Upload
bada-sainath
View
1
Download
0
Embed Size (px)
Citation preview
*
*Enterprise GIS for Distribution ManagementLoss ReductionReliability improvementWorkflowCapital Budgeting
GIS for Distribution Loss ReductionExpectations of Power UtilityImprove revenue by improving ENS ( Energy Not Served). Improve performance by improving SAIFI, SAIDI.Improving Customer Complaints logs in Trouble Call Management.Long-standing faults brought to a minimum.Limiting number of interruption per day a) Breakdown b) Preventive Maintenance c) Load-shedding.
GIS for Distribution Loss ReductionGood collection & billing System.To reduce Outage Time.To stop Power theft.To provide better services to the consumers.To have stabilized Asset Management System.Safety- Zero fatality rate.Expectations of Power Utility
GIS for Distribution Loss ReductionEnterprise wide Geographical Information System (GIS) in RELEnterprise Data Management GIS PlatformSeeing is believing !!!!!!! We have seen it
GIS for Distribution Loss Reduction
BusinessSupport
Transmission/DistributionWMS/Staking/IVRArcGIS(Core GIS Functions)CustomerCare (CIS)OpenRDBMSArcFM Solution(Models and Tools for Mapping and Network Data Management)System Architecture
GIS for Distribution Loss ReductionSystem Architecture
Title
`
GIS for Distribution Loss ReductionNeed for GIS Impressive progress in power sector, but still insufficient.
Demand Widening gap between demand and supply due to T& D losses amounting to 25% in the Supply distribution link.
Target T & D loss Reduction Solution 1) Implementation of GIS modules 2) Distribution management thru GISThe estimated T&D losses for the fiscal 04-05 for BRPL and BYPL, Delhi
LossesBYPLBRPLAT&C Loss %50.7139.68Distribution Loss %48.1142.7No. of Consumers8360001070000
GIS for Distribution Loss ReductionEstimates of Implementing GIS at DelhiInitiatives taken by GIS group established at Central Technical Services of the company are as follows -
Development of Functional Requirements and Data Model. Updating of Reliance Corporate Land base Maps. Capturing the entire EHV/HV network. Capturing the entire LV network. Capturing Consumer Information. In House Digitization and field QC. Consultancy Services by REL
GIS for Distribution Loss ReductionUpdating of Reliance Corporate LAND base Maps Integrated large scale corporate land base map prepared based on RICs data requirements with base data as IKONOS imagery imported from Space Imaging. IKONOS imagery digitized by RDWL team through network of digitization vendors. Maps supplemented with field survey information conducted by contractors identified by RDWL.
Flaw in above system Information updated by RDWL was insufficient for locating Electrical network and individual Consumer Service points.
Solution * Updating of all buildings with service line feeding * Including all new transport features including road, railway, flyovers.
Codification Guidelines of RDWL Providing unique id to all building for its identification. Linking it with its consumer/service line.Cost Estimates for Land base and Updating
UnitUnit CostQty.Total Cost (Mn) Cost Per ConsumerLand BaseSq Km20,000900189.44Land Base UpdatingPolygons81,000,00084.2
GIS for Distribution Loss ReductionDevelopment of Functional Requirements and Data Models ESRI / M&M appointed as GIS service providers by REL ( on behalf of BRPL and BYPL ) for - studying existing system. - developing functional requirement for proposed GIS. GIS Tools * COTS available platforms from ESRI. * Third party applications from Miner and Miner. * Customer Applications for GIS interfaces for integration with other applications - SAP (ISU-CCS for Consumer Information). - SAP (PM) for Operations and Maintenance. - Cymedist Interface for Network Analysis. - GIS Interface for SCADA system.Development of tool based on functional requirement and application design document approved by REL for ESRI / M&M Testing and approval for implementation at cluster citrix application servers at DAKC.Applications made available for access from anywhere in the Reliance Network including both the DISCOMS in Delhi.
