Energy Balance Project Document FINAL

Embed Size (px)

Citation preview

  • 8/2/2019 Energy Balance Project Document FINAL

    1/87

    Ministry of Industry, Mines and Energy

    Cambodia

    Ministry for Foreign Affairs

    Finland

    Capacity Development for Energy Balance Construct ion

    and Sustainable Energy Planning in Cambodia

    Project Document

    April 27, 2011

  • 8/2/2019 Energy Balance Project Document FINAL

    2/87

    April 2011 - Page 2 / 87 -

    Table of Contents

    PROJECT FACT SHEET 6

    EXECUTIVE SUMMARY 7

    1 BACKGROUND 11

    2 DEFINITION OF INTERVENTION 13

    2.1 Problem Analysis 13

    2.2 Project Approach 14

    2.3 Overall Objectives 16

    2.4 Project Purpose 17

    2.5 Project Components 17

    2.6 Results, Achievement Indicators and Activities 18

    2.6.1 Component 0: Project Management 19

    2.6.2 Component 1: Establishment of Energy Information System and Database 20

    2.6.3 Component 2: Capacity Building for Energy Modelling 21

    2.6.4 Component 3: Capacity Building for Energy Planning 22

    3 ASSUMPTIONS AND RISKS 24

    4 COMPATIBILITY AND SUSTAINABILITY 26

    4.1 Compatibility 26

    4.1.1 Finnish Development Policy 26

    4.1.2 National Strategic Development Plan and Energy Sector Development 28

    4.1.3 Statistics Law 29

    4.2 Sustainability 30

    5 IMPLEMENTATION 31

    5.1 Implementation Strategy 31

    5.2 Data Collection 31

    5.2.1 Demand side data collection 31

    5.2.2 Supply side data collection and energy import statistics 34

    5.3 Capacity Development and Training 36

    5.4 Project Organization 38

    5.4.1 Energy Statistics Office, Energy Modelling Unit and Project Management Unit 38

    5.4.2 Steering Committee 40

    5.4.3 Technical Assistance 41

    5.4.4 National Annual Workshop for Policy Planners 42

    5.5 Data Collection Working Group 43

  • 8/2/2019 Energy Balance Project Document FINAL

    3/87

    April 2011 - Page 3 / 87 -

    5.5.1 Time Schedule 43

    5.5.2 Budget 45

    6 MONITORING AND EVALUATION 466.1 Monitoring 47

    6.2 Evaluation 47

    ANNEX 1: PRESENT SITUATION: ENERGY SECTOR IN CAMBODIA 49

    ANNEX 2: TERMS OF REFERENCE OF EXPERTS 63

    ANNEX 3: JOB DESCRIPTIONS 66

    ANNEX 4: LOGICAL FRAMEWORK 71

    ANNEX 5: PROJECT ACTIVITIES 78

    ANNEX 6: PROJECT TIME SCHEDULE 85

  • 8/2/2019 Energy Balance Project Document FINAL

    4/87

    April 2011 - Page 4 / 87 -

    List of Abbreviations

    ADB Asian Development Bank

    ACE

    ASEAN

    ASEAN Center for Energy

    Association of Southeast Asian Nations

    CDC Council of Development of Cambodia

    CDI Cambodian Development Institute

    CNPA Cambodian National Petroleum Authority

    CTA

    DEDE

    DIME

    Chief Technical Advisor

    Department for Alternative Energy Development and Efficiency of

    Thailand

    Provincial Departments of Industry, Mines and Energy

    EAC Electricity Authority of Cambodia

    EBC

    EdC

    Energy Balance of Cambodia

    Electricity du Cambodge

    EIS

    EMU

    EPPO

    ESO

    FAO

    Energy information system

    Energy Modeling Unit

    Energy Policy and Planning Office of Thailand

    Energy Statistics Office

    Food and Agriculture Organization of the United Nations

    GDP Gross Domestic Product

    GERES Groupe Energies Renouvelables, Environnement et Solidarits (French

    non-profit NGO)

    HEI ICI Higher Education Institutions Institutional Cooperation Instrument

    ICT Information and Communication Technology

    IEA International Energy Agency

    ITC Institute of Technology Cambodia

    IPP Independent power producer

    JICA Japan International Cooperation Agency

    MAFF Ministry of Agriculture, Fishery and Forestry

    MEF Ministry of Economy and Finance

    MFA Ministry for Foreign Affairs of Finland

    MIME Ministry of Industry, Mines and Energy

    MoP Ministry of Planning

    MRD Ministry of Rural Development

    MPWT Ministry of Public Works and Transport

    NCDD National Committee for Sub-National Democratic Development

    NIS National Institute of Statistics

  • 8/2/2019 Energy Balance Project Document FINAL

    5/87

    April 2011 - Page 5 / 87 -

    ONEBC Overall National Energy Balance of Cambodia

    PMUPO

    RGC

    Project Management UnitProject officer

    Royal Government of Cambodia

    REE Rural Electricity Enterprise

    SC

    SIDA

    TA

    Steering Committee

    Swedish International Development Cooperation Agency

    Technical Assistance

    TOR Terms of Reference

    UNFCCC

    UNDP

    United Nations Framework Convention on Climate Change

    United Nations Development ProgramWB The World Bank

  • 8/2/2019 Energy Balance Project Document FINAL

    6/87

    April 2011 - Page 6 / 87 -

    Project Fact Sheet

    Project Title Capacity Building for the Energy Balance Construction andSustainable Energy Planning in Cambodia

    Sector Energy

    Sub-Sectors Energy Statistics, Renewable Energy, Energy Planning,Power Sector Planning, Climate Change Mitigation.

    Geographical Coverage Cambodia (national level)

    Duration: 2011 - 2015 (four years)

    Project Financing Total

    Royal Government of Cambodia

    in kind contribution, approximately 10% of the totalbudget (salary of staff, office, electricity and water)

    Government of Finland

    EUR 2.3million

    1 EUR = 5,683 Cambodia Riels KHR (25 March, 2011)

    Competent Authorities Ministry of Industry, Mines and Energy

    General Department of Energy

    Institutional Framework Steering Committee

    Project Management Unit embedded in General Departmentof Energy, MIME

    Overall Objective The overall objective is to contribute to planning and

    implementing of Cambodian climate change policy and

    programmes through development of sustainable energydata and planning system which promotes inclusive growth

    and responds to poverty reduction and sustainabledevelopment goals of Cambodia

    Purpose To strengthen MIME to be sustainable and capable of

    employing advanced techniques, methodologies and

    modeling tools in: establishing and managing energy information

    system

    drawing up plans for energy sector development and

    climate change mitigation and adaptationinterventions

    prioritizing energy sector and climate changemitigation investments

    mainstreaming of gender and poverty in energyplanning..

  • 8/2/2019 Energy Balance Project Document FINAL

    7/87

    April 2011 - Page 7 / 87 -

    Executive Summary

    Background

    Energy services in Cambodia are inadequate and costly (electricity tariff rates are oneof the highest in Southeast Asia) with electricity supply systems dominantly fossil fuel-

    based which contributes to the emissions of local pollutants and greenhouse gases.These are symptomatic to the existence of significant barriers that hinder thedevelopment of sustainable energy supply systems in the country. The lack ofadequate training and capacity building to carry out comprehensive planning, as well as

    lack of information, are identified as the main contributing factors to the currentcircumstances of the energy sector in Cambodia. The Ministry of Industry, Mines and

    Energy (MIME) requested the Finnish Government for support in developing itscapacity on energy statistics, energy balance and planning.

    Problem to be addressed

    Biomass will be the dominant energy resource in Cambodia for the short and medium

    term, and therefore it is essential to recognize the contribution of wood energy in theenergy balance and to plan for a continued and sustainable supply. This is particularly

    pertinent given the disparity in fuel wood resources within and between provinces, andthe significant impact that the lack of access to biomass has on the poor. Also overall

    energy and electricity services in Cambodia are inadequate and expensive with supplysystems highly vulnerable to external disruptions and fluctuations of internationalenergy prices and increasingly contributing to local environmental pollution andgreenhouse gas emissions. These are the results of an electricity supply system which

    is highly fragmented, less extensive (mainly providing services in large urban centres)and highly dependent on imported fossil fuels. The lack of energy services particularly

    those in rural areas and unaffordable energy services in urban areas could undermineeconomic growth and sustainable development of the country.

    Project approach

    The overall project approach can be described as follows: first the project focuses on

    the role of MIME in the National Statistics System by strengthening the capacity ofMIMEs Energy Statistics Office, and second, on the role of MIME in the NationalEnergy Planning by strengthening the capacity of MIMEs Energy Modelling Unit.

    Project is based on the assumption that energy planning should serve the overall socio-economic development planning and not function as a separate entity. The inclusion of

    socio-economic and environmental aspects in the energy planning requires informationof the interlinkages of these activities and sectors.

