Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
www.electricitypolicy.org.uk
Implementing EU Renewables Directive
Karsten Neuhoff
With input from Adam Rysanek, Sarah Lester, Simone Cooper
Cambridge – MIT Summer ConferenceBrussels 9/10, 2009
www.electricitypolicy.org.uk
EU and national policy to achieve EU renewable targets
• Offer guidance to coordinate investment
• Deploy flexible market design to avoid delays
• Demonstrate commitment to attract investment
• Monitor to create accountability&responsiveness
• Carry regulatory risk to attract capital at low cost
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 3
0
50
100
150
200
250
Mto
e E
nerg
y O
utpu
t
6.3%
20%
Indicative trajectory
Policy targets frame public & private investment
Guidance from• Consistent objectives• Strategic choices
Heat
Wind
Biomass - heat
Biofuels - transport
Biomass - electricity
Solar Heat
Tide+ Wave
Geothermal
PV
Wind offshore
Wind
Hydro
Biomass and Waste
Based on Green-X projections
Allocating across time & fuels
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 4
Creating confidence for investors in supply chain
Source: IEA, GWEC, Worldwatch Institute
Installed wind power per year (MW)
China
U.S.
SpainIndiaGermanyU.K.ItalyFrance
Denmark
www.electricitypolicy.org.uk
Governments role in managing a transition to large scale use of renewables
• Offer guidance to coordinate investment
• Deploy flexible market design to avoid delays
• Demonstrate commitment to attract investment
• Monitor to create accountability&responsiveness
• Carry regulatory risk to attract capital at low cost
www.electricitypolicy.org.uk
Current transmission access
• Connect for firm access– delay until reinforcements in place– > excessive T capacity for wind– > excessive delays in connecting wind
• TSO uses contracts and balancing mechanism to manage congestion– weak incentives on G to manage output– costly to deal with congestion
www.electricitypolicy.org.uk
Our model outputs:
Wind output Wind investmentCCGT investment
*
*
*
*** *
* Regional build constraint binding
build constraints create scarcity rent
Source: Neuhoff et al. Space and Time: Wind in an Investment Planning Model, Energy Economics.
www.electricitypolicy.org.uk
Model price duration curve – 40% wind energy from system
0
10
20
30
40
50
60
70
80
90
100
Euro/MWh
20052010
2015 2020
0 1 year
Illustrative
www.electricitypolicy.org.uk
Nodal pricing for effective network utilisation
3,500 MW extra G for only 2000 MW Tif congestion management appropriate
www.electricitypolicy.org.uk
The value of optimised dispatch
Müsgens, F. and Neuhoff, K., 2006, Modelling Dynamic Constraints in Electricity Markets and the Costs of Uncertain Wind Output, EPRG Working Paper 05/14
www.electricitypolicy.org.uk
Spatial and temporal optimisation
• Nodal price reflects congestion & marginal losses– lower prices in export-constrained region– efficient investment location, guides grid expansion
• Central dispatch for efficient scheduling, balancing
• Market power monitoring – benchmark possible
• PJM demonstrates that it can work– Repeated in NY, New England, California (planned)
www.electricitypolicy.org.uk
Market design to support operation and investment
Network investment
Generation investment
finance•enable•access p•enable•pricing•flexibility
Planning
Supplychain
Finance
Renewable support
CO2 policy
Nuclearpolicy
Uncertainties
Planning
Regulation*
SupplyChain*
Uncertainties
* off-shore
Market design for flexible operation:• More generation can be connected• Generation can be connected even
at times of bottle-necks
www.electricitypolicy.org.uk
Governments role in managing a transition to large scale use of renewables
• Offer guidance to coordinate investment
• Deploy flexible market design to avoid delays
• Demonstrate commitment to attract investment
• Monitor to create accountability&responsiveness
• Carry regulatory risk to attract capital at low cost
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 14
Incentives for compliance with EU renewable targets
Several options:• Legal enforcement, possible financial penalty• Positive encouragement
– TEN, Agricultural etc funding in exchange for delivery against objective
• One or both parties share (financial) responsibility
• Naming and shaming
www.electricitypolicy.org.uk
Investing in the grid – to demonstrate commitment:The European “SuperGrid”
The “EUMENA” ConceptMediterranean-focused HVDC
Transmission “Highways” to complement the existing AC infrastructure
Objective for Grid Expansion: By 2050, expand Europe’s
transmission capacity to accommodate a 15% electricity supply contribution from concentrated solar power (CSP) resources in North Africa. This does not include the expected contribution of CSP to North Africa’s generation mix, which will be significant.
