62
NON-POTABLE WATER REUSE SYSTEMS ENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC HEALTH December 2014 WSP Flack + Kurtz

ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Embed Size (px)

Citation preview

Page 1: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

NON-POTABLE WATER REUSE SYSTEMS

ENGINEERING REPORT

PROVIDED TO THE

SAN FRANCISCO DEPARTMENT OF PUBLIC HEALTH

December 2014

WSP Flack + Kurtz

Page 2: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

December 2014

Table of Contents 1 General

1.1 Objective of the Project

1.2 Facility Information

2 Rules and Regulations

2.1 San Francisco Department of Public Health

2.2 San Francisco Public Utilities Commission

3 Producer–Distributer–User

4 Non-Potable Supply Sources, Flows, Water Quality and Characteristics

4.1 Non-Potable Supply Sources

4.2 Volumes and Flow Rates of the Non-Potable Sources

4.3 Source Water Quality Summary

5 Treatment Process

5.1 Design Basis

5.2 Process Schematic

5.3 Filtration/Ozone Treatment System

5.4 Filtration and Disinfection Systems

5.5 System Operation and Maintenance Manual

5.6 Operations Support

6 Reliability

6.1 Automated Controls System

6.2 Treatment Process Reliability

6.3 Hydraulic Control and Overflow Prevention

6.4 Supply Reliability

7 Supplemental Water Supply

8 Monitoring Reporting

9 Contingency Plan

9.1 Flow Diversion

9.2 Fail Safe Procedures in the Event of Power Failure or Natural Disaster

Procedures

10 Public Access and Impact

List of Tables Table 1 Baseline Water Quality of Raw Graywater vs. Potable

Characterization of Graywater for Title 22 Reuse Standards San

Francisco Public Utilities Commission

Table 2 Design Final Effluent Characteristics

Table 3 System Component Capacity Summary

Table 4 Design Parameters

Table 5 Water Quality Monitoring Requirements for Graywater Treatment

Systems in Buildings

Table 6 Flow Diversion Conditions

Page 3: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

December 2014

List of Appendices Appendix A System Commissioning & Operator Training Manual

Appendix B System Schematics

Appendix C Component Cut Sheets

Page 4: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 1

December 2014

1 General

1.1 Objective of the Project

The Transit Joint Powers Authority (TJPA) is currently developing plans to

significantly decrease the use of potable water for non-potable uses with

its comprehensive approach to the use of alternate water sources such as

rainwater and graywater at the Transbay Transit Center (TTC).

TTC encompasses a large scale integrated water management system.

Graywater is collected from restroom sinks, not including restroom sinks

from the Tenant Retail Space and conveyed to a treatment and

storage system.

Rainwater runoff is collected from the rooftop park and then piped to

the storage system after pre-treatment.

Blackwater (from toilets, urinals, service sinks, etc.) is directed to the

city’s sewer system.

Water treatment happens at different stages throughout the system by

means of physical, biological and mechanical processes. This

combination of processes is typically necessary for water reuse.

At the rooftop park a subsurface constructed wetland performs

polishing treatment of graywater. No water is exposed at the surface

of the wetland nor is any human contact with untreated graywater

allowed. The subsurface constructed wetland, also called the Water

Reuse Garden presents a unique opportunity for public education and

engagement while creating a rich and diverse habitat island within

the dense urban landscape.

At the end of conveyance, storage, filtering and treatment processes,

the graywater will be reused for toilet flushing for the Transbay Transit

Center, including the Tenant Retail Space.

1.2 Facility Information

The Transbay Program is a $4.5 billion project to replace the former

Transbay Terminal at First and Mission streets in San Francisco with a

modern regional transit hub that will connect eight Bay Area counties and

the State of California through eleven transit systems: Alameda–Contra

Costa Transit, BART (Bay Area Rapid Transit), Caltrain, Golden Gate Transit,

Greyhound, Muni (San Francisco municipal bus lines), SamTrans (San

Mateo County Transit), WestCAT (Western Contra Costa Transit) Lynx,

Amtrak, Paratransit, and high-speed rail from San Francisco to Los

Angeles/Anaheim.

The Transbay Program will be constructed in two phases. Phase 1 includes

design and construction of the above-grade portion of the Transit Center

which is located between Second Street and Beale Street and between

Minna Street and Natoma Street. The structure and core of the two

Page 5: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 2

December 2014

below-grade levels of the train station, new bus ramps, a bus storage

facility, and a temporary bus terminal. The Downtown Rail Extension (DTX)

tunnel, the build-out of the below-grade train station facilities at the Transit

Center, a pedestrian tunnel, and an intercity bus facility will follow as

Phase 2 of the Program.

The TTC will feature “City Park,” a public 5.4-acre rooftop park. The 1,400

foot long elevated park will feature a wide range of activities and

amenities, including an outdoor amphitheater, gardens, trails, open grass

areas, and children’s play space, as well as a restaurant and café.

Highlights of City Park include:

Green roof with sustainable design features

Public space including both quiet and active areas

Restaurant and cafe

Open air amphitheater

Display gardens featuring climate-appropriate plants

Children’s play spaces

Pedestrian bridges connecting surround development to the park

Bike storage to accommodate approximately 600 bikes

Ten different public access points

2 Rules and Regulations

2.1 San Francisco Department of Public Health

Article 12C, Section 853 of the San Francisco Health Code established

permitting requirements for the use of alternate water sources for non-

potable applications and set permit and annual fees. The San Francisco

Department of Public Health (SFDPH) is responsible for ensuring that

Alternate Water Source Systems are in compliance with applicable laws.

SFDPH performs ongoing monitoring, review, and inspections of permitted

Alternate Water Source Systems to ensure such compliance is maintained.

As established in the City and County of San Francisco Charter section

4.110, the SFDPH is authorized to perform duties associated with regulating

the internal uses of recycled water through its general authority to provide

for the preservation, promotion and protection of the health of the

inhabitants of the City and County.

Additionally, Articles 11 and 12A of the City’s Health Code authorize the

SFDPH to investigate and abate any nuisance, activity, or condition that

the SFDPH deems to be a threat to public health and safety, and to

investigate and abate any cross connection risks between potable and

Non-Potable Water and sanitation systems in both public and private

facilities. The Health Code authorizes the SFDPH to order a person to

vacate property, cease prohibited activities, abate unsafe or unsanitary

conditions, and pay penalties for violations.

Page 6: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 3

December 2014

2.2 San Francisco Public Utilities Commission

The San Francisco Public Utilities Commission (SFPUC) would provide water

and wastewater services to the Transbay Program.

3 Producer-Distributer-User

The Contractor implicated in the system operation and maintenance has

not been chosen at this time, but the Contractor would have to have the

experience and the manpower to operate and maintain the system in

accordance to SFPDH requirements.

The Producer, Distributor and System Operator for this project are the

same agency, the TJPA.

Users of non-potable water generated by the system include TJPA

employee, the general public who visit the TTC and transit system

passengers.

4 Non-Potable Supply Sources, Flows, Water Quality and Characteristics

4.1 Non-Potable Supply Sources

Wastewater flows are segregated and piped separately as graywater

and blackwater. Blackwater from the toilets and urinals, air handlers and

any other sources are all discharged into the city sewer.

Graywater from showers and restroom sinks, not including restroom sinks

from the Tenant Retail Space, is collected for reuse. Also rainwater and

irrigation runoff is collected from the rooftop park landscape and

hardscape areas, also for building reuse. In the future other water sources

will likely become available such as municipally (SFPUC) supplied recycled

water. The municipally supplied potable/recycled water will be used to

supplement non-potable water needs.

4.2 Volumes and Flow Rates of the Non-Potable Sources

The estimated number of visitors/users are as follows (per Ridership

Report):

Retail Staff/Office Workers: 822

Bus Passengers: 45,831

Train Passengers (Phase 2): 78,953

The following number of fixtures were included in the estimates: 113

toilets, 27 urinals, 94 lavatories and 20 showers.

Page 7: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 4

December 2014

The expected water demand per person is (per Industry Standard):

Office/Retail Staff: 12 gal/day

Passengers: 1.5 gal/day

Notes:

TTC Water Use

Total TTC water demand: 16,885,044 gallons/year Total water use based on current design

with water-conserving fixtures.

Potable water demand: - 1,690,356 gallons/year Demand for potable to be supplied by

PUC (lavatory sinks, etc.).

Non-potable water

demand: 15,194,688 gallons/year

Non-potable water demand; includes

toilet and urinal flush, etc.

15,194,688

On-Site

Availability

Captured rainwater

availability: - 2,010,794 gallons/year

Based on observed rainfall data over 5-

year period. Reflects current tank size,

rainwater runoff coefficient and rate of

reuse.

Treated graywater

availability: - 1,527,910 gallons/year

Treated graywater availability accounts

for water losses from treatment

operations.

11,655,983 gallons/year Demand for water to be supplied by PUC

that could be either potable or municipal

reclaimed water.

Summary:

Demand from

Municipality

Unmet non-potable

demand: 11,655,983 gallons/year

Demand for water to be supplied by PUC

that could be either potable or municipal

reclaimed water.

Potable water demand: 1,690,356 gallons/year Demand for potable water to be supplied

by SFPUC.

Number shown are current estimates as of June 22, 2012

Page 8: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 5

December 2014

The estimated number of visitors/users are as follows:

Retail Staff/Office Workers: 822

Bus Passengers: 45,831

Train Passengers (Phase 2): 78,953

The following number of fixtures were included in the estimates: 113

toilets, 27 urinals, 94 lavatories and 20 showers.

The expected water demand per person is:

Office/Retail Staff: 12 gal/day

Passengers: 1.5 gal/day

4.3 Source Water Quality Summary

The quality of graywater constantly fluctuates, thus it is difficult to

determine what the true composition of graywater at the TTC will be.

Many variables will cause fluctuations including: user inputs, time of year

and water temperature. Several studies analyzing the quality of

graywater have been compared to determine conservative values for

the quality of graywater.

It is anticipated that during the first few months after completion of the

roof park, rainwater runoff may contain a higher level than normal level of

turbidity because of soil on the park level. Typically after the first season

the runoff water quality will increase as the roof soil structure stabilizes.

The building usage will also change over time. The system is designed for

a maximum occupancy of the building, but graywater flows will be less

prior to Phase 2 of the program, which will include the extension of

Caltrain and the California High Speed Rail (CHSRA) of the TTC.

Water availability will vary significantly between the summer and winter

months. During the rainy season the graywater supply will be augmented

heavily by rainwater collection from the rooftop park. When CHSRA

service is at TTC, it is expected that during the summer months there will

be higher ridership and higher production of graywater. In any case,

when water supply is low potable water backup will supply water

necessary to meet the demand of the toilets and to provide a constant

supply of water to the wetland.

Page 9: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 6

December 2014

TABLE 1:

Baseline Water Quality of Raw Graywater vs. Potable Characterization

of Graywater for Title 22 Reuse Standards San Francisco Public Utilities

Commission

Parameter Potable Water Raw Graywater

Range Average Range Average

Total Coliform (CFU/100 mL) Non-detect Non-detect 131 - 5,153 2155

pH 8.0 - 10.1 9.3 6.4 - 6.8 6.8

Turbidity (NTU) 0.1 – 0.3 0.1 6.6 - 26.0 17.0

5 Treatment Process

5.1 Design Basis

Rainwater receives primary biological and physical treatment as it flows

through the roof park soil layer before draining into three storage tanks.

The rainwater will pass through a vortex filter before being stored. Once

rainwater is mixed with primary treated graywater in the storage tanks,

undergoes ozonation and chlorination, it assumes the designation of

treated graywater and is labeled as such.

Graywater requires primary mechanical treatment in the form of a pre-

screen filter, and a 25 micron basket filter. The pre-screen filter removes

large debris from the water and prevents clogging of plumbing, valves,

and pumps. Pumps located in the collection pit pressurize the water and

send it through the pre-screen filter and the 25 micron basket filter. The

graywater mechanical filtration system features a low flow backflush and

water quality monitoring system. The filter automatically cleans itself with

an efficient backflush, minimizing water loss.

For additional treatment, water on the eastern part of the facility

graywater is then pumped to the subsurface constructed wetlands on the

rooftop park for polishing treatment. Water is distributed evenly across the

width of the wetland cell by distribution piping. Gravity and hydrologic

pressure move the water through the wetland at a rate determined by

the projected graywater supply. Microbes in the filtration media and

wetland plant roots clean the water, removing nutrients and the

pathogens. In compliance with state codes, graywater will remain below

the surface at all times. Water flows through a layer of filtration media in

the subsurface wetland. A collection pipe at the opposite end of the

wetland receives the treated water. Water then flows through an

adjustable weir that gives the operator control of the water level in the

wetland. Finally a filter removes residual debris from the treated

graywater (wetland effluent) before being piped back to the concourse

level for ozone disinfection and storage.

