Environmental Impact Assessment
Awareness TrainingBy
David King
Why do we need an EIA in Ausgrid
Due to the Environmental Planning legislation (Environmental Planning and Assessment Act 1979)
All new work requires an assessment
To ensure that the environment is considered
As an environmental planning instrument / tool
To consider ecologically Sustainable Development
Why do we need an EIA in Ausgrid network construction & maintenance
Consequences of breaching the legislation
Severe penalties For corporations , Directors, Managers and individuals
Fines up to 1.1m – EP& A NSW planning $5m – POEO – NSW Pollution $5.5m – EPBC – Federal environmental Up to 7 years Jail Remediation and other additional costs
Typical Ausgrid network Projects that are covered by an EIA
Distribution substations Kiosks Pole transformers (PT)
Distributors Underground cables Overhead power lines
Typical Activities covered in an Ausgrid EIA
Construction Excavation Traffic disruptions After hours works Vegetation clearing Using heavy machinery Storing materials &
equipment Staging areas Discharging water
Operation Construction Noise Handling oil Oil filled equipment EMF
Maintenance Traffic disruptions Excavation Vehicle access
Things to be aware of about Ausgrid EIA document
EIA is a legal Document EIA will be used in court as evidence for and
against you EIA Is a document to be taken seriously by both
parties and will form part of the contract with the Construction Company
The Ausgrid EIA Worksheet is divided basically into four tables following
Table 1 – project details including a description of the environment where the works will take place
Table 2 – possible approval and licences which may be required
Table 3 - sensitive areas and issues that be affected by the project. etc. sulphate soils
Table 4 – Project specific environmental controls that are required in addition to the controls already listed in Environmental handbook
Typical Ausgrid network project that required the EIA Document provisions to be reviewed
Project location Yerroulbin St
BirchgroveCCO016339Field service representative Peter MarozCCL representativeDavid KingConstruction CompanyDunmain pty LtdAusgrid Project officer Nesta Penna
Ausgrid proposed network project located at Yerroulbin St Birchgrove
Ausgrid proposed Network project located at Yerroulbin st Birchgrove
The following EIA did not address the issue of the close proximately of the harbour foreshore and the associated risk in polluting this prestige area. This issue was raised at the pre-works and the EIA was amended
Original EIA Document for Ausgrid located at Yerroulbin st Birchgrove
Original EIA Document for Yerroulbin st Birchgrove areas highlights are deficient
Original EIA Document for Yerroulbin st Birchgrove areas highlights are deficient
Original EIA Document for Yerroulbin st Birchgrove areas highlights are deficient
Amended EIA Document for Yerroulbin st Birchgrove (Not all pages shown)
Amended EIA Document for Yerroulbin st Birchgrove (Not all pages shown)
New EIA addresses the issue of the waterways and has requested that an Erosion and sedimentation plan to be produced and approved by Environmental services group
Please see the following 5 slides showing the plan
Existing kiosk
Trial hole (trench)
Pro
perty
line
Tem
pora
rySe
curit
yFe
ncin
g
Property 111 D
Louisa Rd
Future Temp kiosk
Property 113
Louisa Rd
Yerroulbin Rd
Sediment Fencing
Sediment Fencing
Minimum 1 meter
Minimum 0.5 meter
Approx 25 metersto Snails Bay (Sydney Harbour)
SKETCH 1 OF 4
TRIAL HOLE Sedimentation Control Plan for Yerroulbin St Rozelle
EA project CCO016339
NTS
Prepared by P. Marosz ph 9394 6772 08/12/2010
Minimum 1 meter
Must exceed 1 meter
Slope approx1 :10
Slope approx1 :10
Grassed area where: - excavation may take place, or- surface soil cover is disturbed
Legend
Sandbag bund wall
Minimum 0.2 meter
Existing kiosk
Excavation to install compacted road base (instead of piers)
Pro
perty
line
Tem
pora
rySe
curit
yFe
ncin
g
Property 111 D
Louisa Rd
Future Temp kiosk
Property 113
Louisa Rd
