Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.1
CHAPTER – 8 RISK AND SAFETY MANAGEMENT
8.1 PREAMBLE
Increasing use of hazardous chemicals as raw materials, intermediates and finished
products has attracted attention of the Government and the public at large in view of the
chemical disasters. The serious nature of the accidents, which cause damage to the
plant, personnel and public, has compelled industries to pay maximum attention to the
safety issues and also to effectively manage the hazardous material and operations. It
is mandatory for the industries handling hazardous chemical to maintain specified
safety standards and generate an on-site emergency plan and keep it linked with off
site emergency plan.
The Risk Assessment Study and safety management for the proposed expansion
project of Natural Petrochemicals Pvt. Ltd. has been carried out and the details are
elaborated in this chapter. Based on the findings & recommendations of RA report
management plan for the proposed expansion has also been prepared and included.
Risk Assessment is defined as a continuous and integrated process of identification,
evaluation and measurement of risks, along with their potential impact on the
organization.
The benefits of risk assessment include the following:
Prevention or reduction in occurance of accidents.
Mitigation of the severity and/or consequences by way of improved process
techniques, fire protection systems, arrangements of storage, inventory
monitoring to fit production requirements.
Development of confidences in employees by improving competency.
Preparedness and prompt response to deal with any accident.
The safety management includes the implementation of preventive methods or accident
prevention methods to avoid incident or accident and handling of emergency in case of
accident.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.2
8.2 OBJECTIVE, PHILOSOPHY AND METHODOLOGY OF RISK ASSESSMENT
8.2.1 Objective
The principle objective of this study is to identify major risks in the manufacturing
process and to evaluate on-site & off-site consequences of identified hazard scenarios.
Pointers are then given for effective mitigation of hazards in terms of suggestions for
effective disaster management, suggesting minimum preventive and protective
measures & change of practices to ensure safety.
8.2.2 Philosophy
The following aspects and areas have been covered in this study;
Identification of major risk areas.
Hazard identification / Identification of failure cases.
Consequential analysis of probable risks / failure cases;
o Determination of the probable risk by Releasing of chemical due to leakage of
storage tank and catastrophic failure.
o Risk assessment on the basis of the above evaluation & risk acceptability.
o Minimum preventive & protective measures to be taken to minimize risks to
maximum possible extent.
Giving pointers for effective disaster management.
Suggesting measures to further lower the probability of risk.
8.2.3 Methodology
Design data, built in safety systems are studied. Discussions are held with officials.
Safety related individual system is discussed. Hazard identification exercise is
conducted taking into consideration of materials, material handling methods, operating
procedures, built in safety in reactors, operating parameters and safety measures to be
taken in proposed plant. Few areas like process building, storage of hazardous
chemicals, to evaluate safety systems in the event of any abnormalities occurring.
Containment failure scenario related to storage area is considered for hazard Analysis
and consequences of such containment failures are considered in detail. Thus, this
study is mainly oriented towards actual risks rather than chronic risks.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.3
8.3 HAZARDOUS MATERIAL, PROCESS AND SAFETY MANAGEMENT
The proposed project includes manufacturing of various bulk drugs and drug
intermediates along with the existing products. Manufacturing of these synthetic organic
chemicals required raw materials are listed in Chapter-2, Section-2.8 with hazardous
identification.
8.3.1 Hazardous Chemicals
None of the product is defined as hazardous in MSIHC rules but may fall under the
definition of hazardous material/chemicals either due to its hazardous and toxic nature.
Most of the raw materials fall under the definition of hazardous chemical. The details of
hazardous chemicals are given in Table 8.1.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.4
Table 8.1: Details of Hazardous Chemicals
Sr. No.
Name of Chemicals
CAS No. State Colour Odor Sp.
GravityVapour Density
Boiling Point ºC
Melting Point
ºC
Flash Point
ºC
Explosive limitSolubility in
water Hazardous
Characteristics LEL UEL% %
1. Styrene (Monomer)
100-42-5 Clear viscous
liquid Colorless
Sweetish, Aeromatic
0.906 3.59 145.2 (-) 30.6 31.1 1.1 6.1 Very slightly
soluble in cold water
Hazardous, Flammable
2. Ethylene Glycol
107-21-1 Viscous liquid Colorless Odorless 1.113 2.1 196-198 (-) 13 110 3.2 15.3 Miscible in all proportions
Hazardous, slightly Flammable
3. Diethylene Glycol
11-46-6 Clear Viscous
liquid Colorless Odorless 1.12 3.66 245.8 (-) 8 138 2 12.3 Easily soluble
Hazardous, Flammable
4. Propylene Glycol
57-55-6 Clear oily liquid Colorless Odorless 1.0361 2.6 188.2 (-) 59 99 2.6 12.5 Miscible Hazardous, slightly
Flammable
5. Dipropylene Glycol
25265-71-8
Slightly Viscous liquid
Colorless Odorless 1.0252 4.63 231.9 -- 99 2.6 12.5 Miscible Slightly Hazardous
6. Phthalic Anhydride
85-44-9 Solid (Crystals
Solid) White
Characteri-stic acrid, choking
1.53 6.6 295 131 151.67 1.7 10.4 Very slightly
soluble in cold water
Hazardous, flammable in
presence of heat, corrosive, toxic
7. Terephthalic Acid
100-21-0 Solid (Powdered
Solid) Off-white -- -- 5.74 -- 300 260 -- -- Insoluble Hazardous, Toxic
8. Maliec Anhydride
108-31-6 Scales White Aeromatic 1.32 3.4 202 51 - 53 103 1.4 7.1 Soluble
(decomposition)
Hazardous, flammable, corrosive,
sensitizing, toxic
9. Isopthalic Acid
121-91-5 Fine crystals White Almost
Odorless 1.54 -- -- 345-348 -- -- Slightly soluble
Slightly Hazardous, toxic
10. Xylene 1330-20-7 Liquid Colorless Aromatic
hydrocarbon odor
-- -- 134-140 -- 37.7 -- -- Insoluble Hazardous, flammable
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.5
8.3.2 Safety Measures for Transportation, Storage & Handling of chemicals
Styrene is received by road tankers stored in tanks and Xylene is received in drums.
Solvent unloading standard procedure is in place and implemented for safe
unloading of road tanker.
Static earthing provision is made for tanker unloading.
Flexible steel hose is used for unloading from the tanker.
Flame proof electric motor is used during loading/unloading.
NRV is provided on pump discharge line.
Fixed pipeline with pumps is provided for transfer to vessel.
TERM CARD is provided to all transporters and they are trained for transportation
Emergency of hazardous chemicals.
Drum handling trolleys are used for transportation of drums up to plant.
Muffler on the silencer of the tanker during entering in factory premises.
Safety permit system is followed for loading and unloading.
Isolate storage is provided with wire fencing under lock and key.
Only authorized person is permitted in storage area.
Display Boards are provided on all storage tanks which includes the name of the
chemicals and storage capacity.
Caution note, hazardous identification board is provided.
On-site detectors for fire based on heat &/or smoke detection with alarm system is
provided as required.
Fire extinguishers and fire hydrant system are provided as per requirement.
First aids boxes are provided at different places wherever required.
Water showering system is provided to the flammable chemicals storage area,
wherever required to avoid the vaporization due to increase in atmosphere
temperature.
Hazardous Chemical storage area is declared as “NO SMOKE ZONE”.
Hazardous material handling is carried out by using all PPE with proper ventilation &
under supervision.
8.3.3 Critical Safety Measures for Process Units
Critical safety measures are the most important aspect of selection of process
technology to ensure safety in production unit. For the safety in production area some
important critical safety measures are provided within the process technology/
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.6
equipment itself & put continue efforts for developing new technology/equipment.
Company ensures such provision in the technology /equipment /machineries at time of
purchase. The details of the critical safety measures for process unit are as below;
Any reaction upsets is confined to the reaction vessel itself as defined quantity of raw
materials are issued to the reaction vessel by metering pumps/load cells.
Process parameters control is provided vide Standard Operating Procedures.
Materials are transferred by pumping through pipeline or by vacuum from drums.
All reactors are connected to vapor condensers system.
Hazardous materials are transferred by pipelines and in control manners.
Trained person is engaged for handling of hazardous materials.
Proper safety precautions are taken during handling of hazardous materials.
Solvents and flammable material storage area is kept away from the process plant and
required quantity of material is charge in reactor by pump or by gravity.
Further all the vessels are examined periodically by a recognized competent person.
All the vessels and equipments are well earthed appropriately and well protected
against Static Electricity. Also for draining in drums proper earthing facilities are
provided.
Temperature indicators are provided near all reactors.
Caution note, safety posters, stickers, periodic training & updation in safety and
emergency preparedness plan are displayed and conducted.
Flame proof light fittings are installed in the plant.
All the Plant Personnel are provided with Personal Protection Equipments to protect
against any adverse health effect during operations, leakage, spillages or splash. PPE
like Helmets, Safety Shoes and Safety Glasses are provided to the employees.
Material Safety Data Sheets of raw materials & products are kept readily available at
the shop floor.
