87
RE DEVELOPMENT OF KIDWAI NAGAR (EAST) IS A PRESTIGIOUS PROJECT UNDER MINISTRY OF URBAN DEVELOPMENT, GOVT. OF INDIA NBCC, A NAVRATANA CPSE UNDER MOUD, IS THE IMPLEMENTING AGENCY FOR THIS PRESTIGIOUS PROJECT TRAFFIC CONSULTANTS Engineering and Planning Consultants

Engineering and Planning Consultants - uttipec.nic.in · Delhi haat Metro U/C BBSB Setu U/C. CHECKLIST 16 – SAFETY AUDIT FOR VULNERABLE ROAD USERS Sl# DESCRIPTION OBSERVATIONS 1

Embed Size (px)

Citation preview

RE DEVELOPMENT OF KIDWAI NAGAR (EAST) IS A PRESTIGIOUS PROJECT UNDER MINISTRY OF URBAN DEVELOPMENT, GOVT. OF INDIA

NBCC, A NAVRATANA CPSE UNDER MOUD,  IS THE IMPLEMENTING AGENCY  FOR THIS PRESTIGIOUS PROJECT

TRAFFIC CONSULTANTS

Engineering and Planning Consultants

SCOPESCOPE

PROPOSAL FOR CONNECTIVITY OF  EAST KIDWAI NAGAR

• Towards Baba Banda Singh Bahadur Setu (BBSB Setu) phase II

• Safe Pedestrian Crossing at T‐ Junction of BBSB Setu Phase II & Aurbindo Marg

• Kidwai Nagar (East) has been identified as one of the colonies for redevelopment as General

Pool Residential Accommodation (GPRA) on 27/07/1993 under Approved Zone D in Master

Plan of Delhi by DDA .

PROJECT  STATISTICSPROJECT  STATISTICS

Existing structures(in 2013)

2444 nos. (Type‐I, Type II &  Type V quarters ) 3 Schools, Some local shopping markets, Religious structures, etc.

Plot Area  • 86 Acres  (3,48,029 Sqm) 

Area under Darya Khan Tomb (schedule B)  • 14 acres 

Area under Redevelopment  • 72 acres 

FAR permissible  as per MPD 2021  • 300 (10,44,087 sqm) 

FAR achieved  • 203 (6,96,167 sqm) 

Office / commercial  complex as permissible  • 10% (1,04,412 sqm) 

Car parking provided in basement  • 10639 nos 

Total Density Achieved  • 134 DU/ Ha 

Total Ground Coverage Achieved  • 23.43% 

Existing green area  • 13% (47,000 sq M ) 

Green area provided  • 47% (1,65,000 sq M)

Sl No HOUSING  TYPE Existing(IN 2013) PROPOSED

1 Type I  1336  Nil 

2 Type II  1000  780 

3 Type III  1025 

4 Type IV  1472 

5 Type V  108 1078 

6 Type VI  192 

7 Type VII  61 

Total Nos. of Units 2444 4608

PROJECT  STATISTICSPROJECT  STATISTICS

TOWARDS SARAI KALE KHAN

SITE AND ENVIRONSSITE AND ENVIRONS

VIKAS SADAN

DILLI HAAT

AIIMS SAFDARJANG HOSPITAL 

SOUTH  EXT.

TO DHAULA KUAN

PROJECT SITE 

RING     ROAD 

ACCESS‐1ACCESS‐

2

ACCESS ‐3 

ACCESS ‐4 

ACCESS‐5 

ACCESS‐6 ACCESS‐7 ACCESS‐8

EARLIER APPROVED ACCESS SYSTEMEARLIER APPROVED ACCESS SYSTEM

In earlier approved access system 4 nos entry/exit (namely 1 to 4 ) were present towards upcoming Baba 

Banda Singh Bahadur Setu (BBSB Setu) Phase II road/flyover construction. Same was to be incorporated by 

PWD in their connectivity drawing

While PWD submitted the connectivity drawing to UTTIPEC entry/exit no 1 & 2 were incorporated but 

entry/exit 3 & 4 were not incorporated due to some technical reason (presence of JJ cluster).

