Upload
warren-armstrong
View
213
Download
0
Embed Size (px)
Citation preview
Engineering Ethics
WVU Parking Group 12
Heather Roberts, Lance Pearce, Jacob Tyo, Jeffery Blankfeld
• 1957 Construction began on the Cypress Street Viaduct
• This freeway was built to connect to I-80 in the San Francisco Bay Area
• The final design was a reinforced concrete, 2km, two-tier highway with 5 lanes per deck
• However it was constructed over portions of soft mud where the bedrock was over 150m below the surface
• In 1971 stricter seismic criteria was required to increase resistance against earthquakes
• These precautions were voided
Cypress Street Viaduct
Cypress Street Viaduct
• October 17th, 1989 an earthquake, measuring 7.1 on the Richter Scale, Loma Prieta shook the San Francisco Bay area
• Nearly 1.4km out of the 2km stretch collapsed
• The soft bay mud that it was constructed on increased the amplitude of vibrations
• Breaks in the freeway almost exactly matched the angular frequency of the seismic waves
• Out of the total 65 deaths, 35 were due to the viaduct
Cypress Street Viaduct
• Well-graded soils help to dampen vibrations • Inadequate compensation for weak soil conditions• Insufficient reinforcement in concrete columns • Disaster could've been avoided if they followed
through with recommended upgrades • Todays reconstruction includes steel reinforcing
for compensation • Reconstruction cost estimated at $1.25 billion
Ford Pinto
• In the late 60’s Ford introduced the new affordable Ford Pinto
• Under 2000lbs and $2000• Production and design of typical car
took an average of 43 months where as the Pinto only took 25
• After initial crash tests were conducted a serious defect in the gas tank was revealed:
• In crashes over 25mph the gas tank always ruptured
• In crashes over 40mph it was likely that the doors would jam leaving the passengers with no escape
• No further changes were made to the Pinto before it was put on the market.
Ford Pinto
• Engineers were aware of the problem but did nothing to change it
• The cost of fixing the problem out weighed the cost of settling lawsuits
• One engineer quoted “Safety doesn’t sell”• These minor changes could’ve potentially prevented over
180 deaths due to fire
• 1976 Crown Center Redevelopment Corporation plans to design a Hyatt Regency Hotel in Kansas City.
• 1976 Gillum-Colaco Inc. hired to be Structural Engineers for project.
• 1978 Project Prepared using Kansas City building codes.
• 1979 Construction begins as schematics are signed off.
• 1979 Minor roof collapse, construction continues as planned.
• 1981 Major walkway collapse killing 144 and injuring 200 more.
• 1984 Missouri Board of Ethics files suit against Gillum-Colaco charging negligence, incompetence, and unprofessional conduct.
Hyatt Regency Walkway
• 1984 G.C.E International, Inc. found guilty of all charges against them.
• Engineers involved lost licenses to practice engineering in Missouri.
• American Society of Civil Engineering states that structural engineers have full responsibility for design aspects and all liabilities.
• Duncan and Gillum now practicing in States other than Missouri.
• Main issues of concern involved here are:• Negligence
• Apathy
• Dishonesty
Hyatt Regency Walkway
• Potential ethical issues for our project include:• Wrongfully issuing tickets to payed customers.
• Not properly documenting infractions, leading to confusion if client wishes to dispute a ticket.
• Not securing all P.I.I in regards to credit card information, license plate numbers, names, student ID numbers.
• A full scale implementation of these solutions could reduce the amount of workforce needed to monitor parking.
• Efforts to avoid ethical issues:• Send all ticket notifications to University parking
authorities to issues tickets.
• Develop a secure database and webpage to host all information entered into the application.
• Re-assign the workforce to monitoring the system for crashes and bugs.
Parking Project