Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Permit
_____________________________________________________________________________________________________________
Page 1 of 3 ABN 46 640 294 485
Environmental Protection Act 1994
Environmental authority EPPG00712213This environmental authority is issued by the administering authority under Chapter 5 of the Environmental Protection Act1994.
Environmental authority number: EPPG00712213
Environmental authority takes effect on 11 February 2019
Environmental authority holder(s)
Name(s) Registered address
SANTOS GLNG PTY LTD Ground Floor, Santos Centre 60 Flinders StreetADELAIDE SA 5000 Australia
Total GLNG Australia Level 13 28 The Esplanade PERTH WA 6000PAPL (Downstream) Pty Limited 'ADDISONS' Level 12 60 Carrington Street SYDNEY
NSW 2000KGLNG Liquefaction Pty Ltd Level 11 28 The Esplanade PERTH WA 6000
Environmentally relevant activity and location details
Environmentally relevant activity/activities Location(s)
Resource Activity, Schedule 2A, 08: A petroleum orGHG storage activity, other than items 1 to 7, thatincludes an activity from Schedule 2 with an AES
PFL10
Additional information for applicants
Environmentally relevant activities
The description of any environmentally relevant activity (ERA) for which an environmental authority (EA) isissued is a restatement of the ERA as defined by legislation at the time the EA is issued. Where there is anyinconsistency between that description of an ERA and the conditions stated by an EA as to the scale, intensityor manner of carrying out an ERA, the conditions prevail to the extent of the inconsistency.
An EA authorises the carrying out of an ERA and does not authorise any environmental harm unless a conditionstated by the EA specifically authorises environmental harm.
A person carrying out an ERA must also be a registered suitable operator under the Environmental ProtectionAct 1994 (EP Act).
Permit
Environmental authority
_____________________________________________________________________________________________________________
Page 2 of 3 ABN 46 640 294 485
Contaminated land
It is a requirement of the EP Act that an owner or occupier of contaminated land give written notice to theadministering authority if they become aware of the following:
- the happening of an event involving a hazardous contaminant on the contaminated land (notice must begiven within 24 hours); or
- a change in the condition of the contaminated land (notice must be given within 24 hours); or- a notifiable activity (as defined in Schedule 3) having been carried out, or is being carried out, on the
contaminated land (notice must be given within 20 business days);that is causing, or is reasonably likely to cause, serious or material environmental harm.
For further information, including the form for giving written notice, refer to the Queensland Government websitewww.qld.gov.au, using the search term ‘duty to notify’.
Take effect
Please note that, in accordance with section 200 of the EP Act, an EA has effect:
a) if the authority is for a prescribed ERA and it states that it takes effect on the day nominated by theholder of the authority in a written notice given to the administering authority-on the nominated day; or
b) if the authority states a day or an event for it to take effect-on the stated day or when the stated eventhappens; or
c) otherwise-on the day the authority is issued.However, if the EA is authorising an activity that requires an additional authorisation (a relevant tenure for aresource activity, a development permit under the Sustainable Planning Act 2009 or an SDA Approval underthe State Development and Public Works Organisation Act 1971), this EA will not take effect until the additionalauthorisation has taken effect.
If this EA takes effect when the additional authorisation takes effect, you must provide the administeringauthority written notice within 5 business days of receiving notification of the related additional authorisationtaking effect.
If you have incorrectly claimed that an additional authorisation is not required, carrying out the ERA withoutthe additional authorisation is not legal and could result in your prosecution for providing false or misleadinginformation or operating without a valid environmental authority.
Department of Environment and ScienceDelegate of the administering authorityEnvironmental Protection Act 1994 Date issued: 07 June 2019
Enquiries:Petroleum and Gas UnitDepartment of Environment and SciencePhone: 3330 5715Email: [email protected]
Permit
Environmental authority
_____________________________________________________________________________________________________________
Page 3 of 3 ABN 46 640 294 485
Obligations under the Environmental Protection Act 1994
In addition to the requirements found in the conditions of this environmental authority, the holder must also meettheir obligations under the EP Act, and the regulations made under the EP Act. For example, the holder mustcomply with the following provisions of the Act:
- general environmental duty (section 319)- duty to notify environmental harm (section 320-320G)- offence of causing serious or material environmental harm (sections 437-439)- offence of causing environmental nuisance (section 440)- offence of depositing prescribed water contaminants in waters and related matters (section 440ZG)- offence to place contaminant where environmental harm or nuisance may be caused (section 443)
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 1 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
Environmental Authority Conditions
This environmental authority consists of the following Schedules:
Part A – Coordinator General Report Conditions:
Schedule A General Conditions
Schedule B Air Emissions
Schedule C Water Management
Schedule D Noise Management
Schedule E Waste Management
Schedule F Land Management
Schedule G Storage and Handling of Chemicals, Flammable and Combustible
Substances
Schedule H Petroleum Infrastructure
Schedule I Monitoring Programs
Schedule J Community Issues
Schedule K Notification Procedures
Schedule L Release to Land
Part B – Additional Conditions:
Schedule BA General Conditions
Schedule BB Air Emissions
Schedule BC Water Management
Schedule BE Waste
Schedule BF Land
Appendix 1 Definitions
Appendix 2 Maps and Plans
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 2 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
PART A – COORDINATOR GENERAL REPORT CONDITIONS
SCHEDULE A – GENERAL CONDITIONS
A1
PREVENT AND/OR MINIMISE LIKELIHOOD OF ENVIRONMENTAL HARM
This authority does not authorise environmental harm unless a condition contained within this
authority explicitly authorises that harm. Where there is no condition or the authority is silent on a
matter, the lack of a condition or silence shall not be construed as authorising harm.
A2 In carrying out petroleum activities the holder of this authority must prevent and / or minimise the
likelihood of environmental harm being caused.
A3
MAINTENANCE OF MEASURES, PLANT AND EQUIPMENT
The holder of this authority must:
(a) install all measures, plant and equipment necessary to ensure compliance with the conditions of this authority
(b) maintain such measures, plant and equipment in a proper and efficient condition (c) operate such measures, plant and equipment in a proper and efficient manner.
A4 All instruments, equipment and measuring devices used for measuring or monitoring in
accordance with any condition of this authority must be calibrated, appropriately operated and
maintained.
A5 The holder of this authority must ensure that daily operation and maintenance of all plant and
equipment relating to the authorised petroleum activities are carried out by suitability qualified,
competent and experienced person(s).
A6 No change, replacement or alteration of any plant or equipment is permitted if the change,
replacement or alteration increases the risk of environmental harm from the petroleum activities.
A7 All analyses and tests required to be conducted under this authority must be carried out by a
laboratory that has NATA certification for such analyses and tests, except as otherwise
authorised by the administering authority.
A8 Despite Condition (C1), the holder of this environmental authority may carry out maintenance
activities at the product loading facility (PLF) and materials offloading facility (MOF) (depicted in
Appendix 2, Figure 7) which may result in direct or indirect release of contaminants to Port Curtis.
A9 When carrying out activities authorised under Condition (A8), the holder of this environmental
authority must ensure that any direct or indirect release of contaminants to waters does not
cause environmental harm.
A10 A management plan must be developed and implemented to ensure that maintenance activities
authorised under condition A8 do not result in environmental harm. This management plan must
be reviewed in accordance with Condition (I4).
A11 At least twenty-four (24) hours prior to carrying out an activity under condition A8, the holder of
this environmental authority must notify the administering authority of its intention to carry out the
activity and what the expected duration will be for carrying out the activity.
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 3 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
A12
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
The holder of this authority must conduct construction in accordance with the Construction
Environmental Management Plan approved by the Coordinator-General in accordance with
Condition 3 of Appendix 2, Part 1 of the Coordinator-General’s Evaluation Report.
A13
ENVIRONMENTAL MANAGEMENT PLAN
An Environmental Management Plan (EM plan) must be implemented that provides for the
effective management of the actual and potential impacts resulting from the carrying out of the
petroleum activities. Documentation relating to the EM plan must be kept.
A14 The EM plan required by condition (A13) must address, at least, the following:
(1) Describe each of the following:
(a) each relevant resource authority for the environmental authority; (b) all relevant petroleum activities (c) the land on which the activities including associated accommodation and recreational
activities are to be carried out (d) the environmental values likely to be affected by the activities including associated
accommodation and recreational activities (e) the potential adverse and beneficial impacts of the activities including associated
accommodation and recreational activities on the environmental values.
(2) State the environmental protection commitments the applicant proposes for the activities, including associated accommodation and recreational activities, to protect or enhance the environmental values under best practice environmental management.
(3) Include a rehabilitation program for land proposed to be disturbed under each relevant resource authority for the application.
(4) State a proposed amount of financial assurance for the environmental authority as part of the rehabilitation program.
(5) Training staff in the awareness of environmental issues related to carrying out the petroleum activities, which must include at least:
(a) The environmental policy of the authority holder, so that all persons that carry out the petroleum activities are aware of all relevant commitments to environmental management.
(b) Any relevant environmental objectives and targets, so that all staff are aware of the relevant performance objectives and can work towards these
(c) Control procedures to be implemented for routine operations for day to day activities including associated accommodation and recreational activities, to minimise the likelihood of environmental harm, however occasioned or caused
(d) Contingency plans and emergency procedures to be implemented for nonroutine situations to deal with foreseeable risks and hazards, including corrective responses to prevent and mitigate environmental harm (including any necessary site rehabilitation)
(e) Organisational structure and responsibility to ensure that roles, responsibilities and authorities are appropriately defined to ensure effective management of environmental issues
(f) Effective communication procedures to ensure two-way communication on environmental matters between operational staff and higher management
(g) Obligations with respect to monitoring, notification and record keeping obligations under the EM plan and relevant approvals
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 4 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
(h) Monitoring of the release of contaminants into the environment including procedures, methods and record keeping.
(6) The conduct of periodic reviews of environmental performance and procedures adopted, not less frequently than annually
(7) A program for continuous improvement.
A15 A Stormwater Management Plan must be prepared and implemented for the site prior to
construction and operation. The Stormwater Management Plan must address at least the
following:
(a) prevention of incident storm water and storm water run-off from contacting wastes or contaminants;
(b) diversion of upstream run-off away from areas where it may be contaminated by bulk products being loaded or unloaded, wastes, contaminants or other materials; and
(c) collection, treatment and disposal of all contaminated storm water run-off.
A16 A Waste Management Program (WMP) in accordance with Part 5 of the Environmental
Protection (Waste Management) Policy 2000 must be developed, implemented within 3 (three)
months from the date of this authority, and maintained for the authorised petroleum activities.
A17 The EM Plan must not be implemented or amended in a way that contravenes or is inconsistent
with any condition of this approval.
A18 Contingency plans and emergency procedures must be developed and implemented for
nonroutine situations to deal with foreseeable risks and hazards including corrective responses to
prevent and mitigate environmental harm (including a contingency plan when plant shuts down
for maintenance or other reasons).
A19
THIRD PARTY AUDITING
Compliance with the conditions of this authority must be audited by an appropriately qualified
third party auditor, nominated by the holder of this authority and accepted by the
administering authority, within one year of the completion of commissioning of the LNG
Facility, and every three years thereafter.
A20 Notwithstanding condition (A19), and prior to undertaking the third party audit, the scope and
content of the third party audit can be negotiated with the administering authority.
A21 Upon receipt of the final third party audit report, the holder of this authority must submit a
copy to the administering authority.
A22 The third party auditor must certify the findings of the audit in the report.
A23 The financial cost of the third party audit is borne by the holder of this authority.
A24 The holder of this authority must, within a reasonable period of time agreed in writing with the
administering authority, act upon any recommendations arising from the audit report and:
(a) investigate any non-compliance issues identified; and
as soon as practicable, implement measures or take necessary action to ensure compliance
with this authority.
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 5 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
A25 Subject to condition (A24), but otherwise not more than one (1) month following the
submission of the audit report, the holder of this authority must provide written advice to the
administering authority addressing the:
(a) actions taken by the holder to ensure compliance with this authority; and (b) actions taken to prevent a recurrence of any non-compliance issues identified.
A26
FINANCIAL ASSURANCE
The holder of this authority must provide a financial assurance in the amount and form
required by the administering authority for the authorised petroleum activities.
A27 The financial assurance is to remain in force until the administering authority is satisfied that
no claim is likely to be made on the assurance.
A28
DEFINITIONS
Words and phrases used in this authority are defined in Appendix 1 – Definitions. Where a
definition for a term used in this authority is not defined within this authority, the definitions in
the Environmental Protection Act 1994, its Regulation and Environmental Protection Policies
must be used.
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 6 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
SCHEDULE B—AIR EMISSIONS
B1
NUISANCE
The release of noxious or offensive odours or any other noxious or offensive airborne
contaminants resulting from the activities must not cause an environmental nuisance at any
nuisance sensitive or commercial place.
B2 The release of dust and/or particulate matter resulting from the activities must not cause an
environmental nuisance at any nuisance sensitive or commercial place.
B3 Dust and particulate matter must not exceed any of the following levels when measured at any
nuisance sensitive or commercial place:
(a) Dust deposition of 120 milligrams per square metre per day over a 30-days averaging period, when monitored in accordance with Australian Standard AS 3580.10.1 of 2003 (or more recent editions); OR
(b) A concentration of particulate matter with an aerodynamic diameter of less than 10 micrometre (μm) (PM10) suspended in the atmosphere of 50 micrograms per cubic metre (with five one day exceedances allowed in any one year period); and over a 24 hour averaging time, at a dust sensitive place downwind of the licensed place, when monitored in accordance with:
(i) Australian Standard AS 3580.9.6 of 2003 (or more recent editions) 'Ambient air - Particulate matter - Determination of suspended particulate PM10 high-volume sampler with size-selective inlet -Gravimetric method'; or
(ii) any alternative method of monitoring PM10 which may be permitted by the 'Air Quality Sampling Manual' as published from time to time by the administering authority.
