Upload
vunguyet
View
216
Download
1
Embed Size (px)
Citation preview
Environmental Impact Study of a Pumped Storage Project on Hilly
Tract of Purulia, - A Remote Sensing GIS Analysis.
*@Abhisek Chakrabarty, ** Dilip Kumar Pal and *** Soumendu Chatterjee
*Lecturer, Dept. of Remote Sensing & GIS, Vidyasagar University, Midnapore-721102, W.B. India.
email: [email protected] / [email protected]
** Head, Department of Surveying & Land Studies,
The Papua New Guinea University of Technology, Lae, Papua New Guinea.
***Lecturer, Dept of Geography & Env. Management,
Vidyasagar University, Midnapore, W.B. India.
KEY WORDS: PPSP, Remote Sensing and GIS, Environmental Impacts Study, Cost Benefit
Analysis, Optimum Land and Water Use Planning, Sustainable Development.
ABSTRACT: The Purulia Pumped Storage Project (PPSP) on Kistobazar River of Ajodhya
Hills is developed to improve the peaking power scenario of West Bengal in India. The project
involves construction of two reservoirs with rock-fill dams comprising of central clay core, rock
crushing ground, cement mixing plant, staff quarters, service roads and disposal ground, which
in turn claimed a huge amount of forest and agricultural land. On the other hand stream
impoundment for filling the reservoirs created water scarcity in the canal fed agricultural land of
the downstream villages. This study attempts to find out the aerial extent of land use alteration,
and its consequent land degradation took place during the gestation period of the project (1998
to 2007). To accomplish this target a multi-temporal image analysis has been done with an IRS-
LISS-III data (GCR-23.5m) of 1999 and another IRS-LISS-IV MX data (GCR-5.8m) of 2005.
Hence a change detection map is prepared. This map reveals that the alteration of natural forest
and agricultural land to built-up area and permanent fallow were the most remarkable
happenings in this area. Cadastral map overlay on the change detection map clearly shows -
which private ownership lands are acquired by this project and which are simply damaged. Use
of SCS (NRCS) Curve Number method and Modified Universal soil Loss Equation (MUSLE)
helped to estimate the increase in runoff and soil erosion in the study area from 1999 to 2005.
Not only the physical impacts but also the economic and social impacts as a consequence of this
development are taken into consideration, and assessed with the help of “Questionnaire
Checklist” and “Leopold Matrix”. “Monetary Valuation” of all social and environmental
elements and Cost Benefit Analysis (CBA) are also done to judge the economic viability of this
project. Lastly an action plan for land use practices is prepared for the entire study area, which is
optimally suitable for the sustenance of the project and for the maintenance of the environmental
stability.
1.0 INTRODUCTION: The environmental impacts of a project are those resultant changes in
environmental parameters, in space and time, compared with what would have happened had the
project not been undertaken. The parameters may be any of the type of environmental receptors
like air quality, water quality, noise, levels of local unemployment and crime etc. (ref9). For
environmentally compatible and sustainable development In India, Ministry of Environment and
Forest (MoEF) is responsible for environmental concern. One such initiative is the notification
issued on 27 January 1994, making Environmental Impact Assessment (EIA) mandatory for 30
categories of developmental projects among which hydropower generation is significant one.
The main goal of EIA is to influence decision-making procedure of the project developers by
providing sound information on environmental impacts and the means for preventing or
reducing those impacts (ref1). In an advance stage of a project an environmentalist can only
investigate the impacts and take decision on mitigation measures. It is called Environmental
Impact Study (EIS), which is a systematic process that examines the environmental
consequences of development actions. The emphasis, compared with many other mechanisms
for environmental protection, is on mitigation of adverse impacts. Of course planners have
traditionally studied the impacts of developments on the environment, but invariably not in the
systematic, holistic and multidisciplinary way required by ElS.
