The program will support the government in establishing inclusive, green urban development, resilient rangeland management, and sustainable agribusiness values chains in three select Aimags. For each Aimag the ASDIP will comprise a sequenced set of green urban and rural infrastructure developments, and agribusiness investments, which are supported by implementation mechanisms, policy actions, and capacity building support. The ASDIP investments will reduce the vulnerability of the country to climate change and further pastureland degradation. 5. The multisector ASDIP will invest in the three selected Aimag centers and four soum centers in the following two major component areas:
(i) basic urban infrastructure, services, and facilities; and (ii) agribusiness facility developments including improved pastureland management.
6. Table 1 summarizes the planned investments for Tranche 1 in Ulgii which is the Bayan-Ulgii Aimag center, and the soum centers of Deluun and Buyant. The urban infrastructure investments will occur primarily inside the Aimag and soum centers, whereas the agribusiness investments will occur outside but near the Aimag and soum centers. The new agribusiness facility investments will also be supported with infrastructure.
1 An aimag is an administrative subdivision equivalent to province in Mongolia. There are 21 aimags and aimag centers.
A soum is an administrative subunit of an aimag, and its center is called a soum center. There are 304 soums in Mongolia (not including Aimag centers). Soums have average populations of 4,000 and cover an average land are of 5,000 square kilometers.
2
Table 1: Planned Investments in Ulgii Center and Deluun Soum Center
Urban and Agribusiness Infrastructure
Ger housing redevelopment2 Heating supply network
improvements
Road developments and drainage Khovd river embankment and
urban levee rehabilitation for flood control
Improvements to wastewater collection and new or completely upgraded treatment plants (WWTP)
Urban water reservoir
Water treatment and distribution improvements
Landfill improvements
Electrical power upgrades Upgraded schools, hospitals,
municipal buildings
Communication towers and fibre optic networks
Agribusiness Investments*
Community-based micro-projects for PUGs3:
- animal husbandry, - hay protected areas and storage, - small irrigation, - well water development, - small river/stream bridges
Agro-parks
- Disease Free Establishments - Meat processing facilities - Laboratory and veterinary services - Research Development Center - Business incubator centers - Processing industries
Irrigation networks and fodder farms
* Investments will be supported by infrastructure. Source: Asian Development Bank.
1. Assessment Context
7. The ASDIP is category B for environment pursuant to ADB’s 2009 Safeguard Policy Statement and supporting good practice sourcebook (2012). The EIA Department of the Ministry of Environment and Tourism (MET) is expected to require that a detailed environmental impact assessment (DEIA) of Tranche 1 of the ASDIP be prepared which MET will specify with the conclusions of the General Environmental Impact Assessment (GEIA) that they will prepare for Tranche 1.
2 This is in relation to an ongoing ADB project. ADB. 2018. Report and Recommendation of the President to the Board
of Directors: Proposed Loan and Administration of Loan and Grants to Mongolia for the Ulaanbaatar Green Affordable Housing and Resilient Urban Renewal Sector Project. Manila.
3 Pasture User Groups.
3
II. INSTITUTIONAL ARRANGEMENTS AND RESPONSIBILITIES
A. Project level
8. The institutional arrangements for ASDIP for all Aimags of the ASDIP are illustrated in Figure 1 and summarized below. A Steering Committee (SC), chaired by MOF and including representative of MCUD, MOFALI, MET, Development Bank of Mongolia (DBM), and targeted aimag governments will be established to oversee project implementation, provide strategic and policy guidance, and inter Ministry and agencies coordination. An Executive Working Group (EWG) including the MCUD, MOFALI, DBM, and the aimag governments will be established to directly supervise and monitor the implementation of the project. The project executing agency (EA) will be the MCUD representing the Government of Mongolia for project implementation oversight. The EA will report directly the EWG and SC. A program management office (PMO) will be established under MCUD with the head of ALAMGac as the PMO director. The PMO will be organized into three departments managed by three deputy coordinators: (i) for urban and land development reporting to the PMO director and liaising with MCUD; (ii) for rangeland management and agricultural component, reporting to PMO director and liaising with MOFALI; and (iii) for procurement, finance, safeguard and due diligence reporting to PMO director. A program implementation unit (PIU) for managing the FIL component of the project will be established by AMC-DBM under the supervision of DBM and will liaise and coordinate with PMO director and coordinator.
1. Aimag level
9. At the Aimag level an Aimag Project Office (APO) will be established, and an Inter-Soum Implementation Office (IPO) in each inter-soum targeted by the project. Each will have urban development, rangeland management, agri-business, and safeguard and due diligence team. Each APO will be managed by APO coordinator and report to the PMO director and coordinator and will liaise and coordinate with Aimag Governor’s Office. A local Agri-Business Council, comprising of representatives of associations or federations for production of meat, wool and cashmere, skin and hide products, and Mongolian National Chamber of Commerce and Industry (MNCCI), herders organizations, and cooperatives, will be established to provide economic and value chain development guidance and support to the EWG and PMO. In each soum targeted by the project, an Inter-soum Project Implementation Unit (IPIU) will be established, and will have urban development, rangeland management, and agri-business team. The IPIUs will be managed by a coordinator who will report to and liaise with Soum Governor’s Office.
2. Environmental management of separate FIL component
10. The program implementation unit (PIU) to be established by the Development Bank of Mongolia (DBM) for the parallel FIL component of the project (Figure 1) will manage the implementation of the separate EMPs that will be developed by the FIs for private sector investments in the Green Investment Regional Agribusiness Fund (GIRAF). The EMPs prepared by the FIs will developed from and be guided by the separate Environmental and Social Management System (ESMS) that has been prepared for the FIL component to meet the requirements of the SPS (2009) and EIA requirements the MON government.
4
B. Bayan-Ulgii Aimag
11. The primary management framework responsible for the implementation of the EMP for Tranche 1 in Bayan-Ulgi Aimag is summarized as follows. The MCUD as project EA will take overall responsibility for successful implementation of the EMP in the Aimag center of Ulgii and the soum centers of Deluun and Buyant with higher level decision support provided when necessary from the EWG or perhaps SC. Within the UB-based PMO, the Deputy Coordinator #3 for the Safeguard, Due Diligence, Procurement and Finance Department (Figure 1) will assign an environment safeguard officer (ESO) who will work alongside an assigned social safeguard officer. The ESO will ensure that the Bayan-Ulgii EMP is implemented successfully. The ESO will work closely with the Aimag Coordinator at the Bayan-Ulgii APO in Ulgii who will assign an environment safeguard officer (SO) to the safeguard and due diligence team at the APO. With support from the ESO, the SO will work at the project sites to ensure the EMP is implemented satisfactorily in Ulgii, and in Deluun and Buyant soums. The SO in turn will work closely with and guide the Deluun and Buyant project implementation units (IPIU) with the implementation of the EMP. With support from the ESO, the SO will direct and monitor the construction contractors as they implement their contractor EMPs (CEMP). The contactors will develop specific CEMPs in their bidding documents from the EMP which will be included in the tender documents for the different construction packages for the Bayan-Ulgii subprojects.
Figure 1: Institutional Arrangements for ASDIP
Source: Asian Development Bank.
5
12. The SO with assistance from the ESO and PISC (below) will be responsible for day-to-day management of the successful completion of the EMP in Ulgii, and in Deluun and Buyant soums. An EIA licensed Mongolian Firm will be retained to conduct all environmental monitoring and analyses for Ulgii, Deluun, and Buyant that are specified by the Monitoring Plan of the EMP.
13. Support for implementation of the EMP by the ESO and SO will be provided by the international environment specialist (IES) of the Project Implementation and Supervision Consultant team (PISC) hired to oversee the detailed design and implementation of Tranche 1 of ASDIP, along with the safeguard officer of the Asian Development Bank (ADB). The construction package contractors will be responsible for implementing the EMP with their own contractor EMPs (CEMP) that they develop from the Uvs EMP as part of their bid documents. Major and minor responsibilities of institutions and personnel for environmental management of Tranche 1 are further defined below and summarized in Table 2.
14. The MCUD being EA and project owner has ultimate responsible for ensuring successful completion of the EMP for the Bayan-Ulgii Aimag, and for interacting with the MET and ADB as necessary. 15. The Steering Committee (SC) with support from the Executive Working Group (EWG) is responsible for: (i) resolving any environmental management matters that require action from senior management; and (ii) ensuring allocation and timely disbursement of adequate resources for EMP implementation including the environmental monitoring plan of the EMP. The SC/EWG through ESO and SO will also facilitate the necessary inputs and/or assistance from the affected communities and private sector in Ulgii, or Deluun and Buyant soums to meet environmental safeguard obligations, and to ensure collaboration with communities in consultations and information disclosure, environmental monitoring, and with implementation/observance of the grievance redress mechanism (GRM). 16. The Coordinator of Bayan-Ulgii Aimag with support from the SO will be responsible for undertaking and managing day-to-day activities of the Bayan-Ulgii EMP. The SO with assistance from the IES/PISC shall coordinate and supervise EMP implementation, including but not limited to: (a) update the EMP after detail project design; (b) oversee incorporation of EMP recommendations into the contractor design/bid documents, and ensure procurement of environmentally responsible contractors; (c) ensure that government DEIA prepared for the MET as applied to Bayan-Ulgii Aimag is approved prior to the awarding of civil works contracts; (d) facilitate as necessary the acquisition of any supplemental baseline environmental data (e.g., ambient air, surface and groundwater quality, noise, traffic issues) in affected areas of Ulgii and Deluun; (e) confirm and coordinate grievance redress mechanism (GRM); (f) review and clear CEMPs of the selected Contractors; (g) monitor contractors to ensure adherence to the EMP; (h) prepare monthly reports on EMP implementation for the PMO which form part of the PMO’s annual environmental monitoring reports4 (EMR) to the ADB; (i) conduct consultation meetings with local stakeholders as required, informing them of imminent construction works, and updating stakeholders on latest project development activities, GRM, etc.; and (j) support training conducted by international environmental specialist (IES) of Project Implementation and Supervision Consultant (PISC) (see below), EMP compliance reviews, annual reporting, etc. 17. Contractors will develop, implement, and (internally) monitor implementation of their Contractor EMPs (CEMP) which will be fully responsive to the EMP, and also comply with the clauses that the PMO establishes in bidding documents such as: (a) the list of environmental
4 Example EMR for ASDIP in Appendix B
6
management requirements to be budgeted by the bidders in their proposals; and (b) environmental clauses for contractual terms and conditions.