    For energy balance construction both supply and demand side data is needed, anddata collection methods will cover both bottom-up and top-down approaches.

    Objectives and components

    The overall project objective is to contribute to planning and implementing ofCambodian climate change policy and programmes through development ofsustainable energy data and planning system which promotes inclusive growth and

    responds to poverty reduction and sustainable development goals of Cambodia.. The

    project purpose is to strengthen MIME to be sustainable and capable of employingadvanced techniques, methodologies and modeling tools in:

  • 8/2/2019 Energy Balance Project Document FINAL

    8/87

    April 2011 - Page 8 / 87 -

    Establishing and managing energy information system, Drawing up scenarios and plans for energy sector development, and for climate

    change mitigation and adaptation interventions,

    Prioritizing energy sector and climate change mitigation activities, and Mainstreaming of gender and poverty in energy planning.

    To achieve the objectives and purpose, the projects activities and outputs are organizedinto four project components. These are the following:

    Component 0: Project Management

    Component 1: Establishment of Energy Information System and Database

    Component 2: Capacity-building for Energy Modelling

    Component 3: Capacity-building for Energy Planning

    Coherence, compatibility and sustainability

    This project is consistent and compatible with the principles pursued by the FinnishDevelopment Cooperation. While project activities are very specific and related toenergy information and planning, the overarching goal of the project is the development

    of a sustainable energy supply system which is sensitive to developmental, energysecurity, climate change and energy access goals of the country. With the energy

    information and energy sector development plans, RGC can make decisions andprioritized investments on sustainable energy systems that enhance energy access,

    mitigate climate change and fuel economic development of the country. With detailedenergy sector information, RGC could also prioritize energy sector investments and

    development that promotes gender and social cohesion and equality as well asmainstream gender in the energy sector.

    In addition, the project is not only compatible with the development principles of RGCbut also complements and supports the achievement of the energy sector policy andrural electrification strategies contributing to the overall developmental goals of the

    National Strategic Development Plan. Energy information and plans will be used byRGC to prioritize energy investments that achieve and optimize developmental benefits

    from improving energy access to stimulating rural development, protecting theenvironment and promoting gender equality. Similarly, energy sector information and

    plans will provide the private sector the basis for making decisions to invest in energysector development.

    The project also supports the creation of the Energy Statistics Office from the existingSecretariat of General Department of Energy of MIME, and strengthens its capacity inorder to meet its responsibilities and be able to perform its tasks as a designated

    statistical unit. Thus the project fulfils the mandate of the Statistical Law and the Sub-Decree on the Organization and Functioning of the National Statistical System. In

    addition, by placing the National Institute of Statistics (NIS) as member of the SteeringCommittee, the project further satisfies the requirement of the Law ensuring

    coordination between the designated statistical unit and NIS. Energy Modelling Unitenables long-term energy planning.

    The project design ensures long-term sustainability of the project:

    Pre-conditions related to the creation and staffing of the Energy Statistics Officeand Energy Modelling Unit. The Energy Statistics Office will be created from the

  • 8/2/2019 Energy Balance Project Document FINAL

    9/87

    April 2011 - Page 9 / 87 -

    existing Secretariat Office of the General Department of Energy bystrengthening and redirecting its activities

    This project makes sure that MIME will own the project and take the lead in the

    implementation of activities through leadership of the Project Management Unit(PMU).

    The overall project design emphasises capacity development in data collection,energy modelling and policy planning. Project also ensures learning by doingapproach for the above-mentioned MIME units.

    Data Collection Working Group enhances the practical data collection and

    cooperation between relevant data producing Ministries. National Annual

    Workshop for Policy Planners presents project activities and results as well as

    action plan to the high level actors in line Ministries and other organizations,

    which also increases information flow between Ministries.

    The entities to be strengthened by the project will be providing services to thepublic and private sectors. The information services are required by government

    agencies, private sector and non-profit organizations for various activities for

    planning, research and investment decisions. The project builds capacity to

    respond constant demand for information and planning services.

    Project implementation

    Project activities implementation will be integrated within the General Department of

    Energy which is the main counterpart of the project. The General Department of Energyshall create the Energy Statistics Office from existing Secretariat Office, and the EnergyDevelopment Department shall create the Energy Modelling Unit within Planning Office

    as necessary entities for project implementation. Primary data collection is organised incooperation with other Ministries and other organisations through Data Collection

    Working Group. The Head of the Energy Statistics Office (ESO) will become the ProjectDirector. This Team will be supported by the projects Chief Technical Advisor (CTA)

    who will be the Project Co-Director and by the Project Officer (PO) who will beresponsible for project administrative tasks. The CTA and PO will be engaged by the

    Ministry for Foreign Affairs of Finland. This group will constitute as the ProjectManagement Unit (PMU). The PMU will be supervised by a Steering Committee. Theproject is tabled for financing in 2011.

    Project beneficiariesThe project beneficiaries are i) MIME (including Provincial Departments of Industry,Mines and Energy DIMEs) whose staff will receive technical support. MIME will also getthe data needed for national energy policy planning and for international reporting (e.g.for ACE and IEA) ii) Ministry of Environment which can use the energy data for nationalcommunication in reporting for UNFCCC; iii) ;Ministry of Planning receives informationon middle and long term energy development for the basis of national policy planning(e.g. National Strategic Development Plan, and National Poverty Reduction Strategy).Government agencies that benefit from the results generated by project includeElectricit du Cambodge, Electricity Authority of Cambodia, and others that will use theproject results as input for their activities. Private entities and investors will also benefitfrom the use of energy information which serves as basis for their investment decisions.

    In general, the Cambodian society will benefit from better targeted energy infrastructureplanning and from private sector investments on energy services. Particular attention is

  • 8/2/2019 Energy Balance Project Document FINAL

    10/87

    April 2011 - Page 10 / 87 -

    paid to increasing energy access and affordability of energy services to populationgroups that are easily marginalized, emphasizing productive uses of energy.

  • 8/2/2019 Energy Balance Project Document FINAL

    11/87

    April 2011 - Page 11 / 87 -

    1 Background

    Energy services in Cambodia are inadequate and expensive which are symptomatic to

    the existence of significant barriers that hinder the development of sustainable energysupply systems in the country. Among the government agencies and ministries in

    Cambodia, the Ministry of Industry, Mines and Energy (MIME) is one of thoseinstitutions with limited information concerning the sector and lack of adequate training

    and capacity building (both physical and financial) to establish energy informationsystem and energy supply planning. Yet the potential role of MIME in supporting the

    RGCs economic growth, environmental and climate change protection anddevelopment goals is enormous.

    Compared with other agencies, the National Institute of Statistics (NIS) of the Ministry

    of Planning for example, through strong donor support, is able to carry out routinely(every 4 years since 1993 and annually since 2007) Cambodian Socio-Economic

    Survey (CSES) which provides excellent data on household expenditure and livingconditions whose trends over the past two decades offer an insight on the developmentof different income groups in the country.

    Similarly, the Ministry of Agriculture, Forestry and Fisheries (MAFF) publishes yearlyreports about the state of the Cambodian agriculture including data on produce, yields

    and cost. The Ministry of Transportation publishes statistics of vehicles and estimateson fuel consumption. The Statistics Unit of Industry and Mines departments of MIMEalso publish statistics and information concerning industry and mining in the country.

    Specific information on electricity demand and generation capacities are howevercompiled and published yearly by the regulatory agency, the Electricity Authority of

    Cambodia (EAC). The current energy balance available at MIME does not provide a

    reliable national picture since data and information from several institutions and lineministries were collected on secondary data. On the other hand MIME does not havethe financial resources or capacity to carry primary data gathering.

    The lack of information and adequate capacity building to carry out comprehensiveplanning are identified as the main contributing factors to the current circumstances ofthe energy sector in Cambodia. MIME requested support to build capacity to develop areliable energy balance for which energy development planning could be built upon.

    MIME requested the Finnish Government for support in developing the capacity onenergy statistics, balance and energy planning.The letter sent by MIME to MFA, dated

    January 5, 2008 stated the following needs to develop strategic energy planning work

    in Cambodia:

    Create a network, which coordinates the data collection and construction of

    annual energy balance together with local government agencies and industries inCambodia;

    Develop the energy planning activities in Cambodia through capacity building;

    Construct energy models for planning purposes in order to enhance capabilitiesfor long term scenario building for future energy planning in Cambodia;

    Create basis for effective climate policy planning by providing needed databaseand providing capacity building; and,

    Develop duration programme and facilitate collaborative research for energybalance construction and energy planning.

  • 8/2/2019 Energy Balance Project Document FINAL

    12/87

    April 2011 - Page 12 / 87 -

    This project document details the response of the Finnish Government to the above-mentioned request.

