29
AUGUST 10-14, 2020 NOW A VIRTUAL EVENT 1 Energy Resilience Program and Assessment Tool

Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

  • Upload
    others

  • View
    3

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

1 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT1

Energy Resilience Program and Assessment Tool

Page 2: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

2 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT2

Energy Resilience Program and Assessment Tool

Ariel Castillo, Ph.D.Director, Installation Energy Resilience

ODASD(Energy)

Annie Weathers, Ph.D.MIT Lincoln Laboratory

11 August 2020

Page 3: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

3 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT3

Energy Priorities Mission

• Sustain warfighting readiness and lethality by providing all energy-related policy and governance for programs and activities that enable resilient, efficient, and cyber-secure energy for Joint forces, weapon systems, and installations

ODASD(Energy) priorities aligned to ASD(S) goals• Enhance material readiness• Prepare the battlefield for 2025• Maintain safe places• Create and sustain resilient installations

Four primary focus areas• Energy Resilience• Energy Risk • Energy Performance • Cyber Secure Facilities

DoD Acquisition & Sustainment

Page 4: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

4 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT4

Energy Resilience (ER) Program Timeline

Energy resilience policies and capabilities align to

national security and mission requirements

Key enablers to ER Program:• DoDI 4170.11 Energy Resilience Policy• Installation Energy Plans (IEPs)• Black Start Exercises • Alternative Finance

DoD Acquisition & Sustainment

Page 5: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

5 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT5

DoD Energy Resilience

SicilyNAS Sigonella 1NAS Sigonella 2NRTF Niscemi

HawaiiJBPHH

Fort GreelyGuam

NSA AndersenNB Guam

NBGTS

• Energy Resilience Assessment (ERA) tool allows sites to understand risks to critical systems and inform project development

• Tabletop exercises investigate responses and capabilities during an extended simulated outage

• Black start exercises provide awareness of actual system capabilities during a real outage

NB Kitsap BangorNB Kitsap Keyport

Beale AFB

Fort Irwin

Camp PendletonNB San DiegoNB CoronadoNB Point Loma

Camp Lejeune

NS Norfolk

JB Andrews

NSA PhiladelphiaPhiladelphia NSY

Fort StewartDobbins ARB

Barnes ANG

Vandenberg AFB

NSB Kings Bay

Creech AFB

Hanscom AFB

Fort Bragg

Fort Hood

Analysis and Exercise Locations

4 6 168

>30 energy resilience base assessments and exercises completed- ~1/5 of the Department’s electricity consumption- > $450 million in electricity costs

• Adverse weather events are damaging our electrical infrastructure

• Downstream effects may cause outages on DoD installations

• Real-world exercises ensures preparedness for an outage scenario

DoD Acquisition & Sustainment

Page 6: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

6 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT6

Requires analyzing the problem from a mission resilienceperspective with a technology agnostic approach.

How can we best arrange the electrical generation and storage systems on a military installations to provide “resilient” energy solutions at the lowest possible cost?

Two challenges for military installations:- The periods of greatest need are often the periods of greatest risk- The edge cases are paramount to any analysis

Page 7: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

7 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT7

One Piece of The Mission Analysis PuzzleMission

Method 1 Method 2 Method 3

Installation X Installation Y Installation Z

Redundant methods of accomplishing a mission

Redundant installations that can perform that method

Page 8: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

8 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT8

One Piece of The Mission Analysis PuzzleMission

Method 1 Method 2 Method 3

Installation X Installation Y Installation Z

Redundant methods of accomplishing a mission

Redundant installations that can perform that method

Ability to reduce mission capabilities

Ability to move missions to another building

Ability to repair and troubleshoot equipment

Infrastructure Reliability

Factors That Influence Energy Resilience

… among many others

Page 9: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

9 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT9

Energy Resilience Assessment (ERA) ToolMission

Method 1 Method 2 Method 3

Installation X Installation Y Installation Z

Redundant methods of accomplishing a mission

Redundant installations that can perform that method

• Power Distribution System• Backup Power System• Infrastructure Reliability• Energy Costs• Continuity of Operations Plan (COOP)• Installation Energy Plan (IEP)• …Mission B

Mission A

Installation Energy Manager

Installation Commander

Stakeholders Energy Resilience Analysis Components

At the installation level, the ERA tool is one method for assessing the appropriate infrastructure for energy resilience.