8.3.4 Safety Measures For Preventive Maintenance
The safety measures in form of the general Do's & Don'ts for safety in process & other
plant area are as below:
Do not work on equipments without permission from plant head and maintenance
head.
Make sure equipment is empty and fluxed with nitrogen and air.
Check VOC content for flammable and make sure that no flammable vapour contents.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.7
Keep proper and adequate fire extinguisher near work area.
Use proper PPE.
Do not allow any employment without pre-medical check-up or without checking
fitness.
Check all motors are disconnected and fuse pulled out before maintenance.
Work in any equipment must be conducted in presence of supervisor.
Make sure all process lines are disconnected.
Additional safety measures in form of the checklist covering Do's & Don'ts of
preventive maintenance, strengthening of EHS are updated timely and made available
to all concern department & personnel.
8.3.5 Safety measures to prevent spillage / leakage of toxic chemicals
The preventive maintenance are planned and carried out as per plan to avoid the failure
of valve, pipe lines and other component of transferring line. The spillage is confined to
the dyke area underneath the vessel. The resultant splash of such chemicals result in
exposure of toxic chemicals to employees. Facilities like Safety shower and eye wash
fountains are provided in the plant area, which can be used to decontaminate the
affected employees.
Suitable decontamination procedure is used to decontaminate the spilled or leaked
material. The SOP for decontamination is reared with all related department. The
followings are some measures taken for handling the toxic chemicals safely;
Safety equipments like electric siren, safety belts, safey shower etc are provided at
some places in plant as per the requirement and Suitable personal protective
equipment like splash goggles, gloves and protective clothes are provided while
handling the toxic chemicals.
The installation of all the equipment is as per guidelines of provision of Gujarat
Factories Rule 1963.
All the toxic chemicals are stored under adequate safe condition.
The storage of corrosive and toxic chemicals are segregated from each other.
The piping is examined thoroughly every year for finding out any defects; and a defect
is removed forthwith. The record of such examination is maintained.
Smoking is prohibited inside the factory. Train employees are employed for handling of
toxic and corrosive chemicals.
All pipe joints are provided with heavy duty champion gaskets to prevent any leakage.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.8
Self breathing apparatus are provided and workers are trained about their use also.
Dyke wall is provided to area where hazardous chemicals are stored.
Spare barrels of sufficient quantity are kept ready for any emergency spillage or
leakage.
Drum trolley is used for the movement of drums of hazardous chemicals.
Liquid chemicals are transferred by mechanical seal pump through closed pipeline.
8.4 OCCUPATIONAL HEALTH & SAFETY PROGRAM
The main effects of chemicals especially VOCs are anticipated in proposed expansion.
No other source of adverse effects on occupation health & safety is likely to occur.
However, MSDS of hazardous chemicals are made available with the management as
well as concern personnel working with the materials or area likely to be affected by the
materials. Following are the key safety measure which has already been taken and will
be updated timely;
Provision of drinking water supply for the employees as per standard of the drinking
water as per WHO guidelines.
Availability of proper sanitary facilities for the employees so that they do not suffer from
any health ailments.
Provision of all necessary equipment like portable detector, online detectors and other
laboratory equipments as mentioned above for regular monitoring of workplace air and
other conditions (VOC, Temperature, Humidity and Light Intensity etc.).
Provision of suitable personal protective equipment like safety gloves, helmets,
safety belts, as described below in Table 8.2 to personnel in the plant and
compulsory use of these PPEs for all workers.
Table 8.2: Details of Personal Protective Equipments
Item Nos. Safety Helmet 83 Safety Goggles 50 Safety Shoes 70 Rubber Gloves 04 Eye Wash Fountain 02 Gum Boots 02 Nose Mask 30 Safety Belt 04 Organic Vapor Mask 03 Self Contained Breathing Apparatus 01
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.9
Provision of ear muffs/ ear plugs to the workers exposed to higher noise level.
Provision of first –AID boxes (Containing Tincture iodine, Eye Drops, Burnol,
Soframycin (ointment), Sterilized cotton wool, Band-aid, Antiseptic Solution (Sevlon),
Bandage, Rose Water, etc) at various places in the premises.
Organize training program for information on accident prevention, proper control and
maintenance of equipment, first aid training and safe material handling practices.
Availability of MSDS and antidotes of the chemical used at the place of use.
Installation of fire hydrant system and fire extinguishers at required places.
Regular monitoring of work area to measure airborne contamination and to control
fugutue emissins.
Protection of storage area with Dyke wall.
Provision of adequate ventilation in process area so that airborne contamination does
not exceed threshold limit value.
Monitoring of occupational hazards like noise, ventilation, chemical exposure at
frequent intervals.
Provision of proximity suits and self-breathing apparatus.
Display various instruction boards, cautionary notices etc. at different locations.
As described in Chapter-6, unit has already made necessary tie-up with nearby
hospital for the medical assistance in case of any emergency. Medical officers are
appointed for the periodical health check-up of the employees. Periodical health
check-up reports of all the employees are being maintained and the reports of two
employees are given in Annexure-13 for reference.
In addition to the above, unit will maintain health records in Form 33 as per the factory
act as well as in format attached as Annexure-14.
In addition to the above, unit has allocated Rs. 2 Lacs for various purposes like purchase
of personal protective equipments, medical facilities, hire of ambulance etc. to ensure the
occupation health and safety of company employees, contract & sub-contract workers.
8.5 RISK ASSESSMENT STUDY
Chemical process industries have undergone tremendous changes during last five
decades. Process conditions such as pressure & temperature have become severe;
concentration of stored energy has increased. The scale of possible fire, explosion,
toxic release, body injuries and occupational diseases has grown considerably. These
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.10
factors have greatly increased the risk for major industrial disasters, involving loss of
human lives, plant & property and environmental degradation.
Identification analysis and assessment of hazard and risk are very useful in providing
information to risk management. It provides basis for what should be the type and
capacity of its on-site and off-site emergency plan also what types of safety measures
are required. Risk and consequence analysis is carried out considering storage and
handling of various hazardous raw materials, intermediates and products as well as
manufacturing process. The objectives considered for Risk Assessment study are as
follows;
To assess the risk involved in transporting, storing & processing raw material up to
final product.
To define Emergencies including risk & Environment impact assessment.
To evaluate the risk and to get the complete view of the available facilities.
To take appropriate action to control the incidents.
To safe guard employees and people in vicinity.
To minimize damage to property and neighboring environment.
To inform the employees, general public & Government authority aboutvarious
type of hazards, assessed risk, safe guards provided, residual riskif any, and role
to be played by them in the event of emergency.
To inform Police, fire brigade, District authority and statutory authority for providing
help during emergency.
To work out a plan with all provisions to handle emergencies and to provide training to
employees through mock rehearsals.
To rescue and give treatment to the casualties and to count the number of injured
persons.
8.5.1 Identification of High Risk Areas
It is observed that the storage areas pose fire/explosion hazards which may lead to
major accident event. In the process areas it is observed that inventories of chemicals
are very low & so there are not deemed to pose major off-site hazards. Thus, the
quantitative risk assessment studies are limited to unit and some extent in vicinity.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.11
8.5.2 Modes of Failure
Storages system can fail in different ways depending on the materials stored, storage
conditions & may involve systems in their vicinity. Conditions such as over filling, over
pressure, missile, lightening or bomb attack, earthquake & resultant replier or release
scenarios have been identified. Outcomes of such incidents are determined by
presence of ignition either immediate or delayed. As can be seen depending upon
modes of failure different scenarios are possible viz:
1. Continuous release
2. Instantaneous release
This may be of gas / liquid depending upon type of material stored/released & its
characteristics. More examples, a liquid boiling at ambient conditions, will immediately
be converted to gas upon exposure to atmosphere.
An instantaneous release is any release occurring for a period less than 15 seconds.
Failure mode responsible for instantaneous releases may be catastrophic failure of
chemical storage tank / drum. For an instantaneous gas release important parameters
are release height & quantity released whereas for instantaneous liquid release,
important parameters are amount spilled, spill area & pool temperature, evaporation
rate, vapour mass etc.
Continuous release occurs when the material is released over a period greater than 15
seconds. For a continuous gas release, important parameters include height of leak
above ground, emission rate & total time of release. For continuous liquid release
important parameters are spill rates, duration, area & pool temperature, evaporation
rate and vapor mass or Gas mass.
8.5.3 Maximum Credible Accident Analysis and Its Mitigation Measures
A Maximum Credible Accident (MCA) can be characterized as the worst credible
accident. In other words: an accident in an activity, resulting in the maximum
consequence distance that is still believed to be possible. A MCA-analysis does not
include a quantification of the probability of occurrence of the accident. Another aspect,
in which the pessimistic approach of MCA studies appears, is the atmospheric condition
that is used for dispersion calculations.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.12
The Maximum Credible Loss (MCL) scenarios have been developed for the Facility.
The MCL cases considered, attempt to include the worst “Credible” incidents-what
constitutes a credible incident is always subjective. Nevertheless, guidelines have
evolved over the years and based on basic engineering judgment, the cases have been
found to be credible and modeling for assessing vulnerability zones is prepared
accordingly.