Note: The above 5 days exceedances per year are based on the expected exceedances from
the natural events such as bushfires and dust storm.
B4
THE RELEASE OF CONTAMINANTS TO THE ATMOSPHERE
The release of contaminants to the atmosphere from a point source must only occur from
those release points identified in Schedule B, Table 1 - Contaminant Release Points and must
be directed vertically upwards without any impedance or hindrance.
B5 Contaminants must be released to the atmosphere from a release point at a height and a flow
rate not less than the corresponding height and velocity stated for that release point in
Schedule B, Table 1 - Contaminant Release Points
B6 Contaminants must not be released to the atmosphere from a release point at a mass
emission rate/concentration, as measured at a monitoring point, in excess of that stated in
Schedule B, Table 2 - Contaminant Release Limits to Air.
B7 Contaminants must be monitored not less frequently than specified in Schedule B, Table 2 -
Contaminant Release Limits to Air.
B8 Monitoring of any releases to the atmosphere required by a condition of this approval must be
carried out in accordance with the following requirements:
Environmental Authority No. EPPG00712213
Santos Reference: PEN101623910
Page 7 of 66
Department of Environment and Science
www.des.qld.gov.au ABN 46 640 294 485
(1) Monitoring provisions for the release points listed in Schedule B, Table 1 – Contaminant Release Points must comply with the Australian Standard AS 4323.1 - 1995 'Stationary source emissions, Method 1: Selection of sampling positions' (or more recent editions).
(2) The following tests must be performed for each determination specified in Schedule B, Table 2 - Contaminant Release Limits to Air: (i) gas velocity and volume flow rate (ii) temperature (iii) water vapour concentration (moisture content).
(3) Samples must be taken when emissions are expected to be at maximum rates. (4) During the sampling period the following additional information must be gathered:
(i) production rate at the time of sampling (ii) raw materials and fuel used (iii) number of plant or equipment and operating units operating; (iv) reference to the actual test methods and accuracy of the methods.
Permit
Environmental authority EPPG00712213
Page 8 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
B9
All release points referred to in Schedule B, Table 1 - Contaminant Release Points must be
conspicuously marked with the corresponding release point number.
Schedule B – Table 1: Contaminant Release Points
Number of
stacks/units Source description
Minimum release
height (m) above
grade level
Minimum
velocity
(m/s)
A1 – Methane
Compressor Driver
Mass emission rate and
concentration of oxides of
nitrogen (NOx) in the flue
gas at 15 percent oxygen
reference level.
32 12
A2 - Methane
Compressor Driver 32 12
A3 - Ethylene
Compressor Driver
(Bypass Stack)
44 2.4
A3 - Ethylene
Compressor Driver
(Waste Heat
Recovery Unit Stack)
44 8.5
A4 - Ethylene
Compressor Driver
(Bypass Stack)
44 2.4
A4 - Ethylene
Compressor Driver
(Waste Heat
Recovery Unit Stack)
44 8.5
A5 - Propane
Compressor Driver 32 12
A6 - Propane
Compressor Driver 32 12
A7 – Acid Gas and
Nitrogen Vent 43 10
A8 – Hot Oil Heater
Mass emission rate and
concentration of oxides of
nitrogen (NOx) in the flue
41 1.2
Permit
Environmental authority EPPG00712213
Page 9 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
gas at 3 percent oxygen
reference level.
A9 – Gas Turbine
Generator Turbine
Driver
Mass emission rate and
concentration of oxides of
nitrogen (NOx) in the flue
gas at 15 percent oxygen
reference level.
30 26
A10 - Gas Turbine
Generator Turbine
Driver
30 26
Number of
stacks/units Source description
Minimum release
height (m) above
grade level
Minimum
velocity
(m/s)
A11 - Gas Turbine
Generator Turbine
Driver
Mass emission rate and
concentration of oxides of
nitrogen (NOx) in the flue
gas at 15 percent oxygen
reference level.
30 19
A12 - Gas Turbine
Generator Turbine
Driver
30 19
A13 - Wet Gas Flares N/A 100 N/A
A14 - Marine Flare N/A 30 N/A
A15 - Dry Gas Flare N/A 100 N/A
A16 - Backup Wet &
Dry Flare N/A 100 N/A
B1 - Methane
Compressor Driver
Mass emission rate and
concentration of oxides
of nitrogen (NOx) in the
32 12
B2 - Methane
Compressor Driver 32 12
B3 - Ethylene
Compressor Driver
(Bypass Stack)
44 2.4
B3 - Ethylene
Compressor Driver
(Waste Heat
Recovery Unit Stack)
44 8.5
Permit
Environmental authority EPPG00712213
Page 10 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
B10
B4 - Ethylene
Compressor Driver
(Bypass Stack)
flue gas at 15 percent
oxygen reference level. 44 2.4
B4 - Ethylene
Compressor Driver
(Waste Heat
Recovery Unit Stack)
44 8.5
B5 - Propane
Compressor Driver 32 12
B6 - Propane
Compressor Driver 32 12
B7 - Acid Gas and
Nitrogen Vent 43 10
B8 – Hot Oil Heater
Mass emission rate and
concentration of oxides of
nitrogen (NOx) in the flue
gas at 3 percent oxygen
reference level.
41 1.2
Number of
stacks/units Source description
Minimum release
height (m) above
grade level
Minimum
velocity
(m/s)
B9 - Gas Turbine
Generator Turbine
Driver
Mass emission rate and
concentration of oxides
of nitrogen (NOx) in the
flue gas at 15 percent
oxygen reference level.
30 19
B10 - Gas Turbine
Generator Turbine
Driver
30 19
The minimum velocity limits specified in Schedule B, Table 1 - Contaminant Release Points apply
during normal operating conditions.
Permit
Environmental authority EPPG00712213
Page 11 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Schedule B – Table 2: Contaminant Release Limits To Air
Monitoring
location Contaminant
Emission limits per
stack
Frequency of
monitoring
A1 – Methane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 1.
Thereafter, at least one
Methane Compressor
Driver stack must be
monitored annually on a
rotational basis.
A2 - Methane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
A3 - Ethylene
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 1.
Thereafter, at least one
Ethylene Compressor
Driver stack must be
monitored annually on a
rotational basis.
A4 - Ethylene
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
A5 - Propane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 1.
Thereafter, at least one
Propane Compressor
Driver stack must be
monitored annually on a
rotational basis.
A6 - Propane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
A8 – Hot Oil
Heater
Oxides of
Nitrogen
350mg/Nm3(dry)
@3%O2 & 0.95
grams/second
The Hot Oil Heater must
be monitored within 3
months of
commissioning Train 1
and annually thereafter.
Permit
Environmental authority EPPG00712213
Page 12 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Monitoring
location Contaminant
Emission limits per
stack
Frequency of
monitoring
A9 – Gas Turbine
Generator Turbine
Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 1.74
grams/second All stacks must be
monitored within 3
months of
commissioning Train 1.
Thereafter, at least one
Gas Turbine Generator
Turbine Driver stack
must be monitored
annually on a rotational
basis.
A10 - Gas Turbine
Generator Turbine
Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 1.74
grams/second
A11 - Gas Turbine
Generator Turbine
Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 1.74
grams/second
A12 - Gas Turbine
Generator Turbine
Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 1.74
grams/second
B1 - Methane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 2.
Thereafter, at least one
Methane Compressor
Driver stack must be
monitored annually on a
rotational basis.
B2 - Methane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
B3 - Ethylene
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 2.
Thereafter, at least one
Ethylene Compressor
Driver stack must be
monitored annually on a
rotational basis.
B4 - Ethylene
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
B5 - Propane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 2.
Thereafter, at least one
Propane Compressor
Driver stack must be
B6 - Propane
Compressor Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 3.6
grams/second
Permit
Environmental authority EPPG00712213
Page 13 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
monitored annually on a
rotational basis.
B8 – Hot Oil
Heater
Oxides of
Nitrogen
350mg/Nm3(dry)
@3%O2 & 0.95
grams/second
The Hot Oil Heater must
be monitored within 3
months of
commissioning Train 2
and annually thereafter.
Monitoring
location Contaminant
Emission limits per
stack
Frequency of
monitoring
B9 - Gas Turbine
Generator Turbine
Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 1.74
grams/second
All stacks must be
monitored within 3
months of
commissioning Train 2.
Thereafter, at least one
Gas Turbine Generator
Turbine Driver stack
must be monitored
annually on a rotational
basis.
B10 - Gas Turbine
Generator Turbine
Driver
Oxides of
Nitrogen
51mg/Nm3(dry)
@15%O2 & 1.74
grams/second
B11
B12
The emission limits per stack specified in Schedule B, Table 2 – Contaminant Release Limits to Air
apply during normal operating conditions.
Within 3 months of commissioning Train 1 and Train 2 respectively, the holder of this environmental
authority must conduct air emission monitoring and prepare a report to demonstrate compliance with
air emission limits listed in Schedule B, Table 2 - Contaminant Release Limits to Air.
B13 Notwithstanding Condition (B6) and Schedule B, Table 2 - Contaminant Release Limits to Air, the
following emission limit for Oxides of Nitrogen is authorised to apply to any two Gas Turbine Generator
Turbine Drivers (monitoring locations A9 – A12, B9 & B10) at any one time until, and including, 20 July
2021:
(a) 73mg/Nm3 (dry) @15%O2 ; and
(b) 2.17 grams/second.
B14 Until, and including, 20 July 2021 the total maximum LNG Facility air emission limit for Oxides of
Nitrogen must not exceed 55.54 grams/sec @ 15%O2.
B15 During the period until, and including, 20 July 2021 each Gas Turbine Generator Turbine Driver
operating under Condition (B13) must:
(a) have air emissions monitoring undertaken at least once; and (b) air emissions monitoring must be undertaken in accordance with Condition (B8).
Permit
Environmental authority EPPG00712213
Page 14 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
B16
Flare conditions
The flare must be equipped with a flare tip design to provide good mixing with air, flame stability and
achieve a minimum Volatile Organic Compound (VOC) removal efficiency of 98 per cent under varied
gas flow rate and meteorological conditions and meet the best practice design standards (e.g. NSW
EPA: Protection of the Environmental Operations (Clean Air) Amendment (Industrial and Commercial
Activities) Regulation 2005, or the US EPA Code of Federal Regulations: 40 CFR 60.18 and 40 CFR
63.11).
B17 The flare must be equipped with a continuously burning pilot or other automatic ignition system that
assures gas ignition and provides immediate notification to appropriate personnel when the ignition
system ceases to function.
B18 The flare must be designed to handle large fluctuations in both the volume and the chemical content of
gases.
B19 Visible smoke and particulate emissions must not be permitted for more than five minutes in any two
hour period during normal operating conditions.
B20 Contingency plans and emergency procedures must be developed and implemented for nonroutine
situations to deal with foreseeable risks and hazards including corrective responses to prevent and
mitigate environmental harm (including a contingency plan when plant shuts down for maintenance or
other reasons).
B21
Fugitive Emissions
The holder of this environmental authority must ensure that all reasonable and practicable measures
are taken in the design and operation of the plant to minimise fugitive VOC emissions. Reasonable
and practicable measures include but are not limited to:
(a) implementation of a monitoring program to regularly leak test all units/components including pumps, piping and controls, vessels and tanks; and
(b) operating, maintenance and management practices to be implemented to mitigate fugitive VOC sources.
B22 The ducting and extraction systems that transfer effluent gases from one location to another must be
constructed, operated and maintained so as to minimise any leakage of VOCs and vapours to the
atmosphere occurring from these sources.
B23 In the event of emissions of contaminants occurring from industrial plant or ducting systems that
transfer effluent gases from one location to another, the fault or omission that resulted in that emission
must be corrected as soon as practicable.
B24
Fuel Burning
This authority only permits the burning of natural gas, methane gas or diesel fuel in the fuel burning
equipment under normal operating conditions at the rate of the design capacity of the equipment.
B25 The sulphur content of fuel burned in the power generators must not exceed 0.5 percent by weight
Permit
Environmental authority EPPG00712213
Page 15 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
B26
Greenhouse Gas Emissions
The holder of this authority must develop and implement a greenhouse gas reduction strategy for the
LNG Facility. The strategy must include, but not limited to, the company’s policy on greenhouse gas
emissions, an energy efficiency program, a continuous improvement program, better control systems
and a CO2 recovery plan.
Permit
Environmental authority EPPG00712213
Page 16 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
RELEASE TO WATERS
C1
PERMITTED CONTAMINANT RELEASE AND DISCHARGE POINT(S)
The only contaminant(s) permitted to be released directly or indirectly to any waters from the
petroleum activities authorised on the petroleum facilities licence are the following releases to Port
Curtis:
(1) Reverse Osmosis Concentrate (ROC) via the diffuser discharge point WW2 to Port Curtis during the construction of train 1 and train 2, (refer plan Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia); and
(2) Treated sewage effluent via the diffuser discharge point WW2 to Port Curtis during the construction of train 1 and train 2 (refer plan Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia).
C2
The release of contaminants directly or indirectly to waters must not produce any slick or other
visible or odorous evidence of oil, grease or petrochemicals nor contain visible floating oil, grease,
scum or litter.