Table 2: Summary of Indicative Responsibilities for Uvs Aimag EMP
Phase
Responsible Agencies
Environmental Responsibilities
Project Preparation
MET Conduct General EIA (GEIA) of ASDIP Review and approve government EMP or DEIA of ASDIP
EA, Ulgii PMO Request MET to conduct General EIA, comply with MET instructions Conduct IEEs in accordance with EARF pursuant to ADB SPS (2009), and DEIA or EMP in accordance with Law on EIA (2012)
PPTA Consultants Support EA in preparing request to MET, and prepare IEE (SPS (2009) ADB Review and approve ADB IEE and EMP, disclose on ADB website
Detailed Design
PISC With support from ESO and SO, incorporation of environmental mitigation measures in detailed designs, and bidding documents.
Ulgii SO/PMO, PISC-IES
Update EMP to meet detailed design Provide updated EMP to ADB
ADB Approve updated EMP Tendering UB-PMO, Ulgii PMO,
tendering company Incorporate mitigation measures and the ADB and government EMP clauses in tender documents, civil contracts, and contractor construction management plans.
PISC, ADB Review tender documents, and confirm project readiness Construction SC and EWG Support to EA
EA, Ulgii PMO Advise on implementation of mitigation measures Contractors Prepare and submit Contractor EMPs (CEMP) that are fully responsive
to ADB and government EMPs Implement mitigation measures and conduct internal monitoring/ supervision
ESO/UB-PMO, Ulgii SO/PMO
Coordinate GRM, supervise EMP implementation, conduct regular site inspections, prepare EMP progress reports, conduct training, and support PISC in preparing annual Environmental Monitoring reports (EMR).
EIA Firm Conduct quarterly environmental monitoring and prepare monitoring reports
PISC-IES Advise on the mitigation measures, provide comprehensive technical support to PMO for environmental management, conduct training, conduct annual EMP compliance review, and support ESO with preparing annual Environmental Monitoring reports (EMR).
ADB Conduct review missions, review and approve annual EMP monitoring and progress report, including disclosure
Operation
Ulgii PMO Conduct EMP compliance review, instruct PIU-DBM and APOs on environmental management requirements, and prepare EMRs until PCR is issued
EIA Firm Conduct environmental monitoring of approved Monitoring Plan ADB Review and approve EMP monitoring and progress reports, and
disclose on ADB project website ADB = Asia Development Bank; ESO = Environmental Safeguards Officer of UB-PMO; PISC = Project Implementation and Supervision Consultant, IES = International Environment Specialist of PISC; SO = Safeguard Officer of Ulgii PMO, EA = Executive Agency (MCUD); MET = Ministry of Environment and Tourism; DEIA = Detailed Environmental Impact Assessment; IEE = Initial Environmental Examination; EMP = Environmental Management Plan; EMR = Environmental Monitoring Report. Source: Asian Development Bank.
18. Affected communities will assist the Ulgii PMO and benefit from: (a) public disclosure of the Tranche 1 IEE, Bayan-Ulgii Aimag EMP and contribute information to EMRs of Aimag EMP, (b) the community awareness program on health and safety impacts of Tranche 1 implementation; (c) establishment of health and safety baseline data prior to construction; (d) provide input and
7
when requested review EMRs and results of environmental monitoring by Contractors reports which will be available at community centers at Ulgii, and Deluun and Buyant soums, and (e) ensure necessary corrective actions are taken for reported environmental/social exceedances that are confirmed as being caused by Contractor negligence. The available monitoring information, the GRM, and general participation of the affected communities identified above will result in the direct involvement of the community with contractor performance. 19. A licensed EIA Firm will be engaged to conduct any required supplemental baseline data collection prior to start of construction phase, and quarterly environmental monitoring during construction and operation phases following the Monitoring Plan of the EMP (Table 4). The EIA Firm will comply with Mongolian Quality Assurance/Control procedures and regulations for sampling and monitoring of environmental media and will assess compliance with Mongolian environmental quality standards for ambient air, water and noise quality. The EIA firm will submit quarterly environmental impact monitoring reports to the PMO in Ulaanbaatar. 20. The International Environment Specialist (IES) of Project Implementation and Supervision Consultant (PISC), with support from the ESO and SO is responsible for providing technical advice, guidance, and “hands-on training” to the EWG and EA for EMP implementation of Tranche 1. The IES-PISC will support the ESO/SO and EA with (a) detailed design and project preparation; (b) training, (c) (c) assistance with EMP compliance monitoring; (d) assistance to PMO with preparation of annual EMRs for ADB; (e) identifying environment-related implementation issues and necessary corrective actions; and (f) undertaking site visits as required. 21. Asian Development Bank (ADB) is responsible for reviewing relevant documents for clearance purposes, and conducting periodic review missions to review, amongst other things, the environmental aspects of Tranche 1. For example, review and clearance will be required for the updated EMP at detailed design phase of Tranche 1, and for subsequent annual EMRs during implementation phase of Tranche 1.
III. SUMMARY OF POTENTIAL IMPACTS
22. The significant impacts of the Tranche 1 of ASDIP in Ulgii, and Deluun and Buyant soums are positive which will arise from: (a) significant increases in the standard of living of the affected communities which will be caused from the major improvements to the diverse array of urban infrastructure and services; and (b) the modern agribusiness developments. The agribusiness developments will; (i) increase the quality of meat and vegetable production enabling access to previously inaccessible lucrative international markets thereby strengthening agricultural livelihoods and incomes; (ii) ultimately reduce the number of livestock which will reduce livestock overgrazing leading to pastureland restoration; and (iii) from (ii) significantly reduce the carbon emission (CO2, CH4, NOX) footprints of the affected project areas. 23. The potentially negative impacts of Tranche 1 that are addressed by the EMP are summarized in Table 3. These impacts focus on: (i) short-term disturbances and impacts caused from the civil works activities of the construction phase of the different project components; and (ii) potential water shortages caused from planned expansion of potable water supplies, water consumption by Agropark facilities such as meat processing facilities; and (iii) increased air pollution from likely increased emissions from the existing coal-fired heating plant in Ulgii arising from expanded hot water supply. The short-term construction disturbances and impacts, and the potential water shortages and air, water, and soil pollution will be managed and mitigated with Mitigation and Monitoring Plans provided below.
8
24. Required land acquisition or resettlement for ASDIP of affected households (AH) is minimal and is reported in detail in the separate Land Acquisition and Resettlement Plan (LARP) for the ASDIP. Table 3 summarizes LARP for Bayan-Ulgii Aimag.
Table 3: Summary of Potential Impacts of ASDIP
Pre-construction Phase
Land acquisition and resettlement, with compensation
Affected Entities Affected Land Parcels
AH Affected
Organizations Total Affected
Entities Fully Partially Total Affected land area (m2)
5 2 7 1 6 7 10,438
Construction Phase Demolition and disposal of traditional ger houses and site remediation:
The partial or complete demolition of khasha homesteads in Bag 13 and optional Bag 5 will not produce toxic materials because the traditional ger houses and wooden buildings do not contain toxic materials such as asbestos. Family pit latrines will be destroyed and filled in with soil following ongoing procedures of the ADB On-site Sanitation Project in UB. Soil near pit latrines will be spray-disinfected with a bactericide.
Upgraded and expanded underground utility trunk lines (potable water, hot water, wastewater) above utilities (electricity, communications), upgraded and new roads, drainage, new water canals, rehabilitated riverbanks, and new and rehabilitated buildings (modern ger apartments, WWTPs, WTPs, meat processing facilities, laboratories, schools, hospitals, community centers, and clean-up and fencing of dumpsites:
Common disturbances and impacts from civil works are defined by (i) reduced and/or blocked public access and pedestrian movement, (ii) disrupted business and recreation, (iii) noise, dust and air pollution caused by increased truck traffic and equipment use, (iv) soil and surface water pollution caused by equipment operation and maintenance and soil erosion, (v) public and worker accidents, (vi) disruption of traffic and increased traffic accidents, (vii) solid and domestic waste from temporary worker camps, (viii) social issues and community problems caused by migrant workers, (ix) potential disturbance to cultural property and values, schools, hospitals, and community centers.
Disruption of utility services: The extensive rehabilitation and expansion of infrastructure and utilities in the Ulgii and Deluun
soum center will undoubtedly cause periods of utility outages for residents and businesses. Where possible temporary auxiliary or alternate utility service will be supplied to minimize the disruptions to the community.
Quarries and borrow pits:
Existing local borrow pits and quarries approved by Bayan-Ulgii Aimag Department of Environment (DoE) will be used. This requirement will be included in construction package tender documents including provisions that no new pit or quarry will be created, and, no new lands will be disturbed, and only proper and safe site restoration is needed after the pits and quarries are used.
9
Batch concrete and asphalt plants: Temporary batch plants for asphalt and concrete may be used for the infrastructure works in the
urban areas. Batch plants potentially act as point sources of environmental and aesthetic pollution for the affected sites and local community. The issues arise from potential wind and water erosion (dust and sedimentation) from stockpiles of the raw materials of sands and other aggregates, chronic noise and public safety risks from batch processing and heavy truck traffic to/from the plants. Improper handling and storage of raw materials can also cause soil and surface water pollution from the curing chemicals in cement and hydrocarbons from (e.g., oil and thinners) for asphalt.
Best practice methods must be conducted to manage the creation, operation, and ultimate decommissioning of temporary batch plants. The contractor must follow best practice method stipulated by the World Bank (IFC) EHS Guidelines for 1) Cement and Lime Manufacturing, 2) Construction Material Extraction; and 3) Retail Petroleum Networks. The recent USEPA (2014) Code of practice Concrete batch processing can also be consulted.