Page 10: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 7

December 2014

Overflows to the sewer are provided throughout the system to prevent

building damage, ensure safety and to enable the maintenance of

various system components. For example, to accommodate for a storm

event greater than the holding capacity of the wetland, an overflow to

the sewer is provided.

5.2 Process Schematic

Rainwater runoff from the rooftop is directed through vortex filters, then to

three storage tanks. One tank contains rainwater only and two tanks

contain rainwater mixed with primary treated graywater. Graywater is

collected from sinks and showers in the bathrooms and is filtered through

one of two mechanical treatment systems located on the east and west

end of the TTC. Graywater on the west end is directed to the storage

tanks immediately after mechanical filtration, while graywater on the east

end of the facility is sent to the Park Level constructed wetland for

polishing before being collected in the storage tanks. Two 25,000 gallon

and one 50,000 gallon storage tanks hold water for reuse. Water is

transferred between the tanks to meet fluctuating demands across the

facility. Two of these are located on the lower concourse level and one

on the train platform level. An ozone sterilizer disinfects the water by

releasing ozone tanks into each tank. A small dose of chlorine is added to

ensure a 1ppm residual in the non-potable water, per IAPMO

recommendations.

The treated graywater from these tanks supplies all of the toilets and

urinals in the TTC. A back-up supply of domestic water ensures that a

minimum level of water remains in the tanks at all times. Domestic water is

used for make-up until the city supplied recycled water is available. There

is a capped connection to the future city provided recycled water in the

water pump room. When this source becomes available, new piping will

have to be installed to deliver make-up water to the capped connection

in lieu of the currently used potable water. New piping to connect to the

city provided recycled water will have to be installed regardless of

whether or not the water treatment system is included in the project. An

air gap is provided to ensure no cross contamination of the make-up

source.

Page 11: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 8

December 2014

TABLE 2: Design Final Effluent Characteristics

Parameter Final Effluent after Disinfection (a)

Average Maximum

BOD, mg/L (b) <10 <2

Turbidity, NTU (c) <2 <10

Total Coliform, CFU/100 mL (d) <2.2 23

(a) From sample port on reclaimed water line. (b) Monthly average and maximum based on monthly samples. (c) Based on weekly measurements. (d) Colony forming units per 100 mL. Average and monthly maximum based

weekly samples.

TABLE 3: System Component Capacity Summary

Component Function Capacity Notes

Storage Tank –

Sector A+B

Primary treated water

storage.

50,000 gal.

Storage Tank –

Sector C

Primary treated water

storage.

25,000 gal.

Storage Tank –

Sector D

Primary treated water

storage.

25,000 gal.

Submersible

Graywater Pumps

Pump graywater from

collection pits to

treatment skid.

50 gpm

Water Treatment

Skid

Water treatment

including disinfection

100 gpm Filters, ozone,

generator,

chlorination, dye

injection

Treated Graywater

Booster Pumps to

Fixtures

Pump treated

graywater to fixtures.

50 gpm to

80 gpm

TABLE 4: Design Parameters

Design Parameter Units Value

Storage Tank – Sector A+B gal. 50,000

Storage Tank – Sector C gal. 25,000

Storage Tank – Sector D gal. 25,000

Booster Pump – Sector A+B gpm 80

Booster Pump – Sector C gpm 50

Booster Pump – Sector D gpm 60

Page 12: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 9

December 2014

5.3 Filtration/Ozone Treatment System

5.3.1 System Construction

The packaged commercial water reclamation and delivery system shall

consist of enclosed ozone generation/injection equipment, duplex side-

stream circulation loop pumps, 25 micron auto-clean basket filter in 150

psi rated stainless steel housing, 25 micron bag filter, 5 micron bag filter,

chlorine and dye injector pumps and tank accessories, duplex pressure

booster pumps, duplex “over-flow” pumps, disinfection/filtration control

panel with local disconnect(s) and LED system status indicators in NEMA

3R enclosure, and booster/over-flow pump control panel with analog

input for tank level controls.

5.3.2 Mechanical Features

The water disinfection/filtration system shall disinfect stored water via side

stream circulation and ozone injection. Water shall be circulated

between the storage tank and the disinfection/filtration system by a

duplex pumping system. Re-circulated water shall pass through duplex 25

micron bag filters and ozone shall be injected into the tank return flow. An

ORP (Oxygen Reduction Potential) meter (located in tank) shall take

constant tank oxidation measurements and cycle the ozone generation

equipment and the pump as necessary in order to maintain tank ozone

concentrations within a range of approximately 0.1 ppm – 0.5 ppm.

Treated disinfected water shall be supplied to fixtures and equipment

from a packaged duplex booster system. Booster system shall deliver

water to fixtures/equipment after flowing through duplex 2 5 micron bag

filter and receiving a proportional dose of approximately 1 ppm residual

injection of sodium hypochlorite and colored dye as prescribed.

5.3.3 Connections

Pipe and fixtures conveying reclaimed water shall be properly marked

and labeled per local code. See drawings for connection sizes and

locations.

5.3.4 Controls and Fail-Safe Mechanisms

System shall include on-board electronic controller in NEMA 3R enclosure,

with LED system. Controller shall monitor at all times tank ORP levels, pump

temperatures, and pressure differential through Auto clean filter(s) on skid.

Should ORP levels in tank drop such that ozone concentrations have fallen

to the equivalent of approximately, 0.1 mg/l, controller shall engage the

ozone system on to rebuild concentrations. Should pressure differential

through Auto clean exceed 9 psi, controller shall initiate backwashing of

the Auto clean filter(s) using water from the storage tank. An integral

mechanical room air quality monitor shall shut down the ozone system,

Page 13: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 10

December 2014

and activate an alarm should any ozone leakage occur. Should either

the sodium hypochlorite or dye injection drums (supplied by others) run

low, system shall activate alarm. Status of all fail-safe functions shall be

clearly displayed on LED control panel. System controller shall include dry

contacts for connection of any alarms and/or indicator lights to the

master control panel.

5.3.5 Performance

Disinfection levels: The system shall maintain and monitor tank water

disinfection levels via ORP (oxygen reduction potential) meter. Tank ORP

readings shall be displayed on system control panel. Ozone levels of

approximately 0.1 ppm to 0.5 ppm (200 - 300 mV ORP over untreated

water levels) shall be maintained.

5.3.6 Temperature Requirements

Ideal system operating temperatures shall be 50°-75°F. Minimum

operating temperature shall be 35°F. Maximum operating temperature

shall be 100°F. System shall not be subjected to freezing temperatures.

5.3.7 Backwashing Filters

Stand alone duplex backwashing filter array shall include 25 micron,

stainless steel backwashing filter for fine filtration of graywater fed into the

cistern. Filter, control, and motorized valves shall be pre-plumbed and

mounted on a skid. Filter backwash effluent shall be delivered to sludge

interceptor barrel supplied with system skid.

5.3.8 Packaged Skid Mounting

The entire system shall be pre-assembled on a heavy structural steel

frame. The frame shall be welded in accordance with AWS D1.1

specifications. The steel frame shall have a zinc oxide primer and a

machine enamel topcoat. All skid-mounted panels and electrical

components will be pre-wired to a master control panel as specified.

5.3.9 Booster System

Booster pump package shall be UL Listed, and have all components

frame mounted, piped, painted, wired and factory tested. All wetted

surfaces shall be lead free. Package shall include duplex pumps,

suction/discharge manifolds, hydro-pneumatic bladder tank, and control

panel. Package shall have a single point 480 volt, 3 phase power

connection and include a control voltage transformer.

Page 14: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 11

December 2014

5.3.10 Hydropneumatic Tank

Hydropneumatic tank shall be ASME rated with a ring stand base and

replaceable bladder. The tank shall be skid mounted and piped. The tank

shall be provided and installed with a union isolation ball valve, pressure

gauge and drain valve.

5.3.11 Bag Filters

Bag style filter with 304 stainless steel housing, clamped cover with Buna N

rubber O-ring seal, 125 psig pressure rating, non-ASME code vessel, high

and low side 1/4” NPT gauge ports, 10 micron nominal filter rating at

design flow. Flow and nominal design pressure drop per equipment

schedule.

5.3.12 Tank Over-Flow/Transfer Pump System

Each pump and motor to have nameplate listing manufacturer’s name,

pump serial number, capacity in GPM and feet of head at design

conditions, motor horsepower, voltage, frequency, speed and full load

current.

5.3.13 Chlorine/Dye Injection System

Packaged skid system shall include two on-board chemical injector

pump(s) and feed line each mounted on separate 30 gallon drum to

inject a) 12% sodium hypochlorite solution at a concentration of 1 ppm

and b) biodegradable and non-toxic blue dye into system output.

Injection equipment shall include chemical tank float switch to activate

alarm in cases of low tank levels. Injector pump shall accept a 4-20mA

input signal from the booster pump control panel to modulate chemical

and dye injection based on booster pump operating speed.

5.3.14 Master Control Panel

Provide a Master Control panel to integrate the controls signals from all

skid-mounted control panels and electronic control devices and provide

a BacNet gateway interface to the building management system for

control and monitoring of the system. The panel shall include the

following:

Micro-processor based supervisory controller (HMI) shall be a panel

door mounted unit with color graphic touch screen display. The HMI

shall provide an easy to use operator interface to all system

parameters and display those parameters in plain English and

engineering units. Monitoring functions shall be available to all users,

but access to parameters shall be restricted by two levels of password

protection.

Page 15: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 12

December 2014

Main power circuit breaker disconnect

Control circuit transformer with protected secondary.

General Alarm with alarm horn and push to silence button

Provide a set of dry contacts, wired to a terminal strip in the control

panel for transmission of general fault alarm to building automation

system. The PLC shall provide a data log including a date and time

stamp of past 20 system faults. These faults shall be displayed in English

text on the door mounted supervisory controller (HMI).

The PLC shall be capable of connection to a building management

system (BMS) using Modbus, BACnet or Lonworks.

Programmable logic controller

Analog static pressure cistern level sensor (shipped loose for field

installation)

Data points for monitoring and control to include the following as a

minimum:

1. Water Control Corp model RW-OZ-100

a. Remote Enable/Disable (control DO)

b. Operation mode – Auto/Off (monitor DI)

c. Dirty Filters – yes/no (monitor DI)

d. Recirculation pump status – on/off (monitor DI)

e. Alarm Status – on/off (monitor DI)

f. ORP level – ppm (monitor AI)

2. Duplex Reclaimed Water Booster

a. Remote Enable/Disable (control DO)

b. Pump Status (one per pump) – on/off (monitor DI)

c. Pump Failure (one per pump) – normal/alarm (monitor DI)

d. Low Tank Level – normal/alarm (monitor DI)

e. High Discharge Pressure – normal/alarm (monitor DI)

3. Duplex Overflow Pumps

a. Remote Enable/Disable (control DO)

b. Pump Status (one per pump) – on/off (monitor DI)

c. Pump Failure (one per pump) – normal/alarm (monitor DI)

d. Low Flow Shutdown – normal/alarm (monitor DI)

4. Backwashing Filters

a. Power – on/off(monitor DI)

b. Filter Status – normal/backwash (monitor DI)

5. Bag Filters

a. Differential Pressure – normal/high (monitor DI)

6. Chlorine Injection

a. Pump Status – on/off (monitor DI)

b. Chlorine tank level – normal/low (monitor DI)

7. Dye Injection

a. Pump Status – on/off (monitor DI)

b. Chlorine tank level – normal/low (monitor DI)

8. Cistern

a. Low level domestic water makeup

Page 16: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 13

December 2014

5.3.15 Wetland System

1. Biological Water Treatment

Biological processes of plant roots, fungi, and bacteria filter water by

removing organic and inorganic pollutants. Biological water

treatment is successful when temperature, plant species, soil types,

nutrients, humidity, and the concentration of pollutants are all

considered.

2. Physical Water Treatment

Retention time in wetlands promotes physical treatment of graywater.

Contact with plant roots and growing media as well as the process of

sedimentation all contribute to the removal of pathogenic

microorganisms from the water column where they are metabolized

by the community of microorganisms within the soil.

3. Constructed Wetlands Overview

A constructed wetland is a bed, or series of beds or trenches filled with

substrate material and aquatic plants. This provides both aerobic and

anaerobic conditions. In sub-surface flow constructed wetlands water

is directed below the media surface, where treatment occurs.

