Energy Conservation for the Philippine Steel and Iron Industries: Case Studies Loreto C. Carasi Loreto C. Carasi Philippine Council for Industry and Energy Philippine Council for Industry and Energy Research and Development Research and Development Department of Science and Technology Department of Science and Technology 17 November 2006 17 November 2006 Twin Tower Hotel, Thailand Twin Tower Hotel, Thailand

Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Energy Conservation for the Philippine Steel and Iron Industries: Case Studies

Loreto C. Carasi Loreto C. Carasi Philippine Council for Industry and Energy Philippine Council for Industry and Energy Research and Development Research and Development

Department of Science and TechnologyDepartment of Science and Technology

17 November 200617 November 2006

Twin Tower Hotel, ThailandTwin Tower Hotel, Thailand

Page 2: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

OUTLINEOUTLINE

About DOST/PCIERD

PCIERD EE & C Initiatives

EE&C for the Philippine Steel and Iron Industry

Conclusion

Page 3: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Premier science and technology body Mandates:

Central direction, leadership & coordinationPolicy, program & project formulation Councils, R&D Institutes, Service Institutes, Regional Offices

DEPARTMENT OF SCIENCEAND TECHNOLOGY (DOST)

Page 4: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Philippine Council for Industry Philippine Council for Industry and Energy Research and and Energy Research and Development (PCIERD) Development (PCIERD)

Philippine Council for Agriculture, Forestry and Natural Resources Research and Development (PCARRD)

Philippine Council for Aquatic and Marine Research and Development (PCAMRD)

Philippine Council for Advanced Science and Technology Research and Development (PCASTRD)

Philippine Council for Health Research and Development (PCHRD)

R&DR&D

INSTITUTION INSTITUTION BUILDINGBUILDING

MANPOWER MANPOWER DEVDEV’’T AND T AND SCHOLARSHIPSCHOLARSHIP

SEMINARS ANDSEMINARS ANDCONFERENCESCONFERENCES

TECHNOLOGYTECHNOLOGYTRANSFERTRANSFER

POLICY POLICY DIRECTIONSDIRECTIONS

DOST Sectoral Planning Councils

Page 5: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

PCIERD Mandates

Industry & energy policies, strategies, plans and programs

Fund programming & allocation

Project & program monitoring

External fund generation

Page 6: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Provides Grants-in-Aid (GIA)Grants applied S&T scholarships Disseminates & promotes S&T information Supports scientific & technological services

Services Offered by PCIERD

Page 7: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

FOOD & FEEDSECTORAL COVERAGE

MINING & MINERALS

PROCESS /CHEMICAL

METALS & ENGINEERING

TEXTILE AND GARMENTS

ENERGYTRANSPORTATIONCONSTRUCTIONENVIRONMENDISASTER AND MANAGEMENT

Page 8: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

PCIERD EE & C InitiativesCapacity Building

Establish Core of Experts in the Region

Factory Energy Audit on SMEs

GAP Funded

PCIERD Funded

Infrastructure Support

Provision of equipment

Policy Support

Report to DOE the DOST’s Energy Savings

Establishment of Vehicle Research and Testing Facility

Promotion of Biofuels

Page 9: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Objectives of the program:

To provide technological exchange of information and expertise

To conduct human resources development

To conduct energy audit and technical assessment on the selected industries

To establish network and linkages among the local and Japanese industries

EE & C for the Philippine Steel and Iron Industry

Page 10: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

ProductsPlain and deformed steel bars and rods for concrete reinforcement

Production capacity250,000MT per year

Total Energy consumption per yearElectricity

25 Mw-hrFuels

9,500 Kilioliters

Number of employees147

LocationMetro Manila

Company A

Page 11: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

(1) Air Temp

(2) Recuperator

(4) Flame Loss

To burner

(3) Flue Gas Loss

(7) Surface Temp

(8) Burner

(5) Induce Air

(6) Discharging Operation

Furnace

Page 12: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Findings:

1. Preheated Air : Defective instrument to grasp the preheated air temperature

2. Recuperator: Defective recuperator tubes

3. Waste Gas Loss: Temperature of outlet is 798 oC% Oxygen in flue gas is 3.8%

4. Heat Loss from Charging Door: Temp. of gas from charging door is 691 oCOpen space is measured at 0.92 m2

5. Induced Air from Discharging Door: Amount of air is 4,900 m3 per hr

6. Discharging Operation: No problem

7. Heat Loss from Surface: Temperature of furnace shell external surfaces (roof and side walls) is 90-100oC

7. Burner: Straight type burners is used

Page 13: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Cooling System (Pumps)