Page 10: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

10 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT10

Purpose of the ERA Tool Provide comparison of lifecycle costs and mission resilience for a

variety of energy generation and storage technology combinations Answer high level questions:

• Does it make more sense to import or generate electricity?• Is centralized generation with a microgrid more effective than building level

generation?• What solutions have the lowest lifecycle costs?• What technology combinations provide the best mission availability?

Does not provide a full system design for the installation. Instead, provides simulated model results and recommendations for the types of architectures to cost-effectively pursue.

Page 11: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

11 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT11

When Do You Use This Tool? The tool is required for OSD’s Energy Resilience Conservation Investment Program (ERCIP) as an

initial planning tool before project scoping (e.g., before a 1391) Could be part of an Installation Energy Plan (IEP) Could be part of an educational course on the costs and benefits of different types of technologies

ERCIP Process

Prepare 1391 (Initial project proposal)• Initial project scope• LCCA for selected project • Project narrative

Initial Data Analysis• ERA Tool• IEP• System Analysis• Preliminary design

Project Discussion• Synthesis of ERA tool outputs, IEP,

COOP, master planning documents, preliminary designs

• Does the proposed project make sense holistically?

Page 12: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

12 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT12

How Does The Tool Work?

Page 13: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

13 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT13

How Does The Tool Work?

Possible Architecture Combinations

Architecture Option 1: Utility feed + grid-tied solarArchitecture Option 2: Utility feed + building level generatorsArchitecture Option 3: Utility feed + centralized generators + microgridArchitecture Option 4: Utility feed + centralized generators + microgrid + fuel cellsetc…

Site access: https://osdera.ll.mit.edu (CAC-enabled)

Page 14: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

14 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT14

How Does The Tool Work?

Installation name and location Fuel and electricity costs Number of feeders and substations Historical utility and distribution system outages Critical electrical and thermal load

Page 15: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

15 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT15

How Does The Tool Work?

/

Simulates failures and repairs of each generation and storage asset (e.g., each generator)

Considers failures in utility service and distribution system

Simulation of normal operation with sporadic utility and distribution system failures

Simulation of black-sky, multi-day outage event, with option for suspending fuel delivery and equipment repairs

Page 16: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

16 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT16

How Does The Tool Work?

/

Lifecycle Cost

Mission Downtime

Each technology combination

Page 17: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

17 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT17

Example of an Installation Assessment

Far enough apart that centralization of generation across the entire installation is not possible

Main campus8 MW

Housing0.5 MW

Critical Mission 3 MW

~ 12 MW total load

Page 18: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

18 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT18

Example of an Installation Assessment

Main campus8 MW

Housing0.5 MW

Critical Mission 3 MW

~ 12 MW total load

0.5 MW is a small load that can be handled adequately with a couple building level generators Not a critical mission function that requires high availability

Page 19: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

19 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT19

Example of an Installation Assessment

Main campus8 MW

Housing0.5 MW

Critical Mission 3 MW

~ 12 MW total load

The critical mission already had centralized generation with recently updated infrastructure. Not a candidate for detailed assessment.

Page 20: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

20 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT20

Example of an Installation Assessment

Main campus8 MW

Housing0.5 MW

Critical Mission 3 MW

~ 13 MW total load

The main campus, with a load of 8 MW, was a good candidate for a more detailed assessment. How does the cost and resilience of the existing power system compare

to other possible technology options?

Page 21: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

21 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT21

Planning for Day-to-Day OperationsUsers are provided with 10 year lifecycle cost, broken out

by funding mechanism 10 year unserved load, mission

downtime, or site-wide availability

Color coded to drive discussion towards what is important to you (e.g., CapEx versus operational costs)

Technology combinations

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

25

50

75

Solar PPA Nat Gas Electricity Diesel Fuel Maintenance CapEx

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

5

10

15

10 Year Unserved Load (MWh)

10 Year Project Cost ($MM)

Page 22: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

22 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT22

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

25

50

75

Solar PPA Nat Gas Electricity Diesel Fuel Maintenance CapEx

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

5

10

15

10 Yr Unserved Load (MWh)

10 Year Project Cost ($MM)

Planning for Day-to-Day Operations

Existing Architecture• Central backup generators• Building backup generators

The existing option includes centralized and building level generation

On average, over a 10 year period, approximately 10 MWh of lost load, equivalent to 2 hours of downtime.