Subsurface flow wetlands are the focus of this report to address any

concerns regarding public exposure to wastewater. The roots of plants

bring oxygen to the top eighteen inches of soil, but because

graywater will not be allowed to surface, mechanical pumps may be

needed to provide aeration.

Increased wetland efficiency is achieved through controlled flow

rates, engineered media, tailored plant lists, and wetland size and

shape. Constructed wetland projects are typically monitored and

documented, providing assurance that post-treatment water quality

meets the requirements of the EPA and other regulatory agencies.

4. Wetland Sizing

Wetland design and sizing is based on the methodology provided in

the Environmental Protection Agency (EPA) Manual, “Constructed

Wetlands Treatment of Municipal Wastewaters”. This manual provides

the federal guidelines for determining the capabilities of constructed

wetlands. Treatment objectives of constructed wetlands are to

achieve target levels for suspended solids, organic matter, pathogens

and nutrients. Target levels of treatment vary greatly depending on

regulatory agency regulations and expected end use of effluent

water.

Page 17: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 14

December 2014

The wetlands are designed to respond to the fluctuations in water

quality and flow rate. Since the occupancy of the TTC will be

constantly in flux the wetlands are designed to accommodate varying

flow rates. Residency time of the water in the wetlands can be

adjusted to accommodate variable flow rates. Wetlands will not have

to be irrigated with potable water when the occupancy is down;

instead, the residency time in the wetlands is increased to maintain a

minimal amount of water in the wetlands beds to maintain plant

health.

Figure 6 is a sectional view of the length of a wetland cell. Graywater

enters the inlet zone of the treatment wetland via a distribution

header.

BOD and TSS are removed through settling, flocculation and filtration

of suspended particles and large colloidal particles as the graywater

passes through the wetlands. The outlet is designed to allow the

operator to adjust the water level within the wetland through the use

of an in-line weir and to completely drain the wetland for

maintenance purposes, if necessary.

Wetland media consists of 18” depth of washed and graded +/- 5/16”

or +/- 3-4” expanded, kiln fired shale. The advantages of this material

are that is has a large amount of surface area, which aids in filtration,

and is very lightweight when compared to gravel or other media

types. Flow rate through wetland cells shall be at a constant rate of

~2.5 gpm per wetland cell.

5.4 Filtration and Disinfection Systems

5.4.1 Ozone Disinfection Technology

A variety of options are available for disinfection of graywater. Ozone is a

reliable and widely accepted means of disinfection and is the preferred

method for the TTC because it most effectively treats large volumes of

water quickly. It is not required to disinfect rainwater for toilet reuse, but

when the rainwater mixes with graywater both need to be treated with

ozone. Due to the high volumes and flow rates associated with rainwater,

a conventional chlorine system does not have adequate time to disinfect

the water without using large volumes of chlorine.

Collected rainwater and treated graywater is exposed to diffused ozone

bubbles. Ambient air generates the toxic gas that causes the cell wall of

an organism to burst, thereby destroying it.

Page 18: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 15

December 2014

The effectiveness of ozone disinfection depends on the characteristics of

wastewater, the intensity of ozone, the amount of time the

microorganisms are exposed to the ozone, and the dimensions of the

tank. The range of ozone concentration that will be maintained in the

tanks is 0.1 ppm to 0.5 ppm.

Ozone is produced on site, reducing the transportation and storage costs,

as well as the associated carbon footprint. With the proper design, the

only by-product of ozone disinfection is oxygen. There are three

components to an ozonation system: the generator, contactor, and

ozone destruction device. Ozone is produced in an ozone generator,

supplied with air and electricity. (USEPA 1999)

5.4.2 Ozone Generators

A high voltage (approximately 6,000 volts) is applied to two electrodes

and the high voltage produces an arc. In the arc part of the Oxygen (O2)

is converted into Ozone (O3). Ozone is very unstable and reverts back into

O2 within minutes. That is why ozone must be generated on-site and

cannot be shipped for later use. About one to ten percent of the oxygen

flowing past electrodes is converted into ozone. With air as the feed gas,

ozone concentrations between one and four percent are generated.

Ozone generators are an efficient means of water treatment. The energy

demand of a commercial ozone water treatment system is roughly the

same as a 50W light bulb. The overall energy consumption of the ozone

generator is dependent on: applied power, source oxygen flow, water

temperature, the manufactured efficiency and design of the generator.

(USEPA 1999)

5.4.3 Contactor

A contactor is the distribution system to evenly disperse ozone into water.

A contact chamber is the tank where ozone is introduced into the water.

To optimize water disinfection, ozone must be diffused as finely as

possible. The ability of a system to transfer ozone from a high

concentration (generator) to a low concentration (stored water) is called

mass transfer efficiency. The greater the efficiency, the less ozone

required for disinfection. Efficiency is increased by decreasing the size of

the ozone bubbles and the method in which ozone is introduced into the

water. (Rakness 1996).

Page 19: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 16

December 2014

5.4.4 Ozone Destruction Device

Ozone bubbles introduced in the water storage tank off-gas into a vent

pipe. The concentration of ozone being off-gassed from a water tank

generally exceeds the limit of 0.1 ppm, the current limit set by

Occupational Safety & Health Administration (OSHA) for worker exposure

in an eight-hour shift. For example, at 90 percent transfer efficiency, a 3

percent ozone feed stream has 3,000 ppm of ozone in the off-gas. Off-

gas is collected and the ozone converted back to oxygen prior to release

into the atmosphere. Ozone is readily destroyed at high temperatures (>

350°C or by a catalyst operating above 100°C) to prevent moisture

buildup. The off-gas destruction unit reduces the concentration to 0.1

ppm of ozone by volume. A blower on the discharge side of the destruct

unit pulls the air from the contactor, placing the contactor under a slight

vacuum to ensure that no ozone escapes. The power requirement is

between 1 to 3 kW per 100 scfm (standard cubic feet/min.) of gas flow.

(DeMers, 1996)

5.4.5 Ozone Safety Standards

Ozone gas is hazardous and should be handled accordingly. OSHA

regulates workplace safety standards, including allowable levels of ozone.

The pungent odor of ozone provides a warning to operators of any

possible ozone leak. Ozone is detectable by the human nose at 0.01-0.05

ppm (Reiff 1992). Instrumentation and equipment is provided to measure

ambient ozone levels and perform the following safety functions:

Initiate an alarm signal at an ambient ozone level of 0.1 mg/L (by

volume). Alarms include warning lights in the main control panel and

at entrances to the ozonation facilities as well as audible alarms (IO3A

2009).

Initiate a second alarm signal at ambient ozone levels of 0.3 mg/L (by

volume). This signal immediately shuts down ozone generation

equipment and initiates a second set of visual and audible alarms at

the control panel and at the ozone generation facility entrances. An

emergency ventilation system capable of exhausting the room within

a period of 2 to 3 minutes also would be interconnected to the 0.3

mg/L ozone level alarm (IO3A 2009).

In case of an electrical failure, the ozone generator shuts down along

with system pumps. An alarm powered by the emergency backup

generator sounds to notify personnel that the disinfection system has

been shut off. The alarm stops when power is restored to the ozone

generator. Ozone gas is vented out of the mechanical room. In case

of a rupture in the tank, negative air pressure in the tank causes air to

rush into the tank, preventing possible exposure to ozone.

Page 20: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 17

December 2014

5.4.6 Chlorine Injector

Chlorine is a common chemical disinfectant that when added to water,

leaves a detectable residual. Treated graywater is used to supplement

toilet flushing as long as there is a detectable chlorine residual of a least

1ppm at the toilet (IAPMO 2006). Chlorine breaks down over time as it

reacts with the water, air, and impurities. Chlorine can be added as a

powder, liquid, or gas. The most appropriate form of chlorine for the TTC is

liquid because the dosages can be closely controlled. Chlorine tablets

lead to variable concentrations, requiring higher application rates than

are required. High chlorine levels can lead to eye and throat irritation

during off-gassing.

To reach the minimum 1ppm of chlorine in treated water, an injector is

used to add liquid chlorine. The injector adds approximately 5ppm of

chlorine, exceeding the minimum requirement. The exact amount of

chlorine will vary as the flow rate varies. The chlorine injector modifies the

amount of chlorine used, which is determined by the variable pumping

rate (assuming a variable flow device is used).

The purpose of the chlorine injection is to ensure that the water is sterilized

before reuse in case any residual water pathogens are present. The

graywater and rainwater treatment systems function without the chlorine

additive, but including it complies with existing code requirements, and

minimizes liability for the TJPA. (IAPMO 2006)

Chlorine is a hazardous chemical, and should be handled with care.

Storage and handling of chlorine varies based on form and

concentration. Maintenance staff must follow the safety measures stated

by the manufacturer.

5.5 System Operation and Maintenance Manual

5.5.1 Graywater Maintenance

The water treatment system does not need to be registered under any

governmental or regulatory agency, but will undergo review and

inspection by local regulatory authorities if requested by the TJPA. The

TJPA, as owners of the TTC facility will own and operate the water

treatment system and have complete jurisdiction over the long term

maintenance of the system. The TJPA could also establish a third party

contract with a maintenance company.

Page 21: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 18

December 2014

5.5.2 Maintenance of Constructed Wetlands

1. Long-Term Maintenance

Subsurface constructed wetlands are biological systems and have

very few regular maintenance needs after they become established.

Wetland treatment systems rely largely on passive treatment

mechanisms and have very few operational controls compared to

mechanical treatment systems. They often run unattended for

extended periods of time. With proper wetland sizing and inlet and

outlet structure design, the wetland requires infrequent but regular

observation of the inlet zone, outlet zone and the adjustable weir.

Maintaining of wetland plants and gravel beds for aesthetics is similar

to any other planting area in the park; litter removal, pruning, plant

replacement, and fertilization may be required as part of the regular

landscape maintenance, but is not expected to require more

maintenance than a typical park planting area, depending on

planting design.

5.6 Operations Support

The TJPA, as owners of the TTC facility will own and operate the water

treatment system and have complete jurisdiction over the long term

maintenance of the system. The TJPA could also establish a third party

contract with a maintenance company.

6 Reliability

6.1 Automated Controls System

The entire reuse water system operation is fully automated through a

Programmable Logic Controller (PLC) based on programmed logic,

operator input and multiple sensors. Water level sensors (ultrasonic type),

located in all tanks in the treatment process sense various levels. Water

levels, flow rates and the operational status of pumps are monitored by

the system controls at all times.

A graphic user interface in the PLC system provides a visual indication of

all water levels, operating status of pumps, flow rates and other sensor

readings. Clearly labeled operator input fields and control points are

included in the graphic interface for each subsystem. In addition, alert

and alarm conditions are displayed on the alarm screen and forwarded

to operators. The alert/alarm conditions include a simple explanation of

the art/alarm cause. These features allow easy diagnosis of problems and

straight forward resolution.

Page 22: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 19

December 2014

The BMS will receive monitoring data and alarms from the Treatment

System, allowing building staff to review and respond to alarms 24 hours

per day, 7 days per week. The Treatment System alarm log is accessible

through the BMS both locally and remotely.

6.2 Treatment Process Reliability

The reuse water system includes proven treatment processes (for filtration

and disinfection). These processes are very reliable and overflows from

these tanks to the sewer provide an alternate outlet.

6.3 Hydraulic Control and Overflow Prevention

If a water level surpasses a predetermined maximum, the appropriate

overflow system will come into play. High water levels will be logged in

the PLC and flagged for operation review.

There are three water levels in the tanks that trigger overflow protection:

At the first level the three-way valve will divert the rainwater to the

gravity storm drainage.

As the second level overflow water pumps will pump the water into the

storm drainage.

At the third (highest) level the tank overflow will discharge indirectly

into the floor sink at next to the tank.

Critical high water conditions will trigger an alarm that will be broadcast

to designated operations staff.

All critical points in the system are equipped with emergency overflows or

bypass pumps to prevent uncontrolled overflow of graywater. Because of

these safeguards there is virtually no chance of overflow into equipment

rooms.

Graywater is pumped to each of the two wetland cells at a constant rate

of ~2.5gpm, thus under normal operation, the wetland will discharge

through each weir at a constant rate. Wetland weir inlets/outlets are 4”

diameter and sized to accommodate the design storm. As an additional

failsafe wetland cells are equipped with a four inch overflow drain so that

the water in the wetland will never surface. The wetland overflow drain

discharges back to the storage tank.

Page 23: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 20

December 2014

6.4 Supply Reliability

The system will reliably supply water to toilets and urinals. If the water level

in storage tanks drops to a certain level, potable water make-up supply

will be delivered. In the event of a power failure, all pumps and controls

are supplied with emergency power provided by on-site emergency

generators.