Transmission Investment: 45€ Billion between 2020 and 2050
Reference:DESERTEC. Clean power from deserts, The Club of Rome. Hamburg: Whitepaper; 2007.
www.electricitypolicy.org.uk
Investing in the grid – to demonstrate commitment:The North Atlantic Offshore Wind Transmission Corridor
Objective for Grid Expansion: EU-DG TREN: Support the development of
129 to 187 TWh/a of offshore wind generation by 2020 (between 3.7% and 5.9% of total generation demand of EU-15)
Airtricity’s 10GW Foundation Project: Provide 10 GW of offshore wind generation capacity (approx. 35 TWh/a) with grid connection to the UK, Netherlands, and Germany
Transmission Investment: EU-DG TREN: Between 7.7€ billion and
11.8€ billion between 2005 and 2013; between 17.1€ billion and 25.4€ billion between 2014 and 2023
Airtricity: 2€ Billion between 2011 and 2015
10 GW Foundation Project
Future SuperGrid
References:Airtricity,”European Offshore Supergrid Proposal”, Airtricity, Dublin, 24 pp., May 2006.
DG TREN. TEN-Energy-Invest. Brussels, Rambøll A/S: European Commission, Directorate-General Transport and Energy (DG-TREN), CESI spa, Instituto de Investigacio´n Tecnolo´ gica, Mercados Energeticos; 2005.
www.electricitypolicy.org.uk
Improvements to Transmission Technology and Practices
Flexible AC Transmission Systems (FACTS)
Table from: DG TREN. TEN-Energy-Invest. Brussels, Rambøll A/S: European Commission, Directorate-General Transport and Energy (DG-TREN), CESI spa, Instituto de Investigacio´n Tecnolo´ gica, Mercados Energeticos; 2005.
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 18
Matching transmission and generation
Grid
cap
acity
time
Nodal pricing, etc.Smart grid
Current grid
Grid expansion
Investment lag grid
• Provide visibility for supply chain and project investors
• Coordinate grid expansion with generation investment
www.electricitypolicy.org.uk
Governments role in managing a transition to large scale use of renewables
• Offer guidance to coordinate investment
• Deploy flexible market design to avoid delays
• Demonstrate commitment to attract investment
• Monitor to create accountability&responsiveness
• Carry regulatory risk to attract capital at low cost
www.electricitypolicy.org.uk
Monitoring Progress using Indicators
• Widely used across many levels/sectors of economy• Allow for performance benchmarking• Increase domestic accountability• Facilitate evidence based (international) dialogue• Co-benefit metrics useful to shift debates (e.g. CAP)
1. Highlight impact of current policy2. Incentivising countryside management3. Increase share of CAP linked to metrics
www.electricitypolicy.org.uk
Experience with indicators across sectors
Case Study Sectors and Level of metrics Objective/Motivation Literature base
Sustainable Development
and environmental metrics
National/ all sectors/ OECD
• Monitor and compare coupling of economic activity and environmental pressures. Inform and guide policy
• Sustainable development policy • Environmental evaluation and
monitoring. Infrastructure and land-use planning
Indicators for Overseas
Development Aid
International development plans /National indicators/ all sectors.
• Inform and guide international dialogue, provide transparency and accountability, policy learning
• International development literature• Development institution measurement
(World Bank, IMF and IEA literature). • Globalisation, trade and aid literature
UK government Performance
Indicators (PSA framework)
From local level and national targeted priorities for UK public
sector governance.
• Measure progress of policy, incentivise local government action and policy reform
• Results-Based Management (RBM), Performance Management Frameworks
• Public administration, performance budgeting and indicator systems
Key Performance Metrics (KPI) Firm level indicators.
• Benchmarking for process learning and external comparison for adoption of ‘best practice’
• Business Process Management (BPM).
• Corporate Social Responsibility (CSR)• Operational/strategic performance
management. Systems thinking
OECD Science and Technology
Indicators
OCED aggregated indexes of innovation for technology
development.