The objective of the study is Emergency planning, hence only holistic & conservative
assumptions are used for obvious reasons. Hence, though the outcomes may look
pessimistic, the planning for emergency concept should be borne in mind whilst
interpreting the results.
In Consequence analysis, geographical location of the source of potential release plays
an important role. Consideration of a large number of scenarios in the same
geographical location serves little purpose if the dominant scenario has been identified
and duly considered.
The Consequence Analysis has been done for selected scenarios by ALOHA (version
5.4.1.2) of EPA.The details of software used for MCA analysis are described below.
A computer based version ALOHA 5.4.1.2 is used to calculate toxic and explosive
effect of the accidental release of liquid chemicals within the plant area.
ALOHA (Areal Locations of Hazardous Atmosphere) is a computer program
designed especially for use by people responding to chemical release as well as for
emergency planning and training.
ALOHA was jointly developed by the National Oceanic and Atmospheric
Administration (NOAA) and the Environment Protection Agency (EPA).
The mathematical model is based on the Emergency Response Planning
Guidelines (ERPGs) which gives Toxic Levels of Concern (LOCs) to predict the
area where a toxic liquid concentration might be high enough to harm people.
ALOHA models key hazards-toxicity, flammability, thermal radiation (Heat), and
over pressure (expansion blast force)-related to chemical releases that result in
toxic gas dispersion, fire and/or explosion.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.13
8.5.4 Consequences Analysis
From the raw materials Styrene Monomer and Xylene have been taken for the
consequences analysis considering their hazardous nature. Storage condition and
threshold value of these chemicals are mentioned in the Table 8.3 & 8.4. Other
properties are given in Table 8.1.
Table 8.3: Storage details of Hazardous Chemicals
Sr. No.
Hazardous chemicals
Physical form
Type of storage
Size of Storage
Unit
Qty. of Storage
Unit
Maximum Storage Capacity
Storage PressureKg/cm2
StorageTemp.
ºC
1 Styrene Monomer
Clear Viscous Liquid
Tank 250 KL 3 750 KL ATM At RT
2 Xylene Liquid Drum 200 Kg 50 10 MT ATM At RT
Table 8.4: Threshold values of the Hazardous Chemicals
Sr. No.
Chemicals Threshold Value (ppm)
ERPG-1 / TEEL-1 ERPG-2 / TEEL-2 ERPG-3 / TEEL-3
1. Styrene Monomer 50 250 1000
2. Xylene 150 200 900
ERPG: Emergency Response Planning Guidelines (For Styrene Monomer) TEEL: Temporary Emergency Exposure Limits (For Xylene)
8.5.4.1 Definitions & Explanation of Terms Used
ERPG-1 : Emergency Response Planning Guidelines (ERPG) The maximum concentration in air below which it is believed nearly all individuals could be exposed for up to one hour without experiencing other than mild transient adverse health effects or perceiving a clearly defined objectionable odor.
ERPG-2 : The maximum airborne concentration below which it is believed that nearly all individuals could be exposed for up to 1 hour without experiencing or developing irreversible or other serious health effects or symptoms which could impair an individual's ability to take protective action.
ERPG-3 : The maximum airborne concentration below which it is believed that nearly all individuals could be exposed for up to 1 hour without experiencing or developing life-threatening health effects.
TEEL-1 : Temporary Emergency Exposure Limits (TEEL). TEELs are intended for use until AEGLs or ERPGs are adopted for chemicals. TEEL-1 is the airborne concentration (expressed as ppm [parts per million] or mg/m3 [milligrams per cubic meter]) of a substance above which it is predicted that the general population, including susceptible individuals, when exposed for more than one hour, could experience notable discomfort, irritation, or certain asymptomatic, nonsensory effects. However, these effects are not disabling and are
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.14
transient and reversible upon cessation of exposure.
TEEL-2 : TEEL-2 is the airborne concentration (expressed as ppm or mg/m3) of a substance above which it is predicted that the general population, including susceptible individuals, when exposed for more than one hour, could experience irreversible or other serious, long-lasting, adverse health effects or an impaired ability to escape.
TEEL-3 : TEEL-3 is the airborne concentration (expressed as ppm or mg/m3) of a substance above which it is predicted that the general population, including susceptible individuals, when exposed for more than one hour, could experience life-threatening adverse health effects or death.
AEGL-1 : Acute Exposure Guideline Levels (AEGL) The airborne concentration of a substance above which it is predicted that the general population, including susceptible individuals, could experience notable discomfort, irritation, or certain asymptomatic nonsensory effects. However, the effects are not disabling and are transient and reversible upon cessation of exposure.
AEGL-2 : The airborne concentration of a substance above which it is predicted that the general population, including susceptible individuals, could experience irreversible or other serious, long-lasting adverse health effects or an impaired ability to escape.
AEGL-3 : The airborne concentration of a substance above which it is predicted that the general population, including susceptible individuals, could experience life-threatening health effects or death.
IDLH : IDLH is an estimate of the maximum concentration in the air to which a healthy worker could be exposed without suffering permanent or escape-impairing health effects.
LEL : LEL is the minimum concentration of fuel in the air needed for a fire or an explosion to occur if an ignition source is present. If the concentration is below the LEL, there is not enough fuel in the air to sustain a fire or an explosion -- it is too lean.
UEL : UEL is the maximum concentration of fuel in the air that can sustain a fire or an explosion if an ignition source is present. If the concentration is above the UEL, there is not enough oxygen to sustain a fire or an explosion -- it is too rich (much like an engine that cannot start because it has been flooded with gasoline).
STEL : The concentration to which workers can be exposed continuously for a short period of time without suffering from (1) Irritation (2) Chronic or Irreversible tissue damage (3) Narcosis of sufficient degree to increase injury, impair self-rescue or materially reduce work efficiency and provide that the daily TLV-TWA is not exceeded.
TWA : The time-weighted average concentration for a normal 8-hour workday and a 40-hour workweek, to which nearly all workers may be repeatedly exposed, day by day, without adverse effect.
Source Strength
: The source strength is either the rate the chemical enters the atmosphere or the burn rate, depending on the scenario. A chemical may escape very quickly (so that source strength is high), as when a pressurized container is ruptured, or more slowly over a longer period of time (so that source strength is low), as when a puddle evaporates.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.15
Threat zone : It represents the area within which the hazard level (toxicity, flammability, thermal radiation, or overpressure) is predicted to exceed the Level of Concern (LOC) at some time after a release begins.
Evaporation Puddle
: Choose Puddle from the Source submenu under the set up menu to model a liquid that has spilled and formed a puddle on the ground. ALOHA can model the puddle either as an evaporating puddle or, if the chemical is flammable, as a Pool Fire.Choose Puddle when a puddle has already formed on the ground and is not changing in area. If liquid is continuing to leak from a tank and spilling into a puddle (so that the puddle's area and volume are increasing) choose Tank from the Source submenu instead. Check the "Tank source" help topic to learn more about this option.
Toxic Threat zone
: A Toxic Level of Concern (LOC) is a threshold concentration of an airborne pollutant, usually the concentration above which a hazard may exist.
Flammable Threat zone
: A Flammable Level of Concern (LOC) is a threshold concentration of fuel in the air above which a flammable hazard may exist. Generally, this LOC will be some fraction of the Lower Explosive Limit (LEL).
Threat zone of thermal radiation from jetfire
: The thermal radiation effects that people experience depend upon the length of time they are exposed to a specific thermal radiation level. Longer exposure durations, even at a lower thermal radiation level, can produce serious physiological effects. The threat zones displayed by ALOHA represent thermal radiation levels; the accompanying text indicates the effects on people who are exposed to those thermal radiation levels but are able to seek shelter within one minute. Below are some effects at specific thermal radiation levels and durations (on bare skin): 2 kW/(sq m) -- people will feel pain after 45 seconds and receive second-
degree burns after 3 minutes; 5 kW/(sq m) -- people will feel pain after 13 seconds and receive second-
degree burns after 40 seconds; and 10 kW/ (sq m) -- people will feel pain after 5 seconds and receive second-
degree burns after 14 seconds.
Threat at point
: It represents the specific information about the hazards at point of interest (such as schools and hospitals) in and around the threat zones.
8.5.4.2 Possible Accident Scenario
Different possible ways of occurrence of any accidents due to storage/usage of above
hazardous chemicals are prescribed here below;
Scenario-A: Release of chemical due to leakage and form evaporating puddle (Not
burning)
Scenario-B: Release of chemical due to leakage and form burning puddle (Pool fire)
Scenario-C: Release of chemical due to catastrophic failure (BLEVE)
Atmospheric conditions assumed at the time of accidents are mentioned in Table 8.5.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.16
Table 8.5: Atmospheric Conditions Assumed
Particulars Details
Wind (Max) 6.8 meter/second
Ground Roughness Open Country
Cloud Cover 1 tenth
Air Temperature 19.83° C
Stability Class D
Relative Humidity 43.97%
1) STYRENE MONOMER
The possibilities of source strength considered at the time of accidents due to leackage
of Styrene Monomer from hole of 0.5 inches diameter at bottom of tank are mentioned
in Table 8.6.