7 Supplemental Water Supply

In the event that the reuse water system is incapable of producing

enough treated graywater to meet the non-potable water demand for

toilets and urinals in the building, there are two supplies of make-up water:

Potable water supplied via the City’s potable water distribution

network.

Recycled water (Title 22, tertiary treated water) supplied by the future

recycled water distribution network.

Potable water can be delivered to the non-potable storage tanks in the

building when a low water condition in the tank triggers a valve to open

and fill the tank to a safe operating level. Water level sensors and valves

are controlled by the Treatment System PLC panel. Potable water is

delivered through an air gap to ensure no cross contamination to the

City’s potable distribution network.

8 Monitoring Reporting

Monitoring and sampling recommendations for this project will be

developed by the SFDPH. The sole use of reclaimed water in this system is

toilet and urinal flushing.

Table 4 provides a list of critical parameters with anticipating effluent

concentrations and sampling frequency to ensure proper operation and

performance of the system.

Page 24: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 21

December 2014

TABLE 5: Water Quality Monitoring Requirements for Graywater Treatment Systems in Buildings

Parameter Units Water Quality Limits Monitoring

Frequency Monitoring Location

Escherichia

Coli CFU/100 mL

The median concentration shall not exceed

2.2 CFU/100 mL utilizing the bacteriological

results of the last 4 weeks for which analysis

have been completed; and Weekly (Start-up &

Temporary), Monthly

Entry point to

distribution system

(following treatment

and storage)

No sample shall exceed 200 CFU/100 mL at

any time.

Turbidity NTU

The median shall not exceed 2 NTU utilizing

the results of the last 7 days for which analysis

have been completed; and Daily

No sample shall exceed 10 NTU at any time.

Odor n/a The system shall not emit offensive odors. n/a

Chlorine

Residual mg/L

Over any 24 hour period, the average

chlorine residual shall be within the rage 0.5-

2.5 mg/L.

Continuously

pH n/a At any time, the pH shall between 6 and 9. Weekly

Routine Reporting Frequencies:

Start-up Permit: Monthly Operational changes, system malfunctions, and/or monitoring results

which are outside of the excepted limits shall be reported within 24 hours. Temporary Permit: Monthly

Final Permit: Annually

Page 25: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 22

December 2014

9 Contingency Plan

The contingency plan describes system features and operational

procedures that will be employed to prevent spills and system

malfunctions. The plan for provision of supplemental water supplies is also

described.

9.1 Flow Diversion

Diversion of flow to sewer can occur at several points as listed below:

Excess rainwater to three-way diversion valves.

Treated graywater transferred to other tanks (manually operated

valves).

Wetland overflow to the treated graywater tank.

Diversion of flow at these points is automatic under certain conditions and

can also be initiated by operations staff through the control system or

manual override. Level sensors in all tanks or wetland cells detect when

water reaches a critical level. In these cases, water will overflow or can

be diverted to the sewer. The conditions for diversion and the method are

outlined in Table 5.

TABLE 6: Flow Diversion Conditions

Condition Diversion Point(s) Method (a)

Emergency High Water Level Sewer diversion

valves Auto

Water Reuse Treatment, extended

shutdown Transfer valves Manual

Building pump malfunction

Sewer diversion

valves Auto or Manual

Overflow Auto

(a) Method of diverting flow; “auto” is automatically performed by the

system controls based on operator-defined set points. Manual is

performed by operations staff through the PLC or switches.

9.2 Fail Safe Procedures in the Event of Power Failure or Natural Disaster

Procedures

In the event of a power failure the equipment will be supplied with

emergency power provided by on-site emergency generators. Also the

BMS will receive data and alarm signals from the treatment system.

The building evacuation and protection procedures for natural disasters

will be provided by TJPA.

Page 26: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 23

December 2014

10 Public Access and Impact

The Reuse Water Treatment System components are located primarily in

the basement mechanical rooms. The wetlands are contained in

watertight concrete basins with an above grade portion similar to

landscape planters. The treatment wetlands surface portions will be

located in the roof park area.

Public contact with wastewater and/or graywater aerosols will be

prevented by various measures, as described below.

Treated graywater will not surface in the wetlands, but is kept below

the surface medium (gravel-like material).

Plants will grow in and cover most of the wetland surface, acting as an

additional barrier to contact.

Because the wetlands will be filled slowly from the bottom or

subsurface manifolds, there will be no spraying or splashing of the

water that would release aerosols.

The dry gravel medium above the water surface will prevent any

droplets from becoming airborne.

The installation of warning and interpretation signs at all public access

points including planters and mechanical components.

The wetlands will not generate objectionable odors outdoors. Odors are

prevented by the design of the wetland process. Treated graywater is

always brought into the wetlands subsurface and odor compounds are

captured by the microbial bio films on the medium above water surface.

The wetlands will also be used as a public education tool with respect to

the water reuse systems and methods of treatment.

In the public restrooms, where treated graywater will be used for toilet

flushing, signage will be consistent with Use Area Requirements as

described in 60310 of CCR Title 22 and Dual-Plumbed Recycled Water

Systems as described in 60313-60316 of CCR Title 22 with the term

“Recycled Water” replaced with “Nonpotable Water”.

Page 27: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 24

December 2014

APPENDIX A

SYSTEM COMMISSIONING

&

OPERATOR TRAINING MANUAL

To be developed further by

System Installer and System Operator

Page 28: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 25

December 2014

Table of Contents – Appendix A Overview

Section 1 Treatment Systems Commissioning

Section 2 Instrumentation and Control Systems Commissioning

Section 3 Wetland Commissioning

Section 4 Operator Training

4.1 Initial Operator Training Session

4.2 Follow-up Operator Training Session

Page 29: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 26

December 2014

Overview

1 General System

Whenever the rainwater in the storage tank is above the minimum

operating level, the rainwater reclamation/filtration system will operate on

a cycle timer to draw water from the storage tank through a strainer and

pump it through a 25 micron auto-backwashing filter media and Ozone

injection chamber(s) and back to the storage tank as disinfected water.

2 Normal Operation

Water level in the storage tank is measured by an ultra sonic level sensor

to determine if there is sufficient water to run the reclamation system. If

tank level is too low, the control system indicates a “low tank level”

condition and opens the make-up water valve.

The auto-backwashing filter has a differential pressure indicator/switch

which will initiate a backwash cycle if the pressure drop exceeds 9 psid.

From the filter output the water passes through an Ozone injection

chamber and then returned to the storage tank. An Oxygen Reduction

Potential (ORP) sensor in the storage constantly monitors the ORP and

cycles the ozone generator to maintain ozone concentration in the range

of 0.1 to 0.5 ppm.

3 Alarms

The alarm will be activated in the event that:

The ozone generator fails, manual reset

The ORP reading is low, automatic reset(a)

Any time the system is on Fresh (not Gray) water, automatic reset(b)

Pump “Over Temp” sensor is tripped, manual reset

Notes: (a) This is a normal condition, not a system fault. When the storage tank

ORP level is back within range, the alarm will automatically clear

allowing the system to return to normal operation.

(b) This is a normal condition, not a system fault. When the storage tank

level rises to or above the normal operating level, the alarm will

automatically clear allowing the system to return to normal

operation.

Page 30: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 27

December 2014

4 Monitoring

SFDPH Table of Water Quality and Monitoring Requirements

Suggested Performance and Operating Monitoring Requirements

Parameter and

Units

Effluent, Post Disinfection (a) Monitoring Frequency

Average Maximum

BOD5, mg/L (b) <10 <20

Weekly

(Months 0-3) (f)

Weekly

(Months 4-12)

Turbidity, NTU (c) <2 <10

Continuous, following

filtration, prior to UV

disinfection

Total Coliform,

CFU/100 mL (d) 2.2 49

Daily

(Months 0-3) (f)

Three (3) times per

week

(Months 3-12)

Monthly

(Post 1-year)

Total Residual

Chlorine, mg/L (c)

0.5 4.0 Daily

(Months 0-3) (f)

pH, Standard

Units (e) 6.0-9.0 n/a

Weekly

(Months 0-3) (f)

Bi-Weekly

(Months 4-12)

Monthly

(Post 1-year)

(a) From sample port on reclaimed water line. (b) Average and maximum based on monthly samples. (c) Based on continuous, on-line measurements. (d) Colony forming units per 100 mL. Average and monthly maximum based

on frequency of samples. (e) Daily grab sample. (f) Monitoring trial period begins at building occupancy.

5 Reporting Plan

All water quality sampling shall be performed on approved Discharge

Monitoring Reports which shall be submitted to the SFDPH by the 15th of

the month following the last day of the period reported and shall be

signed by the operator. During the Start-up Mode and Temporary Use

Page 31: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 28

December 2014

Mode, reporting of monitoring results shall be monthly. During Final Use

Mode reporting shall be annually.

6 Method and frequency of testing laboratory’s instrument calibration

shown in table below:

Method Initial Calibration Blank Continuing

Calibration

pH Everyday samples are

run. At least two points

that bracket the

expected range of the

samples.

Ran after every

calibration.

At the end of

each day.

Turbidity Everyday samples are

run. Six standards and

a standard from a

second source.

Ran after every

calibration.

A low and high

standard at the

end of the

batch.

Odor A calibration criteria

does not apply to this

method.

Residual

Chlorine

A calibration criteria

does not apply to this

method.

Escherichia

Coli

A calibration criteria

does not apply to this

method.

Page 32: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 29

December 2014

APPENDIX B

SYSTEM SCHEMATICS

Page 33: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 30

December 2014

FIGURE 1 – PROCESS SCHEMATIC DIAGRAM AREA A and B

Page 34: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 31

December 2014

FIGURE 2 – PROCESS SCHEMATIC DIAGRAM AREA C

Page 35: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 32

December 2014

FIGURE 3 – PROCESS SCHEMATIC DIAGRAM AREA D

Page 36: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 33

December 2014

FIGURE 4 – REUSE WATER SYSTEM PIPING DIAGRAM (AREA A)

Page 37: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 34

December 2014

FIGURE 5 – REUSE WATER SYSTEM PIPING DIAGRAM (AREA B)

Page 38: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 35

December 2014

FIGURE 6 – REUSE WATER SYSTEM PIPING DIAGRAM (AREA C)

Page 39: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 36

December 2014

FIGURE 7 – REUSE WATER SYSTEM PIPING DIAGRAM (AREA D)

Page 40: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 37

December 2014

FIGURE 8 – ROOF WETLAND

Page 41: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Transbay Transit Center

Page 38

December 2014

APPENDIX C

COMPONENT CUT SHEETS

Page 42: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

RW—

100

TRA

NS

BA

YTE

RM

INA

LSP

EC.

FRO

NT

VIE

W

NOP

RIM

AR

YPU

MP

ABO

ARD

30G

RA

M/H

RO

ZON

EG

EN

ER

ATO

RNO

FRE

SH

WA

TER

BY

PA

SS

NOB

LAD

DE

RTA

NK

CH

LOR

INE

INJE

CT

ION

PUM

PE

XTE

RN

AL

CH

LOR

INE

TA

NK

(TB

D)

ORP

CO

NTR

OL

FOR

RE

CIR

CO

NLY

17.0

RIG

HT

SID

E

Mo~

&R

W-1

00R

AIN

WA

TER

EZ

LNE

a<-S

PE

CF

ILT

ER

SY

STE

M

17,0

0

IT

hr-

I

~_

__

_

rH

c~j\~

U:

TSP

70

.5’

91.0

Page 43: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

1

CATEC P/N: 550M0N073

C-3OZX Ozone Monitor

Simple, Inexpensive Ozone Monitor

For water treatment plants, pulp bleachingmills, ozone generator monitors, photocopier and laser printercenters, fumigation projects, HVAC and indoor air quality systems,vehicular pollution monitors, research labs and pilot plants, andwherever ozone exposure is possible: the C-3OZX has a very fastand continuous response. It is rugged and versatile. There are notouchy controls.

Benefits

• Constantly monitors your work environment; showsthe ozone concentration by a multicolor graphicaldisplay, and alarms when there is a health hazard

• No installation typically required; easily understoodby non-technical personnel

• Virtually no maintenance

Page 44: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

2

Features:

• LED readout changes color as ozone levelincreases

• Audio alarm and output for data logger• Connections for external equipment control• For general monitoring and ozone control• Many accessories available such as data

loggers, calibrators, and protectiveenclosures with heaters and 4-20 mAoutputs

Specifications:

• Range: .02-.l4ppm of ozone(LED scale); .02-.30 ppm viaexternal data readout

• Bargraph Display: Normallygreen; yellow at .05 ppm(caution); red at .1 ppm(danger)

• Response time: Within tenths ofseconds of ozone reaching thesensor

• Measurement principle: HMOS(heated metal oxidesemiconductor) sensor

• Size:85x35x60mm(3.25x1.375 x 2.375 in)

• weight: 140 gr (5 oz)• Power requirements: 12 VDC

at 300 mA. AC adapters availableworldwide.