GIS for Distribution Loss ReductionCapturing Entire EHV/HV Network Phase 1The GIS data dictionary included the entire network of EHV and HV. EHV Grid Stations and their equipments. 11/0.44 kv substations and their equipments. 66.33 and 11 kv feeders. Survey agencies identified for capturing EHV/HV networks.Digitization of captured data using in-house digitization tools developed by RDWL and RELDigitized data migrated to REL Corporate electric data base server at DAKC.Database made accessible through ESRI COTS and customer application from anywhere in Reliance WAN including both DISCOMS in Delhi. Cost Estimates for EHV / HV Data Collection
UnitUnit CostQty.Total Cost (Mn) Cost Per Consumer33/66 KV ConductorKm33/66 KV CablesKm6504760.30940.1611 KV ConductorKm11 KV CablesKm6501,4410.93670.49EHV StationNos2,5001240.310.16HV StationsNos5008,00042.1
GIS for Distribution Loss Reduction Capturing the entire LV NetworkPhase 2Capturing LV network
Features captured Consumer Feeding Points * LV Support Structures * LV Feeder Pillars * Street Light Structures LV Feeder Network (0.44 kv ) connectivity
Consumer Feeding Structure points codified with unique codes for linking them with respective set of consumers.This would enable linking of every consumer with its feeding point & 11/440 v substation, required for energy audit, NA, O&M and other applications. Cost Estimates for LV Data Collection
UnitUnit CostQty.Total Cost (Mn) Cost Per ConsumerFeeder Pillars/Support StructuresSS8800,00063.36
GIS for Distribution Loss Reduction In-House Digitization and Field QCData being captured is governed with stringent QA requirements based on feature being capturedTeam deputed for carrying out QC who conducts field checks before accepting data for digitizationData is then handed over to digitization team where digitization is done using industry standard CAD/GIS packages.
GIS for Distribution Loss ReductionCapturing Consumer InformationNon-availability of accurate consumer records had been one of the main reasons for commercial losses.
GIS based consumer indexing has been carried out by many DISCOMS / SEBs, without much of a fruitful result.
At BSES, Delhi it is at a conceptual; stage and different models are being evaluated for collecting consumer information
The consumer data being collected will be integrated with its building id for its spatial location and network connectivity with its feeding structure id in GIS. Cost Estimates for Consumer Data Collection
UnitUnit CostQty.Total Cost (Mn) Cost Per ConsumerConsumersConsumer71,906,000137
GIS for Distribution Loss ReductionSkeleton of GISSCADANOCISSAPOMS CISDATA
GIS for Distribution Loss ReductionINTEGRATION AS A CONCEPT
GIS for Distribution Loss ReductionUse work process flows to define touchpoints of integration to support business processesUse enterprise and process modeling to describe how data and components service the needed business processesShared data doubles the accuracy and quality requirementslook at the data from each systems perspective (financial vs. operations)
INTEGRATION AS A CONCEPTWhen Should Integration be Considered?Data/applications exist in many placesMerger/acquisition of requirementsSupporting thousands of users with many different requirementsScalability
Why integration?Benefits of IntegrationReduces cost of connecting components and adding/changing components.Adds value to business processesEnforces process consistencyData Consistency
Metrics -- Measuring Integration SuccessCustomized for the organizationTie Benefits and MetricsCustomer service measurements related to more up-to-date informationHow can Integrationincrease revenue?improve customer service?give more information about our business?
GIS for Distribution Loss ReductionHigh Tension NetworkSCADASAPNotification &WorkorderIntegration with Other Applications
GIS for Distribution Loss Reduction
GIS for Distribution Loss ReductionNetwork AnalysisConsumerInformationSystem(CIS)SCADA-DMSSAPEnterprise Wide Integrated GIS.OMS- ResponderCustom Tools( Energy Audit Scheduler et al.)