  • 8/2/2019 Energy Balance Project Document FINAL

    13/87

    April 2011 - Page 13 / 87 -

    2 DEFINITION OF INTERVENTION

    2.1 Problem Analysis

    Biomass is the most important source of energy in Cambodia and it will continue to be

    the dominant energy resource in Cambodia for the short and medium term. Therefore itis essential to recognize the contribution of wood energy in the energy balance and to

    plan for a continued and sustainable supply of wood. At the moment 70-75% of totalenergy consumption is based on biomass, mainly fuel wood and charcoal. Households

    consume 87 % of all energy in Cambodia. Fuel wood is by far the main source ofenergy for cooking with urban areas shifting to charcoal. Still more than 90% of the

    rural households depend on firewood (See Annex 1). Wood fuel energy is also used ine.g. brick and garment industry.

    Due to high dependence on biomass and to the significant role of the households intotal energy consumption, in the energy balance construction the central issues are (i)collection of gender disaggregated household level data on energy consumption from

    different provinces; (ii) data collection of both supply and utilization of biomass forenergy. This is particularly pertinent given the disparity in fuel wood resources within

    and between provinces, and the significant impact that the lack of access to biomasshas on the poor. Deforestation is severe in Cambodia. In some areas it is difficult to find

    wood for cooking. Deforestation increases climate change and locally can create e.g.flooding and drought and therefore impact food production. It is essential to establishgood co-operation between the relevant ministries responsible for energy and forestry(especially MIME and MAFF).

    Household energy consumption data relates to many socio-economic andenvironmental issues that can be used in policy planning. These include, e.g. the use ofenergy in different socio-economic groups; money spent on energy in different socio-

    economic groups; the impact of increases in energy price on the food security; the timeallocated to wood collection; the changes in the access to fuel wood (how rapid

    deforestation, reasons for deforestation etc.). There are differences how men andwomen use energy, which mostly relate to their different social roles in the society. Also

    problems and priorities relating to energy can be different. Therefore, genderdisaggregated energy data is also needed. Fuelwood for cooking is mostly (but notonly) collected by women who often spent significant amount of time in collecting wood,especially in the areas where deforestation is severe. Women and children are alsooften the victims of indoor air pollution caused by wood fuel burning.

    Besides biomass emphasis should be given to different factual and potential renewableenergy sources, including agricultural waste such as rice husk. The role of renewable

    energy in energy planning is crucial. At the moment most electricity in Cambodia isproduced by fossil fuels that cause local pollutants as well as greenhouse gases. As

    the oil prices are expected to rise rather than decline, this will cause increase in foodprices as well as problems in balance of payments.

    Currently energy and electricity services in Cambodia are inadequate and lessaffordable with supply systems highly vulnerable to external disruptions and fluctuations

    in international energy prices and increasingly contributing to local environmentalpollution and greenhouse gas emissions. These are the results of an electricity supply

    system which is highly fragmented, less extensive (mainly providing services in largeurban centres) and highly dependent on imported fossil fuels. The lack of energy

  • 8/2/2019 Energy Balance Project Document FINAL

    14/87

    April 2011 - Page 14 / 87 -

    services particularly those in rural areas and unaffordable energy services in urbanareas could undermine economic growth and sustainable development of the country.

    Various underlying causes to generate these issues were identified such as the

    following: i) lack of information and knowledge on the real needs of the diversifiedsegments of the society, ii) lack of information and awareness of the availablesustainable indigenous resources, iii) lack of knowledge on alternative approaches and

    mechanisms in energy service provisions, and iv) lack of adequate training to criticallyanalyze, respond and strategically plan and develop energy supply systems.

    In addressing these issues, the project will focus on removing these barriers throughstrengthening the capacity of the Ministry of Industry, Mines and Energy in the field of i)energy statistics and information system, and ii) energy and electricity planning.

    2.2 Project Approach

    The overall project approach can be described as follows: first the project focuses onthe role of MIME in the National Statistics System by strengthening the capacity of

    MIMEs Energy Statistics Office (created from Secretariat Office), and second, on therole of MIME in the National Energy Planning by strengthening the capacity of MIMEsEnergy Modeling Unit.

    In both approaches, the project provides assistance in the establishment of therespective units, in defining the functions and in identifying the expertise needed to fulfil

    their mandates. Various types of trainings will be conducted related to energydatabase and information systems for the national statistics system; and demand

    analysis and forecasting, and energy demand-supply balancing analysis for energy

    planning system.

    Project is based on the assumption that energy planning should serve the overall socio-

    economic development planning and not function as a separate entity. The inclusion ofsocio-economic and environmental aspects in the energy planning requires informationof the interlinkages of these activities and sectors. The possibilities to utilise synergiesand avoid trade-offs in the development of different sectors should be taken into

    account in the planning by combining indicators from different fields into a coherentplanning framework.

    The Cambodian national statistic system contains lot of socio-economic information

    from different surveys, but it is not connected to the energy statistical information. The

    formulation of energy statistics should take into account the present statistical systemsin order to enable the use of them together. This means e.g. that the sectoral divisionsof the statistical information should follow similar sectors in order to enable the use ofdifferent energy-economic models. The National Accounting uses sectoral divisionindicated in the Box 1:

    Sectoral allocation of GDP in National

    Accounting in Cambodia

    AGRICULTURE, FISHERIES & FORESTRY

    Crops

    Paddy

    Other crops

    Livestock & PoultryFisheries

    Forestry & Logging 1

    INDUSTRY

  • 8/2/2019 Energy Balance Project Document FINAL

    15/87

    April 2011 - Page 15 / 87 -

    Mining

    Manufacturing

    Food, Beverages & Tobacco

    Textile, Wearing Apparel & Footwear

    Wood, Paper & PublishingRubber Manufacturing

    Other Manufacturing

    Non-Metallic Manufacturing

    Basic Metal and Metal Products

    Other manufacturing

    Electricity, Gas & Water

    Construction

    SERVICES

    Trade

    Hotel & Restaurants

    Transport & Communications

    FinancePublic Administration

    Real Estate & Business

    Other services

    Box 1: Sectoral division in National Accounting in Cambodia

    For modelling purposes it would be advantageous to use similar sectoral division in

    energy data collection in order to be able to link the energy use in different sector to thevalue added produced in these sectors. The revised International Recommendations

    for Energy Statistics (IRES) that are being developed by UN Statistics Division,

    including the Energy Statistics Compilers Manual, should be followed to the maximumextent within the project. IRES and the System of Environmental-Economic Accountingfor Energy system of UN (SEEA-E) are two complementary and fully coordinated

    documents. The IRES principles acknowledge that needs of major user groups shouldbe considered as a starting point and be taken into account to the maximum extent

    possible to ensure that the compiled data are policy relevant, meet the needs of theenergy community (both producers and users) and provide a solid foundation for

    integration of energy statistics into a broader accounting framework. The IRESguidelines does not support so detailed division of sectors, but for modelling purposes itwould create crucial benefits. However, it has to be taken into account that, in somecases, the costs of extra data collection and organisation may exceed the benefits

    obtained.Both demand side and supply side energy data is needed for energy balanceconstruction. Data should be collected annually. Primary data collection is organised in

    cooperation with Ministries and other organisations in the most efficient and sustainablemanner through Data Collection Working Group. Members of this working group arethose who are involved in actual implementation of data collection.

    Both bottom-up and top-down approaches are used in energy data collection andplanning. In the bottom-up approach it is possible to combine socio-economic and

    environmental household level data to the energy use in these households. This makesit possible to use e.g. gender or income specific analysis for supporting energy

    planning. Also the household level and gender specific information of health aspects

    and environmental issues can be taken into account in the data analysis. The top-downapproach in energy data collection and planning makes it possible to link the energydevelopment to macro-economic and sectoral development planning. This is crucial in

  • 8/2/2019 Energy Balance Project Document FINAL

    16/87

    April 2011 - Page 16 / 87 -

    making scenarios for future demand and assessing the needs for larger scale energyproduction and transmission investments.

    In order to guarantee the flow of information at the high level authorities (director and

    vice-directors), National Annual Workshop for Policy Planners is organised every yearin order to present the project activities and results as well as work plan for thefollowing year.

    The project approach can be described as follows: first the project focuses on the role

    of MIME in the National Statistics System by strengthening the capacity of MIMEsStatistical Office, and second, on the role of MIME in the National Energy Planning bystrengthening the capacity of MIMEs Energy Modelling Unit. The project providesassistance in the establishment of the respective units, in defining the functions and in

    identifying the expertise needed to fulfil their mandates. Various types of trainings willbe conducted related to energy database and information systems for the national

    statistics system; and demand analysis and forecasting, and energy demand-supply

    balancing analysis for energy planning system.Vital tools, methodologies and models will be provided related to surveys, analysis and

    information system management for the national statistics system, and demandanalysis, and demand-supply optimization for national energy planning system.