• Outputs: LED bar graph, audioalarm, 0-3 V analog output suchas for data loggers, and externalalarm relay contacts; alarmactuation and relay contactclosure at .1 ppm (standard) andis programmable.

Page 45: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

TOP VIEW TYf

SPECIFICATIONSENTRY 8< EXIT PORTS 6.80”ø 011RECOMMENDED COUPLERS:

FERNCO 1070—66 OR EQUIVOR SCH. 80 PVC PIPE FITTINGS

DEBRIS REJECTION: 100 MESH>> 010011 CROSS SECTION

THROUGH PUT: 200 GPM GRAVITY FED

BODY MATERIAL WHITE POLYPROPYLENESCREEN 316 STAINLESS STEEL

5// DIA.

DEBRISEXIT

(TNS ~YW~ ~1TM~S fl~OMT •J~I~ fOE~fl 1C1 n11I •flOlY Cf ~thlCf Cc.na CS~.

I NflCf T)n ~JIf,

WATER CONTROL CORP.PMSEY. WI

RAIN DOWN SPOUTDEBRIS STRAINER

250 6PM

MOUNTINGBRACKETS1/8k X 1”SSTL

5~, DIA

REMOVABLE TOPFOR CLEANING 8<MAINTENANCE

5.0

776” 111kDOWNPORT SIDE VIEW ~ILESS OThERVA~ SPEGF1EO

DII€NSI~IS ME IN hOES pp~ici.

TIRE INITIAL DATE O~. NO. REV

E~AVN HET 9/16/09 AEta. HET 1/21/09 ~ fl sOAa I ~

Page 46: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

CAB

LES

INC

ON

DU

ITTO

CO

NTR

OL

COVE

R

PIPI

NG

FIN

ISH

FLO

OR

ELEV

ATIO

N

TOTR

ANSD

UC

ERTY

PELE

VEL

SUBM

ERSI

BLE

SU

BM

ER

SIB

LESC

ALE:

NO

NE

FOR

REF

EREN

CE

PUM

PD

ETA

IL

JUN

CTI

ON

BOX

PAN

EL

DIS

CH

ARG

EAN

DVA

LVES

PIT

VEN

TAI

RTIG

HTPI

T

PUM

PS

NO

TE:

1.TH

ISDE

TAIL

APPL

IES

SUBM

ERSI

BLE

(WES

TSE

WAG

E

TOPU

MP

(DU

SEW

AGE

PLEX

CO

NTR

OL

EJEC

TOR

EJEC

TOR

/GR

AY

PIT

ROO

MO

NLY

)

CO

NC

RET

E

WAT

ERAL

SOPA

NEL

)

ON

LY

Page 47: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

CAB

LES

INC

ON

DU

ITTO

CO

NTR

OL

PA

NE

LTR

AIN

PLAT

FORM

ELEV

ATIO

N

BOX

TYPE

PUM

PS

NO

TE:

1.TH

ISD

ETAI

LA

PP

LIE

SP

UM

P(D

UP

LEX

CO

SEW

AGE

PA

NE

L)EJ

ECTO

RS

ALS

O.

SU

BM

ER

SIB

LE

SU

BM

ER

SIB

LES

CA

LE:

NO

NE

FOR

REF

EREN

CE

ON

LY

DIS

CH

AR

CE

AND

VALV

ESPI

PIN

GPI

TV

EN

T

/AI

RTI

GH

TPI

TC

OVE

R

/JU

NC

TIO

N

NTR

OL

CO

NC

RE

TEPI

TS

UB

ME

RS

IBLE

TON

TRO

L PUM

PD

ETA

IL

Page 48: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

ACTUATOR — SEE ELEVATION

tiN STORM DRAIN 3—WAY DIVERTER VALVE DETAIL

8

3—WAY DfvV~1UtVALN’E — FWWIEKMODEl. MPF15OSIZE 200 (8~

CPUN

nII

14

~ti p

ACIUATOR - ELECTWCMODEl. SETh ES 70

21

ELEVATION

SCAl~E.~ NONE

Page 49: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

IO”ø

WEL

D

GEN

ERAL

NO

TE:

ALL

RIG

HTS

RESE

RVED

.TH

ISDR

AWIN

GOR

ANY

PART

THER

EOF

MUS

TNO

TBE

REPR

ODU

CED

INAN

YFO

RMwm

ioisr

ThE

WRI

TTEN

PERM

ISSI

ON

OF

HIG

HLAN

DTA

NK.

HIG

HLAN

DTA

NKSH

ALL

BERE

SPO

NSIB

LEO

NLY

FOR

ITEM

SIN

DICA

TED

ON

THIS

FABR

ICAT

ION

DRAW

ING

UNLE

SSO

THER

WIS

ENO

TED.

CUST

OM

ERIS

RESP

ONS

IBLE

FOR

VERI

FYiN

GCO

RREC

TNES

SO

FSI

ZE/

LOCA

TIO

NO

FFT

~T1N

GS•

ACCE

SSO

RIES

&CO

ATIN

GS

SHO

WN

ONTh

ISDR

AWIN

G

GEN

ERAL

SPEC

IFIC

ATIO

NS

MO

DEL

CUST

OM

NOM

INAL

CAPA

CRY:

41.2

36G

ALLO

NSTO

TAL

—2

TANK

STY

PE:

SING

LEW

ALL,

ABO

VEG

ROUN

DM

ATER

IAL

304

STAi

NLES

SST

EEL

GAU

GE

OF

SH

ELL

1/4

”G

AUG

EO

FHE

ADS:

1/4

”O

PERA

TING

PRES

SURE

:AT

MO

SPHE

RIC

PRO

VID

EDEQ

UIP

MEN

T1.

8”ø

PIPE

STUB

INLE

TW

I45

”EL

BOW

2.4”

ø1

50

jRF

SOFL

ANG

EFI

G3.

DISC

HARG

EVO

RTEX

BREP

J(ER

4.6”

øPI

PEST

UBO

VERF

LOW

5.DI

FFUS

ION

BAFF

LEW

/W

EAR

PLAT

E6.

36ӯ

MAN

WAY

7.LO

CKAB

LEHI

NGED

EASY

ACCE

SSUD

5.4”

NPT

GAU

GE

FIG

WIT

HPL

UG9.

1/4

’ST

RIKE

RPL

ATE

ATAL

LM

ANW

AYS

10.

8”ø

MAN

IFO

LDPI

PE—

SEE

DETA

IL11

.O

VERF

LOW

ELBO

W12

.4”

NPT

FIG

—TA

NKVE

NT13

.6”

FABR

ICAT

EDBE

AM14

.3”

ø15

00RF

SOFL

ANG

EFI

G

(iN

TREA

TED

GRA

YW

ATER

TAN

KTG

WT

Ri—

C—

i.TG

WT—

Bi—

D—

1

TANK

BSH

ELL

TANK

ASH

ELL

WEL

DAL

LAR

OUN

D—

TIP

8”ø

BUN

DR

AN

GE

B’s

SCH

40TR

ANSF

ERPI

PEW

ELD

TOTA

NKA

TANK

BOTT

OM

pw€

Daa

fmi-~

3SC

ALE:

NONE

Page 50: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

GM-i ~4m~L W6HE,t≤j6C&WElL 2—Inch Discharge Submersible Pun-~f0fl~ 1 ~~vn

Disch. Size 2 InchCommercial and induslrial applications.Pump clear waler, gray waler and effluent. Dlsch. Type ANSIHandles 3/4-inch solids from septic tanks, sump pits, Solids Max. 3/4 Inchloading docks, etc.

Mounting Style RemovalHigher Head, 3450 RPM

PumpCase - Cast IronImpeller - Cast IronStrainer - 304SSStainless Steel HardwareStainless Steel lifting cable —20 feet

MotorDouble Seal — Tandem

- Upper — Carbon against Ceramic- Lower— Silicon Carbide against

Silicon CarbideAir-Filled Hermetically SealedShaft — Stainless Steel Series 300Motor Shell — Cast IronInsulation — Class FBall Bearings —2— Double SealedPower Cord Length —25 ft.Three-phase motor —3450 RPM

- 60 Hz, 208-230 or 460 voltsSingle-phase motor —3450 RPM

- 60 Hz, 115 or 208-230 volts________ - Automatic reset thermal and

overload protection- Capacitor and start relay in motor

Disch. Minimum Basin Dia.Location Simplex Duplex

Above 24 Inches 36 InchesGradeBelow

24 Inches 36 InchesGrade

Sohme&bleWnt~ntvPump Associatw.isiam

Hi

Options• UL Explosion-Proof motor• Moisture Sensor and Temperature Limiter• Additional Power Cable Lengths

LIFTINGBArL

32 1/2MAX

3

11 -H

3450 RPM 1.0 S.C. 70’F Curve Number: CK 1622-3450Pump Size: 2 Inch ANSI

Impeller Type: Enclosed15894.1588015899

TOTAL HEADMTR PSI FT

37 52 120

33 48 110

30 43 100

27 39 90

24 35 80

21 30 70

18 26 60

15 22 50

12 17 40

9 13 30

6 9 20

3 4 10

U.S GALLONSPER MINUrE

20 40 60 80 100 120 140

cusic METERS 0 4 9 14 18 23 27 32 36 41PER HOUR

1 60 180

1622Replaces SN-1622, June 1, 2001 SN-1622 FEBRUARY 2, 2004

Page 51: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

WElL 2 Inch Removal System 2613-2

System Includes:• 2 Inch Floor Discharge Elbow• Upper Guide Pipe Bracket with Bosses

Flat Bracket for mounting to Weil 8800 Covers90 Degree Bracket for Below Cover Mounting

• Sliding Bracket for 2 inch discharge pumpStandard — IronUI. Explosion Proof— Bronze

Options:• Discharge Flange Kit for floor elbow discharge

Plain end pipe or threaded pipe• Intermediate Guide Bracket Assembly

90 Degree Bracket with mounting slotsMount to Discharge Pipe or Angle Brace in Wet WellFor ‘vet wells deeper than 20 feet

Not Included:

How to Order: Specie’ Order Number and Discharge Flange KitFOB. Cedarburg (Milwaukee), Wisconsin or Irvine. California

• Lifting Cables• Guide Pipe — I inch schedule 40

Cut to required lengths

Order 2 InchNumber Pipe Type Type

26131(202 Plain End Weil Oval26l3K102 Threaded Weil Oval

Discharge Flange Kit for plain end pipe includes- Discharge flange, Rubber Compression Gasket.

Two bolts, nuts, and washersDischarge Flange Kit for threaded pipe includes:

- Discharge flange with female threads, Gasket,Bolts, nuts and washers

wReplaces SN-26I3, August 1,2001

WcU On’ PiengeS.spptied WithWet Welt cover

Flat Upper GuidePipe Uraclcet Mount.To Wet. Well Cover

90’ intermediateGuide Pipe Bracicet

Weil OvalMount

Of WetCover

Order WeightNumber Description Lbs.

2613K102I Removal System with Flat Guide Bracket 422613K5013 Removal System with 90 Degree Guide Bracket 4226I3K2021 UL Explosion Proof System with Flat Guide Bracket 422613K6032 UL~ Explosion Proof System with 90 Degree Guide Bracket 422613K501 Sub Base - Minimum wet well dia. = 36 inches 40

205.666,002 Intermediate Guide Bracket Assembly 2For wet well deeper than 20 feet

Discharge Flange Kit

2613-2SN-2613-2 DECEMBER 1,2004

Page 52: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

WElL

• The 8165 is a flail featured duplex panel that controls twopumps with tilL explosion-proof motors.

• Panel can be operated on SOot 60 Hertz power.• Requires model 8234 single-pole level switches - three for

level control andone forhighwateralarm.• iWo 4 enclosure ftrr indoor or outdoor use. Provides a

degree of protection against falling rain, splashing water andbose-directed water undamaged by the formation of ice onthe enclosure.

• Exceeds Type 1,3K and 12 requirements.

Control Panel Selection Guide- Deaermlne Phase and Voltage- Determine maximum run current in

amps required by the pump motor.

8165Duplex

Panel Includes‘ti/L Listed Label - meets ti/L 698A• Lights, hour meter, switches, and test buttons are mounted on

inner door,• One lockable panel disco nncct; through-the-door with door

interlock on inner door. The mechanical interlock prevents thedoor from being opened when the disconnect is in the ONposition. Lock is not provided.