C3
Reverse Osmosis Concentrate (ROC)
The total quantity of ROC released to waters as authorised in conditions (C1) and (BC3) on any one
day must not exceed 12 megalitres.
C4 The waste water effluent released via the diffuser discharge point WW1 must not exceed the release
limits specified in Schedule C, Table 1: Quality Characteristic Limits WW1 Waste Water Effluent
when measured at the monitoring point S9 described as the Discharge Monitoring Point (N
7369052, E 317270), refer plan Appendix 2 – Figure 1: GLNG Project Simplified Waste Water
Schematic.
Schedule C – Table 1: Quality Characteristic Limits WW1 Waste Water Effluent
Monitoring
Point
Quality
Characteristics
Release Limit Limit Type Minimum
monitoring
frequency
S91
Dissolved
Oxygen
4.0 mg/L Minimum
Weekly Grab
Sample Total Residual
Hydrocarbons
C10 – C36
10 mg/L Maximum
pH 6.0 to 8.5 Range
Notes:
1 Monitoring point S9 as the Discharge Monitoring Point (N7369052, E317270), shown in Appendix 2 – Figure
1: GLNG Project Simplified Wastewater Schematic.
Permit
Environmental authority EPPG00712213
Page 17 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
C5
Monitoring
Monitoring of contaminants released to Port Curtis must be undertaken for the quality characteristics
and parameters, at the monitoring point(s), and at the frequencies specified in Schedule C, Table 1:
Quality Characteristic Limits WW1 Waste Water Effluent.
C6
Diffuser validation
Provide to the administering authority a monitoring plan for the diffuser modelling validation within 40
business days from the issue of this environmental authority. The monitoring plan must have the
following objectives:
(a) To validate all modelling and investigations related to the diffuser; and (b) To confirm that expected dilutions predicted in design of the diffuser under specified flow
conditions are met as a minimum.
C7 The Monitoring Plan (Diffuser Validation), required by condition (C6), must include (but not be
limited to) the following:
(a) A description of the diffuser as installed (b) A list of the environmental values to be protected within and adjacent to the diffuser (c) Sampling of reference sites to determine the background concentration of relevant water quality
parameters (d) Investigate employing other approaches (e.g. dye-based diffuser validation techniques) where
electrical conductivity-based methods are inconclusive (e) The methods for the collection and analysis of samples (including the Quality Assurance and
Quality Control protocols adopted) (f) The methods of analysing the data and responding to the results (g) Monitoring must be done by a competent person(s) in accordance with methods prescribed in
the latest edition of the Department of Environment and Heritage Protection Water Quality Sampling Manual; and carried out on representative samples.
C8 The holder of the environmental authority must have due regard to comments, provided by the
administering authority, in the finalisation of the Monitoring Plan (Diffuser Validation).
C9 The holder of the environmental authority must provide to the administering authority a Diffuser
Validation Report, not more than 20 business days after receipt of the results obtained from the
Monitoring Plan (Diffuser Validation). The report must include:
(a) The outcome of the monitoring including the methodology, findings and recommendations of the Monitoring Plan (Diffuser Validation)
(b) A determination on the validation of modelling and investigations undertaken
C10
MONITORING OF VOLUME OF SEAWATER DESALINATION PLANT SEAWATER
INFLUENT, DESALINATION EFFLUENT AND BRINE
The daily volume and daily average flow rate of seawater influent treated must be determined or
estimated by an appropriate method with an accuracy of +/- 5 per cent, and records kept of such
determinations.
Permit
Environmental authority EPPG00712213
Page 18 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
C11 The daily volume and daily average flow rate of desalination effluent released from the premises
must be determined or estimated by an appropriate method with an accuracy of +/- 5 per cent, and
records kept of such determinations.
C12 The daily volume and daily average flow rate in m3/s of the brine component of the desalination
effluent discharged to marine waters must be determined or estimated by an appropriate method
with an accuracy of +/- 5 per cent, and records kept of such determinations.
C13 Monitoring of seawater influent for pH, temperature, turbidity, and conductivity must involve
instrumentation that is continuous, on-line, real-time and be able to be recorded and alarmed.
C14 Monitoring of desalination effluent for pH, chlorine, dissolved oxygen concentration and percent
saturation, temperature, turbidity, and conductivity must involve instrumentation that is continuous,
on-line, real-time and be able to be recorded and alarmed.
C15
RECEIVING ENVIRONMENT MONITORING PROGRAM (REMP)
A REMP must be developed and implemented to monitor and record the effects of the release of
contaminants on the receiving environment whilst contaminants are being discharged, with the aims
of identifying and describing the extent of any adverse impacts to local environmental values, and
monitoring any changes in the receiving water. For the purposes of the REMP the receiving
environment is defined as the waters of the China Bay and connected waterways within Port Curtis
(e.g. Xkm) downstream of the release. (i.e. Port Curtis) that addresses at least the following:
1. Description of potentially affected receiving waters including key communities and background water quality characteristics based on accurate and reliable monitoring data that takes into consideration any temporal variation (e.g. seasonality); and
2. Description of applicable environmental values and water quality objectives to be achieved (i.e. as scheduled pursuant to the Environmental Protection (Water) Policy 2009); and
3. Any relevant reports prepared by other governmental or professional research organisations that relate to the receiving environment within which the REMP is proposed; and
4. Water quality targets within the receiving environment to be achieved, and clarification of contaminant concentrations or levels indicating adverse environmental impacts during the REMP.
C16 The REMP must be maintained by a person possessing appropriate qualifications and experience in
the field of hydrology and surface water monitoring program design.
C17
The REMP must address but not be limited to the following:
1. Monitoring for any potential adverse environmental impacts caused by the intake or release, particularly in terms of potentially toxic contaminants that may be present in the ROC or Treated Sewage Effluent;
2. Monitoring performance of the diffuser to ensure adequate mixing and dilution; 3. Sampling to determine the extent of the near-field mixing zone at various tidal phases
(including the vertical profile) to validate modelling estimates; 4. Monitoring of selected toxicants (including ammonia nitrogen, total and free chlorine, dissolved
metals and metalloids likely to be present in intake water) to assess the extent of the compliance of concentrations with water quality objectives and the extent of the toxicity zone,
5. Monitoring of selected physical chemical parameters (including turbidity, pH, dissolved oxygen saturation, conductivity, temperature) that would assist in quantifying the mixing and dilution of the diffusers
Permit
Environmental authority EPPG00712213
Page 19 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
6. The locations of monitoring points including monitoring transects away from the outfall of the designated release point as well as control locations;
7. The proposed sampling depths; 8. The frequency or scheduling of sampling and analysis; 9. Any historical datasets to be relied upon; 10. Description of the statistical basis on which conclusions are drawn, and 11. Any spatial and temporal controls to exclude potential confounding factors.
C18 The REMP must be prepared and submitted in writing to the administering authority within three (3)
months prior to discharge occurring.
CONTAMINANT RELEASES TO GROUNDWATER
C19 There must be no release of contaminants
Permit
Environmental authority EPPG00712213
Page 20 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE D—NOISE MANAGEMENT
D1 Noise from the LNG plant activities must not cause environmental nuisance at any sensitive place
or commercial place.
D2 When requested by the administering authority, noise monitoring must be undertaken within a
reasonable and practicable timeframe nominated by the administering authority to investigate any
complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of
the authorised officer) of environmental nuisance at any sensitive place or commercial place, and
the results must be notified within 14 days to the administering authority following completion of
monitoring.
D3 If the authority holder can provide evidence through monitoring that the limits defined in Schedule
D – Table 1: Noise Limits for the LNG Plant at Sensitive Receptors are not being exceeded then
the holder is not in breach of Condition (D1). Monitoring and subsequent analysis must provide:
(a) determination of LAeq,15 mins for the LNG plant noise at the noise sensitive place or commercial place;
(b) narrow band analysis and the noise ‘signature’ of the LNG plant to determine the contribution from the LNG plant to the total noise level at the noise sensitive place or commercial place;
(c) the level and frequency of occurrence of impulsive or tonal noise; (d) taking measurements of the low frequency noise below 200 Hz; (e) atmospheric conditions including temperature, wind speed and direction; and (f) location, date and time or recording.
D4 If monitoring indicates exceedence of the limits in Schedule D – Table 1: Noise Limits for the LNG
Plant at Sensitive Receptors due to the contribution from the LNG plant activities, then the holder
of this authority must:
(a) resolve the complaint with the use of appropriate dispute resolution techniques to the satisfaction of the administering authority; or
(b) consider Best Practice Environmental Management in instigating noise abatement measures to comply with noise emission limits in Schedule D – Table 1: Noise Limits for the LNG Plant at Sensitive Receptors .
Permit
Environmental authority EPPG00712213
Page 21 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Schedule D – Table 1: Noise Limits For The LNG Plant At Sensitive Receptors
P1
Tid
e a
nd
Wit
t Is
lan
d
P2
So
uth
En
d
Cu
rtis
Is
lan
d
P3
Au
ckla
nd
Hill
P4
Yarw
un
P5
Targ
an
ie
P6
Gla
dsto
ne
Mari
na
P7
Fis
herm
an
s
Rd
Construction Noise Criteria dBA LAmax (Table 15 in EIS Appendix U1)
Monday - Friday
6.30am – 6.30pm
6.30pm – 6.30am
-
50
-
50
-
50
-
50
-
50
-
50
-
50
Saturday 6.30am – 6.30pm
6.30pm – 6.30am
-
50
-
50
-
50
-
50
-
50
-
50
-
50
Sundays and Public Holidays
6.30am – 6.30pm
6.30pm – 6.30am
50
50
50
50
50
50
50
50
50
50
50
50
50
50
Note: (-) Means no criteria apply during this time period
Operational Noise Criteria dBA LAeq
Monday - Sunday and Public Holidays
7am – 6pm
6pm – 10pm
10pm – 7am
46
46
44
38
37
34
47
47
40
46
45
40
36
36
36
50
47
41
40
35
30
Notes: Sensitive receptor locations are provided in Appendix 2 - Figure 6: Noise Monitoring Locations.
The noise levels in Schedule D - Table 1: Noise Limits for the LNG Plant at Sensitive Receptors apply for the
day, evening and night periods since the LNG plant operates continuously on a 24-hour basis.
D5 The method of measurement and reporting of noise levels must comply with the latest edition of
the Department of Environment and Heritage Protection’s Noise Measurement Manual.
D6
NOISE CONTROL MEASURES
The authorised activities must be carried out by such reasonable and practicable means
necessary to minimise the noise generated. The measures adopted must be incorporated into the
relevant procedure(s) implemented under the Environmental Management Plan required by
condition (A12) and must include, but not necessarily be limited to, the following noise abatement
measures:
(i) ensure that any equipment to be used on the site is assessed for potential noise nuisance impacts and appropriately attenuated;
(ii) low frequency components at the plant including the gas turbine are to be attenuated according to Australian standards and Best Practice Environmental Management;
Permit
Environmental authority EPPG00712213
Page 22 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
(iii) ensure that engine cowlings and high efficiency silencers are fitted to all the engines of all plant and equipment identified as impacting on noise sensitive receptors; and
(iv) where operation of reversing beepers is likely to cause environmental nuisance, taking measures to ensure mitigation of the environmental nuisance, for example by de-tuning the reversing beepers, replacing the reversing beepers with other warning devices and/or replacing reversing beepers with alternative reversing beepers which adjust their noise level output in accordance with the prevailing background noise level.
D7
LOW FREQUENCY NOISE
Notwithstanding condition (D1) and the limits specified in Schedule D Table 1: Noise Limits for the
LNG Plant at Sensitive Receptors in condition (D4), emission of any noise below 200 Hz must not
cause an environmental nuisance.
D8 Low frequency noise from the LNG plant is not considered to be a nuisance under condition (D7)
if monitoring shows that noise emissions do not exceed the following limits:
a) 60 dB(C) measured outside the sensitive receptor, and b) the difference between the external A-weighted and C-weighted noise levels is no greater
than 20 dB; or c) 50 dB(Z) measured inside the sensitive receptor; and d) the difference between the internal A-weighted and Z-weighted noise levels is no greater
than 15 dB.
Permit
Environmental authority EPPG00712213
Page 23 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE E – WASTE MANAGEMENT
E1 Waste generated in the carrying out the activities must be stored, handled and transferred in a
proper and efficient manner. Waste must not be released to the environment, stored, transferred
or disposed contrary to any condition of this authority.
E2 The holder of this authority must ensure that activities authorised under this environmental
authority do not result in the release or likely release of a hazardous contaminant to land or
waters.
E3 The holder of this authority must ensure that all general waste produced from the conducting of
the activities under this environmental authority is removed and disposed of at a facility that is
permitted to accept such waste.
E4 All regulated waste removed from the site must be removed by a person who holds a current
authority to transport such waste under the provisions of the Environmental Protection Act 1994
and sent to a facility that is permitted to accept such waste.
E5 When regulated waste is removed from within the boundary of the authorised facility and
transported by the holder of this authority, a record must be kept of the following:
a) date of waste transport b) quantity of waste removed and transported c) type of waste removed and transported d) quantity of waste delivered e) any incidents (e.g. spillage) that may have occurred en route.
E6 Regulated waste is not permitted to be disposed on site, including septic waste, sewage, and
concentrate and back wash water from the reverse osmosis plant.
Permit
Environmental authority EPPG00712213
Page 24 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE F – LAND MANAGEMENT
F1
EROSION AND SEDIMENT CONTROL PLANS
An Erosion and Sediment Control Plan must be developed and implemented for all stages of the
petroleum activities and which has been certified by a Certified Professional in Sediment and
Erosion Control, or a professional with appropriate experience and or qualifications accepted by
the administering authority.