• Measure and report relevant indicators to enhance cooperation and policy design for innovation
• Technology policy and Innovation chain literature. Renewable and energy literature. Low-carbon electricity systems
www.electricitypolicy.org.uk
Measuring policy actions towards the EU Renewables Directive: NREAPs
• By June 2010, each EU Member State must submit a National Renewable Energy Action Plan (NREAP) which describes how the EU Renewables Directive target will be achieved domestically
• The NREAPs require member states to provide specific RE supply targets, and detail specific actions taken to:
1) Provide appropriate planning regimes for deployment of RE projects
2) Provide grid / market infrastructure and access to new RE generators
3) Provide financing (directly or through incentives) for RE projects
Inform the known
barriers to RE
deployment
www.electricitypolicy.org.uk
Global Input:Technically-Feasible RE Generation Capacity
Global Output:Installed / Target
RE Capacity
PlanningAccess to Grid and
Energy Market Supply Chain Project Finance
Barriers along the RE pipeline
Barriers
Lack of effective legal / regulatory framework
Lack of private participation and professional institutions
Uncertainty with government policies
Lack of coordination between authorities
Lack of consumer/social acceptance of RE technologies
Barriers
Highly controlled energy sector
Lack of grid access for RE technologies
Lack of clear practises and procedures (related to planning barriers)
Lack of available grid capacity
High grid connection costs for RE developers (poor cost allocation)
Lack of access to energy market
Barriers
Lack of competition and lack of standards and codes of certification
Lack of entrepreneurs, skilled labour, and training and O&M facilities
Lack of R&D capacity
Restricted access to technologies
Lack of reliability of products
Lack of institutions / mechanisms to disseminate information
Barriers
Financial Support(costs, risks, ...)
Energy Market(access, structure, long-term costs, ....)
Capital Market(perception of technical risk, perception of regulatory risk, ...)
Visibility(uncertainty, ....)
www.electricitypolicy.org.uk
Global Input:Technically-Feasible RE Generation Capacity
PlanningAccess to Grid and
Energy Market Supply Chain Project Finance
Barriers along the RE pipeline:Indicators provided in NREAPs:
Barriers
Lack of effective legal / regulatory framework
Lack of private participation and professional institutions
Uncertainty with government policies
Lack of coordination between authorities
Lack of consumer/social acceptance of RE technologies
Barriers
Highly controlled energy sector
Lack of grid access for RE technologies
Lack of clear practises and procedures (related to planning barriers)
Lack of available grid capacity
High grid connection costs for RE developers (poor cost allocation)
Lack of access to energy market
Barriers
Lack of competition and lack of standards and codes of certification
Lack of entrepreneurs, skilled labour, and training and O&M facilities
Lack of R&D capacity
Restricted access to technologies
Lack of reliability of products
Lack of institutions / mechanisms to disseminate information
Barriers
Financial Support(costs, risks, ...)
Energy Market(access, structure, long-term costs, ....)
Capital Market(perception of technical risk, perception of regulatory risk, ...)
Visibility(uncertainty, ....)
Quantitative and qualitative indicators
Qualitative indicators
Global Output:Installed / Target
RE Capacity
Not covered
www.electricitypolicy.org.uk
Examples of Indicators used Across Sectors:EPRG Survey
Survey Data:• 49 respondents (41% private sector, 23% government, 21% NPOs,15% international institutions)
www.electricitypolicy.org.uk
Global Input:Technically-Feasible RE Generation Capacity
Global Output:Installed
RE Capacity
PlanningAccess to Grid and
Energy Market Supply Chain Project Finance
Indicator Source(s)
Number of RE Certificates (or FIT contracts) issued
Various nat. bodies (EU, Aus, Can)
Poll of public opinion of RE technologies
BERR (UK)
Indicator Source(s)
Indicator Source(s)
Public and private investments in RE technologies
IEA, UNEP, New Energy Finance
RE trade barriers (exports)
Foreign Affairs (Canada)
Import tarriffs on RE technologies
EC Tax. and Customs Union Datab.
