43
MINISTRY OF ELECTRICITY AUTHORITY EGYPTIAN ELECTRICITY TRANSMISSION COMPANY (EETC) Head for Studies Sector Tel-Fax (020) 22616531 22618458 Environmental and Social Impact Assessment (ESIA) for Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary December 2013 12 El -SalehAyoub St., Zamalek, Cairo, Egypt 11211 Tel: + 20 2 27359078 – 2736 4818 Fax: + 20 2 2736 5397 E-mail: [email protected] URL: http://www.ecoconserv.com

Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

MINISTRY OF ELECTRICITY AUTHORITY EGYPTIAN ELECTRICITY TRANSMISSION COMPANY (EETC) Head for Studies Sector

Tel-Fax (020) 22616531 22618458

Environmental and Social Impact Assessment (ESIA)

for

Manshyet Nasser Substation and Interconnection

Underground Cables

Executive Summary

December 2013

12 El-SalehAyoub St., Zamalek, Cairo, Egypt 11211 Tel: + 20 2 27359078 – 2736 4818 Fax: + 20 2 2736 5397 E-mail: [email protected] URL: http://www.ecoconserv.com

Page 2: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Executive Summary

Environmental and Social Impact Assessment (ESIA)

For Manshyet Nasser Substation and Interconnection Underground Cables

December 2013

Page 3: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

Contents

1. Introduction ................................................................................................................................................ i

2. Legislative and Regulatory Frameworks .................................................................................................. ii

3. Project Description..................................................................................................................................... i

4. Project Alternatives.................................................................................................................................. iii

5. Baseline Environmental and Social Conditions .......................................................................................iv

A. Baseline Environmental Conditions .........................................................................................................iv

B. Baseline Socioeconomic Conditions ........................................................................................................ ix

6. Potential Impacts ..................................................................................................................................... xii

7. Environmental and Social Management Plan (ESMP) and Monitoring Plan ...................................... xxi

Page 4: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

ABBREVIATIONS

EEAA Egyptian Environmental Affairs Agency

EEHC Egyptian Electricity Holding Company

EETC Egyptian Electricity Transmission Company

EIB European Investment Bank

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

FGD Focus Group Discussion

IEA International Energy Agency

MW Mega Watt

NGO Non-Governmental Organization

PS Pumping Station

ARAP Abbreviated Resettlement Action Plan

ROW Right of Way

SS Substation

SSI Semi Structured Interview

ToR Term of Reference

WW Wastewater

Page 5: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

i

Executive Summary 1. Introduction

Project Background

Egypt is witnessing a rapid expansion in urbanization and population, paralleled with a surge in demand for electricity. The rate of electricity coverage in 2009 was approximately 99.6 percent; according to International Energy Agency (IEA). This rate is among the highest rates in Africa with 100 percent connection rates at urban areas and 99.3 percent at rural areas. However, with the growing population, it is expected that the demand for energy will rise. It is calculated that the demand for energy has risen by 30% from 2007/2008 to 2011/2012; from 19,738 MW to 25,705 MW. In addition, the number of the customers has increased from 23.8 million to 28.1 million (during the fiscal year 2007/2008 to 2011/2012). In order to meet the forecasted demand and secure the electricity stability in addition to the commitment to supply electricity to slum areas and informal buildings (based on the approval of the Cabinet (2005) and the Council of Governors approval (2005)), the Egyptian Electricity Transmission Company (EETC) together with the distribution companies need to provide additional substations and their interconnections. The European Investment Bank (EIB) has agreed to fund the construction of several substations and interconnection lines for electricity connection in Egypt in cooperation with the EETC, which is undertaking efforts to expand its services in response to growing demand for electricity, hence, to meet the plan of EEHC. The EETC is committed to carrying out an ESIA of the Manshyet Nasser Substation (SS) as per the requirements of the Egyptian Environmental Affairs Agency (EEAA) and the EIB. EcoConServ has been asked to prepare the ESIA study; according to the ToR which was signed between EETC and EcoConServ, to investigate the potential of the substation at Manshyet Nasser and interconnection between the new substation (Manshyet Nasser SS) and the existing underground cables connected to the existing SSs (Ain Serra, Abbasiya, Metro Abbasiya, Abdeen and Gabal El Akhdar) to identify and assess the environmental and social conditions in the project’s area. In addition, the management and monitoring plan, including the mitigation measures during construction and operation and maintenance phases are described in the ESIA report for all project components involved. According to the ToR, this consultancy task had two main outputs; An Environmental and Social Impact Assessment (ESIA) study, and An RPF / RAP study if necessary (in case resettlement or compensation is triggered by the project activities). During the preparation of the study, it was identified that the RPF / RAP was not necessary since the Substation site has already been allocated by the governor decree. Concerning the route of the interconnection underground cables, the routes will be under state government land and along / beside the existing roads (for 66 kV and 220 kV). For the 66 kV underground cables, it will be connected at the front of the SS site, and for the 220 kV underground cables, it will be connected to the existing underground cables under the middle island of the existing main road (El Nassr Rd). Therefore, RPF / RAP of interconnection underground cables are not triggered as well since it identified that the resettlement or compensation is not occurred.

The ESIA Methodology

The ESIA focused on identifying and assessing the negative and positive impacts of the project on the environment and the socioeconomic characteristics of the impacted groups in addition to developing

Page 6: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

ii

necessary mitigations for the negative impacts. The identifications and assessments were conducted for each of the project components during construction and operation phases. The mitigation measures were developed and presented in Environmental and Social Management Plan matrix. In addition, the monitoring plan was developed to monitor implementation of the ESMP as well as identifying the necessary capacity building activities for the implementation team. The consultant proposed the necessary budget, to implement the ESMP and the monitoring plan. Similarly, the monitoring plan is presented in the form of a matrix.

The ESIA methodology included reviewing the secondary data sources from previous reports and studies about the environmental and socio-economic characteristics of the project area. The literature review (included both reports provided by the client as well as web based resources), contributed to elaborating the ESIA study’s objectives mentioned above by assessing:

- The environmental and socio-economic characteristics of the project areas - Project background and proposed interventions - The legal, institutional and organizational framework and background of the electricity sector and the

historical background - Environmental and social standards and guidelines for related environmental and social issues

In addition to the literature review, structured site visits were undertaken to collect primary data from the site. The visits also were used as a tool to identify stakeholders’ perceptions regarding some issues (especially social issues), such as:

- The current environmental and socioeconomic characteristics on the site and at the surrounding area

- The current electricity supply at the area and its impact on the families’ livelihoods particularly on the vulnerable groups (children, women, the poor),

- Gender issues related to energy management on the level of household, - The perception of the local community towards the existing electricity service

provider, - The environmental and socioeconomic short and long term impacts predicted from

the project, - Ideas for maximizing the positive benefits especially on people’s livelihoods and the

economic development of the project, - Consult with project-affected groups and local non-governmental organizations

about potential resettlement issues, and take their views into account.

2. Legislative and Regulatory Frameworks

Laws and Regulations in Egypt

- Environmental Law 4/1994 - Law 38/1967 on Public Cleanliness - law 93/63 on Discharge of Liquid Waste - Law 63/1974 on Electricity Installation - Law 67/2006 Electricity Law for protecting the consumers

EIB Guidelines

- Environmental Statement,1996

Page 7: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

iii

- Environmental Statement 2004 and Environmental and Social Practices Handbook – 2010 EIB

- EIA Directive 85/337/EEC, amended by Directives 97/11/EC and 2003/35/EC for EIA requirement

- EIB Sourcebook on EU Environmental Law - EIB Social Guidance Notes - Chapter C.9 Public Consultation and Participation – EIB Environmental and Social

Practices Handbook 2010

World Bank Safeguards and Policies

- OP 4.01 for Environmental Assessment - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan

Potential Egyptian Laws and Regulations, EIB policies and guidelines and WB operational procedures regarding Environmental and Social aspects for Manshyet Nasser SS and their interconnection underground cables project are summarized as follows:

Page 8: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

i

Table 1 Summary of the potential Egyptian, EIB and WB triggered regarding the Manshyet Nasser SS and its interconnection project

Safe guard Policy Triggered

Justification EEAA EIB WB

1 EIA Yes Yes Yes ESIA is a compulsory study (in accordance to Egyptian and International guidelines and regulations); that has to be provided prior to the implementation of any project.