    In strengthening the role of MIME in both the national statistical system and energy

    planning, the project will be involved in the publications of annual energy balance,energy and power statistics and other relevant energy sector information as well aspublication of energy plans.

    The project will also adopt a learning-by-doing approach in capacity building. The staffof the Energy Statistics Office and Energy Modelling Unit will carry out the programmed

    project activities such as actual surveys, analysis, preparation of energy balances,energy statistics, demand simulation, demand-supply analyses, and preparation ofenergy plans. The role of the consultants will be to provide training on the concepts,analytical frameworks, methodologies, tools and models.

    2.3 Overall Objectives

    The overall objective is to contribute to planning and implementing of Cambodianclimate change policy and programmes through development of sustainable energydata and planning system which promotes inclusive growth and responds to povertyreduction and sustainable development goals of Cambodia

    Specific indicators for monitoring the project objectives are the following:

    Increase investment in renewable energy and energy efficiency

    Improved access to energy services

    Enhanced energy security

    Reduction of local environmental and greenhouse gas emissions

    These indicators will be verified through the national and regional energy sector andenvironmental development reports.

  • 8/2/2019 Energy Balance Project Document FINAL

    17/87

    April 2011 - Page 17 / 87 -

    2.4 Project Purpose

    The project purpose is to strengthen MIME to be sustainable and capable of employing

    advanced techniques, methodologies and modeling tools in:

    establishing and managing energy information system, and

    drawing up plans for energy sector development, and for climate changemitigation and adaptation

    prioritizing energy sector and climate change mitigation interventions

    mainstreaming of gender and poverty in energy planning.

    Specific indicators for monitoring the project purpose are the following:

    establishment energy information system in Cambodia with gender-disaggregated statistics where appropriate

    MIMEs contribution to the national economic and development planning as wellas to climate change intervention planning process and international reporting

    Achievements of Energy Statistics Office and Energy Modelling Unit actionplans

    These indicators will be verified through the evaluation study on energy information andplanning; project evaluation of MIMEs statistical office and energy modelling unit;

    publications of official documents (energy balance, statistical yearbooks, energy andpower strategy plans) and through MIMEs website; and steering committee reviews.

    2.5 Project Components

    To achieve the objectives and purpose, the projects activities and outputs areorganized into four overlapping components:

    Component 0: Project Management

    Component 1: Establishment of Energy Information System and Database

    Component 2: Capacity Building for Energy Modelling

    Component 3: Capacity Building for Energy Planning

    Components are represented in Figure 1 below.

  • 8/2/2019 Energy Balance Project Document FINAL

    18/87

    April 2011 - Page 18 / 87 -

    Figure 1: Project components

    2.6 Results, Achievement Indicators and Activities

    One of the expected results of the project is to develop an Energy Information System.An important feature of the system is that there is a regular production and

    dissemination of information on energy statistics, balances and various plans tostakeholders through publications, workshops, presentations, etc. Such information

    can also be uploaded in MIMEs website and hard copies will be available in bothEnglish and Khmer to line ministries, NGOs, private sector and international agencies.The structure of the information system is shown in Figure 2.

    The results, achievement indicators and activities for each specific component arediscussed in the following sections.

    Component 0: Project Management

    Establishment of Project Management Unit (PMU)Establishment of Energy Statistics Office (ESO)

    Establishment of the Energy Modelling Unit (EMU)

    Establishment of National Annual Workshop for Policy Planners

    Component 1: Establishment of Energy Information System and DatabaseCapacity building for data collection

    Establishment of National Energy Statistics for Cambodia

    Establishment of Energy Balance for Cambodia

    Component 2: Capacity Building for Energy ModellingCapacity building for long term energy modelling and planning

    Capacity building for power sector modelling and planning

    Component 3: Capacity Building for Energy PlanningCapacity Building for Energy Planning

    Preparation Energy Supply/Demand Balancing scenarios and energy strategy plan

    Capacity building for electricity demand load scenarios and power strategy plan

  • 8/2/2019 Energy Balance Project Document FINAL

    19/87

    April 2011 - Page 19 / 87 -

    Figure 2: Energy Information System Structure

    2.6.1 Component 0: Project Management

    The objective of this component is to create the central units, i.e. Project ManagementUnit (PMU), Energy Statistics Office (ESO), Energy Modelling Unit (EMU) and NationalAnnual Workshop for Policy Planners.

    Results Achievement Indicators Activities

    Established ProjectManagement Unit

    Adequately staffed PMUestablished and active

    Assigning the space for,tendering the staff positions and

    furnishing the PMU

    Established Energy Statistics

    Office (created from existing

    Secretariat Office)

    Adequately staffed ESO

    established and active

    Assigning the space for,

    tendering the staff positions and

    furnishing the ESO; Nomination

    and appointment of 4-6 people

    to be trained as statistics

    experts

    Established Energy Modelling

    Unit

    Adequately staffed EMU

    established and active

    Assigning the space for,

    tendering the staff positions and

    furnishing the EMU; Nominationand appointment of 3-5 people

    to be trained as modelling

    Policy

    Planners

    MoP

  • 8/2/2019 Energy Balance Project Document FINAL

    20/87

    April 2011 - Page 20 / 87 -

    experts

    Annually organised Workshop

    for Policy Planners

    Project activities, results and

    action plans are presented and

    discussed in the workshop

    Inviting the members to the

    National Annual Workshop for

    Policy PlannersOrganisation of National AnnualWorkshop for Policy Planners.

    Table 1: Results, Achievement Indicators and Activities of Component 0.

    The specific indicator of this phase is that adequately staffed Project Management Unit,Energy Statistics Office and Energy Modelling Unit within MIME are operational. The

    results, achievement indicators and activities of this phase are shown in Table 1. Moredetailed activities are shown in Annex 4.

    2.6.2 Component 1: Establishment of Energy Information System andDatabase

    The objective of this component is to establish the Energy Information System and

    database to serve, firstly, national policy planning, not only for energy sector but also tobenefit economic planning (including National Strategic Development Plan) and

    environmental sector. Secondly, the energy information system and database will alsohelp to fulfil Cambodias international reporting obligations defined e.g. by ASEANCenter for Energy (ACE), International Energy Agency (IEA) and United Nations

    Framework Convention on Climate Change (UNFCCC). Data collection is done incollaboration with line Ministries and other institutions through Data Collection WorkingGroup. From the beginning the data collection is planned in such manner that it is cost-

    effective and sustainable, i.e. annual data collection and analysis is able to continuealso after the project has ended. The establishment of energy information system will

    require the analysis of the energy data needs of different Ministries and otherorganisations (including Ministry of Environment), and clarification of the availability of

    already existing primary data. After the assessment of data needs and existing data thecomplementary surveys will be will be made.

    The results, achievement indicators and activities of this component are shown in Table

    2. More detailed activities are shown in Annex 4.

    Results Achievement Indicators Activities

    Institutionalcooperationarrangements andquality controlmeasures forobtaining requireddata in cost-effective and

    sustainably way arein place

    Report onelaborated data

    Data Collection WorkingGroup is established and ismeeting regularly

    Energy data collection planagreed by key stakeholdersis adopted

    Signed institutionalagreements (etc.) for

    obtaining the requiredprimary data from differentsources are in place

    Analysing the type and levelof detail of required primarydata to serve differentplanning and internationalreporting needs

    Clarifying of alreadyexisting data and plan forcomplementary data

    collection and utilization Revision of existing survey

    questionnaires andsamples, if needed

  • 8/2/2019 Energy Balance Project Document FINAL

    21/87

    April 2011 - Page 21 / 87 -

    needs (livingdocument)

    Negotiations withcooperating entities toobtain the required primarydata in most cost efficientand sustainable way. .

    Trained staff of theEnergy StatisticsOffice and itscollaboratingagencies tomanage, collect andsubmit data

    Establishment ofEnergy InformationSystem

    Software selected

    Trainings organised

    Preparation of surveyquestionnaires; checkingthe existing questionnaires

    At the end of the projectstaff of ESO and its partnerinstitutions are capable ofupdating and checking thequality of the data

    Selecting the software for

    and designing the structureof database

    Trainings on methodology,

    design, implementation,

    data processing quality

    control, maintenance etc.

    10 experts from MIME and

    other organizations are

    trained.

    Energy Balancecompleted

    Information can beobtained in flexibleand user friendlymanner

    Surveys and other datacollection methods areimplemented. Datacollection is repeatedannually

    Energy Balance is prepared

    Stakeholders are consulted Data is published

    Data collection, compilationand analysis

    Organisation of NationalAnnual Workshop for PolicyPlanners

    Publication of data

    Statistic Law ismodified

    Proposal of modification ofthe Statistic Law to improvethe collection of data on apermanent basis

    Preparation of the proposalto modify the Statistic Law

    Table 2: Results, Achievement Indicators and Activities of Component 1

    2.6.3 Component 2: Capacity Building for Energy Modelling

    The objective is to train the staff in the Energy Modelling Unit in energy modelling. Atthe end of the project Energy Modelling Unit will be able to scenarios that will benefit

    policy planning. They are able to assess energy resource requirements anddevelopment of long-term sustainable supply options based on RGCs economic

    development scenarios to be used for energy sector and climate change policyplanning, and as input to Cambodias National Strategic Development Plan. The

    scenarios will be made available for other stakeholders, national and internationalorganizations, private companies, and donor agencies.