Table 8.6: Source Strength considered for Styrene Monomer
Particulars Value
Tank diameter 6.5 m
Tank height 7.6 m
Tank volume 250 m3
Opening diameter 0.5 inches
Opening from tank bottom 0 m
Internal temperature 19.83 ºC Scenario-1A: Release of Styrene due to leakage from tank and form evaporating puddle (Not burning) a) Source Strength
In case of Styrene escape from tank by a hole of 0.5 inch, then maximum average
sustained release rate will be 5.1 kg/min and hence approx. 178 Kg of Styrene will be
released in about 1 hour. Isopleths results are given in Figure 8.1.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.17
Figure 8.1: Source Strength in case of Styrene escape
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Styrene release is given in Table 8.7. Threat zone
was not drawn because effects of near-field patchiness make dispersion predictions
less reliable for short distances.
Table 8.7: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm Threat Zone, m
Horizontal Direction
Vertical Direction
Red 1000 (ERPG-3) 10 Orange 250 (ERPG-2) 13 Yellow 50 (ERPG-1) 32
Flammable Threat Zone:
Model output of the flammable threat zone for chemical release is given in Table 8.8.
Table 8.8: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone
Horizontal Direction
Vertical Direction
Red 6,600 (60 % LEL) 10 m
Yellow 1,100 (10 % LEL) < 10 m
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.18
Isopleths result of flammable threat zone showing area of vapor cloud at LEL value was
not drawn because effect of near field patchiness make dispersion prediction less
reliable for short distance.
c) Threat at Point
In case of leakage of Styrene from tank, the significant effects will be upto 32 meter in
case of toxic threat zone with concentration of 50 ppm. Effect has been worked out at a
point in downwind direction within the premises at about 500 meters distance from the
source. Maximum concentration of styrene estimated at described point is 1.02 ppm at
outdoor and 0.434 ppm in indoor and Isopleths for the same is shown in Figure 8.2.
Figure 8.2: Isopleths result of Toxic threat at a point for Styrene Monomer
Scenario-1B: Release of Styrene Monomer due to leakage & form burning puddle
(pool fire)
a) Source Strength
Styrene Monomer is below its flash point and is unlikely to catch on fire. However,
considering worst case, model has been run for such case. When styrene monomer
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.19
escaped from tank and forms a burning puddle, maximum burn rate in this case will be
28.6 kg/min considering maximum attentive time of 60 min. Moreover, puddle will be
spread to a diameter of 2.9 m. Isopleths results are given in Figure 8.3.
Figure 8.3: Source Strength in case of Styrene Monomer escapes (pool fire)
b) Threat zone of thermal radiation from pool fire
Model output of the threat zone of thermal radiation from pool fire is given in Table 8.9.
Isopleths results are given in Figure 8.4.
Table 8.9: Threat zone of thermal radiation from pool fire
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone
Radial Distance Red 10 (Potentially lethal within 60 sec.) 11 m
Orange 5 (2nd degree burns within 60 sec) 14 m
Yellow 2 (Pain within 60 sec) 18 m
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.20
Figure 8.4: Thermal radiation at a point in case of Styrene Monomer escapes (pool fire)
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 500 meters distance from the source and no significant radiation observed at
selected point.
Scenario-1C: Release of chemical due to catastrophic failure (BLEVE)
a) Source Strength
Styrene Monomer is below its flash point and is unlikely to catch on fire. However,
considering worst case, model has been run for such case. When styrene monomer will
be released from tank as a liquid and forms a fire ball, diameter of fire ball will be 354 m
and burn duration will be 20 seconds.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.21
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 8.10 & Figure 8.5.
Table 8.10: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance Red 10 (Potentially lethal within 60 sec.) 733 m
Orange 5 (2nd degree burns within 60 sec) 1000 m
Yellow 2 (Pain within 60 sec) 1600 m
Figure 8.5: Isopleths result of threat zone of thermal radiation from BLEVE
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.22
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 500 meters distance from the source. The maximum thermal radiation estimated
at point will be 20.5 kW/m2. Persons working in the area upto 500 m distance from the
source will get potentially lethal within 60 seconds.
2) XYLENE
The possibilities of source strength considered at the time of accidents due to Xylene
are mentioned in Table 8.11.
Table 8.11: Source Strength considered for Xylene
Particulars Value
Drum Diameter 0.65 mDrum Height 0.7 mDrum volume 0.23 m3
InternalTemperature 19.83° CChemical Mass in cylinder 200 Kg Scenario – A & B Circular Opening Diameter 0.5 inchesOpening from Drum bottom 0 mGround Type Concrete Scenario – C Percentage of Tank Mass in Fireball 100%
Scenario-2A: Release of Xylene due to leakage and form evaporating puddle (Not
burning)
a) Source Strength
When Xylene will escapes from drum and formed an evaporating puddle, Maximum
average sustained release rate in this case will be 987 gms/min considering maximum
attentive time of 1 min or more and puddle spread to a diameter of 7.3 m. Isopleths
results are given in Figure 8.6.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.23
Figure 8.6: Source Strength in case of Xylene escapes
b) Threat Zone
Toxic threat zone
Model output of the Toxic threat zone and isopleths for chemical release are given in
Table 8.12. Isopleths result was not drawn because effect of near field patchiness
make dispersion prediction less reliable for short distance.
Table 8.12: Toxic Threat zone
Threat Zone Concentration
(ppm) Threat Zone
Horizontal Direction Vertical Direction
Red 900 (TEEL-3) < 10 m
Orange 200 (TEEL-2) < 10 m
Yellow 150 (TEEL-1) < 10 m
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 8.13.
Isopleths result was not drawn because effect of near field patchiness make dispersion
prediction less reliable for short distance.
Table 8.13: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone Horizontal Direction Vertical Direction
Red 6,600 (60 % LEL) < 10 m
Yellow 1,100 (10 % LEL) < 10 m
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.24
c) Threat at point
In case of leakage of Xylene, the significant effects will be within 10 m in case of toxic
threat zone with concentration of 1,100 ppm. Effect has been worked out at a point in
downwind direction at 500 m within the premises from the source. Maximum
concentration of Xylene estimated at described point is 0.197 ppm at outdoor and 0.103
ppm in indoor and Isopleths for the same is shown in Figure 8.7.
Figure 8.7: Isopleths result of Toxic threat at a point for Xylene
Scenario-2B: Release of Xylene due to leakage and form burning puddle (pool
fire)
a) Source Strength
When Xylene will escape from drum and forms a burning puddle, maximum burn rate in
this case will be 6.14 kg/min considering maximum attentive time of 33 seconds.
Puddle spread to a diameter of 1.3 m.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.25
Figure 8.8: Source Strength in case of Xylene escapes (pool fire)
b) Threat zone of thermal radiation from pool fire
Model output of the threat zone of thermal radiation from pool fire is given in Table
8.14. Isopleths result was not drawn because effect of near field patchiness make
dispersion prediction less reliable for short distance.
Table 8.14: Threat zone of thermal radiation from pool fire
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone
Radial Distance Red 10 (Potentially lethal within 60 sec.) < 10 m
Orange 5 (2nd degree burns within 60 sec) < 10 m
Yellow 2 (Pain within 60 sec) < 10 m
c) Threat at point
Effect has been worked out at a point in downwind direction at about 500 m distance
from the source within the premises and no significant concentration or effect observed
at given distance.
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
a) Source Strength
When Xylene will escape from drum and forms a fire ball, diameter of fire ball will be 34
m and burn duration will be 3 seconds.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.26
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 8.15 & Figure 8.9.
Table 8.15: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance
Red 10 (Potentially lethal within 60 sec.) 78 m
Orange 5 (2nd degree burns within 60 sec) 111 m
Yellow 2 (Pain within 60 sec) 173 m
Figure 8.9: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction at about 500 m distance
rom the source within the premises. The maximum thermal radiation estimated at point
will be 0.22 kW/m2. No significant effect observed at such low concentration at given
distance.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.27
8.6 RISK MITIGATIVE MEASURES
Unit has already taken all the risk mitigative measures in the existing plant.
Photographs showing safety management in existing plant are given in Annexure-16.
However, following measures are recommended for the proposed expansion.
Layout and location of hazardous chemical storage should be based on natural and
mechanical ventilation.
For any case of fire emergency, standard type of Fire extinguishers should be
provided in the storage area as well as required places in the plant.
Regular inspection of all tanks/ drums of hazardous chemicals should be carried out
before it is taken to the storage area and damaged drums should be separated and
disposed to avoid the possibility of catastrophic rupture.
All equipments related to hazardous chemical storage should be maintained and
calibrated regularly.
A trained person should be deployed for handling operation.
First-aid facility and first-aid trained person should be available at the time of
handling operation.
The adequate and suitable personnel protective equipments should be provided to
the operating workers.
SOP for handling should be displayed in local language for safe operating
procedure.
8.6.1. Fire Fighting System
Adequate system is provided by the unit for fire fighting as described below;
Sufficient numbers of Fire extinguishers are installed in all plants and storage area
as given below in Table 8.16.