Potential disrupted domestic water supplies The ongoing practice of manual transport of bottled water from local kiosks to home in Ulgii and
Deluun soum for domestic use could easily become disrupted from construction activities. Ulgii Improvements to southern section of Khovd river embankment for flood control:
A 1.25km section of Khovd river embankment along north edge of Bag 5 will be upgraded to prevent seasonal flooding of Ulgii from spring highwater flows. Extra care must be taken to ensure that berms and / or silt curtains are placed between the riverbank works areas and the river to prevent soil erosion and siltation of the river.
Ulgii and Deluun soum center Dumpsite rehabilitation:
Tranche 1 will conduct a detailed needs assessment of solid waste management including operation of both dumpsites at Ulgii and Deluun soum and an assessment of the water table depth and groundwater quality. The dumpsites will also be cleaned and fenced to contain and prevent the continuation of solid waste wind-blow across land. Assessment of the depth of the water table and groundwater quality at both dumpsites is important to ensure that groundwater is not being contaminated by the garbage in existing dumpsites.
Operation Phase Planned expansion of central hot water heating in Ulgii could lead to increased air pollution because the heating plant will not be upgraded by Tranche 1, and current emissions of plant do not meet national or international standards (i.e., IFC-EHS, WHO 2007). Planned increased extraction of groundwater for expanded potable water supplies, and new extractions of groundwater and surface water for the meat processing facilities and irrigation schemes could create water shortages for those project components, and for other “downstream” users in Ulgii, and Deluun and Buyant soums soum. The feasibility estimates of the water requirements of the various project components, and in particular, sustainable local water resource availability must be confirmed at detailed design stage. Monitoring of effluent quality and water quality of receiving waters is required for planned and new WTTP in Ulgii. The same monitoring is required for new wastewater collection and treatment planned for Deluun soum and the Agropark facilities in Ulgii and Deluun such as meat processing facilities to confirm that planned wastewater treatment at the new WWTPs actually meets targeted international standards (i.e., IFC-EHS 2007).
Water quality monitoring of surface waters downstream of the irrigated fodder/hay farms near Ulgii and Buyant and Deluun soums is required to confirm that the specially designed peripheral, treed swales/ditches of the irrigation schemes that are designed to capture and contain irrigation runoff are effective at preventing runoff from the fertilized fields from entering downstream surface waters. Source: Asian Development Bank.
10
IV. PUBLIC CONSULTATION
25. The stakeholder consultation program developed for the Ulgii, and Deluun and Buyant soums began with the consultation with affected stakeholders in both locations on the feasibility design of Tranche 1 (see chapter V of IEE). The second step will be to disclose the draft IEE to the same affected stakeholders to obtain their review and comment. Information disclosure and consultation of affected stakeholders will continue during the pre-construction phase, throughout the construction phase via the GRM (chapter G of IEE), and will continue into the operation phase of Tranche 1.
26. A key element of the successful consultation and meaningful input of stakeholders affected by Tranche 1 of the project will be monitoring of the efficacy of the engagement of project stakeholders. During the pre-construction, detailed design phase the stakeholder engagement plan will be finalized by the PISC with close input from the EA (MCUD). Throughout the construction phase of the project stakeholder engagement along with implementation of the GRM will be monitored by the PISC with support from the PMO in Ulaanbaatar, and the three Aimag PMOs. During the operational phase of completed Tranche 1 The MCUD and DBM with support from the three Aimag governments will take responsibility for monitoring the continued engagement and consultation with the affected urban and herder communities.
V. MITIGATION PLAN 27. The impact mitigation measures of the EMP are presented in a comprehensive mitigation plan in Table 4. Similar to the IEE the mitigation plan is structured by the three development phases of ASDIP defined by pre-construction; construction; and post construction operational phases. The mitigation plan addresses the environmental issues and concerns raised at the stakeholder consultation meetings. 28. The mitigation plan combines construction phase impacts that are common to project components, for which, single mitigation measures are prescribed. In this way common mitigation measures are not re-stated numerous times causing unwieldy and unnecessary redundancy. However, impacts and required mitigations that are specific to a project component are identified, and common mitigations that are particularly important for a potential impact on an environmental or cultural component are emphasized where needed. 29. The mitigation plan identifies potential impacts, required mitigations, responsible parties, location, timing, and indicative costs. As indicated in the description of the Institutional Arrangements for the EMP above, the PMO-ALAMGac is responsible for the environmental management of the public infrastructure investments with support from MOFALI on the environmental management of the public agribusiness and pastureland investments. The PIU-DBM will oversee the management of all private sector investments in agribusiness components either directly or through the Xac Bank and Khan Bank FIs. The mitigation plan by design is comprehensive in order for the plan to be updated easily to meet the final detailed designs of Tranche 1 in Ulgii, and Deluun and Buyant soums.
11
Table 4: Mitigation Plan
ASDIP
Activity
Potential Environmental
Impacts Proposed Mitigation Measures Location Timing Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision Implementation
Pre-Construction, Detailed Design Phase of ALL Infrastructure and Agribusiness Components
Confirmation of required resettlement, and compensation
No negative environmental impacts
1. Participating khasha households in Bags 13 and optional Bag 5 well informed of ASDIP implementation. Procedures and schedule for ger redevelopment must be distributed to affected Bags ahead of initial meetings.
All affected persons in all Aimag/soum project areas
Before project implemented
See LARP See LARP PMO LARP committees
Finalization of levels of Khasha participation in Bag 13 and optional Bag 5
No negative environmental impacts on participants and non-participants
As part of reporting on DD of Tranche 1
No marginal cost
APO
Disclosure, and engagement of community
No community impacts
2. Initiate Information Disclosure and Grievance Mechanisms, and IEE distributed to community.
For all construction sites.
Beginning of project
Quarterly, next PubCon report
No marginal cost
PMO APO/PISC
GoM approvals No negative impact
3. Notify MET of project initiation to ensure EIA requirements complete, and obtain required project permits and certificates.
For all sites Before initiation of construction
As required by PMO reporting
No marginal cost
PMO/MET PISC-IES
Sustainable water supply assessment
Insufficient water supply for project and other all users
4. Confirm local groundwater and surface water availability assessments (hydrogeology) during low flow periods at sites of components potentially requiring relatively large volumes of water (e.g., irrigation schemes).
5. Conduct assessment of water consumption of other local and downstream users of water resources.
Catchments of WTP facilities, agropark facilities, and all irrigation schemes
Before finalizing size of water consuming components
As required by detailed design (DD) and DD reporting (see 6 ix below)
No marginal cost
PISC/PMO PISC
Detailed designs of Tranche 1 completed,
Minimize negative environmental impacts
6. Work with PISC to complete detailed designs of components.Ensure the following measures are included: (i) confirm water requirements
of all project components
12
ASDIP
Activity
Potential Environmental
Impacts Proposed Mitigation Measures Location Timing Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision Implementation with focus on agro-business components (i.e., irrigation schemes, meat processing facilities);
(ii) spill management prevention and emergency response plans for all construction sites;
(iii) no disturbance or damage to culture property and values;
(iv) no unnecessary cutting of trees;
(v) after receiving permit from DoE locate all required aggregate borrow pits away from human settlements with fencing and access barriers;
(vi) plan ahead to ensure no disruption to normal pedestrian and vehicle traffic along all Ger pilot roads and all construction sites with established contingency alternate routes;
(vii) plan to notify and provide residents and merchants of construction activities and schedule to minimize disruption to normal household, community, and commercial activities;
(viii) measures to prevent or minimize disturbances to affected schools and cultural/social centers;
(ix) site remediation and restoration plan for all construction sites;
(x) validate sustainability of water consuming
Final siting Before construction initiated
Once with updated detailed design documents
No marginal cost
PMO PMO/PISC
13
ASDIP
Activity
Potential Environmental
Impacts Proposed Mitigation Measures Location Timing Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision Implementation components with accurate assessment of seasonal low-flow supplies of source groundwater and surface waters, and downstream user demands;
(xi) ensure all components vulnerable to flood exposure incorporate flood resistant designs; and
(xii) ensure all components not just ger redevelopment maximize energy efficiency, e.g., LED lighting.
Update EMP Positive environmental impacts
7. Review final alignments for all new/upgraded linear infrastructure (i.e., all utility trunk lines, roads, transmission lines, water reservoir, and update construction mitigation measures to prevent/minimize impacts on adjacent property.
8. Review new/rehabilitated buildings including new Agro-park facilities, and update construction mitigation measures to prevent/minimize impacts on adjacent property
9. Review final improvements to Khovd riverbank and update measures to prevention/ mitigation of erosion and sedimentation of Khovd river.
10. Review final water diversion/head structure for irrigation scheme and update mitigation measures to ensure no erosion/sedimentation of Buyant river.
11. Confirm treated effluent and emission qualities of new WWPTs and Ulgii heating plant
All sites on Ulgii, and Buyant and Deluun soums
Before construction initiated
Once with updated EMP
See Monitoring Plan below
PMO
PISC-IES
14
ASDIP
Activity
Potential Environmental
Impacts Proposed Mitigation Measures Location Timing Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision Implementation will meet IFC-EHS (2007) standards including sludge management.
12. Confirm actions to improve solid waste dumpsites in Ulgii and Deluun soum with DoE.
13. Identify any/all new potential environmental impacts of Tranche 1 and include in EMP.
14. Submit updated EMP including any new potential impacts to MCUD and ADB to review.
15. Clarify individual mitigation management sub-plans for use in CEMPs: (i) construction drainage; (ii) soil erosion; (iii) noise and dust; (iv) contaminated spoil disposal; (v) construction solid and wastewater management and disposal; (vi) construction and urban traffic congestion; (vii) utility and power disruption; (viii) worker and public safety; (ix) tree and vegetation removal and site restoration; (x) construction materials acquisition, transport, and storage; and (xi) cultural chance finds. The scope of chance finds procedure must be reviewed at DED to ensure it includes all defined excavation sites for the final designs of utility trunk lines and all other infrastructure.