GIS for Distribution Loss ReductionElectric Network Trace
*LT NETWORKService LineService Point
*SLD WITH REF-ID
*SUPPORT STRUCTURE WITH ATTRIBUTES
*CONSUMER DATA
GIS for Distribution Loss Reduction Consultancy Services by RELIt is proposed that REL will be appointed as technical consultant to BRPL and BYPL and carry out management services including
Survey and digitization Procurement and contracting Contract management and monitoring QA and QC Hardware and Software Application testing Migration and hosting services for application and database at DAKC
GIS for Distribution Loss Reduction Load growth planning Using Geo-referenced data
GIS for Distribution Loss Reduction Distribution Management thru integrated GIS Load Calibration (LC), Load Flow Calculation (LFC) Switching Orders based on minimum Loss path Static spatial connection and dynamic behavior of organizational model & equipment model Switch and switch status telemetry superimposed with cable/conductor type & length Electrical parameters (R, X, B, G ) derived there from to give loss data and options Voltage profiling with load data superimposed on above Power quality and THD Distance relay zones superimposed on map to give nearest fault location Fault Isolation and switching restoration options
GIS for Distribution Loss ReductionEstimated Benefits of GIS As per estimation, GIS will benefit by decreasing both Commercial and Technical losses. Based on assumption for 0.5%, 1.5% and 2.5% increase in MU billed for the first, second and third year respectively by reduction of losses and better O & M.
Benefits after GIS Implementation Note: From the table, increase in revenues with prevailing tariff is 175mn, 265Mn and 450Mn respectively for three years.
Pre GIS ImplementationPost GIS ImplementationBYPL MUBRPL MUTotalApprox TariffI Yr. (1.0% Incr MU)Approx. Increase in RevenueII Yr. (1.5% Incr MU)Approx. Increase in RevenueIII Yr. (2.5% Incr MU)Approx. Increase in RevenueDomestic159128014392243.9287.8466.54133.08112.56225.12Commercial5807401320413.252.82079.9933.83135.32Industrial27240667846.7827.1210.2741.0917.3869.51Agriculture1666710.670.341.020.511.720.86Bulk36811001468114.687.3422.2411.1237.6218.81Total Units Billed 28125113792579.25175.44120.06265.78203.11449.62
GIS for Distribution Loss Reduction
List of Engg Departments
Centralised Departments
1RECEIVING STATION MAINTENANCE
2RECEIVING STATION CONSTRUCTION
3SYSTEM CONTROL & OPERATIONS
4PLANNING
5TESTING & PROTECTION
6H. T. METERING
7LTP II & III METERING
8RESEARCH & DEVELOPMENT
Zonal Engineering Departments
1HT MAINTENANCE
2CABLE SAFEGUARDING
3LT MAINTENANCE
4ST. LT. MAINTENANCE
5HT CONSTRUCTION
6LT CONSTRUCTION
7ST. LT. CONSTRUCTION
8SERVICES
9
Zonal Commercial Departments
PROGRESS
I & C : Bill Distribution & Consumer Enquiries
RECOVERY
HT Maintenance Dept
Sr. NoActivitiesDescription of activityHow GIS can help
1Maintenance of 33 kV, 22 kV and 11 KV cables in the systemInformation of the 33KV or 22 kV feeder tripping is conveyed to the zonal engineering deptThe affected are can be viewed on the GIS, so that the cusomers may be informed accordingly.
Arrangements are made for the necessary load transfer operations as per the directions of the Load Cella) Locating a Substation during an emergency, for carrying out Switchover operationsb) Determining the shortest route between two substations or any two facilities
Staff is deputed along with personnel of Testing Dept. to pinpoint the location of faultKnowledge of existing joints on the cable and the topology of the area beforehand
Excavation is arranged for exposing the fault after issuing necessary intimations to concerned local authorities.Generation of Intimation letters to appropriate BMC Ward, with drawings of the portion to be excavated
After exposure, the fault is ascertained, the cable identified and punctured. If fault is not discernible, re-testing is requestedThe number of cables lain along the same route can be verified. The correct cable can then be exposed.
