Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
ADDRESS COWI A/S
Parallelvej 2
2800 Kongens Lyngby
Denmark
TEL +45 56 40 00 00
FAX +45 56 40 99 99
WWW cowi.com
PROJECT NO. A052992
DOCUMENT NO. 1.0
VERSION 3
DATE OF ISSUE June 27 2014
PREPARED MORH
CHECKED AFJ
APPROVED TTAN
CONTENTS
1 Introduction 3
2 Scope 5
3 National and international legislation 6
4 Alternatives 7
5 Construction 7
6 Operation 8
7 The surrounding environment 8
8 Environmental impacts during construction 13
8.1 Discharges during drilling 13
8.2 Emissions 13
8.3 Laying of pipelines 13
8.4 Noise and Light 13
9 Environmental impacts during operation 14
9.1 Discharges of production water 14
9.2 Emissions 14
9.3 Physical presence of the platform 14
9.4 Noise and Light 14
9.5 Ship collision 15
MAERSK OIL
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT OF THE
CONSTRUCTION AND OPERATION OF ADDA AND TYRA N
NON-TECHNICAL SUMMARY
2/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
10 Environmental impacts from decommissioning 15
11 Environmental impacts from unplanned events 15
11.1 Blow out events 15
11.2 Pipeline ruptures 16
11.3 Other spills 16
12 Impacts on protected areas (Nature 2000
screening) 16
13 Socio-economic assessment 17
14 Cumulative impacts 18
15 Transboundary impacts 18
16 Mitigating measures 18
ESIA OF ADDA AND TYRA N DEVELOPMENT 3/19
1 Introduction
This document is a non-technical summary of the Environmental and Social Impact
Assessment (ESIA) of the development of the Adda and Tyra LC fields located in
the Danish sector of the North Sea.
Maersk Oil is the operator of the development project and the assessment is
carried out as required by Danish Law (Order no. 632 of 11th June 2012) on EIA,
consequence evaluation regarding international nature protection areas and
protection of certain species in connection with projects concerning hydrocarbon
production, pipelines, etc. at sea and on the continental shelf). The Danish Energy
Agency is the responsible authority.
The Adda field is located 250 km from the Danish west coast, approximately 10
km north of the existing facilities Tyra East and West. The Tyra LC field is located
5 km southwest of the Adda field (Figure 1-1).
Figure 1-1 Location of the Adda field in the Danish sector of the North Sea.
Gas and oil have been found in the area in chalk and limestone layers and in
profitable amounts and quality.
4/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
The development includes the construction of two unmanned platforms, Adda and
Tyra North LC (Tyra N), which will be connected to each other and the existing
nearby Tyra East facility through a pipeline system of 11.6 km.
Figure 1-2 Diagram of the Adda and Tyra LC field development and its connection to Tyra
East.
Up to 22 wells will be established on the two platforms, which will be controlled
and monitored from Tyra East. The production from the platforms will be
transported to Tyra East for processing and continued transport ashore.
Figure 1-3 The Tyra East facility.
ESIA OF ADDA AND TYRA N DEVELOPMENT 5/19
2 Scope
The ESIA comprises assessments of the various phases of the project life cycle
from construction to operation and decommissioning. It includes:
› A technical description of the facilities, their construction and operation,
including installation of the platforms and construction of the wells, laying of
pipelines and processing of the production on Tyra East as well as the
dismantling of facilities at the end of the lifetime of the field
› A description of the relevant legislation and conventions in regard to the
project
› A detailed description of the environmental state in the project area and the
socioeconomic conditions, which potentially may be impacted by the project.
The former includes a screening of what fauna and flora live in the area from
microscopic plankton to whales
› An impact assessment and screening in regard to potential impacts on
protected areas during the lifecycle of the project
› An assessment of transboundary effects and possible mitigating activities
Figure 2-1and Figure 2-2 presents an overview of the activities during the
construction and operation phases of the project which are assessed in the ESIA, as
well as the environmental features which may be impacted.
Figure 2-1 Activities during the construction phase, which are assessed in the ESIA.
6/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
Figure 2-2 Activities during the operation phase, which are assessed in the ESIA.
