ENERGY SECTOR ROADWAY REPAIR PROJECT & OTHER HOUSE BILL 1025 - FUNDED PROJECTS
December 19, 2013
Texas Transportation Commission Meeting
1
December 19, 2013
Scope
Base Scope
– Reconstruction, rehabilitation,
restoration and/or resurfacing
of roadways and/or bridges
– Design plans provided by TxDOT
for optional use
Four Districts
– Corpus Christi, Laredo, San
Antonio and Yoakum
31 Locations Total
Maximum 540 days after
Notice to Proceed (NTP) 1
substantial completion
schedule
Energy Sector Roadway Repair Project 2
December 19, 2013
Procurement History
August 2, 2013 – Issued Request for Qualifications (RFQ)
September 23, 2013 – Short-listed four of the seven proposers
September 27, 2013 – Issued Request for Proposals (RFP)
November 20, 2013 – Received four technical proposals
December 4, 2013 – Received four price proposals
December 19, 2013 – Recommend Conditional Award
Energy Sector Roadway Repair Project 3
December 19, 2013
Submitted Proposal — Austin-Angel, JV*
Equity owner: Austin-Angel, JV
- Austin Bridge and Road, L.P.
- Angel Brothers Enterprises, LTD
Major non-equity members and other team members:
Burns & McDonnell Engineering
Company Inc.
Fugro Consultants Inc.
A.L. Helmcamp Inc.
Bay Ltd.
H.L. Zumwalt
Energy Sector Roadway Repair Project
*alphabetical order
James Construction Group
Salinas Construction Technologies
ACI Consulting
Gorronda & Associates Inc.
ETTL Engineers & Consultants Inc.
4
December 19, 2013
Equity owner: Hunter Anderson Joint Venture
- Hunter Industries, Ltd.
- Anderson Columbia Co., Inc.
Major non-equity members and other team members:
LNV Inc.
Brannon Paving Company Ltd.
Foremost Paving Inc.
Haas-Anderson Construction Ltd.
Ray Faris Inc.
Rexco Inc.
Energy Sector Roadway Repair Project
Submitted Proposal — Hunter Anderson Joint Venture*
*alphabetical order
Pave Tex Engineering and Testing Inc.
Rock Engineering and Testing Laboratory Inc.
Costello Inc.
Don Durden Inc. dba Civil
Engineering Consultants
Colorado Materials, Ltd.
5
December 19, 2013
Equity owner: Kiewit Infrastructure South, Co.
Major non-equity members and other team members:
H.W. Lochner Inc.
Lamb Star Engineering LP
Intermountain Slurry Seal Inc.
Corsair Consulting
Cox McLain Environmental Consultant
Cobb Fendley & Associates Inc.
CivilCorp
Submitted Proposal — Kiewit Infrastructure South, Co.*
*alphabetical order
6 Energy Sector Roadway Repair Project
December 19, 2013
Equity owner: Zachry-Parsons Eagle Ford Infrastructure Partners
- Zachry Construction Corporation
- Parsons Transportation Group, Inc.
Major non-equity members and other team members:
Poznecki Camarillo Inc.
Arias & Associates Inc.
Transtec Group Inc.
Kleinfelder Central Inc.
Submitted Proposal — Zachry-Parsons Eagle Ford Infrastructure Partners*
*alphabetical order
7 Energy Sector Roadway Repair Project
December 19, 2013
Evaluation
Implemented a pre-established and rigorous procedure to evaluate and select the
proposal that offers the best value
Separate pass/fail, technical and price evaluations
Evaluation subcommittees provided scoring recommendations to the Evaluation
Selection Recommendation Committee (ESRC)
ESRC provided scoring recommendations to the Project Steering Committee
Project Steering Committee reviewed ESRC recommendation
8 Energy Sector Roadway Repair Project
December 19, 2013
Scoring
Price includes design and construction
Technical score is based upon Technical
Solutions as well as the Project
Management, Quality Management,
Delivery Schedule and Safety & Health
Plans.
Energy Sector Roadway Repair Project
Price 90 points
Technical 10 points
-----------------------------------------------------------
Maximum 100 points
Best Value Scoring:
9
+
December 19, 2013
Scoring
DB Price Score = 90 points
– 70% number of Base Scope Locations
– 15% Base DB Price
– 15% Total Scope DB Price
Technical Score = 10 points
– 40% Preliminary Project Baseline schedule
– 60% Project Development Plan & Safety
Energy Sector Roadway Repair Project 10
December 19, 2013
Evaluation Results Summary
Detailed evaluations resulting in…
Energy Sector Roadway Repair Project 11
December 19, 2013
Equity owner: Austin-Angel, JV (Score of 88.98 pts)
- Austin Bridge and Road, L.P.
- Angel Brothers Enterprises, LTD
Major non-equity members and other team members:
Energy Sector Roadway Repair Project
Best Value Recommendation
Burns & McDonnell Engineering
Company Inc.
Fugro Consultants Inc.
A.L. Helmcamp Inc.
Bay Ltd.
H.L. Zumwalt
James Construction Group
Salinas Construction Technologies
ACI Consulting
Gorronda & Associates Inc.
ETTL Engineers & Consultants Inc.
12
December 19, 2013
Evaluation Results Summary
Austin-Angel, JV……………………….………….……………....…….......88.98 pts
Hunter Anderson Joint Venture………….………………...….....……85.07 pts
Kiewit Infrastructure South, Co…………………………….…….....…81.67 pts
Zachry-Parsons Eagle Ford Infrastructure Partners…………..74.27 pts
Energy Sector Roadway Repair Project 13
December 19, 2013
Austin-Angel, JV
Base Scope Design-Build Price (27 of 31 Locations): $ 149,995,000
Additional Locations Design-Build Price (4 Locations): $ 32,875,500
Total Price: $ 182,870,500
Energy Sector Roadway Repair Project
Evaluation Results Summary
14
December 19, 2013
Energy Sector Roadway Repair Project
Evaluation Results Summary
Austin-Angel, JV
Base bid of 27 Locations: 540 Days
Total bid of 31 Locations: 540 Days
15
December 19, 2013
Next Steps
Negotiate final terms of design-build contract
and assemble other documents necessary for
commercial close
Execute DB contract at commercial close
Issue NTP1
– Base Scope (27 Locations) construction
substantial completion within 540-days after
NTP1
– Total Scope (31 Locations) construction
substantial completion within 540-days after
NTP1
Energy Sector Roadway Repair Project 16
December 19, 2013
Other House Bill 1025-Funded Project Status
$75M allocated
5 Districts
11 Projects
TOTAL AWARD AMOUNT
$ 83,196,808
District Let Projects
•1 project (September)
•$16.9M
Amarillo
•1 project (October)
•$7.7M
Corpus Christi
•2 projects (October)
•$6.4M
Lubbock
•3 projects (November)
•$18.0M
Odessa
•4 projects (October, November, December)
•$34.2M
San Angelo
Award Amount
Energy Sector Roadway Repair Project 17
December 19, 2013
Energy Sector Roadway Repair Project
Questions?
Staff recommends and requests Commission approval of this minute order.
18