F2 Appropriate measures to achieve compliance with condition (F1) for the petroleum activity must
be described in the EM plan and include:
(1) diverting uncontaminated stormwater run-off around areas disturbed by petroleum activities or where contaminants or wastes are stored or handled that may contribute to stormwater
(2) contaminated stormwater runoff and incident rainfall is collected; and treated, reused, or released in accordance with the conditions of this environmental authority
(3) roofing or minimising the size of areas where contaminants or wastes are stored or handled (4) using alternate materials and or processes (such as dry absorbents) to clean up spills that will
minimise the generation of contaminated waters (5) erosion and sediment control structures are placed to minimise erosion of disturbed areas
and prevent the contamination of any waters (6) an inspection and maintenance program for the erosion and sediment control features; (7) provision for adequate access to maintain all erosion and sediment control measures
especially during the wet season months from December to March (8) identification of remedial actions that would be required to ensure compliance with the
conditions of this environmental authority.
F3 Erosion protection measures and sediment control measures must be implemented and
maintained to minimise erosion and the release of sediment and contamination of stormwater.
F4 The maintenance and cleaning of any vehicles, plant or equipment must not be carried out in
areas from which contaminants can be released into any waters, roadside gutter or a stormwater
drainage system.
F5 Any spillage of wastes, contaminants or other materials must be cleaned up as quickly as
practicable. Such spillages must be cleaned up using dry methods that minimise the release of
wastes, contaminants or materials to any stormwater drainage system, roadside gutter or waters.
F6
ACID SULFATE SOILS
The holder of this authority must conduct an acid sulfate soils (ASS) investigation prior to
construction and in accordance with the requirements of the State Planning Policy 2/02
Development involving Acid Sulfate Soils and relevant guidelines such as the Guidelines for
Sampling and Analysis of Lowland Acid Sulfate Soils in Queensland 1998.
F7 Acid sulfate soils must be managed in accordance with the Queensland Acid Sulfate Soil
Technical Manual, Soil Management Guidelines 2002 such that contaminants are not directly or
indirectly released, as a result of the activity, to any waters or the bed and banks of any waters.
F8 As soon as practicable and within 3 (three) months of cessation of authorised activities that cause
any significant disturbance to land, the holder of this authority must investigate contaminated land
Permit
Environmental authority EPPG00712213
Page 25 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
status in accordance with Environmental Protection Act 1994 requirements and the NEPM where
land has been subject to contamination caused by activities authorised under this authority;
F9
PEST AND WEED SPECIES
Pest and weed species must be managed to prevent their growth and proliferation.
F10
MANAGEMENT OF FAUNA
The holder of this authority must develop and implement, within three (3) months from the date of
this approval, a Fauna Management Plan that details how the holder will ensure that authorised
activities are undertaken to minimise the potential risk of causing harm to fauna.
F11 The holder of this authority must minimise lighting disturbance to marine turtles by:
(a) physically shielding lights and directing the lights onto work areas (b) keeping light heights as low as practicable (c) using long wave length lights instead of short wavelength lights unless required for the safe
operation of the LNG Facility (d) minimising reflective surfaces (e) fitting motion detectors and light timers where practicable.
Permit
Environmental authority EPPG00712213
Page 26 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE G – STORAGE AND HANDLING OF CHEMICALS, FLAMMABLE AND COMBUSTIBLE
SUBSTANCES
G1 All explosives, hazardous chemicals, corrosive substances, toxic substances, gases, dangerous
goods, flammable and combustible liquids (including petroleum products and associated piping
and infrastructure) must be stored and handled in accordance with the relevant Australian
Standard where such is available.
G2 Notwithstanding the requirements of any Australian Standard and any other relevant Australian or
State legislation, any liquids stored on site that have the potential to cause environmental harm
must be stored in or serviced by an effective containment system that is impervious to the
materials stored and managed to prevent the release of liquids to waters or land. Where no
relevant Australian Standard is available, the following must be applied:
(a) storage tanks must be bunded so that the capacity and construction of the bund is sufficient to contain at least 110 per cent of a single storage tank or 100 per cent of the largest storage tank plus 10 per cent of the second largest storage tank in multiple storage areas; and
(b) drum storages must be bunded so that the capacity and construction of the bund is sufficient to contain at least 25 per cent of the maximum design storage volume within the bund.
Permit
Environmental authority EPPG00712213
Page 27 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE H - PETROLEUM INFRASTRUCTURE
H1 All infrastructure (including buildings, structures, petroleum equipment and plant erected and/or
used for the authorised activities) but excluding the Material Offload Facility and haul road,
authorised under this authority must be removed from the relevant environmental authority prior
to surrender of this authority, except where agreed in writing by the administering authority and
the current landowner.
H2 Prior to the commencement of decommissioning or abandonment activities, the scope of work for
decommissioning or abandonment of project infrastructure shall be developed and agreed to with
the administering authority.
Permit
Environmental authority EPPG00712213
Page 28 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE I – MONITORING PROGRAMS
I1 The holder of this authority must:
(a) develop and implement a monitoring program, within six (6) months from the date of this approval or three (3) months from commencement of construction activities, that will demonstrate compliance with the conditions in this authority
(b) document the monitoring and inspections carried out under the program and any actions taken.
I2 The holder of this authority must ensure that a suitably qualified, experienced and competent
person(s) conducts all monitoring required by this authority.
I3 The holder of this authority must record, compile and keep for a minimum of five (5) years all
monitoring results required by this authority and make available for inspection all or any of these
records upon request by the administering authority. Monitoring results relating to rehabilitation
should be kept until the administering authority has accepted surrender of the environmental
authority.
I4 Any management or monitoring plans, systems or programs required to be developed and
implemented by a condition of this authority must be reviewed for performance and amended if
required on an annual basis.
I5 An annual monitoring report must be prepared each year and presented in the format requested
(including electronic) to the administering authority when requested. Information and results held
by the administrating authority in relation to this approval may be used for any purpose including
supply to third parties. This report shall include but not be limited to:
(a) a summary of the previous twelve (12) months monitoring results obtained under any monitoring programs required under this authority and, a comparison of the previous twelve (12) months monitoring results to both this authority limits and to relevant prior results
(b) an evaluation/explanation of the data from any monitoring programs (c) a summary of any record of quantities of releases required to be kept under this authority (d) a summary of the record of equipment failures or events recorded for any site under this
approval (e) an outline of actions taken or proposed to minimise the environmental risk from any
deficiency identified by the monitoring or recording programs.
Permit
Environmental authority EPPG00712213
Page 29 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE J – COMMUNITY ISSUES
J1 When the administering authority advises the holder of a complaint alleging environmental
nuisance, the holder must investigate the complaint and advise the administering authority in
writing of the action proposed or undertaken in relation to the complaint.
J2 When requested by the administering authority, the holder of this authority must undertake
monitoring specified by the administering authority, within a reasonable and practicable timeframe
nominated by the administering authority, to investigate any complaint of environmental harm at
any sensitive or commercial place.
J3 The results of the investigation (including an analysis and interpretation of the monitoring results)
and abatement measures implemented must be provided to the administering authority within
fourteen (14) days of completion of the investigation, or receipt of monitoring results, whichever is
the latter.
J4 If monitoring in accordance with Condition (J2), indicates that emissions exceed the limits set by
this authority or are causing environmental nuisance, then the holder of this authority must:
(a) address the complaint including the use of appropriate dispute resolution if required; and/or (b) as soon as practicable implement abatement or attenuation measures so that noise, dust,
particulate or odour emissions from the authorised activities do not result in further environmental nuisance.
J5 Maintain a record of complaints and incidents causing environmental harm, and actions taken in
response to the complaint or incident; and
J6 The holder of this authority must record the following details for all complaints received and
provide this information to the administering authority on request:
(a) name, address and contact number for complainant; (b) time and date of complaint (c) reasons for the complaint (d) investigations undertaken (e) conclusions formed (f) actions taken to resolve complaint (g) any abatement measures implemented (h) person responsible for resolving the complaint.
J7 The holder of this authority must retain the record of complaints required by this condition for five
(5) years.
Permit
Environmental authority EPPG00712213
Page 30 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE K – NOTIFICATION PROCEDURES
K1 The holder of this environmental authority must telephone the Department of Environment and Heritage Protection’s Pollution Hotline (telephone: 1300 130 372) and any affected landholder, occupier or their nominated representative as soon as reasonably practicable, but within 24 hours after becoming aware of:
(a) an unauthorised release of contaminants as provided for in condition (K3); or (b) any event where environmental harm (excluding environmental nuisance) has been caused or
may be caused.
K2 Notwithstanding condition (K1), the holder of this environmental authority must telephone the
Department of Environment and Heritage Protection’s Pollution Hotline (telephone: 1300 130 372) as
soon as reasonably practicable, but within 24 hours after becoming aware of any non-compliance with
any condition of this environmental authority other than in relation to a release of contaminants.
K3 Subject to condition (K1), the holder of this environmental authority must report spills of contaminants (including but not limited to hydrocarbons) of the following volumes or kind:
(a) unauthorised releases of any volume of contaminants to water; (b) unauthorised releases of volumes of contaminants to land greater than 200L of hydrocarbons; or (c) any other release not authorised under this environmental authority which has caused, or has the
potential to cause serious or material environmental harm.
K4 The notification of emergencies or incidents as required by conditions (K1), (K2) and (K3) must include but not be limited to the following information:
(a) the environmental authority number and name of the holder; (b) the tenure type and number where the emergency or incident occurred; (c) the name and telephone number of the designated contact person; (d) the location of the emergency or incident (GDA94); (e) the date and time that the emergency or incident occurred; (f) the date and time the holder of this environmental authority became aware of the emergency or
incident; (g) details of the nature of the event and the circumstances in which it occurred; (h) the estimated quantity and type of any contaminants involved in the incident; (i) the actual or potential suspected cause of the emergency or incident; (j) a description of the land use at the site of the emergency or incident (e.g. grazing, pasture, forest
etc.) and / or the name of any relevant waters and other environmentally sensitive features; (k) a description of the possible impacts from the emergency or incident; (l) a description of whether stock and / or wildlife were actually or potentially exposed to any
contaminants released and measures taken to prevent access for the duration of the emergency or incident;
(m) any sampling conducted or proposed, relevant to the emergency or incident; (n) landholder details and details of landholder consultation; (o) immediate actions taken to control the impacts of the emergency or incident and how
environmental harm was mitigated at the time of the emergency or incident; and
Permit
Environmental authority EPPG00712213
Page 31 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
(p) whether further examination / root cause analysis is required and if so, the expected date by when this examination will be completed and reported to the administering authority.
K5 Within 10 business days following the initial notification, unless a longer time is agreed to by the administering authority, a written report must be provided to the administering authority, including the following (where relevant to the emergency or incident):
(a) the information required by condition (K4); (b) the root cause of the emergency or incident; (c) the confirmed quantities and types of any contaminants involved in the incident; (d) results and interpretation of any analysis of samples taken at the time of the emergency or
incident (including the analysis results of any impact monitoring); (e) a final assessment of the impacts from the emergency or incident including any actual or potential
environmental harm that has occurred or may occur in the longer term as a result of the release; (f) the success or otherwise of actions taken at the time of the incident to prevent or minimise
environmental harm; (g) results and current status of landholder consultation, including commitment to resolve any
outstanding issues / concerns; and (h) actions and / or procedural changes to prevent a recurrence of the emergency or incident.
K6 Within 10 business days following the initial notification of an emergency or incident or receipt of
monitoring results indicating any significant changes in groundwater quality caused by the petroleum
activity(ies), then the analysis results indicating these changes, including any proposed actions to
mitigate the changes in groundwater quality information must be submitted to the administering
authority.
K7 If groundwater contamination caused by the petroleum activity(ies) is encountered, the following must be reported to satisfy requirements under condition (K6): (a) the level of environmental harm caused as a result of such contamination to soils and
groundwater; and (b) the determination of groundwater flow direction, groundwater flow rate and hydraulic conductivity.
Permit
Environmental authority EPPG00712213
Page 32 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE L - RELEASE TO LAND
L1
PERMITTED CONTAMINANT RELEASE AND DISCHARGE POINT(S)
Contaminant(s) are not permitted to be released directly or indirectly to land unless otherwise
authorised under this environmental authority.
MAINTENANCE OF STORMWATER MANAGEMENT DEVICES
L2 Suitable banks and/or diversion drains must be installed and maintained to exclude
stormwater runoff from entering the LNG facility footprint.
L3 All stormwater management devices must be installed and maintained to ensure they are
working properly at all times, including the following:
a) oil and grit separator devices;
b) detention basin(s);
c) grass swales; and
d) trash racks and protected risers.
Permit
Environmental authority EPPG00712213
Page 33 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
PART B – ADDITIONAL CONDITIONS
SCHEDULE BA – GENERAL CONDITIONS
BA1
Scope
This environmental authority authorises:
a) A petroleum activity that is likely to have a significant impact on a category A or category B environmentally sensitive area;
b) the construction and operation of a two train Liquid Natural Gas Facility with a capacity up to 7.8 Million Tonne per annum; and
c) A petroleum activity or GHG storage activity, other than an activity mentioned in any of the items 1 to 7 of Schedule 2A of the Environmental Protection Regulation 2008, that includes 1 or more activities mentioned in schedule 2 of the Environmental Protection Regulation 2008 for which an AES is stated, including the following specified relevant activities:
(i) ERA 8(3) – Chemical storage consisting of storing more than 500m3 of chemicals of class C1 or C2 combustible liquids under AS1940 or dangerous goods class 3 under subsection (1)(c).