    The results, achievement indicators and activities of this phase are shown in Table 3.More detailed activities are shown in Annex 4.

    Results Achievement Indicators Activities

    Energy Modelling Unit

    (EMU) Staff is trained toconduct analysis

    The Energy Modelling Unit

    (EMU) equipped with

    state-of-the art software for

    Model(s) have been selected

    to prepare long termscenarios

    Energy planning models are

    used for demand and supply

    scenario construction for

    Different trainings on

    energy demand analysismethodologies and

    models

    Finalising the basic

    structure and deciding on

  • 8/2/2019 Energy Balance Project Document FINAL

    22/87

    April 2011 - Page 22 / 87 -

    Table 3: Results, Achievement Indicators and Activities of Component 2.

    2.6.4 Component 3: Capacity Building for Energy Planning

    The Component 3 focuses on capacity building for energy planning. It includes trainingof Energy Modelling Unit experts on energy planning methodologies and models, as

    well as socio-economic and environmental linkages related to energy planning. Energyand electricity scenarios will be made. National Annual Workshop for Policy planners of

    high level decision makers from various energy entities will discuss about long termenergy development. Long-term energy supply/demand balancing scenarios will beprepared and published. Based on the scenarios and discussions within the Workshoppolicy plans and interventions will be planned and published in the form of energy

    strategy plan. Similarly power sector scenarios will be constructed and discussed inthe Workshop, and after formulation of policy plans and interventions a power sector

    development strategy will be published.

    The results, achievement indicators and activities of this phase are shown in Table 4.More detailed activities are shown in Annex 4.

    energy modelling taking

    into account the specifics

    of the Cambodian energysector and its socio-

    economic and

    environmental

    considerations.

    Trained staff to conduct

    the analysis.

    different sectors, integrating

    the socio-economic and

    environmental impactassessment in the planning.

    the factors (including

    socio-economic and

    environmental) to betaken into account in the

    modelling and shown in

    the energy supply-

    demand scenarios and, as

    needed, conducting

    additional data gathering,

    studies and surveys to

    serve the analysis.

    Finalized scenarios for

    both energy and electricitysupply and demand in

    different economic sectorscorresponding with the

    environmental targets and

    general socio-economicdevelopment plans.

    The energy supply and

    demand scenarios includingsocio-economic and

    environmentalconsiderations are finalized

    and the results published.

    Finalisation of the analysis

    in co-operation with localand international experts

    (with simultaneous on-the-job training) and

    publishing of its results

    (including feedback fromNational Annual

    Workshop for Policy

    Planners) together with

    related presentations in

    workshops, etc.

    Recommendationsaddressing the identified

    data gaps and suggestionfor improving the Energy

    Information System to

    better serve the energy

    modelling and planning.

    Recommendationsaddressing the identified

    data caps provided

    Revision of annual surveyquestionnaires if needed

    Research of additionaldata needed for power

    sector modelling

    Checking the consistency

    of input data sets for

    selected models

  • 8/2/2019 Energy Balance Project Document FINAL

    23/87

    April 2011 - Page 23 / 87 -

    Results Achievement Indicators Activities

    The Energy Modelling Unit(EMU) equipped with state-of-the art software for energysupply and policy planningtaking into account thespecifics of the Cambodianenergy sector, theenvironmental and socio-economic aspects

    Trained experts are able totake into account socio-economic and environmental

    linkages of energy issues

    Energy supply, socio-

    economic and

    environmental impact

    assessment as well as

    climate change mitigation

    and adaptation analysis and

    scenarios are being

    prepared by EMU by using

    the selected software.

    Evaluation, selection and, asneeded, modification of theenergy supply and policyplanning software or softwarepackage to cover theidentified energy sectorplanning and interventionprioritization needs within theset socio-economic andenvironmental targets.

    Training of the staff of theEMU on i) energy supply and

    policy planning and how tocombine it with energymodelling in general and byusing the selected softwarepackages, ii) the integrationof the socio-economic andenvironmental targets andimpact assessment withenergy planning, and iii)management of theuncertainties andcomplementary datagathering.

    Various long term energydemand scenarios havebeen prepared with detailedexplanation of hypothesis,results and potentialconsequences

    National Annual Working

    Group for Policy Planners

    discusses the targets and

    long term scenarios

    The working group is

    established and meetings

    are organised

    Establishment of National

    Annual Working Group for

    Policy Planners (high level

    decision makers)

    Long term energy strategy

    plan is completed

    Results have beendisseminated and

    commented

    Scenario results are

    published

    Results are commented bythe Working Group and

    finalized

    Finalising the basic structure

    and factors to be taken into

    account in energy strategyplan

    Finalisation of the analysis in

    co-operation with local andinternational experts.

    Finalizing the supply-demand

    scenarios and related policy

    and intervention plans based

    on the workshop feedback

    Power strategy plan is

    completed

    Results have beendisseminated and

    commented.

    Cambodia's long term

    power demand load

    forecasts and productionscenarios are published

    Power sector developmentplan is prepared and reports

    Finalising the basic structure

    of power sector modelling

    and deciding on the factorsto be taken into account and,

    as needed, conductingadditional data gathering,

  • 8/2/2019 Energy Balance Project Document FINAL

    24/87

    April 2011 - Page 24 / 87 -

    are published.

    Power sector supply-

    demand balancingscenarios including socio-

    economic and

    environmental impacts arediscussed in the Working

    Group, scenarios are

    finalized and published.

    studies and surveys to serve

    the analysis.

    Finalisation of the analysis inco-operation with local and

    international experts.

    Finalizing the power sectorsupply-demand scenarios

    and related policy and

    intervention plans based on

    the workshop feedback.

    Table 4: Results, Achievement Indicators and Activities of Component 3

    3 ASSUMPTIONS AND RISKS

    Institutional

    One of the main assumptions in the design of the project is that the Secretary of Stateis supportive of the project, and agrees to the transformation of the Secretariat Office

    into Energy Statistics Office (ESO) and the establishment of the Energy Modeling Unit(EMU) under the Energy Planning Office. Existing Secretariat Office will be reorganised

    to accommodate the Energy Statistics Office in MIME. This avoids the risk of creatingan additional department in MIME where a moratorium in establishing new departments

    in government agencies is currently imposed. There is also a risk that the project officewill be attached to a lower unit in MIMEs hierarchy which may limit inter-ministerialcoordination. The level of the Secretariat turned Statistical Office however is already

    high in the MIME hierarchy and the Office reports directly to the Director General.Another key assumption is that the National Institute of Statistics (NIS) of Ministry of

    Planning supports the establishment of the Energy Statistics Office of the GeneralDepartment of Energy as one of the designated statistical units of MIME under the

    Statistics Law and Sub-decree on the Organization and Functioning of the NationalStatistical System. The Law and the Sub-decree strengthens the case for this project.

    However, energy data collection on a permanent basis, in collaboration with differentenergy data producing organizations should be guaranteed by legislation. Statistics

    Law should be modified accordingly. The procedures specified and the rules stipulatedin the Statistics Law should be enforced. Confidentiality agreement should be used andpenalties stipulated under the Law should be enforced.It is also assumed that the

    Electricit du Cambodge (EDC) supports this initiative and will provide necessaryinformation and inputs related to the generation, transmission and distribution ofelectricity. In addition, the project design also assumes full participation andcooperation from other government agencies and provincial authorities.

    Capacity

    The lack of experience in energy statistics and planning as well as the lack ofmultidisciplinary skills in MIME and the Provincial Departments of Industry, Mines and

    Energy (DIME) may undermine the project. The technical assistance therefore willfocus on developing the required specialized skills. If the training of the trainers

    method is used to increase the capacity of DIME staff, sufficient amount of time should

    be allocated for learning and actual use of new methods before the new trainers trainothers. Also the quality of the teaching provided by newly trained trainers should befollowed. Several persons from each province should be trained to increase the

  • 8/2/2019 Energy Balance Project Document FINAL

    25/87

    April 2011 - Page 25 / 87 -

    sustainability (in case trained personnel migrate from the province etc.) The project isbased on increasing the capacity and therefore resources and time should be allocatedto this purpose. Careful planning of the trainings will increase the sustainability of the

    project.Furthermore, even though the capacity-building in DIMEs would focus mostly on thosewho will be collecting the data, workshop(s) should also be organized for high level

    provincial authorities to inform about the rational of the project, objectives and methodsof energy data collection, as well as to receive their input and support.