For entry/exit 3 & 4 joint survey was conducted by UTTIPEC/PWD/DMRC/NBCC In the joint survey it was 

observed that entry/exit 3 & 4 was not possible due to presence of JJ cluster, hence NBCC was advised to 

carry out the feasibility study with alternate plan

NBCC appointed M/s EPC  to carried out feasibility study and prepared alternate plan in concurrence with 

PWD and DMRC

The  feasibility report was submitted to UTTIPEC which was reviewed in Working Group‐II A , 34th meeting 

held on 07.04.2016. In this meeting, group members had certain observations which were incorporated 

and presented in 35th Working Group Meeting held on 25.05.2016.

Back ground/ChronologyBack ground/Chronology

In 35th Working Group meeting of UTTIPEC held on 25.05.2016 in which it was recommended that 

PWD & NBCC will  integrate the safe pedestrian crossing at Aurobindo Marg T‐ Junction and will 

submit the road safety audit report for further discussion in working group meeting

M/s EPC and M/s RITES was engaged by NBCC to prepare proposal for Safe Pedestrian Crossing and 

Conduct Traffic Safety audit at T‐ Junction of  BBSB Setu Phase II road/flyover & Aurbindo Marg. 

Same was presented in 39th Working Group Meeting held on 07.02.2017.

The proposals of signalized at grade crossing at T Junction and underpass across Aurbindo Marg for 

safe pedestrian crossing was recommended by Working Group and it was advised that NBCC should 

submit it with the comments of all stakeholders for further consideration by Governing Body. 

Proposed connectivity no 3 & 4, prepared in concurrence with NBCC, PWD & DMRC and Proposal of  

safe pedestrian crossing at T‐ Junction is being submitted for further consideration of Governing 

Body.

Contd.Contd.

Proposed Access 3 & 4 ( Mutually agreed by PWD, NBCC & DMRC)

DETAIL OF MODIFIED ACCESSESDETAIL OF MODIFIED ACCESSES

BUS STOP AS PER MMI PLAN

TWO LANE ONEWAY CB MARG

SUGGESTIVE KASHMIRI MARKET ACCESS

Pedestrian plaza

CRITICAL PEDESTRIANAREA

RUMBLE STRIPS OR ANY TRAFFIC CALMING MEASURES

VIEW OF PROPOSED ACCESS NO 3VIEW OF PROPOSED ACCESS NO 3

NALA

DETAIL OF AFFECTED ACCESSES (ACCESS NO 3)DETAIL OF AFFECTED ACCESSES (ACCESS NO 3)

NALA

VIEWS OF  PROPOSED ACCESS ‐3 FROM NMT AREA VIEWS OF  PROPOSED ACCESS ‐3 FROM NMT AREA 

VIEW FROM KIDWAI NAGAR PROJECT TOWARDS  INA SIDEVIEW FROM KIDWAI NAGAR PROJECT TOWARDS  INA SIDE

EAST KIDWAI  NAGAR BONDARY

INSIDE  

EAST KIDWAI  NAGAR BONDARY

INSIDE  

BACK

VIEW FROM KIDWAI NAGAR PROJECT TOWARDS  INA SIDEVIEW FROM KIDWAI NAGAR PROJECT TOWARDS  INA SIDE

SAFETY AUDIT OF PEDESTRIAN SAFETY MEASURES AT T-JUNCTION OF BABA BANDA SINGH BAHADUR SETU WITH

AUROBINDO MARG

STUDY LOCATIONSTUDY LOCATION

Metro entry/exit

Metro entry/exit

SITE APPRECIATIONSITE APPRECIATION

Downstream Ramp of BBSB Setu (Gradient 2.56%) Upstream Ramp of BBSB Setu (Gradient 2.5%)

View of study location for pedestrian crossing View of Study location from Delhi haat

SITE APPRECIATIONSITE APPRECIATION

U/C ramp of BSSB setu in Barapullah Drain (Gradient 3.8%) INA market

U/C INA Interchange entry/exit Existing Pedestrian activity on Aurobindo Marg

SITE APPRECIATIONSITE APPRECIATION

View of Aurobindo Marg (near Petrol Pump) Traffic waiting on pedestrian signal on Aurobindo Marg

Pedestrians at INA metro station NMT vehicles on C.B. Marg

SITE APPRECIATIONSITE APPRECIATION

Queue of Vehicles at Petrol Pump on Aurobindo marg

A panoramic view of Aurobindo Marg with BBSB Setu and NBCC complex on LHS and Delhi haat and U/C INA metro entry/exit on RHS