(ii) ERA 8(4) - storing 200t or more of chemicals that are solids or gases, other than chemicals mentioned in items 1 to 3, under subsection (1)(d);
(iii) ERA 9(c) - Hydrocarbon gas refining consisting of refining coal seam gas;
(iv) ERA 10 - Gas producing consisting of manufacturing, processing or reforming 200t or more of hydrocarbon gas in a year;
(v) ERA 14(2)(a) - Electricity generation consisting of generating electricity by using a fuel, other than gas, at a rated capacity of 10MW electrical to 150MW electrical;
(vi) ERA 15 - Fuel burning consisting of using fuel burning equipment that is capable of burning at least 500kg of fuel in an hour;
(vii) ERA 16(1)(b) - Extractive and screening activities consisting of dredging, in a year, the following quantity of material more than 10000t but not more than 100000t;
(viii) ERA 16(2)(c) - Extractive and screening activities consisting of extracting, other than by dredging, in a year, the following quantity of material more than 1000000t;
(ix) ERA 16(3)(c) - Extractive and screening activities consisting of screening, in a year, the following quantity of material more than 1000000t;
(x) ERA 33 – Crushing, milling, grinding or screening consisting of crushing, grinding, milling or screening more than 5000t of material in a year;
(xi) ERA 38(2) - Surface coating consisting of coating, painting or powder coating, using, in a year, more than 100t of surface coating materials;
(xii) ERA 47(c) - Timber milling and woodchipping consisting of milling more than 20000t but not more than 100000t of timber in a year;
(xiii) ERA 50(2) – Bulk material handling consists loading or unloading 100t or more of bulk materials in a day or stockpiling bulk materials;
(xiv) ERA 63(1)(c) – Sewage treatment consisting of operating sewage treatment works, other than no-release works, with a total daily peak design capacity of more than 1500 but not more than 4000EP;
(xv) ERA 63(1)(b)(ii) – Sewage treatment consisting of operating sewage treatment works, other than no-release works, with a total daily peak design capacity of more
Permit
Environmental authority EPPG00712213
Page 34 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
BA1A
BA1B
than 100 but not more than 1500EP which is discharged from the works other than to an infiltration trench or through an irrigation scheme;
(xvi) ERA 64(1)(b) - Water treatment consisting of desalinating, in a day, more than 5ML of water, allowing the release of waste only to seawater.
This environmental authority authorises the carrying out of the authorised environmentally relevant activities subject to the conditions of this environmental authority.
This environmental authority does not authorise a relevant act[1] to occur in carrying out an
authorised relevant activity unless a condition of this environmental authority expressly
authorises the relevant act to occur.1
BA2
Financial Assurance
The calculation of financial assurance must be in accordance with the most recent version of
the administering authority’s Guideline “Financial Assurance for Petroleum Activities”.
BA3 Subject to Part A – Condition (A26), the holder of this authority must submit a revised
calculation of the financial assurance to the administering authority:
(a) with the annual return; and (b) prior to the second year of construction activities, 2012; and (c) prior to the third year of construction activities, 2013; and (d) prior to the commissioning of the plant, 2016.
BA4
Third Party Audit
The third party auditor certification required by Part A – Condition (A22), must include a
Statutory Declaration certifying the findings of the audit in the report.
BA5
Contingency Plans and Emergency Procedures
The emergency response/contingency plan required under Part A - Condition (A18) must
address the following matters as a minimum:
(a) A clear definition of what constitutes an emergency event for the activity; (b) Response procedures to be implemented to prevent or minimise the risk of environmental
harm arising from incidents; (c) Response procedures to minimise the extent and duration of environmental harm caused
by an incident; (d) The practices and procedures to be employed to restore the environment or mitigate any
environmental harm caused; (e) The resources to be used in response to an incident; (f) Procedures to investigate the cause of any incidents, including releases, and where
necessary, implement remedial actions to reduce the likelihood of recurrence of similar events;
(g) A receiving environment (surface waters/land) monitoring program, to be implemented in the event of a release to waters/land to examine/assess environmental impacts (for waters this must include upstream and downstream monitoring);
(h) The provision and availability of documented procedures to staff attending any incident to
[1] See section 493A of the Act.
Permit
Environmental authority EPPG00712213
Page 35 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
enable them to effectively respond; (i) Training of staff that will be called upon to respond to incidents to enable them to
effectively respond; (j) Timely and accurate reporting of the circumstance and nature of incidents to the
administering authority in accordance with conditions of this environmental authority; (k) Procedures for accessing monitoring points during incidents; and (l) Procedures to notify any potentially impacted stakeholder who may be affected by the
event.
BA6
Spill Kit
An appropriate spill kit, personal protective equipment and relevant operator
instructions/emergency procedure guides for the management of wastes and chemicals
associated with the activities must be kept and maintained at the site.
BA7
Spill Kit Training
Anyone operating under this approval must be trained in the use of the spill kit.
BA8
Documentation and Records Management
All records and results required by the conditions of this environmental authority must be kept
for a minimum of five (5) years.
BA9 All documentation required by this environmental authority (including but not limited to the
results of any audits, assessments, monitoring, inspections and complaint records) must be
made available to the administering authority upon request.
BA10
Cultural Heritage
In the carrying out of the petroleum activity the holder of this environmental authority must not
adversely impact on the cultural heritage values of any place registered on the Queensland
Heritage Register.
BA11
Abrasive Blasting and Surface Coating
In carrying out abrasive blasting and surface coating activities, the environmental authority
holder must comply with the Code of Environmental Compliance for certain aspects of Mobile
and Temporary Abrasive Blasting.
Permit
Environmental authority EPPG00712213
Page 36 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE BB—AIR EMISSIONS
Construction Diesel Generators
BB1 The holder of this environmental authority must ensure that the ground level concentrations do not
exceed the criteria for each air contaminant in Schedule BB, Table 1 – Maximum Ground Level Concentration Criteria.
Schedule BB – Table 1: Maximum Ground Level Concentration Criteria
Contaminant Concentration at
0°Celsius Units Averaging time
Nitrogen Dioxide 250 µg/m3 1 hour
Nitrogen Dioxide 33 µg/m3 1 year
Carbon Monoxide 11 mg/m3 8 hour
BB2 The holder of this environmental authority must undertake emissions testing within three (3) months
post commissioning of any three (3) fuel burning and combustion equipment capable of burning at least 500 kg of fuel in an hour to verify the estimates used in the air dispersion modelling.
BB3 Where the results of the emissions testing required under condition (BB2) indicate that the emission
estimates used in the document titled GLNG LNG Facility Construction Project – Assessment of Emissions to Air from Generator Plant dated 09 September 2011 are exceeded, the holder of this environmental authority must:
(a) provide details to the administering authority within 10 business days; (b) re-undertake the modelling based on the new information; and (c) determine and implement appropriate pollution control measures to bring the emissions into
compliance with the limits specified in Schedule BB, Table 1 – Maximum Ground Level Concentration Criteria.
Permit
Environmental authority EPPG00712213
Page 37 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE BC – WATER MANAGEMENT
BC1
General
Contaminants that will, or have the potential to cause environmental harm, must not be released directly
or indirectly to any waters except as permitted under the conditions of this environmental authority.
BC2 Unless stated otherwise all conditions apply to construction.
BC3
PERMITTED CONTAMINANT RELEASE AND DISCHARGE POINT(S)
In addition to Part A, Condition (C1), the only contaminant(s) permitted to be released directly to any
waters from the petroleum activities authorised on the petroleum facilities licence are the following
releases to Port Curtis:
(a) Stage 1 – Early Works (excludes Stage 2 – construction works)
(i) Stormwater via release points for Stage 1 – early works listed in Schedule BC Table 1:
Contaminant Release Points and in accordance with release limits specified in Schedule BC –
Table 3: Stormwater Release Limits (including stage 2 – construction works).
(b) Construction
(i) Blended Reverse Osmosis Concentrate and Sewage Treatment Effluent via the diffuser discharge point WW2 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 2 – construction works;
(ii) Stormwater via discharge points SW1, SW2, SW3, SW4, SW5, SW6, SW7, SW9 and SW10 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 2 – construction works;
(iii) Hydrotest water (other than seawater used to hydrotest LNG tanks), flushing water and firewater system testing water via sediment basins to discharge points SW2, SW3 and SW5 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Port Curtis Island Australia during Stage 2 – construction works;
(iv) Waste Water Effluent via the diffuser discharge point WW1 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Port Curtis Island Australia during Stage 2 – Construction;
(v) Turbine Inlet Air Chilling condensate water via discharge point SW3 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 2 – construction works;
(vi) Seawater used to hydrotest LNG tanks via temporary discharge point TWW1 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 2 – construction works; and
(vii) Firewater system testing water released from the Product Loading Facility (PLF) Loading Platform to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 2 – construction works.
(viii) Treated waste water effluent via discharge point SW2 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 2 – construction works.
(c) Operation
Permit
Environmental authority EPPG00712213
Page 38 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
(i) Waste Water Effluent via the diffuser discharge point WW1 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 3 – operational works;
(ii) Stormwater via discharge points SW1, SW2, SW3, SW4, SW5, SW6, SW7, SW9 and SW10 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 3 – operation;
(iii) Turbine Inlet Air Chilling condensate water via discharge point SW3 to Port Curtis, Appendix 2 – Figure 3: Air and water Discharge Points Curtis Island Australia during Stage 3 – Operation;
(iv) Firewater system testing water release from the PLF Loading Platform to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during stage 3 – operation works; and
(v) Firewater system testing water via sediment basins to discharge points SW2, SW3 and SW5 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during stage 3 – Operation.
(vi) Treated waste water effluent via discharge point SW2 to Port Curtis, Appendix 2 – Figure 3: Air and Water Discharge Points Curtis Island Australia during Stage 3 – operation works.
BC4
Releases to Waters
The release point WW1 must be submerged such that the top of the outfall pipe is at least 10 metres
below Low Water Datum. The release point WW2 must be submerged such that bottom of the outfall
pipe is at least 6m above the seabed.
BC5 All contaminants from discharge location WW1 must be released through a proper and effective diffuser
to achieve a minimum initial dilution of 91:1.
BC6 All contaminants from discharge location WW2 must be released through a proper and effective diffuser
to achieve a minimum initial dilution of 1:50.
BC7
Contaminant Releases to Waters
The release of contaminants directly to waters must only occur from the release points specified in
Schedule BC – Table 1: Contaminant Release Points.
Schedule BC – Table 1: Contaminant Release Points
Release
Point
Latitude or northing
(GDA94)
Longitude or
easting
(GDA94)
Contaminant
Source,
Location and
Description of
Release Point
Monitoring Point Receiving
Waters
Description
WW1 N7368573.212 E316794.358 Construction
and
Operational
Outfall
S9 – Prior to
outlet of
diffuser
discharge
point WW1
Port
Curtis
Permit
Environmental authority EPPG00712213
Page 39 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
TWW1 N7368547.323 E316793.228 Temporary
Construction
Outfall
- Port
Curtis
WW2 N7367192 E318191 Construction
Outfall
S3 – Outlet of
Sewage
Treatment
Plant prior to
release to
outfall
Port
Curtis
S4 – Outlet of
Reverse
Osmosis
Plant prior to
release to
outfall
SW1 N7367745 E317917 Construction
and
Operation
Outfall
SW1 – MOF Port
Curtis
SW2 N7369034 E317596 Construction
and
Operation
Outfall
SW2 –
Sedimentation
Basin 2
Port
Curtis
SW3 N7368738 E318308 Construction
and
Operation
Outfall
SW 3–
Sedimentation
Basin 3
Port
Curtis
SW4 N7368776 E318563 Construction
and
Operation
Outfall
SW 4 –
Diversion
Ditch Outfall –
East
Port
Curtis
SW5 N7368844 E317060 Construction
and
Operation
Outfall
SW 5 –
Diversion
Ditch Outfall
and
Sedimentation
Basin 1
Port
Curtis
Permit
Environmental authority EPPG00712213
Page 40 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SW6 N7367490 E318166 Construction
and
Operation
Outfall
SW 6 – MOF
area drainage
outfall
Port
Curtis
SW7 N7368365 E318760 Construction
and
Operation
Outfall
SW 7 – Heavy
haul road
drainage
outfall
Port
Curtis
SW 8 N7369052 E317117 Construction
and
Operation
Outfall
SW 8–
Sedimentation
Basin 1
Port
Curtis
SW 9 N7367621 E317985 Construction
and
Operation
Outfall
SW9 – MOF
outfall
Port
Curtis
PLF
Loading
Platform
N7368542
N7368560
N7368584
N7368602
E316824
E316793
E316852
E316825
Construction
and
Operation
Discharge
Area
- Port
Curtis
SW10 N7368569 E316798 Construction
and
Operation
Outfall
SW10 – PLF
LNG Spill
Containment
Bund Release
Point
Port
Curtis
Release points are accurate to +/- 25m
BC8
Contaminant Release to Waters (Treated Sewage Effluent)
The total quantity of treated sewage effluent released to waters via the release points listed in Schedule
BC – Table 1: Contaminant Release Points, after wet weather storage is exceeded, on any one day
must not exceed:
(a) 1.08 mega litres during construction.
QUALITY CHARACTERISTICS OF RELEASE TO WATERS (CONSTRUCTION TREATED SEWAGE
EFFLUENT)
BC9 The release of contaminants from the sewage treatment plant to waters during construction must
comply, at the sampling and in situ monitoring point(s) specified in Schedule BC, Table 2 - Quality
Permit
Environmental authority EPPG00712213
Page 41 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Characteristic Limits (Construction Treated Sewage Effluent), with each of the limits specified in
Schedule BC Table 2 – Quality Characteristic Limits (Construction Treated Sewage Effluent) for each
quality characteristic.
