107
Managing Office 2400 College Road 3105 Lakeshore Dr. Suite 106A 4402 Thane Road Fairbanks, Alaska 99709 Anchorage, Alaska 99517 Juneau, Alaska 99801 p. 907.452.5688 p. 907.222.2445 p: 907.586.6813 f. 907.452.5694 f. 907.222.0915 f: 907.586.6819 www.nortechengr.com ENERGY AUDIT – FINAL REPORT North Pole High School 601 NPHS Blvd. North Pole, Alaska Prepared for: Mr. Larry Morris Fairbanks North Star Borough School District July 31, 2012 Acknowledgment: "This material is based upon work supported by the Department of Energy under Award Number DE-EE0000095.”

ENERGY AUDIT – FINAL REPORT - Alaska Energy Efficiency · obtain project-specific quotes or bids from local vendors before ... placing vending machines on ... RS Consulting Energy

  • Upload
    doanque

  • View
    219

  • Download
    2

Embed Size (px)

Citation preview

Managing Office 2400 College Road 3105 Lakeshore Dr. Suite 106A 4402 Thane Road

Fairbanks, Alaska 99709 Anchorage, Alaska 99517 Juneau, Alaska 99801 p. 907.452.5688 p. 907.222.2445 p: 907.586.6813 f. 907.452.5694 f. 907.222.0915 f: 907.586.6819

www.nortechengr.com

ENERGY AUDIT – FINAL REPORT

North Pole High School 601 NPHS Blvd.

North Pole, Alaska

Prepared for:

Mr. Larry Morris Fairbanks North Star Borough School District

July 31, 2012 Acknowledgment: "This material is based upon work supported by the Department of

Energy under Award Number DE-EE0000095.”

ENVIRONMENTAL ENGINEERING, HEALTH & SAFETY

Anchorage: 3105 Lakeshore Dr, Ste 106A, 99503 907.222.2445 Fax: 222.0915 Juneau: 4402 Thane Rd, 99801 907.586.6813 Fax: 586.6819

Fairbanks: 2400 College Rd, 99709 907.452.5688 Fax: 452.5694 [email protected] www.nortechengr.com

F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-100 Doyon Fairbanks Region\50-140 FNSB SD North Pole

High\Reports\Final\North Pole High Cover Letter V1.Docx

As a Technical Service Provider (TSP) to the Alaska Housing Finance Corporation (AHFC) under Task Order 4, NORTECH has completed an Investment Grade Audit (IGA) of North Pole High School in North Pole, Alaska. This work was funded by AHFC through the American Recovery and Reinvestment Act of 2009 (ARRA). Due to the scheduling requirements for completion of the IGAs and to provide a more thorough review of certain mechanical systems, NORTECH sub-contracted RS Consulting for the primary energy audit services for North Pole High School. RS Consulting is owned and operated by Ray Sneeringer, a licensed Mechanical Engineer in the State of Washington and most of the audit field work was completed by Sandra Edwards, a Certified Energy Manager (CEM) and owner of Edwards Energy Environmental and Waste Management. RS Consulting’s IGA methodology generally followed that outlined in the REAL Manual for an IGA. RS Consulting used Trane Trace 700 to model North Pole High School due to the more complex systems found in this facility. This report evaluates a few major EEMs and ECMs, which are generally consistent with NORTECH’s overall findings that FNSB SD facilities are well-maintained and well-operated with few areas for significant potential energy savings. While NORTECH agrees with the recommendations for the EEM/ECM packages, the cost estimates appear to be somewhat lower than expected from local vendors. Since the recommended upgrade(s) involve specific pieces of equipment and installation methods, NORTECH recommends the FNSB SD obtain project-specific quotes or bids from local vendors before approving the specific project. Due to rapid advancements of lighting technologies, project-specific lighting retrofits should be designed no more than six months prior to retrofitting in order to achieve the best technology and maximum savings. NORTECH believes some additional energy and cost savings may be achievable in particular areas of the building. The data necessary to evaluate these upgrades is outside the scope of work of this IGA, but could most likely be collected relatively easily using the mechanical system controls and/or some dataloggers. Specific areas that have the potential for additional energy and cost savings include:

1) Plug load retrofits (ex: replacing old refrigerators, placing vending machines on timers) 2) De-lamping areas of high foot-candles if lighting replacement isn’t performed 3) Domestic hot water generation and use (ex: low flow/automatic fixtures, solar water heating)

While this report differs from the format of other NORTECH reports produced for AHFC and the FNSB SD, NORTECH has reviewed the work of RS Consulting and determined this report is complete and accurately depicts the energy use of the building. Any future questions, comments, or correspondence regarding this report should be addressed to the undersigned. Sincerely, NORTECH

Peter Beardsley, PE, CEA Principal

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 1    

 

ENERGY AUDIT REPORT  

FOR  

ALASKA HOUSING FINANCE CORPORATION 

 

Client:    Alaska Housing Finance Corporation  

  Research and Rural Development Division 

  P.O. Box 101020 

  Anchorage, Alaska  99510 

  Attention:  Ms. Rebekah Lührs  

 

Prepared by:    RS Consulting  

    2400 NW 80th Street, Suite 178 

    Seattle, Washington 98117 

    Telephone:  (206) 368‐1784 

     

    Edwards Energy Environmental & Waste Management 

    PO Box 2110 

    Issaquah, Washington 98027 

    Telephone:  (206) 303‐0121 

 

Principal    Ray W. Sneeringer, PE  

Investigators:    Sandra F. Edwards, CEM, CDSM 

     

Prepared for:    NORTECH 

    Sustainable Environmental Engineering, Health, & Safety 

    2400 College Road 

    Fairbanks, Alaska  99709 

    Telephone:  (907) 452‐5688 

 

 

 

 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 2    

ACKNOWLEDGMENT  

AND  

DISCLAIMER 

 

Acknowledgment: 

We would  like to acknowledge and extend our heartfelt gratitude to the Department of Energy.     This material  is  based  upon  work  supported  by  the  Department  of  Energy  under  Award  Number  DE‐EE0000095.  

Disclaimer: 

This  report  was  prepared  as  an  account  of  work  sponsored  by  an  agency  of  the  United  States Government.  Neither  the  United  States  Government  nor  any  agency  thereof,  nor  any  of  their employees, makes any warranty, express or  implied, or assumes any  legal  liability or responsibility  for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or  represents  that  its use would not  infringe privately owned  rights. Reference herein  to any  specific commercial product, process, or  service by  trade name,  trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government  or  any  agency  thereof.  The  views  and  opinions  of  authors  expressed  herein  do  not necessarily state or reflect those of the United States Government or any agency thereof.  

 

 

 

 

          

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 3    

 

TABLE OF CONTENTS 

1.0   EXECUTIVE SUMMARY ................................................................................................................. 4 

2.0   INTRODUCTION ............................................................................................................................ 6 

3.0   BUILDING DESCRIPTION ............................................................................................................... 8 

4.0   ENVELOPE .................................................................................................................................... 9 

5.0  LIGHTING ................................................................................................................................... 13 

6.0  MECHANICAL ............................................................................................................................. 15 

7.0   ENERGY USE ............................................................................................................................... 18 

8.0   ENERGY MEASURES .................................................................................................................... 19 

9.0   ENERGY MEASURE DESCRIPTIONS .............................................................................................. 21 

10.0  SIMPLE PAYBACK AND SIR .......................................................................................................... 24 

11.0  OPERATIONS AND MAINTENANCE .............................................................................................. 25 

12.0  RECOMMENDATIONS ................................................................................................................. 26 

 

APPENDICES 

APPENDIX A ......................................................................................................  ENERGY UTILIZATION INDEX 

APPENDIX B ........................................................................................................................... COST ESTIMATE 

APPENDIX C ...........................................................................................................  LIGHTING CALCULATIONS 

APPENDIX D .................................................................................................... MECHANICAL CALCULATIONS 

APPENDIX E ..................................................................................................................... SYSTEM DIAGRAMS 

APPENDIX F ............................................................................................................ EQUIPMENT SCHEDULES 

APPENDIX G ........................................................................................................................ TRACE 700 INPUT 

APPENDIX H ..................................................................................................................... TRACE 700 OUTPUT 

APPENDIX I ......................................................................................................... TREND LOG INFORMATION 

APPENDIX J ............................................................................................................................... FLOOR PLANS 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 4    

1.0 EXECUTIVE SUMMARY 

Background 

This energy audit  report was prepared by RS Consulting and Edwards Energy Environmental & Waste Management in conjunction with NORTECH Sustainable Environmental Engineering, Health, & Safety for the Alaska Housing Finance Corporation.     The North Pole High School  is a 156,400 square foot facility located  in North  Pole,  Alaska.    The  building  serves  9th  through  12th  grade  high  school  students  and consists  of  classrooms,  an  auditorium,  a  gymnasium,  administrative  offices,  and  other miscellaneous support functions.   