Skid FurnaceOperates well

MillMotor loading is low

QuenchMotor loading is low

Page 14: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Compressors

Loading and Unloading time : Ok

Load requirements vs. Delivery capacity: Ok

Discharge Pressure vs. Required Pressure at the User Side : Decrease the discharge pressure gradually

Leakage Along Supply Line

Draining of Moisture

Page 15: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Instrument wirings on the control panel were modified to get readings of pre-heated air

Repair of recuperator to eliminate air leakage

Installation of “heat curtain” at the charging door of furnace to minimized heat loss (Later replaced with sliding-plate type)

Reduction of induced air from discharging door

Improvement of burner combustion efficiency

Minimizing heat loss from furnace

Improvement of furnace data monitoring

Implemented MeasuresFurnace:

Page 16: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Improvement of combustion blower motor loadingThe 100 HP motor for combustion blower was replaced with a 75 HP motor. The motor loading was increased from 70% to 95%.

Repair of Rolling Mill Circulating PumpThe impeller was replaced and the seal ring was repaired. Motor loading was increased from 70% to 95%.

Air Compressors:Minimized air leakage in the system

Conduct leak test for the air supplyCorrection of air leakages in the system is a continuing program

Mill bay LightingUsed/installed skylights at strategic locations inside the mill to enhance illumination.

Implemented MeasuresPumps/Blowers:

Page 17: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

0

5

10

15

20

25

30

35

40

45

50

2001 2002 2003 2004 2005

Fuel and Power Consumption Trends

92

94

96

98

100

102

104

106

108

2001 2002 2003 2004 2005

98.87104.04106.5898.2897.22Power, Kw-hr/ton

36.5139.2642.945.7745.88Fuel, Lit/ton

20052004200320022001

Power Electricity

Page 18: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Energy SavingsParticular

Savings (Peso)%Lit/ton4.167 M8.483.64Reduction in Fuel

Savings (Peso)%Kw-hr/tonReduction in Power 1.418 M2.382.54

5.585 MTOTAL ENERGY SAVINGS

Amount of Energy (2004)

Page 19: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Energy SavingsParticular Savings (Peso)%Lit/ton

3.4M7.02.75Reduction in FuelSavings (Peso)%Kw-hr/ton

Reduction in Power 2.8 M4.975.176.2MTOTAL ENERGY SAVINGS

Amount of Energy (2005)

Page 20: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Lengthen the heating zone of the furnace to reduce flue gas temperatureAdditional insulation on the furnace shell outside surfacesUse of inverter control for the TTL process pumpsReplacement of straight-type burners to swirl type burnersClose Monitoring of plant power factor to ensure PF is always at its optimum Recycling of used oil and greaseProvision of pneumatic lubricatorContinue the checking/repair of air leakages in the plant

Plans

Page 21: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

ProductsDeformed bars

Production Capacity121,337.22 MT per year

Annual Energy Consumption (average)Electricity = 13.4 MWHFuels = 4,114 kiloliters

Number of Employees185

LocationMetro Manila

Company B

Page 22: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

(1) Air Temp

(2) Recuperator

(4) Flame Loss

To burner

(3) Flue Gas Loss

(7) Surface Temp

(8) Burner

(5) Induce Air

(6) Discharging Operation

Furnace

Page 23: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Findings:

1. Preheated Air Temp : Low @ 224oC

2. Recuperator: Check leakage

3. Waste Gas Loss: Waste gas temperature at recuperatror inlet is quite low at 665oC

4. Heat Loss from Charging Door: Temp. of gas from charging door is 680 oCOpen space is measured at 0.92 m2

5. Induced Air from Discharging Door: Amount of air is 1,100 m3 per hr

6. Discharging Operation: 2-3 billets are discharged together, and the 2nd and 3rd billets cannot be rolled coz its temp. has lowered and thus require further heating

7. Heat Loss from Surface: Temperature of furnace shell external surfaces (Ceiling: 100-130, Side: 85-95oC

8. Burner: Straight type burners is used

9. Furnace Scale Generation: The ave. concentration for waste gas oxygen concentration is 1.7%

Page 24: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Replacement of existing recuperatorInstallation of insulation curtain at the inlet door of the furnaceReduce opening time of billet discharge doorReduction of waste gas oxygen concentration from 1.7% to 1.3% Raising the furnace pressure setting Optimization of Billet Reheating Furnace Application of cladding insulation on the oil pipe linesIncrease setting of oil heaters at the main line (soaking and heating zone) from 90oC to 110oCSet-up energy conservation group

Implemented Measures

Page 25: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

05

10152025303540

2003 2004 2005

107

107.5

108

108.5

109

109.5

2003 2004 2005

Fuel and Power Consumption Trends

Power Electricity

108108.56109.19Power, Kw-hr/ton

3033.4536.39Fuel, Lit/ton200520042003

Page 26: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Energy SavingsParticular