Cable jointing arranged and intimation given to drawing dept. regarding the same.a) Joint details can be updated on to the GIS directlyb) All attribute details, viz jointing date, jointers name, type of joint etc can be attached to the joint
On completion of jointing and refilling of excavated area, pressure testing of the cable is carried outKeeping track of whether the excavated area has been reinstated
After successful pressure test, message for charging the cable is given. System normalising operations carried out as per Load CellOther faults/ disturbances/ abnormalities in the vicinity of this area can be checked
System normalising operations carried out as per Load Cell.Keeping track of affected areas, on the GIS map
2Maintenance of 11 kV/ 430V substationsPreventive Maintenance
a)Area-wise peak load period can be displayed on the GISb) An automatic schedule for load reading & Inspection can be generated keeping into account the shortest travel time for the maintenance crew
a) The GIS can provide updated graphical information on where the outages have been takenb) Line clear cards can be automatically generated and ven mailed to the consumer in advancec) The BDV of the Oil can be attached as an attribute data to the Transf
Same as above
3Proposing improvements in networkThese proposals are for improvement of supply conditions in the area and include: 1) Reinforcement of H.T.U.G. Cable ( i.e. replacement of existing cable with higher size cable)2) Change / addition of switch-gear3) Change / addition of L.T. Panel4) Ina)Detailed interior layout of the Substation is available instantlyb) Approach roads and possible shorted cable routes can be identified.c) Automatic generation of Bill of Material/ Cost Estimatesd) Displaying areas requiring improvements based on load
4Miscellaneous worksR Jobs
These are request jobs executed at the behest of consumers, other utilities or the local authorities or repair works carried out to rectify damages on our cables as a result of works carried out by the party. Estimates for the same are prepared and forwara) Generating Estimates for execution of the Jobb) Locating the area of interest
Safeguarding
Cable Safeguarding
Sr. NoActivitiesDescription of activityHow GIS can help
1Prevention of damages to HT / LT cablesThe section sends out staff on routine area inspection routes and concentrates on locations where excavation activities of other utilities is in progress. It also co-ordinates with the local authorities regarding their proposed works which are likely to d
2Intimating local authorities regarding BSES excavationsThe section intimates the local authority the excavations being proposed by the zone and also requests the local authority to reinstate the excavations on completion of the jobs.
LT Maintenance
LT Maintenance Department
Sr. NoActivitiesDescription of activityHow GIS can help
1Attending NO SUPPLY complaints.Consumer NO SUPPLY complaints are received and recorded at the Receiving Stations ( called as COMPLAINT CENTRES).
The complaint is then passed over to the district for rectification. A district is manned by one / two linesman gangs on 8 hrs. shifts throughout the day and are provided with cycles / motorcycles for mobility.
On rectification of a complaint, an acknowledgement in the form of a signature of the consumer is taken as a token of satisfactory attendance of the complaint
In case of fault, the linesman isolates the fault, restores supply as far as possible and informs the details to the Controlling Station to make appropriate arrangements to attend the fault.
If the meter of the consumer is found faulty, a request for providing direct supply to single-phase residential and water-supply meters is available in the form of a request letter which is pre-printed on the reverse of the complaint form. In other cases,
The linesman reports back to the Complaint Centre the details of the complaint and the rectification work done.
Complaint centres are provided with E-mail facility which enables the zonal office to retrieve complaint data for MIS analysis.