An above ground Fire Hydrant System as described below has been installed in the
plant with rings around all blocks to achieve maximum coverage.
o Water reservoir - 500 m3
o Type of Hazard- Chemical, Ordinary Hazard
o Total no. of Fire Hydrant including landing Values, Water monitor-28 Nos.
o Diesel operated pump of 273 m3/hr capacity
o No. of Hose Boxes-20 nos.
o No. of Hoses- 30 reels
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.28
o No. of Nozzles - 21
Separate Water storage tank is provided for fire water as well as process water
requirement.
D.G. Sets is provided for emergency power.
Mock drill & training is conducted at scheduled intervals.
Fire fighting team members and rescue squad members as listed in Table 8.17 are
available at any time in the premises.
In addition to this, in case of any emergency help will be taken from the following
companies.
Name of Company Contact Person Contact number
Ratnamani Metal & Tubes Ltd. Mr.Haribandhav Barik 9099052117
Met Trade India Ltd. Mr.Kundan Suman 9909960206
Renaissance Corporation Ltd. Mr.Kuldeep Gautam 9714009111
Table 8.16: Details of Fire Extinguishers
Sr. No.
Area Location Type Capacity
1 Main Gate Security Office DCP 10 Kg 2 Admin Office Admin Office ABC 2 Kg 3 Admin Office Commercial Dept. ABC 2 Kg 4 Pump House Pump House DCP 5 Kg 5 Q/C Dept Lab Room DCP 10 Kg 6 Canteen Near Kitchen DCP 10 Kg 7 Styrene Tank Farm Front side of tank-1 M.Foam 45 liter 8 Styrene Tank Farm Front side of tank-1 M.Foam 45 liter 9 Styrene Tank Farm Front side of tank-2 M.Foam 45 liter
10 Styrene Tank Farm Front side of tank-2 M.Foam 45 liter Store/Ware House
11 Load Out Front side of load out M.Foam 45 liter 12 Load Out Near Load out gate DCP 10 Kg 13 Entarnce-1 Front side of Entrance-1 DCP 10 Kg 14 Entrance-1 Front side of Entrance-1 DCP 10 Kg 15 Store Office In Store office DCP 5 Kg 16 Store Office Near Store office M.Foam 45 liter 17 Entrance-2 Front side of Entrance-2 DCP 10 Kg 18 Entrance-2 Front side of Entrance-2 DCP 10 Kg 19 Exist Near Exist DCP 10 Kg 20 Exist Near Exist DCP 10 Kg 21 Raw material storage Malice Stock DCP 5 Kg 22 Raw material storage Malice Stock DCP 5 Kg 23 Raw material storage Monomer Stock DCP 10 Kg
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.29
Sr. No.
Area Location Type Capacity
Utility 24 MCC Room Near MCC Room entrance Co2 4.5 Kg 25 Utility Near motor Co2 22.5 Kg 26 DG House DG House DCP 5 Kg 27 Transformer Near Transformer gate Co2 4.5 Kg 28 Glycol tank Near Glycol tank M.Foam 45 liter
New Utility 29 Entrance Near welding/cutting area DCP 10 Kg 30 New Boiler Near Boiler DCP 5 Kg 31 MCC Room Front side of MCC Room gate Co2 6.5 Kg
Process Plant 32 Ground floor Near front Entrance gate M.Foam 9 liter 33 Ground floor Near front Entrance gate M.Foam 9 liter 34 Ground floor Near Stair case DCP 10 Kg 35 Ground floor Near Stair case DCP 10 Kg 36 Ground floor Front side of Hoist-2 DCP 10 Kg 37 Ground floor Near Holding tank-1 DCP 10 Kg 38 Ground floor Near Holding tank-2 DCP 10 Kg 39 1st Floor Near Stair case DCP 5 Kg 40 1st Floor Near Hoist-2 DCP 5 Kg 41 1st Floor Near Blender-5 DCP 5 Kg 42 1st Floor Near Hoist-1 DCP 5 Kg 43 1st Floor Near Stair case DCP 10 Kg 44 2nd Floor Near Stair case DCP 5 Kg 45 2nd Floor Near Hoist-2 DCP 5 Kg 46 2nd Floor Near Reactor-5 DCP 5 Kg 47 2nd Floor Near Hoist-1 DCP 5 Kg 48 2nd Floor Near Stair case DCP 10 Kg
Total Fire Extinguisher:
Sr. No Types of Extinguisher Total Nos.1 DCP 33 2 CO2 04 3 Foam 09 4 ABC 02 5 Sand Buckets Stand 06
Table 8.17: List of Fire Fighting & Rescue Squad Members
Fire Fighting Squad First Aider (Rescue Squad)
Mr. Digvijay Narayan Mr. Sanjay Dhabi
Mr. Sankar Samant Mr. Praveen Chavda
Mr. Surendra Verma Mr. G.C.Yadav
Mr. Sunil Kumar Sharma Mr. Dharmaraj
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.30
Mr. Pratap Swain Mr. Amit Shukla
Mr. Sankarsen Nahka Mr. Vishal Kumar
Mr. Rajendra Yadav Mr. Praveen Kumar Ved
Mr. Nawal Matoliya Mr. Motibhai Patel
Mr. Shishram Rar
Mr. Avinash Tomar
8.6.2. Emergency Management
Emergency Planning
Emergency siren and wind sock is installed.
On Site emergency Plan is prepared.
Tele communication system and mobile phone is used in case of emergency
situations for communication.
First Aid Boxes and First Aid Centre are made at site.
Safety Practices in the Work Area
Unit provides information to all employees about the potential hazards of contact
with chemicals and trains them in appropriate first-aid procedures.
Chemical handling areas are clearly marked and restricted to qualified, trained
personnel only.
Emergency Procedures
In case of emergenciesfirst aid and emergency response procedures are
adopted
Transportation Emergencies
In emergency situations resulting from vehicle accidents:
Notify the local police, fire departments, emergency responders and the carrier.
Isolate the area.
Any person not dressed in proper protective clothing and not using a NIOSH
approved self-contained breathing apparatus should be kept a safe distance
away.
Call to the supplier.
Seek immediate medical assistance for those injured and follow recommended
first aid procedures.
Leaking Containers
When handling a leaking bottle personal protective clothing, goggles and NIOSH
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.31
approved self contained breathing equipment must be worn.
Clear contaminated area of non-essential personnel and send them to assembly
point.
There should be provision of proper ventilation. Scrub the floors and equipment
with soap and water.
First Aid Procedure
For skin contact, immediately flush skin with plenty of water for at least 15
minutes while removing contaminated clothing and shoes.
To avoid the risk of static discharges and gas ignition, soak contaminated
clothing thoroughly with water before removing it. Wash clothing before reuse.
Clean shoes thoroughly before reuse. Get medical attention immediately.
In all cases of injury, obtain immediate medical attention.
Provide emergency personnel with information about all materials used by the
person
8.7 ONSITE EMERGENCY PLAN AND DISASTER MANAGEMENT PLAN
As emergency is said to have risen when operators in the plant are not able to cope
with a potential hazardous situation i.e. loss of an incident causes the plant to go
beyond its normal operating conditions, thus creating danger. When such an
emergency evolves, chain of events which affect the normal working within the factory
area and / or which may cause injuries, loss of life, substantial damage to property and
environment both inside and around the factory takes place and a DISASTER is said to
have occurred.
Various steps involved in Disaster Management Plan can be summarized as follows:
1. Minimize risk occurrence (Prevention)
2. Rapid Control (emergency response)
3. Effectively rehabitate damaged areas (Restoration)
Disaster Management Plan is evolved by careful scrutiny and interlinking of
a. Types and causes of disaster
b. Technical know-how
c. Resource availability
Types of Disaster:
a. Due to Fire and Explosion
b. Due to Vapour Cloud
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.32
c. Due to Toxic Gas Release from:
i. Within the Unit
ii. External Sources
d. Hurricane, Flood, Cyclone and other Natural Calamities
This plan is developed to make best possible use of resources to:
Reduce possibilities of accident.
Contain the incident and control it with minimum damage.
Safeguard others
Rescue the victims and treat them suitable.
Identify the persons affected/ dead.
Inform relatives of the causalities.
Provide authorative information to the news media.
Preserve relevant records and equipment needed as evidence incase of any inquiry.
Rehabilitate the affected areas.
The primary purpose of the on-site emergency plan is to control and contain the
incident and so as to prevent from spreading to nearby plant. It is not possible to
cover every eventuality in the plan and the successful handling of the emergency
will depend on appropriate action and decisions being taken on the spot. Onsite
emergency plan prepared by the unit is described hereunder;
8.7.1 Emergency Control Centre
For the purpose of handling emergency, the following Emergency Control Centres has
been identified.