    The trainings should be conducted by different short-term experts with good knowledgein both the substance of the trainings as well as training methods. Experts should coverwide range of issue areas including energy and power planning, statistics, information

    systems, social and environmental impact assessment, renewable energy and genderissues. (See Annexes 2 and 3)

    The technical assistance focusing mainly for MIME and DIME may also create a risk

    that there may be only limited specialized skills being developed by the project.Universities and Institutes are being involved in the project in such a way that specific

    skills required in energy statistic analysis and planning be taught in these institutions,thus increasing the available qualified staff in the country and increasing the impact of

    the project on human capacity development. However, at the moment, the Institute ofTechnology of Cambodia needs additional capacity building in the field of energymodelling and policy planning. This would increase the sustainability of the activitiesalso after the project funding ends.

    The project design also assumes that MIME staff is motivated to learn in energy

    statistics and planning. The project will further provide incentives for learning such asopportunities to participate in regional trainings and workshops.

    Financing

    It is assumed in the project design that MIME will provide the salary of the staff and will

    provide office space including basic utilities such as electricity and water use. Theproject will however provide support in project operating costs, office equipment, and

    transportation and per diem (for field work). Trainings and capacity building activitieswithin the country and abroad will also be financed by the project.

    However, one of the most severe risks relates to the financing of the data

    collection and other activities after the ending of the project. Even if the capacity

    development would be successful, the data collection still requires annual

    funding.

    Energy Data

    Another assumption made in the project design is that there is a free flow of energydata from other Ministries, private sector or from other agencies to MIME. There is a

    risk relating to the continuous collaboration between MIME and other energy dataproducing Government agencies. Continuous collaboration in data collection is

    necessary not only at the beginning but also in the future. MIME will need tocollaborate closely with e.g. NIS, MAFF and MoE, Ministry of Commerce, Ministry ofPublic Works and Transport to get data without extra payment. This requires

    commitment also from other Ministries, not only MIME. Data Collection Working Groupand Steering Committee will be established to enhance collaboration between the dataproducing (and using) organisations. Also National Annual Workshop for PolicyPlanners will be organised every year for the high level officials.

  • 8/2/2019 Energy Balance Project Document FINAL

    26/87

    April 2011 - Page 26 / 87 -

    Sustainability

    There is a risk that the once the support from the Government of Finland will culminate

    project activities will not be sustained. In general it can be said that long commitmentto capacity development creates best results (c.f. SIDA funding for NIS). The projectdesign ensures that the information system and energy planning will be supported inthe long term:

    The establishment of the Energy Statistics Office under MIME should be

    undertaken within the framework of Statistics Law which requires Ministries andagencies to create designated statistical units; in addition the annual

    publications of energy information and statistics will also create demand forsuch units;

    Since MIME is the only agency undertaking energy and power sector planning,

    once the capacity of these units are strengthened, the demand for energy andpower plans from government agencies and the private sector will ensure thatthe modeling unit will be needed and supported. This, however, requires goodcooperation and information exchange between different Government agencies;

    The structure of the project management unit in the project design making the

    Head of the Energy Statistics Office as Project Director and the Chief TechnicalAdvisor as Project Co-Director will also ensure that MIME owns the project at

    the inception stage, and that project activities are designed to be the routineactivities for both Statistics Office and Energy Modeling Unit.

    The sufficiently resourced trainings of the trainers and learning-by-doing

    approach also ensures that MIME staff are trained on their required skills. The

    quality of the training provided by newly trained trainers (e.g. in DIME) shouldbe guaranteed.

    4 COMPATIBILITY AND SUSTAINABILITY

    4.1 Compatibility

    4.1.1 Finnish Development Policy

    Finlands Development Cooperation Policy, in coherence with the United Nations

    Millennium Development Goals, aims to support activities that eradicate poverty andpromote sustainable development. Therefore the collection of socio-economic and

    environment related energy data both on different levels (including household andprovincial levels) is important. The energy planning benefits also environmentalplanning and reporting, as well as poverty alleviation measures and policy planning.

    The Finnish Development Policy issued in 2007 promotes actions that areenvironmentally, socially and economically sustainable. More specifically, the

    government aims to promote sustainable use of natural resources; to maintain thebiodiversity; prevent climate change, soil exhaustion and desertification and to protectliving conditions.

    In addition, the Finnish Development Cooperation aims to build on the partnercountries own poverty reduction and development strategies. The GovernmentDecision-in-Principle 2007 emphasises coherence, complementarity, and effectiveness.

  • 8/2/2019 Energy Balance Project Document FINAL

    27/87

    April 2011 - Page 27 / 87 -

    Policy coherence for development requires that strategies and actions in all policyareas support the goals of development policy in eradicating poverty and in sustainabledevelopment.

    Promotion of the rights and the status of women and girls, and promotion of gender andsocial equality is one of the cross-cutting themes supported by the FinnishDevelopment Policy. Gender equality is also a priority concept on Cambodias

    Rectangular Strategy for Growth, Employment, Equity, and Efficiency. Gendermainstreaming needs to be addressed in all policies. Men and women use energy

    differently, mostly due to their different roles in the society. Also problems and prioritiesrelating to energy can be different for women and men. Therefore, gender aspect

    should be taken into account at least in following issues: (i) different energy needs andenergy related problems determined by social roles and gender; (ii) different rights ofdecision-making in the selection of energy sources and equipment; (iii) differentparticipation in the maintenance and management system. These aspects could be

    taken into account in energy data collection. In addition, the gender differences in theserious health impacts of energy use, especially from firewood use for cooking, should

    be taken into account in planning. In developing alternatives for domestic energy,attention is to be paid to health and safety as well as efficiency, cost and convenience.

    Following issues could be used to improve the gender mainstreaming:

    1) A gender advisor should be hired as a short term expert. Gender audit isrecommended. The audit could follow ILOs guidelines for participatory Gender Audit.1

    According to the Ministry of Womens Affairs, also local experts are available to work as

    gender advisors. ENERGIA Network should be consulted if necessary.

    2

    The genderexpert should be hired during the first phase of the project. Important part of her/his jobwould be to comment draft data collection questionnaires and to plan household data

    collection as well as other surveys.

    2) Cooperation with JICAs Project on Gender Mainstreaming (PGM, Phase 2) isrecommended. In PGM project the main counterpart is Ministry of Womens Affairs but

    also MIME and five other line ministries are partners. JICA has in this project alsodeveloped methods in gender mainstreaming.3

    3) Representative of Ministry for Womens Affairs should be a member in Steering

    Committee, Data Collection Working Group and National Annual Workshop for PolicyPlanners.

    1A Manual for Gender Audit Facilitators. The ILO Participatory Gender Audit Methodology.

    International Labour Organisation (ILO). Geneva, 2007.2 ENERGIA is a international network on gender and sustainable energy (founded in 1996). ENERGIAdoes gender mainstreaming and capacity-building in Africa and Asia but they dont have a focal point

    in Cambodia (according to their web pages http://www.energia-asia.org/home/) but they provide

    regional gender and energy workshops.3 Sources given by JICA on gender mainstreaming:

    http://www.jica.go.jp/project/cambodia/0211055E0/04/pdf/01_eng.pdf and

    http://jica-net.jica.go.jp/dspace/handle/10410/697

    http://www.energia-asia.org/home/)http://www.jica.go.jp/project/cambodia/0211055E0/04/pdf/01_eng.pdfhttp://jica-net.jica.go.jp/dspace/handle/10410/697http://jica-net.jica.go.jp/dspace/handle/10410/697http://www.jica.go.jp/project/cambodia/0211055E0/04/pdf/01_eng.pdfhttp://www.energia-asia.org/home/)
  • 8/2/2019 Energy Balance Project Document FINAL

    28/87

    April 2011 - Page 28 / 87 -

    4) In planning questionnaires and selecting respondents gender issues should be takeninto account

    5) Socio-economic issues should be taken into account in energy data collection.

    Besides gender, other cross-cutting themes supported by the Finnish Development

    Policy are the following; Promotion of the rights of groups that are easily excluded,particularly children, people with disabilities, indigenous people and ethnic minorities,

    promotion of equal opportunities for participation; and Combating HIV/AIDS; HIV/AIDSas a health problem and as a social problem. In the Energy Balance project and in

    energy projects more generally, the relevant but easily excluded groups (besideswomen) are the poorest communities. Data collection questionnaires and energy policy

    planning should be formulated in such way that they would also take into the accountthe respondents from the poor communities and other easily excluded groups. These

    groups should also be taken into account when planning the sample and selecting therespondents to the questionnaires. Combating HIV/AIDS is not very relevant issue in

    energy data collection and energy planning, except possibly in the cases related to theconstruction of large power plants, where large number of migrant workers can create

    conditions favourable for spreading of HIV/AIDS. The role of children as workforce forenergy production (firewood collection) and their health impacts from the indoor air

    pollution from cooking stoves should also be seriously taken into account in the project.Furthermore the overarching goal of the project is the development of a sustainable

    energy supply system which is sensitive to developmental, energy security, and energyaccess goals of the country.