2Maintenance of LT network
3Proposing improvements in LT network
4Follow-up in Electrical AccidentsInformation regarding the occurrence of an electrical accident is received from consumers, the police station or from our staff.The site is inspected and if the accident pertains to a individual consumer, the supply to the consumer is disconnected. If it
5Miscellaneous works.These are request jobs executed at the behest of consumers, other utilities and local authorities or repair works carried out to rectify damages on our cables as a result of works carried out by an external agency. Estimates for the same are prepared and
GIS for Distribution Loss Reduction
List of Engg Departments
Centralised Departments
1RECEIVING STATION MAINTENANCE
2RECEIVING STATION CONSTRUCTION
3SYSTEM CONTROL & OPERATIONS
4PLANNING
5TESTING & PROTECTION
6H. T. METERING
7LTP II & III METERING
8RESEARCH & DEVELOPMENT
Zonal Engineering Departments
1HT MAINTENANCE
2CABLE SAFEGUARDING
3LT MAINTENANCE
4ST. LT. MAINTENANCE
5HT CONSTRUCTION
6LT CONSTRUCTION
7ST. LT. CONSTRUCTION
8SERVICES
9
Zonal Commercial Departments
PROGRESS
I & C : Bill Distribution & Consumer Enquiries
RECOVERY
HT Maintenance Dept
Sr. NoActivitiesDescription of activityHow GIS can help
1Maintenance of 33 kV, 22 kV and 11 KV cables in the systemInformation of the 33KV or 22 kV feeder tripping is conveyed to the zonal engineering deptThe affected are can be viewed on the GIS, so that the cusomers may be informed accordingly.
Arrangements are made for the necessary load transfer operations as per the directions of the Load Cella) Locating a Substation during an emergency, for carrying out Switchover operationsb) Determining the shortest route between two substations or any two facilities
Staff is deputed along with personnel of Testing Dept. to pinpoint the location of faultKnowledge of existing joints on the cable and the topology of the area beforehand
Excavation is arranged for exposing the fault after issuing necessary intimations to concerned local authorities.Generation of Intimation letters to appropriate BMC Ward, with drawings of the portion to be excavated
After exposure, the fault is ascertained, the cable identified and punctured. If fault is not discernible, re-testing is requestedThe number of cables lain along the same route can be verified. The correct cable can then be exposed.
Cable jointing arranged and intimation given to drawing dept. regarding the same.a) Joint details can be updated on to the GIS directlyb) All attribute details, viz jointing date, jointers name, type of joint etc can be attached to the joint
On completion of jointing and refilling of excavated area, pressure testing of the cable is carried outKeeping track of whether the excavated area has been reinstated
After successful pressure test, message for charging the cable is given. System normalising operations carried out as per Load CellOther faults/ disturbances/ abnormalities in the vicinity of this area can be checked
System normalising operations carried out as per Load Cell.Keeping track of affected areas, on the GIS map
2Maintenance of 11 kV/ 430V substationsPreventive Maintenance
a)Area-wise peak load period can be displayed on the GISb) An automatic schedule for load reading & Inspection can be generated keeping into account the shortest travel time for the maintenance crew
a) The GIS can provide updated graphical information on where the outages have been takenb) Line clear cards can be automatically generated and ven mailed to the consumer in advancec) The BDV of the Oil can be attached as an attribute data to the Transf
Same as above
3Proposing improvements in networkThese proposals are for improvement of supply conditions in the area and include: 1) Reinforcement of H.T.U.G. Cable ( i.e. replacement of existing cable with higher size cable)2) Change / addition of switch-gear3) Change / addition of L.T. Panel4) Ina)Detailed interior layout of the Substation is available instantlyb) Approach roads and possible shorted cable routes can be identified.c) Automatic generation of Bill of Material/ Cost Estimatesd) Displaying areas requiring improvements based on load
4Miscellaneous worksR Jobs
These are request jobs executed at the behest of consumers, other utilities or the local authorities or repair works carried out to rectify damages on our cables as a result of works carried out by the party. Estimates for the same are prepared and forwara) Generating Estimates for execution of the Jobb) Locating the area of interest
Safeguarding
Cable Safeguarding
Sr. NoActivitiesDescription of activityHow GIS can help
1Prevention of damages to HT / LT cablesThe section sends out staff on routine area inspection routes and concentrates on locations where excavation activities of other utilities is in progress. It also co-ordinates with the local authorities regarding their proposed works which are likely to d
2Intimating local authorities regarding BSES excavationsThe section intimates the local authority the excavations being proposed by the zone and also requests the local authority to reinstate the excavations on completion of the jobs.