The impact on the environment from the project activities during construction,
operation and decommissioning is assessed. The assessment is based on the nature,
size, duration , and geographical extent of the impact. Thereby, the environmental
impact can be characterized according to the following categories: i) No impact, ii)
Insignificant impact, iii) Minor impact, iv) Moderate Impact and v) Major impact.
3 National and international legislation
Danish law stipulates that an ESIA must be carried out for such a project in order
to obtain permission to extract oil and gas offshore. The requirement is stated in the
EIA EU directive, which is implemented in Danish Law.
Denmark has ratified several other international laws and conventions, which,
together with the national legislation, sets the framework and criteria for several
aspects of projects like the Adda/Tyra LC fields development. It involves the Act
on the Protection of the Marine Environment, the Offshore Safety Act, the Act on
CO₂ Quotas and EU directives on emissions and protected areas (Natura 2000) as
well as the Espoo and OSPAR conventions and the Marine Strategy Framework
Directive.
ESIA OF ADDA AND TYRA N DEVELOPMENT 7/19
4 Alternatives
Maersk Oil has considered other options for the development of the Adda and Tyra
LC fields, including the 0-alternative which is no further development. The chosen
option was selected as the best possible alternative from a technical and
economical viewpoint as well as from a safety and environmental perspective.
5 Construction
The development of the Adda and Tyra LC fields will begin with the establishment
of the Adda platform, approximately 5 km north of the position of the Tyra N
platform. From the Adda platform, up to 16 wells will be drilled, while a maximum
of six are planned for Tyra N. The drilling of each well is expected to take about
120 days. It is planned that the first two wells will be drilled at Adda in 2015 from
a drilling rig, which is towed to the area and secured to the seabed on its own three
legs. The remaining wells will be drilled after installation of the Adda platform.
The construction schedule of the Tyra N platform and accompanying wells has not
yet been finalized.
Figure 5-1 Example of a drill rig, which can be used in the development of the Adda and
Tyra LC fields.
Several activities during the drilling and well construction process include the use
of materials and chemicals, which are either discharged to the sea or collected and
shipped to shore depending on their potential impact on the environment. The main
part of the discharges will be drilling mud and cuttings, which mainly consist of
material drilled out of the well.
Laying of pipelines will be done with a specialized vessel after a trench has been
made in the seabed.
8/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
Figure 5-2 Specialised pipe laying vessel.
6 Operation
The Adda and Tyra N production will be separated and transported to Tyra East. In
the separation process, oil , gas and production water containing oil substances and
other chemicals are separated. All discharges of production water and emissions
from the treatment processes will take place on Tyra East.
The Adda and Tyra N platforms will be remotely controlled from Tyra East.
Chemicals and power will also be delivered through a service pipeline (umbilical)
from Tyra East. Monthly maintenance visits will be made by ship from Tyra East,
and the pipelines will be maintained by pigging operations.
7 The surrounding environment
The part of the North Sea, where the Adda and Tyra N field (hereafter project area)
are located, has an average depth of 40 m and is dominated by east-going currents.
The water masses of the central and northern parts of the North Sea are fully mixed
during winter, but as the sun heats up the surface water in spring and summer,
stratification develops with heavy cold water at the bottom and warmer light water
in the surface. The stratification stops nutrient exchange between the layers. In the
autumn, the stratification is destroyed and the water column is remixed by water
movement induced by heavy winds.
In some parts of the North Sea frontal zones are created between water masses with
different temperatures, salinities or nutrient concentrations. Frontal zones are
created by tidal movement, wind or differences in salinity which create upward
movement of high nutrient bottom water. There is a relatively high biological
ESIA OF ADDA AND TYRA N DEVELOPMENT 9/19
production in and around the frontal zones due to the increased access to nutrients
and they are thus important nursing grounds for fish and feeding areas for birds.
The project area is more than 100 km from the nearest typical frontal zone areas
and is characterized by a low biological productivity.
Figure 7-1 Areas with potential frontal zones.
Phytoplankton is an essential part of marine ecosystems in which the main part of
the primary production takes place. Plankton consists of pelagic phyto- and
zooplankton, varying in size from microscopic algae to millimeter sized fish larvae.