This policy applies to all projects requiring a Category B of Egyptian Laws and Regulations 4/1994, WB Policy (OP 4.01) and Table D of EIB project categorization will be applied. In addition, the EIA is in accordance to EIA Policy summarize in Environmental Statement 2004 governed by Directive 85/337/EEC, amended by Directives 97/11/EC and 2003/35/EC

All Environmental and Social aspects related to construction of the substation and interconnections project will be adequately examined in accordance to the Egyptian and EIB regulations and guideline (and reference to the WB policies)

All Environmental and Social aspects related to operation of the substation and interconnections project shall be adequately examined in accordance with the Egyptian and EIB regulations and guidelines (and reference to the WB policies)

2 Natural habitat and Bird Migration

No No No No natural habitat or physical cultural or natural protectorate property issues have been identified during site visits or desk studies, hence the risk of project affecting natural habitats or physical cultural or natural protectorate property is considered negligible.

The project does not belong to the international bird migration path. Therefore, the bird migration is not triggered in this study (by both national (Egyptian) and International (EIB or WB).

In addition, the project sites are mainly urban areas which are characterized by only local bids 3 Involuntary

Resettlement No No No For this particular component of the project, involuntary resettlement was not triggered.

There is no private land acquisition or resettlement that will take place at the new SS site and along the interconnection line. The proposed site for SS is already plotted and approved by the decree from Cairo Governorate. In addition, the interconnection lines pass through the state government land (under the main existing road and beside the existing service road).

4 Public Consultation

No Yes Yes Although it is not compulsory under the Egyptian laws and regulations, Public consultations were held to ensure that the public is well informed. The consultations involved as part of the scoping, several discussions and interviews held to receive stakeholders’ feedback on the project’s and followed by the

Page 9: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

ii

Safe guard Policy Triggered

Justification EEAA EIB WB

second public consultation near the end of the project, with the stakeholders and affected communities; according the EU Directive Article 6 and 9 and WB OP 17.50.

Public Consultation Process has been designed in accordance with World Bank Guidance for the Preparation of a Public Consultation and Disclosure Plan (January 1996).

Public Consultation process and results are presented as a part of the ESIA study Public Consultation Process has been designed in accordance with World Bank Guidance for the

Preparation of a Public Consultation and Disclosure Plan (January 1996) 4 Disclosure No Yes Yes According to Egyptian Law and Regulation, Disclosure is only applicable to category C project; hence

it is not applicable to the current project. However, as the Disclosure process is compulsory under the EIA Directive, it has been designed in

accordance with World Bank Guidance for the Public Consultation and Disclosure Plan (January 2006). This will involve:

For the scoping session (first Public Consultation) will involve invitation, presentation, short description of the project components and predicted impact

For the second Public Consultation will involve publishing an invitation in a widely circulated newspaper two weeks prior to the event, invitations, distribution of the executive summary (in Arabic) for the invitees and attendees, and disclosure at the EETC and the Consultant website two weeks prior to the public consultation event. In addition, the report will be available as well at the donor’s (EIB) website after the approval.

Page 10: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

i

3. Project Description

Project Objectives

The construction of Manshyet Nasser SS (3x125 MVA 220/66/11 kV and 4x40 MVA 66/11 kV transformers GIS SS) and its interconnection underground cables (220 kV and 66 kV) will improve power capacity at the area with minimum losses of transferred power.

Those objectives are in accordance to the EEHC and its affiliated companies’ mission toward the society: to provides continuous and safe supply of electricity to all type of consumers. In addition, as the EEHC and its affiliated companies’ long term goals, all the implementation of their project is in accordance with international performance standards and taking into consideration all the environmental, social and economic determinants.

As part of the current project, the new substation will be connected with the five existing substations using interconnection underground cables (double circuits). The new SS (Manshyet Nasser SS) will be connected to the existing underground cables and to the existing SSs. Once the establishment of the new SS is completed, the existing underground cables will be connected through underground tunneling (for 220 kV underground cables) and excavation at the surrounding roads (cutting the El Salam rd) and service road beside the Sheikh Zayed hospital rd. for 66 kV underground cables.

Project Locations

The site of the proposed substation at Manshyet Nasser will lay at the empty land with U shape. The location is determined as the following coordinates:

Latitude 30° 3'1.23"N

Longitude 31°17'21.27"E

The map of the proposed location of Manshyet Nasser SS is presented at Figure 3.1 and the routes for the underground interconnection cables are presented at Figure below.

Figure 1 Map of the proposed location of Manshyet Nasser Substation (Enlarged map 1:50,000)

Page 11: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

ii

Figure 2 Routes of Underground interconnection cables (to be connected to the existing

underground cables) - (Enlarged map 1:5,000)

Project Components

The main components of the project are, the construction of:

1. Manshyet Nasser SS:

3x125 MVA 220/66/11 kV and 3x40 MVA transformers GIS SS 2. Underground interconnection cables between the existing SSs and the Manshyet Nasser

SS.Please note there are existing underground cables along the existing road. Under this project, the existing underground cables will be connected (around 150 m) along the existing road. The existing underground cables will be connected to the proposed SS at Manshyet Nasser to the five existing SSs as described below:

Connections with the 220 kVexisting underground cables (networks): Double circuit 220 kV underground cables to Ain El Seera S/S Double circuit 220 kV underground cables to MetroAbbasiya S/S

Connections with the 66 kV existing underground cables (networks): Double circuit 66 kV cables to Abdeen S/S Double circuit 66 kV cables to El Gabal El Akhdar S/S Double circuit 66 kV cables to Abbasia S/S

Page 12: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

iii

4. Project Alternatives

No Project Alternative

The main objective of the project is to connect Manshyet Nasser SS to the existing SSs. Environmental and social impacts from the project are assessed and no significant impacts are anticipated.The site of the proposed SS at Manshyet Nasser is a suburb area within the residential area and surrounded with public services, such as main road, wastewater pumping station, hospital, etc. therefore, the indoor GIS substation is the most appropriate technological alternative for substation.

In addition, the interconnection underground cables should be done instead of the overhead transmission lines. The site is located at an urban area as well as using the existing underground cables already connected to the existing SSs will benefit environmentally and economically. The excavation and disturbance to the environment will be minimized; in addition the cost for the underground cables will be reduced.

If the SS and interconnections underground cables were not built, the consequences would be as follows:

Energy capacity will not increase Secure the demand of the new establishment as well as to cope with the demand increased from the

residential / housings will not be achieved The power supply to the consumers will not be improved The consumers’ financial losses from low quality power supply will decline As a result, an increase in the economic activities in the region in not expected

Location/Route Alternatives

The selection of the SS location and interconnection underground cables routes should be undertaken according to criteria that fulfills technical, environment as well as socioeconomic objectives in order to achieve the most feasible application.

Accordingly, SS site at Manshyet Nasser is already plotted since 2008 to be built to serve the increase of the electricity demand from the surrounding new establishment and demand on new connections to residential area around the substation. Formerly, the SS location was plotted few hundred meters above the hill. However, due to the additional length of the routes and excavations needed for underground cables, the substation location was moved to downhill to be closest as possible to the main road. The selection of the SS location and the proposed routes have been considered length optimization thus reducing the cost as much as possible whilst at the same time the proposed routes are aligned to the existing road network as much as possible for easy access during construction and maintenance and to reduce to a minimum the number as possible the number of sensitive receptors.

Generally there are few environmental constraints for construction and operation the SS and interconnection lines that are described in the ESMP. If these constraints were followed during the implementation (construction and operation phase) of the project there will be no environmental/social objection with regards to site selection; both SS site selection and routes of interconnections underground cables.

Page 13: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

iv

Tunneling Construction Alternatives

As mentioned above, there are three different scenarios to construct the underground cable of 220 kV (to connect the new SS with AinSeera SS and Abdeen SS):

a) Current scenario is storing the equipment in the middle of the road (at the island) at nearby the pedestrian bridge; which has around 3.5 m width) the little traffic disturbance will be expected but it will not destruct the traffic and create conjunction.

b) If the unused railway will be covered, the available space for setting the equipment and the storing space will be solved and the route of the cables will not be difficult due to the depth of the railway.

c) If the traffic department agrees to close one side of the road, the maximum 3 days of the underground construction cables can be done with excavation only and the road will be closed and paved immediately.