There are options that are cheaper and better performing

Solar PPA Nat Gas Electricity Diesel Fuel Maintenance CapEx

10 Year Unserved Load (MWh)

10 Year Project Cost ($MM)

Page 23: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

23 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT23

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

25

50

75

Solar PPA Nat Gas Electricity Diesel Fuel Maintenance CapEx

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

5

10

15

10 Yr Unserved Load (MWh)

10 Year Project Cost ($MM)

Planning for Day-to-Day Operations

Architecture #79 assets:• Microgrid• Central backup generators• UPS system• Islandable solar PV

Architecture #83 assets:• Microgrid• Central backup generators• Battery system• Islandable solar PV

Architecture #71 assets:• Microgrid• Central backup generators• Islandable solar PV

Alternative options with potentially better performance at lower cost

Centralization and consolidation of generation assets could provide lower unserved load at a reduced cost

Centralized UPS can help to bridge generator startups

Six hour storage battery doesn’t cost out

Solar PPA Nat Gas Electricity Diesel Fuel Maintenance CapEx

10 Year Unserved Load (MWh)

10 Year Project Cost ($MM)

Page 24: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

24 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT24

Planning For An Edge CaseFuel Storage 100000 Gallons, Black Sky Outage: 14 Days

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

25

50

75

Black Sky Scenario

Historical Scenario

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

5

10

15

20

25

3483

Existing Alternatives Factors to consider during a multiday outage Length of simulation Fuel availability Repair technician availability Changes to mission requirements Targeted attacks on specific

equipment

Installation concern: 14 day outage with 100,000 gallons of on-site diesel storage without fuel redelivery

10 Year Unserved Load (MWh)

10 Year Project Cost ($MM)

ERA Tool FocusBlack sky scenarioDay-to-day operations

Page 25: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

25 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT25

Fuel Storage: 14 Days, Black Sky Outage: 14 Days

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

25

50

75

Black Sky Scenario

Historical Scenario

98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81 74 73 68 2 67 64 63 80 79 72 71 1

Architecture #

0

5

10

15

20

25

Planning For An Edge Case

3483

Existing Alternatives

When the fuel shortage issue is fixed, the existing solution suffers from high fuel costs and poor performance due to an over-resilience on diesel generators without redundancy.

14 day outage with 14 days of on-site diesel storage

10 Yr Unserved Load (MWh)

10 Year Project Cost ($MM)

Black sky scenarioDay-to-day operations

Page 26: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

26 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT26

Holistic Energy Resilience Assessment

• Is there sufficient fuel storage for a multi-day outage?• What is the relative reliability of the distribution system and utility service?• Is producing electricity on-site more cost effective than importing it?• What technologies make sense from a cost and reliability perspective?

Mission

Method 1 Method 2 Method 3

Installation X Installation Y Installation Z

Redundant methods of accomplishing a mission

Redundant installations that can perform that method

One piece of analysis for a larger discussion of whether centralization of generation and alternative generation technologies make sense for an installation.

Page 27: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

27 AUGUST 10-14, 2020 • NOW A VIRTUAL EVENT27

Questions?

Ariel Castillo, Ph. D.Director

Installation Energy ResilienceDefense Department

[email protected]

Annie Weathers, Ph. D.Technical Lead

Energy Systems GroupMIT Lincoln Laboratory

[email protected]

Site access: https://osdera.ll.mit.edu (CAC-enabled)

Page 28: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

28

Page 29: Energy Resilience Program and Assessment Tool · 8/11/2020  · Black Sky Scenario Historical Scenario 98 97 94 93 86 85 78 77 84 83 90 89 76 75 96 95 88 87 92 91 70 69 66 65 82 81

29