• Padlocldng hasp - on outer door, padlock not included.• Two lockable pump disconnects, one for each pump motor.

Lock is not provided.• Electric Alternator. Two Contactors-tndustrial Duty.• Two Overloads - one per pump. Ambient compensated hi

metallic (Class 10) motor overluad circuit protector.Instantaneous magnetic trip for short circuit protection. Single—phase protection for three-phase motors. Field adjustable withinthe amp range.

• Control transformer with tused primary and ltssedsecondary on all three-phase and single-phase 208 and 230-volt.Single-phase 115-volt has a fi,sed control circuit

• Pump run switches - one per pump. Three position TOA (test-off-automatic) with spring return to off from test.

• Green light indicates power to pump motor. One light per pump.• Amber light indicates control power on, Light is rated for

100,000 hours.• Red overload light indicates motor overload condition and pump

is off, Light remains on and pump remains off until reset. Onelight per pump.

• Hour meters (2). Non resetting meter indicntes total pump runtime.

• Moisture sensor relay and pump shut down circuit mounted insideenclosure. Amber lights indicate moisture in pump motor.Includes moisture sensor test button.

• Temperature limiter circuit shuts down pump motor when motorover temperature is sensed, The temperature limiter circuitautomatically resets when the motor temperature falls to anormal operating range. Blue light indicates there is a motorover temperature.

• Intrinsically safe relay and intrinsically safe circuit for 4 levelcontrol switches.

• High Water Alarm System.- HWA Test-Auto-Silence switch with spring return from test

and silence position.- Red HWA light on ismer door.- Hom, 95dB, and silence button mounted on side of enclosure.- Two isolated contacts for remote monitoring and/or

telephone connection,• Alann Dome Light - Lexan, red flashing on top of enclosure.

Light indicates a motor overload or high water alarm condition.Would also indicate moisture in motor or motor overtemperature if moisture sensor/temperature limiler option itordered. Light remains on until condition is corrected.

• Control Terminal hoard, numbered and wired.• Layout and schematic CAD diagrams use provided. Installer

connections at terminal board are clearly marked.

Duplex Alternating Pump Control PanelIntrinsically Safe Relay Meets U/L 698A

Type 4 Double Door Dead Front Enclosure

Alarm Light

it fl51

OUTER DOOR VIEW005)1

Enclosure size 2411 xZ4W x 81)

8165

uu

Order NumberMotorProtractor S~e-Phan Single-phase Three-Phase Appror.

208 or 230 208, 230,460 WeightLbs.Amp Range 115 Volts Volt, Volts —

1.0-1.6 8165-L-0l6 8165-D-016 8165-T-0l6 801.6-25 8165-L-025 8165-D-025 8165-T.o25 802.5- 4.0 8l65-L-040 8165-D-040 8165-T-040 804.0-6.3 8165-I.-06 Rl6i-D-063 SlSS-T-063 So

6.3 - 10.0 8l65-L-l0O 8165-V-ICC 8165-T-lOC 8010.0- 16.0 8165-L-160 8165-D-l60 8165-T-160 8116.0- 20.0 8165-L-200 8165-D-200 8165.T-200 8320.0- 25.0 8l65-L-250 8165-D-250 8l65-T-250 83

How to Order: Speci~’ the Order Number, System Phase and Voltage, and Pump Motor HP.FOB. Cedarburg (Milwaukee), Wisconsin 8165Replecos SN-8 165, August 2,2004 SN-8165 JULY 1, 2008

Page 53: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Duplex Alternating Pump Control PanelIntrinsically Safe Relay Meets UI 698A

Type 4 Double Door Dead Front Enclosure

HIGH WATRR 1® A!TO~

PUi~IP 2~: orr~j

PUMP 2

OVflLOAO OflRTtM7

PUMP 2

HOISThIflSEI4IOK

S

WElL 8165Duplex

Alarm Light

HORNINNER DOOR VIEW

SILENCE CONTROL POWER

PUMP I

PLOd? I

00OVIIILOAO Ovnmw

PLO!? I

QoMOI$IURE2~aOL

S8165 ]

8234 TetheredMounting

HWAJHigh Water

LSA

Lag/StandbyLS3

Cover

8165LS

SN-8165 JULY 1,2008

Page 54: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

1. The designer must determine the total system gpm typically using the combined cold and hot water fixturecount and then converting this to gpm using the Hunter curves.2. The designer then determines the required system boost pressure typically by adding the static lift for the highest fixture, the system friction loss at the maximum flow, and the minimum required inlet pressure of the fixturewith the highest inlet pressure requirement and then subtracts the minimum suction pressure supplied to thebooster system. Do not forget to also add the booster system pressure drop to the system boost pressure. Thiscan be determined by using the booster system Cv shown in the Pressure Booster Details Table.

Booster System Pressure Drop Equals: AP = (QICv)2

AP Booster System Pressure DropQ Booster System Maximum Flow RateCv Booster System Flow Coefficient

4. Using the pressure booster selection chart select a flow capacity that is equal to or the next larger flow required by the system. Select the pressure boost equal to or the next higher pressure required by the system.5. As an example select a duplex system that will produce 230 gpm at a pressure boost of 95psig. The modelnumber is a FMV2-9.6. Go to the Duplex Pressure Booster Detail Table and find that this model consists of two ITT 335VB-3/1 pumpswith 1 5HP motors, 2.5” check valves, 4” headers and has a system Cv of 75.7. System dimensions are shown on the Duplex Pressure Booster Dimension Table. Certified drawings should berequested for construction coordination

1 CONSULT FACTORY FOR ADDITIONAL SELECTIONS

PRESSURE BOOSTER SELECTION PROCEDURE fc’/’7t’5

DUPLEX PRESSURE BOOSTER SELECTION CHARTMODEL NUMBERS

0

BOOST CAPACITY (GPM)(PSI) 40 80 120 160 200 240 280 320 360 400 440 480 520 560 600

40 FMV2-1 FMV2-1 FMV2.1 FMV2.4 FMV2.4 FMV2.5 FMV2.5 FMV242 FMV2-12 FMV2-13 FMV2-13 FMV2-17 FMV2.17 FMV-217 FMV247

50 FMV2-1 FMV2-1 FMV2-1 FMV2-4 FMV2.4 FMV2-5 FMV2.5 FMV242 FMV2.12 FMV2.13 FMV2dI3 FMV2.17 FMV2.17 FMV2.18 FMV2.18

60 FMV2-1 FMV2-1 FMV2-2 FMV2-4 FMV24 FMV2-5 FMV2-7 FMV2-12 FMV2.12 FMV2-13 FMV2-I3 FMV2-18 FMV2-18 FMV2-18 FMV2-I3

70 FMV2.1 FMV24 FMV2.2 FMV2.6 FMV24 FMV2.7 FMVZ-7 FMV2-12 FMV2-12 FMV2-13 FMV243 FMV2-18 FMV2.18 FMV2-18 FMV2-18

~ 80 FMV2.2 FMV2.2 FMV2.2 FMV2-6 FMV2-8 FMV2-9 FMV2-9 FMVZ-12 FMV2-12 FMV2-15 FMV2.15 FMV2-18 FMV2.19 FMV2-19 FMV2-19

90 FMV2.2 FMV2.2 FMV2.2 FMV2-8 FMV2-8 FMV2-9 FMV2-9 FMV2-14 FMV2.14 FMV2-15 FMV2.15 FMV2-19 FMV2-19 FMV2-19 FMV2.19

100 FMV2-2 FMV2.2 FMV2~3 FMV2.8 FMV2.8 FMV2-9 FMVZ-9 FMVZ-14 FMV2-14 FMV245 FMV2.15 FMV2.19 FMV2.19 FMV2-19

110 FMV2-2 FMV2-2 FMV2.3 FMV2.8 FMV24 FMV2-9 FMV2.11 FMV2-14 FMV244 FMVZ-15 FMV2-15 FMV2-20 FMV2-20 FMV2-20

120 FMV2-2 FMV2-3 FMV2-3 FMV2.8 FMV24 FMV2.11 FMV2dh FMV2.14 FMV2.14 FMV2.15 FMV2-15 FMV2-20 FMV2-20 FMV2.2O

130 FMV2-3 FMV2.3 FMV2.3 FMV2.1O FMV2.1O FMv2.11 FMV2-11 FMV244 FMV2-14 FMV2-15 FMV2-16 FMV2-20 FMV2-20 FMV2-21

140 FMV2.3 FMVZ-3 FMV2-1O FMV2-1O FMV2.1O FMV2.11 FMV2.11 FMV2.14 FMV2.16 FMV2-16 FMV2-16 FMV2.21 FMVZ-21 FMV2-21

150 FMV2-3 FMV2-3 FMV2-1O FMV2-1O FMV2-1O FMV2-11 FMV2-11 FMVZ-16 FMV2-16 FMV2-16 FMV2.16 FMV2.21 FMV2.21 FMV2-22

Page 55: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

5~E NOTE#4

DUPLEX PRESSURE BOOSTER DIMENSIONS TABLE

3ooster Models Skid Length Skid Width Oversil Height Discharge Height Suction Height Center io Center Suction Discharge Boit Width Bolt Length

(SL) (SW) (OH) (DH) (SH) (CC) Connection Connection (BW) (BL)

~MY2L~, 3-6” I’S” ._5~0!L__ 1 n-sir 3-I” 1 25# 3’~3” 3,-n”FMV2-2 3-6” 3-6” 5-0’ 10-318” 10-318’ 3-1” 125# 125# 3-3” 3-0”

FMV2-3 3-6” 3-6” 5’O” 10-318 10-3/8’ 3-1” 125# 125# 3!_3!! 3-0”

FMV2-4 3-6” 3-6” 5-0” 11-118” 11-1/8” 2-7-1/8” 125# 125# 3!3!! 3-0”

FMV2-5 3-6” 3-6” 5-0” 11-1/8” 11-1/8” 2-8-3/8” 125# 125# 3’~3” 3-0”

FMV2-6 3-6” 3-6” 5L0” 11-1/8” 11-1/8’ 2-7-1/8” 125# 125# 3!3!! 3-0”

FMV2-7 3-6” 3-6” 5’O” 11-1/8’ 11-118” 2-8-3/8 125# 12511 3-3” - 3-0”

FMV2-8 3-6” 3-6” 6-0” 11-1/8” 11-1/8’ 2-7-1/8” 125# 12511 3-3” 3-0”MV2~9 3-6” 3-6” 6-0” 11-1/8” 11-1/8” 2’-8-3/8” 12511 12511 3-3” 3-0”

FMV2-10 3-6” 3-6” 6-0” 11-1/8” 11-1/8” 3-2-7/8” 125# 300# 3-3” 3-0”

FMV2-11 3-6” 3-6” 6-0” 11-1/8” 11-1/8”’ 3-1-7/8” 12511 30011 3-3” 3-0”

FMV2-12 3-6” 4-0” 6-0” 1-0-1/2” 1-0-1/2” 3-0-1/2” 12511 12511 3-8” 3-0”

FMV2-13 3-6” 4-0” 6-0” 1-0-1/2” 1-0-1/2” 3-2-5/8” 12511 12511 3-8” 3-0”

FMV2-14 4-0” 5-6” 6-0” 1-0-7/8” 1-0-7/8” 4-2-1/2” 12511 30011 5-2’ 3-6”

FMV2-15 4-0” 5-6” 6-0” 1-0-7/8” 1-0-7/8” 4-4-5/8” 125# 30011 5-2” 3-6”

FMV2-16 4-0” 5-6” 6-0” 1-0-7/8” 1-0-7/8’” 4-2-1/2” 125# 30011 5-2” 3-5

FMV2-17 4-0” 4-0” 6-0” 1-0-1)2” 1-0-1/2” 3-4-3/8” 12511 12511 3-8” 3-6”

FMV2-18 4-0” 4-0” 6-0” 1-0-1/2” 1-0-1/2” 3-4-3/8” 12511 125# 3-8” 3-6”

FMV2-19 4-0” 5-6” 6-0” 1-0-7/8” 1-0-7/8” 34-3/8” 12511 125# 5-2” 3-6”

FMV2-20 4-0’ 5,-B” 6-0” 1-0-7/8” 1-0-7/8” 4-6-5/8” 125# 30011 5-2”’ 3-6”

FMV2-21 4-0’ 5’-6” 6-0” 1-0-7/8” 1-0-7/8” 4-6-518” 12511 30011 5-2” 3-6”