Scope  

This Level II Energy Audit focused on the building’s envelope, lighting, and HVAC systems and consisted of  an  on‐site  review  of  the  existing  facility,  a  review  of  the  most  current  construction  drawings, identification of potential energy efficiency measures (EEMS), creation of a computer simulation model to examine these EEMs, and a schematic level estimate of the installed costs and relative pay backs for each measure examined.    

The Trane Trace 700 computer program was used to model the existing building’s energy consumption.   The  energy  consumption  values  predicted  by  the  model  were  then  compared  to  actual  energy consumption as shown  in utility bills  from 2009 and 2010.   The computer model was then “tuned” to match the actual energy consumption as closely as possible.   

Energy Use Index 

Two years of utility bills were examined  to determine  the current energy consumption of  the  facility.  The Energy Use  Index  (EUI) for this facility  is 75 kBTU/SF.   The chart below compares the existing and proposed EUI for the building with the EPA Energy Star design target value for a similar building in this location.  This target value was developed using the Energy Star Target Finder software and represents the design criteria for a 50% Energy Star Rated Building, rather than the median value for existing K‐12 Schools. 

 

 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 5    

Energy Consumption 

The majority of the facility’s energy consumption can be attributed to the energy required to heat the outside ventilation air as  it  is  introduced  into the building.     Any effort to conserve energy should start with an examination of the operation of the ventilation system. 

Utility Costs 

The  annual  utility  cost  predicted  by  the  energy  model  for  the  existing  building  is  $327,940.    The estimated utility cost after  implementation of  the  recommended Energy Efficiency Measures  (EEM)  is $307,110 for an annual savings of $20,830.   A breakdown of the current and proposed energy costs  is presented in the following charts: 

 

Recommendations 

We  recommend  implementation  of  a  program  to  ensure  that  the  operable windows  remain  closed during the heating season.  The remaining original windows are failing and should be replaced in order to  improve the performance of the building’s envelope.     An  inspection and monitoring the outside air dampers of each air handling unit should be performed  in order  to  reduce  the amount of outside air being  introduced  into the  facility to current code minimums during cold weather and to eliminate the introduction of outside air into the facility during unoccupied hours. 

We  also  recommend  implementation  of  the  Energy  Efficiency Measures  listed  in  the  table  below.  Implementation of these measures should be accompanied by a more detailed Level  III analysis which should  include operational data  logging, detailed engineering drawings and cost estimates, and a plan for future monitoring and verification of the performance of the installed measure.  

NORTH POLE HIGH SCHOOL ‐ Recommended Measures 

Tag  Measure Description  Cost Payback (Yrs) 

SIR 

EEM‐1  Variable Speed Fans on AHU‐2 and REF‐2    $18,000  7.8  1.8 

EEM‐2  Variable Speed Main Heating Water Pumps    $60,000  3.2  4.4 

Please refer the body of this report for additional information on these Energy Efficiency Measures. 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 6    

2.0 INTRODUCTION 

This energy audit report has been prepared by RS Consulting (RSC) and Edwards Energy Environmental & Waste Management  (EEEWM)  in  conjunction with NORTECH  Sustainable  Environmental  Engineering, Health, & Safety for the Alaska Housing Finance Corporation  (AHFC).     RSC and EEEWM audited North Pole High School in an effort to find cost effective opportunities to reduce building energy consumption.  The Energy Conservation Measures (ECMs) and Energy Efficiency Measures (EEMs) analyzed in‐depth as part of the contract included several mechanical system improvements.  

Two classifications of energy saving measures were examined during this energy audit. The first is a low cost or no cost solution designed to save energy by making changes to occupant activities, schedules, control set points, or small upgrades  to existing equipment.   This  type of measure  is  identified  in  this report as an Energy Conservation Measure (ECM).   The second type of energy saving measure requires significant  capital  investment  to  achieve  energy  savings.  This  is  referred  to  as  an  Energy  Efficiency Measure (EEM). 

This  Level  II Energy Audit  focused on  the building’s envelope,  lighting, and HVAC  systems.   A  level  II energy  audit  includes  a  survey  of  the  building  and  a  breakdown  of  the  energy  end  uses within  the building.  This audit identifies and examines practical ECMs and EEMs to determine the potential energy savings realized  if the measure  is enacted.    It also serves to  identify potential  improvements that may require  the more  thorough  data  collection  and  detailed  engineering  drawings  and  estimates which typically occur in a Level III audit.  The scope of work for this audit consisted of an on‐site review of the existing  facility, a  review of  the most current construction drawings,  identification of potential Energy Conservation  Measures  (ECMs)  and  Energy  Efficiency  Measures  (EEMs),  creation  of  a  computer simulation model  to  examine  these  EEMs,  and  a  schematic  level  estimate  of  the  installed  costs  and relative pay backs for each measure examined.    

The audit team inspected the building during preliminary stages of the energy audit.  The purpose of this field visit was to verify the configuration of the existing mechanical equipment and to assess its condition. Information was also gathered on the size and efficiency of the existing accessible mechanical system motors.   A list of major mechanical equipment used in this facility can be found in Appendix F. 

We also performed a review of the building envelope to identify any potential areas for possible improvement in energy performance and documented the type and number of lighting fixtures used throughout the facility to in order to identify opportunities to improve the performance of the lighting system. 

Two years of utility bills were analyzed to determine the energy performance of the existing building in order to match the existing use with the use predicted by the computer model.   Potential EEMs were identified  and  examined  via  the  computer model or  spreadsheet  calculations.    The predicted  energy savings  of  these measures were  then  compared  to  the  estimated  installation  cost  to  determine  the relative pay back of each measure. 

The Trane Trace 700 computer program was used to model the existing building’s energy consumption.   The energy consumption values predicted by the model were compared to actual energy consumption as  shown  in utility bills  from 2009 and 2010.   The computer model was “tuned”  to match  the actual 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 7    

energy  consumption  as  closely  as  possible.      This  baseline was  used  to  predict  the  energy  savings realized by the proposed EEMs.   The existing building energy use, as predicted by the computer model is shown in Figure 1. 

 

Figure 1:  North Pole High School:  Energy Use by System 

Heating energy comprises 65% (59% plus 6%) of the energy used  in the school.   This  is consistent with the extremely  low  temperatures experienced during  the  subarctic winters  in  Fairbanks.   This heating energy consists of an oil component, which  is  the oil used by  the boilers and  the domestic hot water generators,  and  an  electrical  component,  which  is  the  electricity  used  by  the  boiler’s  ancillary equipment, such as the oil pump, the burner fan and miscellaneous electrical controls.    

The cost of heating oil is significantly less than the cost of electricity per unit of energy ($.018/mbtu vs. $.052/mbtu) so although  the heating system consumes 65% of  the building energy,  it represents only 45% of the total utility bills.  Figure 2 shows the actual cost of the energy consumed by the facility. 

 

Figure 2:  North Pole High School:  Energy Cost by System 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 8    

The  heating  load  consists  of  the  heat  lost  across  the  building  envelope  and  the  heat  used  to warm outside  air  as  it  enters  the  building.    This  outside  air  is  necessary  to  provide make  up  air  for  the building’s exhaust fans and ventilation air for the occupants.   The breakdown of the total heat  load of the school is shown in Figure 3. 

 

Figure 3: North Pole High School:  Building Heating Loads by Component 

It  can be  concluded  from  the preceding  charts,  that efforts  to  conserve energy  in  the  facility  should begin with an examination of the ventilation air system.  Please refer to Section 9.0 of this report for a more detailed discussion of this ventilation system. 

Information  in  this  study has  focused on  the  areas of building  envelope,  lighting,  and HVAC.   Please reference  subsequent  sections of  this audit  report  for detail  information on  the Energy Conservation Measures (ECMs), Energy Efficiency Measures (EEMs), calculation methodologies, and a summary of the findings and recommendations.   

3.0 BUILDING DESCRIPTION 

North Pole High School is a two‐ story 156,362 square foot facility located in North Pole, Alaska.  The 

building serves 9th through 12th grade high school students and consists of classrooms, an auditorium, a 

gymnasium, administrative offices, and other miscellaneous support functions.   This school was 

constructed in 1984 and is 28 years old.  The school is part of the Fairbanks North Star Borough School 

District, located in Fairbanks, Alaska.    The student enrollment for year 2011‐2012 consists of 781 

students and 100 staff.  The energy utility suppliers are Golden Valley Electric (GVEA) and Sourdough 

Fuel.   

 

 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 9    

3.1 Building Construction 

Year Built:  1984 

Area:  156,362 sq. ft. 