    With the energy information and energy sector development plans, the Government of

    Cambodia can make decisions and prioritized interventions on sustainable energysystems that enhance energy access and fuel economic development of the country.

    With detailed energy sector information, the Government of Cambodia could alsoprioritize energy sector policies and plans that promote poverty alleviation, climate

    change mitigation, and equity. In practise this could mean, for example, a program thatwould focus on promotion and support (e.g. with subsidies) of fuel wood saving cook

    stoves in the rural areas. Now the efficient cook stoves are mainly used in the cities.The efficient cook stoves would reduce the consumption of wood, which would have

    positive impacts on deforestation, climate change mitigation, time and/or money spentin fuel wood collection, less respiratory illnesses etc. The support of improved cookstoves program targeted on rural areas would benefit especially women (and children)

    and it would also reduce CO2 emissions.

    4.1.2 National Strategic Development Plan and Energy Sector Development

    The National Strategic Development Plan (NSDP) embodies the overarchingdevelopment policy and strategy of RGC to meet the Millennium Development Goals

    particularly the goal of eradicating poverty and human development. RGC adopted aRectangular Strategy for Growth, Employment, Equity, and Efficiency with GoodGovernance as the core and i) enhancement of the agriculture sector, ii) rehabilitationand construction of physical infrastructure, iii) private sector development and

    employment generation, and iv) capacity building and human resources developmentas the four main pillars. The main aim of the Rectangular Strategy is to promote

    economic growth, generate employment for Cambodian workers, ensure equity and

  • 8/2/2019 Energy Balance Project Document FINAL

    29/87

    April 2011 - Page 29 / 87 -

    social justice, and enhance efficiency of the public sector through the implementation ofthe Governance Action Plan and in-depth reforms that are coordinated and consistentacross all levels and sectors.

    Energy sector development plans are defined under the second pillar on physicalinfrastructure. RGCs energy sector policy aims to i) provide adequate supply atreasonable prices, ii) ensure a reliable and secure electricity supply, iii) encourage

    exploration of environmentally and socially acceptable development of energyresources, and iv) encourage efficient use of energy. In addition, RGC also developed

    a rural electrification strategy which aimed at increasing access to energy servicesparticularly those in rural areas improving living standards and promoting agriculturaland small-scale industrial development.

    This project is not only compatible with the development principles of RGC but alsocomplements and supports the achievement of the energy sector policy and rural

    electrification strategies contributing to the overall developmental goals of the National

    Strategic Development Plan. Energy information and plans will be used by RGC toprioritize energy investments that achieve and optimize developmental benefits fromimproving energy access to stimulating rural development, protecting the environment

    and promoting gender equality. Similarly, energy sector information and plans willprovide the private sector the basis for making decisions to invest in energy sectordevelopment.

    4.1.3 Statistics Law

    The Statistics Law was issued by RGC in 2005 governing the collection, processing,

    compilation, analysis, publication and dissemination of statistical data in the country.The Law assigns the National Institute of Statistics of the Ministry of Planning as the

    overarching body responsible for making official statistical policies in establishing anintegrated National Statistical System.

    In addition, the Law also required the Ministries and institutions of RGC to collect

    sectoral data either independently or in cooperation with the National Institute ofStatistics (NIS).

    A sub-decree on the organization and functioning of the National Statistical System was

    issued in 2007 detailing the main functions of NIS and the designated statistical unitwithin each Ministry or government institution.

    This project supports the establishment of the Energy Statistics Office (ESO) of

    General Department of Energy of MIME and strengthens its capacity in order to meetits responsibilities and be able to perform its tasks as designated in the Sub-Decree.

    Thus the project fulfils the mandate of the Statistical Law and the Sub-Decree. Inaddition, by placing NIS as member of the Steering Committee, the project further

    satisfies the requirement of the Law ensuring coordination between the designatedstatistical unit and NIS.

    However, Statistics Law should be modified to improve the energy data collection on

    permanent basis. Providing energy and other data to MIME on regular basis should berendered compulsory for main energy actors (supply and demand industries, utilities,commercial consumers, etc), as well for other line Ministries (Agriculture, Public Works

    and Transport, Finance and Economy, Environment, etc.)

  • 8/2/2019 Energy Balance Project Document FINAL

    30/87

    April 2011 - Page 30 / 87 -

    4.2 Sustainability

    The issue of sustainability has been raised in various discussions during the project

    preparation phases, thus sustainability is one of the key considerations in projectdesign. It is crucial that the project is sustainable and that the annual data collectioncontinues also after the project ends.

    There are features embedded in the project design that ensure long-term sustainabilityand these are the following:

    Pre-conditions related to the creation and staffing of the Energy Statistics Office

    from the already existing Secretariat Office, and of Energy Modelling Unit. Alsofunding of annual data collection activities should be guaranteed also after the

    project is completed. One of the pre-conditions set by the project is that MIMEshould establish and nominate staff of the Energy Statistics Office and Energy

    Modelling Unit to be funded from its internal financial resources. In this case, theproject will not create a new entity but strengthen the capacity of the existing

    units of MIME. This ensures sustainability with respect to financial support ofthe said units.

    Statistics Law. The establishment of the Energy Statistics Office will be

    undertaken within the context of the Statistics Law which requires Ministries andGovernment agencies to establish designated statistics units. Statistics Law

    should be modified to improve the collection of energy data on a permanentbasis, and to enable the continuous collaboration between different Governmentagencies producing energy and other relevant data.

    Continuous collaboration between MIME and several other Government

    agencies is needed, and therefore Data Collection Working Group isestablished to enhance information exchange. MIME will need to collaborateclosely with e.g. NIS, MAFF and MoE, Ministry of Commerce, Ministry of Public

    Works and Transport to get data without extra payment. This requirescommitment also from these Ministries, not only MIME.

    Design of the Project Management Unit (PMU). This technical assistance

    project makes sure that MIME will own the project and take the lead in theimplementation of activities. The Head of the Energy Statistics Office will be

    designated as the Project Director and will be responsible for the execution ofthe project activities and at the same time take the lead in undertaking routineactivities for the provision of energy information and preparation of energy

    plans. The role of the Chief Technical Adviser as Project Co-Director and othershort-term international experts will mainly provide capacity development,training, control and technical assistance.This ensures hands-on project

    implementation experience for the Energy Statistics Office and EnergyModelling Units.

    Organised trainings and learning by doing approach. The overall project design

    ensures learning by doing approach for the above-mentioned MIME units.International experts will provide specific trainings to MIME staff but the actual

    preparation of energy balance and statistical publications as well as thepreparation of energy plans will be carried out by the staff themselves, underthe supervision of experts. This guarantees learning and that the activities

    carried out in the first year will be routinely replicated in the following years. Demand for services. The entities to be strengthened by the project will be

    providing services to the public and private sectors. The Statistics Office will be

  • 8/2/2019 Energy Balance Project Document FINAL

    31/87

    April 2011 - Page 31 / 87 -

    generating publications such as energy balance and energy statisticalyearbooks, etc. On the other hand, the Energy Modelling Unit will be generatingenergy strategy plans, power strategy plans and other long term energy

    demand supply information. This information is required by governmentagencies, private sector and non-profit organizations for various planning,research and investment decisions ensuring constant demand for informationand planning services.

    5 IMPLEMENTATION

    5.1 Implementation Strategy

    MIMEs request to the Government of Finland for support and development of thecapacity on energy statistics, energy balance and planning requires at least 2 dedicated

    units responsible for energy information system and energy planning. The projectstrategy is to support MIME create these units under the General Department of

    Energy, and build their capacities through learning-by-doing approach. These units arethe Energy Statistics Office (ESO), which will be created from the existing SecretariatOffice, and Energy Modelling Unit (EMU).

    The first 4 months of the project will be the Inception Phase. During this period, theproject document will be reviewed and revised if necessary, and the first annual plan

    will be prepared with the annual budget and staffing revised if needed, withoutchanging the agreed project scope and purpose.

    During the inception phase, the logical framework will also be reviewed and amended ifneeded to add more detail to the proposed achievement indicators and quantify someof the outputs if possible. In addition, a monitoring plan will be prepared by the project

    management unit (PMU) in order to guarantee timely implementation and achievementof results.

    5.2 Data Collection

    5.2.1 Demand side data collection

    Both demand side and supply side energy data is needed for energy balance

    construction. Due to the decentralized system, many Ministries collect data that caneither directly or as bases of evaluation used in energy statistics and energy balance

    construction. The most feasible way to organize the data collection is to use the datacollected by MIME and other Ministries and to improve the quality of data collectionmethods and analysis.