Purulia is the western most district of West Bengal, India. The Purulia upland includes
the Baghmundi plateau, which is an extension of the Ranchi plateau of Chotanagpur region and
constituted by the granite-gneiss of oldest Precambrian or Archean formations. Among the
twenty Blocks of Purulia district Jhalda, Arsa, Baghmundi and Balarampur share the hilly tracts
of Ajodhya, with an average elevation of 600m. (ref6). In mid nineties the Government of West
Bengal along with the Major Japanese Corporate such as Mitsubishi Heavy Industries Ltd,
Taisei Corporation, Toshiba and Mitsui of Japan as well as Bharat Heavy Electricals Ltd. has
initiated the construction work for a 2952 crore pumped storage project named Purulia Pumped
Storage Project (PPSP) on the Kistobazar River, a tributary of Sobha River, in the southern
slope of Ayodhya hills (23°12′51′′N, 86°06′10″E). In future two additional Pumped Storage
Projects, i.e. Turga Pumped Storage Project (TPSP) and Kathlajal Pumped Storage Project
(KPSP), will be constructed on either side of PPSP (ref3).
Satellite remote sensing provides a reliable, accurate and updated database on land and
water resources, which is a prerequisite for change detection, environmental impact study and
optimal management of resources of a geographical area. As a demonstration of this concept the
newly built Purulia Pumped Storage Project (PPSP) of Ayodhya Hills and its surrounding area
of Baghmundi and Balarampur Blocks of Purulia, has been chosen as the study area for
Environmental Impact Study (EIS), land use planning and management for sustainable
development of the region. The study area consists of fourteen (14) micro-watersheds of the
southern slope of Ajodhya hills and foothill plains, and altogether form the physical boundary of
the area of interest. As physical boundary does not coincide with the administrative boundary,
mauza boundaries of Baghmundi and Balarampur Blocks covering the physical boundary
presumed as the administrative boundary of the study area. Thus Seventy-nine Mauzas
(villages) and four protected forest patches consisting of fourteen micro-watersheds are
considered as the ultimate study area (23°05′58′′N-23°15′01′′N, 85°58′11″E-86°12′22″E) of this
assignment (fig-1).
2.0 OBJECTIVES AND METHODOLOGY OF THE STUDY: There are three basic
objectives of this study. First one is the measurement of aerial extent of land use alteration, and
its consequent land degradation, that took place throughout the gestation period (1995-2005) of
the project. Change detection map was prepared by “Post Classification Comparison Change
Detection” (Jensen et. al. 1993), which shows changes in land use class for individual pixel and
also the no change pixels. This process needs two classified layers of same Ground Cell
Resolution (GCR). Therefore the LISS-IV data (5.8m) were degraded to match the resolution of
LISS-III data (23.5m). The “Degrade” command in ERDAS Imagine-8.6 is used to reduce the
resolution of an image by an integer factor in the X and Y directions. “Degrade” averages all of
the original "small" pixels that make up the new "big" pixels. These two classified layers of
same resolution are then compared pixel-by-pixel basis using RSI ENVI–4.3 software. A change
detection matrix also prepared with “To↔From” row and column, showing the aerial exchange
between major classes.
Photography and field survey for gully measurement helped to assess the level of land
degradation. In case of land degradation surface runoff and soil erosion of a particular region
will also increase. To fortify our findings, fourteen (14) micro watersheds are delineated inside
the study area from SOI toposheet, and runoff and soil loss from those micro watersheds, are
estimated for both the year 1999 and 2005. Detailed on the SCS Runoff Curve Number (CN)
method is described in Chapter-4 of National Engineering Handbook (NEH-4) of USDA Soil
Conservation Service (SCS 1969). SCS is nowadays known as NRCS i.e. Natural Resource
Conservation Service. The SCS runoff equation is given below (TR55, 1986).
Q=(P-0.3S)2/(P+0.7S)…………..………………[eq.-1]
Q is the daily runoff, P is daily rainfall, S is potential maximum retention after runoff
begins that is (25400 / CN) – 254, where CN refers to the runoff curve number of hydrologic
soil cover complex which is a function of soil type land cover and antecedent moisture
condition. Ia denotes initial abstraction before runoff begins, that can also be substituted by
0.3S. These all values are expressed in mm (ref2).
Computed runoff volume of different years generally shows some variation in their
means and standard deviations and thus become difficult to compare. Therefore these values are
standardized by “Z-Score” or Standard Score”.