16. Special mitigation subplan for Bag 13 and optional Bag 5 must be finalized for khasha housing demolition, site clearing, soil remediation, and disposal of residual khasha coal supplies and surplus
All sites on Ulgii, and Deluun and Buyant soums
Before construction initiated
Once with updated EMP
See Monitoring Plan below
PMO
PISC-IES
15
ASDIP
Activity
Potential Environmental
Impacts Proposed Mitigation Measures Location Timing Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision Implementation homestead appliances. Subplan can be part of worker and public safety subplan.
17. Special subplan must be available for disposal of any asbestos that might be found in the Khasha homesteads that will be demolished.
18. Update cost of EMP.
Confirm GoM
approved
construction
waste disposal
sites
No negative impact
19. Notify DoE to confirm locations of sites for borrow pits and disposal areas for construction for Ulgii, and Deluun and Buyant soums, and obtain required permits.
All areas in Ulgii, Deluun, and Buyant
Before construction
As required in PMO report
No marginal cost
PMO/MET PISC-IES
Develop bid
documents
No negative environmental impact
20. Ensure updated EMP is included in contractor tender documents, and that tender documents specify required contractor-defined CEMPs (#13) that also must be budgeted.
21. Specify in bid documents that contractor must have experience with designing and implementing CEMPs, or must provide staff with the experience.
All sites in Ulgii, Deluun, and Buyant
Before construction begins
Once for all tender documents
No marginal cost
ADB/PMO PISC
Create
awareness of
physical cultural
resources in
area
No negative environmental impact
22. PMO/PISC to review potential locations of physical cultural resources, and explain possible PCR to contractors
All areas in Ulgii, Deluun, and Buyant
Before construction begins
Once in PMO report
No marginal cost
PMO PISC-IES
Obtain and
activate permits
and licenses
Prevent or minimize impacts
23. Contractors to comply with all statutory requirements set out by GoM for use of construction equipment, and operation construction plants such as concrete batching.
For all construction sites
Beginning of construction
Once in PMO report
No marginal cost
PMO PISC/contractors
Capacity
development
No negative environmental impact
24. Develop and schedule training plan for PMO/PISC-IES to be able to fully implement EMP,
For all project areas Ulgii, Deluun, and
Before construction begins
Initially, refresher later if needed in
No marginal cost
PMO/PISC PISC
16
ASDIP
Activity
Potential Environmental
Impacts Proposed Mitigation Measures Location Timing Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision Implementation and to manage implementation of mitigation measures by contractors.
25. Create awareness and training plan for contractors whom will implement mitigation measures.
Buyant PMO training plan
Recruitment of
workers
Spread of sexually transmitted disease
26. Use local workers as much as possible thereby reducing #s of migrant workers.
All worker forces
Throughout construction phase
Worker hiring stages in procurement plan report
No marginal cost
PMO Contractor’s bid
documents
Construction Phase of All Urban and Agribusiness Infrastructure
Initiate EMP
and sub-plans,
Prevent or minimize impacts
27. Initiate updated EMP and CEMPs including individual management sub-plans for different potential impact areas that are completed in pre-construction phase (see below).
For all construction sites
Beginning of construction
Once in
1st EMR
No marginal cost
PMO/PISC Contractor
Operation of
worker camps
Pollution and social problems, e.g., STDs, disputes, fights, robberies
28. Locate worker camps away from human settlements.
29. Ensure adequate housing and waste disposal facilities including pit latrines and garbage cans.
30. A solid waste collection program must be established and implemented that maintains a clean worker camps
31. Locate separate pit latrines for male and female workers away from worker living and eating areas.
32. A clean-out or infill schedule for pit latrines must be established and implemented to ensure working latrines are available at all times.
33. Worker camps must have adequate drainage.
Any temporary worker camp or staging area
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
17
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
34. Local food should be provided to worker camps. Guns and weapons not allowed in camps.
35. Transient workers should not be allowed to interact with the local community. HIV Aids education should be given to workers.
36. Camp areas must be restored to original condition after construction completed.
Training and capacity
Prevent of impacts through education
37. Implement training and awareness plan for PMO/APO and contractors.
PMO/APO offices, construction sites
Beginning of construction
After each event in PMO’s EMR report
No marginal cost
PMO/PISC PISC-IES
Operation of borrow pits
Pollution, injury, increased construction traffic congestion
38. All selected borrow pits should be reviewed by DoE.
39. Select pits in areas with low gradient and as close as possible to construction sites.
40. Required aggregate volumes must be carefully calculated prior to extraction to prevent wastage.
41. Pits and quarries should not be located near surface waters, houses, or cultural property or values.
42. All topsoil and overburden removed should be stockpiled for later restoration.
43. All borrow pits and quarries should have a fence perimeter with signage to keep public away
44. After use pits and quarries should be dewatered and permanent fences installed with signage to keep public and domestic animals such as cows, sheep and goats out, and restored as much as possible using original overburden and topsoil.
All borrow pits and construction areas.
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
18
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
45. Unstable slope conditions in/adjacent to the quarry or pit caused by the extractions should be rectified with tree planting.
Transport of construction materials, and storage of materials on site
Pollution, injury, increased construction traffic congestion
46. Define and schedule how materials are extracted from borrow pits and rock quarries, transported, and handled and stored at sites.
47. Define and schedule how fabricated materials such as steel, wood structures, and scaffolding will transported and handled.
48. All aggregate loads on trucks should be covered.
49. Piles of aggregates at sites should be used/or removed promptly, or covered and placed in non- traffic areas
50. Stored aggregates well away from all human activity and settlements, and cultural (e.g., schools, hospitals), and ecological receptors. Bitumen batch plants and handling areas should be isolated from residential and commercial areas.
For all construction areas
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC contractor
Asphalt production, and application
Air pollution, land and water contamination, and traffic and access problems
51. Contractors must be well trained and experienced with the production, handling, and application of bitumen.
52. All spills should be cleaned immediately and handled as per hazardous waste management plan, and according to GoM regulations.
53. Bitumen should only be spread on designated road beds, not on other land, near or in any surface waters, or near any human activities.
For all construction areas.
Throughout construction phase
Monthly contractor reports
No marginal cost
PMO/PISC contractor
19
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
54. Bitumen should not be used as a fuel.
Implement spoil management sub-plan
Contamination of land and surface waters from excavated spoil, and construction waste
53. Uncontaminated spoil to be disposed of in DoE-designated sites, which must never be in or adjacent surface waters. Designated sites must be clearly marked and identified
54. Spoil must not be disposed of on sloped land, near cultural property or values, ecologically important areas, or on/near any other culturally or ecologically sensitive feature.
55. Where possible spoil should be used at other construction sites, or disposed in spent quarries or borrow pits authorized by DoE as per requirements of Law on Waste
56. A record of type, estimated volume, and source of disposed spoil must be recorded.
57. Contaminated spoil disposal must follow DoE/GoM regulations including handling, transport, treatment (if necessary), and disposal.
58. Suspected contaminated soil must be tested, and disposed of in designated sites identified as per DoE regulations.
59. Before treatment or disposal contaminated spoil must be covered with plastic and isolated from all human activity.
All excavation areas
Throughout construction phase
Monthly Contractor reports
See Monitoring Plan for contaminated soil analyses
PMO/PISC contractor
Implement solid and liquid construction waste sub- plan
Contamination of land and surface waters from construction waste
60. Management of general solid and liquid waste of construction will follow DoE/GoM regulations, and will cover, collection, handling, transport, recycling,
All construction sites and worker camps
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC
Contractor
20
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
and disposal of waste created from construction activities and worker force.
61. Areas of disposal of solid and liquid waste to be determined by DoE.
62. Disposed of waste should be catalogued for type, estimated weigh, and source.
63. Construction sites should have large garbage bins.
64. A schedule of solid and liquid waste pickup and disposal must be established and followed that ensures construction sites are as clean as possible.
65. Solid waste should be separated and recyclables sold to buyers in community.
Hazardous Waste 66. Collection, storage, transport,
and disposal of hazardous
waste such as used oils,
gasoline, paint, and other
toxics must follow DoE/GoM
regulations.
67. Wastes should be separated
(e.g., hydrocarbons, batteries,
paints, organic solvents) 68. Wastes must be stored above
ground in closed, well labeled, ventilated plastic bins in good condition well away from construction activity areas, all surface water, water supplies, and cultural and ecological sensitive receptors.
69. All spills must be cleaned up completely with all contaminated soil removed and handled with by contaminated spoil sub-plan.
All construction sites and worker camps
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
21
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
Implement dust management sub-plan
Unnecessary dust pollution
70. Regularly apply wetting agents to exposed soil and construction roads which must be budgeted in contractor bid documents.
71. Cover or keep moist all stockpiles of construction aggregates, and all truckloads of aggregates.
72. Minimize time that excavations and exposed soil are left open/exposed. Backfill immediately after work completed.
All construction sites
Fulltime Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
Implement noise subplan
Unnecessary noise pollution
73. As much as possible restrict working time between 07:00 and 18:00 during summer construction work period, i.e., in particular are activities such as pile driving.
74. Maintain all equipment in proper working order 75. Replace unnecessarily noisy
vehicles and machinery. 76. Vehicles and machinery to
be turned off when not in use.
77. Construct temporary noise barriers around excessively noisy activity areas where possible.
All construction sites
Fulltime Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
Implement water supply, heating, and electricity disruption sub-plan
Loss or disruption of water supply, heating, and electricity
78. Develop carefully a plan of days and locations where outages in utilities and services will occur or are expected.
79. Contact local utilities and services with schedule, and identify possible contingency back-up plans for outages.
80. Contact affected community to inform them of planned
All construction sites
Fulltime Monthly Contractor reports
No marginal cost
PMO/PISC,
Utility
representatives
Contractor
22
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
outages. 81. Try to schedule all outages
during low use time such between 24:00 and 06:00.