Pedestrian Plaza of Delhi Haat

Aurobindo marg

NBCC Complex U/C

Delhi haat Metro U/CBBSB Setu U/C

CHECKLIST 16 – SAFETY AUDIT FOR VULNERABLE ROAD USERSCHECKLIST 16 – SAFETY AUDIT FOR VULNERABLE ROAD USERS

Sl # DESCRIPTION OBSERVATIONS

1 Has there been a survey of non-motorised vehicleand pedestrian flows?

Details not available

2 Will there be any major conflicts between motorizedtraffic and pedestrians and other disabled /handicapped road users?

Yes, Pedestrians willhave conflict with trafficon elevated road whilecrossing the road

3 Have pedestrians need for crossing the road andwalking safely alongside it been adequatelyprovided for?

Zebra Crossings withPelican signals proposed

4 Have measures been taken to reduce the accidentrisk for children going to and from roadside schools(Pedestrian guardrail may be needed to preventchildren from running out into the road)?

Details not shown

CHECKLIST 16 – SAFETY AUDIT FOR VULNERABLE ROAD USERSCHECKLIST 16 – SAFETY AUDIT FOR VULNERABLE ROAD USERS

Sl. # DESCRIPTION OBSERVATIONS

5. Have the need of cyclists and other non-motorised vehicles been provided

Cyclist will cross the roadalong with pedestrian

6. Where necessary, is fencing installed to guidepedestrians and cyclists at crossings oroverpasses?

Details not available

SAFETY AUDIT FOR VULNERABLE ROAD USERSSAFETY AUDIT FOR VULNERABLE ROAD USERS

Sl # SAFETY ISSUES/CONCERNS OBSERVATIONS

1 Zebra crossing proposed at the merging of 2.56%down gradient / 2.5% up gradient

Two sets of Raised Barmarkings proposed ondown gradients to warnthe drivers

2 It will be difficult for the speeding vehicle to stop ondown gradient

Pelican signal have beenproposed to stop thetraffic

Design speed at the intersection shall be 40% ofapproach speed

As elevated highway design speed is 80 km/hr, speedintersection shall be 32 km/hr

A reverse curve of 60m radius provided 200m beforeintersection i.e. a design speed of 30 km/hr

A 15m curve provided at intersection with AurbindoMarg i.e. a design speed of 15 km/hr

SAFETY ENHANCMENT –SPEED REDUCTION BY HORIZONTAL GEOMETRYSAFETY ENHANCMENT –SPEED REDUCTION BY HORIZONTAL GEOMETRY

STOPPING SIGHT DISTANCE (IRC 66-1976)STOPPING SIGHT DISTANCE (IRC 66-1976)

SAFETY ENHANCMENT –RAISED BAR MARKINGS AS PER IRC 35 (2015)SAFETY ENHANCMENT –RAISED BAR MARKINGS AS PER IRC 35 (2015)

SAFETY ENHANCMENT –RAISED TABLE TOP CROSSING AS PER IRC 103(2012)SAFETY ENHANCMENT –RAISED TABLE TOP CROSSING AS PER IRC 103(2012)

Signalized turning pockets may be provided where left-

turning volumes are high. Raised table top crossings may

also be introduced and shall invariably be provided at slip

roads, with a minimum 20-seoond pedestrian signal, to allow

pedestrian and cyclists to cross the road safely and

comfortably at the same level. Table top with flat surface will

be preceded followed by the gradient at 1:15

SAFETY ENHANCMENT –RAISED TABLE TOP CROSSING AS PER IRC 103(2012)SAFETY ENHANCMENT –RAISED TABLE TOP CROSSING AS PER IRC 103(2012)

ESTIMATION OF PEDESTRIAN TRIPSESTIMATION OF PEDESTRIAN TRIPS

Zoning of Project Site

(INA Metro stn.)

(AIIMS Metro stn.)(South-ex Metro stn.)

