13
AHMED USSEIN 1 Dear Sir, It gives the greatest pleasure to present myself as one candidate of those who will be honored to work at your organization. Please find here my curriculum Vitae, hoping to gain your acceptance and attain the level of your best Satisfaction, Thank you for your consideration. SIGNATURE: Personal information: Name: Ahmed Hussein Hassan Ibrahim. Date of Birth: 28 / 07 / 1980. Nationality: Egyptian. Location: Cairo. Military service: Done. __________________________________ Contacts: Mobile phone: +20-1005238340. : +20-1119982277. E-mail: [email protected] _______________________________________ Educational information: Bachelor of Electrical Power & Machines Department. Granted on: 2002. Granted By: Faculty of Engineering, Ain Shams University. Overall Grade: Good. Graduation Project: Part (1): Grounding system and lightning protection. Part (2): Lighting Distribution. Graduation project Grade: Very Good. AHMED HUSSEIN

Eng.Ahmed Hussein(4)

Embed Size (px)

Citation preview

AHMED USSEIN 1

Dear Sir,

It gives the greatest pleasure to present myself

as one candidate of those who will be honored

to work at your organization. Please find here

my curriculum Vitae, hoping to gain your

acceptance and attain the level of your best

Satisfaction, Thank you for your consideration.

SIGNATURE:

Personal information:

Name: Ahmed Hussein Hassan Ibrahim.

Date of Birth: 28 / 07 / 1980.

Nationality: Egyptian.

Location: Cairo.

Military service: Done.

__________________________________

Contacts:

Mobile phone: +20-1005238340.

: +20-1119982277.

E-mail: [email protected]

_______________________________________

Educational information:

Bachelor of Electrical Power & Machines

Department.

Granted on: 2002.

Granted By: Faculty of Engineering, Ain

Shams University.

Overall Grade: Good.

Graduation Project:

Part (1): Grounding system and lightning

protection.

Part (2): Lighting Distribution.

Graduation project Grade: Very Good.

AHMED HUSSEIN

AHMED USSEIN 2

PROFESSIONAL QUALIFICATIONS:

Key Experience:

A- Experienced in project management especially in Electrical transmission substations -

turn key projects AIS & GIS type.

1- Project plane.

2- Work as per budget.

3- Work as per time schedule.

4- Resources plane.

B- Experienced in site management especially in Electrical transmission substation

projects and Electrical scope inside Electrical generation substations.

1- The site manager is the project key person.

2- Client and consultant.

3- Man power and subcontractors.

4- Monitoring the site.

5- Budget.

6- Time schedule.

C- Experienced in tendering and cost estimation work.

D- Experienced in construction works of different type of air insulation substations AIS

(indoor and outdoor type) from 66 KV to 500 KV with different equipment as:

1- Bus-Bar.

2- Circuit breakers.

3- Disconnecting switches.

4- Voltage, current transformers and surge arrestors.

5- Erection and assembly for control, protections, low voltage and medium voltage panels with

and without capacitor bank sets.

6- Power transformers (erection – oil treatment) Up to 125 MVA.

7- Control cables laying and termination

8- Power cables laying with different methods, cable sealing ends (porcelain and heat

shrinkable).

9- Assembly of steel structure and towers.

E- Experienced in construction works of electrical scope of a power plant as:

1- Earthing grad and secondary earthing.

2- Lightening system and air craft.

AHMED USSEIN 3

3- Lighting systems.

4- Fire detection systems.

5- Pipe racks.

6- Cable trays and ladders.

7- Control and power cables laying and terminations.

8- Erection and Aluminum welding for IPB.

F- Experienced in technical advisor for primary design.

G- Experienced in fabrication and assembly for all type of Low voltage panels.

H- Experienced in Safety management (risk assessment & risk control).

COMPUTER SKILLS:

1- Microsoft Office (Word, Excel, Power point, Microsoft project).

2- Auto-CAD 2D.

3- Primavera.

LANGUAGES:

1- Arabic: mother tongue.

2- English: fluent (written, speaking).

3- French: poor.

TRANING:

Managing safety a course approved and validated by Institution of Occupational Safety and

Health “IOSH”.

AHMED USSEIN 4

PROFESSIONAL HISTORY:

1- From 2004 – to 2007

EGYPTION GERMAN ELECTRICAL MANUFACTURING CO. (EGEMAC)

Position: Project Engineer.

Responsibilities:

A- Managing the project plane and the project time schedule.

B- Managing the project budget and resources.

C- Communication and liaising effectively with client, consultant, colleagues and sub-

contractors.

D- Scheduling materials and equipment and its delivery to the site.

E- Adopting all the project relevant requirements around issues as Building Permits,

Environmental regulations and Sanitary Design.

F- Managing the reviewing and approval cycle with client and consultant for the project

drawings.

G- Presence the weekly site meetings and site survey.

H- Supervising and monitoring the site day by day.

I- taking over certificate TOC.