Technically, all the options are suitable and can be done with the same duration and result. Financially, the option a) is the most costly. However, EETC will do all the necessary precaution for selecting the best scenario. The approval from traffic department to implement the scenario will be discussed and the selection will be obtained prior to the installation.

5. Baseline Environmental and Social Conditions

A. Baseline Environmental Conditions

The project selected for construction of the SS at Manshyet Nasser and routes of the underground interconnection cables with the existing SSs lies within the radius of less than 400 m. Therefore, both project components sites (SS and interconnections underground cables) have similar environmental conditions.

Physical Environment

Location and Land Use

The project is located in the East of Cairo city, at the outskirt of crowded area of Manshyet Nasser. The location adjacent to the main road (El Nasr Rd) ensures accessibility of the heavy machines and materials and equipment transport to the site. The location of the SS is an empty land dedicated since 2008; with Governor’s decree for the future purpose of SS to supply the electricity demand to the existing and new establishment surrounding the area. Currently, public establishments surrounding the proposed site of SS are Arab Contractor hospitals, nearby clubs, new Sheikh Zayed Hospital, wastewater PS and mosques. In addition, the new SS site is surrounded by the housings existing and new housing compounds and residential buildings with some small home industrial workshops within.

Page 14: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

v

Figure 3 Layout of the proposed SS and its underground interconnection underground cables

Existing Networks

- EETC project of Manshyet Nasser SS and interconnections underground cables are located close to the main road (El Nasr Rd). City public transport will easily reach the site through any existing public transportation; taxi services and bus lines from around greater Cairo city.

- There is an existing complete road network that will serve easy access to any part of Cairo city. - There is an existing water supply at the project component sites. - Wastewater network is also available at the SS site. - Domestic solid waste collection (domestic non-hazardous waste) already exists in the area.

Regarding the other generated solid waste (during construction and operation phase) such as rejected construction materials, rejected underground cables, etc (for non-hazardous waste) and empty toxic containers, waste oils, etc (for hazardous waste), the collection, temporary storage, handling and disposal during construction will be managed by the Contractor with the approval from EETC (for storage and transportation to the designated landfill).

Climate Conditions

Cairo lies in the arid belt characterized by low rainfall and high evaporation rates. The mean annual rainfall is about 21 mm, relative humidity is 50%- 70%, and the average temperature is 30oC in the summer and 10o C during the winter.

Soil

Only one type of soil characterizes Greater Cairo which is the Calcaricfluvisols, relatively young soils developed on recently deposited colluvial, fluviatile, lacustrine, or marine sedimentsin the Nile Valley and Delta, and on some of the coastal plains. From the description of the soil characteristic in the area, soil characteristics are not expected to have significant impacts both during construction and operation phase. The soil is not characterized as a fertile soil, thus the site will not decrease the opportunity for agriculture land to be used in the future purpose. Only, there is a potential of wind erosion that might impact on the dust development during construction, therefore measures will be provided for the workers to reduce the impact on air quality (dust).

Page 15: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

vi

Geomorphology, Geology and Groundwater Hydrology

Geomorphology and geological features of project site belongs to old aluviatile plain and tertiary characterized by Miocene, composed mainly of sand and gravel and local intercalation of limestone or shale. The area is not sufficient for cultivation.

The project site belongs to non-aquifer and is characterized mainly with sand and gravel. The project will not have significant disturbance to the groundwater and as it is concluded at the previous section, the site cannot be cultivated for agriculture purposes. With the depth of the foundation will be constructed for the SS and interconnection underground cables, as it is described above, groundwater will not be impacted.

As described previously, the surface water (river and irrigation canals) are not passing at nearby the project site. The closest water surface (the Nile River) is located 7.60 km - South West heading 250.34 degrees of the proposed project location. There will be no direct or indirect impact to the surface water due to the construction and operation of the project components.

Tectonic activities

Even though greater Cairo does not belong to the sensitive area for the tectonic framework, historically some earthquakes were recorded at greater Cairo. However, the project site does not belong to the epicenter of the tectonic activities and as the project site is within greater Cairo, the seismic activities are well recorded.

Air quality

For this study, the air quality measurements have been conducted at different places representing the existing air quality at the specific project areas. The substation site, the proposed underground cable were measured at July 28, 2013 by Central Lab of Cairo University. Air quality Measurements were done for the evaluation of hourly concentrations of sulphur dioxide (SO2), nitrogen dioxide (NOx), carbon monoxide (CO). Air samples were taken on filters for the evaluation of the concentrations of Total Suspended Particulates (TSP) and Particulate Matters having a diameter less than 10 micrometer (PM10). The standard method used for the air quality (work environment) and particulate matters are in accordance to the International standard, and the equipment are regularly calibrated. The summary of the air quality at SS site and Underground cable site are as follows1:

- Temperature during the measurement at site was 34.7 0C - CO and SO2 at both sites are undetectable (under the analytical method used during the

measurement) - NO2 at both sites are 2.5 ppm - PM (especially PM10 and PM2.5) as well as TSP are not detected

Noise quality

The noise measurements were conducted at project sites (SS site and underground cable site) on 28 July, 2013. The 8 hours measurement was conducted at the SS site. The 24 hours noise measurements were conducted at the entrance of the SS site (nearby the underground cable site as the majority of activities 1 The copied of the measurement report is presented at Annex 3

Page 16: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

vii

(mainly during construction phase; since the vehicles movement used for transporting materials and machineries will be limited to night time only).

In addition to the noise measurements conducted at the proposed project sites, spot noise measurements at different locations at Ain Serra SS was also conducted during the same period. Ain Serra SS was selected due to the similarity of the capacity of the proposed SS at Manshyet Nasser in addition to the similarity on the design of the SS and interconnection underground cables. In addition, Ain Serra SS is located adjacent to the residential areas. The locations were selected due to their expected impacts during the operation phase. It concluded based on the noise measurements that at all locations measured, the noise level do not exceed the indicated limits of environmental law 4/1994 and its executive regulations regarding the limits of work exposure (occupational exposure at the workplace). Please refer to Table below for the measurement result at the proposed SS site and the existing SS (Ain Serra) that has similar design and capacity of the proposed SS.

Table 2 Noise level at project sites and similar SS design capacity (for noise prediction during operation and maintenance of new SS)

No Locations Mean value (dB)

1 Ain Serra SS (existing SS) Outside (nearby transformers) 78 GIS (indoor) 65.4 Control room (indoor) 61 Outside SS (nearby surrounding community) 72

2 Manshyet Nasser SS (proposed SS) SS site (centre) 66 Underground cable site (nearby the entrance of new SS) During the day 75.5

Underground cable site (nearby the entrance of new SS) During the night 76

Electromagnetic Field

To indicate the EMF exposure, especially during long term operation phase, the different locations at existing SSs to be connected to the new SS were measured, during site visits (conducted on July, 26 and 29, 2013). As indicated previously, similar to the air quality, the EMF exposure at the existing SSs will give indications how the common practice of maintenance of the SS and underground cables will result to the EMF exposures to the new SS and interconnection underground cables. The EMF results at different locations at existing SSs are presented on the following table.

Table 3Typical measured of EMF at existing SSs to be connected to the proposed SS

Existing SS Magnetic field in mG

Nearby transformers

Outside transformers area

Metro Abbasiya SS - - Abbasiya SS 149 71 Abdeen SS - 21.5

Page 17: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

viii

Existing SS Magnetic field in mG

Nearby transformers

Outside transformers area

Gabal el Akhdar SS 98.5 37 Ain Serra SS 103.5 71.5

Biological Environment

Flora

Most of Cairo urban areas have rare vegetation cover, except from exotic vegetation for ornamental purposes. Apart from some public parks and trees planted on street sides and middle islands, most areas are urbanized. The project is located in the eastern part of the city centre. Trees are limited at this area. The neighboring areas have rare vegetation cover as well. For public trees that are planted at the public places, along the service road, treated wastewater is used for the irrigation. There is no expected impact on vegetation to occur at the project site, both for SS site and the interconnection underground cables. The flora impact for EETC project is negligible. However, positive impact can be predicted during the operation phase of the substation when the empty spaces within the substation area are planted with ordinary plantation.