Plankton flows passively with sea currents. Some zooplankton species spend their
whole life cycle suspended in the water masses (holoplankton) and some are only
pelagic in the first larval stages of their life cycle (meroplankton). The latter may
be species of fish, sea stars, sea urchins, bristle worms, mussels, crabs, shrimps and
lobsters all of which possess a pelagic larval stage.
The phytoplankton of the North Sea and in the project area is dominated by
diatoms and dinoflagellates, their growth cycle is governed by stratification. There
is a spring bloom, while the water is still mixed and nutrients are available, but
when the water column is stratified, nutrients are quickly depleted in the surface
water where the light can penetrate. That causes a decline in phytoplankton
biomass. A smaller bloom can occur during autumn, when the water masses are
remixed and fresh nutrient rich water comes to the surface.
The zooplankton in the North Sea is dominated by copepods, which are found in
large numbers and are a food source for fish and other organisms including larvae
and adults of commercially important fish species such as herring and sprat. The
average water temperature of the North Sea is increasing and there are indications
10/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
of a shift in the composition of copepod species, which is coupled to the increase in
temperature. Smaller species from warmer waters migrate into the North Sea and
drive out the established species, which may in turn lead to decreases in the fish
species who feed on the established copepods.
Benthic fauna in the North Sea consists of a wide range of invertebrates such as
bristle worms, mussels, snails and crustaceans. The animals can be separated
according to their choice of habitat. The composition of benthic fauna in an area is
a result of complicated interactions between factors, including type of sediment,
oxygen conditions, sea currents, stratification, salinity, hazardous substances etc. In
the North Sea it is primarily the salinity and temperature of the bottom water
together with tidal patterns, which affect the composition and abundance of the
benthic community. The tolerance and preferences of the different species to the
mentioned factors varies at the same time as biological factors like predation,
competition for space and food and parasitism influence the composition. The
dominating species of benthic fauna in the project area are the crustacean
Bathyporeia elegans and the bristle worms Spiophanes bombyx and Chaeotozone
setosa.
The amount of bottom dwelling fish around the project area is relatively smaller
than in other parts of the North Sea. It is dominated by dab, grey gurnard, whiting
and sand eel. Herring, sprat and mackerel are the dominating pelagic species.
Dab is the most common flounder in the North Sea. Dab spawns from January to
September, with the main activity taking place from February to April. The largest
amount of eggs are found in the German Bight, north of the Frisian Islands and
along the southern part of Dogger Bank and off Flamborough Head. The project
area does not represent an important spawning area for Dab. Grey gurnard is also a
common bottom fish in the North Sea, but it is mostly caught as by-catch and is not
important for the fishing industry. In winter Grey gurnard is found in deep water in
the central North Sea and it migrates to the southeastern North Sea in spring to
spawn. Grey gurnard spawns in the project area. Whiting is common in large
numbers all over the North Sea, except at Dogger Bank and it is caught by
commercial fishermen. It spawns its pelagic eggs over longer periods starting in
January in the southern North Sea and in July in the northern North Sea. Whiting
spawns around the project area.
Herring is the dominating fish species in the water masses of the North Sea, both in
numbers and in economic value. Herring is found in large shoals close to the
bottom during the day and in the night it migrates to surface water to feed on
zooplankton, which is its primary food source. The species spawn their eggs on the
seabed where they adhere to rocks, stones and sand. Several herring stocks are
found in the North Sea, which spawn in different areas in different periods. The
largest stocks are the Bucanan, Dogger and Downs, all of which are far away from
the project area. Haddock is found primarily in the northern North Sea with a
southern border from northeastern England, along Dogger Bank to Skagerrak and
the inner Danish waters. Haddock spawns in deep water in the northern North Sea
and is a valuable fish caught together with cod and whiting. Sprat is a small pelagic
schooling fish, mostly found in shallow water and which is an important food item
for larger fish and is also caught for industrial purposes. Sprat is most common
south of Dogger Bank and in the Danish inner waters, but can also be found around
ESIA OF ADDA AND TYRA N DEVELOPMENT 11/19
the project area. It spawns its pelagic eggs several times during spring and summer,
but mainly in May-June.