Stories:  Two 

Roof:  Flat 

Floor:  Slab on grade  

Walls:  Combination of Stucco, Concrete, Sheetrock 

Windows:  Combination of Double and Triple‐pane  Wood Frame 

Windows 

Doors:  Combination of Wood‐Hollow‐Metal/Glass 

3.2 Building Operation 

Use:  Education 

Operation:  6:00 am – 11:00 pm (cleaning /events until 11:00 pm) 

  Monday – Friday 

  Summer School  (No) 

Occupancy / 

Enrollment: 100  Staff & 781 Students 

 3.3 Existing Energy Efficiency Items  Several energy efficient measures are currently in use in this facility.  These include:   Recent energy efficient lighting upgrade.  Variable speed supply and return fans on the main air‐handling unit (AHU‐1 and REF‐1).  Demand controlled ventilation (DCV) system with return air CO2 monitors  Exhaust air heat recovery on the toilet room, locker room and gym exhaust systems. 

4.0 ENVELOPE 

4.1 General 

The building envelope  is more  than a polished exterior of glass, concrete and  steel. The  components utilized for controlling heat transfer, infiltration, stack effect, solar gain and humidity are vital for a high‐performance building.  Insulated window or door panes whether  it  is  single, double, or  triple and  “R” factors has  an  impact on  the  loads  and  efficiencies of mechanical  and  electrical  systems.   A  cursory 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 10    

review of the existing building envelope and windows was performed to  identify any areas which may benefit from replacement, new weather stripping, caulking and/or seals to prevent infiltration of outside air.  This review included verifying the proper operation and alignment of windows and doors, checking for proper levels of insulation where accessible, and noting if any insulation was found to be damaged.  

The Department of Energy has identified eight (8) climate zones for the United States.  A list of counties and  their respective climate zones can be  found  in American Society of Heating Refrigerating and Air‐Conditioning  Engineers  (ASHRAE)  Advanced  Energy Design Guide,  and  in  the Department  of  Energy, Energy Efficiency and Renewable Energy VOLUME 7.1 Building America Best Practices Series.  North Pole High School is a part of Zone 8 which means it is a part of the subarctic climate.   A subarctic climate is defined as a region with 12,600 heating degree days (65° basis) or more.   For this climate and to achieve over  30%  above  ASHRAE  Standard  90.1‐1999,  R  values  of  between  R13  to  R60  are  recommended depending  on  the  type  and  the  location  of  the  envelope  description.     Window U‐values  of  .33  are recommended to exceed energy savings of 30% above ASHRAE standard 90.1‐1999.   4.2 Windows 

The windows installed at North Pole High School are the original windows that were installed when the school was built  in 1984. These  inefficient windows are twenty‐eight (28) years old and are  in need of replacement.   Many of  the window  levers have been  removed and  some of  the windows have been glued shut (Figures 4.2, 4.3, and 4.5).  These levers were removed because many of the windows were being  left opened.   When the windows are  left open,  it causes the heating system to work harder and waste  heat.    These  opened windows  often  short‐circuits  the  heating  system where  the  thermostat thinks  that  it  needs  to  heat  the  room,  even  though  the  heat  is  going  out  the window.    Should  an emergency arise where the only way to escape  is through a window,  it will be very difficult to exit the school  if  the windows are glued  shut and  the  levers are  removed.   These problems may  result  in an increase in energy consumption, mechanical repairs, equipment replacement, and potential risk of life. 

When  a window breaks  and  a work order  is  submitted,  the window maybe  replaced with double or triple pane glass whatever  is available.   There  is a  combination of  triple‐pane and double‐pane  glass located throughout the school. Figure 4.6  is a typical example of a double and triple pane  installation.  This window is located on the second level near mechanical room 248.  Condensation and air infiltration are caused at the school due to failure of the window seals.  When a teacher accidently leaves a window opened one of the cleaning crew must shut it, and when the cleaning crew performs this task it places them in a precarious position which can be very dangerous because these wood trim windows are tilted outward.   

The window films on these windows have deteriorated with age.  The film is beginning to bubble.  This is 

very visible in several of the classrooms on the first floor (Figure 4.1 and Figure 4.4).   Bubbling film is a 

sign that the adhesive used to apply the tint to the window is failing. After a single bubble appears, 

many more will follow.  The original school was built with windows where the interior part of the 

windows were made of wood and the exterior part of the windows were made of hollow metal frames 

with 5/8” of rabbeted glazing with a thermal break and u‐value of approximately  .50. 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 11    

4.3 Roof 

North Pole High  School Roof was  replaced  in 2009 under Project Number 06‐NPHPRJ‐2,  IFB Number 08054.   The roof  insulation (R‐value) thickness  is approximately R‐40 and  is made of polyisocyanurate.  Polyisocyanurate  is  rigid  foam  that  provides  continuous  thermal  insulation  barriers  for  roofs.    The advantages of using polyisocyanurate  are  the high R‐value  and  the  good  compressive  strength.    The disadvantage  is  the R‐value degrades over  time.      Larger R‐values have greater  thermal  resistance or more insulating potential than smaller R‐values.    

4.4 Walls 

Typical wall insulation at North Pole High School has an R‐value of approximately R‐36.  The wall consists of 7/8“ Stucco, ½” plywood sheathing, 2”  rigid  insulation, 8” batt  insulation, 2”  rigid  insulation, vapor barrier, and 2x8 @24” on center (oc).     

4.5 Doors 

Air leakage was evident around a few of the doors.  There were ice and snow built up around some of the doors.  Typical doors are 3’x7’x1¾” wood and hollow metal with ¼” wire‐glass glazing.  

4.6  Recommendations 

The following items should be implemented to improve the performance and operation of the building’s envelope:    Window repair/replacement  Behavioral changes/education to eliminate open windows during the heating season  Replace worn and/or broken weather‐stripping around doors  

 Implementing  these  potential  opportunities will  have  a  holistic  impact  on mechanical  and  electrical systems through building envelope improvements.  Investments in the building envelope will often add value to the buildings appearance.   

Please refer to Appendix D for calculation of building envelope heat transfer properties. 

 

 

 

 

 

 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 12    

 

Printed below are some of the photos taken during this cursory walkthrough. 

     Figure 4.1 NPHS Damaged Window Film  Figure 4.2 NPHS Broken Levers  

          Figure 4.3 NPHS Outdated  Window  Figure 4.4 NPHS  Damaged Window Film 

 

            Figure 4.5 NPHS Damaged Windows               Figure 4.6 NPHS Double/Triple Pane Window      

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 13    

5.0 LIGHTING 

The most energy efficient lighting systems have already been installed, therefore no additional lighting upgrades are recommended for this facility.  A detail study was conducted under Project # 09‐NPHPRJ‐1, IBF #11034.  This detail study was completed in May 2011. The lighting upgrade retrofit project was implemented during the summer of 2011.  Some of the most energy efficient state of the art lighting installed consisted of T5 fluorescent lamps and LED’s (reference Figures 5.1‐5.7).  Information on this recent lighting upgrade is provided in Appendix C .    Skylights are an excellent way to  light the commons area and some corridors using natural  light.     Natural daylight provides free  lighting and  free heating. Lutron daylight  sensors were  installed during  this lighting upgrade.  These sensors are designed to harvest natural light and  to  maintain  specific  light  levels  in  the  space.    The  sensor automatically dims the lights when the available daylight is high and brightens the lights when the daylight is low.  This sensor can control an  individual  fixture or a group of  fixtures and can be programmed through the daylight sensor’s integrated infrared receiver.  When the sun permits,  the  lighting energy consumption  in  these areas should be greatly reduced.     We commend you on the LED  lighting and the sensors  that were  installed during  this  recent  lighting upgrade. The new  lighting  should  impact  the  district’s  operation  and maintainence(O&M) in a very positve manner.    Printed below are some of  the photos  taken of  the state of  the art energy efficient lighting:                                                                                                                                         Figure 5.1  LED 48‐Watt  

                                                                                                                                    (TMS Lighting)

 

     Figure 5.2 Wall Mounted LED Fixture   Figure 5.3 Pole Mounted LED                (Kim Lighting 120 W‐Wall Pack)                      (Kim Lighting 120 W)            

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 14    

   Figure 5.4 2‐lamp T5 2x4 Fixture Prismatic Lens  Figure 5.5 2x2 Recessed LED Troffer 2‐18.5 LED (H. E. Williams  lamp inside of Fixture)                               (H. E. Williams  2‐18.5 Powerstick Inside of Fix.) 

      Figure 5.6 2‐lamp T5 2x4 Fixture Prismatic Lens  Figure 5.7  2x2 Recessed LED Troffer 2‐18.5 LED  (H. E. Williams Lighting)                                                          (H. E. Williams Lighting 2‐18.5 Powerstick) 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 15    

6.0 MECHANICAL 

6.1 Air Handling Systems 

North  Pole  High  School  is  served  by  several  air handling  units  located  in  second  floor  and penthouse mechanical rooms.   The main classroom area is served by a variable volume air handling unit (AHU‐1).    This  air  handling  unit  consists  of  an outside  air  /return  air  mixing  plenum,  a  glycol heating  coil  and  a  variable  speed plug  type  supply fan.   The associated variable flow return fan (REF‐1) is  equipped  with  a  variable  speed  drive  and  is located in the same fan room.   The return fan draws return air into the fan room and discharges it to the exterior.      Both  AHU‐1  and  REF‐1  were  originally provided with  inlet vanes, which open and close  in response  to  system  demand  to  vary  the  flow  of  air from  the  constant  speed  supply  fan.    These  inlet  vanes  have  been  locked  in  the  open  position  and replaced with variable speed drives.  Variable speed drives vary the speed of the fan to provide variable airflow to the building and consume  less energy than the original  inlet vanes.   Please refer to Drawing M1.2 in Appendix E for a diagram of this system. 