Sediment yield for the year 1999 and 2005 also measured by using the ‘Modified
Universal Soil Loss Equation’ (MUSLE), proposed by Williams (1978). Because of the non-
availability of entire calculation procedure in metric system, FPS system is followed for this
equation and the result later converted to metric system. It follows the structure of the Universal
Soil Loss Equation (USLE) of Williams and Berndt (1972), with the exception that the rainfall
factor is replaced with the runoff factor. The equation calculates sediment yield from a 24hr
storm within each micro-watersheds of less than ten (10) square miles (ref9). The structure of the
MUSLE is:
A = B (Qv*qp)0.56
*K*LS*C*P ………………[eq.-2]
Where -
A=computed soil loss per unit area (tones / mile2)
Qv =volume of Runoff (acre-feet)
qp=peak flow rate (feet3/second)
K= soil erodibility factor (dimensionless)
LS=slope length & gradient factor (dimensionless)
C= cropping management factor (dimensionless)
P=erosion control practices factor (dimensionless)
B is a constant, and the value is 95 in FPS system and 11.8 in metric system.
A 24hr design storm of 105.4 mm for a recurrence interval of 5 years is calculated from
the analysis of 10 years (1996-2005) rainfall data of Baghmundi. The runoff (Q) from the design
storm is computed by SCS Curve Number method and the volume of Runoff Qv is obtained by
multiplying (Q) with the area of the micro-watershed.
Second objective of this study is the assessment of economic and social changes taken
place as a consequence of this development are taken into consideration. “Questionnaire
Checklist” method is adopted for identification of key impacts. Door-to-door household survey
in twenty-six (26) Mauzas (villages) surrounding the project sites (PPSP, TPSP and KPSP) is
done. Once the key impacts are short-listed; “Leopold Matrix” is used to assess the magnitude of
impacts of individual project actions on individual human environmental elements. This matrix
was developed for US geological survey by Leapold et al. (1971). It is based on horizontal lists
of project actions and vertical lists of environmental components. After few modifications of
“Leopold Matrix” fourteen (14) project actions, twenty-one (21) environmental components and
their 294 possible interactions are considered in this study.
Monetary values of tangible impacts were obtained by questionnaire survey in
households, markets and offices. Where as valuation of intangible impacts were done by taking
instances from other literatures or by using “Contingent valuation method” (CVM) where
people are asked what they are willing to pay for keeping ‘X’ or preventing ‘Y’, or what they
are willing to accept for losing ‘A’ or tolerating ‘B’ (ref14
). We have considered all the negative
impacts along with the project expenditure as a ‘cost’ of the project and all the positive impacts
including electricity generation as ‘benefit’. A balance sheet is prepared to get the value of the
total cost with respect to the total benefit.
Lastly it has been strived to prepare an action plan for optimum pattern and method of
land use for mitigation of those impacts. At first watershed prioritization map is prepared based
on the level of degradation taken place in each micro-watersheds. Study of present land use with
other attributes of the land and land capability classification is the second stage of this planning.
“Environmental Approach” is adopted for land capability assessment. In this approach the
capability of land is assessed by taking into account the overall environmental attributes (ref8).
The methodology essentially employs overlay analysis of different GIS layers e.g. satellite
Remote Sensing data to unravel the land use / land cover, geomorphology and soil properties to
assess the land capability. Also the annual range of temperature pattern of rainfall, slope, shape,
sizes and physiographic position of the micro-watershed plays a major role in deriving the
optimum land use plan. Mauza maps showing individual plot or land holding are overlaid on the
ultimate sustainable land and water use map and thus cadastral level action plan map is
prepared.
3.0 RESULTS AND DISCUSSION: Studying each and every impact minutely, it could be
concluded that alteration of land use land cover is the most remarkable upshot of these projects.
During 1995 to 2005 huge infrastructure development has taken place in the study area. Two
reservoirs with rock-fill dam, one power station, one cement mixing plant, three land bridge, 7
km of service roads surrounding Upper and Lower dam and 20 Km of repaired and widened
roads from Balarampur to Baghmundi, one twelve bedded hospital, one fire station, two office
building and fifty staff quarters are constructed in an around the PPSP project site. Most of these
are developed at the cost of 7.9 sqkm. of forest and 3.26 sqkm. of agricultural land of the study
area and twice the amount will be destroyed for construction of TPSP and KPSP. Not only built-
up areas were grown, but also fallow land has increased by 25.77%. Total environmental cost of
deforestation is estimated to be 15.73 billion rupees per year.