Besides dab, whiting and grey gurnard, the fish species which spawn around the
Adda field include cod, plaice, long rough dab and mackerel. The spawning
periods of the relevant fish species are summarized in Figure 7-2.
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
Cod
Whiting
Dab
Plaice
Long rough
dab
Grey gurnard
Mackerel
Figure 7-2 Spawning periods of the fish species, which spawn in the project area.
The North Sea is important for millions of sea birds, which find their food in the
area during migration or breed in coastal colonies. Sea birds normally find food in
shallow areas connected to banks and in areas of high biological productivity far
from the project area, such as Dogger Bank to the southwest and Little Fish Bank
and Skagerrak to the northeast (Figure 7-3). The average depth in the project area
is relatively deep at ca. 40 m and thus does not represent an important area for
seabirds. The area is visited by fulmar and kittiwake, gannets and guillemots. The
eastern part of the German Bight is the closest important bird area, where red- and
grey-throated divers, red-necked grebe, common scooter, little gull, common gull
and sandwich tern can be found.
Figure 7-3 Location of internationally important open sea areas for sea birds and coastal
areas important for birds.
12/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
Harbor porpoise, white-beaked dolphin and minke whale are the only species
which are regularly seen in the western part of the Danish sector of the North Sea
including the project area. Harbor porpoise is the most common whale species in
the North Sea with approximately 340,000 individuals. Most of the animals in
Danish waters are found in the inner Danish waters, Skagerrak and the waters off
Blåvandshuk. Harbor porpoise is also found in smaller numbers in the central
North Sea and in considerable numbers southwest of the project area close to
Dogger Bank. White-beaked dolphin is common in the western North Sea, but in
smaller numbers than Harbor porpoise. In Danish waters it is mainly seen in
Skagerrak, the northern part of the Danish sector of the North Sea and parts of the
central North Sea. The total population consists of approximately 8,000
individuals. Minke whale is the only baleen whale which is regularly seen in the
North Sea, and the total population number is estimated to approximately 8,500.
Harbor seals are observed in the Danish sector of the central North Sea. Harbor
seal lies mainly in coastal areas where they stay in remote and isolated areas and
seldom move further than 20 km away from the coast. Grey seal are also observed
in the Danish sector of the central North Sea. Grey seals feed primarily on fish like
sand eel, cod, whiting and flounders as well as herring and rays. The species breed
in several places along the English east coast and in the German Bight near Sylt,
Amrum and on Helgoland. Studies have shown that grey seals from British
colonies move far out in the North Sea, but are rarely observed in the Danish part
of the North Sea.
The most important commercial activities in the central North Sea are the oil and
gas production together with commercial fishing. The project area has some
importance for the Danish trawl fishery of sand eel, which goes on in April – July.
Fishing of plaice, cod and sprat is also taking place. The project area is of less
importance to fishing from other countries.
Figure 7-4 Harbor porpoises (mother and calf) close to Tyra East platform in May 2014.
Photo: Torsten Radberg.
ESIA OF ADDA AND TYRA N DEVELOPMENT 13/19
8 Environmental impacts during construction
The development of the Adda and Tyra LC fields may potentially affect the
environment through discharges to the sea during drilling, cementing and
completion of wells and testing of pipelines. Activities related to laying down
pipelines may affect the seabed. Noise will be generated above and under water
during the construction and the areas will be lit up by artificial light. Furthermore,
emissions will arise from energy consumption and transport activities.
8.1 Discharges during drilling
The environmental impacts from planned discharges from drilling activity will be
limitedto the drilling period (about 120 days per well). The environmental impact
from discharges of mud and cuttings on water quality, plankton and fish is assessed
to be minor whereas it is assessed to have a moderate impact on benthic fauna. The
environmental impact from discharge of drilling chemicals on the water quality,
plankton and fish is assessed to be minor.