Projects:

1- RABAA EL-ADAWEYA SUBSTATION (2004-2005):

a- Turn key Project.

b- Power Transmission Substation, (AIS) INDOOR TYPE 66/11 KV, 4X25 MVA.

c- 66 KV switchgear, 12 bay.

d- 11 KV switchgear, 4 sections.

e- Control building.

f- Power cables HV, MV and Control cables.

2- EL-ZAGAZIG UNIVERSITY SUBSTATION (2005-2006):

a- Turn key Project.

b- Power Transmission Substation, (AIS) 220/66/22 KV, 4X40 MVA.

c- 220/66 KV, 125 MVA Transformer and 66 KV switchgear, 12 bay.

d- 22 KV switchgear, 4 sections.

AHMED USSEIN 5

e- Control building.

f- Power cables HV, MV and Control cables.

3- EXTENTSONS OF (SEUZ, MANAEEF and EL RASWA) SUBSTATIONS (2006-2007):

a- Three turn key projects in (EL-Suez, Ismailia, Port Said) 220/66/11 KV.

b- For Every substation:

1- Extension one transformer bay 220 KV ‘’outdoor’’.

2- Extension one transformer bay 66 KV ‘’indoor’’.

3- Extension of 220 KV and 66 KV control building.

4- NEW EL-NABQ SUBSTATION:

a- AIS substation 220/66/22 KV.

b- 220 KV switchgear, 8 bay, 2x125 MVA transformers.

c- 66 KV switchgear, 12 bay, 4x25 MVA transformers.

d- 220 KV and 66 KV control building.

f- Power cables HV, MV and Control cables.

2- From 2007 to 01/12/2008:

VATECH – TRANSMISSION AND DISTRIBUTION

Position: Site Manager.

Projects:

- EL MAGD 66/11 KV SUBSTATION, (2007).

a- Turn key Project.

b- Power Transmission Substation, (AIS) INDOOR TYPE 66/11 KV, 3X25 MVA transformers.

c- 66 KV switchgear, 10 bay.

d- 11 KV switchgear, 3 sections.

e- Control building.

f- Power cables HV, MV and Control cables.

3- From 01/12/2008 to 15/09/2014:

Siemens S.A.E (Power Transmission and Distribution) Department PTD

AHMED USSEIN 6

Positions:

A- SITE MANAGER (2008-2012).

Projects:

1- REHABILITATION OF HIGH DAM ELECTRICAL SUBSTATION (2008-2010):

a- Replace the high dam switchyard 132 KV with new one 220 KV and connection with the new network

and re-connection with the existing system in the high dam substation that in two stage and four steps.

b- Replace to 220 KV, 12 bay.

c- New control and protection system and reconnection with the exist one.

d- 500/220/11 KV transformers.

e- Power cables HV, MV and Control cables.

2- SHLLATEEN SUBSTATION (2010):

a- 2x25 MVAR Reactors.

b- 220 KV switchgear for two bay.

c- Control building.

d- Steel structures and towers.

e- Power cables HV, MV and Control cables.

3- SHARM EL-SHEIKH SUBSTATION (2010 -2011):

a- Turn key Project.

b- Power Transmission Substation, (AIS) INDOOR TYPE 66/22 KV, 4X25 MVA transformers.

c- 66 KV switchgear, 12 bay.

d- 22 KV switchgear, 4 sections.

e- Capacitor bank, 4 sets.

f- Control building.

g- Power cables HV, MV and Control cables.

4- ASSUIT UNIVERCITY SUBSTATION (2011-2012):

a- Turn key Project.

b- Power Transmission Substation, (AIS) INDOOR TYPE 66/11 KV, 3X25 MVA transformers.

c- 66 KV switchgear, 12 bay.

AHMED USSEIN 7

d- 11 KV switchgear, 3 sections.

e- Control building.

f- Power cables HV, MV and Control cables.

B- LOW VOLTAGE PANELS MANUFACTORING MANAGER at (SIEMENS Factory) (2012-2014):

LOW VOLTAGE PANELS:

1- Remote control Panels.

2- Local control Panels.

3- Protection Panels.

4- Metering Panels.

5- Distributions panels.

Responsibilities:

1- Preparing the B.O.Q and material lists for consumable materials which needed for panel’s assembly.

2- Reviewing the panel’s front views and preparing the Auto-CAD drawings:

2a- primary design drawings for panels.

2b- Cut-out drawings.

2c- Internal arrangement drawings.

3- Full responsibility about panel’s assembly tell receiving by client of SIEMENS Projects.

Projects:

1- New Cairo Substation. (6 panels)

2- Abo-Ghaleb 66/11 KV Substation. (44 panels)

3- Ashmoon 220 KV GIS Substation. (42 panels)

4- Extensions of (Selwa, El-Nakra and South Qena). (31 panels)

5- Senoras 66/11 KV Substation. (34 panels)

6- Samasta 66/11 KV Substation. (32 panels)

7- Extension of Nagah Hammadi 500/220/66/11 KV. (11 panels)

AHMED USSEIN 8

8- Eythedco Substation. (8 panels)

9- Rehabilitation of South Qena. (24 panels)

10- EL-Suez Thermal 220 KV GIS Substation. (15 panels)

11- Cairo South Substation. (3 panels)