Implement tree and vegetation removal, and site restoration sub-plan
Damage or loss of trees, vegetation, and landscape
82. Contact DoE/MET for advice on how to minimize damage to trees and vegetation.
83. Restrict all tree and vegetation removal to strict road and utility alignments.
84. Prevent tree removals, and install protective physical barriers around trees that do not need to be removed.
85. All areas to be re-vegetated and landscaped after construction completed with allocated budget. Consult DoE/MET to determine the most successful restoration strategy and techniques. Aim to replant three trees for each tree removed.
All construction sites
Beginning and end of ASDIP
Monthly Contractor reports
No marginal cost
DoE/PMO/
PISC
Contractor
Implement erosion control sub-plan
Land erosion 86. Berms, and plastic sheet fencing should be placed around all excavations and earthwork areas specifically to protect Khovd river for irrigation schemes
87. Earthworks should be conducted during dry periods.
88. Maintain a stockpile of topsoil for immediate site restoration following backfilling.
89. Protect exposed or cut slopes with planted vegetation, and have a slope stabilization protocol ready.
90. Re-vegetate all soil exposure areas immediately after work completed.
All construction sites
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
Implement worker and
Public and worker injury,
91. Proper fencing, protective barriers, and buffer zones should
All construction
Fulltime Monthly Contractor
No marginal cost
PMO/PISC Contractor
23
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
public safety sub-plan
and health be provided around all construction sites and along all roadways
92. Sufficient signage and information disclosure, and site supervisors and night guards should be placed at all sites
93. Worker and public safety guidelines of DoE/GoM should be followed.
94. Speed limits suitable for the size and type of construction vehicles, and current traffic patterns should be developed, posted, and enforced on all roads used by construction vehicles.
95. Standing water suitable for disease vector breeding should be filled in.
96. Worker education and awareness seminars for construction hazards should be given at beginning of construction phase, and at ideal frequency of monthly. A construction site safety program should be developed and distributed to workers.
97. Appropriate safety clothing and footwear should be mandatory for all construction workers.
98. Adequate medical services must be on site or nearby all construction sites.
99. Drinking water must be provided at all construction sites.
100. Sufficient lighting be used during necessary night work.
101. All construction sites should be examined daily to ensure unsafe conditions are removed.
sites reports
Civil works Degradation of water
102. Protective berms, plastic sheet fencing, or silt curtains should
All construction
Throughout construction
Monthly c ontractor
No marginal cost
PMO/PISC Contractor
24
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
quality and aquatic resources
be placed between all earthworks for Khovd riverbank rehabilitation and construction of irrigation canals to protect Khovd river
103. Erosion channels must be built around aggregate stockpile areas to contain rain-induced erosion.
104. Earthworks should be conducted during dry periods.
105. All construction fluids such as oils, and fuels should be stored and handled well away from all surface waters including Khovd river.
106. No waste of any kind is to be thrown into surface waters including Khovd river.
107. No washing or repair of machinery near any surface water including Khovd river.
108. Temporary pit latrines to be located well away from surface waters, homes, and businesses.
109. All existing drainage canals and channels to be protected the same way Khovd river.
sites phase reports
Civil works Degradation of terrestrial resources
110. All construction fluids such as oils, and fuels should be stored and handled well away from both rivers.
All construction sites
Throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
Implement construction and urban traffic sub- plan
Traffic disruption, accidents, public injury
111. Schedule construction vehicle activity during light traffic periods. Create adequate traffic detours, and sufficient signage and warning lights.
112. Post speed limits, and create dedicated construction vehicle
All construction sites
Fulltime Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
25
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
roads or lanes. 113. Inform community of location of
construction traffic areas, and provide them with directions on how to best co-exist with construction vehicles on their roads.
114. Demarcate additional locations where pedestrians can develop road crossings away from construction areas.
115. Provide construction road and walkway lighting.
Implement construction drainage sub-plan
Loss of drainage and flood storage
116. Provide adequate short-term drainage away from construction sites to prevent ponding and flooding.
117. Manage to prevent borrow pits and quarries to fill with water. Pump periodically to land infiltration or nearby water courses.
118. Install temporary storm drains or ditches for construction sites
119. Ensure connections among surface waters (ponds, streams) are maintained or enhanced to sustain existing stormwater storage capacity
All areas near stream
Design and construction phases
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
Civil works and Chance finds sub-plan
Damage to cultural property or values, and chance finds
120. As per detailed designs all civil works should be located away from all cultural property and values in and outside Ulgii, and Deluun and Buyant soums.
121. Chance finds of valued relics and cultural values should be anticipated by contractors. Site supervisors should be on the watch for finds.
122. Upon a chance find all work stops immediately, find left untouched, and PMO notified to
All construction sites
At the start, and throughout construction phase
Monthly Contractor reports
No marginal cost
PMO/PISC Contractor
26
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
determine if find is valuable. Culture section of MET notified by telephone.
123. Work at find site will remain stopped until MET allows work to continue.
Construction of Agro-business facilities
All worker and civil works activities, construction materials acquisition, transport and application to build agribusiness facilities
Potential short-term disturbances and impacts of infrastructures on environment and communities.
124. The mitigation measures and subplans prescribed for the construction of the urban and agribusiness infrastructures detailed above apply to the construction of the agribusiness facilities.
All construction sites
Throughout construction phase
Monthly c ontractor reports
No marginal cost
PMO/PISC contractor
Siting of Agro-parks: (Disease Free establishments (DFE), Laboratories and Veterinary services, Research and development centers, Meat processing facilities, Production centers)
Siting of Agroparks in/near Ulgii and Deluun
Potential aesthetic impact
125. Locate laboratories, RandD centers, and Production centers away from homesteads, businesses, and surface waters, and install fenced and treed perimeter around entire Ago-park.
Near Ulgii and Deluun soum
At final detailed design stage
Final DD report
No marginal cost
EA/PMO/
PISC
Contractor
Siting of meat processing facilities in near Ulgii and Deluun
Potential aesthetic and pollution impacts
126. Locate both meat processing facilities including animal holding areas and WWT facility well away from homesteads, businesses, surface waters, and groundwater water wells, and install treed perimeter fence.
127. Locate treated wastewater of meat processing facilities (collection reservoir or discharge pipe) away from homesteads and users of receiving environment
128. Ensure either onsite or offsite plan for sustainable disposal for
Outside Ulgii and Deluun soum
At final detailed design stage
Final DD report
No marginal cost
EA/PMO/
PISC
Contractor
27
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
solid processing wastes is established.
Siting of Animal Disease Free Establishment (DFE)
Potential aesthetic impact
129. Locate DEFs away from homesteads, businesses, and surface waters, and install separate treed and fenced perimeter.
Near Ulgii and Deluun soum
At final detailed design stage
Final DD report
No marginal cost
EA/PMO/
PISC
Contractor
Siting of WWTP of Agro-park
Potential aesthetic impact
130. Isolate WWTP inside Agro-park with a separate treed and fenced perimeter.
Near Ulgii and Deluun soum
At final detailed design stage
Final DD report
No marginal cost
EA/PMO/
PISC
Contractor
Siting and Construction of Irrigation Networks for Fodder/hay farms
Siting of Fodder farms (at irrigation scheme)
Potential pollution impacts
131. Ensure site is away from Khovd river, or that there is a treed peripheral swale or ditch around fodder farm to prevent and contain runoff from fodder fields from re-entering both source rivers
Deluun and Buyant soums
At final detailed design stage
Final DD report
No marginal cost
EA/PMO/
PISC
Contractor
Construction of water diversion structure and canals
Land erosion and sedimentation, and pollution of Buyant and Deluun rivers
132. Silt curtains and berms should be placed between construction of diversion structure to minimize soil erosion. Canal excavations must be well away from source river.
133. Construction equipment must not be operated in or adjacent to source river.
134. No construction or worker waste must enter river, pit latrines located well away from rivers
Deluun and Buyant soums
At final detailed design stage
Final DD report
No marginal cost
EA/PMO/
PISC
Contractor
Operation of Urban and Agribusiness Infrastructure
28
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
Operation of new and upgraded infrastructure facilities and buildings
Risk of vehicle accidents and air pollution
135. Ensure enforced, well marked safe speed limits are posted along new and upgraded roads and in areas with increased traffic.
136. All vehicles that use the roads should be required to be in good working condition with regular inspection.
Along all new upgraded roads and to new facilities roads
Fulltime Biannual Aimag/soum Roads Dept Report
O&M A/S Roads Dept.
Operation of new or upgraded utility networks including rehabilitated Khovd riverbank in Ulgii.
Equipment failure and maintenance needs
137. Regular maintenance and inspections of utility networks including rehabilitated riverbank
Ulgii and Deluun
Fulltime Biannual Utility and Bayan-Ulgii Aimag government reporting
O&M Utility and Bayan-Ulgii Aimag
government
Regular monitoring of operation of upgraded or new WWTPs in Ulgii and Deluun, including effluent qualities
Pollution of Khovd river
138. The effective operation of the WTTPs should be monitored to determine how well the increased load of wastewater from the urban areas treated by the plants meet MNS standard or IFC-EHS (2007) standards.
WWTPs in Ulgii
and Deluun, and below effluent discharges
Quarterly
Regular monitoring of operation of new heating plant in Ulgii emission qualities
Air pollution 139. The effective operation of the new heating plant in Ulgii should be monitored to determine how well plant emissions from the increased production of hot water meet MNS standard or IFC-EHS (2007) standards.
Heating plant in
Ulgii,
Quarterly Biannual Utility and Bayan-Ulgii Aimag government reporting
O&M Utility and Bayan-Ulgii Aimag
government
Operation of Agribusiness Facilities
Meat processing facilities
Monitoring of groundwater supply to meat
Insufficient process water for meat processing
140. Local water table depth and groundwater availability, and potential shortages for meat
Catchment of meat processing
Monthly Biannual Bayan-Ulgii Aimag /
O&M Bayan-Ulgii Aimag/soum
government
29
ASDIP
Activity
Potential Environmental
Impacts
Proposed Mitigation Measures
Location
Timing
Activity
Reporting
Estimated
Cost (USD)
Responsibility
Supervision
Implementation
processing facilities
facilities and other groundwater users
processing facilities and other users should be monitored.
facilities Deluun soum government reporting Monitoring of
treated effluent and solid waste disposal from meat processing facilities
Pollution of receiving Khovd river or land
141. The quality of the treated effluent effluents (BOD, oxygen, coliform bacteria, TSS, NH3, NOx, TP), the downstream quality of Khovd river, and the location of the disposal site for solid waste should be monitored to determine whether waste streams meet MNS or IFC-EHS (2007) standards.
