ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT Ganchimeg Chimed Officer of the Foreign Cooperation Division IEEJ:July 2019 © IEEJ2019

ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

ENERGY SECTOR OF MONGOLIA,COUNTRY REPORT

Ganchimeg Chimed Officer of the Foreign Cooperation Division

IEEJ:July 2019 © IEEJ2019

Page 2: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

CONTENT

•General information /Economic indicators, Country profile/•Reserves of Energy Mineral Resources •Current Energy Policy and Measures•Current Situation of Mongolian Energy Sector•Electric and Heat Demand Increase•Government action plan

IEEJ:July 2019 © IEEJ2019

Page 3: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

3

Area: 1.564 million square km Population: 3,238,479.0 (2019)Government Type: Parliamentary

republicCapital city: Ulaanbaatar

(approx. 1.31 million)GDP:11,2 billion USD (2017)GDP per capita: 4,017.120 USDReal GDP growth: 1 % (2017)Unemployment rate: 6.6%Inflation: 7Exports: 7.4 billion USDImports: 4.8 billion USD

1. General information

IEEJ:July 2019 © IEEJ2019

Page 4: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

4

Number of state households: 859106 In capital city: 376 419 households Official language: Khalkha Mongol 90%

(official), Turkic, Russian 10 % Official script: Mongolian Cyrillic,

Mongolian Script Ethnic groups: 96% Mongolians, 4%

Khazakhs Religions: Buddhist 53%, Muslim 3%,

Christian 2.2%, Shamanist 2.9%, other0.4%, none 38.6% (2010 est.)

Lowest annual average temperature: -33°C (-50°C)

Highest annual average temperature:+23°C (+35.8°C)

IEEJ:July 2019 © IEEJ2019

Page 5: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

5

Structure of Energy sector

IEEJ:July 2019 © IEEJ2019

Page 6: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

6

Western Power System, 32 MW

Eastern Power System, 63 MW

Ulaanbaatar

Altai-Uliastai Power System, 18 MW

Central Power System, 1166MW

IEEJ:July 2019 © IEEJ2019

Page 7: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

7

• Estimated total resources ~ 173 billion ton in 15 coal basins

• Over 370 identified occurrence in 85 deposits• Proven Reserves 12 billion ton, of which 2

billion is coking coal• Around 1/3 in Gobi Region • Around 1/3 in Eastern Region

• Mines in Gobi area are for export /18 million in 2013/

• Nariin Sulhait• Tavan tolgoi

• Mines in other region are for power production and household heating /12 million in 2013/

• Baganuur, Shivee-Ovoo, Shariin Gol, Aduunchuluun etc.,

COALCoal Basins Key Mines

2. Reserves of Energy Mineral Resources

IEEJ:July 2019 © IEEJ2019

Page 8: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

8

• Rich resources of Solar, Windand Hydro in Mongolia:

• Solar: 270-300 sunny days in ayear, 4.3-4.7 kWh/meter orhigher per day

• Wind: 10 % of the total landarea can be classified asexcellent for utility scaleapplications, Power density 400-600 W/m2, the resource couldpotentially supply over 1100 GWof installed capacity.

• Hydro: Theoretical potential 6.2GW, more than 1 GW of theseahs been identified

RENEWABLES

IEEJ:July 2019 © IEEJ2019

Page 9: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

999

STATE POLICY ON ENERGY

SAFETY

EFFICIENCY ENVIRONMENT

PRIORITY AREAS AND STRATEGIC GOALS

• Ensure energy safety and reliable supply

• Develop mutually beneficial cooperation with regional countries

• Develop a human resource

• Transfer the state dominated energy sector into private based competitive market

• Support innovation and advanced technology in energy sector, and implement conservation policy

• Increase the production share of renewables and reduce negative environmental impact from traditional power generation and greenhouse gas

3. CURRENT ENERGY POLICY AND MEASURES

IEEJ:July 2019 © IEEJ2019

Page 10: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

6/17/2019 Date & Location 10

In the 1st stage 2015-2023: The stage to develop energy safety resources andbackup capacity, establish a foundation for the development of renewable, enhancenormal documents and improve legal environment.• The installed power capacity will be doubled, and start using critical technology

with high parameters. Hydro will be taken place at least 10% of the total installedpower capacity and it will increase backup capacity to 10%, and create fundamentfor renewable sector to development intensively, enhance tariff system.

In the 2nd stage 2024-2030: The stage to export secondary energy and developsustainably the renewable sector.• The backup capacity of power system will be reach at 20% and share of

renewables will be reach at 30%. Integrated smart energy system will be createdby connecting regions with high capacity transmission lines. State owned Powercompanies will be become a public company. Distribution and supply service willbe privatized and energy sector will be worked as a competitive marked withregulation. Secondary energy will be exported by connecting with North east Asiancountries with high capacity DC lines.