Number of incubators in clean energy market
UNEP, New Energy Finance
Employment in the RE sector, per technology
BMU (Germany)
Number of publicly traded companies in the RE sector
UNEP, New Energy Finance
Total market share of three largest energy suppliers and generators
Swedish Energy Agency
Indicator Source(s)
Comprehensive private investment statistics in RE sector (multiple indicators)
UNEP, New Energy Finance
Distribution of energy subsidies within EU-15, RE and non-RE
EEA
Type of public financial support scheme for RE-projects
IEA
Investment and production costs of RE and non-RE technologies
IEA
Amount of public financial support provided
Various nati. bodies (EU, Aus, Can)
Examples of Regularly-Reported Indicators along the RE Pipeline
Input Indicators(resources / actions taken to address a problem)Process Indicator(initial reaction to input activities)
Output Indicators(direct results of policies / actions taken)
More Exist
www.electricitypolicy.org.uk
Justifying the costs of indicators
0 50,000 100,000 150,000 200,000 250,000 300,000 350,000 400,000
Bulgaria
Hungary
Lithuania
Malta
Netherlands
Austria
Portugal
Romania
Slovenia
Argentinia
Nicaragua
Kenya
Mid size
Nat
iona
l Sus
tain
able
Dev
elop
men
t Stra
tegy
Trab
ajar
Proj
ect
Sch
ool
Ref
orm
Agr
icul
tur
exte
nsio
nN
at.
Com
s.
Eur
osta
tW
orld
bank
UN
FCC
C
Euro
Sources:
•Eurostat: http://epp.eurostat.ec.europa.eu/portal/page/portal/grants/documents/Tab/List%20of%20Grants2008EN.pdf
•World Bank: http://www-wds.worldbank.org/external/default/WDSContentServer/WDSP/IB/2004/08/18/000112742_20040818172234/Rendered/PDF/2980000182131497813.pdf
•UNFCCC : http://unfccc.int/resource/docs/2008/sbi/eng/inf03r01.pdf
www.electricitypolicy.org.uk
Examples of Indicators used Across Sectors:EPRG Survey
Ability of indicators to facilitate policy / project management
Strongly Disagree
Disagree Strongly Agree
Agree
NOTE: 80% of respondents agreed that the data collection process for the indicators was labour intensive
www.electricitypolicy.org.uk
Governments role in managing a transition to large scale use of renewables
• Offer guidance to coordinate investment
• Deploy flexible market design to avoid delays
• Demonstrate commitment to attract investment
• Monitor to create accountability&responsiveness
• Carry regulatory risk to attract capital at low cost
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 30
Current capital structure (fall 08)
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000DebtEquity
Mio Euro
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 31
Cost of debt – reflecting perceived risk
www.climatestrategies.org www.electricitypolicy.org.ukNeuhoff, 32
How much debt could utilities raise?
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
Potential for new debt?
DebtEquity
Mio Euro ~ 300 billion Euro
Missing so far Vattenfall, Centrica ..
www.electricitypolicy.org.uk
Investors’ risk – an important design criteria
RO
des
ign
Ene
rgy
pric
e
Bal
anci
ng c
osts
Impa
ct tr
ansm
issi
on
cons
train
ts
Pro
ject
risk
and
de
velo
pers
mar
gin
RO
C m
arke
t
Cos
ts
Project revenue requirement
Performance/operation Regulatory uncertaintyFuture market evolution
Risk from:
Pro
fit fo
r in
fram
argi
nal
tech
nolo
gies
/loca
tions
RO
des
ign
Ene
rgy
pric
e
Bal
anci
ng c
osts
Impa
ct tr
ansm
issi
on
cons
train
ts
Pro
ject
risk
and
de
velo
pers
mar
gin
RO
C m
arke
t
Cos
ts
Project revenue requirement
Performance/operation Regulatory uncertaintyFuture market evolution
Risk from:
Pro
fit fo
r in
fram
argi
nal
Reduce (a) infra-marginal rent (b) regulatory risk (c) re-allocate risk from future technology mix/fuel prices
a
b cBreak even point
Fixed & banded ROCTake or pay contract
Sou
rce:
Tak
e-or
-pay
con
tract
sfo
r Ren
ewab
les
Dep
loym
ent,
with
Joh
nsto
n an
d K
aval
i
www.electricitypolicy.org.uk
Governments role in managing a transition to large scale use of renewables
• Offer guidance to coordinate investment
• Deploy flexible market design to avoid delays
• Demonstrate commitment to attract investment
• Monitor to create accountability&responsiveness
• Carry regulatory risk to attract capital at low cost