Schedule BC – Table 2: Quality Characteristic Limits (Construction Treated Sewage Effluent)
Monitoring
point
Quality
Characteristics
Release
Limit Limit Type
Minimum
monitoring
frequency
S31
5-day Biochemical
Oxygen Demand <5mg/L
80 percentile
compliance
Weekly
(composite
sample2)
5-day Biochemical
Oxygen Demand 35 mg/L maximum
Weekly
(composite
sample2)
Suspended Solids <5 mg/L 80 percentile
compliance
Weekly
(composite
sample2)
Suspended Solids 50 mg/L Maximum
Weekly
(composite
sample2)
pH 6.5 to 8.5 pH
units Range Online continuous
Faecal Coliforms,
based on a minimum
of 5 samples collected
at not less than weekly
intervals
1000
colonies per
100ml
sample
Median
Weekly
(composite
sample2)
Total -N 3 mg/L 50 percentile
compliance
Weekly
(composite
sample2)
Total -N 10 mg/L Maximum
Weekly
(composite
sample2)
Total -P 1 mg/L Maximum
Weekly
(composite
sample2)
Ammonia -N 1 mg/L 50 percentile
compliance
Weekly
(composite
sample2)
Permit
Environmental authority EPPG00712213
Page 42 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Ammonia -N 3 mg/L Maximum
Weekly
(composite
sample2)
Dissolved Oxygen 4 mg/L Minimum Online Continuous
1 Monitoring point S3 described as the Discharge Monitoring Point (N7,369,000 E317,150), refer plan Appendix
2 – Figure 2: GLNG Project Simplified Waste Water Schematic attached to this environmental authority.
2 Composite Sample – Taken as a composite grab sample over a 2 hour period. The sample to be made up of
sub-samples taken at least every 15 minute and mixed in equal proportion, all sub samples must comply the
provisions of the EHP’s most recent version of the Water Quality Sampling Manual.
BC10 The finalised Monitoring Plan (Diffuser Validation), required by Part A - Condition (C8) must not be
changed without prior written consent from the administering authority.
BC11 A report outlining the findings of the REMP, required by Part A – Conditions (C15), (C16) and (C17),
including all monitoring results and interpretations in accordance with Part A - Conditions (C15) and
(C17) must be prepared and submitted in writing to the administering authority within 2 years of
commencement of operations and thereafter every 12 months. This should include an assessment of
background water quality, any assimilative capacity for those contaminants monitored and the suitability
of current discharge limits to protect environmental values.
BC12
Stormwater Management Plan
Notwithstanding Part A – Condition (A15), the environmental authority holder must provide a Stormwater
Management Plan for:
(a) Stage 2 - Construction Works not less than 30 business days prior to the commencement of construction activities; and
(b) Stage 3 - Operation Works not less than 30 business days prior to commencement of operational works.
BC13 If, within 30 business days following the submission of the Stormwater Management Plans submitted in
accordance with Part B - Condition (BC12) the administering authority provides comments on the
submission, the holder of this environmental authority must:
(a) have due regard to that comment in the finalisation of the Stormwater Management Plans; and (b) submit the finalised Stormwater Management Plans within 40 business days after the
administering authority provided comments; and (c) implement the amended Stormwater Management Plans.
BC14
Stormwater Management Plan
The Stormwater Management Plan required by Part B – Condition (BC12) must be consistent with the
requirements of the environmental authority and include, but not be limited to:
(a) Environmental Values (b) Impacts (c) Performance Criteria and Objectives (d) Mitigation Strategies
Permit
Environmental authority EPPG00712213
Page 43 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
(i) Erosion, runoff and sediment control measures; (A) Sediment control basins; (B) Stockpile management;
(ii) Stormwater erosion control; (iii) Reconstruction of slopes; (iv) Buffers near wetlands, streams and sensitive areas; (v) Silt fences at streams and wetlands; (vi) Road drainage and inlet/outlet filters; (vii) De-watering; (viii) Re-vegetation
(e) Implementation of Mitigation Strategies (f) Monitoring
(i) Monitoring (ii) Inspections; (iii) audits
(g) Responsibilities (h) Scheduling
(i) Sequence of installation (i) Reporting and Auditing
(i) Inspection and reporting requirements; (ii) Maintenance requirements; and
(j) Corrective Actions (k) Plans
(i) Site Environmental Plans (ii) Sediment Control Plans
(A) Locations of proposed control measures; (B) Flow Paths; (C) Discharge Points;
(iii) Diversion Drains Plans (A) Site Domains/Catch Areas; (B) Site Layout; (C) Drainage Collectors/distributors; (D) Flow paths
BC15 The holder of this environmental authority must ensure that the management of stormwater is
conducted and implemented in accordance with the Stormwater Management Plan developed in
accordance with Part B - Condition (BC12), (BC13) and (BC14). If the environmental authority holder
can provide evidence that the environmental authority holder is in compliance with this Condition BC15,
then the holder also complies with conditions C1(3), BC3(a)(ii), BC3(a)(i) and BC3(b)(ii) and BC3(c)(ii).
BC16 The holder of this environmental authority must ensure that sediment and erosion control is conducted
and implemented in accordance with the Stormwater Management Plan and the Erosion and Sediment
Control Plans developed in accordance with Conditions (BC12), (BC13), (BC14), (BC15), Part A - (A15)
and Part A - (F1) and (F2).
BC17 The release of contaminants from the stormwater discharge points to waters must be monitored at the
locations and for each quality characteristic and at the frequency specified in Schedule BC – Table 3:
Stormwater Release Limits
Permit
Environmental authority EPPG00712213
Page 44 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
BC18
The release of contaminants from the stormwater discharge points to waters must not exceed the
release limits stated in Schedule BC – Table 3: Stormwater Release Limits for each quality
characteristic.
Schedule BC – Table 3: Stormwater Release Limits
Release
Point
Monitoring
Point
Quality
Characteristic
Limit
Limit Type Minimum
Monitoring
Frequency
Stage 1 – early works and Stage 2 – construction works release limits
SW2,
SW3,
SW8
SW2, SW3,
SW8
Turbidity
(NTU)
66NTU
Maximum
Limit applies up
to the design
event of 42.1
mm rainfall event
over a 5-day
period
Monitoring to
be undertaken
prior to active
discharge
pH 6.5 - 8.5 Range
Limit applies up
to the design
event of 42.1
mm rainfall event
over a 5-day
period
Total
Hydrocarbons
Monitor only Monitor only
Total
Suspended
Solids
Monitor Only Monitor Only
Aluminium1,2 Monitor Only Monitor Only
Arsenic1,2 Monitor Only Monitor Only
Chromium1,2 Monitor Only Monitor Only
Copper1,2 Monitor Only Monitor Only
Iron1, 2 Monitor Only Monitor Only
Permit
Environmental authority EPPG00712213
Page 45 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Manganese1,2 Monitor Only Monitor Only
Vanadium1,2 Monitor Only Monitor Only
SW10 SW10 Total
Hydrocarbons
No Visible
Sheen
Visual Inspection
Stage 3 – operation works
SW2,
SW3,
SW8
SW2, SW3,
SW8
pH 6 - 8.5 Range
Limit applies up
to the design
event of 42.1
mm rainfall event
over a 5-day
period
Prior to
discharge and
during
discharge
events during
first flush.
Turbidity
(NTU)
31 NTU Maximum
Limit applies up
to the design
event of 42.1
mm rainfall event
over a 5-day
period
Total
Hydrocarbons
No Visible
Sheen
Maximum
Dissolved
Oxygen
4 mg/L
(minimum)
Minimum
SW10 SW10 Total
Hydrocarbons
No Visible
Sheen
Visual Inspection
Notes:
1 Total
2 Dissolved
BC19 The period of active discharge from the release points authorised by Schedule BC, Table 3:
Stormwater limits must be recorded.
BC20
Erosion and Sediment Control
The Erosion and Sediment Control Plan required by Part A – Conditions (F1) and (F2) must
include but not necessarily be limited to:
Permit
Environmental authority EPPG00712213
Page 46 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
(a) procedures for re-vegetating disturbed areas as soon as practicable after the completion of works;
(b) surface water monitoring program designed to detect erosion and sediment runoff into watercourses;
(c) identification of erosion risks areas; (d) implementation of preventative and control procedures for identified erosion risk areas; (e) procedures for avoiding disturbance to riparian areas; (f) topsoil management procedures, including but not limited to:
(i) stripping and storing topsoil during clearing and grading activities for restoration and/or decommissioning;
(ii) stabilisation of topsoil stockpiles; (iii) minimisation of loss of topsoil due to erosion; (iv) seeding of long term topsoil stockpiles to prevent erosion; (v) locating topsoil stockpiles in areas segregated from construction works activities and to
minimise soil structure degradation; (vi) constructing a diversion drain around the topsoil stockpile area; (vii) implementing erosion control measures around the topsoil stockpile area;
(g) provisions for environmental awareness training for site personnel; (h) identification of vegetated buffer strips between construction works and wetlands and surface
water boundaries; (i) monitoring and maintenance program for:
(i) silt fences on a daily basis; (ii) erosion and sediment control devices on a daily basis; (iii) disturbed areas; (iv) topsoil stockpile areas; and (v) stormwater drainage channels.
BC21 Notwithstanding Part A – Conditions (F1) and (F2) and Part B – Condition (BC20), runoff from the
site is to be directed to appropriately sized and designed1 sediment basins. For all areas not
draining to sediment basins, install other erosion and sediment controls in accordance with the
conditions of this approval to prioritise stabilisation in these areas.
1. Sediment basin appropriately sized and designed in accordance with the IECA Best Practice Erosion and Sediment Control Guideline (2008).
BC22 All activities must be designed and maintained in accordance with the guideline “Best practice
erosion and sediment control, International Erosion Control Association 2008” and supporting
documentation as updated from time to time.
BC23 Notwithstanding Part A – Conditions (F1) and (F2) and Part B – Condition (BC20), Stage 1 – Early
works and Stage 2 - Construction works must include the implementation and maintenance of
erosion protection measures and sediment control measures, including but not necessarily limited
to:
(i) rock check dams; (ii) silt fences installed in accordance with the International Erosion Control Association
Guidelines 2006 around soil and stockpile sites; (iii) silt fences installed in accordance with the International Erosion Control Association
Guidelines 2006 between construction areas and surface waters and wetlands; (iv) drainage ditches; (v) diversion channels around disturbed areas; (vi) rapid stabilisation of exposed areas; (vii) mechanical compaction of graded areas;
Permit
Environmental authority EPPG00712213
Page 47 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
(viii) controlled flows through stormwater drains and temporary basins; and (ix) rock armouring drainage discharge points.
BC24 Notwithstanding Part A – Conditions (F1) and (F2) and Part B – Condition (BC20), Stage 1 – Early
works and Stage 2 - Construction works must include the stabilisation of slopes and areas of high
erosion potential by implementing and maintaining measures including but not limited to:
(i) terracing; (ii) geotextile; (iii) geo-matting; (iv) surface roughening; (v) mulch; and (vi) promoting vegetation growth.
BC25 During Stage 1 – Early works and Stage 2 - Construction works vehicle access to salt marshes,
mudflats, mangroves and riparian zones is prohibited unless authorised under a separate
approval.
Note: A separate approval would include a Prescribed Tidal Works Approval or Marine Plants
Disturbance Approval.
BC26 During Stage 1 – Early works and Stage 2 - Construction works inlet and outlet filters must be
installed and maintained to prevent the clogging of existing stormwater drains and to prevent the
release of gross pollutants.
BC27 During Stage 1 – Early works and Stage 2 - Construction works must include the installation and
maintenance of erosion control measures to prevent scouring at outfall locations, including but not
limited to pipes, culverts and sediment basins. Erosion control measures are to include but not,
necessarily be limited to:
(a) matting; (b) gravel check dams; and (c) rock armouring.
BC28
Degraded sediment control structures and stormwater control devices are to repaired and replaced
as soon as practicable upon identification in the monitoring and maintenance program required by
Part B – Condition (BC20).
BC29
Reverse Osmosis Concentrate (ROC)
Despite Part A, Condition (C3), the total quantity of ROC released to waters on any one day during
Stage 3 - operation works must not exceed 0.24 megalitres.
BC30 The ROC released via the diffuser discharge point WW2 during Stage 2 - construction works must
not exceed the release limits specified in Part B – Schedule BC - Table 4: Quality Characteristic
Limits (Construction Reverse Osmosis Concentrate (ROC)) when measured at the monitoring
point S4 described as the Discharge Monitoring Point (N7,367,650 E318,100), refer plan Appendix
2 – Figure 2: GLNG Project Simplified Waste Water Schematic attached to this approval.
Permit
Environmental authority EPPG00712213
Page 48 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Part B – Schedule C - Table 4: Quality Characteristic Limits (Construction Reverse Osmosis
Concentrate (ROC))
Monitoring
point
Quality
Characteristics
Release
Limit Limit Type
Minimum
monitoring
frequency
S41
Total Chlorine (as
Cl)
0.5 mg/L Long term 50th
percentile Daily (grab
sample/single
measurement) 1 mg/L Maximum
Dissolved Oxygen 4.0 mg/L Minimum
Chemical Oxygen
Demand No Limit No Limit
Weekly (composite
sample2) 5-day Biochemical
Oxygen Demand
(inhibited)
20 mg/L Maximum
Turbidity
33 NTU Long term 50th
Percentile
Daily (single
measurement)
295 NTU Maximum
EC 96418 µS/cm Maximum
TDS 64600 mg/L Maximum
pH 6.5 to 8.5 Range
1 Monitoring point S4 described as the Discharge Monitoring Point (N7,367,650 E318,100), refer plan
Appendix 2 – Figure 2: GLNG Project Simplified Waste Water Schematic attached to this environmental
authority.