Fauna

The fauna species at Cairo area are mostly those adapted to urban areas such as feral cats and dogs, rodents, lizards, bats and local birds. These species depend largely on human waste for feeding. The project is located at a densely populated area at the eastern part of the city of Cairo which does not have any particular endangered animals nor have bird species been recorded in the area. In addition, there is no bird migration path across the project sites. Similarly, there is no expected impact predicted from the project components on fauna and bird migration, during both construction and operation phase. Thus the impacts on fauna on the project components, both during construction and operation are negligible.

Natural Protected Areas

No natural protectorate areas are present in the project vicinity. The two closest natural protectorate areas from the project are present at the southeast of Cairo (Petrified Forrest and Degla protectorates). However these sites are located at distances of around 19 km - South East heading 148.52 degrees from the project area (for Petrified Forest) and10 km south of Cairo (about 17.5 km away from the proposed project) for WadiDegla area.

Culturally Valuable Sites

No culturally valuable sites are present at or in the vicinity of project area. The closest culturally valuable sites are located in the city centre and the Old Cairo; about 7-10 km from the project site. Those culturally valuable sites surrounding the project areas will not have significant impact and can be classified as negligible. Ambient air, noise, vibration impacts due to the construction and operation of the project components will be dismissed within distance and will not reach any culturally sites surrounding the project sites.

Page 18: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

ix

B. Baseline Socioeconomic Conditions

Manshyet Nasser is one of the poor communities in Cairo, which signifies growing socio-economic disparity since the early 1970’s. Manshyet Nasser represents one of the areas among poverty belts surrounding Cairo which attracts rural migrants and urban poor residents. Cairo is characterized by higher land prices and shortage of affordable housing areas. Manshyet Nasser settlement is located at Muqattam Mountain Plateau within the Easter part of Cairo. Manshyet Nasser came into public attention as one of priority areas for development upon the rockslide on Deweka district. Official authorities have been continuously trying to improve the living conditions at the area.

Manshyet Nasser belongs to informal dwellings of Egypt, within the Egyptian context slums have been known as ‘Ashwa’iyyat’, which literally means ‘disordered’ or ‘haphazard’. It refers to informal areas suffering from problems of accessibility, narrow streets, the absence of vacant land and open spaces, very high residential densities, and insufficient infrastructure and services2.

Egypt appeared to have 39.9% of its urban population, with total number 11.8 million inhabitants living in slums. Furthermore, Cairo is located on the world map to have 4 out of 30 biggest “mega-slums” in the world; these include Imbaba2 (1.0 million), Ezbet El-Haggana (1.0 million), City of the Dead (cemeteries) (0.8 million) and Manshyet Nasser (0.5 million).

Demographic Profile

The total number of inhabitants at Manshyet Nasser district is estimated by around 311630 in 20123, living in a total area of 15,22 km2.

Employment Conditions:

Males are dominantly own the business than females. Majority of the females work as laborer and among the population almost 90% of the male were previously employed than females in addition to half of the unemployed males were never employed (according to national cencus data 2006).

Education Conditions:

The following table presents the distribution of the population of Manshyet Nasser district per educational status, as per the National Census of 20064:

2World Bank. (2008). Egypt: Urban sector update, Vol. 1 of 2. Washington D.C.: World Bank. 3 IDSC, Descrip on of Egypt by Informa on, 2012 4 CAPMAS, Na onal Census, 2006

Page 19: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

x

Table 4 Distribution of Population at Manshyet Nasser by Education

Illiterate

Read /write

Illiteracy class

Primary education

Intermediate diploma

Vocational education

University degree

Postgraduate degree

Total

Males 45845 14211 1027 22263 18560 1646 3338 96 106986

Females 49815 10468 1065 18270 14043 958 1670 47 96336

Total 95660 24679 2092 40533 32603 2604 5008 143 203322

Health Conditions:

Currently no public hospitals are available at Manshyet Nasser area, the new public hospital “Sheikh Zayed Hospital” is not functioning yet, though it is expected to start functioning within few months. Only 3 private hospitals operate in the area. The total number of health care providers is estimated by 75 doctors, 64 nurses and 12 Pharmacists.

Infrastructure Accessibility

Manshyet Nasser area suffers severely from lack of infrastructure services, there are currently several infrastructure projects under construction such as: Improving water and wastewater network at Zarayeb area, construction of sanitation network at Dewyka area project5.

Sanitation

The area is currently served by sanitation network with a total capacity of 80.24 m3/day.

Potable Water

The amount of consumed potable water reaches 270 thousand m3/day.

Community-Based Organizations6

There are around 60 CBOs in Manshyet Nasser. However, most of them are family associations which act as solidarity groups and provide help for the inhabitants of Manshyet Nasser in weddings and funerals only. The services of such CBOs are usually exclusive to inhabitants of Manshyet Nasser whose rural origins are the same as those of the founders of the CBOs. Only 10-15 CBOs somewhat demonstrate development thinking and are actually trying to bring about development in the neighborhood through the implementation of several initiatives. Most of these CBOs receive applicants from all over Manshyet Nasser and have 5Manshyet Nasser district, Informa on Center, 2013 6Nazly Amr Ismail Abdel Azim, 2011, Dealing with Urban Poverty: The Case of EzbetBekhit, Manshiet Nasser, MA. Thesis submitted to The American University in Cairo

Page 20: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xi

beneficiaries everywhere. The division of Manshyet Nasser into areas does not represent an obstacle to the inhabitants of Manshyet Nasser nor do they prevent CBOs from extending their services to all inhabitants.

Page 21: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xii

6. Potential Impacts

Table 5 Significance of Expected Impacts Assessment during Construction Phase of Manshyet Nasser Substation and its interconnection underground cables

Impact Likelihood and severity Significance Mitigation Measures During construction of Manshyet Nasser Substation Impact on Noise High likelihood to occur – short term

and temporary - Highly sensitive receptors includes construction workers and staff of wastewater pumping station. Receptors with low sensitivity include nearby projects/settlements (residential areas and hospital)

Medium Impact on wastewater pumping station staff and the construction workers Minor impact on settlement and nearby establishment

Application of the normal precautions normally taken by construction workers. Notification to the surrounding establishment prior to the construction of the SS Time management and construction schedule according to the IFC regulation provided by the contractor prior to the construction phase

Impact on traffic High likelihood to occur – short term, temporary and localized only on the main road mainly (El Nasser Rd) – Highly sensitive receptors include main road (El Nasser road traffic) and El Salam (local road) traffic and nearby residential area using El Salam road

Low to medium impact Time management for transporting the materials, equipment, debris, etc Clear sign surrounding construction site and the enter / exit gate Coordination with traffic department (ministry of interior) for vehicles route and movement.

Impact on Air Quality

High likelihood to occur – short term, temporary and localized - Highly sensitive receptors include construction workers. Receptors with low sensitivity include nearby projects/settlements.

Medium impact on construction workers Low impact on the residents, surrounding establishment and pedestrians passing by the construction site

Spraying the sandy soil with water (if needed, especially during the dry period). Maneuver area and the parking area should be well paved Management of the number of vehicles at the same time for specific location and the scheduling the intensity of vehicles

Impact on Vibration

Low likelihood to occur Minor impact Schedule and time plan for vehicles movements

Page 22: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xiii

Impact Likelihood and severity Significance Mitigation Measures Impact on Hazardous materials and waste generation

Uncertain likelihood – Uncertain impact duration - Highly sensitive receptors include soil pollution and workers. Receptors with low sensitivity include nearby projects/settlements. Physical environment receptors with low sensitivity include groundwater, surface water and drinking water

Low to Medium impact Agreement should be reached prior to commencing construction work between the contractor and landfill for officially assigning a location for the disposal of construction waste. Waste management submitted by the contractor for waste management (solid waste; hazardous and non-hazardous) Protection of spillage including paved site for workshop or maintenance of vehicles Temporary storage of wastes including on site sanitation before the proper connection to the existing sewage network is installed. It is preferable to include the temporary onsite waste management for the workers in the ToR of the contractor.