8.2 Emissions
The main part of project related emissions will occur in connection with drilling
and well testing which are going to be spread over several years. It will take place
in open sea where gases are emitted far away from populated areas and will be
dispersed rapidly. The emission of CO₂ during construction of the project equals
approximately 2% of the total emission by Maersk Oil activities in the North Sea
during 2013 and emission of other gasses (NOx, SOx, CH4 and nmVOC) equals
between 0.03 and 76% of the 2013 emissions by Maersk Oil activities. The
environmental impact of construction related emissions is assessed to be moderate.
8.3 Laying of pipelines
The environmental impacts of laying down 11.6 km pipeline from the Adda
platform to Tyra East via Tyra N will be limited to the trenched area and a 10-20 m
wide belt on each side. It is expected that benthic fauna will return to the area
within 0.5- 2 years after operations are terminated. The environmental impact of
pipeline laying on the benthic fauna is assessed to be minor.
8.4 Noise and Light
The most significant impact of noise is expected when ramming takes place before
a well is drilled of the platforms will be installed. These operations are planned to
last about 6-8 hours each. Marine mammals (harbor porpoise, whales, dolphins and
seals) will escape from a 20 km area from the area during rammin but are expected
to return when ramming operations are completed. There is a risk of hearing
damage to whales and sealsif there are found within 100 m of rammingHowever,
the risk is mitigated by applying a “soft start” procedure for which the ramming is
initiated with progressively increasing noise levels. Some marine mammals use
echolocation for navigation, but it is expected that they will not be affected by the
noise more than 1 km from the drilling rig. Under water noise from ships in the
14/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
area will only marginally affect fish and marine mammals.
Light may attract migrating birds at night, causing them to lose temporarily their
orientation and circling the rig. The environmental impact of noise and light to fish,
marine mammals and birds is assessed to be minor. Other animals are not expected
to be affected.
9 Environmental impacts during operation
Production operation may impact the environment through emissions and
discharges of produced water to the sea at Tyra East. The physical presence of the
platforms can have an impact and any noise and light generation during operation
can affect the environment. Finally, a potential impact can arise from ship
collisions with the platforms.
9.1 Discharges of production water
The risk of impact caused by discharged of produced water is based on computer
simulations which predict thee fate of the chemicals discharged with the produced
water based on the ir toxicity and persistence in the water. The risk assessment
concludes that the total amount of discharged produced water from Tyra East
including the amounts generated from the production at Adda and Tyra N may
affect the environment within a maximum distance of 13.6 km in a northeast
direction covering an area of 14 x 5 km. The environmental impact of the discharge
of produced water on water quality, plankton, fish and benthic fauna is assessed to
be minor.
9.2 Emissions
Production related emissions are primarily from generators and compressors on
Tyra East. It will take place in open sea where gases are emitted far away from
populated areas and will be dispersed rapidly. Emissions will vary considerably
during the project lifetime with an expected peak at year 6. The production will
produce a total annual emission of CO₂ equal to approximately 3% of the total
yearly emission in 2013 by all Maersk Oil facilities in the Danish North Sea. The
environmental impact of production related emissions is assessed to be moderate.
9.3 Physical presence of the platform
The physical presence of the platforms may affect the environment by occupying
small areas of the seabed, which will no longer be available for benthic fauna. The
platform legs may, however, act as artificial reefs covered by sessile animals and
attract fish and possibly harbor porpoise. The platform topsides may act as resting
place for migrating birds. The environmental impact of the presence of the
platforms on bottom animals is assessed to be minor.
9.4 Noise and Light
No significant noise will be generated from the platforms during operation and
lighting is reduced to navigational lights. Therefore, no impact is expected from
noise and light during operation.
ESIA OF ADDA AND TYRA N DEVELOPMENT 15/19
9.5 Ship collision
The risk of collisions is assessed to be minimal as the platforms are placed away
from major traffic routes and are secured by navigational lights and surveillance.
10 Environmental impacts from decommissioning
The decommissioning of equipment and facilities is regulated by Danish law and
international conventions. The regulation sets the framework for handling
platforms, pipelines and other equipment. The project has an expected lifetime of
27 years after which it is expected that the platforms will be dismantled and the
parts transported ashore for reuse or recycling whereas the wells will be emptied
and closed with cement and pipelines emptied of oil and gas and cleaned. Buried
parts of the platforms and pipelines may remain in place. The decommissioning of
the equipment and facilities will follow legislation in force at the time of
decommissioning.