LT Maintenance
LT Maintenance Department
Sr. NoActivitiesDescription of activityHow GIS can help
1Attending NO SUPPLY complaints.Consumer NO SUPPLY complaints are received and recorded at the Receiving Stations ( called as COMPLAINT CENTRES).
The complaint is then passed over to the district for rectification. A district is manned by one / two linesman gangs on 8 hrs. shifts throughout the day and are provided with cycles / motorcycles for mobility.
On rectification of a complaint, an acknowledgement in the form of a signature of the consumer is taken as a token of satisfactory attendance of the complaint
In case of fault, the linesman isolates the fault, restores supply as far as possible and informs the details to the Controlling Station to make appropriate arrangements to attend the fault.
If the meter of the consumer is found faulty, a request for providing direct supply to single-phase residential and water-supply meters is available in the form of a request letter which is pre-printed on the reverse of the complaint form. In other cases,
The linesman reports back to the Complaint Centre the details of the complaint and the rectification work done.
Complaint centres are provided with E-mail facility which enables the zonal office to retrieve complaint data for MIS analysis.
2Maintenance of LT network
3Proposing improvements in LT network
4Follow-up in Electrical AccidentsInformation regarding the occurrence of an electrical accident is received from consumers, the police station or from our staff.The site is inspected and if the accident pertains to a individual consumer, the supply to the consumer is disconnected. If it
5Miscellaneous works.These are request jobs executed at the behest of consumers, other utilities and local authorities or repair works carried out to rectify damages on our cables as a result of works carried out by an external agency. Estimates for the same are prepared and
GIS for Distribution Loss Reduction
List of Engg Departments
Centralised Departments
1RECEIVING STATION MAINTENANCE
2RECEIVING STATION CONSTRUCTION
3SYSTEM CONTROL & OPERATIONS
4PLANNING
5TESTING & PROTECTION
6H. T. METERING
7LTP II & III METERING
8RESEARCH & DEVELOPMENT
Zonal Engineering Departments
1HT MAINTENANCE
2CABLE SAFEGUARDING
3LT MAINTENANCE
4ST. LT. MAINTENANCE
5HT CONSTRUCTION
6LT CONSTRUCTION
7ST. LT. CONSTRUCTION
8SERVICES
9
Zonal Commercial Departments
PROGRESS
I & C : Bill Distribution & Consumer Enquiries
RECOVERY
HT Maintenance Dept
Sr. NoActivitiesDescription of activityHow GIS can help
1Maintenance of 33 kV, 22 kV and 11 KV cables in the systemInformation of the 33KV or 22 kV feeder tripping is conveyed to the zonal engineering deptThe affected are can be viewed on the GIS, so that the cusomers may be informed accordingly.
Arrangements are made for the necessary load transfer operations as per the directions of the Load Cella) Locating a Substation during an emergency, for carrying out Switchover operationsb) Determining the shortest route between two substations or any two facilities
Staff is deputed along with personnel of Testing Dept. to pinpoint the location of faultKnowledge of existing joints on the cable and the topology of the area beforehand
Excavation is arranged for exposing the fault after issuing necessary intimations to concerned local authorities.Generation of Intimation letters to appropriate BMC Ward, with drawings of the portion to be excavated
After exposure, the fault is ascertained, the cable identified and punctured. If fault is not discernible, re-testing is requestedThe number of cables lain along the same route can be verified. The correct cable can then be exposed.