Health and Safety High likelihood to occur for the construction workers Low likelihood to occur for the surrounding establishment and sensitive receptors. Highly sensitive receptors include workers. Receptors with low sensitivity include nearby residents and existing establishments

Minor impact for sensitive receptors and medium to high / major impact for the workers

Standard protection by placing clear project signs. Time management for vehicles movement; especially avoiding the peak hours Standard protection for the workers especially working at elevated heights

Impact on natural disaster risks

Low likelihood to occur Negligible impact No mitigation measures is prepared Technical specifications of the equipment is include the standard measures for natural disaster risks

Impact on visual Resources

Low likelihood to occur Minor impact, localized and temporary

Following the standard protection for the ground and soil disturbance, air quality (and dust) measures and proper waste management described on the section of waste management measures Clear sign of the construction activities

Impact on water resource (ground water, surface water and drinking water)

Low likelihood to occur Minor impact on groundwater, surface water and drinking water

Following standard protection for the ground and soil and proper waste management described on the section of waste management measures

Ecological Resources

Low likelihood to occur No significant impact No mitigation measures is prepared

Page 23: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xiv

Impact Likelihood and severity Significance Mitigation Measures Impacts on Fauna and Flora and bird migration

Low likelihood to occur Negligible impact (no impact)

No mitigation measures are needed.

Impact on landscape

Low likelihood to occur Negligible or no impacts No mitigation measures is prepared

Impact on land use and Involuntary resettlement

Low likelihood to occur Very low or no impacts No mitigation measures is prepared

Impact on archeological and cultural sites

Low likelihood to occur Very low or no impacts No mitigation measures is prepared

Socio Economy Temporary impacts on the temporary prayer area used instead of the mosque under renovation

Minor and temporary impacts

Coordination with the adjacent mosque prior to the start of the construction activities

Creation of Job opportunities and flourishing Economics of construction site

Creating job opportunities for members of the local community

High positive temporary impact

Coordination with the contractor to employ members of the local community as construction workers and guards

Culture and Privacy of Local Communities

Construction workers must respect the culture and privacy of members of the surrounding residential area

Minor and temporary Respect from construction workers to the privacy of the surrounding houses

During construction of underground cables (220 kV and 66 kV) Impact on Noise High likelihood to occur – short term

and temporary - Highly sensitive receptors includes construction workers. Receptors with low sensitivity include nearby projects/settlements

Low Impact on residential and surrounding establishment and Medium impact on the construction workers

Application of the normal precautions normally taken by construction workers. Notification to the surrounding establishment prior to the construction of the underground cables Time management and construction schedule according to the IFC regulation provided by the contractor prior to the construction phase

Page 24: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xv

Impact Likelihood and severity Significance Mitigation Measures Impact on traffic High likelihood to occur – short term,

temporary and localized only on the main road mainly (El Nasser Rd) and El Salam rd– Highly sensitive receptors include main road (El Nasser road traffic) and El Salam (local road) traffic and nearby residential area using El Salam road

Low to medium impact on the residents and surrounding establishment and medium impact on the main road (El Salam road) and the inhabitant passing by the road during the construction phase

Time management for transporting the materials, equipment, debris, etc Clear sign surrounding construction site and the enter / exit gate Close coordination with traffic department (ministry of interior) for vehicles route and movement and additional space, if needed at the main road during the peak construction period (estimated within maximum 3 months period)

Impact on Air Quality

High likelihood to occur – short term, temporary and localized - Highly sensitive receptors include construction workers. Receptors with low sensitivity include nearby projects/settlements.

Medium impact on construction workers and inhabitants passing by the main road Low impact on the residents, surrounding establishment

Dust control (if needed, especially during the dry period). Standard protection of the workers to avoid inhalation problem Vehicles, machineries and equipment time management to reduce the accumulation of dust and exhaust gas. In addition, the regular maintenance of the machinery and equipment to ensure a minimum emission.

Impact on Vibration

Low likelihood to occur Minor impact Schedule and time plan for vehicles movements and work activities

Impact on Hazardous materials and waste generation

Uncertain likelihood – Uncertain impact duration - Highly sensitive receptors include soil pollution and workers. Receptors with low sensitivity include nearby projects/settlements. Physical environment receptors with low sensitivity include groundwater, surface water and drinking water

Low to Medium impact Agreement should be reached prior to commencing construction work between the contractor and landfill for officially assigning a location for the disposal of construction waste. Waste management submitted by the contractor for waste management (solidwaste; hazardous and non-hazardous) Protection of spillage including paved site for workshop or maintenance of vehicles Temporary storage of wastes including on site sanitation before the proper connection to the existing sewage network is installed. It is preferable to include the temporary onsite waste management for the workers in the ToR of the contractor.

Page 25: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xvi

Impact Likelihood and severity Significance Mitigation Measures Health and Safety High likelihood to occur for the

construction workers and for the surrounding establishment and sensitive receptors.

Medium to Major impact for sensitive receptors and for the workers

Standard protection by placing clear project signs. Time management for vehicles movement; especially avoiding the peak hours Standard protection for the workers especially working with excavation and drilling Temporary construction fences to localize and privatize the construction sites. Proper management and monitoring done by contractor under supervision from the independent consultant and EETC

Impact on natural disaster risks

Low likelihood to occur Negligible impact No mitigation measures is prepared Technical specifications of the equipment is include the standard measures for natural disaster risks

Impact on visual Resources

Low likelihood to occur Minor impact, localized and temporary

Following the standard protection for the ground and soil disturbance, air quality (and dust) measures and proper waste management described on the section of waste management measures Clear sign of work activities

Impact on water resource (ground water, surface water and drinking water)

Low likelihood to occur Minor impact on groundwater, surface water and drinking water

Following standard protection for the ground and soil and proper waste management described on the section of waste management measures

Ecological Resources

Low likelihood to occur No significant impact No mitigation measures is prepared

Impacts on Fauna and Flora and bird migration

Low likelihood to occur Negligible impact (no impact)

No mitigation measures are needed.

Impact on landscape

Low likelihood to occur Negligible or no impacts No mitigation measures is prepared

Impact on land use and Involuntary resettlement

Low likelihood to occur Very low or no impacts No mitigation measures is prepared

Page 26: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xvii

Impact Likelihood and severity Significance Mitigation Measures Impact on archeological and cultural sites

Low likelihood to occur Very low or no impacts No mitigation measures is prepared

Socio Economy Impact on socio-economic activities at el Salam road during excavation

Minor and temporary impact

Conducting the excavation in the shortest possible time Coordination with the traffic department to divert the route of the street during excavation activities

Creation of Job opportunities and flourishing Economics of construction site

Creating job opportunities for members of the local community

High positive temporary impact

Coordination with the contractor to employ members of the local community as construction workers and guards

Table 6 Significance of Expected Impacts Assessment during Operation Phase of Manshyet Nasser Substation and its interconnection underground cables

Impact Likelihood and severity Significance Mitigation Measures During operation and maintenance of Manshyet Nasser Substation Impact on Noise High likelihood to occur –

Highly sensitive receptors include nearby projects/settlements (residential areas and hospital) especially during the night and the permanent workers at the substation.

Low to Medium Impact on on settlement and nearby establishment especially during the night :Low to medium impact on permanent workers

Application of the normal precautions normally taken such as planting trees. Besides reducing the visual impact, the green environment will be achieved as well. Standard protection for the workers will be provided at the substation.

Impact on traffic Low likelihood to occur Low impact No mitigation measure is prepared Impact on Vibration Low likelihood to occur Low impact No mitigation measure is prepared

Minor or very low likelihood to occur

Very minor No mitigation measure is prepared

Page 27: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xviii

Impact Likelihood and severity Significance Mitigation Measures Impact on wastes generated (hazardous and non-hazardous, solid and liquid wastes)

Uncertain likelihood – Uncertain impact duration - Highly sensitive receptors include soil pollution and workers. Receptors with low sensitivity include nearby projects/settlements. Physical environment receptors with low sensitivity include groundwater, surface water and drinking water

Medium impact on industrial wastes generated (hazardous and non-hazardous) Low impact on domestic wastes (solid and liquid wastes)

Waste management implemented according to EEAA regulations, especially for industrial hazardous wastes (solid and liquid wastes) Regular monitoring for domestic sewage network and provision of waste bins for temporary storage before collected by municipality.