Yerroulbin Rd
Sediment Fencing
Sediment Fencing
Minimum 0.5 meter
Minimum 0.5 meter
Approx 25 metersto Snails Bay (Sydney Harbour)
SKETCH 2 OF 4
EXCAVATION & INSTALLTION OF COMPACTED ROAD BASE (INSTEAD OF PIERS) FOR TEMP KIOSK -Sedimentation Control Plan for Yerroulbin St Rozelle
EA project CCO016339
NTS
Prepared by P. Marosz ph 9394 6772 08/12/2010
Minimum 1 meter
Must exceed 1 meter
Slope approx1 :10
Slope approx1 :10
Slope approx1 :10
Grassed area where: - excavation may take place, or- surface soil cover is disturbed
Legend
Sandbag bund wall
Minimum 0.2 meter
Existing kiosk
Excavation to install & connect new cables
Pro
perty
line
Tem
pora
rySe
curit
yFe
ncin
g
Property 111 D
Louisa Rd Temp kiosk
Property 113
Louisa Rd
Yerroulbin Rd
Sediment Fencing
Sediment Fencing
Minimum 0.5meter
Minimum 0.5 meter
Approx 25 metersto Snails Bay (Sydney Harbour)
SKETCH 3 OF 4
EXCAV TO INSTALL & CONNECT NEW CABLES , INSTAL PIERS FOR PERMANENT KIOSK -Sedimentation Control Plan for Yerroulbin St Rozelle EA project CCO016339
NTS
Prepared by P. Marosz ph 9394 6772 08/12/2010
Minimum 1 meter
Must exceed 1 meter
Slope approx1 :10
Slope approx1 :10
Grassed area where: - surface soil cover might be disturbed
Legend
Sandbag bund wallMinimum 0.2 meter
Pump out of trench water permissible over site grass – NO sediment into water ways.
Existing kiosk
Bulkheads in trench every 6 meters
or trench backfilled after each length of conduits installed
Property line
Property 111 D
Louisa Rd
Temp kiosk
Property 113
Louisa Rd
Yerr
oulb
in R
d
Sediment Fencing
Approx 25 metersto Snails Bay (Sydney Harbour)
SKETCH 4 OF 4
EXCAVATION & INSTALLATION OF NEW CONDUITS -Sedimentation Control Plan for Yerroulbin St Rozelle EA project CCO016339
NTS
Prepared by P. Marosz ph 9394 6772 08/12/2010
Slope approx1 :10
Grassed area v
Legend
Sandbag bund wall
New trench & conduits 2 on 2
Baulk head -extending at least 1 meter on either side of bund wall
Conduits sealed to prevent water ingress.
Louisa Rd
Slope approx1 :10
Sealed area ( asphalt & concrete) v
Excavation covered with plywood /steel plates & sealed with cold mix at edges to minimise water ingress
Pump out of trench water permissible over site grass – NO sediment into water ways.
Another project that the EIA Document needed to be revised due do to the changes in the scope of works
Project location Ewos St Cronulla
CCO016191Field service representativeMatt mobile 0421 416 329CCL representativeStephen BrennanConstruction CompanyCLMAusgrid Project officerDavid King
Ewos St Cronulla CCO016191
The proposed Low Voltage jointbay original position was to be excavated adjacent the pole. Unfortunately due to the location of the existing cable this would have raised the issue of maintaining pedestrian access and also the bending radius / length of the existing cable in the jointbay
With consultation with the field service representative it was proposed the jointbay be moved into the park area to follow the existing cable
Ewos St Cronulla CCO016191
Unfortunately the EIA only covered the excavation works in the carriageway & footway area.
The EIA did not address the issue of the close proximately of the waterway and the associated risk in polluting this prestige area.
Ewos St Cronulla CCO016191
The issue was raised with the field service representative and work in the park was put on hold until the matter was resolved.
Outcome was to minimise the impact of the works . Additional sediment measure was initiated in the park area and the jointbay was only excavated on the morning of the commissioning of the new cable . Backfilled same day
Summary EIA documents are legal
documents EIA document are to minimise
the risks to Ausgrid & the environment
If the EIA document supplied with the Ausgrid works order does not cover or seems not to cover the proposed work please refer the matter to your Ausgrid representative assigned to that project
Be aware of your Ausgrid responsibilities -see environmental code of conduct
Not banana bread was harmed in the produce of this presentation