ESTIMATION OF PEDESTRIAN TRIPSESTIMATION OF PEDESTRIAN TRIPS

Zone‐wise distribution of Housing units and office complex

FLAT TYPENO. OF DWELLING UNITS

ZONE 1 ZONE 2 ZONE 3Type 2 355 - 425Type 3 683 - 342Type 4 779 - 606Type 5 504 630 -Type 6 - 192 -Type 7 - 61 -Total 2361 883 1373

Zone No. Office Complex (in sqm)2 52,0003 52,000

ESTIMATION OF PEDESTRIAN TRIPSESTIMATION OF PEDESTRIAN TRIPS

Assumptions for Daily Trip Estimation

Trip Factor Assumption

Average house hold size 4 Per Capita Trip Rate (PCTR) 2Peak Hour Trip Share 10% of Daily Trips

ESTIMATION OF PEDESTRIAN TRIPSESTIMATION OF PEDESTRIAN TRIPS

Assumptions for PT Trip EstimationType of Housing PT Share (%)

Type 2 and Type 3  80%Type 4, Type 5, Type 6  & Type 7 40%Office complex 70%

Estimated Trips

Zone  Daily PT Trips Peak PT Trips Influence  Metro Station

1 11280 1128 INA 2 8660 866 South‐ex3 12784 1278 AIIMS 

ESTIMATED TRAFFIC VOLUME ON MAJOR ROADS ESTIMATED TRAFFIC VOLUME ON MAJOR ROADS

Road Name

Direction of Traffic

Peak Hour Traffic (No. of Vehicles) growth @5%

2016 2021 2022 2023 2024 2025 2026 2027

Baba Banda Singh

BahadurSetu

To Aurobindo marg 2882 3679 3863 4056 4259 4472 4695 4930

From Aurobindo marg 1275 1627 1708 1793 1883 1977 2076 2180

From AIIMS Ramp 1275 1627 1708 1793 1883 1977 2076 2180

Aurobindo Marg

AIIMS to INA 5758 7349 7717 8102 8507 8933 9380 9848

INA to AIIMS 5506 7027 7379 7748 8135 8542 8969 9417

C.B. Marg To Thyagraj stadium 1386 1769 1857 1950 2047 2150 2257 2370

Source: Barapullah Phase‐1 traffic data (2013), PWD, Aurobindo Marg and CB marg traffic data (2015), RITES

ALTERNATIVE OPTION EVALUATIONALTERNATIVE OPTION EVALUATION

1. AT-GRADE PEDESTRIAN CROSSING FACILITY

2. FOOT OVER BRIDGE OVER BBSB SETU

3. SUBWAY UNDER AUROBINDO MARG

WALKING DISTANCE MEASUREMENT FOR ALL OPTIONSWALKING DISTANCE MEASUREMENT FOR ALL OPTIONS

AT-GRADEFOOT OVER BRIDGESUBWAY

FOB95 -110 Meter

ALTERNATIVE OPTION EVALUATIONALTERNATIVE OPTION EVALUATION

AT-GRADE PEDESTRIAN CROSSING FACILITY

STUDY OBJECTIVESSTUDY OBJECTIVES

• Evaluation of pedestrian/vehicular delay and queue lengths for different scenarios to analyse the requirement of pedestrian facilities for safe crossing of pedestrians

Simulation Model Development

NEED FOR SIMULATIONNEED FOR SIMULATION

The micro-simulation models not only build confidence in the proposal but also:

• Model vehicular/pedestrian conflict realistically for accessing impact of various scenarios on delay/queue lengths to evaluate guidelines as per IRC 103-2012

Software Used: PTV VISSIM is a microscopic, time step and behavior based simulation model and it is the most powerful tool available for simulating multi-modal traffic flows, including cars, trucks, buses, heavy rail, trams, LRT, bicyclists and pedestrians.

• Models vehicular and pedestrian behaviour accurately with scientifically calibrated models

• Provides credibility on the estimated delays and queues, considering various dynamic factors such as arrival rates, speeds/accelerations/

• Helps model scenarios such as violations and assessment of Intelligent transport systems efficacy such as push button signals.

SIMULATION METHODOLOGY SIMULATION METHODOLOGY

Traffic/Pedestrian Data 

(Volumes, Composition)

Observations and Inferences

Geometric Data 

(Road Network)Data Processing & Analysis

Data Collection and Compilation 

Evaluation and comparison of Proposed Models

Calibration and Validation of the 

Simulation Model for peak hour Use calibrated parameters

Network Setup in VISSIM (Simulation Software)