Savings (Peso)%Lit/ton4.206M8.082.94Reduction in Fuel

Savings (Peso)%Kw-hr/tonReduction in Power 0.444M0.510.63

4.65 MTOTAL ENERGY SAVINGS

Amount of Energy (2004)

Page 27: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Energy SavingsParticular Savings

(Peso)%Lit/ton

5.074M10.313.45Reduction in Fuel

Savings (Peso)

%Kw-hr/tonReduction in Power

0.377 M0.520.565.451MTOTAL ENERGY SAVINGS

Amount of Energy (2005)

Page 28: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

BRF heat conservation (charging and discharging side)BRF waste gas temperature monitor and controlUse of stand alone electric furnace in preheating pre-determined steelDemand KW monitor and controlMake-up water volume monitor and controlCompressed air leakage monitor and control

Plans

Page 29: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

ProductsGalvanized and Pre-painted Sheets/Coils

Production capacity per year (average)Continuous Galvanizing Line (CGL)

34,703 tons Color Coating Line (CCL)

27,588 tons

Total Energy Consumption (average)Electricity

CGL1,058 MWh per year

CCL845 MWh per year

Company C

Page 30: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Total Energy Consumption (average)

Fuel consumption per yearCGL

Fuel Oil:577,728 litersLPG: 256,513 kgs.

CCLLPG: 492,170 kgs.

No. of employees170

LocationLaguna

Page 31: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Power and Electricity Consumption Trend

Continuous Galvanizing Line (CGL)

16.0696.752

27.914

17.1727.971

32.841

Rate of ConsumptionBFO/SFO, Lit/tonLPG, Kg/tonPower, Kw-hr/ton

529,959222,678920,634

625,497290,349

1,196,234

Energy ConsumptionBFO/SFO, LitersLPG, KgsPower, Kw-hr

20042003

Page 32: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Power and Electricity Consumption Trend

Color Coating Line (CCL)

16.31329.393

19.10631.650

Rate of ConsumptionLPG, Kg/tonPower, Kw-hr/ton

407,863734,896

576,477954,965

Energy ConsumptionLPG, KgsPower, Kw-hr

20042003

Page 33: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

1.075 M0.305 M

157.1

4.9272.257

Reduction in Power

CGLCCL

5.665 MTOTAL

0.654 M61.103Bunker Oil

CGL

KW-hr/ton

Lits. per ton of product

1.327 M2.304 M

15.314.6

1.2192.793

LPGCGLCCL

Savings (Peso)% SavingsKgs. per ton of product

Reduction in Fuel

Energy SavingsParticulars

Page 34: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

System ImprovementImproved treading time from 5-6 minutes to 3 minutesInstallation of cartridge type coaters to reduce downtime in changing colors and replacing paint coater rollsInstallation of 12.5 MT overhead crane to handle bigger coil materialsInstallation of horizontal direct fired LPG preheaterChange technology from zinc lead-lead-zinc hot dip galvanizing to a modified John Lysaght processInstallation o direct fired LPG coil heater

Conduct study on peak kW Reduced demand at CGL furnace Reduced demand at CCL oven

Improvement of power factor from 81% to 94%Improvement of light distribution at CCL

Implemented Measures

Page 35: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Decommission boiler using BFOShift of fuel materials from BFO to SFOImprove burner firing at LPG preheaterDecommission air dryers, exhaust gas from LPG direct fired alkali heaters used as air dryersDecommission smoothener rolls drive of 7.5kWWaste heat recovery at LPG heaters and dryersConduct efficiency tests in ovens and furnaces for temperature profiling

Plans

Page 36: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Common measures implementedMinimizing heat loss from furnaceImprovement of burner efficiencyImprovement of pump motor loadingMinimized compressed air leakage

Common plansHeat conservation on the reheating furnaceWaste gas temperature monitor and controlDemand kW monitor and controlMake-up water volume monitor and controlCompressed air leakage monitor and control

Page 37: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

Conclusion

The participating factories shows positive response. Recommended measures or areas of improvement suggested by the experts have been implemented and it was reported that there was a great improvement in plant efficiency and significant savings was realized. Local skills were enhanced and they can now do energy audit by their own.

The significance of Energy Conservation and Management has been recognized, which is evident to their new initiatives.

Setting-up of company’s energy conservation targetsCreation of energy managers and auditorsEnergy conservation are discussed during management meetings

Page 38: Energy Conservation for the Philippine Steel and Iron Industries: … · 2010. 6. 24. · 1. Preheated Air : Defective instrument to grasp the preheated air temperature 2. Recuperator:

PCIERD Website http://www.pcierd.dost.gov.ph