11 Environmental impacts from unplanned events
Unplanned events during construction and operation of the project which may lead
to environmental impacts have also been assessed. Unplanned events may include
oil and gas spills from blow-outs or pipeline ruptures where large or small amounts
of oil or gas are released to the environment. Such events are extremely rare, and
comprehensive technical measures are in place on the platforms to prevent and
control a blow-out event.
11.1 Blow out events
Based on statistical information, the probability of a blow-out during drilling is
extremely unlikely.
In a gas blow-out the environmental impacts are limited to a relatively small area
where the gas will rise to the surface and pose a risk to rig crews, platforms or
vessels and a high risk of fire and explosions. The environmental impact of a gas
blow-out at Adda or Tyra N is assessed to be moderate on air and water quality,
benthic fauna and fish.
The environmental impact assessment of an oil spill from a blow-out at Adda or
Tyra N is based on the worst case scenario. The oil spill model simulation takes
into account the oil type, spilled amounts, weather conditions together with
information of the fate of oil in seawater and its toxicity to animals and habitats in
the North Sea.
The environmental impact assessment from the oil in the water column or at the
water surface on water quality, plankton, fish and marine mammals is assessed to
be moderate whereas it is assessed to be significant for birds. It is further estimated
that up to ca. 30% of the oil may reach the sea bottom. The environmental impact
of the oil on the benthic fauna, including protected areas in German waters
southwest is assessed to be moderate.
16/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
There is a relatively high probability of the oil ending up on the coast of northern
Jutland. It is estimated that the oil may reach the coastline from Thy to Nissum
Fjord within a minimum of 5 days. The socio-economic impact of an oil spill on
tourism and fisheries is assessed to be minor. There is a relatively small probability
of oil reaching the Norwegian south coast with vulnerable areas of protected rocky
shores and also the Wadden Sea along the Danish, German and Dutch coasts. It
will take more than 28 days for the oil to reach these shores. After being in the
water for such a long time the oil will be weathered to form less degradable, less
toxic and non-adhesive tar balls.
The above assessment is based on the situation where no oil spill response is in
place. Maersk Oil has oil spill response equipment placed in Esbjerg dimensioned
to an oil spill of approximately 5,000 m³ per day in reasonable weather conditions.
The equipment can be mobilized immediately. If necessary, additional equipment
will be mobilised from Oil Spill Response Ltd (OSR) in Stavanger (Norway) or
Southampton (UK). Additional equipment such as floating booms, skimmers and
dispersants etc. can be mobilized from these sources on a short notice.
In summary, it is assessed that a gas or an oil blow-out events at Adda or Tyra N
may cause a significant impact on the environment, but due to their extremely low
probability the environmental risk is low.
11.2 Pipeline ruptures
The risk of a spill of oil or gas in case of a pipeline rupture is unlikely. If it occurs,
the pipelines will immediately be shut down as pipeline pressure is constantly
monitored from Tyra East.
11.3 Other spills
The platforms are unmanned and are supplied with chemicals through the pipeline,
and no chemicals are transported by ship, which makes the risk of a chemical spill
unlikely.
12 Impacts on protected areas (Nature 2000 screening)
Southwest of the Adda and Tyra LC fields is a German protected area covering
Dogger Bank. As an extension of that, a Dutch protected area stretches further
southwest. In the two areas the habitat type 1110 Sandbanks which are slightly
covered by sea water all the time and the two species 1351 Harbour porpoise and
1365 Harbour seal are listed in the basis for the designation. In the Dutch area,
1364 Grey seal is also listed in the basis for the designation.
Other protected areas in the North Sea include far away areas along the Danish and
German coastlines (Figure 12-1).
There are no planned discharges to the sea in relation to this project which are
expected to impact the German and Dutch Natura 2000 protected areas.
ESIA OF ADDA AND TYRA N DEVELOPMENT 17/19
Figur 12-1 Protected areas in the North Sea.
Harbour porpoise and seals in the northeastern part of the Natura 2000 German
Dogger Bank areas might escape during ramming periods, however, it is expected
that they will return to the areas when ramming operations have been completed.