The Music Area  is served by AHU‐2 and REF‐2.     These are similar to the units described above (AHU‐1 and REF‐1), except the original inlet vanes are still  in operation.   Both AHU‐1 and AHU‐2 provide air to individual terminal units at each classroom or temperature control zone.  The terminal units do not have heating coils and heating is provided by hot water finned tube units on the perimeter and supplemented 

by warm air delivered by the main air handling unit.    

The  auditorium,  gymnasium,  and  locker  rooms  are served by  individual air handling units  (AHU‐3, AHU‐4, and AHU‐5).  These AHUs have an outside air /return air mixing plenum, a glycol heating  coil and a  two  speed, two  motor  supply  fan.      The  supply  fan  switches between high  speed and  low  speed depending on  the load  in  the space.   At  low speed,  the smaller,  low rpm motor  runs  and  at  high  speed,  the  larger  high  rpm motor runs.   Please refer to Drawing M1.3  in Appendix E for a diagram of this system. 

There  are  also  several  heat  recovery  loops  utilized  in the building.   Each  loop  is a  run‐around heat  recovery  loop which uses a glycol mixture and pump  to transfer heat from the exhaust air stream to the incoming outside air.   Heat is recovered from the toilet room, locker room and shop exhaust systems.  Refer to drawing M1.4 in Appendix E for a diagram of this system. 

Figure 6.2 – Typical Air Handling Unit

Figure 6.1 – Inlet Vanes on REF‐1 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 16    

6.2 Heating Systems 

Three Weil McLain oil fired cast iron sectional boilers provide heat for the facility.  These boiler and their associated pumps are  located  in a ground  floor mechanical  room.     The boilers are piped  in a  series configuration.   This means the output of the first boiler  is mixed with the system flow before  it enters the second boiler, and the output of the second is mixed with the system flow prior to entering the third boiler.   Each boiler raises the temperature of the system flow approximately 14 degrees F.   

A constant volume pump distributes heating water  to various mechanical rooms.   At each mechanical room, this water is utilized in one of three ways: 

1) Passed through a glycol to hot water heat exchanger via a manual balancing valve to generate hot glycol for use in the outside air preheat coils. 

2) Mixed with return water and distributed to hot water coils in the AHUs via individual coil pumps and three‐way valves. 

3) Pumped  to  fin  tube perimeter heating units via a single pipe “mono‐flo” system  through  two‐way valves. 

 Please refer to Diagram M1.1 in Appendix E for additional information on the heating water distribution system.  

 

 

 Figure 6.3 ‐ Heating Water Boilers Piped in Series 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 17    

6.3 Control Systems 

The majority  of  the mechanical  systems  are  controlled  by  a  Johnson  Controls Metasys  direct  digital control  (DDC) system.   This system was substantially upgraded  in 2000.       The DDC system starts and stops  the mechanical  equipment,  controls  space  temperature  and maintains  the  proper  amount  of outside  air  flow  to  accommodate  the  occupant  load  at  any  given  time.    Outside  air  control  is accomplished with the use of CO2 monitoring.   The level of CO2 in the sampled air is an indicator of the number of occupants in the building.  The DDC system adjusts the outside air dampers to maintain the CO2  levels at  the set point value.       The control of ventilation air based on actual space occupancy  is known as Demand Controlled Ventilation (DCV) and can be a very effective way to conserve energy by reducing the amount of outside air introduced into the building.  

6.4 Domestic Hot Water 

Domestic hot water  is generated by  three oil  fired hot water heaters with combination storage tanks. These are located in the Boiler Room.   

6.5 Mechanical System Trend Logs 

With the assistance of FNSB personnel, the operating parameters of a single air handling unit and the heating water system were monitored and recorded over a period of several days.  This period included weekday and weekend operation.  The intent of monitoring a select group of points was to determine if the  operation  of  the mechanical  systems was  consistent with  the  assumed  schedules  and  operating parameters used  in the computer simulation model, and to  identify any potential energy saving  items that may be  candidates  for more  in depth monitoring  and  analysis  in  the  future.  This data  (typically referred  to as a  trend  log) was  taken  for AHU‐1, which serves  the main classroom and administrative areas.   Observations  for AHU‐1 may  or may  not  apply  to  the  other  units  that were  not monitored.  Certain sections of the trend data were graphed to  illuminate  items of  interest that were noted  in our review  of  the  data  collected.    The  data  points  that were monitored  during  this  study were  a  small selection of  the  total number of points  available  for monitoring  in  the  future.          Since only  a  small selection  of  points  were  monitored  it  should  be  noted  that  while  we  were  able  to  calculate  the percentage  of  outside  air  from  the  trend  logs, we were  not  able  to  determine  the  total  amount  of outside air because  the  total  fan airflow  is not known.   AHU‐1  is a variable air volume system, so  the total airflow of the system will vary in response to the opening and closing of the terminal units serving individual zones. 

 The following observations are from our analysis of the trend logs: 

The supply fan started at 6:00 am and the outside air percentage at this point is around 12%  At  10:00  am  the  outside  air  percentage  jumped  to  35%,  indicating  that  the  DCV  control  is 

responding correctly to a buildup of CO2 from the occupants.  At 3:00 pm the outside air damper closed  The supply fan continued to run since the outside air temperature was below minus 20.  The outside air dampers did not  close  fully during  this  time and approximately 6% of  the air 

introduced into the building was outside air.    

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 18    

In addition, the operation of the boiler plant was monitored for the same time period.   Analysis of the boiler plant trend logs shows that the load on the boiler plant peaks when the outside air dampers are opened, as expected, but the  load during the unoccupied hours (when the outside air dampers should be closed) is still fairly substantial.     Control  of  the  boiler  leaving  water  temperature  is  not  stable  and  this  is  causing  the  system temperatures to hunt.   During one four hour period on Jan 14th, all boilers were enabled, yet the system temperature difference varied from between 7 degrees and 17 degrees several times.  Typical variations would be expected to be  in the range of 3‐5 degrees for this type of operating scenario.       Fluctuating leaving water  temperature will  cause  the  heating water  valves  located  at  the  air  handling  units  to become unstable and may lead to excessive energy consumption.    Based on our review of trend logs for AHU‐1 and the boiler system, we have the following recommendations: 

Visually inspect the outside air dampers at each air handler to ensure that they are fully closed during unoccupied hours. 

Inspect the control system and sequences related to the heating water supply temperature control to determine if the control loop can be tuned to reduce the variations in supply water temperature. 

 A graphical representation of the operation of AHU‐1 and the boiler plant is included in Appendix I.  

7.0 ENERGY USE 

The purpose of this energy audit is to identify measures or practices that will result in a reduction in the energy use of the facility.  Fuel oil is used for building heating and domestic hot water generation, while electricity is used by fans, pumps, lights, and miscellaneous plug loads.    

A reduction in oil use can be achieved by one or more of the following actions:   

Reduce the amount of ventilation air being introduced into the building 

Reduce the amount of heat lost through the envelope of the building. 

Recover heat before it is exhausted from the building. 

Improve the efficiency of the oil burning equipment. 

A reduction in electrical consumption can be achieved in one or more of the following manners:   

Improve the efficiency of the lighting systems. 

Vary the speed of fans and pumps in response to the building loads. 

Improve the efficiency of the motors. 

Turn off systems when they are not required. 

Two  years  of  utility  bills were  analyzed  to  determine  the  energy  consumption  characteristics  of  the facility.   These numbers were then normalized to account for any unusual weather conditions that may 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 19    

have occurred during  the  span of  the  two years.   For example,  if  the winter of 2010 was abnormally warm, the yearly energy consumption would be  less than that of a typical year.   The number of actual heating  degree  days  (HDD)  for  each month  during  the  two  year  time  period was  compared  to  the historical average heating degree days for that month, and the oil consumption use was adjusted based on this ratio.  These adjusted energy consumption values were then used to calculate an overall building energy use  index.   The calculated Energy Utilization Index (EUI) for this facility  is 75 kBTU/SF.   The EUI calculation is included  in Appendix A.  Figure 7.1 shows a comparison of the existing and proposed EUI with both the average EUI found in the building operated by the Fairbanks North Star Borough and the Environmental Protection Agency’s Energy Star rating for a median building of a similar type.  This target value was developed using the Energy Star Target Finder software and represents the design criteria for a 50% Energy Star Rated Building, rather than the median value for existing K‐12 Schools. 