2 Composite Sample – Taken as a composite grab sample over a 2 hour period. The sample to be made
up of sub-samples taken at least every 15 minute and mixed in equal proportion, all sub samples must
comply the provisions of the EHP’s most recent version of the Water Quality Sampling Manual.
Permit
Environmental authority EPPG00712213
Page 49 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE BE – WASTE
BE1 The Waste Management Program required by Part A – Condition A16 must include:
(a) a description of the activities that may generate waste; (b) the types and amounts of wastes generated by the activities; (c) a program for reusing, recycling or disposing of all wastes; (d) how the waste will be dealt with in accordance with the waste management hierarchy,
including a description of the types and amounts of waste that will be dealt with under each of the waste management practices in the waste management hierarchy (i.e. avoidance, reuse, recycling, energy recovery, disposal);
(e) procedures for identifying and implementing opportunities to minimise the amount of waste generated, promote efficiency in the use of resources and improve the waste management practices employed;
(f) procedures for dealing with accidents, spills and other incidents; (g) details of any accredited management system employed, or planned to be employed, to
deal with waste; (h) how often the performance of the waste management program will be assessed; (i) the indicators or other criteria on which the performance of the waste management
program will be assessed; and (j) staff training and induction to the waste management program.
BE2
Waste Records
A record of all general waste must be kept detailing the following information:
(a) date of pick of waste; (b) description of waste; (c) quantity of waste; (d) origin of the waste (e) destination of the waste.
NOTE: Trackable wastes as listed in Schedule 1 of the Environmental Protection Waste
Management Regulation 2000 are not covered by this condition.
BE3 All regulated waste removed from the site must be removed by a person who holds a current
authority to transport such waste under the provisions of the Environmental Protection Act 1994
and sent to a facility that is permitted to accept such waste.
BE4 Each container of regulated waste stored awaiting movement off-site must be clearly marked to
identify the contents.
Permit
Environmental authority EPPG00712213
Page 50 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
SCHEDULE BF – LAND
BF1
Disturbance to Land – Environmentally Sensitive Areas
A total maximum area of 188.0504hectares of vegetation can be cleared within the boundary of
PFL10, refer to plan Appendix 2 – Figure 4: LNG Facility Regional Ecosystems, comprising of:
(a) a maximum cleared area of 38.0363 hectares of Endangered Regional Ecosystem 12.3.3; (b) a maximum cleared area of 42.921 hectares of Of Concern Regional Ecosystem 12.11.14; (c) a maximum cleared area of 0.6 hectares of saltpan vegetation Regional Ecosystem 12.1.2; (d) a maximum cleared area of 1.9931 hectare of mangrove shrubland Regional Ecosystem
12.1.3; and (e) a maximum 104.5 hectares of Corymbia citriodora and Eucalyptus crebra open forest
Regional Ecosystem 12.11.6.
BF2
Management of Fauna
The fauna management plan required by Part A – Condition (F10) must include, in respect to
species:
(a) address the impacts to the species; (b) provide for the survival of the species in the wild; and (c) achieve a net conservation benefit for the species.
BF3 A suitably qualified, licensed and experienced fauna spotter will be present during the vegetation
clearing activities to relocate fauna or recover any injured fauna.
BF4 The holder of this authority must ensure any protected animals injured by clearing activities
under this permit are referred to an appropriate wildlife carer group or veterinarian (to be
predetermined prior to clearing) and the administering authority must be notified within 24 hours
of any injuries or deaths.
BF5
Chemical and Fuel Storage
Spillage of all chemicals and fuels must be contained within an on-site containment system and
controlled in a manner that prevents environmental harm.
Vibration and Blasting
BF6 A Blast Management Plan must be developed in accordance with Australian Standard 2187 by a suitably qualified person prior to each blasting activity.
BF7 The Blast Management Plan must include measures to minimise the likelihood of any adverse effects
being caused by airblast overpressure and / or ground borne vibrations at any sensitive receptor and
demonstrate current best practice environmental management.
BF8 All blasting must be carried out in a proper manner by a suitably qualified person.
BF9 All blasting must be carried out in accordance with the Blast Management Plan.
Permit
Environmental authority EPPG00712213
Page 51 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
BF10 Noise from blasting operations must not exceed an airblast overpressure level of 120 dB (linear peak) at
any time, when measured at or extrapolated to any sensitive receptor.
BF11 Ground-borne vibration peak particle velocity caused by blasting operations must not exceed 10 mm/s
at any time, when measured at or extrapolated to any sensitive receptor.
Blast and Vibration Monitoring
BF12 Monitoring and recording of the air blast overpressure and ground borne vibration of every blast must be
undertaken.
BF13 Blast and vibration monitoring must include but not necessarily be limited to:
(a) maximum instantaneous charge; (b) location of the blast within the site (including any bench level); (c) airblast overpressure level (dB Linear Peak); (d) peak particle velocity (mm / s); (e) location, date and time of recording; (f) measurement instrumentation and procedure; (g) meteorological conditions for blast monitoring (including temperature, relative humidity,
temperature gradient, cloud cover, wind speed and direction); and (h) distances from the blast site to potentially noise-affected buildings or structures
Permit
Environmental authority EPPG00712213
Page 52 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
APPENDIX 1 - DEFINITIONS Note: Where a term is not defined in this environmental authority the definition in the Environmental Protection
Act 1994, its regulations and Environmental Protection Policies or the Petroleum and Gas (Production and Safety) Act 2004 and its regulations must be used in that order.
"aggregation dam" means a dam that is used to aggregate and contain CSG water or CSG water concentrate
prior to use, treatment or disposal of that water (by means other than evaporation). The primary purpose of the
dam must not be to evaporate the water even though this will naturally occur.
“associated works” in relation to a dam, means:
operations of any kind and all things constructed, erected or installed for that dam; and
any land used for those operations.
“background noise level” means the sound pressure level, measured in the absence of the noise under investigation, as the L A90,T being the A-weighted sound pressure level exceeded for 90 percent of the measurement time period T of not less than 15 minutes, using Fast response.
“bed and banks” for a watercourse or wetland means land over which the water of the watercourse or wetland normally flows or that is normally covered by the water, whether permanently or intermittently; but does not include land adjoining or adjacent to the bed or banks that is from time to time covered by floodwater.
“beneficial use” means
with respect to dams, that the current or proposed owner of the land on which a dam stands, has found a use for that dam that is:
of benefit to that owner in that it adds real value to their business or to the general community,
in accordance with relevant provisions of the Environmental Protection Act 1994,
sustainable by virtue of written undertakings given by that owner to maintain that dam, and
the transfer and use have been approved or authorised under any relevant legislation.; or
with respect to coal seam gas water, refer the EHP’s Operational Policy Management of water produced in association with petroleum activities (CSG water) and Notice of decision to approve a resource for beneficial use – CSG water which can be accessed on EHP’s website at www.ehp.qld.gov.au.
“brine” means either saline water with a total dissolved solid concentration greater than 40 000mg/l or CSG water after it has been concentrated through water treatment processes and/or evaporation.
“bund or bunded” in relation to spill containment systems for fabricated or manufactured tanks or containers designed to a recognised standard means an embankment or wall of brick, stone, concrete or other impervious material which may form part or all of the perimeter of a compound and provides a barrier to retain liquid. Since the bund is the main part of a spill containment system, the whole system (or bunded area) is sometimes colloquially referred to within industry as the bund. The bund is designed to contain spillages and leaks from liquids used, stored or processed above ground and to facilitate clean-up operations. As well as being used to prevent pollution of the receiving environment, bunds are also used for fire protection, product recovery and process isolation.
“category A ESA” means any area listed in Section 25 of the Environmental Protection Regulation 2008.
“category B ESA” means any area listed in Section 26 of the Environmental Protection Regulation 2008.
“category C ESA” means any of the following areas:
Nature Refuges as defined under the Nature Conservation Act 1992;
Koala Habitat Areas as defined under the Nature Conservation Act 1992;
State Forests or Timber Reserves as defined under the Forestry Act 1959;
Declared catchment areas under the Water Act 2000;
Resources reserves under the Nature Conservation Act 1992
Permit
Environmental authority EPPG00712213
Page 53 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
An area identified as “Essential Habitat” for a species of wildlife listed as endangered, vulnerable, rare or near threatened under the Nature Conservation Act 1992;
Any wetland shown on the Map of Referable Wetlands available from EHP’s website; or
“Of concern” regional ecosystems identified in the database maintained by EHP called ‘Regional ecosystem description database’ containing regional ecosystem numbers and descriptions.
“certification or certified by a suitably qualified and experienced person” in relation to a design plan or an annual report regarding dams, means that a statutory declaration has been made by that person and, when taken together with any attached or appended documents referenced in that declaration, all of the following aspects are addressed and are sufficient to allow an independent audit at any time:
exactly what is being certified and the precise nature of that certification.
the relevant legislative, regulatory and technical criteria on which the certification has been based;
the relevant data and facts on which the certification has been based, the source of that material, and the efforts made to obtain all relevant data and facts; and
the reasoning on which the certification has been based using the relevant data and facts, and the relevant criteria.
“certified by a suitably qualified and experienced person” in relation to a hazard assessment of a dam, means that a statutory declaration has been made by that person and, when taken together with any attached or appended documents referenced in that declaration, all of the following aspects are addressed and are sufficient to allow an independent audit at any time:
exactly what has been assessed and the precise nature of that assessment;
the relevant legislative, regulatory and technical criteria on which the assessment has been based;
the relevant data and facts on which the assessment has been based, the source of that material, and the efforts made to obtain all relevant data and facts; and
the reasoning on which the assessment has been based using the relevant data and facts, and the relevant criteria.
“clearing” means:
in relation to grass, scrub or bush—the removal of vegetation by disturbing root systems and exposing underlying soil (including burning), but does not include—
the flattening or compaction of vegetation by vehicles if the vegetation remains living; or
the slashing or mowing of vegetation to facilitate access tracks; or
the clearing of noxious or introduced plant species; and
in relation to trees—cutting down, ringbarking, pushing over, poisoning or destroying in any way.
“commercial place” means a work place used as an office or for business or commercial purposes, which is not part of the petroleum activities and does not include employees accommodation or public roads.
“construction” means:
in relation to a dam includes building a new dam and modifying or lifting an existing dam; and
in relation to the LNG plant the period when the construction of the LNG plant takes place on Curtis Island and during commissioning.
“CSG water” means groundwater that is necessarily or unavoidably brought to the surface in the process of coal seam gas exploration or production. CSG water typically contains significant concentrations of salts, has a high sodium adsorption ratio (SAR) and may contain other contaminants that have the potential to cause environmental harm if released to land or waters through inappropriate management. CSG water is a waste, as defined under s13 of the EP Act.
“CSG water concentrate” is the concentration of saline water waste stream from a water treatment process that does not exceed a total dissolved solid concentration of 40 000mg/L.
“CSG evaporation dams” is defined as an impoundment, enclosure or structure that is designed to be used to hold CSG water for evaporation.
Permit
Environmental authority EPPG00712213
Page 54 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
“dam” means a land-based structure or a void that is designed to contain, divert or control flowable substances, and includes any substances that are thereby contained, diverted or controlled by that land-based structure or void and associated works. A dam does not mean a fabricated or manufactured tank or container, designed and constructed to an Australian Standard that deals with strength and structural integrity of that tank or container.
“design plan” means the documentation required to describe the physical dimensions of the dam, the materials and standards to be used for construction of the dam, and the criteria to be used for operating the dam. The documents must include design and investigation reports, specifications and certifications, together with the planned decommissioning and rehabilitation works and outcomes. A design plan may include ‘as constructed’ drawings.
“discharge area” means: (a) that part of the land surface where groundwater discharge produces a net movement of water out of the
groundwater; and (b) identified by an assessment process consistent with the document: Salinity Management Handbook,
Queensland Department of Natural Resources, 1997; or (c) identified by an approved salinity hazard map held by the Department of Environment and Heritage
Protection.
“ecosystem functioning” means the interactions between and within living and nonliving components of an ecosystem and generally correlates with the size, shape and location of an area of vegetation.
“end” means the stopping of the particular activity that has caused a significant disturbance in a particular area. It refers to, among other things, the end of a seismic survey or the end of a drilling operation. It does not refer to the end of all related activities such as rehabilitation. In other words, it does not refer to the ‘completion’ of the petroleum activity, the time at which the petroleum authority ends or the time that the land in question ceases to be part of an authority.
“equivalent person or EP” means an equivalent person under volume 1, section 2 of the Guidelines for Planning and Design of Sewerage Schemes, October 1991, published by the Water Resources Commission, Department of Primary Industries, Fisheries and Forestry.
“fill” means any kind of material in solid form (whether or not naturally occurring) capable of being deposited at a place but does not include material that forms a part of, or is associated with, a structure constructed in a watercourse, wetland or spring including a bridge, road, causeway, pipeline, rock revetment, drain outlet works, erosion prevention structure or fence.
“firewater system testing water” means potable water used for testing of the firewater system.
“flowable substance” means matter or a mixture of materials which can flow under any conditions potentially affecting that substance. Constituents of a flowable substance can include water, other liquids fluids or solids, or a mixture that includes water and any other liquids fluids or solids either in solution or suspension.