Runoff Estimation (SCS –CN) Soil Loss Estimation (MUSLE)
1999 (Total
rainfall 1029.8mm)
2005 (Total
rainfall 1057.6mm)
1999 (24 hr storm
105.4 mm / 4.15 inch)
2005 (24 hr storm
105.4 mm / 4.15 inch)
Micro
Water-
sheds
Runoff
Q
(mm) Z-Score
Runoff
Q
(mm) Z-Score
Micro
Water-
sheds
Soil loss
SY
(tons/Sqmile)
Soil loss
SY
(ton's/Hec)
Soil loss
SY
(tons/sqmile)
Soil loss
SY
(ton's/Hec)
MW1 211.63 0.828441 357.66 0.674555 MW1 4853.36 18.74 6684.31 25.81
MW 2 327.26 2.290095 505.33 2.197869 MW 2 599.06 2.314 1125.29 4.341
MW 3 74.36 -0.90676 191.22 -1.04238 MW 3 4091.08 15.79 2703.39 10.44
MW 4 166.48 0.257709 331.13 0.400881 MW 4 6889.00 26.59 15219.72 58.76
MW 5 240.56 1.194138 422.06 1.338884 MW 5 406.50 1.57 981.22 3.79
MW 6 89.64 -0.71361 234.1 -0.60005 MW 6 9663.14 37.31 12545.28 48.42
MW 7 211.67 0.828946 357.66 0.674555 MW 7 3974.40 15.34 5606.32 21.65
MW 8 186.61 0.512168 333.34 0.423679 MW 8 11163.92 43.10 17626.76 68.06
MW 9 42.28 -1.31228 151.99 -1.44707 MW 9 707.81 2.73 749.17 2.89
MW 10 83.93 -0.78579 221.88 -0.7261 MW 10 6283.94 24.26 7115.47 27.47
MW 11 53.28 -1.17323 166.17 -1.30079 MW 11 2464.85 9.52 2061.57 7.96
MW 12 98.66 -0.59959 246.59 -0.4712 MW 12 6909.16 26.68 5801.45 22.39
MW 13 109.14 -0.46711 260.94 -0.32318 MW 13 18276.49 70.56 17764.00 68.59
MW 14 149.8 0.046861 311.69 0.200345 MW 14 23594.24 91.09 21878.96 84.48
Table-1 Runoff and soil loss of the study area of 1999 and 2005.
Land degradation is in its peak at the project site. In micro-watershed No. 6 (project
site), from total annual rainfall of 1999, only 8.7% flowed as surface runoff. But in 2005,
22.13% of total rainfall ran over the surface. Soil loss estimation from a 24hr design storm also
revealed that in 1999 the soil loss was 37.31tons/hac from micro-watershed No. 6 but in 2005 it
increased to 48.42 tons/hec. Micro-watershed No. 7, the downstream agricultural land of PPSP
generated very low amount of sediment (15.34 tons/hec) in 1999 but in 2005 conversion of
agricultural land to fallow land increased the soil loss to 21.65 tons/hec (Table-1). Increase in
runoff and soil erosion indicates land degradation. Massive gully erosion visualise the fact.
Spatial extent of the gullied lands estimated to be 3.46 sq km. In some cases maximum width
and depth of the gullies are found to be more than 4m. Few minor landslides in the hill slopes,
because of removal of underneath lateral support by rock quarrying made them totally exposed
to weathering.
The animal communities of Ajodhya hills were also affected by land use alteration.
Migratory elephants that were trying to migrate from the Saranda to Ayodhya Hills were
stopped due to the PPSP project activities. Migration for food is essential for the elephants.
Because of this obstacle they are facing the threat of extinction and becoming aggressive.
From economic point of view it has been found that during the last ten years more than
thousands of local people have got jobs in this project. At present 265 regular staff and 682
casual labours, are working in the construction site and in future approximately 300 permanent
staff will run the Project. Beside this direct employment roughly 100 people engaged in
transport sector and 50 people as daily use commodity supplier for the workers are also
indirectly employed in this project. These employees will earn 47.05 million rupees annually.