Impact on soil contamination

High likelihood to occur, only during the incident of oil spillage from the transformers and possible vehicles.

Low to medium impact Standard design of precaution for the site of transformers Paved within surrounding site of substation especially at the area for parking and movement of vehicles

Health and Safety High likelihood to occur for the permanent workers Low likelihood to occur for the surrounding establishment and sensitive receptors. High risk likelihood impact during the emergency and accident

Minor impact for sensitive receptors (public and residents as well as existing establishment) and medium impact for the workers High risk likelihood impact during the emergency and accident

Standard protection by placing clear project signs. Time management for vehicles movement; especially avoiding the peak hours Standard protection for the workers especially working at elevated heights

Impact on natural disaster risks

Low likelihood to occur Negligible impact No mitigation measures is prepared Technical specifications of the equipment is include the standard measures for natural disaster risks

Impact on visual Resources

Low likelihood to occur Very low impact or negligible impact

No mitigation measure is prepared

Impact on water resource (ground water, surface water and drinking water)

Low likelihood to occur Minor impact on groundwater, surface water and drinking water

Proper waste management according to EEAA regulations Monitoring for pipeline of sewage network Provision of waste bins for temporary storage

Ecological Resources Low likelihood to occur No significant impact No mitigation measures is prepared

Page 28: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xix

Impact Likelihood and severity Significance Mitigation Measures Impacts on Fauna and Flora and bird migration

Low likelihood to occur Negligible impact (no impact) No mitigation measures are needed.

Impact on landscape and land use

Low likelihood to occur Negligible or no impacts No mitigation measures is prepared

Impact on archeological and cultural sites

Low likelihood to occur No impacts No mitigation measures is prepared

Socio Economy Improving living conditions Providing a stable electricity service Increasing illegal connections

High Positive impacts The distribution and collection company at EETC should have an awareness plan to connect beneficiaries legally. Increase awareness about the importance of having official connections

Creation of Job opportunities and flourishing Economics of construction site

Increasing the opportunity for opening small business and shops as a result of having a stable electricity service

Moderate positive impact No mitigation measures is prepared Awareness campaigns for community members to rationalize consumption of electricity service

During operation of interconnection underground cables (220 kV and 66 kV) Impact on operation and maintenance along the route

Low likelihood to occur – short term and temporary only during repaired or replacement of underground cables- Highly sensitive receptors includes construction workers. Receptors with low sensitivity include nearby projects/settlements

Low Impact on residential and surrounding establishment and Medium impact on the workers

Application of the normal precautions normally taken by workers. Notification to the surrounding establishment prior to the replacement or repaired of the underground cables

Impact on ROW along the underground cable routes

Low likelihood to occur No impact No mitigation measure is prepared

Page 29: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xx

Impact Likelihood and severity Significance Mitigation Measures Impact on noise, traffic, air quality, ecological resources, hazardous wastes, health and safety, water resources, visual, landscape and land use

Low likelihood to occur, except during accident to occur, emergency situation and possible replacement and repaired of the underground cables

Low impact Temporary and localized low impact during accident, emergency situation and replacement or repaired

Time management for repair or replacement Clear sign surrounding site to be repaired or replaced Standard protection to workers Implementation of emergency plans and periodic trainings for accidents or emergency situations

Impact on EMF for public concern

Low likelihood to occur Low impact Monitoring and regular tightening of the underground cables connection to GIS substation

Impact on archeological and cultural sites

Low likelihood to occur No impacts No mitigation measures is prepared

Page 30: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxi

7. Environmental and Social Management Plan (ESMP) and Monitoring Plan

The Environmental and Social Management Plan (ESMP) consists of a set of mitigation, management and monitoring measures to be taken during implementation of the project to avoid, reduce, mitigate, or compensate or offset any adverse social and environmental impacts analyzed at the previous chapter. The ESMP has distinguished between mitigation measures that should be implemented during the construction and operation of the project.

ESMP defines procedures to ensure that the management of environmental and social issues during the different project phases are undertaken in accordance with national legislation and best practice procedures. The Environmental and Social Management Plan (ESMP) presented in this chapter reflects the implementation procedures and mechanisms for the mitigation measures and monitoring activities of the expected impacts previously discussed in Chapter 6. The ESMP assigns certain tasks for different stakeholders according to their roles and responsibilities in the project.

The successful implementation of the ESMP will depend on a range of different elements. To ensure a management plan that incorporates and successfully integrates with interface documents, the following elements must be considered and acted upon:

The environmental and Social Management unit should be adequately staffed to ensure the proper implementation and monitoring of the ESMP. The organizational structure of the environmental and social at PMU should also reflect the range of complete competencies to perform the tasks.

The development and management of registers for the proper documentation and tracking of environmental and social training, environmental and social incidents and environmental and social related complaints.

Roles and responsibilities for implementing the ESMP during the construction phase have been proposed based on the following set-up:

- EETC will contract an authorized and specialized consultant to prepare detailed designs and tender documents, for construction of substation and its interconnection, which will include the environmental measures that should be undertaken by the construction contractor

- During tenders evaluation EETC will assure that the winning offer includes the required environmental mitigation measures to be implemented during construction. This will include the management of traffic and management of wastes (solid and liquid; hazardous and non-hazardous wastes)

- EETC will assign supervision staff who will undertake supervision over the contractor to make sure that the mitigation measures specified in the design/tender document are implemented on field

- The site supervisor consultant from EETC will produce the monthly report about the performance of the contractor in implementing the ESMP measures

During the operation phase, the substation shall have permanently at least one staff member for health, environmental and safety during operation and maintenance of the substation and its interconnection (under supervision of the substation management). HSE staff of the substation and interconnection appointed by EETC (under environmental safety and health department) will be responsible for monitoring the ESMP. He will be responsible for implementing the mitigation measures through periodic reports presented to EETC including auditing and inspections that will be undertaken on random basis.

Page 31: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxii

Table 7 ESMP Matrix during preparation and construction of the substation and its interconnection underground cables

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities

(enforcement and coordination) Cost Estimates ($)* Comments

During Preparation and Construction of the SS Noise and vibration during site preparation, construction and installation of equipment

General measures for surrounding establishments and sensitive receptors Notification letter of the introduction of project and duration to surrounding establishment and municipality

Contractor - Cover letter from EETC for approval of starting of the project

Clear sign and warning sign (can be seen during day and night) of the project (including duration)

Contractor as a part of ToR for EHS general requirements

None as a part of tender process

Duration of the working on site (including uploading and loading) are during day only (between 7AM – 5 PM)

Contractor -

Mitigation measures for construction workers during preparation and construction Strictly standard procedures for health and safety of the workers according to IFC general EHS guidelines (including limitation of the duration and expose to high noise) and management of concentration works of heavy machineries

Contractor (through tendering activity) None as a part of tender process

Strictly standard equipment especially for ear protection during the work

Contractor (through tendering activity) related to the EHS requirements during construction works

None as a part of tender process

Traffic destruction or congestion during transportation of construction materials, construction waste, equipment and movement of project vehicles and machineries

Approval from traffic department prior to the construction

Contractor - Cover letter from EETC for approval of starting of the project

Clear sign and warnings (including duration) of the project that can be seen during the day and night

Contractor as a part of the tender activities related to EHS requirements

None as a part of tender process

Destruction of El Salam road done section by section and during the end of the day the street should be covered from the excavation and other work activities

Contractor in assistance from traffic department and the EETC supervisor

-

Movement of vehicles (for transporting Contractor in coordination with traffic None as a part of

Page 32: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxiii

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

materials, construction waste and SS equipment done during the night and loading and uploading done during the day within the site of the SS.

department, if needed Contractor financial budget during the bidding activities

Agreement for temporary storage and the final disposal to the designated landfill

Based on the waste management plan submitted by the contractor and approval from EETC

None as a part of the ToR for waste management

Careful turn at the main road. The drivers and operators of the machineries should have training on safety utilization of their machines

Drivers and operators employed by the Contractor. It is the responsibility of the contractor for implementing regulations to the drivers and operators

None as a part of contractor responsibility

Ambient Air Quality by dust emission and the air emission due to the exhaust gasses from the construction vehicles and machineries

Localize and minimize the vehicle movements including limiting the speed

Contractor As a part of their financial budget during the bidding activities

Low impact and temporary

If needed, spray the soil before any excavation, filling loading and unloading. Pavement (graveled) of access roads prior to usage in construction of the project components

Contractor -

Maintaining the efficiency of the vehicles and machineries

Contractor As a part of their financial budget during the bidding activities

Waste management of temporary stock piles, construction materials, construction waste. The periodic waste transportation to the designated landfill should be included on the waste management as well.