During normal working hours - The Administrative Office
During other times - The Security Office
All communications to and from will originate at this control centre. The Emergency
Control Center will have the following;
a. List of important telephone numbers such as Police, Fire Brigade, Hospitals, and
other outside Emergency Services, etc. as given below;
Services Description/Place Contact. No Police Anjar 02836-243259 Fire Brigade Gandhidham 02836-270176,
02836-270439 Hospital Govt.Dispensary 02836-260608
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.33
Ram Baugh 02836-220263 Jivatram mangatrai 02836-260836 St.Joseph 02836-230160
Ambulance Gandhidham 02836-225636 Co. Doctor Divine life, Adipur 02836-263245
b. List of key Personnel with addresses and telephone numbers.
Name Contact numbers Mr.D.R.Karwasra 9714009140 Mr.S.T.Pillai 9714009148 Mr.Pradeep Garnayak 9714009149 Mr.Harshvardhan Sharma 9714009107 Mr.Amit Shukla 9714022209 Mr.Surendra Verma 9714009128 Mr.Digvijay Narayan 9714055592 Mr.Sankar Samanta 9714009156
c. List of Fire and Rescue Squad Members
d. Plant layout indicating storage of hazardous materials
e. Details of Fire Extinguishers and Fire Hydrant System
f. List of Personal Protective Equipment
g. Details of First Aid box
h. Details of Mutual Aid Scheme Members
8.7.2 Assembly Points
In case of an EMERGENCY the employees should assemble near the defined
Assembly Points, as indicated below:
Near parking area (Between Accounts office and Canteen)
Near RCL gate.
Wind direction to be determined by the wind socks installed on top of the utility-1
Building. The employees should run perpendicular to the wind direction and not against
/ along the wind direction.
8.7.3 Codification of Sirens
Sr. No.
Sirens Indicates Authority
1. 1 minute continous On site Emergency (alert) Incident controller 2. 30 second continous Emergency Controlled (all clear) Site controller
Note:
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.34
Emergency siren to be sounded only if required
All employees in areas other than affected to continue work unless emergency siren
is blown.
No emergency organization member will leave the emergency spot unless `All
Clear’ siren blown.
Emergency siren is tested on every Friday at 11:30 am.
8.7.4 Training and Education
Experience with on site –emergency planning has proved the need of training and
rehearsal. Major emergency procedure should be laid down clearly and convincingly to
everyone on site particularly Key Personnel and Essential workers. It is obvious that in
house or outdoor training is essential. The duties and responsibilities of each person
and the emergency procedure to be followed by him should be very clear.
a. Seminar/refresher guidance On Site Emergency Plan.
Seminar: Seminar is conducted in house. Awareness sessions shall be conducted to
explain the plan to all associated concerned employees.
b. Induction program:
Safety officer shall explain onsite emergency plan to all new employees during
induction program
8.7.5 Mock Rehearsal
Inform all the employees about mock drill.
Fix the date for mock drill.
Observers will not be involved in the exercise. They will monitor the Mock drill.
Emergency Siren / alarm will be raised.
After hearing the Siren / alarm, Emergency procedure will be followed as mentioned
in the OEP.
Observer will note down the activities with respect to the time.
8.7.6 Updating the Plan
On Site Emergency Management plan will be reviewed annually or any significant
incident or any change in regulation.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.35
8.7.7 Key Personnel & their Responsibilities
a) Site Controller
He will retain overall responsibility for the factory and its personnel. As soon as he is
informed of the emergency he shall proceed to the control room and meet the P&A.
Manager. His duties shall be:
Assess the magnitude of the situation and decide if staff needs to be evacuated
from their assembly points.
Exercise direct operational control over areas other than those affected.
Maintain a continuous review of possible development and assess in consultation
with Incident Controller and other Key personnel as to whether shutting down of the
plant or any section of the plant and evacuation of persons is required.
Liaison with Senior Officials of Police, Fire Brigade, Directorate of Industrial Safety,
provide advice on possible effects on areas outside the factory premises.
Control rehabilitation of affected areas on discontinuation of emergency.
Issue authorised statements to news media, and ensure that evidence is preserved
for inquiries to be conducted by statutory authorities.
b) Incident Controller
On hearing of an emergency siren he will rush to the scene of the occurrence and take
overall charge and report to Site Controller. On arrival he will assess the scale of
emergency and decide if major emergency exists or is likely and inform the
Communication Officer accordingly.
Direct all operations within the affected areas with the priorities for safety of
personnel minimise damage to the plant, property and minimise loss of materials.
Pending arrival of Site Controller, assume the duties of his post and, in particular.
Direct the shutting down and evacuation of plant and areas likely to be adversely
affected by the emergency.
Ensure that all Key personnel and outside help are called in.
Provide advice and information to the Fire squad & Security Officer and the local fire
service as and when they arrive.
Ensure that all non-essential workers/staff of the areas affected are evacuated to
the appropriate assembly points, and the areas are searched for casualties.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.36
In the event of failure of electric supply and internal telephones, set up
communication point and establish contact with Emergency Control Centre.
Report on all significant developments to the P & A manager.
Have regard to the need for preservation of evidence so as to facilitate any inquiry
into the causes and circumstances, which caused or escalated the emergency.
c) Human Resources Manager
He will also work as liaison Officer and will be stationed at the Main Entrance (Security
Office near Main Gate) during the emergency. He will under the direction of the site
Controller handle police, press and other inquiries, receive reports from roll-call leaders
from assembly points and pass on the absentee information to the Incident Controller.
His responsibilities shall include;
To ensure that casualties receive adequate attention, to arrange additional help if
required and information relatives.
To control traffic movements into the factory and ensuring that alternative transport
is available when need arises.
When emergency is prolonged, arrange for the relief of personnel and organise
refreshments / catering facility.
From information received, advise the Site Controller of the situation, recommending
(if necessary) evacuation of staff from assembly points.
Recruit suitable staff to act as runners between the Incident Controller and himself if
the telephone and other system of communication fails due to whatsoever reasons.
Maintain prior agreed inventory in the control centre.
In case of prolonged emergency involving risk to outside areas by wind-blown
materials, contact local Meteorological Office to receive early notification of changes
in weather conditions.
d) Security Officer
On hearing alarm advice fire squad and security staff in the factory of the incident zone
and cancel the alarm. He will also announce through telephone or messengers to the
HR Manager, Incident Controller and Site Controller that incident has occurred in such
and such zone. He will open the gates nearest to the incident and stand by to direct the
emergency service.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.37
On hearing the emergency alarm, he will immediately contact Site Controller and on his
advice call the local fire brigade. In case fire is discovered but no alarm is sounding he
shall receive information about location from the person discovering the fire and
thereafter immediately consult the Site Incident Controller and make announcement on
telephone telling the staff location of the incident and to evacuate to their assembly
points. He will continue to operate the switchboard advising the calls connected with
the incident to the Communications Officer.
e) Departmental Head
The Departmental head wherein the incident has taken place will report to Incident
Controller and provide assistance as required. They will decide which members of their
staff they require at the scene.
f) First-aid Teams
The Personnel Manager shall keep in security the roll call lists for the fire and first-aid
teams on duty. Each Departmental Head for his shift-team appoints roll call leaders
and first aiders. Roll call leaders shall check their rolls as members of the services
report for emergency duty. Names of any unaccounted for absentees will be informed
to the Security Officer.
Members of first-aid Teams will report to the Incident Controller on hearing of the alarm
in daytime. The Emergency vehicle driver, if safe to do so, shall collect the emergency
vehicle and park nearest to the scene of the incident. First aider shall inform the
incident controller that the Emergency Vehicle is leaving the site, giving the name of
the patient and destination i.e. hospital or doctor’s room and request the Incident
Controller to inform the destination (hospital, etc.) advising them about the casualties
reaching there.
g) Factory Fire Squad Personnel
The duty Fire fighting Squad under the command of the Security Officer shall be
responsible for fire fighting and rescue. On hearing the alarm, they shall proceed to the
place of incident. The men at security gate shall find out the location of the emergency
and proceed to the site of the occurrence. At the incident scene, a team members
detailed for this purpose will check squad members against roll-call sheet. At the site,
all the squad members will respond to the advice and information given by the Incident
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.38
Controller On arrival of the local fire brigade, they will also assist in fire-fighting work
with the advice of the Incident Controller.
8.7.8 Emergency Organization Chart
8.7.9 Emergency Action Plan
Any one noticing emergency situation like fire, explosion, toxic gas leakage etc. Must
DO’s Attract the nearby person/employee by shouting “FIRE – FIRE – FIRE”.
Seek help from the persons working nearby.
Try to control the incident at its initial stage with available means/sources quickly.
Inform Shift In-charge / Duty Officer (In Night Shift) about the Incident.
DON’Ts Do not be panicky.
Do not run – Walk fast.
Incident Controller Must
DO’s A. If Fire / Other Incidents Are Controllable
Approach the emergency site immediately taking note of wind direction.
Assess the situation.
Inform Security Officer, Tell – NAME, TYPE OF INCIDENT, ACTION TAKEN, HELP
NEEDED and Order Security Officer/Guard to inform all KEY persons.
Take lead in controlling emergency until such time concerned Section Manager
takes over the charge.
Site controller
Incident Controller
Fire fighting Squad, First aid Squad, HR Department, Engineering, Security Department, EHS Department,
Shift in charge
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.39
DON’TS Do not be panicky.
Do not lose temperament.