Infrastructure and public utility services are also better than before and 162 million rupees are
invested for that. But at the same time forestland acquisition and deforestation has weakened the
forest-based economy of the hills and about 898 households of 16 villages are suffering from
that and at the same time it has increased illegal deforestation in the adjoining forests which is
another negative impact of this project. 1403 households dependent on agriculture in
downstream areas also adversely affected by stream impoundment. Supply of irrigation water,
15-28 cusecs for Kharif and 10-12 cusecs for Rabi crops, for 60.25 hec of multi-crop land are
totally stopped after 2005. Influx of outsiders with comparatively higher purchasing power
created a price hike for all daily use commodities and native villagers are suffering from that.
Altogether the inhabitants of the study area are loosing 96.52 million rupees annually.
From social point of view transformation of a forest based agrarian economy to an urban
industrial economy affected the physical and mental health of the local people. Till date 14
labours died in accidents at the construction site. Sound of heavy vehicles and stone blasting is
creating a lot of noise in the relatively noise free zone of Purulia; dry dust from the roads and
crushing stones are creating smog; cement mixing plant near the Lower dam polluting the water
of KIP reservoir. These all are detrimental to the health and hygiene of the villagers. They have
lost many traditional values and customs of their society. Alcohol addiction among local people
is now greater than before. Increase in social crime is also another noticeable fact. Total social
cost of the project is estimated to be 1.03 billion rupees per year.
From monetary valuation and cost benefit analysis it may be concluded that if we
consider only the tangible annual cost (Rs.7642.3367 million) and benefit (Rs.8371.12 million)
of the project, the project appears to be economically viable and profit making too. An annual
profit of 728.8 million rupees is observed. But when we add the intangible cost and benefit with
the tangible one, the total annual cost of the project goes to 23475.4 million rupees, where as
total annual benefit remains 8727.12 with a deficit of 14748.28 million rupees per year. Thus in
an economist’s point of view this project is viable but to an environmentalist it is a destructive
one. Still considering the ever-growing demand of electricity instead of only criticizing the
project we must try to find out the mitigation measures to reduce these adverse environmental
impacts.
4.0 SUGGESTIONS FOR FUTURE LAND USE AND ECONOMIC PRACTICES: To
mitigate the adverse impacts of the project on the environment and the economy of the area the
first step should be immediate afforestation / replantation in the deforested lands by
Participatory Forest Management (PFM) involving rural communities in planning, management
and rejuvenation of degraded forests. Forests of that region will not only provide fuel, fodder
and other minor forest products but also have the potentiality of development of ecotourism near
the dams and water falls of Ajodhya hills. Therefore few strategies like involvement of local
administration in site selection for ecotourism; social forestry and participatory forest
management; formation of co-operative societies to produce agro-horticultural and animal
products, operating restaurants and tourist canteens; employment of local people specially
women in the tourism sectors; encouraging local folk cultures and their inclusion in tour
packages; expenditure of 50% of annual profit from ecotourism in protection of forests and
forest animals etc., are to be adopted for development of ecotourism in Ajodhya hills.
In the agricultural lands of the catchment where water is scarce and immature laterite is
the dominant soil, surface water harvesting and Agro-forestry / Agro-hortipasture is advised.
Intimate and interacting association of agricultural crops and woody perennials will prevent soil
erosion and reduce siltation in the reservoirs. In the stony wastes of structural hills, shrubs and
grasses could be grown for fodder and for road or building materials rock querying could be
done where necessary. The double-cropped lands of the canal fed down stream area are to be
allotted for intensive agriculture. Loamy soil with alluvium is suitable for agriculture. The
deficit of irrigation water must be compensated by ground water exploitation. In the adjoining
single cropped area where soil moisture content is less agro-horticulture, floriculture or cash
crops will be the best suit. In Rabi season when the lands are left fallow, it should be utilized for
fruit, flower, vegetable and fodder production. Other than two reservoirs of PPSP pisciculture
and aquaculture should be practiced in the remaining water bodies. Comparatively elevated
grounds are to be used for settlements and other constructions. Artificial rainwater harvesting
structures and ground water recharge structures (including percolation tank) are proposed to
build up in all the settled areas as well as in office and school compounds. Cadastral level action
plan maps are prepared for twenty-six (26) Mauzas covering PPSP, TPSP and KPSP project
sites, but because of space limitation only the action plan map of Bareriya (Fig-2C) is displayed
here.