Contractor As a part of the ToR for waste management

Implementing the waste management submitted by the contractor and approved by EETC prior to the preparation and construction phase

Waste generated (hazardous and non-hazardous, solid and liquid as well as

Notification and contract, if needed for transporting hazardous and non-hazardous waste to their designated landfills.

Contractor None, as a part of the contractor’s offers and responsibilities

Implementing the waste management submitted by the contractor and approved by EETC prior to the preparation and Separation of hazardous waste and non-

Page 33: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxiv

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

construction waste and domestic waste)

hazardous waste for temporary storage during preparation and construction phase

construction phase

Designated area or location should be included at the waste management plan submitted by the contractor and approved by the EETC Construction waste should be hauled at the end of each business day to the officially approved disposal sites Adequate trucks with standard precaution (coverage of the waste, not overloaded, etc) for transporting the waste to the designated landfills. Regarding the hazardous waste transportation, the vehicles should be according to the standard mentioned on the EEAA regulations for hazardous waste transportation Temporary onsite waste bins for solid waste before its collection and temporary onsite sanitation facilities should be provided within the construction site for the workers

Contractor None, as a part of waste management

According to the waste management plan submitted to EETC

Safety impacts during excavation and trenching for the workers and surrounding communities and establishments

Excavation and trenching in accordance to the design and drawings.

Contractor -

Protection and localized (by fences or barriers) the excavation and trenching sites to reduce the danger and prevent falling of materials and person and the other vehicles or machineries moving nearby the site

Contractor None as a part of contractor offers related to EHS requirements

Standard helmet and safety boots for the workers

Contractor None as a part of contractor offers related to EHS requirements

Page 34: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxv

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

Safety impacts during the mechanical and machineries use for the health and safety of the workers

Provision of authorized and licensed personnel for heavy machineries

Contractor None as a part of contractor responsibilities

Maintaining the efficiency of the heavy machineries, including inspection before its use and following the design capacity and standard manuals of the heavy machineries, etc.

Health and safety of the construction workers

Standard protection for the construction site workers

Contractor

None as a part of contractor offers related to EHS requirements

Provided on job training for the construction workers prior to the preparation and construction phase (including working at the high construction) Identification of the existing underground networks Management of heavy equipment movement, especially nearby other existing underground networks

Water resources and soil pollution during construction

Precaution and prevention of waste management to prevent the soil and further water resource (groundwater or nearby surface water or drinking water network) pollution

Contractor None, as a part of waste management

According to the waste management plan submitted to EETC

During Preparation and Construction of the interconnection underground cables Noise during the preparation and construction

Notification letter to the surrounding establishments and municipality prior to the construction

Contractor - Cover letter from EETC for approval of starting of the project

Fenced, localized and privatized the site (especially at the middle of the road; middle island of the El Nassrrd)

Contractor None as a part of financial offer related to EHS requirements

Temporary and short term only during construction.

Clear project signs and warning signs of the

Page 35: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxvi

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

project (including duration of the project) Construction activities concentrated during the day (7 AM to 5 PM) except during the transportation of equipment and materials. However, loading and unloading should be done during the day

Contractor -

Strictly standard procedures for health and safety of the workers according to IFC general EHS guidelines (including limitation of the duration and expose to high noise) and management of concentration works of heavy machineries

Contractor -

Strictly standard equipment especially for ear protection during the work

Contractor None as a part of financial offer related to EHS requirements

Traffic disturbance Coordination with the traffic department for traffic management during the construction of tunnel (construction site will be at the middle of the street and the middle island) and the excavation of the El Salam road.

Contractor - Cover letter from EETC for approval of starting of the project

Temporary storage area for the construction materials, construction waste and standby machineries.

Contractor None as a part of ToR for waste management

According to waste management plan submitted to EETC prior to preparation and construction phase

Additional lane, if needed to be provided at one side of the road

Contractor in coordination with EETC - Approval or permission, if needed might be obtained for using the temporary empty land area for storage

Management of excavation, especially at El Salam street that has to be done section by section and filled and covered up at the end of working day

Contractor, if needed in coordination with traffic department

If approval needed, it must be obtained prior to the construction

Management of vehicles movement for transportation of the equipment, materials

Contractor -

Page 36: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxvii

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

and waste (transportation of big vehicles done during the night. However, loading and unloading done during the day time)

Careful turns especially at the main El Nasr road to avoid accident that can congest the traffic

Contractor - If necessary, the coordination with the traffic department for traffic management during the turns of vehicles

Licensed and trained drivers and operators Contractor, as a part of their responsibility - Ambient air due to dust emission and exhaust gaseous from vehicles and heavy machineries

Maintain the efficiency of the vehicles and heavy machineries

Contractor, as a part of their responsibility -

Limiting speed of the construction vehicles and machineries

Operators or drivers hired by Contractor - It is a responsibility of the contractor to hire the trained, qualified and licensed drivers and operators

Management of stock piles (including temporary storage, covering up the stock piles and the transportation to the designated landfill, etc.)

Contractor None as a part of ToR for waste management

According to waste management plan submitted to EETC prior to preparation and construction phase

Waste generated from the construction and domestic (workers); management of wastes

Separation of hazardous and non-hazardous waste and identification of recycle, sell or dump it to the landfill.

Contractor None as a part of ToR for waste management

According to waste management plan submitted to EETC prior to preparation and construction phase

Agreement with the landfill for transporting wastes to their designated landfills (construction non-hazardous waste and hazardous waste)

Contractor None as a part of ToR for waste management

According to waste management plan submitted to EETC prior to preparation and construction phase

Temporary storage of the waste (separate areas for hazardous and non-hazardous waste)

Contractor None as a part of ToR for waste management

According to waste management plan submitted to EETC prior to preparation and construction phase

Transportation of wastes should follow the safety regulations (not overloaded, covered

Contractor None as a part of ToR for waste

According to waste management plan submitted to EETC prior to

Page 37: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxviii

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

and not midway dumping). Especially for the hazardous waste, the EEAA regulations should be followed

management preparation and construction phase

Temporary onsite sanitation for construction workers and provision of waste bins within the project site

Contractor None as a part of ToR for waste management

According to waste management plan submitted to EETC prior to preparation and construction phase

Safety during excavation and trenching

Following the designs and drawings accordingly

Contractor in coordination with EETC -

For tunneling of 220 kV, the trained operators should be hired to reduce the risks of accident and injuries

Operators hired by Contractor - It is a responsibility of the contractor to hire the trained, qualified and licensed operators

Prevention and precaution due to the excavation by providing sloping, emergency ladders, barriers, rejected of the vehicles to the nearby excavation area (min 2 m), etc.

Contractor As a part of the financial offer related to EHS requirements

Standard protection to the workers Contractor As a part of the financial offer related to EHS requirements

Safety for mechanical and machineries used during construction

Licensed and trained operators for heavy machineries

Operators hired by Contractor - It is a responsibility of the contractor to hire the trained, qualified and licensed operators

Maintenance of the mechanical and heavy machineries and general inspection before using them.

Contractor -

Health and safety of the construction workers

Localized the site, securely guarded, clear signs and warning signs, especially for the tunneling of 220 kV (at the middle island of El Nasr rd)

Contractor As a part of the financial offer related to EHS requirements

Standard protection of the construction workers including working at high construction

Contractor As a part of the financial offer related to EHS requirements

Training for safety at the construction sites Contractor As a part of the

Page 38: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxix

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities (enforcement and coordination)

Cost Estimates ($)* Comments

including working at high construction financial offer related to EHS requirements

Identification of exact location of existing utilities and networks

Contractor -

Avoid the heavy equipment operating above the underground existing utilities and networks. Otherwise, the additional foundations (if needed) or additional soil covered might be provided above the existing networks

Contractor -

Water resources and soil contamination

Precaution and prevention of waste management to avoid spillage and leakage

Contractor -

Impacts on culture and privacy of local communities

Maximize the use of local workers as much as possible.