• AM Peak Controlled and Uncontrolled Scenario year 2016

• AM Peak Controlled Scenario and violations year 2021

• Capacity Analysis with grade separated options

MODEL INPUT PARAMETERSMODEL INPUT PARAMETERS

Parameters• Warm up period of

900secs• Driver Behavior• Conflict areas• Reduced speed area• Give way coding• Lateral gap• Vehicle speed• Lane changing

distance• Gap Acceptance

Model Inputs• Vehicular Volume

Input• Pedestrian Volume

Input• Signal timings• Vehicle /Pedestrian

classification and related properties

Evaluations• Base Model• Proposed Scenario

SIMULATION GLOBAL PARAMETERSSIMULATION GLOBAL PARAMETERS

The simulation model is set to simulate 15 Minutes + 1 Hour of which first15 minutes are modelled as buffer time for the build of the simulation modeland last 1 hour is the peak hour. All observations were taken 3600simulation seconds of the peak hour operations.

As all micro-simulation models are stochastic in nature, there is a degree ofrandomness associated with all distributions. The random seed parametercontrols the random number generator in the simulation. Simulation runswith identical input files and random seeds generate identical results. Amicro-simulation model must therefore be run with different random seedvalues to average the stochastic variations in the model. The model runswith five different random seed values, from which the results are taken andaveraged before presentation.

ASSUMPTIONSASSUMPTIONS

Pedestrian speed -1.2 m/sec (as per IRC 103-2012)

Pedestrian Peak Composition :

60% Men, 30% Women, 10% Child

Effects of pedestrian grouping, gap acceptance response to approaching

vehicle, pedestrian crossing speed variations, compliance to signals

For all scenarios with signalized crossing for pedestrians, the green time

is kept at 20 seconds for pedestrians phase as per IRC 103-2012

guidelines

NETWORK SETUPNETWORK SETUP

Links And Connectors (Road Network)

Data Processing & Analysis

Calibrated driving/pedestrian behavior parameters

Vehicle Types with acceleration and desired speed curves

Calibrated driving behavior parameters are taken from the consultants previous simulation work. References our given at the end of the presentation

AVERAGE TRAFFIC COMPOSITION (BARAPULLAH DOWNSTREAM)AVERAGE TRAFFIC COMPOSITION (BARAPULLAH DOWNSTREAM)

Vehicle type Mean Desired Speed Range

Car 65 Km/Hr 45‐100 Km/hr

Two Wheeler 45 Km/Hr 30‐80 Km/hr

Desired Speed range

Traffic Composition

LITERATURE REVIEW | CRITICAL GAPLITERATURE REVIEW | CRITICAL GAP

• Average gap accepted by the pedestrians : 5.02 s to 7.19 sbased on gender and 4.73 s to 7.76 s based on age.

• Priority rules are used in Vissimto model gap acceptance behaviour

Min. Gap Acceptance Time: The vehicle/pedestrian must wait at red bar if the current time gap is less than the value which has been entered.

EVALUATION CRITERIA UNCONTROLLED CROSSING EVALUATION CRITERIA UNCONTROLLED CROSSING

Uncontrolled Crossing Scenario with No Signals

As per IRC 103-2012, for providing controlled crossing following criteria needs to be evaluated:

• Peak Hour volume of pedestrians(P) and Vehicles(V) : PV2 > 2x108

• Speed of approaching vehicles is more than 65kph• Waiting time for pedestrians/vehicles becomes too long (evaluated using simulation)• Accident data indicating more than 5 accidents per year due to vehicle collision

Table below indicate the level of service limits as per IRC 103-2012

EVALUATION CRITERIA FOR CONTROLLED CROSSING EVALUATION CRITERIA FOR CONTROLLED CROSSING

Controlled Crossing Scenario with No Signals

As per IRC 103-2012

• High pedestrians/vehicular volume increase cycle timebeyond 120 seconds (Evaluated using Micro simulation)

• Vehicular traffic demands uninterrupted flow• At-grade crossing fails to mitigation problems related to

accident.

DELAY AND QUEUE MEASUREMENT SECTIONSDELAY AND QUEUE MEASUREMENT SECTIONS

Queue counter locations

Queue Counter

TERMINOLOGYTERMINOLOGY

• Vehicle delay: Average delay of all vehicles/Pedestrians

The delay of a vehicle in leaving a travel time measurement is obtained by subtracting the theoretical (ideal) travel time from the actual travel time.

