11
ngineering Operations New hazards in the NTC associated with upgrade activities: Ladders, scaffolds, man-lifts. Cranes, rigging, forklifts. Welding, burning, grinding. Activated/Contaminated radiological work. Electrical Confined spaces. Chemical use. Eye hazards. Uneven work surfaces. A Health and Safety Plan (HASP) and Work Control Center Procedures in force. Address the control of hazards Maintain configuration control Coordinate required permits, technical procedures, etc.

Engineering Operations

  • Upload
    mareo

  • View
    33

  • Download
    0

Embed Size (px)

DESCRIPTION

Engineering Operations. New hazards in the NTC associated with upgrade activities: Ladders, scaffolds, man-lifts. Cranes, rigging, forklifts. Welding, burning, grinding. Activated/Contaminated radiological work. Electrical Confined spaces. Chemical use. Eye hazards. Uneven work surfaces. - PowerPoint PPT Presentation

Citation preview

Page 1: Engineering Operations

Engineering Operations

New hazards in the NTC associated with upgrade activities:• Ladders, scaffolds, man-lifts.• Cranes, rigging, forklifts.• Welding, burning, grinding.• Activated/Contaminated radiological work.• Electrical• Confined spaces.• Chemical use.• Eye hazards.• Uneven work surfaces.

A Health and Safety Plan (HASP) and Work Control Center Procedures in force.

• Address the control of hazards• Maintain configuration control• Coordinate required permits, technical procedures, etc.

Page 2: Engineering Operations

Engineering Operations

Heavy Construction started this winter:• TF turnbuckles and clevis pads have been ground away.

Page 3: Engineering Operations

Engineering Operations

• Space has been cleared for the 2nd Neutral Beam.

Page 4: Engineering Operations

Engineering Operations

• Additional rib welding completed on the upper/lower domes.• New machine platforms installed.

Page 5: Engineering Operations

Engineering Operations

• In-vessel metrology for NB armor installed and brackets welded in place.

• Passive plates were reinstalled in April.

Page 6: Engineering Operations

Engineering Operations

• Outer TF coils #7 and #11 have been removed.

Page 7: Engineering Operations

Engineering Operations

• Platform modifications/usage required for the TF work

Page 8: Engineering Operations

Engineering Operations

• Bay J-K nozzles have been cut away

Page 9: Engineering Operations

Engineering Operations

Upcoming Vessel Modifications:• Installation of In-vessel stiffeners at Bays J-K.

• Ongoing welding of new TF Clevis pads onto VV.

• Weld the new Bay J-K Cap onto the vacuum vessel in early July for the new NB port.

• Vacuum vessel cuts at Bay L in mid-July for MPTS.

• Vacuum leak checking

• Remove platforms at Bays J-K-L in preparation for neutral beam work

Page 10: Engineering Operations

Engineering Operations

Neutral Beam work in the NTC:• Penetrations into NTC for cryo/electrical systems.

• Move Beam-Line into NTC in early August.

• Move lid/cryo-panels, 90” flange, torus and ion source interfaces into NTC in Aug/Sept

• Decontamination of both the NTC and the TTC

• Installation of beam-line systems and HVE’s throughout the fall.

Page 11: Engineering Operations

Engineering Operations

Future NTC Access:• Upon completion of the NB equipment moves, we should be

able to provide greater access to the perimeter of the test cell.

• Access to the North door will remain limited while assembling/commissioning the NB HVE’s and transmission lines.

• Internal and External access to the vessel itself will remain restricted into the spring of 2013 due to ongoing welding of the umbrella legs, PF supports, etc.