Modeling of the oil spill from the extremely unlikely event of a blow-out shows a
low risk of impact on the German and Dutch Natura 2000 areas. It cannot be ruled
out that the oil which might reach the areas would sink to the bottom and thereby
impact the protected habitats. However, it is expected that the environmental
impacts will be moderate and will not affect the capability of the areas to maintain
or reach a good preservation status. This is based on studies from other major oil
spills where bottom animals in similar areas were not significantly affected and/or
because oil is quickly degraded and the benthic fauna reestablish themselves fast in
the affected areas. The risk of impacts from a spill in other Natura 2000 protected
areas is extremely unlikely.
13 Socio-economic assessment
The ESIA contains an assessment of the derived socio-economic consequences of
the environmental impacts from the project. Focus has been on significant
economic consequences for people and businesses in the local area, which is
limited to the west coast of Jutland. In the analysis, two environmental impacts
with strong economic consequences have been studied: exclusion zones for
fisheries and oil spills from blow-outs. Both parameters may influence income
from fisheries and tourism. The socio-economic impact from exclusion zones
around platforms and pipelines is assessed to be insignificant. The socio-economic
impact from an oil spill on the fisheries and tourism is assessed to be minor. Project
related emissions on the physical condition of people or the income from fisheries
are assessed to be insignificant.
18/19 ESIA OF ADDA AND TYRA N DEVELOPMENT
14 Cumulative impacts
Cumulative impacts are combined impacts from more than one project or ongoing
activities in a certain area over time. Relevant potential cumulative impacts in
relation to the development of the Adda and Tyra LC fields include mutual impacts
from this project with activities in other oil and gas fields as well as interactions
with other activities in the area such as fishing and shipping. The platforms i Adda
and Tyra N are located at least 5 km from the nearest platforms. Other temporary
impacts during construction such as noise and chemical discharges may affect the
environment in a larger radius from the platforms, but no activities with potential
long reaching impacts (>2 km) are planned to the closest platforms during the
project period. There are no cumulative impacts from discharges of process water
or emissions on Tyra East. Other studies have shown that the Adda and Tyra N lies
in an area of medium risk of causing cumulative impacts on other activities.
15 Transboundary impacts
The distance from the Adda and Tyra N to the German border is about 25 km.
Noise during the construction is the only planned activity which may reach across
that distance and its potential impact will be limited to the time necessary to
ramming (less than 8 hours per well). Other transboundary impacts are limited to
unplanned oil spill events where areas in Germany, Holland and Norway may
potentially be affected (se section 11).
16 Mitigating measures
Maersk Oil implemented an ISO 14001 standardized environmental management
system in 2010. Through that system, work is continuously being done to eliminate
or minimize emissions, discharges of oil or chemicals and the amount of waste
from exploration and production activities in the Danish sector of the North Sea.
Furthermore, Maersk Oil uses BAT (Best Available Technique) and BEP (Best
Environmental Practices) to the widest possible extent in order to minimize
environmental impacts.
Specific measures related to this project include the ongoing work of reducing
discharges, and in relation to noise during ramming, a 'soft start' procedure will be
used. Finally, Maersk Oil has an oil spill response set-up with equipment available
in Esbjerg and additional equipment will be mobilised from Oil Spill Response Ltd
(OSR). Additional equipment such as floating booms, skimmers and dispersants
etc. can be mobilized from these sources on a short notice. The OSR equipment is
primarily located in Southampton, England, but additional equipment is available
in Stavanger, Norway.
Furthermore, a series of efforts is implemented to mitigate and prevent pipeline
rupture and spills of oil and gas. They include i) corrosion protection of pipelines,
ii) routine surveillance of pipelines, iii) implementation of a 200 m safety zone
around pipelines to prevent bottom trawling equipment or anchoring to cause a
rupture and iv) installation of pressure alarms, which register potential ruptures and
forces immediate closure of pipelines from the platforms.
ESIA OF ADDA AND TYRA N DEVELOPMENT 19/19
Figur 16-1 Overview of Maersk Oil’s approach to decrease its impact on the environment.