At meat processing facilities, in receiving environment (river) of treated effluent, and solid waste disposal site
Biannually
Fodder Farms and Irrigation Network
Monitoring downstream surface and groundwater quality
Pollution of groundwater, and downstream Khovd river from possible escapement of runoff from designed peripheral catchment swales / ditches of fertilized fields.
142. The quality of groundwater, and Khovd river water should be monitored for levels of BOD, oxygen, coliform bacteria, TSS, NH3, NOx, TP, and other active ingredients in the fertilizers that are used on the two fodder farms. The potential impact of potential degraded water quality on downstream users must also be monitored.
At fodder/hay farms near Deluun and Buyant soums
Biannually Biannual Bayan-Ulgii Aimag / Deluun soum government reporting
O&M Bayan-Ulgii Aimag/soum
government
Water Diversion Insufficient water availability for downstream users of Khovd river
143. The consumption of river water by irrigation networks, and flow of river below network needs to be monitored as well as potential impact potential reduced flows on downstream users.
Above and below network, and downstream areas of other users
Quarterly Biannual Bayan-Ulgii Aimag / Deluun soum government reporting
O&M Rover basin management /
Bayan-Ulgii government
Source: Asian Development Bank.
VI. MONITORING PLAN
30. The environmental monitoring plan for the Bayan-Ulgii Aimag EMP is provided in Table 5. The monitoring plan is structured by the three development phases (pre-construction, construction, post-construction operation) of Tranche 1 and consists of environmental indicators, sampling locations and frequency, method of data collection, responsible parties, and estimated costs. The purpose of the monitoring plan is to determine the effectiveness of the impact mitigations, and at the same time, document unexpected positive or negative environmental impacts of the project components. Environmental monitoring will be conducted at sites sampled for the environmental baseline of Tranche 1 project areas. A. Environmental Quality Standards for Tranche 1 of ASDIP
31. Environmental quality standards and criteria for Mongolia are listed in Appendix A. The environmental standards provided by the Environmental, Health and Safety Guidelines of the IFC/World Bank (2007) should also be consulted to supplement GOM standards if required. The most stringent standards apply. 32. The licensed EIA firm will be required to implement the environmental monitoring under the supervision and coordination of the PMO/APO/PISC. The EIA firm will be responsible for the sampling and laboratory analysis of environmental parameters. The PMO and PISC-IES will coordinate monitoring work with the EIA Firm. The APO/PISC will also provide logistical support to the EIA firm where necessary for the implementation of environmental monitoring plan. B. Performance Monitoring
33. Performance monitoring is required to assess the overall effectiveness of the EMP. A performance monitoring system is normally developed by the EA (MCUD) for the entire Project. Select environmental indicators that will be affected primarily by the construction and operation phases of Tranche 1 are drawn from the mitigation and monitoring plans and summarized in Table 6. C. Reporting
34. Regular reporting on the implementation of mitigation measures, and monitoring activities during construction phase of Tranche 1 is required. Reporting is the responsibility the PMO-PISC with input from the APO and should be conducted in conjunction with regular meetings with stakeholders as part of the continuation of stakeholder communications. The mitigation and monitoring plans (Tables 4 and 5) summarize proposed timing of reporting. Appendix B provides an indicative monitoring report. 35. Annual reports on environmental monitoring and implementation of the Bayan-Ulgii Aimag EMP for Ulgii, and Deluun and Buyant soums will be prepared for the MCUD by the PMO with assistance from the IES-PISC and APOs.. The EMR will compile the monthly reports provided by contractor(s), the reports of the EIA firm on monitoring, and input from the IES of the PISC. The PMO’s report will be sent to the DoE, MET and ADB, and will table all indicators measured with the monitoring plan of EMP including performance monitoring indicators (Table 6) and will reference relevant MET environmental quality standards.
Table 5: Environmental Monitoring Plan
ENVIRONMENTAL MONITORING
Environmental Indicators
Location
Means of Monitoring
Frequency
Reporting
Responsibility Estimated Cost (USD)
Supervision Implementation
Pre-construction Phase – Completion of Environmental Baseline
Dry season - low flow - water table depth (m) and groundwater supply (m3/s)
Up-basin of: (i) upgraded WTPs and new wells; (ii) Agropark facilities (i.e., new meat processing facilities);
Existing hydrogeological reports and MNS or Int’l hydrogeology methods
Twice during wet season and dry season
Once
PMO/PISC
EIA Firm
$2,000
Groundwater quality (major ions, pH, nutrient forms of N and P, metals (Pb, Hg, Fe, Zn), coliform bacteria
At new wells and at two dumpsites
MNS (ISO) 5667-11:2000
Once during dry season
$3,000
Low flow monthly discharge (m3/s)
Khovd river at finalized diversion points to irrigation schemes in Buyant and Deluun soums
Existing reports and MNS OIML R 102:2001
MNS 4047:1988
Once, during wet and dry season months (high and low)
$2,000
Confirm location of community drinking water kiosk, and sensitive cultural property and values
Throughout Ulgii, and both soums project sites
Consultation with community,
Once
PISC-IES
No marginal cost
Inventory of present and past land uses that could cause contaminated soil.
Possible contaminated lands at all excavation sites in project areas
Using existing reports and field and analytical methods approved by MET.
Once Once PMO/PISC EIA Firm $400.
Public issues/interest At all project sites Hotline and initiation of GRM
Continuous Monthly PMO/PISC PMO No marginal cost
32
ENVIRONMENTAL MONITORING
Environmental Indicators
Location
Means of Monitoring
Frequency
Reporting
Responsibility Estimated Cost (USD)
Supervision Implementation
Construction Phase of Urban and Agribusiness components
Public comments and complaints
From all project areas including hotline telephone number posted at all construction sites in Ulgii, and Deluun and Buyant soums
Information transferred by hotline number or by GRM
Continuous public input PMO/PISC PMO No marginal cost
Qualitative air quality: dust, noise, and vibration levels
Baseline sampling stations and at all civil works sites not sampled
Visual observations of dust and noise from contractor and public. Qualitative indicators agreed with DoE/MET
Daily visual / qualitative records
monthly EIA firm $200.
Water quality: (TSS, Fe, Zn, pH, DO, BOD5, temperature, NH3, ecoli bacteria)
Project sites at Khovd river MNS 0017-2-3-16, 1998 MNS OIML R 102:2001 MNS 4047:1988. MNS (ISO) 5667-
11:2000
Quarterly during construction periods
$2,000
Soil quality: (ecoli bacteria, Pb, Hg, Fe)
Khasha lands in Ulgii that will develop modern TUs or Apts
Once during khasha land clearing
$1,500
Domestic (worker) and construction solid waste inside and outside construction sites including temporary worker camps.
At all construction sites and worker camps
Visual observations
Continuous Contractors No marginal cost
Incidence of worker or public accident or injury
At, or near all construction sites and construction equipment and materials storage sites
Direct observation Continuously Monthly PMO/PISC Contractors No marginal cost
33
ENVIRONMENTAL MONITORING
Environmental Indicators
Location
Means of Monitoring
Frequency
Reporting
Responsibility Estimated Cost (USD)
Supervision Implementation
Operation Phase
Incidence of traffic accidents, and pedestrian injury
On all new and upgraded roads in Ulgii and Deluun soum
Community and police reporting
Continuous Biannual Aimag / soum leaders, police, No marginal cost
Incidence of failure of new or upgraded below ground utility trunk lines (wastewater, heat,
water), electrical power, and Khovd
riverbank
At all project sites in Ulgii and Deluun
Community, Aimag / soum government, utility company observations and reporting
Aimag / soum leaders, utility companies
Effluent quality of new WWTPs (TN, NH3, NOx, TP, PO4, coliform bacteria, Pb, Hg, Fe, Zn)
Ulgii and Deluun MNS 0017-2-3-16, 1998 MNS OIML R 102:2001 MNS 4047:1988. MNS (ISO) 5667-
11:2000
Quarterly Biannual Utility companies with support from contracted EIA firm
O&M
Emissions quality of new heating plant (CO, NOx, SOx, CO2)
Ulgii
Water quality: (TSS, NO2, NO3, NH3, TP, PO4, BOD5, ecoli bacteria, Pb, Hg, Fe, Zn)
Khovd river upstream and downstream of effluent discharges from new WWTPs and below irrigation schemes (fodder farms).
Quarterly Biannual Aimag / soum leaders
Contracted EIA firm
O&M
Groundwater quality (NO2, NO3, NH3, TP, PO4, BOD5,)
At, and down-basin from irrigation schemes.
Biannually
Groundwater quality (NO2, NO3, NH3, TP, PO4, BOD5,)
At upgraded WTPs and from new wells
Source: Asian Development Bank.