 

Figure 7.1 – Building Energy Utilization Index 

8.0 ENERGY MEASURES  

8.1 Types of Energy Savings Measures 

Potential energy saving measures (ECMs and EEMs) were identified for the facility based upon an on‐site 

inspection, a review of utility records, computer modeling and  interviews with  facility personnel.   The 

purpose of identifying these energy measures is to reduce energy consumption, and  lower operational 

costs.    

Each measure was  analyzed  either by  utilizing  a  spreadsheet  calculation or  by  employing  the  TRACE energy‐modeling  program.      A  rolling  baseline  modeling  system  is  employed  during  the  modeling process.  This system analyzes each alternative based on the results of the previous alternative.  The first alternatives analyzed are the ones thought to be most  likely to result  in a short payback period.     The rolling baseline  system  is used  to prevent double  accounting of energy  savings.    For example,  if one 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 20    

alternative improves the building envelope and the following alternative increases the efficiency of the heating system, the second alternative must take into account the decreased heating load provided by improving the envelope  in the first alternative.    If this reduced heating  load  is not taken  into account, the  second alternative would  show additional heating energy  savings  that would not be  realized  in a building with an improved envelope. 

The following measures were analyzed for this facility: 

8.1.1  Energy Conservation Measures: 

ECM A – Ventilation System Optimization 

ECM B – Replacement of Existing Motors with More Efficient Motors 

8.1.2  Energy Efficiency Measures: 

EEM 1 – Replace Inlet Vanes with Variable Speed Drive on AHU‐2 

EEM 2 – Variable Speed Pumping 

A more thorough discussion of each ECM/EEM can be found in Section 9.0. 

8.2 Computer Modeling 

The TRACE building modeling system examined three alternatives: 

8.2.1  Trace Model Alternative One:  Baseline Building 

This alternative models the existing facility using information from the most current as built drawings, as well as information gathered during our field visits.    The existing wall and roof u‐values were calculated and input into the model.   The existing lighting densities, HVAC system types, airflows and operational schedules were used.  The energy use predicted by the baseline model was then compared to the actual utility bills (normalized to reflect an average year) to determine  if the model was accurately describing the operation of the existing facility.   The model was then “tuned” to follow the existing building energy consumption as closely as possible. 

8.2.2  Trace Model Alternative Two: Replace Inlet Vanes with Variable Speed Drives 

This alternative examines EEM‐1,  locking  the existing modulating  inlet vanes  in  the open position and adding variable  speed drives  to control  the  speed of  the existing variable air volume  fans  serving  the Music and Drama Departments (AHU‐2).   

8.2.3  Trace Model Alternative Three:  Variable Speed Pumping 

This  alternative  includes  all  the  energy upgrades proposed  in Alternative  Two,  and  examines  EEM‐2, variable speed pumping for the main heating water distribution pumps. 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 21    

The TRACE 700 computer model input and output data is included in Appendix G and H respectively. 

8.3 Energy Costs 

The following energy costs were used in this analysis: 

Fuel Oil = $3.40/Gallon Electricity Consumption = $.156 per Kwh Electrical Demand = $10.79 Kw Blended Electrical Rate = $.177 per Kwh 

9.0 ENERGY MEASURE DESCRIPTIONS 

9.1 ECM A – Ventilation Air Reduction 

Heating of  the outside ventilation air  is  the primary source of energy use  for  the  facility.   Any actions taken to reduce the amount of ventilation air introduced into the building will save a significant amount of energy.   

A certain amount of fresh air  is required  in order to provide adequate  indoor air quality, but excessive amounts of outdoor air  lead to  increased energy consumption.     This delicate balance between  indoor air quality and energy consumption  is perhaps  the most  important aspect of any energy conservation project.    

The  2009  International Mechanical  Code  stipulates  the minimum  outside  air  requirements  for  any facility.  These requirements include a people component and an area component.  For each particular use,  the code specifies a cubic  foot per minute of outside air per each occupant  (cfm/person) and an amount of outside air required based on the square footage of the space (cfm/square foot).  Codes that were  in place during  the design of  this  facility  typically only  included a people component.   The 2009 IMC  reduces many of  the  cfm/person  requirements  from  the original  codes  in place during  the  time construction of this facility.  However, some of the requirements for classrooms have actually increased.  Depending  on  the  balance  of  classroom  to  other  uses,  implementation  of  the  new  code may  either increase or decrease the total required amount of outside air for a particular facility.   An excerpt from the current code is listed below: 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 22    

 

Minimum Ventilation Rates ‐ Schools 

Use 

2009 IMC  Previous 

Cfm  Cfm  People Net Cfm  Code 

Person Sq Ft 1000 Sq 

Ft  Person  Cfm/Per 

Classroom (Age 5‐8)  10 0.12 25 14.8  15 

Classroom (Age 9+)  10 0.12 35 13.4  15 

Science Room  10 0.18 25 17.2  15 

Art Classroom  10 0.18 20 19.0  15 

Lecture Classroom  7.5 0.06 65 8.4  15 

Lecture Hall (Fixed Seats)  7.5 0.06 150 7.9  15 

Computer Lab  10 0.12 25 14.8  20 

Shops  10 0.18 20 19.0  20 

Music/Theater/Dance  10 0.06 35 11.7  20 

Multi‐Use/Assembly  7.5 0.06 100 8.1  20 

Office  5 0.06 5 17.0  20 

If the air handling system provides ventilation air to multiple zones, then several additional calculations must be performed to determine the fraction of outdoor required at the air handler.  These calculations provide  correction  factors  for  over  ventilated  zones,  air  distribution  effectiveness  and  system efficiencies.     A calculation of the overall percentage of outside air required at each air handler can be found in Appendix D. 

North Pole High School utilizes CO2 sensors  in  the return air ducts  to monitor  the ambient CO2  level.  The control system modulates the amount of outside air introduced in the building in proportion to the number of people in the space at any given time.  This is known as demand controlled ventilation (DCV) and  is the best method to balance the need  for adequate  indoor air quality with the desire to reduce energy consumption.    

Demand Controlled Ventilation  (DCV)  is  a method of  adjusting  the  amount of outside  ventilation  air introduced  in  to  the building based on  the number of occupants  at  any  given  time.    The number of occupants can be determined indirectly by measuring the concentration of carbon dioxide (CO2) in the air.  Each person produces CO2 at a fairly constant rate, therefore the concentration of CO2 in the return air system can be used as an indication of the number of people occupying the space.   

Measuring the return air CO2 is a relatively inexpensive method of DCV since it requires only one sensor and minimal control wiring.   However, this method provides an average reading of all the spaces served by the system.  If one space is fully occupied and the other is empty the average value read in the return air stream will not be indicative of what is actually happening on a room by room level and some zones may be over ventilated, while others are under ventilated.   

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 23    

The control system monitors the CO2  level  in the return air stream and opens the outside air damper when  this  level exceeds a certain set point.     This set point  is based on a calculation of  the minimum amount  of  outside  air  required  by  code.      The  calculation  of  the maximum  allowable  CO2  level  is provided in Appendix D.  This CO2 set point should be compared to the current set point and adjusted, if possible, to reduce the amount of outside air required.  

The facility’s air handling units are scheduled to run during unoccupied hours any time the outside air temperature drops below minus 20 degrees F.   The temperature in Fairbanks is below minus 20 degrees between the hours of 5 PM and 8 AM  (unoccupied hours) for approximately 550 hours per year.   The control  systems  are  set  up  to  allow  a  small  percentage  (approximately  5%)  of  outside  air  into  the building during these times in order to keep the building pressurized and prevent any infiltration of cold air.  This outside air used for pressurization must be heated prior to entering the building.  The heating of this outside air represents an annual energy cost of approximately $2 per cubic foot per minute (cfm) of outside air.   For example, if AHU‐1 is bringing in 3000 cfm (5%) of outside air, this would result in an annual energy cost of $6,000. 

Although  this  pressurization  of  the  building may  be  required  to  prevent  freeze  up  and maintenance issues when  the outside air  temperatures drop below minus 20 degrees,  it does  require a substantial amount of energy to heat the outside air used to pressurize the building.   We recommend revisiting this practice  to determine  if  the buildings  can be operated with  little or no outside air  (neutral pressure) during this time in order to reduce the overall building energy consumption. 

We also recommend a visual  inspection of all the outside air dampers  in the facility to verify that they are closing properly during unoccupied hours.  Also, the seals on these dampers should be inspected to verify that the damper is not leaking when it is closed. 