• Average/Maximum queue length

Observations | Base Year 2016 | AM Peak Uncontrolled Scenario

AM PEAK UNCONTROLLED SCENARIO | MODEL SNAPSHOTAM PEAK UNCONTROLLED SCENARIO | MODEL SNAPSHOT

No Signals

• Model evaluated for 3 gap acceptance levels, of 4 seconds, 5.5 seconds and 7 seconds, with 4 seconds representing most aggressive pedestrian behaviour

AM PEAK UNCONTROLLED SCENARIO | ESTIMATED DELAYAM PEAK UNCONTROLLED SCENARIO | ESTIMATED DELAY

AM Peak Uncontrolled Scenario | Estimated Delay | ObservationsAM Peak Uncontrolled Scenario | Estimated Delay | Observations

• Average Vehicular delay for all critical gap acceptance value is more than95 seconds, with maximum estimated average delay of 111 seconds forcritical gap acceptance value of 4 seconds.

• For pedestrian movement average delay at critical gap values of 4seconds, 5.5 seconds, 7 seconds, are 24 seconds, 26 seconds and 48seconds respectively, for the movement from NBCC Complex to Metrostation and 24 seconds, 26 seconds and 39 seconds respectively, for themovement from Metro station to NBCC Complex, indicating level ofservice C-D

• Maximum pedestrian delay are estimated at 87 seconds for NBCCComplex to metro station movement and 70 seconds for Metro Station toNBCC Complex movement

AM Peak Uncontrolled Scenario | Percentile Delay ValuesAM Peak Uncontrolled Scenario | Percentile Delay Values

• For gap acceptance of 4 seconds and 5.5 seconds, 90% of the delay values are lessthan 43 sec and 42 sec.

• For gap acceptance of 7 seconds, only 50% of the delay values are fit in the rangefor LOS C for the movement for the side.

Average queue lengths for Vehicles at Pedestrian Crossing (in mts)Critical Gap Acceptance

(4 Seconds)Critical Gap Acceptance (5.5

Seconds)Critical Gap Acceptance (7

Seconds)351.90 m 325.55 m 268.60 m

AM Peak Uncontrolled Scenario | Estimated Vehicular Queue LengthAM Peak Uncontrolled Scenario | Estimated Vehicular Queue Length

Observations | Base Year 2016 | AM Peak Controlled Scenario

AM Peak Controlled Scenario | Model SnapshotAM Peak Controlled Scenario | Model Snapshot

With Signals

• Model evaluated for cycle time 90 seconds and 120 seconds

AM Peak Controlled Scenario | Estimated DelayAM Peak Controlled Scenario | Estimated Delay

• Average Vehicular delay for both cycle time is less than 21 seconds, which issignificant improvement from value of more than 95 seconds estimated inuncontrolled scenario

AM Peak Controlled Scenario | Estimated Delay | ObservationsAM Peak Controlled Scenario | Estimated Delay | Observations

• For cycle time of 90 seconds is average delay is 29 second for bothmovements

• For cycle time of 120 seconds, average delay increases to 37 seconds fortowards metro station movement and 41 seconds for opposite movement.

• Maximum Pedestrian delay is estimated at 54 seconds with cycle time120 seconds,

• maximum vehicular delay at 40 seconds for cycle time 90 seconds

• It is further observed that average values indicate the 90% percentiledelay values for all the movements,

AM Peak Controlled Scenario | Estimated Vehicular Queue LengthAM Peak Controlled Scenario | Estimated Vehicular Queue Length

Cycle time 90 seconds Cycle time 120 secondsAverage Queue

LengthsMaximum Queue

LengthAverage Queue

LengthsMaximum Queue

Length

23.39m 120.55m 13.77m 95m

AM Peak Controlled Scenario | Estimated Queues | ObservationsAM Peak Controlled Scenario | Estimated Queues | Observations

• Average queue lengths is estimated at more than 24m for cycle time 90seconds

• Average queue lengths reduced to 13m for cycle time 120 seconds,

• Maximum queue length is estimated with cycle time 90 seconds at 120m

• Cycle time of 120 seconds provided overall better level of servicefor vehicles,

• Cycle time 90 seconds provided better LOS for pedestrians

Comparison of Uncontrolled & Controlled Scenarios – Base year 2016

Comparing Average Queue Lengths for VehiclesComparing Average Queue Lengths for Vehicles

• Average queue lengths with uncontrolled scenario are very high ascompared with controlled scenario