Table 6: Performance Monitoring Indicators for ASDIP
Major Environmental Component
Key Indicator
Performance Objective36
Data Source
Pre-construction Phase Public Consultation and Disclosure
Affected public and stakeholders of Ulgii, and Deluun Buyant soums
Meetings with stakeholders contacted during IEE and new stakeholders convened for follow-up consultation and to introduce grievance mechanism
Minutes of meeting, and participants list
EMP Updated EMP All stakeholders contacted during IEE re-contacted for follow-up consultation
EMP
Bid Documents Requirements of
CEMP37 based on EMP
EMP appended to bidding documents with clear instructions to bidders for CEMP
Bid documents
Training of PMO and implementing agencies
Training course(s)
and schedule
By end of P-C phase, required course(s) that will be delivered are designed and scheduled
Course(s) outline, participants, and schedule
Surface water and groundwater availability
Water table depth (m), and flow (m3/s)
Sustainable dry season - low flow - availability for project components and downstream users
Study reports and new surveys
Groundwater quality at dumpsites and at new wells
Major ions, pH, nutrient forms of N and P, Pb, Hg, Fe, Zn
Groundwater quality not affected by landfills, MNS: 6148:2010
New surveys
Construction Phase Cultural features Physical cultural
resources Unharmed or disturbed Aimag / soum
leaders, public Surface water quality
TSS, NO2, NO3, NH3, TP, PO4, BOD5, coliform bacteria, Pb, Hg, Fe, Zn
Levels never exceed pre- construction baseline levels
Monitoring by EIA firm
Qualitative air quality
Dust, noise, vibration Levels never exceed pre- construction baseline levels
EIA firm and contractor monitoring reports,
Soil quality at re-developed khashas
Coliform bacteria, Pb, Hg, Fe, Zn, NH3
No exposure of residents to any existing contaminated soil
Contractor and EIA firm monitoring reports
Public and worker safety
Frequency of injuries No increase in injuries or injury risk
Aimag / soum leaders, public, Contractor reports
Traffic Frequency of disruptions and blocked roadways
Disruptions, stoppages, or detours are managed to absolute minimum.
Public input, contractor reports, EMC
35
Major Environmental Component
Key Indicator
Performance Objective36
Data Source
reports
Operation Phase Increased traffic Traffic accidents No increases above
preconstruction levels Aimag /soum roads Dept
Operation of all utility and services infrastructure
Frequency of operations and supply failures
Zero incidence Aimag / soum leaders
Groundwater and surface water
Availability to project and all users
Sustainable supply Aimag / soum leaders
Surface water quality
Effluent quality of all new WWTPs
MNS 6561:2015 or IFC-EHS if more stringent
Aimag / soum leaders
Air quality Emissions quality of new Ulgii heating plant
MNS 6298: 2011 or IFC-EHS (WHO) if more stringent
Aimag leaders
36 Example Monitoring Report in Appendix B. 37 Contractor Environmental Management Plan developed from EMP in contractor bidding document. D. Estimated Cost of EMP
36. The costs for implementing the EMP are dominated by the completion of the hydrogeological baseline of available groundwater and surface water required for the agribusiness components (Table 5). The costs for implementing impact mitigation measures (Table 4) are included with the construction costs in contractor bid documents. The preliminary costs for the implementation of the EMP for Tranche 1 of ASDIP of USD $17,100.00.00 are summarized in Table 7. These costs include per diem technician fees, and a budget for training and capacity development of the PMO and EA. 37. An estimated budget of USD $7,000.00 is required for capacity building and training for environmental management in conjunction with other capacity development activities of the project such as occurring as part of overall the capacity development component of the PPTA. The costs to implement the EMP will need to be updated by the PISC in conjunction with the PMO during the pre-construction phase.
Table 7: Indicative Costs for Bayan-Ulgii Aimag EMP
Activity Type Estimated Cost
(USD)
Pre-construction Phase
Updating Environmental Baseline environmental quality $7,400.00
public consultation No marginal cost
Construction Phase
environmental quality $3,700.00
36
Activity Type Estimated Cost
(USD) public consultation No marginal cost
Post-construction Operation Phase
environmental quality O&M
public input
Capacity Development and training $7,000.00 Total $18,100.00
Source: Asian Development Bank.
E. Emergency Response Plan
38. An emergency response plan has been prepared to support the EMP and to protect the construction workers and general public. The draft emergency response plan is outlined in Appendix C.
37
APPENDIX A: ENVIRONMENTAL QUALITY STANDARDS OF MONGOLIA
Environmental Standards relevant to ASDIP
Code Standard
MNS 6298:2011 Boiler Emissions Guidelines: The Permissible Level of Air Pollutants from Power and Heating Plants.
MNS 5919:2008
The Permissible Level of Air Pollutants from Operations of Water Heating and Steam Generating Facilities at Power and Heating Plants
MNS 17.5.1.18:1983
Environmental Protection: Rehabilitation of Eroded Land/Category of Eroded Land.
MNS 17.5.1.19:1992
Environmental Protection: The General Requirements for Rehabilitation of Eroded Lands
MNS 3473:1983 Environmental Protection. Land, Land Use and Terms and Definitions
MNS 17.5.13:1980 Environmental Protection: Rehabilitation of Eroded Land, Terms and Definitions
MNS 17.0.0.06:1979
The System of Standards for Environmental Protection and Basic Rules
MNS 5914:2008 Environmental Protection: Rehabilitation of Eroded Land, Terms and Definitions
MNS 5918:2008 The General Technical Requirements for Vegetation of Eroded Land
MNS 17.2.0.07:1979
Air Pollutants and Category
MNS 17.2.1.17:1980
The Terms and Definitions of Industrial Pollutants to Atmosphere
MNS 4585:2016 Air Quality, The General Technical Requirements
MNS 3383:1982 The Terms and Definitions of Pollutant Sources for Atmosphere
MNS 5885:2008 The Permissible Level of Pollutant Substance to Air/General and Technical Requirements
MNS 3113:1981 The Technical Requirements for Determination of Air Emissions
MNS 17.2.3.16:1988
Guidelines for Monitoring of Air Quality in Urban Settlements
MNS 6063:2010 Air Quality: Permissible Level of Pollutants
38
Code Standard
MNS ISO 14064-2:2015
Greenhouse Gas- Second Chapter: Indicative Guidelines for Reporting and Monitoring on Changes and Adsorption of Greenhouse Emissions
MNS 3384:1982 The General and Technical Requirements for Sampling of Air Quality Test
MNS 17.1.1.10:1979
The Terms and Definitions for Water and Water Use
MNS 4047:1988 Guidelines for Monitoring of Surface Water Quality
MNS 3342:1982 The General Requirements for Protection of Underground Water from Pollution
MNS 6148:2010 Water Quality: The Permissible Level of Pollutants for Underground Water
MNS ISO 5667 13 2000
Water Quality-Sampling: Chapter 13: Sampling method for sludge from wastewater treatment plants
MNS 0899:1992 Sanitary Requirements for Sources of Water Supply to Urban and Household Purposes
MNS 0900:2005 Sanitary Requirements and Safety Assessment for Drinking
MNS ISO 5667:1:2002
Water Quality-Sampling: Chapter 1: Sampling method for drinking water
MNS ISO 5667-3:1999
Water Quality-Sampling: Chapter 3: Guidelines for handling of water samples
MNS ISO 5667:6:2001
Water Quality-Sampling: Chapter 6: Sampling method for rivers and streams
MNS 4943:2015 Water Quality: The General Requirements for Wastewater
MNS BS 8525-1:2015
The General Requirements for Grey Water
MNS ISO 5667-10:2001
Water Quality-Sampling: Chapter 10: Instructions for Sampling from Wastewater
MNS ISO 5667-7:2002
Water Quality-Sampling: Chapter 7: Instructions for Sampling from Water and Steam at Heat only Boilers (HOB)
MNS 6561:2015 Water Quality. General Requirements for Wastewater discharged to Sewerage Network
MNS 5666:2006 Water Biological Test: Determination Method of Dynamic Sludge
39
Code Standard ate Wastewater Treatment Plant
MNS 4288:1995 General Requirements for location, treatment process and levels of Wastewater Treatment Plant
MNS 3297:1991 Soil: Soil Quality Indicators and Norms in Urban Settlements
MNS 5850:2008 Soil Quality: The Permissible Levels of Soil Pollutants
MNS 3298:1991 Soil Quality: The General Requirements for Soil Sampling
MNS 3985:1987
Soil. Types of Sanitary Indicators of Soil
MNS 2305:1994 Soil. Instructions to Sampling, Packing and Storing of Soil Samples
MNS 4968:2000 Work Safety: General Requirements for Work Place
MNS 4994:2000 Work Safety: Vibrations Norm and General Requirements for Safe Operations
MNS 5147:2002 Electric and Static Conditions. Permissible Acid Level at Workplace
MNS 5150:2002 General Requirements for Safety Procedures with Electric Appliances
MNS 5146:2002 Work Safety: Electric Works; Protection and Wiring.