9.2 ECM B – Energy Efficient Motors 

The pay back derived from replacing existing electric motors with premium efficiency motors depends on  the horsepower,  the existing motor efficiency,  the hours of operation,  the  type of system and  the location  of  the  existing motor.    Larger motors  tend  to  provide  lower  pay  back  periods.    The  tables included  in Appendix D provide  information on the typical motors used  in this facility and  indicate the existing motor efficiency at which the payback period becomes feasible.   For example, if an existing 10 horsepower motor used  in a perimeter heating  loop has an efficiency  less  than 87.5%,  then  replacing the motor with a premium efficiency model will provide a payback of approximately 5 years.   Motors used  in  variable  speed  systems will  have  a  longer  payback  than  indicated  in  the  charts  because  the motor is not operating at full design horsepower for the number of hours indicated.  Additionally motors located  in  the  airstream  of  fan  systems  will  also  have  a  slightly  longer  payback,  because  the  heat produced by the inefficiency of the motor is used in a beneficial way during the heating season.  Please refer  to  the  tables  to determine  the  feasibility of replacing other motors used  throughout  the  facility.    Since many of the motor nameplates are obstructed or could not be found, a simple payback calculation for each motor  is not  feasible.   However, as maintenance personnel are working  in  this building,  this chart can be used to determine if the motors should be replaced or re‐used.  

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 24    

9.3 EEM 1‐ Add Variable Speed Drives to AHU‐2 and REF‐2 

The original design of the variable air volume fans included using modulating vanes on the inlet of each fan to vary the amount of air produced by the fans by changing the angle of air as it hit the fans blades.  The fans run at full speed but total horsepower required decreases as  the motor unloads.  This technique saves energy but is not as efficient as simply slowing down the speed of the fan blade by using variable speed drives.   This EEM includes the following:    Remove inlet vane controller and lock inlet vanes in the open position on AHU‐2 and REF‐2.  Provide new variable speed drives for each fan motor.  Extend the existing DDC control system to incorporate these new points. 

 9.4 EEM 2 ‐ Add Variable Speed Drives to the Main Heating Water Distribution Pumps 

The main heating water distribution system serves several different heating water systems throughout the building.  One of which is the heat exchangers that serve the glycol heating water distribution systems.   Manual balancing valves currently control the main system heating water flow that passes through these heat exchangers.  This results in a constant flow of heating water through the system even if there is not a demand for heating.   This alternative includes the following work:   Replace the manual balancing valves on the 

water to glycol heat exchangers with electric 2‐ Way control valves. 

Replace 3‐Way valves on coil pumps with 2‐Way Valves for AHU‐1, AHU‐2, AHU‐3 and AHU‐4. 

Provide new variable speed drives for each pump motor. 

Extend the existing DDC control system to incorporate control of the drives based on system pressure. 

 This measure will reduce the system pumping energy by varying the heating water flow in response to the actual building heating loads.   Refer to Drawing M.1A in  Appendix E for a diagram of the proposed changes.    

10.0 SIMPLE PAYBACK AND SIR 

The total energy saved by employing Energy Conservations Measures ECM‐A, Ventilation Air Reduction and ECM‐B, Energy Efficient Motors, could not be calculated.  Calculation of the total energy saved from implementing  ECM‐A  requires  detailed  data monitoring  and  analysis  of  each  individual  air  handling system  in order  to determine  the existing energy  consumption of each unit.   Calculation of  the  total energy saved by employing ECM B could not be performed since many of the motor nameplates were inaccessible or missing during our walkthrough.  This level of detailed analysis is beyond the scope of a Level II audit and is typically performed during a Level III Audit.  Therefore, simple payback and Savings 

Figure 9.1 – Typical Coil Pump and 

3‐Way Valve 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 25    

to  Investment  Ratio  (SIR)  calculations  are  not  presented  for  the  recommended  Energy  Conservation Measures (ECMs).   

The simple payback and SIR were calculated for each of the Energy Efficiency Measures (EEMs) studied in  this  report.     The estimated  installed cost  for each proposed energy efficiency measure  (EEM) was compared to the estimated energy savings to provide a relative comparison of each measure.    

The  simple payback  calculation  is a quick method of  comparing various EEMs but does not  take  into account the time value of money or the costs or savings beyond the first cost.   

The savings‐to‐investment ratio (SIR) is the ratio of the present value savings to the present value costs of an energy conservation measure. The numerator of  the  ratio  is  the present value of net savings  in energy plus or minus any additional maintenance costs related to the measure.   The denominator of the ratio is the present value of the installation cost of the measure.   

The following formulas were used in the calculation of each ratio: 

Simple Payback = Cost of Energy Saved/Cost of Installation of EEM 

 SIR = Present Value of Energy Saved for the Life of the Measure/Present Value of the Installed Cost 

NORTH POLE HIGH SCHOOL ‐ EEM SUMMARY 

Measure Number 

Measure Description 

Annual Energy and Cost Savings  Payback Calculations 

Peak Demand Savings 

Electricity Usage Savings 

Oil Usage Savings 

Annual Cost 

Savings 

Measure Cost 

Simple Payback 

Savings to 

Invest Ratio 

Kw  Kwh  Therms  $  $  Yrs    

EEM 1  Variable Speed Fans   3  14,548  0  $2,302  $18,000  7.8  1.8 

EEM 2  Variable Speed Pumps  11  118,038  0  $18,533  $60,000  3.2  4.4 

11.0 OPERATIONS AND MAINTENANCE 

A  successful operations  and maintenance plan  is  the  key  to  continued  energy  savings  in  any  facility.  According  to  the American Society of Heating and Refrigeration Engineers  (ASHRAE) 2007 Handbook, the original design and installation of a mechanical system constitutes only around 10% of the total life cycle cost, while operation and maintenance costs represent approximately 80% of the total cost over the life of the system.   The remaining 10% of the life cycle cost is attributed to acquisition, renewal and disposal.  

When a mechanical system  is  installed,  it should be commissioned to ensure that the operation of the system meets the design intent.  Over the life of this system, its operation should be verified via control system  trending  and/or  field measurements.    If  the  system  is  found  to  be  operating  outside  of  the original design intent, corrective action or retro commissioning should be initiated. 

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 26    

A  quality  preventative maintenance  plan  can  extend  the  life  of  the mechanical  system  beyond  the estimated  service  life of  the equipment and  free up  capital  funds  for other projects.    Frequent  filter changes can result  in significant energy savings over the  life of the building.   The pressure drop across the filter increases as it captures dirt and dust.   This increased pressure drop results in additional energy consumption, a decrease  in airflow, or both.   For a  typical 20,000 cfm  fan system a 1” static pressure increase will result in an increased annual energy cost of $2000. 

The level of maintenance at the North Pole High School appears to be excellent.  The level of quality of the  installed Pace custom air handlers  is very high, and  there were no visible signs of wear or of any maintenance problems.   The mechanical spaces are clean and well kept and the filters appear to have been changed frequently.   

12.0 RECOMMENDATIONS 

The lighting systems at North Pole High School have been recently upgraded, therefore, no additional lighting measures are recommended for this facility.   The current windows are 28 years old and are beginning to fail.  Several have been replaced with more energy efficient windows as they have failed and several have had only the glass contents replaced.  We recommend replacing the remaining original windows to decrease the infiltration of cold air and to improve the thermal performance of the building envelope.  We also recommend implementation of an education and monitoring program to ensure that the windows remain closed during the heating season.    In addition, we recommend further analysis of the following Energy Conservation Measures:   ECM A     Ventilation Air Reductions 

Verify that the maximum CO2 set points used in the Demand Controlled Ventilation (DCV) control scheme are in agreement with current codes.  It is possible that some of the set points may be increased, which will reduce the amount of outside air needed. 

Revisit the practice of pressurizing the building in cold weather during unoccupied hours.  This practice may be required to prevent freeze up or damage, but any reduction in the amount of pressurization required will result in substantial energy savings.     

Inspect and repair all outside air dampers that may be leaking or not closing properly to prevent introduction of un‐wanted outside air during unoccupied hours.   

 The majority of the facility energy use can be attributed to the heating of the outside air as it is introduced into the building.  Therefore, anything that can be done to reduce this outside airflow will have the greatest impact on the overall energy consumption of the facility.  

RS Consulting    Energy Audit – Final Report Edwards Energy Engineering &    North Pole High School Waste Management    North Pole, Alaska       

 July 30, 2012    Page 27    

  ECM B    Replace Low Efficiency Motors  Where Applicable 

Replace motors that do not meet the minimum efficiency criteria as listed in the Table provided in Appendix D. 

 We recommend implementation of the following Energy Efficiency Measures:   EEM 1    Add Variable Speed Drives to AHU‐2 and REF‐2 

The variable volume fans serving AHU‐2 and REF‐2 are currently controlled by inefficient inlet vanes.   Replacing these inlet vanes with variable speed drives will reduce the overall fan energy consumption.    

EEM 2    Variable Speed Pumping on the Main Heating System Electrical energy consumption will be reduced significantly by converting the existing constant volume heating water pumps located in the main boiler room to variable volume pumps.   