Cable jointing arranged and intimation given to drawing dept. regarding the same.a) Joint details can be updated on to the GIS directlyb) All attribute details, viz jointing date, jointers name, type of joint etc can be attached to the joint
On completion of jointing and refilling of excavated area, pressure testing of the cable is carried outKeeping track of whether the excavated area has been reinstated
After successful pressure test, message for charging the cable is given. System normalising operations carried out as per Load CellOther faults/ disturbances/ abnormalities in the vicinity of this area can be checked
System normalising operations carried out as per Load Cell.Keeping track of affected areas, on the GIS map
2Maintenance of 11 kV/ 430V substationsPreventive Maintenance
a)Area-wise peak load period can be displayed on the GISb) An automatic schedule for load reading & Inspection can be generated keeping into account the shortest travel time for the maintenance crew
a) The GIS can provide updated graphical information on where the outages have been takenb) Line clear cards can be automatically generated and ven mailed to the consumer in advancec) The BDV of the Oil can be attached as an attribute data to the Transf
Same as above
3Proposing improvements in networkThese proposals are for improvement of supply conditions in the area and include: 1) Reinforcement of H.T.U.G. Cable ( i.e. replacement of existing cable with higher size cable)2) Change / addition of switch-gear3) Change / addition of L.T. Panel4) Ina)Detailed interior layout of the Substation is available instantlyb) Approach roads and possible shorted cable routes can be identified.c) Automatic generation of Bill of Material/ Cost Estimatesd) Displaying areas requiring improvements based on load
4Miscellaneous worksR Jobs
These are request jobs executed at the behest of consumers, other utilities or the local authorities or repair works carried out to rectify damages on our cables as a result of works carried out by the party. Estimates for the same are prepared and forwara) Generating Estimates for execution of the Jobb) Locating the area of interest
Safeguarding
Cable Safeguarding
Sr. NoActivitiesDescription of activityHow GIS can help
1Prevention of damages to HT / LT cablesThe section sends out staff on routine area inspection routes and concentrates on locations where excavation activities of other utilities is in progress. It also co-ordinates with the local authorities regarding their proposed works which are likely to d
2Intimating local authorities regarding BSES excavationsThe section intimates the local authority the excavations being proposed by the zone and also requests the local authority to reinstate the excavations on completion of the jobs.
LT Maintenance
LT Maintenance Department
Sr. NoActivitiesDescription of activityHow GIS can help
1Attending NO SUPPLY complaints.Consumer NO SUPPLY complaints are received and recorded at the Receiving Stations ( called as COMPLAINT CENTRES).
The complaint is then passed over to the district for rectification. A district is manned by one / two linesman gangs on 8 hrs. shifts throughout the day and are provided with cycles / motorcycles for mobility.
On rectification of a complaint, an acknowledgement in the form of a signature of the consumer is taken as a token of satisfactory attendance of the complaint
In case of fault, the linesman isolates the fault, restores supply as far as possible and informs the details to the Controlling Station to make appropriate arrangements to attend the fault.
If the meter of the consumer is found faulty, a request for providing direct supply to single-phase residential and water-supply meters is available in the form of a request letter which is pre-printed on the reverse of the complaint form. In other cases,
The linesman reports back to the Complaint Centre the details of the complaint and the rectification work done.
Complaint centres are provided with E-mail facility which enables the zonal office to retrieve complaint data for MIS analysis.
2Maintenance of LT network
3Proposing improvements in LT network
4Follow-up in Electrical AccidentsInformation regarding the occurrence of an electrical accident is received from consumers, the police station or from our staff.The site is inspected and if the accident pertains to a individual consumer, the supply to the consumer is disconnected. If it
5Miscellaneous works.These are request jobs executed at the behest of consumers, other utilities and local authorities or repair works carried out to rectify damages on our cables as a result of works carried out by an external agency. Estimates for the same are prepared and
GIS for Distribution Loss ReductionEstimating Return on InvestmentsBased on the assumptions of the benefits made, it can be seen that the project has a pay back less than one year of its implementation.From the Table it can be seen that the project not only has very less payback period, but has fabulous returns over second and third year with net cash flows as 135mn, 224mn and 424Mn with IRR as 6%, 955 and 138% for first, second and third year respectively Return on investments
CostIncrease in RevenueNet Cash FlowIRRGIS Implementation 1280-128GIS Implementation (End of I Yr)401751356%Maintenance Cost estimated as 25% Of total Implementation (Yr. II)4226622495%Maintenance Cost estimated as 15% Of total Implementation (Yr. iii)25450424138%
GIS for Distribution Loss ReductionThank You
**********************