Construction supervisor consultant None – part of the TOR

All activities related to the construction have to be placed within the EETC premises in order to avoid interference with the community privacy.

Illegal electricity connections

Awareness campaigns to encourage legal connections Awareness campaigns to rationalize consumption

Social Development officer, Distribution company

Print material and posters, community meetings 5000 EGP

These activities can start on the last period of construction

Table 8 Monitoring Plan during preparation and construction of the substation and its interconnection underground cables

Project activities Parameters to be monitored Locations Measurements (methods and

equipment) Frequency of

measurements Cost Estimates

($)** Responsibilities

During Pre-Construction / Preparation and Construction phase Site clearance Worker’s injuries Construction site

location Preparation of recording form of workers injure during the construction

Monthly None Contractor On the preparation stage, the tendering Base camp Neighbors’ complaints Project construction Recording of complaint and Once during the None

Page 39: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxx

Project activities Parameters to be monitored

Locations Measurements (methods and equipment)

Frequency of measurements

Cost Estimates ($)**

Responsibilities

preparation for the workers

sites type of complaint preparation and prior to start the construction phase

has been done to purchase the standard procedure for site clearance. However, the contractor shall put into consideration on their budget proposal

Monitoring the traffic disturbance due to the vehicles and machineries movement and other related construction activities

Traffic complaint Within 500 m from the construction site (especially at the main road, El Nasr rd)

Visual observation and recording complaint received

During the duration of the construction activities

Monitoring ambient Air Quality during construction works

Ambient air (gasemissions) PM, dust complaint

Within the site and surrounding establishments

Visual investigation and recording of the dust and ambient air increased due to construction activities Recording and reporting of the complaints (monthly report)

during the construction activities at different locations

As a part of contractor’s financial offer

Monitoring Noise and vibration Impacts at the project sites

Noise complaints from the neighboring communities

Project locations Visual investigation and recording and documentation of complaints

during the construction activities at different locations

As a part of contractor’s financial offer

Contractor

Management of construction waste and handling of hazardous waste

Amount of hazardous and nonhazardous waste generated

Project site locations

Estimation of the hazardous waste and non-hazardous waste in relation to the handling and transporting to the landfill

Weekly or monthly depending on the volume of waste

As a part of contractor’s financial offer for wastes handling

Contractor during construction and EETC SS staff during operation

Monitoring soil contamination and water resource contaminations

Area of spillage Project sites Visual observation Recording and documentation of spillage

weekly As a part of contractor’s financial offer for environmental monitoring

Contractor

Monitoring health and safety of the workers during the construction of the

Health records about occupational injuries

Clinic / hospital referred by the contractor

Medical reporting on received cases on received case

The cost is undefined, depending on the cases

contractor

Page 40: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxxi

Project activities Parameters to be monitored

Locations Measurements (methods and equipment)

Frequency of measurements

Cost Estimates ($)**

Responsibilities

project components Storage of the machines and construction materials of the project components

Complaints from neighboring communities and records and documentation of the temporary area for storage of materials or machineries

Project sites Recording and documentation monthly - contractor

Impacts of culture and privacy of local communities

% of local labor to total labor

Construction site Reporting labor origin governorates and calculating the natives ratio

Quarterly - Construction contractor

Table 9 ESMP Matrix during operation and maintenance of the substation and its interconnection underground cables

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities

(enforcement and coordination)

Cost Estimates ($)* Comments

During Operation and Maintenance of the SS Noise General measures for surrounding establishments and sensitive receptors

Planting trees at surrounding the SS site. Besides reducing the noise, the measures will reduce the impact on vibration and visual or aesthetic.

Operators of SS at Manshiyet Nasser

10,000 LE for annual maintenance of the trees (including cutting, watering, etc)

Mitigation measures for operators and staff of SS Standard procedures for health and safety of the workers according to IFC general EHS guidelines (including limitation of the duration and expose to high noise) and management of concentration works of heavy machineries

EETC Around 5,000 LE annually for standard protection of staff

Standard equipment especially for ear protection during the work

EETC

Waste generated Proper waste management (industrial wastes) EETC Undefined as the amount

Page 41: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxxii

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities

(enforcement and coordination)

Cost Estimates ($)* Comments

(hazardous and non-hazardous, solid and liquid industrial wastes as well as domestic waste)

including separation of waste, separate area for temporary waste, transporting and disposing the industrial waste to their designated landfills

of wastes generated, especially for the industrial non-hazardous and hazardous waste are uncertain.

Especially for hazardous waste, the storage, collection, transportation and disposal of hazardous waste should follow the EEAA regulations for hazardous waste. Concerning domestic waste, the standard procedures for maintenance of the networks (including provision of waste bins) should be maintained

Public and operators and staff safety of the EMF exposure

Periodic maintenance of the GIS SS and its interconnections. This includes the regular tightening, SS efficiency, oil quality, gas pressure, etc.

EETC operators of the SS -

EMF reading at the SS and surrounding site EETC 100-150 USD per EMF meter

The cost estimation is based on one time purchased for one meter. It is advisable to purchase two machines for standby purposes.

Trainings provided for potential risks during accidents (firefighting training, oil spillage, smoke detector, etc)

Provision of trainings provided by EETC as a general requirements

EETC Undefined as the type of trainings and the duration of trainings are vary.

The cost estimation is included at annual trainings provided by EETC for their SS and interconnection staffs.

Health and safety of the staff

Standard protection for the SS operators and staffs

EETC

None as a part of precaution of noise protection

Provided on job training for the staff for general health and safety

Page 42: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

xxxiii

Potential Impacts Proposed Mitigation Measures Institutional Responsibilities

(enforcement and coordination)

Cost Estimates ($)* Comments

During operation and maintenance of the interconnection underground cables There is no specific maintenance of the underground cables, unless there is incident when the connection is cut, un-function or need to be replaced. If there is any repair needed, the additional mitigation measures for electrical shock for the workers, including the disconnecting the power temporarily will be applied during the maintenance period. However, regular and periodical trainings of emergency during operation and maintenance is provided by EETC for SS staffs. In general, the administration works, recording of accidents, injuries and other complaints from the surrounding establishment will be done during the monitoring of the operation and maintenance of the SS and interconnection underground cables. The record includes the recording and monitoring of the waste management on the SS (especially industrial waste management). Regarding the EMF exposure, the monitoring of the interconnection line surrounding the SS will be done similar and at the same time with the measurements of EMF exposure of the SS.

Page 43: Environmental and Social for Summary for Manshyat Naser _English.pdf · - OP 4.12 for Involuntary Resettlement - OP 17.50 for Public Consultation and Disclosure Plan Potential Egyptian

Manshyet Nasser Substation and Interconnection Underground Cables Executive Summary

34

Environmental Safeguard Training The Project Company (EETC) will ensure that the substation is manned 24 hours 7 days per week. Typically, a substation of this type employs around 25 staff with around 10 engineers with 3 shifts per day. All staff employed will be trained in the following:

Specific job roles and procedures; Occupational health and safety; and Contingency plans and emergency procedures.

Training will include: Induction training on appointment; Specialist training (as required for their prescribed job role); and Refresher training as required.

The training program will be designed to ensure that appropriate skilled staffs are used to operate and maintain the substation at all times. Aspects of occupational health and safety and emergency procedures are to be emphasized.

In addition to this environmental training will be given to all staff employed at the project and special environmental training will be given to the staff during the operation phase to implement the ESMP. They will receive training in the following:

Day-to-day monitoring activities; Collection and analysis of data; Use of monitoring equipment, operation and maintenance; Industrial hygiene; Occupational health and safety; and Emergency and contingency procedures.

During the consultation with one of the operator in the existing substation, it is already established the safety standard and regular training held for the staff member. The regular refreshment training held besides the operation and maintenance training are:

Administration skills Civil protection Firefighting and fire accident Smoke detection Fire equipment maintenance

In addition, in every substation, EETC provides the emergency plan map including the responsibility of each staff during emergency and their contacts.

For the new SS at Manshiyet Nasser, to ensure the implementation of ESMP especially during operation and maintenance, one additional staff from EETC (from Environmental background) under the head of the SS will be recruited on full time basis for maintaining the implementation of environmental management.