• It is recommended to evaluate only controlled scenarios for horizon years

Comparing Average DelayComparing Average Delay

• Average delay for pedestrians is similar in both scenarios, but for vehicles average delayreduces significantly in the controlled scenario

• Further, recommended to evaluate only controlled scenarios for horizon years

Observations | Horizon Year 2021 | AM Peak Controlled Scenario

AM Peak Controlled Scenario | Year 2021 AM Peak Controlled Scenario | Year 2021

With Signals and Barapullah Downstream Volume 3679 PCU’s

• Model evaluated for cycle time 90 seconds and 120 seconds

Controlled AM Peak| Horizon Year 2021 | Estimated DelaysControlled AM Peak| Horizon Year 2021 | Estimated Delays

The graph above shows the average and maximum estimated delay for bothpedestrian movement and vehicular movement for the controlled scenario

AM Peak Controlled Scenario | Estimated Delays | ObservationsAM Peak Controlled Scenario | Estimated Delays | Observations

• With cycle time of 90 seconds the average estimated delayfor vehicular movement is 86 seconds, which reduces to 37seconds with cycle time of 120 seconds.

• Maximum delay is estimated at 142 seconds for vehiculartraffic with cycle time 90 seconds

• For pedestrian movement, the average delay is highest withvalue of 42 seconds with cycle time of 120 seconds, whichindicate level of service C-D.

Controlled AM Peak | Estimated Queue Length Controlled AM Peak | Estimated Queue Length

• Average estimated queue lengths are 175m & 60m with cycle time of 90 seconds& 120 sec.

• Recommended to have a cycle time of 120 seconds, with 20 secondspedestrians phase,

Observations | Horizon Year 2021 AM Peak | Violations Scenario

Estimated Delay Controlled AM Peak Estimated Delay Controlled AM Peak

Cycle time : 120 seconds

It is observed with cycle time 120 seconds, that as violations increase the average delay forvehicles increase, at level of 20% average estimated delay is 70 seconds which is 30 secondshigher if no violations are observed.

Observations | Horizon Year | Capacity Analysis

OBSERVATIONS WITH CONTROLLED SCENARIOOBSERVATIONS WITH CONTROLLED SCENARIO

• Need for grade separated option for the horizon years 2022-2027• Cycle time of 120 seconds is used.

YearEstimated 

Downstream VolumesVeh/Hr (PCUS)

Average queue length(m)

Average Maximum Queue Length(m)

2022 3863(3442) 69 1802023 4056 (3615) 139 2742024 4259 (3795) 184 3252025 4472 (3975) 235 3782026 4184 (4695) 249 3902027 4393 (4930) 266 395

• The road capacity of the section is estimated near 3800 PCU/Hour with cycletime 120 seconds

• In 2024, estimated volumes near capacity and the average queue lengths areestimated at 184m which indicate the controlled scenario is no more suitable at-grade pedestrian controlled crossing as higher green phase would be requiredfor vehicles

OBSERVATIONS WITH CONTROLLED SCENARIOOBSERVATIONS WITH CONTROLLED SCENARIO

• Need for grade separated option for the horizon years 2022-2027

• Cycle time of 150 seconds is used.

YearEstimated 

Downstream VolumesPCU’S and (Veh/Hr)

Average queue length(m) Average Maximum Queue Length(m)

2022 3863(3442) 34 1282023 4056 (3615) 65 2042024 4259 (3795) 114 2832025 4472 (3975) 164 3522026 4184 (4695) 182 3582027 4393 (4930) 226 415

CONCLUSION AND RECOMMENDATIONSCONCLUSION AND RECOMMENDATIONS

Control Type Year 2016 Traffic(Level of service (LOS))

Year 2021 Traffic (Level of service (LOS))

Year 2024 and Beyond

Uncontrolled Pedestrian LOS : CVehicle LOS: Poor

- -

Controlled Cycletime 90 seconds

Pedestrians: LOS BVehicles LOS : GoodRecommended Option

Pedestrians: LOS C-DVehicles LOS: Poor

LOS very PoorVehicular Traffic

Cycle Time 120 Seconds

Pedestrians: LOS BVehicles LOS : Poor

Pedestrians: LOS C-DVehicles LOS: GoodRecommended Option

LOS very PoorVehicular Traffic

GradeSeparated

- - Recommended Option

CONCLUSION AND RECOMMENDATIONSCONCLUSION AND RECOMMENDATIONS

• Uncontrolled crossing is not recommended due to high vehicular delays available

• Violations by pedestrians have significant effect on the delay for the vehiculartraffic

• Controlled crossing is required for providing better LOS for upstream volumesmore than 2400 PCU/hr on BBSB setu

• In this case, while proposing signals, the queue length for vehicles needs to beconsidered as it may extend on the main carriageway of Aurbindo marg

• Continuous increase in queue length on BBSB setu (downstream traffic) forHorizon years.