APPENDIX A – ENERGY UTILIZATION INDEX

Building Square Footage 156,362

Estimated Estimated Estimated Actual Average Total

Delivered Monthly Monthly Monthly Base 60 Base 60 Cost Per Cost per Energy Use

Date Gallons kbtu Cost Cost/Mbtu Cost/Gal Use (Gal) kbtu-Oil Cost HDD HDD KWH kbtu-Elec Cost KWH kbtu kbtu

Jan-09 11,166 1,506,852 19,098$ 0.013$ 1.710$ 8,010 1,080,979 18,092$ 2182 2236 171,000 583,452 24,146$ 0.141$ 0.041$ 1,664,431

Feb-09 5,690 767,866 10,447$ 0.014$ 1.836$ 6,182 834,266 13,963$ 1684 1709 154,800 528,178 16,114$ 0.104$ 0.031$ 1,362,443

Mar-09 4,631 624,953 7,920$ 0.013$ 1.710$ 6,035 814,449 13,631$ 1644 1652 147,600 503,611 15,863$ 0.107$ 0.031$ 1,318,061

Apr-09 0 0 -$ - - 3,117 420,601 7,039$ 849 775 153,900 525,107 15,896$ 0.103$ 0.030$ 945,708

May-09 0 0 -$ - - 1,072 144,659 2,421$ 292 287 119,700 408,416 16,538$ 0.138$ 0.040$ 553,075

Jun-09 0 0 -$ - - 308 41,614 696$ 84 93 89,100 304,009 12,487$ 0.140$ 0.041$ 345,623

Jul-09 406 54,790 844$ 0.015$ 2.079$ 110 14,862 249$ 30 59 91,800 313,222 12,750$ 0.139$ 0.041$ 328,084

Aug-09 0 0 8,420$ - - 753 101,558 1,700$ 205 166 113,400 386,921 18,661$ 0.165$ 0.048$ 488,479

Sep-09 0 0 -$ - - 1,428 192,713 3,225$ 389 398 139,500 475,974 21,791$ 0.156$ 0.046$ 668,687

Oct-09 8,088 1,091,476 18,408$ 0.017$ 2.276$ 3,396 458,252 7,669$ 925 1076 153,000 522,036 23,574$ 0.154$ 0.045$ 980,288

Nov-09 7,811 1,054,094 19,184$ 0.018$ 2.456$ 6,645 896,687 15,007$ 1810 1716 150,300 512,824 25,856$ 0.172$ 0.050$ 1,409,511

Dec-09 6,389 862,196 15,465$ 0.018$ 2.421$ 7,125 961,585 16,094$ 1941 2064 139,500 475,974 24,960$ 0.179$ 0.052$ 1,437,559

Jan-10 9,239 1,246,803 22,694$ 0.018$ 2.456$ 8,735 1,178,781 23,123$ 2292 2236 166,500 568,098 28,686$ 0.172$ 0.050$ 1,746,879

Feb-10 4,151 560,177 10,047$ 0.018$ 2.420$ 6,098 822,883 16,141$ 1600 1709 153,900 525,107 26,750$ 0.174$ 0.051$ 1,347,990

Mar-10 4,583 618,476 13,479$ 0.022$ 2.941$ 5,663 764,253 14,991$ 1486 1652 149,400 509,753 26,687$ 0.179$ 0.052$ 1,274,006

Apr-10 0 0 -$ - - 2,249 303,438 5,952$ 590 775 153,000 522,036 26,202$ 0.171$ 0.050$ 825,474

May-10 0 0 -$ - - 953 128,576 2,522$ 250 287 109,800 374,638 20,081$ 0.183$ 0.054$ 503,213

Jun-10 6,324 853,424 16,101$ 0.019$ 2.546$ 354 47,830 938$ 93 93 56,700 193,460 11,323$ 0.200$ 0.059$ 241,291

Jul-10 6,000 809,700 15,906$ 0.020$ 2.651$ 217 29,315 575$ 57 59 67,500 230,310 12,806$ 0.190$ 0.056$ 259,625

Aug-10 1,726 232,924 4,662$ 0.020$ 2.701$ 442 59,659 1,170$ 116 166 109,800 374,638 19,495$ 0.178$ 0.052$ 434,297

Sep-10 0 0 -$ - - 1,620 218,578 4,288$ 425 398 142,200 485,186 23,663$ 0.166$ 0.049$ 703,765

Oct-10 4,731 638,448 13,157$ 0.021$ 2.781$ 3,849 519,445 10,189$ 1010 1076 149,400 509,753 25,180$ 0.169$ 0.049$ 1,029,198

Nov-10 4,515 609,299 12,632$ 0.021$ 2.798$ 5,366 724,137 14,204$ 1408 1716 151,200 515,894 25,280$ 0.167$ 0.049$ 1,240,032

Dec-10 3,469 468,142 9,750$ 0.021$ 2.811$ 9,192 1,240,497 24,333$ 2412 2064 139,500 475,974 23,324$ 0.167$ 0.049$ 1,716,471

Heating Deg DaysFuel Oil Use Electrical Use

North Pole High School Energy Use Index

Dec-10 3,469 468,142 9,750$ 0.021$ 2.811$ 9,192 1,240,497 24,333$ 2412 2064 139,500 475,974 23,324$ 0.167$ 0.049$ 1,716,471

Avg Cost

2009 44,181 5,962,226 99,786$ 0.015$ 2.259$ 44,181 5,962,226 99,786$ 12,035 12,231 1,623,600 5,539,723 228,636$ Avg Cost Avg Cost 11,501,949

2010 44,738 6,037,393 118,428$ 0.022$ 2.647$ 44,738 6,037,393 118,428$ 11,739 12,231 1,548,900 5,284,847 269,477$ Per KWH Per Mbtu 11,322,240

Averages 44,460 5,999,810 109,107$ 0.019$ 2.453$ 44,460 5,999,810 109,107$ 11,887 12,231 1,586,250 5,412,285 249,057$ 0.166$ 0.049$ 22,824,189

Energy Adjusted

Energy Use( MBH) Oil Elect Total BTU/SF For HDD

Oil Electric Total

2009 5,962,226 5,539,723 11,501,949 73,560 74,758 Average Annual Utility Costs 109,107$ 249,057$ 358,164$

2010 6,037,393 5,284,847 11,322,240 72,410 75,445 Utility Costs per Square Foot 0.70$ 1.59$ 2.29$

Average 75,100

North Pole High School Energy Use Index

0

50,000

100,000

150,000

200,000

Monthly Electrical Consumption (KWh)

0

500,000

1,000,000

1,500,000

2,000,000

Total Monthly Energy Consumption (kBtu)

0

2,000

4,000

6,000

8,000

10,000

Jan

-09

Mar

-09

May

-09

Jul-

09

Sep

-09

No

v-0

9

Jan

-10

Mar

-10

May

-10

Jul-

10

Sep

-10

No

v-1

0

Estimated Monthly Oil Consumption (Gal)

0

2,000

4,000

6,000

8,000

10,000

12,000

Oil Deliveries (Gallons)

0 0

Jan

-09

Mar

-09

May

-09

Jul-

09

Sep

-09

No

v-0

9

Jan

-10

Mar

-10

May

-10

Jul-

10

Sep

-10

No

v-1

0

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

Building Energy Consumption Oil and Electricty (kBtu)

kbtu-Oil

kbtu-Elec

APPENDIX B – COST ESTIMATE

RS Consulting Opinion of Probable Cost

Job: North Pole High School Date: 2-May-12

Job #: Status of Design: Energy Audit Est: RWS

QTY UNIT MATERIAL LABOR ENGINEERING ESTDESCRIPTION UNIT TOTAL UNIT TOTAL UNIT TOTAL

EEM Provide Variable Speed Drives for AHU-2 and REF-2

Remove Existing Vane Acuators 2 EA 450 900 450 $900Provide VSD for AHU-2 (15 Hp)* 1 EA 1546 1546 450 450 1996 $1,996Provide VSD for REF-2 (3 Hp)* 1 EA 1050 1050 450 450 1500 $1,500Electrical Wiring 1 EA 425 425 3000 3000 3425 $3,425Modify DDC Control Signal 1 EA 250 250 1200 1200 1450 $1,450Control Wiring and Conduit 1 EA 150 150 800 800 950 $950Controls Programming and Test 1 EA 1250 1250 1250 $1,250

* Reuse Exisitng Motor Subtotal $11,471

General Conditions 25% $2,868 $14,339Construction Contingency 15% $2,151 $16,490

Design 12% $1,979 $18,468

Total for EEM $18,468

Round to $18,000

EEM Variable Speed Pumps

Remove Exist Bal Valves @ HX 3 EA 400 1200 400 $1,200Remove Exist 3-Way Vlv @ Coils 3 EA 500 1500 500 $1,500Add Heating Water Temp Sensor 3 EA 425 1275 200 600 625 $1,875Add 2 Way Control Valves at HX 3 EA 1500 4500 450 1350 1950 $5,850Add 2 Way Cntrl Valve at Coils 3 EA 1500 4500 450 1350 1950 $5,850Add Variable Speed Drives (15 HP)* 2 EA 1546 3092 650 1300 2196 $4,392Electrical Wiring for Drives 2 EA 350 700 1500 3000 1850 $3,700Provide DDC Pipe Press Sensor 1 EA 1250 1250 1100 1100 2350 $2,350Control Wiring and Conduit 1 EA 450 450 2500 2500 2950 $2,950