B. If Fire/Othr Incidents Are Not Controllable
In addition to above (A)
Order to blow emergency `ALERT’ Siren (1 minute continuous).
Organize Fire fighting / rescue team members to control the Incident.
Take stock of situation if required shut down the plant / process in affected area.
Call Fire Brigade if situation demands.
Evacuate affected area.
Organize head count of the plant.
Act as INCIDENT CONTROLLER till such time senior person takes charges as
indicated in Emergency organisation
Note:
1) Messenger will wait until such time Security Officer arrives.
2) Also inform Telephone Operator.
Security Officer / Guard Must
DO’s Do not allow any vehicle to come inside the factory.
Do not entertain any outside call except for emergency purpose.
Do not allow visitors to move around.
Inform all key persons about location and type of emergency.
Follow this sequence – Inform concerned HOD/Section Head, Main Site Controller,
Main Incident Controller & Safety Officer and other KEY persons.
Inform Main Site Controller about Government visitors, if any.
DON’Ts Do not entertain any outside call except for emergency purpose.
Do not allow visitor to move around, from reception.
Security Guard Must
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.40
DO’s Immediately report at Security Gate in shortest possible time.
Follow instructions of Officer In-charge.
Assist in controlling emergency.
Assist in controlling contractors, vehicle movement and mob.
Assist in cordoning off the area.
Take note of wind direction while approaching emergency site.
Render all possible help for controlling overall situation.
DON’Ts Do not leave the site unless asked to do so.
Emergency Vehicle Driver
DO’s Immediately start vehicle and reach rescue squad assembly point (near security
gate).
Rescue squad members to emergency site.
Take vehicle near to emergency site as directed.
Take note of wind direction.
Reverse the emergency vehicle for quick transports of injured, if any.
Keep vehicle engine running.
Always be on Driver’s seat of the vehicle.
Take the injured to the hospital as directed.
DON’Ts Do not leave the vehicle.
Do not take the vehicle very near to the site.
Site Controller
DO’s Will approach emergency site immediately / Assess the situation.
Consult Incident Controller.
Consult advising Committee Members.
Instruct Main Incident Controller.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.41
Communicate to higher ups and Govt. authorities, if required.
Decide upon need for evacuation and blow `Disaster Siren’.
After getting satisfied with the situation, give instruction to blow ALL CLEAR Siren.
DON’Ts Do not instruct to blow ALL CLEAR siren unless the situation is fully under control.
Don’t evacuate the entire plant unless the situation demands.
Fire Fighting Squad on Hearing Siren
DO’s Inform fellow employees/Officers.
Report to Fire Squad Assembly point.
Find out emergency location.
Approach emergency site immediately.
Take quick action as per the instructions from Incident controller.
Bring emergency under control as early as possible.
DON’Ts Do not leave process/equipment in UNSAFE CONDITION.
Do not leave emergency site unless ALL CLEAR siren blown.
Do not use improper fire extinguisher.
Do not be panicky.
Rescue Squad
DO’s Report to assembly point near Gate.
Get in touch with security about location and type of emergency.
Approach emergency site quickly with Breathing Apparatus set and First Aid box.
Get in touch with incident controller.
Follow instructions of Incident controller.
Render first aid to the injured, hospitalize, if required.
Accompany him to hospital and assist Doctor / Nurse.
Search for missing person in that area, if required.
Help in head count.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.42
All general employees except those who are in emergency organization on hearing
siren
DO’s Be alert and be available if required.
Wait for further instructions.
Bring down the process/plant/equipment in SAFE CONDITION in case of
DISASTER siren as per instructions from Incident Controller.
Approach respective safe assembling points route as taking note of wind direction.
Help in taking roll call.
After hearing ALL CLEAR, go back to the departments.
Start the work again after setting instruction from Incident controller.
DON’Ts Do not be panicky. Do not run.
Do not approach emergency site unless asked for.
Do not engage telephone except for emergency purpose. Keep lines free.
Technical Team: Engineering Department/ Environmnet, Safety and Health Department
on Hearing Siren
DO’s Be available in Engineering Department at respective location for any help.
Approach emergency site with required with tools and equipments and should work
on instructions of Incident controller.
Help Incident Controller to provide technical assistance.
Isolate lines, process equipments, if required by Incident Controller.
Provide emergency equipments like Fire Extinguisher, Hoses, etc., if asked by
Incident Controller.
Provide stopgap arrangements as per the requirement of Incident Controller.
Carry out electrical isolation of area as per instructions from Incident Controller.
Advisory Committee (All Department Heads)
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.43
DO’s Approach emergency site as early as possible.
Render advice to Main Incident Controller and Main Site Controller to control
emergency.
Communication Committee – (HR & Commercial)
DO’s Consult Main Site Controller
Give necessary instructions to security / Telephone Operator.
Give instruction to Security to control traffic / crowd.
Look after injured; communicate with the family members, if situation demands.
Arrange transportation, if required.
DON’Ts Do not communicate to any one or brief press without permission of Main Site
Controller.
General Intructions
DO’S Stop work at height. / Stop all hot works.
Stop all vessel entry.
Take note of wind direction.
On hearing Disaster Siren evacuates as per evacuation route without running and
panicky and assembles at respective safe Assembly Points.
DON’Ts Do not use telephone except for emergency purpose.
Do not start work at height, vessel entry, hot work unless permit conditions are
verified.
Do not allow unauthorized person to approach emergency site.
Plant Emergency Evacuation Plan is enclosed as Figure 8.10.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.44
Figure 8.10: Plant Emergency Evacuation Plan
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.45
8.8 OFF SITE EMERGENCY PLAN
The Off site emergency plan is made based on events, which could affect people and
Environment out side the premises. The off site plan is largely a matter of ensuring the
co-ordination of proposed services and their readiness as far as possible, for the
specific hazards and problems, which may arise in as incident. Briefly two main
purposes of the plan are as under:
To provide the local district authorities, police, fire brigade, doctors etc. the basic
information of risk and environmental impact assessment and to appraise them of
the consequences and the protection / prevention measures and control plans and
to seek their help to communicate with the public in case of major emergency.
To assist the district authorities for preparing the off site emergency plan for the
district or particular area. We have made our key personnel and other fully aware
about this aspect. The function of the off site plans are as under:
Structure of the off site emergency plan includes the following:-
Organizational set up-Incident controller /Site main controller, Key personnel, etc
Communication facilities - List of important telephones
Specialized emergency equipment - Fire fighting equipment
Specialized Knowledge - Trained people
Voluntary Organization - Details of organization
Chemical information - MSDS of hazardous substances
Meteorological information - Weather condition, Wind velocity etc
Humanitarian arrangement - Transport, First aid, Ambulance
Role of the factory management
The on site and off site plans are come together so that the emergency services are call
upon at the appropriate time and are provided with accurate information and a correct
assessment of situation.
Role of local authority
Generally the duty to prepare the off-site plan lies with the local authority. They may
have appointed an emergency planning officer (EPO) to prepare whole range of
different emergency within the local authority area.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.46
Role of fire authority
The control of a fire is normally the responsibility of the senior fire brigade officer who
would take over the handling of fire from the Incident Controller on arrival at the site.
Role of police
The overall control of an emergency is normally assumed by the police with a senior
officer designated as emergency coordinating officer. Formal duties of the police during
emergency include protection of life and property and controlling traffic movements.
Role of health authorities
Health authorities, including doctors, surgeons, hospitals, ambulances etc. have a vital
role to play following a major accident and they should form an integral part of the
emergency plan. Major off site incidents are likely to require medical equipments and
facilities in addition to those available locally.
Role of the “mutual aid” agencies
Some types of mutual aids are available from the surrounding factories, as per need, as
a part of the on site and off site emergency plan.
The role of the factory inspectorate
In the event of an accident, the factory inspector will assist the District Emergency
Authority for information and help in getting mutual aid from surrounding factories.
Unit maintains the records of details of emergency occur, corrective preventive
measures taken and in future the same practice will be continue. Unit has displayed the
details like list of assembly points, name of the persons involve in the safety team like
site controller, incident controller etc.
8.9 EARTHQUAKE HISTORY & MANAGEMENT PLAN
As per the earthquake sensitivity index, study area lies in Zone V, which is referred as
Very High Damage Risk Zone (MSK > IX). Seismic zone map of Gujarat is given in
Figure 8.11.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.47
Figure 8.11: Seismic Zone Map of Gujarat
Source: http://www.isr.gujarat.gov.in/Seismic_Zoning_India.shtm
Two damaging earthquakes are known to have struck the Kutch Peninsula during the
last two centuries, namely, the 1819 earthquake that killed more than 2000 people and
wiped out several centres of human settlements in the Rann and the more recent event
in 1956 that killed 115 people and damaged a large part of the town of Anjar.
The 26 January 2001 earthquake that occurred in Gujarat is the most disastrous
earthquake in India’s recent history. The earthquake occurred in Gujarat on 26 January
2001, India's 52nd Republic Day, at 08:46 AM local time and lasted for over two
minutes. The epicentre was about 9 km south-southwest of the village of Chobari in
Bhachau Taluka of Kutch Districtof Gujarat, India. This location is about 35 km away
from the Project site in North-North-East direction.