    In this section is listed the energy data that is collected by MIME or other Ministries,and the recommendations on how demand side energy data collection should beorganized. Table 5 at the end of this section summarizes the energy data collectionrecommendations. ).

    Agricultural sector

  • 8/2/2019 Energy Balance Project Document FINAL

    32/87

    April 2011 - Page 32 / 87 -

    At the moment there are no statistics available on energy used in pumping, tractors andother machines used in agriculture.

    Solution for agricultural sector energy demand data collection: DIMEs could dosurveys about the energy consumption in the agricultural sector and cooperate withProvincial Departments of MAFF.

    Industrial sector:

    Industries provide MIME reports of the production value, but not energy use. Largeindustry (capital more than 500 000 USD) report every month by using MIMEs

    reporting format. Small and medium size industry companies report to MIME once ayear. There are no statistics available on the use of wood for energy in industrial sector

    (e.g. in brick and garment industry).

    Solutions for industry energy demand data collection:

    1) Energy questions could be added on the MIME questionnaire sent for companies

    2) Also questions on fuel wood and other biomass use should be included

    3) The use of wood as raw material should also studied in addition to energy use inorder to obtain information of the total demand of wood

    4) Electricity consumption in the industrial sector data can be obtained from Electricitedu Cambodge, Electricity Authority of Cambodia and Rural Energy Enterprises.

    Service sector:

    MIME has a questionnaire for all energy consumption and uses random samplingmethods for the commercial sector (restaurants, hotels, guest houses, shops etc.). InPhnom Penh MIME collects information and in the provinces DIMEs collect the data.Five star hotels are part of the industrial sector. Last time this was made was in 2009.

    Solution for service sector energy demand data collection: This questionnaire used

    by MIME can be used also in the future, possibly after revisions on questionnaire andsampling. Data should be collected annually, if possible.

    Transport sector:

    The fuel used in transport sector is imported (except possible future production of

    biofuels). Statistics concerning the fuel imports are available from CAMCONTROL(under Min. of Commerce) and Customs office. Statistics concerning the number ofvehicles are available from Ministry of Public Works and Transport. Energy use ofagricultural vehicles must be removed from the statistics as it is calculated in

    agricultural sector. There is no data on fuel consumption, so it must be estimated(especially for passanger cars). For evaluation of bus and freight transport fuelconsumption MIME uses survey.

    Solution for service sector energy demand data collection: Statistics fromCAMCONTROL (under Ministry of Commerce), Custom office and Min. of Public works

    and Transport can be used for fuel imports and number of vehicles registered.

  • 8/2/2019 Energy Balance Project Document FINAL

    33/87

    April 2011 - Page 33 / 87 -

    Questionnaire used by MIME for the evaluation of transport fuel consumption can beused also in the future (possibly after revisions on questionnaire and sampling).Information of annual kilometres driven by cars could be estimated from possible future

    collection of data during the technical car inspection.

    Household energy consumption:

    Household energy consumption data should be important part of the energy statisticsand energy balance construction due to the significant role of biomass (fuel wood and

    charcoal) in total energy consumption, and the fact that households consume almost90% of all energy. Household energy data collection should cover all forms of energy,including fuel wood and charcoal, and statistics should be gender dissaggregated.Socio-economic (especially concerning household data collection) and environment

    data should be included to energy data collection. At the moment there are nostatistics on household energy consumption, except what is collected in NationalInstitute of Statistics (NIS) annual socio-economic survey.4

    The household energy data collection should preferably be incorporated to NISsocio-economic surveys, if possible. This would enable the integration of the energy

    related socio-economic and environmental issues (especially regarding fuel wood) tothe energy statistics. In principle the measurement of household wood consumption in

    NIS socio-economic data is possible. However, it depends on funding, capacity andthe decisions how the survey is compiled in the future. In any case NIS expertise

    should be used to the extent possible in household energy data collection.5

    Solutions for data collection on household energy consumption:

    1) First option would be to add energy questions to socio-economic survey collected

    yearly by National Institute of Statistics (NIS) or to the survey of National Committee forSub-National Democratic Development (NCDD). Incorporation of energy questions to

    NIS or NCDD socio-economic survey would enable the linking of socio-economicissues in energy analysis. Negotiations considering this option should be carried outwith NIS and/or with NCDD.

    2) Second option is that DIMEs would conduct (all or part of) surveys on householdenergy consumption. This would require capacity building and other assistance. If

    DIMEs will collect the data, they need capacity-building and other support. Also asurvey questionnaire format has to be defined as DIMEs have not collected this kind of

    4There are few energy related questions in the NIS socio-economic survey such as the type of fuel

    used for cooking; money spent on electricity, firewood, charcoal, battery, LPG (etc); and electricity

    consumption. Collected wood fuel consumption is estimated in bunch (handful). The bunch

    (handful) varies according to the quality of wood.

    5 In the NIS socio-economic survey 2009 (published in December 2010) the sample was 12 000

    households which divided into 12 monthly samples of 1000 households in 60 villages.

  • 8/2/2019 Energy Balance Project Document FINAL

    34/87

    April 2011 - Page 34 / 87 -

    data. UNDP rural household survey questionnaire as well as Finland Futures ResearchCentres (FFRC) survey questionnaires could be taken as reference and modified.6

    Also methods used in Department for Alternative Energy Development and Efficiency of

    Thailand (DEDE) to calculate daily house hold wood fuel consumption could be usedand developed further, if necessary.

    Decision on how household data is collected should be made in the inception phase.Collection of gender disaggregated statistics has to be organised. Gender advisor is

    recommended in planning the household survey. Also cooperation with JICAs andMinistry of Womens Affairs Project on Gender Mainstreaming project (Phase 2) is

    recommended. Furthermore, if the Wood Energy Working Group chaired by MIMEbecomes active, collaboration is recommended in all issues relating to wood energy.7

    5.2.2 Supply side data collection and energy import statistics

    Biomass:

    Different options of supply side energy potentials must be evaluated, but the energysupply must be sustainable (cf. fuel wood and rapid deforestation). In order to evaluate

    the use of biomass for energy, also information on the other uses for wood is needed(including industrial use of wood as raw material, timber and wood residue exports).Also data on the regeneration capacity of forest is required. In the evaluation ofbiomass supply side, collaboration with MAFF and MoE is recommended. Due to the

    rapid deforestation, reforestation would be needed but perhaps also plantations for fuelwood. However it should not compromise food production.

    Biofuel potential is also needed to be calculated for the supply side data. Biofuel

    strategy should be established in such manner that biofuel production would notthreaten food production or natural forests. Other potential sources of energy supplyinclude agricultural waste8, wind, solar, and hydro.

    Fossil fuels:

    Cambodia has oil and gas reserves. In the future the crude oil and gas supply statistics

    will be collected by Cambodian National Petroleum Authority (CNPA)CO2 emissionsand climate change mitigation are central issues in fossil fuel sector and should betaken into account in the energy planning.

    At the moment the fuel used in electricity production and in the transport sector isimported. Ministry of Commerce (CAMCONTROL) collects data on fuel imports.

    6MIME, UNDP, GERES (2008): Residential Energy Demand in Rural Cambodia. An empirical study

    for Kampong Speu and Svay Rieng www.un.org.kh/undp ; Turunen, Jenny et al. (2011) Livelihood

    Resilience and Food Security in Cambodia. Results from a Household Survey. FFRC eBooks 1/2011.81 p. ISBN 978-952-249-062-9 http://ffrc.utu.fi/julkaisut/e-julkaisuja/eTutu_2011-1.pdf UNDP research

    covered two provinces, and FFRCs research covered 12 provinces.

    7 Wood Energy Working Group was established in 2006, but has not been active. It is chaired by

    MIME and has 14 members.8

    Significant potential in e.g. in rice husk, see Akgn et al 2011

    http://www.un.org.kh/undphttp://ffrc.utu.fi/julkaisut/e-julkaisuja/eTutu_2011-1.pdfhttp://ffrc.utu.fi/julkaisut/e-julkaisuja/eTutu_2011-1.pdfhttp://www.un.org.kh/undp
  • 8/2/2019 Energy Balance Project Document FINAL

    35/87

    April 2011 - Page 35 / 87 -

    The Table 5 below summarises the recommendations for data collection:

    Sector Data collection Comments

    Agriculture Survey by DIMEs in cooperation with

    Provincial Departments of MAFF

    At the moment energy

    demand data at the

    agricultural sector is not

    collected

    Industry Energy questions (incl. biomass) added to

    MIMEs survey. Studies on the use of wood

    as raw material. Electricity data provided by

    Electricite du Cambodge, Electricity

    Authority of Cambodia and Rural Electricity

    Enterprises

    Questionnaire and sampling

    should be revised if necessary

    Service Survey by MIME and DIMEs Questionnaire and samplingshould be revised if necessary

    Transport Statistics from CAMCONTROL (under