• Need for grade separated pedestrian facility after Horizon year 2024

PEDESTRIAN VULNERABILITYPEDESTRIAN VULNERABILITY

As per IRC code IRC‐103‐2012, to qualify as a grade separated pedestrian crossing facility, a location should have: 

Where, P = Peak hour pedestrian flow and V = Peak hour vehicularvolumeThe value of PV2/108 higher than or equals to 2 for any locationindicates high conflict between pedestrian across movement and flowof traffic.Thus, need for a grade separated pedestrian facility.

COMPREHENSIVE PLAN INCLUDING ACCESS 3 AND 4 WITH PEDESTRIAN CONNECTIVITYCOMPREHENSIVE PLAN INCLUDING ACCESS 3 AND 4 WITH PEDESTRIAN CONNECTIVITY

Access-4

Access-3

PEDESTRIAN SUBWAY DETAILS

ACCESS -4 DETAILS

ALTERNATIVE OPTION EVALUATIONALTERNATIVE OPTION EVALUATION

FOOT OVER BRIDGE ACROSS BBSB SETU

The high value of PV2/108 shows the need of grade separatedpedestrian facility.

F.O.B ACROSS BBSB SETUF.O.B ACROSS BBSB SETU

Metro Station

NBCC COMPLEX

PED

ESTR

IAN

MO

VEM

ENT

Location Peak hour Pedestrian Across Volume (2021)

Peak hour Vehicular Volume (2021) PV2/108

Across BBSB SETU 1128 6828 526

CROSS-SECTION OF FOB OPTIONCROSS-SECTION OF FOB OPTION

Option for F.O.B over the BBSB Setu require minimum height of 14‐15 meters to maintain the vertical clearance of 5.5 m free aboveroadway.

The high value of PV2/108 shows the need of grade separatedpedestrian facility.

Proposal may be adopted as per conclusion of all scenarios.

SUBWAY BELOW AUROBINDO MARGSUBWAY BELOW AUROBINDO MARG

Metro Station

NBCC COMPLEX

Location Peak hour Pedestrian Across Volume (2021)

Peak hour Vehicular Volume (2021) PV2/108

Across Aurobindo marg 1128 18055 3677

Metro Station

CROSS-SECTION OF SUBWAY OPTIONCROSS-SECTION OF SUBWAY OPTION

Access to Delhi Haat and INA Metro station entry/exit Land requirement for Subway entry/exit

REFERENCESREFERENCES

1: *Marisamynathan ., Vedagiri Perumal “Study on pedestrian crossing behavior at signalized

intersections”, Journal of Traffic and Transportation Engineering 2014

2: *Chaudhari, Shah, Arkatkar “Examining Effect Of Individual Characteristics On Walking

Speed 1 At Un-signalized Mid-block Crossings”, 96th Annual Transportation Research

Board meeting, Washington D.C.

3. Bains M S, Ponnu B, Arkatkar S S (2012). Modelling of traffic flow on Indian expressways

49 using simulation technique. Procedia - Social and Behavioral Sciences, 43, 475 493

4. Bains M S, Anshuman Bhardwaj, Shriniwas Arkatkar , S. Velmurugan (2013) Effect of 1

Speed Limit Compliance on Roadway Capacity of Indian Expressways, 2nd Conference 2

of Transportation Research Group of India (2nd CTRG)

5. Arasan, V.T., and Koshy, R. Z. (2005). Methodology for modelling highly heterogeneous

traffic flow. J. of Transp. Engg., 131, 544 551.

6. Velmurugan, S., Errampalli, M., Ravinder, K., Sitaramanjaneyulu, K. and Gangopadhyay,

S. 2010. Critical evaluation of roadway capacity of multi-lane high speed corridors under

heterogeneous traffic conditions through traditional and microscopic simulation models.

Journal of Indian Roads Congress, 71 (3), 235-264.