FMV2-22 4-0” 5-6” 6-0” 1-0-7/8” 1-0-7/8” 4-6-5/8” 12511 30011 5-2” 3-6’

Notes:1) Connections are standard ASI stub ends with backup flanges. Grooved connections are available,2) All dimensions are in inches and may vary +/- 1/2”.3) Not for construction unless certified4) Reverse header connections are available,

-. —

DH

p

S

SF-I

-~ BwSW

Page 56: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

DUPLEX PRESSURE BOOSTER

DETAILS TABLE

~1ODEL ITT CHECK OPERATING# PUMPS HP VALVE HEADER CV WEIGHT(LBS) *FLA CGW CGH CGL

EMV2L_....~ 3 2” ._2J121L_ AL__ 7.0 1-4” ......1z21...... 1-6FMV2-2 3SVB-5 5 2” 21/2” 45 630 11.2 1-4 1/2 2-3” 1-6”

FMV2-3 3SVB-7 7.5 2” 21/2 45 652 17.8 1-5” 2L4” 1-6”FMV2-4 33SV8-2/2 7.5 2 112” 3” 75 1012 17.8 1-5 112 2-9” 1-6”FMV2-5 33SV6-2/2 7,5 2 1/2’ 4” 75 1052 17.8 1-5 1/2 2-9” 1-8”

FMV2-6 33SVB-2/1 10 2 1/2” 3” 75 1057 22.4 1-6” 2-10” 1-6”

FMV2-7 J3SVB-2/1 10 2 1/2” 4” 75 1097 22.4 1-6” 2-10” 1-6”FMV2-8 33SV8-3/1 15 2 1/2” 3” 75 1267 344 1-6 1/2” 2-11” 1-6”FMV2-9 33SV8-311 15 2 1/2” 4” 75 1315 34.4 1-6 1/2” 2-11” 1-6”

FMV2-1O 33SVB-4/1 20 2 1/2” 3” 75 1325 45.0 1-7” 3-0” 1,-a”FMV2-1I 33SVB-4/1 20 2 1/2” 4” 75 1365 45.0 1-7” 3-0” 1,-a”FMV2-12 ~6SVB-2/1 15 3” 4” 113 1442 34.4 1-9” 3-2” 1-6”

FMV2-13 I6SVB-2/1 15 3” 6” 113 1538 34.4 l’-9 112” 3-2” 1-6”

FMV2-14 168V8-3 25 3” 4” 113 2125 56.0 2-5” 3-3” 1-9”FMV2-15 I6SVB-3 25 3” 6” 113 2193 56.0 2-5” 3-3” 1-9”

FMV2-16 $6SVB-4/1 30 3” 4” 113 2253 66.0 2’-7” 3-4” 1-9”FMV2-17 368VB-1 15 4” 6” 200 1676 34.4 2-4 1/2” 3-1” 1-9”

FMV2-18 368VB-2/2 20 4” 6” 200 1758 45.0 2-4 1/2” 3-2” 1-9”FMV2-19 36SV8-2 25 4” 6” 200 2313 56.0 2’-?” 3-5” 1-9”

FMV2-20 S6SVB-3/2 30 4” 6” 200 2513 66.0 2-7 1/2” 3’-6” 1-9”FMV2-21 36SVB-3 40 4” 6” 200 2531 88.0 2-8” 3’-? 1/2” 1-9”FMV2-22 563V8-4 50 4” 6” 200 2770 108.0 2-8 1/2” 3-9” 1-9”

“Based on 460 VoItI3 Phase/GO Hertz, Premium Efficient, TEFC Motors

CGH

l~l~D

CD

U ouRfly

tGI_

Page 57: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

9.0

/ /9”

PV

CH

OU

SIN

G AIJ

AP

TOR

,8

X4

(2)

,ZR

ED

UC

ER

9

//

4’

PV

CP

IPE

(2)

H——

H--

-

-9

-9.

~9

.9

‘9

-

7.

•9

9

.9

-I

--—

H

-——

H

45

9.1

\

SC

RE

EN

(2)

OZO

NE

CA

rALV

ST

9.0-

17.0

DE

SIG

NE

DTO

RE

MO

VE

OZO

NE

FRO

MTA

NK

VE

NT

OFF

—G

ASE

XH

AU

ST

GAS

FLO

WR

ATE

:U

PTO

200

CFM

OZO

NE

CO

NC

EN

TRA

TIO

N:

UP

TO5

PPM

OZO

NE

RE

MO

VA

L:99

,8X

(mis

DRAN

9NC

CONT

FINS

PRO

PRET

ARY

MD

CCNf

lDET

J1tH

L:N

FOR

IdAf

lON

WHi

CHIS

INS

PRO

PERT

YD

rCU

STO

Mt?

PU

EQ

TECH

NOLO

GY

CORP

.M

Oka

YNO

TBE

USED

MD

/OR

REPR

ODU

CED

WIT

hOUT

WE

EXPR

ESS

WR

IflED

IPE

RDES

SIO

NCF

ThIS

CC

MP

Mf.

UN

tES

SD

INER

W:S

ESP

ECL9

EDD

IMEN

SIO

NS

ARE

ININ

CH

ESCU

STO

MAP

PLIE

DTE

CHNO

LOG

Y.G

YE

XD

EDIA

AL.O

G2

SM

AS

O1A

.F

L~

IDA

CO

RP.

.50<

DEO

MAL

*DO

D.0

<05

0MM

.D:5

T1IL

SFR

ADD

ON

/32

OZO

NE

DE

STR

UC

TOR

MO

LS

rF

or

TAN

KV

EN

TRU

NSUT

.50W

TiM

CO

NC

EP

T12

5/R

MS

DRBE

TTER

OHV

DIAC

H:NE

DP

MIS

.BR

EAK

SR4R

PCD

RNER

SD

OD

/BID

NOBU

RRS

PRO

JEC

T.

INIT

IAL

ISA

TEO

RG.

NO.

IREV

DRAL

4AI-lE

T4

/2/1

1A

lI-lE

T14

/2/1

1B

IOF

Page 58: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

irr~g_Wastewater Level Transmitter

VersaLine VL2000 Series

• 0.1% & 0.25% accuracy

• Ranges 10”WC-150 psi

• All welded 316L SS or Titanium

• Molded polyurethane cable

• 4-20 mA, 2-wire

• FM(C) Class 1,11,111, Div.1, GroupsA-G

The PMC VersaLine VL2000 Series submersible level transmitters are specifically designed for use inwastewater and pump/lift station applications. The ceramic sensing element provides a rugged flush openface design which avoids clogging or sludge build up from materials often encountered in wastewater. Thestainless steel construction will satisfy most applications. Where chemical environments dictate an optionof Titanium is available. The standard polyurethane vented cable is molded to the transmitter providingthe highest integrity waterproof assembly well proven in thousands of installations worldwide. FEP cableis available as an alternate for harsh environments. A feature of the VL2000 Series is full scale ranges aslow as 10” WC.

The VersaLine Series VL3000 and VL4000 offer similar performance with packaging suitable for deep welllevel measurements as well as sanitary flush designs for use in water and wastewater management, foodand beverage, pulp and paper, and pharmaceutical applications. Please refer to appropriate data sheets.

An extensive range of accessories is available including Sink Weights, Cable Hangers, and a uniquemethod of avoiding water ingress through the breather tube for vented gauge transmitters. Also offered areCalibration Adaptors, Lightning Protection, and cable Termination Boxes. Please see separate data sheetVLA 702 detailing these items.

—In

Precision Solutions for pressure, level, vacuum and humidity measurement

Page 59: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

Wastewater Level TransmitterFull Scale Ranges (Zero Based)

0-10, 20, 30, S0’WC0-1, 5, 10, 15, 30, 50, 100 psi9Other ranges and pressure units can be specined

~ Accuracy±0.1% FS (BSL) or ±0.25% FS (BSL)Combined non-linearity, hysteresis & repeatability

~ OverpressureFor full scale ranges up to 20 psi - loxAbove 20 to 150 psi-4X

~ Operating Temperature Range-10° to +175° F (-20° to +80° C)

~ Compensated Temperature Range30° to 85° F (-2° to +30° C)

~ Temperature Effects (Compensated)High accuracy (±0.1)±0.3°/o TEE for ranges 5 psi and above±1.0% TEE for ranges below 5 psi

Standard accuracy (±0.2%)±1.5°/o TEE for ranges 5 psi and above±2.0°/o TEE for ranges below 5 psi

~ Electrical2-wire, 4-20 mA, 10-35 Vdc power

~ Intrinsically Safe ApprovalAvailable with FM Intrinsically Safe Certification for usein Class 1,11, and III, Division 1, Groups A,B,C,D,E,F, & 0hazardous locations.Note: FMC approval is included for Canadian requirements.

~ CablePolyurethane molded vented with Kevlar, 4 conductorsContact factory for FEP cable

~ Housing316L Stainless Steel or TitaniumNote: 5-year corrosion warranty included for Titanium housing.

~ Weight7.6 ox. (excluding cable)

PMC adopts a continuous development program which sometimesnecessitates specification changes without notice.

(2) (1) (1) (3) Example Model Number

(2) Range, including engineering units(3) Cable Length(4) Specify if FM/IS approval is required

Example Ordering Format:VL2113-30”WC-O.25%-20’-IS

VersaLine VL2000 Series

When ordering please specify the following:

(1) Model number from table below

~p~~9EL - ConstructionOpen Face, Ceran,rn 1,,

Housing 7vlatenal1 316 Stainless Steel

2 Titanium - S year corrosion warranty

Electrical connectionI Polyurethane molded cable

2 FEP cable

Electncaj Configiration

~ 4-20rm’~

HART Communication Protocol

1/2” NPT Conduit Style CableConnection

PMC offers a range of accessoriesand variants for depth and leveltransmitters.

Please contact the factory forfurther information.

Represented By:

3: /I

sot u,.ll4Om~

1,—in~iaornar Process Measurement & Controls, Inc.

II Old sugar Hollow RoadDanbury, CT 06810 U.S.A.Tel: 203-792-8686Fax: 203-743-2051Email: [email protected] .com ~L2OOO 005

Page 60: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

M~1-~s-OPACTUATED CONTROL VALVES

CDNt1/1/2” -3” UNIMIZER®:2-WA V

SPECIFICATIONS

Static PressureiTemp:Service:

Flow Optimizer:Body Material:End Connections:Field Repairable Stem:Stem Seals:Ball Valve:

Ball Seals:Angle of Rotation:

360 PSI / 250°F (600 WOG)Chilled water, hot water, up to 50%Glycol,or contact factory foradditional fluids.Glass Filled PolymerForged Brass ASTM B283-06Brass — NPT, Sweat or BSPDual Teflon seals and EPDM 0-ringEPDM 0-RingsNickel-plated brass ballOptional: Stainless Steel ballTeflon Seals with EPDM 0-Rings0—90°

DIMENSIONS & WEIGHTS (NOMINAL) (measured in inches and lbs unless noted)

2803 Barranca Parkway, Irvine, CA 92606(949) 559-6000 Fax (949) 559-6088www.GriswoldControls.com

GRISWOLD0 CONTROLS

W637E4

B:HEIGHsizE MODEL cv A:LENGTH T c:LENGTH’ D:DEPTHFNPT SWT FNPT SWT (NOT SHOWN) E:HANDLE F:HEIGHT WEIGHT

0.38,0,681.3, 2.6, 4.7, 11.7 2.37 2.2a 3.78 6.65 6.65 6.321/2’ uR2A 3.00 2.02 1.0

6.0 2.64 3.03 4.10 6.65 6.75 8.62

0.31, 0.63, 1.2, 2.5, 4.3, 14.7 2.41 2.70 3.7a 6.65 6.54 8623/4” UR2B_ 3.00 2.02 1.2

10.1, 28.8 2.76 2.90 405 8.65 6.65 8.62

9.0, 28.4 2.76 2.88 4.10 6.65 6.65 8.64 1.21’ uR2c_ 4.4, 15.3, 54.2 3.04 3.l5 439 6.73 7.10 3.00 2.02 8.96 1.5

26.1, 43.9 4.29 4.78 4.87 7,38 7.42 945 2.6

4.4, 8.3, 14.9, 41.1 3.01 3.50 4,49 6.71 7.10 9.02 1.51-1)4” UR2D_ — — — 3.00 2.02

36.5, 102.3 3.62 3.88 4.87 7.05 7.13 945 2.6

22.8, 73.9 3.43 4.14 4.87 6.96 7,31 9.45 2.61-1/2” UR2E_ — ~- 3.00 2.02

41.3, 171.7 4.06 4.53 5.44 7.27 7.50 10.02 3.2

41.7, 108.0 3.98 5.04 5,44 7.21 7.72 10.02 3.22” UR2F_ — 3.50 2.02

57.0, 71.1, 100.0, 210, 266 4.90 5.59 6.06 7.69 8.03 10.65 5.02-1/2” uR2G_ 45.0, 55.0, 72.3, 101,162, 202 5.35 N& 6.06 7.91 N/A 3.50 2.02 10.65 ~

3” UR2H_ 49.0,63.0,820, 124, 145 5.73 N/A2 6.38 8.10 N/A 4.00 2.02 10.91 6.4

MODEL NUMBER SELECTION

Select a Ball Size: M1/2”, B3/4”, Cl°, I, U R 2

D1-l/4”, 21-I/2”, F2”, G2-1/2”, H3”

Select a Cv: see Flow Rate TableT= Optional

3” x 3”Aluminum

Hanging ID TagSelect Type: F=FNPT, 5=Female Sweat’, B=BSP-P

Select Ball and Stem: B=Slandard, S=Optional 316 SS, C=Standard Ball wilh SS slem

Insert Actuator Model Number. If Actualor is supplied by olhers, insert ‘1’ for Neptronic, ‘2’ for JohnsonControls, 3’ for Invensys, ‘4’ for Honeywell, 5 for Siemens, ‘6’ for Betimo, ‘7’KMC, “B”ELODrive

NOTES

‘ Dimension ‘C’ is maximum length, which is measured from end fitting or mounting plate, whichever extends farther.2 Sweat ends ore not available On 2-1)2’ and 3’ valves.