“foreseeable future” means the period used for assessing the total probability of an event occurring. Permanent structures and ecological sustainability should be expected to still exist at the end of a 150 year foreseeable future with an acceptably low probability of failure before that time.
“hazard” in relation to a dam as defined, means the potential for environmental harm resulting from the collapse or failure of the dam to perform its primary purpose of containing, diverting or controlling flowable substances.
“hazard category” means a category, either low, significant or high, into which a dam is assessed as a result of the application of tables and other criteria in EHP’s Manual for Assessing Hazard Categories and Hydraulic Performance of Dams (Version 1.0, 2008) or any updated version of the Manual that becomes available from time to time
“heritage place” means any place that may be of cultural heritage significance, or any place with potential to contain archaeological artefacts that are an important source of information about Queensland’s history.
Permit
Environmental authority EPPG00712213
Page 55 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
“high bank” means the defining terrace or bank or, if no bank is present, the point on the active floodplain, which confines the average annual peak flows in a watercourse.
“highly erodible soils” means very unstable soils that are generally described as Sodosols with hard –setting, fine sandy loam to silty clay loam surfaces (solodics, solodised solonetz and solonetz) or soils with a dispersible layer located less than 25cm deep or soils less than 25cm deep.
“hydraulic performance” means the capacity of a regulated dam to contain or safely pass flowable substances based on a probability (AEP) of performance failure specified for the relevant hazard category in the Manual for Assessing Hazard Categories and Hydraulic Performance of Dams (Version 1.0, 2008) published by EHP on its website.
“impulsive sound” means sound characterised by brief excursions of sound pressure (acoustic impulses) that
significantly exceed the background sound pressure. The duration of a single impulsive sound is usually less
than one second.
“infrastructure” means water storage dams, roads and tracks, equipment, buildings and other structures built for the purpose and duration of the conduct of the petroleum activities, but does not include other facilities required for the long term management of the impact of those activities or the protection of potential resources. Such other facilities include dams other than water storage dams (e.g. evaporation dams), pipelines and assets, that have been decommissioned, rehabilitated, and lawfully recognised as being subject to subsequent transfer with ownership of the land.
“itinerant activities” means activities that are carried out at various locations using transportable plant or equipment and carried out at one location and for less than 14 consecutive days and on more than two occasions in each calendar year.
“lake” means: (a) a lagoon, swamp or other natural collection of water, whether permanent or intermittent; and (b) the bed and banks and any other element confining or containing the water.
“landfill monocell” means a specialised, isolated landfill facility where a single specific waste type is exclusively
disposed (i.e. salt).
“leachate” means a liquid that has passed through or emerged from, or is likely to have passed through or emerged from, a material stored, processed or disposed of on site which contains soluble, suspended or miscible contaminants likely to have been derived from the said material.
“levee” means a dyke or bund that is designed only to provide for the containment and diversion of stormwater or flood flows from a contributing catchment, or containment and diversion of flowable materials resulting from unplanned releases from other works of infrastructure, during the progress of those stormwater or flood flows or those unplanned releases; and does not store any significant volume of water or flowable substances at any other times.
“limited petroleum activities” mean activities including geophysical surveys (including seismic activities), well sites, well pads, sumps, flare pits, flow lines and supporting access tracks. Limited petroleum activities do not include the construction of production infrastructure for processing or storing petroleum or by-products, dams, compressor stations, campsites/workforce accommodation, power supplies, waste disposal or other supporting infrastructure for the project.
“long term 50th percentile” means the value which is exceeded by fifty (50) percent of the sample values, calculated over a period of 365 days, or twelve (12) months.
“material impact” means an increase in concentration of a chemical of >10% above background, detection of a chemical that was not present in the background sample or of a chemical that was used in the stimulation process.
Permit
Environmental authority EPPG00712213
Page 56 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
“max LPZ,15 min” means the maximum value of the Z-weighted sound pressure level measured over 15 minutes.
“mg/L” means milligrams per litre.
“normal operating conditions” means the ongoing operation of the LNG plant following commissioning and
excludes start-up, shut-down, maintenance or calibration of emission monitoring devices.
“operation” means the ongoing operation of the LNG plant following the commissioning period.
“overland flow water” means water, including floodwater, flowing over land, otherwise than in a watercourse or lake:
after having fallen as rain or in any other way; or
after rising to the surface naturally from underground.
“permanent infrastructure” includes any infrastructure (roads, tracks, bridges, culverts, dams, bores, buildings, fixed machinery, hardstand areas, airstrips, helipads, pipelines etc), which is to be left by agreement with the landowner.
“pest” means species:
(a) declared under the Land Protection (Pest and Stock route Management) Act 2002; (b) declared under Local Government model local laws; and (c) which may become invasive in the future.
“regulated dam” means any dam in the significant or high hazard category as assessed using the Manual for Assessing Hazard Categories and Hydraulic Performance of Dams (Version 1.0, 2008) or any updated version of the Manual that becomes available from time to time
“rehabilitation” means the process of reshaping and revegetating land to restore it to a stable landform and in accordance with the acceptance criteria set out in this environmental authority and, where relevant, includes remediation of contaminated land
“remnant unit” means a continuous area of remnant vegetation representative of a single Regional Ecosystem
type or a single heterogeneous unit (multiple Regional Ecosystem types that cannot be distinguished
individually due to the scale of mapping).
“River Improvement Trust Asset Area” means an area within a River Improvement Area declared under the
River Improvement Trust Act 1940 that is or has been subject to restoration or flood mitigation works. The
locations and details of these areas can be obtained from the relevant River Improvement Trust.
“sensitive place” means the following, except those within tenure PFL10:
a dwelling (including residential allotment, mobile home or caravan park, residential marina or other residential premises, motel, hotel or hostel); or
a library, childcare centre, kindergarten, school, university or other educational institution;
a medical centre, surgery or hospital; or
a protected area; or
a public park or garden that is open to the public (whether or not on payment of money) for use other than for sport or organised entertainment; or
a work place used as an office or for business or commercial purposes, which is not part of the petroleum activity(ies) and does not include employees accommodation or public roads; or
for noise, a place defined as a sensitive receptor for the purposes of the Environmental Protection (Noise) Policy 2008.
“sensitive receptor” is defined in Schedule 2 of the Environmental Protection (Noise) Policy 2008, and means an area or place where noise is measured.
Permit
Environmental authority EPPG00712213
Page 57 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
“significantly disturbed land or significant disturbance to land” means disturbance to land as defined in section 28 of the Environmental Protection Regulation 2008.
“site” means the petroleum authority(ies) to which the environmental authority relates.
“specified relevant activity” means an environmentally relevant activity that, but for being a resource activity, would otherwise be an environmentally relevant activity under section 18 of the Environmental Protection Act 1994.
“spring” means the land to which water rises naturally from below the ground and the land over which the water then flows.
“stable” in relation to land, means landform dimensions are or will be stable within tolerable limits now and in the foreseeable future. Stability includes consideration of geotechnical stability, settlement and consolidation allowances, bearing capacity (trafficability), erosion resistance and geochemical stability with respect to seepage, leachate and related contaminant generation.
“stage 1 - early works” means clearing forest and understory vegetation, establishing all-weather tracks,
establishing initial diversion of natural channels, cutting and filling for general leveling of site (rough grading),
establishing cut-off drains / perimeter diversion drains, developing site roads, establishing internal drainage
channels and establishing major drainage and sediment control features.
“stage 2 - construction works” means final grading of site, installation of hard surfaced areas, including paved
roads, concrete pads and building roofs, final site surface drainage system completed, final major culverts
installed and functioning, site sediment basins fully functioning and being monitored and maintained,
revegetation and stabilisation of cleared areas and construction of the LNG facility, tanks, and jetty, removal of
temporary construction equipment, facilities, buildings and structures.
“stage 3 - operation works” means the ongoing operation of LNG facility following completion of stage 2 –
construction works.
“state heritage place” means a place entered in the Queensland heritage register under Part 4 of the Queensland Heritage Act 1992.
“stimulation” means a technique used to increase the permeability of a natural underground reservoir,
including, for example, hydraulic fracturing, cavitations, fracture acidising and the use of proppant treatments.
“suitably qualified person” means a person who has professional qualifications, training, skills or experience relevant to the nominated subject matter and can give authoritative assessment, advice and analysis to performance relative to the subject matter using the relevant protocols, standards, methods or literature.
“suitably qualified and experienced person” in relation to dams means one who is a Registered Professional Engineer of Queensland (RPEQ) under the provisions of the Professional Engineers Act 1988, OR registered as a National Professional Engineer (NPER) with the Institution of Engineers Australia, OR holds equivalent professional qualifications to the satisfaction of the administering authority for the Act; AND the administering authority for the Act is satisfied that person has knowledge, suitable experience and demonstrated expertise in relevant fields, as set out below:
knowledge of engineering principles related to the structures, geomechanics, hydrology, hydraulics, chemistry and environmental impacts of dams; and
a total of five years of suitable experience and demonstrated expertise in the geomechanics of dams with particular emphasis on stability, geology and geochemistry, and
a total of five years of suitable experience and demonstrated expertise each, in three of the following categories:
investigation and design of dams.
Construction, operation and maintenance of dams.
Permit
Environmental authority EPPG00712213
Page 58 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
hydrology with particular reference to flooding, estimation of extreme storms, water management or meteorology.
hydraulics with particular reference to sediment transport and deposition, erosion control, beach processes.
hydrogeology with particular reference to seepage, groundwater.
solute transport processes and monitoring thereof.
dam safety.
“third party auditor” means a suitably qualified person who is either a certified third party auditor or an internal auditor employed by the holder of the environmental authority and the person is independent of the day to day management and operation of activities covered by this environmental authority
“threatening processes” means processes, features and actions that can have a detrimental effect upon the health and viability of an area of vegetation. For example altered hydrology, land use practices, invasion by pest and weed species, land degradation, edge effects and fragmentation.
“tolerable limits” means a range of parameters regarded as being sufficient to meet the objective of protecting relevant environmental values. For example, a range of settlement for a tailings capping, rather than a single value, could still meet the objective of draining the cap quickly, preventing damage and limiting infiltration and percolation.
“topsoil” means the surface (top) layer of a soil profile, which is more fertile, darker in colour, better structured and supports greater biological activity than underlying layers. The surface layer may vary in depth depending on soil forming factors, including parent material, location and slope, but generally is not greater than about 300mm in depth from the natural surface.
“uncontaminated stormwater” means stormwater discharged during the stage 1 - early works of the LNG facility, managed in accordance with the conditions in Schedule BC of this environmental authority.
“void” means any man-made, open excavation in the ground (includes borrow pits, drill sumps, frac pits, flare pits, cavitation pits and trenches).
“waters” includes all or any part of a creek, river, stream, lake, lagoon, dam, swamp, wetland, spring, unconfined surface water, unconfined water in natural or artificial watercourses, bed and bank of any waters, dams, non-tidal or tidal waters (including the sea), stormwater channel, stormwater drain, roadside gutter, stormwater run-off, and underground water.
“watercourse” means a river, creek or stream in which water flows permanently or intermittently: (a) in a natural channel, whether artificially improved or not; or (b) in an artificial channel that has changed the course of the watercourse;
but, in any case, only:
(c) unless a regulation under paragraph (d), (e) or (f) declares otherwise-at every place upstream of the point (point A) to which the high spring tide ordinarily flows and reflows, whether due to a natural cause or to an artificial barrier; or
(d) if a regulation has declared an upstream limit for the watercourse-the part of the river, creek or stream between the upstream limit and point A; or
(e) if a regulation has declared a downstream limit for the watercourse-the part of the river, creek or stream upstream of the limit; or
(f) if a regulation has declared an upstream and a downstream limit for the watercourse-the part of the river, creek or stream between the upstream and the downstream limits.
Watercourse includes the bed and banks and any other element of a river, creek or stream confining or
containing water.
“wetland” means an area shown as a wetland on a ‘Map of referable wetlands’, a document approved by the chief executive (environment). A map of referable wetlands can be viewed at www.ehp.qld.gov.au
Permit
Environmental authority EPPG00712213
Page 59 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
“wild river declaration” means a statutory instrument under the Wild Rivers Act 2005. A declaration lists the relevant natural values to be preserved and delineates certain parts of the wild river area and the different constraints that may apply in these areas. With reference to environmental authorities for petroleum, each declaration also specifies conditions to be included in a new authority if the activity is to be located within the wild river area.
“50th percentile compliance” means that not more than two (2) of the measured values is to exceed the stated release limit for any four (4) consecutive samples, where the consecutive samples are taken at approximately equal periods.
“80th percentile compliance” means that not more than one (1) of the measured values is to exceed the stated release limit for any five (5) consecutive samples where:
(1) the consecutive samples are taken over a 5 weekly period; and (2) the consecutive samples are taken at approximately equal periods.
End of Conditions
Permit
Environmental authority EPPG00712213
Page 60 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
APPENDIX 2 - Maps and Plans
Permit
Environmental authority EPPG00712213
Page 61 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Permit
Environmental authority EPPG00712213
Page 62 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Permit
Environmental authority EPPG00712213
Page 63 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Permit
Environmental authority EPPG00712213
Page 64 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Permit
Environmental authority EPPG00712213
Page 65 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Figure 6: Noise Monitoring Locations
Permit
Environmental authority EPPG00712213
Page 66 of 66
Department of Environment and Science
www.ehp.qld.gov.au ABN 46 640 294 485
Figure 7: GLNG Facility PLF and MOF Maintenance Activity Locations