The earthquake reached a magnitude of between 7.6 and 7.7 on the moment
magnitude scale and had a maximum felt intensity of X (Intense) on the Mercalli
intensity scale. The quake killed around 20,000 people (including 18 in South
eastern Pakistan), injured another 1,67,000 and destroyed nearly 400,000 homes. This
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.48
was an intraplate earthquake, one that occurred at a distance from an active plate
boundary, so the area was not well prepared. The shock waves spread 700 km. 21
districts were affected and 600,000 people left homeless.
Unit has prepared all the existing sturture considering the earthquake risk in the area
and for proposed expansion all the structures will be earthquake resists. Training is
given to all the employees about such natural disaster. General Management plan for
earthquake is described hereunder;
Do's & Dont's:
Before an Earthquake
Repair deep plaster cracks in ceilings and foundations. Get expert advice if there
are signs of structural defects.
Anchor overhead lighting fixtures to the ceiling.
Follow BIS codes relevant to your area for building standards
Fasten shelves securely to walls.
Place large or heavy objects on lower shelves.
Store breakable items such as bottled foods, glass, and china in low, closed
cabinets with latches.
Hang heavy items such as pictures and mirrors away from beds, settees, and
anywhere that people sit.
Brace overhead light and fan fixtures.
Repair defective electrical wiring and leaky gas connections. These are potential fire
risks.
Secure water heaters, LPG cylinders etc., by strapping them to the walls or bolting
to the floor.
Store weed killers, pesticides, and flammable products securely in closed cabinets
with latches and on bottom shelves.
Identify safe places indoors and outdoors.
o Under strong dining table, bed
o Against an inside wall
o Away from where glass could shatter around windows, mirrors, pictures, or
where heavy bookcases or other heavy furniture could fall over
o In the open, away from buildings, trees, telephone and electrical lines, flyovers
and bridges
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.49
Know emergency telephone numbers (such as those of doctors, hospitals, the
police, etc)
Educate yourself and family members
Have a disaster emergency kit ready
Develop an emergency communication plan
o In case family members are separated from one another during an earthquake (a
real possibility during the day when adults are at work and children are at
school), develop a plan for reuniting after the disaster.
o Ask an out-of-state relative or friend to serve as the 'family contact' after the
disaster; it is often easier to call long distance. Make sure everyone in the family
knows the name, address, and phone number of the contact person.
Help your community get ready
o Publish a special section in your local newspaper with emergency information on
earthquakes. Localize the information by printing the phone numbers of local
emergency services offices and hospitals.
o Conduct week-long series on locating hazards in the home.
o Work with local emergency services and officials to prepare special reports for
people with mobility impairment on what to do during an earthquake.
o Provide tips on conducting earthquake drills in the home.
o Interview representatives of the gas, electric, and water companies about
shutting off utilities.
o Work together in your community to apply your knowledge to building codes,
retrofitting programmes, hazard hunts, and neighborhood and family emergency
plans.
During an Earthquake
Stay as safe as possible during an earthquake. Be aware that some earthquakes are
actually foreshocks and a larger earthquake might occur. Minimize your movements to
a few steps that reach a nearby safe place and stay indoors until the shaking has
stopped and you are sure exiting is safe.
If indoors,
DROP to the ground; take COVER by getting under a sturdy table or other piece of
furniture; and HOLD ON until the shaking stops. If there is no a table or desk near
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.50
you, cover your face and head with your arms and crouch in an inside corner of the
building.
Protect yourself by staying under the lintel of an inner door, in the corner of a room,
under a table or even under a bed.
Stay away from glass, windows, outside doors and walls, and anything that could
fall, (such as lighting fixtures or furniture).
Stay in bed if you are there when the earthquake strikes. Hold on and protect your
head with a pillow, unless you are under a heavy light fixture that could fall. In that
case, move to the nearest safe place.
Use a doorway for shelter only if it is in close proximity to you and if you know it is a
strongly supported, load bearing doorway.
Stay inside until the shaking stops and it is safe to go outside. Research has shown
that most injuries occur when people inside buildings attempt to move to a different
location inside the building or try to leave.
Be aware that the electricity may go out or the sprinkler systems or fire alarms may
turn on.
If outdoors,
Do not move from where you are. However, move away from buildings, trees,
streetlights, and utility wires.
If you are in open space, stay there until the shaking stops. The greatest danger
exists directly outside buildings; at exits; and alongside exterior walls. Most
earthquake-related casualties result from collapsing walls, flying glass, and falling
objects.
If in a moving vehicle,
Stop as quickly as safety permits and stay in the vehicle. Avoid stopping near or
under buildings, trees, overpasses, and utility wires.
Proceed cautiously once the earthquake has stopped. Avoid roads, bridges, or
ramps that might have been damaged by the earthquake.
If trapped under debris,
Do not light a match.
Do not move about or kick up dust.
Cover your mouth with a handkerchief or clothing.
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.51
Tap on a pipe or wall so rescuers can locate you. Use a whistle if one is available.
Shout only as a last resort. Shouting can cause you to inhale dangerous amounts of
dust.
After an Earthquake
Keep calm, switch on the radio/TV and obey any instructions you hear on it.
Keep away from beaches and low banks of rivers. Huge waves may sweep in.
Be prepared to expect aftershocks.
Turn off the water, gas and electricity.
Do not smoke and do not light matches or use a cigarette lighter. Do not turn on
switches. There may be gas leaks or short-circuits. Use a torch.
If there is a fire, try to put it out. If you cannot, call the fire brigade.
If people are seriously injured, do not move them unless they are in danger.
Immediately clean up any inflammable products that may have spilled (alcohol,
paint, etc).
If you know that people have been buried, tell the rescue teams. Do not rush and do
not worsen the situation of injured persons or your own situation.
Avoid places where there are loose electric wires and do not touch any metal object
in contact with them.
Do not drink water from open containers without having examined it and filtered it
through a sieve, a filter or an ordinary clean cloth.
If your home is badly damaged, you will have to leave it. Collect water containers,
food, and ordinary and special medicines (for persons with heart complaints,
diabetes, etc.)
Do not re-enter badly damaged buildings and do not go near damaged structures.
8.10 LANDSLIDE HAZARD MAP & MITIGATION PLAN
Landslides are downward and outward movement of slope materials such as rock
debris and earth, under the influence of gravity. A landslide hazard zonation map of
India is given below as Figure 8.12.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.52
Figure 8.12: Landslide Hazard Zonation Map of India
Source: Website of National Disaster Management Authority (NDMA), Government of India
The above map shows the areas of different hazard zones in various states of India and
from the same one may note that Himalayas of Northwest and Northeast India and the
Western Ghats are two regions of high vulnerability and are landslide prone. Kutch
district falls under the area having very low hazard due to landslide. However, general
mitigation measures suggested by NDMA are given hereunder;
Environmental Impact Assessment (EIA) Report Proposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.53
Do's & Dont's
We can stop loss of life and prepare ourselves in the wake of landslides. The
Government of India has made plans to identify the areas where landslides occur
repeatedly. This is achieved through Landslide Hazard Zonation (LHZ) maps which
show areas in different colours. Red, Yellow and Green signify as dangerous, caution
and safe in Hilly regions of Coast, Himalayas and rough terrain. NDMA has published
Guidelines on Landslides and Snow Avalanches as given on its website.
Keep drains clean.
Direct storm water away from slopes.
Inspect drains for - litter, leaves, plastic bags, rubble etc.
Keep the weep holes open.
Don’t let the water go waste or store above your house.
Grow more trees that can hold the soil through roots,
Identify areas of rock fall and subsidence of buildings, cracks that indicate landslides
and move to safer areas. Even muddy river waters indicate landslides upstream.
Notice such signals and contact the nearest District Head Quarters.
Ensure that toe of slope is not cut, remains protected, don’t uproot trees unless
revegetation is planned.
Recover and build
Remain calm and be alert and awake, listen to warnings of heavy and prolonged
period of rainfall from weather station, if your home is located below a debris
covered area move away to safer place, listen to sounds of rock fall, moving debris
and cracking of trees, or cracks in ground or any movement. Keep a battery
operated ready for the night.
Call and help rescue teams, keep drinking water containers, first aid kit and
essential medicines and avoid entering damaged houses.
Watch for flooding if close to river, help others who need help especially elderly
people, children and women, seek advice from local authorities for rebuilding
damaged houses, roads etc.
Report any damage of roads, power and telephone lines to concerned authorities.
Environmental Impact Assessment (EIA) ReportProposed Expansion in Manufacturing of Synthetic Organic Resins
Chapter-8: Risk and Safety Management
Page | 8.54
Emergency Kit Contents
Battery operated torch, Extra batteries, Battery operated radio, First aid kit and
manual, Emergency food (dry items) and water (packed and sealed), Candles and
matches in a waterproof container, Knife, Chlorine tablets or powdered water
purifiers, Can opener, Essential medicines, Cash, Aadhar Card and Ration Card,
Thick ropes and cords, Sturdy shoes