Rep/aces form F-4206 11/07This specification © 2007 Griswold Controls F-5395

Page 61: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

ACTUATED CONTROL VALVES 1/2” — 3” UNIMIZER®:2-WA V

Cv SELECTION AND FLOW RATE TABLE (GPM)

FLOWRATE (GPM) ~ DIFFERENTIAL PRESSURE (PSI) ACROSS VALVE

LINE MODEL FULL’ CLOSE 2-PositionSIZE NO. PORT OFF1iP4 HVAC Apps HVAC Modulating Apps

Cv

0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 7.0 10.0UR2A1 0.3 0.38 0.5 0.5 0.6 0.7 0.7 0.8 0.8 0.8 1.0 1.2UR2A2 0.5 0.68 0.8 1.0 1.1 1.2 1.3 1.4 1.4 1.5 1.8 2.2UR2A3 0.9 1.3 1.6 1.8 2.1 2.3 2.4 2.6 2.8 2.9 3.4 4.1

112” UR2A4 I3OPSI 1.8 2.6 3.2 3.7 4.1 4.5 4.9 5.2 5.5 5.8 6.9 8.2UR2A5 3.3 4.7 5.8 6.6 7.4 8.1 8.8 9.4 10.0 10.5 12.4 14.9UR2A6 • 8.3 11.7 14.3 16.5 18.5 20.3 21.9 23.4 24.8 26.2 31.0 37.0UR2A7 5.7 8.0 9.8 11.3 12.6 13.9 15.0 16.0 17.0 17.9 21.2 25.3UR2B6_ 0.2 0.31 0.4 0.4 0.5 0.5 0.6 0.6 0.7 0.7 0.8 1.0UR287 0.4 0.63 0.8 0.9 1.0 1.1 1.2 1.3 1.3 . 1.4 1.7 2.0UR2B8 0.8 1.2 1.5 1.7 1.9 2.1 2.2 2.4 254 2.7 3.2 3.8

~ UR2S1 iaopsi —ii— 3.1 3.5 4.0 4.3 4.7 5.0 ‘4634 7.9UR282 3.0 4.3 5.3 6.1 6.8 7.4 8.0 8.6 S91~9.6 11413.6UR283 • 10.4 14.7 18.0 20.8 23.2 25.5 27~5~. 29.4 3fl2 932.938.946.5L1R284 71 101 124 143 160 1754 -189 202 214 -226 267 319UR255_ • 20.2 28.6 35.0 40.4 45.2 49. 5~53T54 457.2 60.7 484.0 75.7 90.4UR2CI 6.4 9.0 11.0 12.7 14~2SkiI5,6 16849118.0 19~1’S20~1 23.8 28.5UR2C2 201 284 348 4024 19449 ~4929 531 -568 602 435 751 898UR2C7 31 44 54 62 270 ‘76 82v 48894 93 “98’ 116 139UR2C3 100PSI 108 153 $187.- 421 6 ‘242 265 2864 306 $325 342— 405 484UR2C4 383 542- 664~’767 8574 939~<101441084’ 1150 1212 1434 1714UR2C5 185 2619? 320 369 413 45244488 %5229-4554~ 584’ ‘691 825UR2C6 310 4391 538 621 69 4~ 760? 821 878 ‘931 9824 —1161 1388UR2D5 3.1 4t49’1 5.4 6.2’ 7.041 t7~7.69t 98.2 68 15134 9.8 ~1 991.1.6 13.9UR206 59 8399 102 117 131%> “144- 155 166 176-94 186 220 644

1 1/4 UR2DI ioopsi 105 1494 182 21 I 236 258 279 29& 316 333 -39~~ 471UR2D2 291 4114 503 581 650 s712 769 8229 872 1919’1087 1300UR2D3 25.8 3&54444.7 51.6 ~57f7 96&2% 68.3 73.0477.4 981.6 96.6 115.4UR2D4 - 72.3 102132. 4125.3 144a4 4161.8 I771Z 191.4 205 14217 229 271 324IJR2EI 16.1 22.84 427.9 32.29 99360 3916% 942.7 45.60 ~48.4 51.0 60.3 72.1

1 112 UR2E2 IOOPSI 2112 .PLL 1045 —1188 1280 1383 1478 1568 1652 1955 234UR2E3 29.2 41.3 996016> 58.4 165139 71 .5% 9977 3 82.6 87.6 92.3 109.3 130.6UR2E4 • 121.4 171.7 921041 243 >27299 29749 ‘321 343 364 384 454 543UR2F1 29.5 41.7 519-141 059.0 65997 72.2 78.0 83.4 88.5 93.2 110.3 131.9UR2F2 • 76.4 108.0 132.399152.7. ~17O8 187.1 202 216 229 242 286 342UR2F5 40.3 57.0 69.8 <80.6299990.1 98.7 106.6 114.0 120.9 127.5 150.8 180.2

2 uR2F3 IOOPSI 503 711 87.1 100.6 112.4 123.1 133.0 142.2 150.8 159.0 188.1 225IJR2F6 70.7 100.0 122.5 141.4 158.1 173.2 187.1 200 212 224 265 316UR2F7 148.5 210 257 297 332 364 393 420 445 470 558 664UR2F4 • 188.1 268 326 376 421 461 498 532 564 595 704 841UR2G2 31.8 45.0 55.1 63.6 71.2 77.9 84.2 90.0 95.5 100.8 119.1 142.3UR2G3 38.9 55.0 67.4 77.8 87.0 95.3 102.9 110.0 118.7 123.0 145.5 173.9

2-1/2” UR204 IOOPSI 50.9 72.0 88.2 101.8 113.8 124.7 134.7 144.0 152.7 161.0 190.5 228UR2GS 71.4 101.0 123.7 142.8 159.7 174.9 189.0 202.0 214.3 225.8 267.2 319UR2G6 114.6 162.0 198.4 229 256 281 303.1 324 344 362 429 512UR2G7 • 142.8 202 247 288 319 350 378 404 429 452 534 639UR2H1 34.6 49.0 60.0 69.3 77.5 84.9 91.7 98.0 103.9 109.6 129.6 155.0UR2H2 44.5 63.0 77.2 89.1 99.6 109.1 117.9 126.0 133.6 140.9 166.7 199.2

3” UR2H3 IOOPSI 58.0 82.0 100.4 116.0 129.7 142.0 153.4 164.0 173.9 183.4 217 259UR2H4 87.7 124.0 151.9 175.4 196.1 215 232 248 263 277 328 392UR2HS • 102.5 145.0 177.6 205 229 251 271 290 308 324 384 459

NOTES

These valves are full port and do not have the Optimizer insert.Close-Off Pressures measured with 35 in-lb. actuator. The tlose Off Pressure” is the maximum allowable pressure drop across the valvebody when the valve is fully closed. (Do not use actuators with torques higher than 90 in-lbs)

Cv is defined as the quantity of water in GPM at 60°F that will flow through a given valve with a pressure drop of I PSI. Hence the 1.0 PSIpressure differential column in the table above is equivalent to the Cv value.

Replaces form F-4206 11/07This specification © 2007 Griswold Controls F-5395

2803 BarranCa Parkway, Irvine, CA 92606(949) 559-6000 Fax (949) 559-6088 ~pjj C RI SV~(O L D7www.GriswolclControls.com ~ CONTROLS

Page 62: ENGINEERING REPORT PROVIDED TO THE SAN …tjpa.org/uploads/2017/07/Exhibit_I_Non-Potable_Water_System_Report.pdfENGINEERING REPORT PROVIDED TO THE SAN FRANCISCO DEPARTMENT OF PUBLIC

ACTUATED CONTROL VALVES 1/2”— 3” UNIMIZER®:2-WAV

ACTUATOR MODEL NUMBER SELECTION

Griswold Controls EMO-35F-24 EMO-35M-24 EMO-35F-24- EMO S SR

Private Label EMO-35Fv-24 EMO-35MV-24 -70 -24Torque_of 35_in-lbTorque_of 70_in-lbControl_Signal_On/OffControl_Signal_3_PointControl Signal Modulating 2—10 VDCSpeed 150 sec 150 sec 8-10 sec 150 secFail_Safe_(Spnng_Return)Operating Power 4VA 4VA 6VA 8VAWeight 1 5 pounds 1 5 pounds 2 2 pounds 42 pounds

~L ~Wiring Diagram I 2~j~ 1~ 2p ~~D:L4V] ~ ~_j/ ~ 2l~,,

PowersLppiy Pc~ersuFQiy I Pa~ersti~Iy

Where I is Floating 0(2) 1OVControl 0() iCY

and_2is_On/Off Control

Griswold Controls GCDEI3I.IP GCDEIGI.IP GCMAI2I.IP GCMAI3I.IP GCMAI6I IP

Private LabelTorque_of 44_in-lbTorque_of 62_in-lbControl_Signal_On/OffControl_Signal_3_PointControl Signal Modulating 0—10 VDCSpeed 9osec 9osec 9osec 90 sec 9osecFail_Safe_(Spring_Return)Operating Power 3 3 VA 3 3 VA 5 VA 5 VA 5 VAWeight 1 I pounds 1 1 pounds 3 0 pounds 3 0 pounds 3 0 pounds

6 iNPUT OUTPUT SUPPLY ~w cow INPUT outputVA V

Wring Diagram

‘~T__~~‘ 1 2 NEUTRAL SUPPLY NEUTRAL A A

Pcs~Supj1y

ADDITIONAL COMPATIBLE ACTUATORS:LM24, LM24S, LF24, LF24S, LF120, LF120S, LF24-3, LF24-35, LM24SR, LF24SR, LF24SRSBN-44C1U, BNP-44C1U, BS-26F1U, BSP-26F1U, BN-44P1U, BNP-44P1U, BS-26P1U, BSP-26P1ML6161D2006. ML6174D2009, ML7161A2008, ML7174A2001, ML6185A1000, ML6185C1008, ML8185A1008,ML81 85C1 006. ML7285A1007, ML7285C1005

Johnson Controls: M9106-AGA2, M9106-AGC2, M9106-GGA2, M9106-GGC2, M9206-AGA2, M9206-AGC2, M9206-GGA2, M9206-GGC2KMC Controls: MEP-5072, MEP-5073, MEP-5372, MEP-5373Neptronic: BBT-24, BBT-l000. 88T-1060, BBT-102i, BET-bOO, BBTHV-1100, BBTHV-1160, BBTHV-1120, BBTHV-1180,

BBM2000A, BBM2060ASiemens: GDE13I.1P, GDE161.1P, 0DE136.1P, GDE1S6.1P, GMA121.1P, GMA161.1PTAC: MF4O-6083, MA4O-7043, MA4O-7043-501, MA4O-7040, MA4O-7040-501, MF4O-7043, MF4O-7043-50i, MS4O-7o43, M540-

7043-501

Replaces fomi F-4206This specification © 2007 Griswold Controls

2803 BarranCa Parkway, Irvine, CA 92606(949) 559-6000 Fax (949) 559-6088www.GriswoldControls.com

Belimo:ELODrive:Honeywell:

11/07F-5395

fl GRISWOLd0 CONTROLS