Expected Results

IEEJ:July 2019 © IEEJ2019

Page 11: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

11

IEEJ:July 2019 © IEEJ2019

Page 12: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

12

4. CURRENT SITUATION OF MONGOLIAN ENERGY SECTOR

IEEJ:July 2019 © IEEJ2019

Page 13: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

13

IEEJ:July 2019 © IEEJ2019

Page 14: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

6/17/2019 Date & Location 14

Vision

To fully provide reliable operation of theenergy sector, energy security, sustainabledevelopment and economic growth of thecountry and become an energy exportingcountry with efficient and environmentallyfriendly technology based on regulated andcompetitive market dominated by privatesector

IEEJ:July 2019 © IEEJ2019

Page 15: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

15

GOVERNMENT ACTION PLAN 2016-2020

CO2 EMISSION:

IEEJ:July 2019 © IEEJ2019

Page 16: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

16

№ Classification Unit Tariff

1 Simple meter

a Monthly consumption under 150 kWh USA $/ kWh 0.041

b Monthly consumption over 150 kWh USA $/ kWh 0.049

2 Time use of meter /2 parts/a Daytime consumption /06.00 am~21.00 pm/ USA $/ kWh 0.043

b Evening and nighttime consumption / 21.00 pm~ 06.00 am / USA $/ kWh 0.032

3 Monthly base tariff USA $/ kWh 0.828

Electricity tariff for residential

Remark: Daytime, evening and nighttime tariff will apply duration of the meter hours.

IEEJ:July 2019 © IEEJ2019

Page 17: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

17

№ Classification Unit Tariff

1 Mining industries

These : Coal mining exploration and cultivation

Oil and gas mining exploration and cultivation

Iron Mining exploration and cultivation

Other mining exploration and cultivation

1.1 Simple meter USA $/ kWh 0.065

1.2 Time use of meter /3 parts/

а Daytime consumption (06.00 am ~17.00 pm) USA $/ kWh 0.065

b Evining consumption (17.00 pm ~ 22.00 pm) USA $/ kWh 0.011

c Nighttime consumption (22.00 pm~06.00 am) USA $/ kWh 0.032

TARIFF FOR INDUSRIAL ELECTRICITY CONSUMPTIONThe tariff (VAT excluded) for industrial electricity shall be determined depending on the its classification of units of indicators as follows:

IEEJ:July 2019 © IEEJ2019

Page 18: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

18

5. ELECTRICITY AND HEAT DEMAND INCREASE

IEEJ:July 2019 © IEEJ2019

Page 19: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

6/17/2019 Date & Location 19

Recent Challenges:

• Capacity Shortage

8877

97 92 94 9888 90 94 92 94 93

CHP 2 CHP 3 CHP 4 CHP Dar CHP Erd CES

Utilization of Installed Capacity in CES,%, /Winter load/

2016 2017

0

1000

2000

3000

4000

5000

6000

7000

8000

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017

Domestic Production and Import, GWh

Domestic Production Import

IEEJ:July 2019 © IEEJ2019

Page 20: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

6/17/2019 Date & Location 20

Recent Challenges:

• Efficiency

34 4

56

78

10

13*

0

2

4

6

8

10

12

14

16

Transmission and Distribution loss, %

IEEJ:July 2019 © IEEJ2019

Page 21: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

Key projects that need to be implemented in the urgent matter

Capacity Extension Projects on Existing CHPs in short-term• Capacity expansion of CHPP -3’s high pressure section 75 MW

• Expansion of Amgalan heat plant by combined heat and power plant with 50 MW

• Capacity expansion of CHPP 3 by 250 МВт

• Capacity expansion of CHPP 2 by 300 MW/ including one block of gas turbine andgenerator/

Expansion of regional power transmission networks• 220 kV 2 circuit 118 km OHTL between Baganuur substation and Ulaanbaatar

substation, and expansion of substations

• Choir-Sainshand-Zamyn Uud 220 kV 2 circuit 404 km OHTL and substation

• 220 kV 2 circuit 178 km OHTL between Baganuur substation and Choir substation,expansion of Baganuur substation

6/17/2019 Date & Location 21

- 462- 25

- 180 - 61

- 150

- 15

- 7

- 7- 10

- 10

- 6

- 10

- 12

- 16

- 6

- 10

- 9

- 5

- 8

- 7

- 6

- 8

- 8

- 5

- 6

(119) (52)

(6)

(23)

(109)

(6)

(2)

(710)

(8)

(10)

(78)

(150)

(80)

(15)

213(m

ax 235)

IEEJ:July 2019 © IEEJ2019

Page 22: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

Generation recourses to stabilize load fluctuation • Hydro Power Plants

• Eg HPP, Erdenburen HPP

• Gas Turbines• Create gas turbine units using infrastructure of

existing CHP’s

• Storages in Central Power System• Hydro Pumped storage 100 MW or above

• Big sized battery storage 100 МW

Key projects that need to be implemented in the urgent matter

22

THE MID-TERM NATIONAL PROGRAM FOR IMPLEMENTATION OF THE STATE POLICY ON ENERGY

(2018-2023)

22

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Wind Farms

Solar PVs

ImportMax transmission capacity of import line from Russia,

240 MW

CHP#4, 703 MW

CHP#3, 186 MW

Coal fired thermal power

plants

Daily load curve of Central power system, 5th Dec 2018

To Peak load

Regulation

IEEJ:July 2019 © IEEJ2019

Page 23: ENERGY SECTOR OF MONGOLIA, COUNTRY REPORT

6/17/2019 Date & Location 23

For planned and potential projects of power plant and transmission lines:

As a financier, Contractor, Equipment supplier, Consulting service

Concession agreement: Built-Operate-Transfer, . . . . . . . . .

Independent Power Producer

For existing power projects:

In the Projects of Operational enhancement and Restructuring:

Operator company

Consultant

In the Projects of Rehabilitation and Capacity Extension:

Investor, Contractor, Equipment supplier, Consulting service