5.0 CONCLUSION: It cannot be presaged how much these Pumped Storage Projects will
improve the level of peak power scenario of West Bengal, but from the above study it is obvious
that PPSP has caused a great damage to the environment and economy of the study area. Cost
benefit analysis also shows that this type of project in this drought prone region is not
economically viable if we consider the intangible costs that the society and environment have
already paid. Therefore immediate mitigation measures are required to restore environmental
stability and ensure economic prosperity of this region. Only intimate interaction, consultation,
and co-ordination, of Government Officials with local inhabitants can materialize these plans.
Otherwise the entire project will pass through a great phase of uncertainty.
References:
1. Agrawal Mohan Lal, Dixit Anil Kumar and Ghosh Mrinal Kanti (2003), Impact Assessment on Soil Erosion due to Highway Construction using GIS. Dept. of Civil Engineering Indian Institute of
Technology Kharagpur (W.B.), India. http://www.ejge.com/2003/Ppr0339.html
2. Anonymous (1986), TR-55. Computation of Runoff for Small Watersheds, U.S. Dept. of Agriculture
(USDA), Natural Resource Conservation Service (NRCS), Conservation Engineering Division –
Technical Release-55 (210-IV-TR-55, 2nd Ed. June-1986).
3. Anonymous (2003), West Bengal State Electricity Board (WBSEB), Purulia Pumped Storage Project (PPSP). http://www.ppsp-wbseb.com
4. Anonymous (2006), Ananda Bazar Patrika 24th Dec, 2006. 6 Prafulla Sarkar St. Kolkata – 700001.
(Editor – Abhik Sarkar). http:// www.anandabazar.com.
5. Balaszczynski Jacek (2003), Estimating Watershed Runoff and Sediment Yield Using a GIS Interface
to Curve Number and MUSLE Models. BML Science & Technology Center–Denver, Colorado, USA.
http://www.bml.gov/nste/resourcenotes/resnotes.html.
6. Bhattacharya Birendra Kr., Roy P, Chakrabarty B.R, Sengupta S, Sen N.N, Sengupta K.S, Mukherji
S and Maity T (1985), West Bengal District Gazetteers - Purulia. Published by Narendra Nath Sen,
State Editor, WB. Distt. Gazeeteers.
7. Bhattacharya Swaroop (2005), The Purulia Pumped Storage Project: People, Environment Suffer for
Uncertain Peaking Power. Published in Dams, Rivers & People (SANDRP) Sep-Oct. 2005.
http://www.sandrp.in/hydropower/prlia-artcle.pdf
8. De N.K & Jana N.C. (1994), The Land, Multifaceted Appraisal & Management. Sribhumi Publishing
Co. Kolkata.
9. Glasson John, Therivel Riki and Chadwick Andriw. (1999), Introduction to Environmental Impact
Assessment 2nd Ed. Spon press, London.
10. Panda Tapan K, Mishra Sitikantha, Parida Bivraj Bhusan (2004), Tourism Management – The
Socioeconomic and Ecological Perspective 1st Ed. Orient Longman Pvt. Ltd. Hyderabad.
11. Rajora Rajesh (1998), Integrated Watershed Management – A Field Manual for Equitable,
Productive and Sustainable Development. Rawat publication, Jaipur & New Delhi.
12. Singh V.P. (1994), Elementary Hydrology 1st Ed. Prentice-Hall of India Pvt.Ltd. New Delhi-110001.
13. Tiwari K.N, Kumar P, Sebastian M and Pal D.K (1991), Hydrological Modeling for Runoff
Determination. Water Resource Development Vol.7, No.3. Sep-1991, Butterworth – Heinemann Ltd.
14. Vanclay Frank, Bronstein D.A. (1995), Environmental and Social Impact Assessment 1st Ed. John
Wiley and Sons, England.