MNS 5145:2002 Electric Safety: The Maximum level of voltage and electric current
MNS 5002:2000 The General Requirements for Work Safety: The noise norms
MNS 0012.4.005:1985
The Labor Protection Equipment. Tools and Types
MNS 4244:1994 The General Requirements for Fire Safety
MNS 5390:2004 Work Safety and Sanitary Conditions
MNS 6458:2014 The General Requirements for Handling Toxic and Hazardous Chemicals
MNS 3474:2003 Plant Protection: The Terms and Definitions
MNS 5344:2011 The General Requirements for Transportation of Household Wastes
MNS 5872:2008 The Service Requirements for Power Supply
MNS 5043:2011
40
Code Standard The General Technical Requirements for Boilers with capacity of 0.10 МВт - 3.15МВт
MNS 5041:2001 The General Technical Requirements for Boilers with capacity up to 100 кВт
MNS 5045:2001 The Technical Requirements for Water Heating Boiler with solid fuel
MNS 5643:2006 The General Technical Requirements for Power Transmission Sub Station with Capacity of 25-2500 кВ•А
MNS 4084:1988 The General Technical Requirements for Water Heating Unit with Solar Panel
MNS 5207:2011 The Technical Requirements for Installation of the Fiber Optic Cable
MNS AASHTO 86:2005
The Technical Requirements for Concrete Structure of Flood Protection Facilities
MNS ISO 24511:2012
Operation of Water Supply and Sewerage Network: Operations Management and Maintenance of the Sewerage Facilities
MNS ISO 24512:2012
Operations Management and Maintenance of the Water Supply Facilities
MNS 5682:2006 The Technical Requirements for Pedestrians and Access for Disable Persons
MNS 4597:2014 The Technical Requirements for Road Signs
MNS 4759:2014 The Technical Requirements for Road Marks
MNS 4596:2014 The Operational Instructions for Road Signs, Marks, Fences and Traffic Lights
MNS 5342:2007 The General Requirements for Auto Parking Facilities
41
C-1: Surface Water Quality Standards
C-2 Noise Level Standards
42
C-3: Groundwater Quality Standards
43
C-4: Ambient Air Quality Standards
44
C-5 Soil Quality Standards
Table A-6: Boiler Emission Guidelines
45
APPENDIX B: EXAMPLE ENVIRONMENTAL MONITORING REPORT FOR ASDIP
Environmental Monitoring Report
List of Abbreviations Weights and Measures Contents I. Introduction
A. Purpose of the Report B. Background of the Project C. Project Management Arrangements D. Environmental Overview of the Project Area
II. Environmental Management
A. Compliance with Environment Related Project Covenants B. Environmental Responsibilities
III. Environmental Monitoring
A. Responsibilities in Monitoring Of Environmental Safeguard B. Key Environmental Quality Standards C. Selected Climate Data D. Environmental Quality Data E. Monitoring Results and Assessment
IV. Issues, Corrective Actions
A. Key Issues Identified B. Action Taken C. Planned Targets and Activities for the Next Reporting Period
V. Public Consultation, Grievance Redress Mechanism
A. Types of Grievance Expected and Eligibility Assessment B. GRM Steps and Timeframe
VI. Institutional Strengthening And Training
A. Objectives of Training Under Environment and Social Safeguard B. Objectives of the Training Under Resettlement Requirements
VII. Conclusion
A. Overall Progress of Implementation Of Environmental Management Measures B. Problems Identified and Actions Recommended
Appendices:
1. Environmental Management Plan During Construction Stage 2. TOR for Updating The EMP 3. Project Area 4. Actual Observations of Monitoring Plan Developed During IEE Report 5. Summary of Important Features of The Project Sub-Center Area 6. Environmental Monitoring Plan According to Mongolian Legislation 7. Environment Protection Plan /Epp/ 8. Grievance Redress Mechanism Defined for Tranche 1
46
APPENDIX C: EMERGENCY RESPONSE PLAN
Emergency Response Plan
39. The Contractors must develop emergency or incident response procedures during construction. In the operational phase the operator/civil authorities will have responsibility for any emergencies or serious incidents. The construction phase must ensure:
i) Emergency Response Team (ERT) of the Contractor as initial responder; ii) the District fire and police departments, emergency medical service, the Department
of Health (DPH), collectively referred to as the External Emergency Response Team (EERT), as ultimate responders.
40. The Contractor will provide and sustain the required technical, human and financial resources for quick response during construction.
Table 8: Roles and Responsibilities in Emergency Incident Response
Entity Responsibilities
Contractor Team (ERT) - Communicates / alerts the EERT. - Prepares the emergency site to facilitate the
response action of the EERT, e.g., vacating, clearing, restricting site.
- When necessary and requested by the EERT, lends support / helps during EERT’s response operations.
External Emergency Response Team (EERT)
- Solves the emergency/incident
Contractor Resources - Provide and sustain the people, equipment, tools and funds necessary to ensure Subproject’s quick response to emergency situations.
- Maintain good communication lines with the EERT to ensure prompt help response and adequate protection, by keeping them informed of Subproject progress.
41. The ERT will be led by the senior Contractor engineer (designated ERTL) on site with a suitably trained foreman or junior engineer as deputy. Trained first-aiders and security crew will be the core members of the ERT. 42. The Contractor will ensure that ERT members are physically, technically and psychologically fit for their emergency response roles and responsibilities. 43. Prior to the mobilization of civil works, the Contractor, through its Construction Manager, ERTL, in coordination with the PMU/ESS, will meet with the ultimate response institutions to discuss the overall construction process, including, but not limited to:
i) Subproject sites; ii) construction time frame and phasing; iii) any special construction techniques and equipment that will be used; i
47
iv) any hazardous materials that will be brought to and stored in the construction premise and details on their applications and handling/management system;
v) the Contractor’s Emergency Management Plan vi) names and contact details of the ERT members
44. The objective of this meeting is to provide the ultimate response institutions the context for:
i) their comments on the adequacy of the respective Emergency Management Plans ii) their own assessment of what types, likely magnitude and likely incidence rate of potential
hazards are anticipated iii) the arrangements for coordination and collaboration.
45. To ensure effective emergency response, prior to mobilization of civil works, the Contractor will:
i) set up the ERT; ii) set up all support equipment and facilities in working condition iii) made arrangements with the EERT; iv) conducted proper training of ERT members and encouraged and trained volunteers
from the work force; v) conducted orientation to all construction workers on the emergency response procedures and facilities, particularly evacuation procedures, evacuation routes, evacuation assembly points, and self-first response, among others; and vi) conducted drills for different possible situations.
46. To sustain effective emergency response throughout Subproject implementation an adequate budget shall be provided to sustain the capabilities and efficiency of the emergency response mechanism, the emergency response equipment, tools, facilities and supplies. Drills and reminders will take place regularly, the former at least every two months and the latter at least every month.
A. Alert Procedures
47. Means of communicating, reporting and alerting an emergency situation may be any combination of the following: i) audible alarm (siren, bell or gong); ii) visual alarm (blinking/rotating red light or orange safety flag); iii) telephone (landline); iv) mobile phone; v) two-way radio; and vi) public address system/loud speakers. Some rules relative to communicating/alerting will be:
(i) Whoever detects an emergency first shall immediately: - call the attention of other people in the emergency site, - sound the nearest alarm, and/or - report/communicate the emergency to the ERT.
(ii) Only the ERTL and, if ERTL is not available, the Deputy ERTL are authorized to communicate with the EERT. Exceptional cases to this rule may be necessary and must be defined in the Emergency Management Plans.
(iii) When communicating/alerting an emergency to the EERT, it is important to provide them with at least: i) the type of emergency situation; ii) correct location of the emergency; ii) estimated magnitude of the situation; iii) estimated persons harmed; iv) time it happened; v) in case of a spill, which hazardous substance spilled; and vi) in case of fire and explosion, what caused it. Such details would allow the EERT to prepare for the appropriate response actions.
48
48. For an effective reporting/alerting of an emergency situation:
(i) The names and contact details of the relevant persons and institutions must be readily available in, or near to, all forms of communication equipment, and strategically posted (at legible size) in all Subproject sites and vehicles:
- Most relevant construction/operations staffs namely, the ERTL, Deputy ERTL, first-aiders, supervising engineers, foremen
- EERT institutions/organizations - Concerned village authority/ies - IU Office, SO (ii) All Subproject sites must have good access to any combination of audible
and visual alarms, landline phones, mobile phones and two-way radio communication at all times.
(iii) Contractor’s construction vehicles must also be equipped with the appropriate communication facilities.
B. Emergency Response Situations
49. The following tables suggest general procedures that will be refined in the final EMP during detailed design and described in more detail in the Emergency Management Plans of the Contractor.
Table 9. Evacuation Procedure
Procedure Remarks Move out as quickly as possible as a
group but avoid panic. All workers/staff, sub-contractors, site
visitors to move out, guided by the ERT. Evacuate through the directed
evacuation route. The safe evacuation shall have been
determined fast by the ERTL/Deputy ERTL and immediately communicated to ERT members.
Keep moving until everyone is safely away from the emergency site and its influence area.
A restricted area must be established outside the emergency site, all to stay beyond the restricted area.
Once outside, conduct head counts. Foremen to do head counts of their sub-groups; ERTL/Deputy ERTL of the ERT.
Report missing persons to EERT immediately.
ERTL/Deputy ERTL to communicate with the EERT.
Assist the injured in evacuation and hand them over to the ERT first-aiders or EERT medical group
ERT to manage injured persons to ensure proper handling.
If injury warrants special care, DO NOT MOVE them, unless necessary and instructed/directed by the EERT.
ERTL/Deputy ERTL communicates with EERT to get instructions/directions in handling the injured.
49
Table 10: Response Procedure During Medical Emergency
Procedure Remarks Administer First Aid regardless of
severity immediately.
Fundamentals when giving First Aid: Safety first of both the rescuer and the
victim. Do not move an injured person unless: victim is exposed to more danger when
left where they are, e.g., during fire, chemical spill
it would be impossible for EERT to aid victims in their locations, e.g., under a collapsed structure
instructed or directed by the EERT. First AID to be conducted only by a
person who has been properly trained in giving First Aid.
Call the EERT emergency medical services and/or nearest hospital.
ERTL/Deputy ERTL or authorized on-site emergency communicator
Facilitate leading the EERT to the emergency site.
ERTL/Deputy ERTL to instruct: an ERT member on- site to meet EERT
in access road/strategic location. He/she shall hold orange safety flag to get their attention and lead them to site.
Other ERT members to clear access road for smooth passage of the EERT.
If applicable, vacate site and influence area at once, restrict site, suspend work until further notice.
Follow evacuation procedure.
Table 11: Response Procedure in Case of Fire
Procedure Remarks Alert a fire situation.
Whoever detects the fire shall
immediately: call the attention of other people in the
site, sound the nearest alarm, and/or Foreman or any ERT member among the
construction sub-group contacts the fire department (in this case it must be agreed on that it is alright for any ERT member in the sub-group to alert the fire department)
report/communicate the emergency to the ERTL/Deputy ERTL.
Stop all activities/operations and evacuate.
All (non-ERT) workers/staff sub-contractors, site visitors and concerned public to move out to safe grounds following the evacuation procedure.
Activate ERT to contain fire/control fire from spreading.
Guided by the training they undertook, ERT members assigned to mitigate the fire shall assess their own safety situation first before attempting to control fire spread.
50
Procedure Remarks Call the nearest fire and police stations
and, if applicable, emergency medical services.
When alerting the EERT, ERTL will give the location, cause of fire, estimated fire alarm rating, any injuries.
Facilitate leading the EERT to the emergency site.
ERTL/Deputy ERTL to instruct: an ERT member to meet the EERT in the
access road or strategic location and lead them to the site. He/she shall hold the orange safety flag to get their attention and lead them to the site.
some ERT members to stop traffic in, and clear, the access road to facilitate passage of the EERT.
ERT to vacate the site as soon as their safety is assessed as in danger.
Follow appropriate evacuation procedure.