Controls Programming and Test 1 EA 7500 7500 7500 $7,500

* Reuse Exisitng Motor Subtotal $37,167

General Conditions 25% $9,292 $46,459

Construction Contingency 15% $6,969 $53,428Design 12% $6,411 $59,839

Total for EEM $59,839Round to $60,000

APPENDIX D – MECHANICAL CALCULATIONS

U-VALUE CALCULATIONSRS Consulting Seattle, Washington

Job Name: North Pole High School Date: 4-May-12Job Number: Eng: R. Sneeringer

Wall -1 Construction Resistance (R)At Frame Btwn Frame

15% 85%1) Outside Air Film (15 mph) 0.17 0.172) 1" Stucco 0.64 0.643) 1/2" Plywood 0.62 0.624) 2x8 Wood Stud @ 24 OC 9.09 --5) R-25 Batt -- 25.006) 2" Rigid Insul 8.00 8.007) 5/8" Sheetrock 0.56 0.568) Inside Air Film (still air) 0.68 0.68

R-Total 19.76 35.67

Wall U-Value 0.031

Wall - 2Construction Resistance (R)

At Frame Btwn Frame15% 85%

1) Outside Air Film (15 mph) 0.17 0.172) 1" Stucco 0.64 0.643) 1/2" Plywood 0.62 0.624) 2" Rigid 8.00 8.005) 2x8 Wood Stud @ 24 OC 9.09 --6) R-25 Batt -- 24.007) 8" CMU 1.93 1.938) Inside Air Film (still air) 0.68 0.68

R-Total 21.13 36.04

* Effectiveness of Insulation is Reduced by Metal Stud Thermal Path

Wall U-Value 0.031

U-VALUE CALCULATIONSRS Consulting Seattle, Washington

Job Name: North Pole High School Date: 4-May-12Job Number: Eng: R. Sneeringer

Roof-1:

Construction Resistance (R)At Frame Btwn Frame

100%1) Outside Air Film (15 mph) -- 0.172) Built Up Roofing -- 0.503) 20" Rigid Insulation (Avg) -- 40.004) Metal Deck -- --5) Inside Air Film (still air) -- 0.17

R-Total N/A 40.84

Roof U-Value 0.024

Floor: Existing Slab /GradeResistance (R)

Construction At Frame Btwn Frame

Insulated Slab Edge

N/AR-Total

Btu/deg f/lin ftFloor U-Value 0.550

Windows: Triple Pane

Construction

1) Wood/Aluminum Frame with Thermal Break2) Use Value from ASHRAE Table 13 1989

Window U-Value 0.500

Shading Coefficient 0.55Clear Glazing with Film

Building Envelope - Calculations and Common Conversions • U-Value = 1/R-Value • R-Values per Inch of Common Insulation Materials Fiberglass Blanket 3.2 Loose Fiberglass 2.5 Fiberglass Blown-in-Bat 4.0 Loose Rock Wool 2.8 Loose Cellulose 3.5 Wet-Spray Cellulose 3.9 Vermiculite 2.7 Polyisocyanurate 5.8 Expanded Polystyrene (bead board) 3.8 Extruded Polystyrene (blue board) 4.8 Foil Faced Polyisocyanurate 7.0 Spray applied Foam 6.0 U value = btu’s/ Hour x sq ft x deg F = 1/R R value = Hours x sq ft x deg F / BTU’s= 1/U q (Building heat loss in btu’s/hr)= U x A x Delta T = U x A x DD x 24 (annual heat loss)

Sample Calculations: Building Envelope-Heat Transfer Calculations R- “Resistance value” of building materials to heat flow RT = R inside film + R1 + R2 +… R outside film U-value: “overall heat transfer co-efficient” (Includes allowance for BOTH convection and conduction heat transfer) U = 1/ RT Sample Calculation 1: Windows: window area is 1000 square feet Window is triple pane; U = .27 Q = A * U * (Ti – To) Where Q = Total hourly rate of heat loss through walls, roof, glass, etc in Btu/hr U = Overall heat-transfer coefficient of walls, roof, ceiling, floor, or glass in Btu/hr ft2°F A = Net area of walls, roof, ceiling, floor, or glass in ft2 Ti = Inside design temperature in °F = 70 To = Outside design temperature in °F = 30 Q = U * A * delta T = .27 x 1000 x (70 – 30) = .27 x 1000 x 40 = 10,800 Btu/hour

Sample Calculation 2: For sample calculations- outside design = 30 F, inside design = 70 F Walls: wall area is 1000 square feet Wall is wood stud with R-30 insulation; U = 0.033 Q = U x A x delta T = 0.033 x 1000 x (70 – 30) = 0.033 x 1000 x 40 = 1333.3 Btu/hour Radiation heat gain thru windows Q = (A) x (SHGF) x (CLF) x (SC) Where: Q = heat transfer in BTU/HR A = window area in ft2 SHGF= solar heat gain factor (dependent on orientation and location) CLF = cooling load factor (dependent on shading and color of interior surface) SC = shading coefficient (property of glazing; dependent on clear/tinted/mirror glass surface) Other ratings- SHGC = solar heat gain coefficient = SC x 0.86 Glazing selection – Single pane vs. dual/triple pane Single pane- “U” = 1.10 Dual pane- “U” = 0.35 Triple pane- “U” = 0.22 (NOTE effect of interior “films” at glass surfaces; insulation value increases due to air space and number of surface films) – “low E” glass coating that allows light to get thru but not heat Glazing Selection SHGC- Solar Heat Gain Coefficient (% of ALL radiation (UV, visible and IR) that gets thru glass) VT- Visible Transmittance (% of visible light that gets thru glass) SOUTH FACING GLAZING: – Cold climate: SHGC > 0.6; high VT; low “U” – Moderate climate: SHGC < 0.6; high VT; low “U” – Hot climate: SHGC < 0.4; medium VT; low “U” – East/west facing: SHGC < 0.4; high VT; low “U”

Job Name: North Pole High SchoolJob Number:

Date: 30-Apr-12

Zone Zone Area Ceil Ht Room Zone SA OA Zone Zone OA Current Primary Zone

No. Description Sf Ft Vol cf Cfm Density Total cfm/per cfm cfm/sf cfm Vbz Eff (Ez) Voz Design OA Fract Served

Az V Vpz #/1000 sf Pz Rp Ra Vbz Ez Voz OSA Zp By

113 Business/Typing 1,513 9 13,617 2,600 33 50 10 500 0.12 180 680 0.8 850 33% AHU-1

114 Drivers Ed/Simulator 1,472 9 13,248 1,620 14 20 10 200 0.12 180 380 0.8 480 30% AHU-1

115 Power/mech/elect lab/auto 1,501 9 13,509 1,220 8 12 10 120 0.12 180 300 0.8 380 31% AHU-1

116 Corridor 6,842 10 68,420 1,200 0 0 0 0 0.06 410 410 0.8 510 43% AHU-1

117 Voc Ed/Din/Living/Drafting class 2,444 9 21,996 2,770 33 80 10 800 0.12 290 1,090 0.8 1,360 49% AHU-1

118 Home economics 2,652 9 23,868 4,680 30 80 10 800 0.12 320 1,120 0.8 1,400 30% AHU-1

119 Biology 1,300 9 11,700 2,210 31 40 10 400 0.18 230 630 0.8 790 36% AHU-1

120 Biology/Earth Science/Chem stg 2,968 9 26,712 3,500 27 80 10 800 0.18 530 1,330 0.8 1,660 47% AHU-1

121 Bio/Earth Sci/Earth Phys/Chem 4,336 9 39,024 5,000 28 120 10 1200 0.18 780 1,980 0.8 2,480 50% AHU-1

122 Biology/Animal and Plant 1,278 9 11,502 1,980 27 35 10 350 0.18 230 580 0.8 730 37% AHU-1

125 Corridor 4,020 9 36,180 1,200 0 0 0 0 0.06 240 240 0.8 300 25% AHU-1

126 Recp/Sec/Princ/VP/Offices 1,680 9 15,120 830 9 15 5 75 0.06 100 175 0.8 220 27% AHU-1

127 Kitchen/Food Strg/Dish wash 1,976 9 17,784 1,050 5 10 5 50 0.06 120 170 0.8 210 20% AHU-1

128 Commons 8,819 9 79,371 5,500 28 250 5 1250 0.06 530 1,780 0.8 2,230 41% AHU-1

129 Faculty Lounge/Fac Prep 2,352 9 21,168 2,425 11 25 5 125 0.06 140 265 0.8 330 14% AHU-1

202 Math 3,618 8.6 31,115 5,500 33 120 10 1200 0.12 430 1,630 2.8 580 11% AHU-1

203 Social Studies 3,618 8.6 31,115 5,250 33 120 10 1200 0.12 430 1,630 3.8 430 8% AHU-1

204 Math/Computer/Prep 2,070 8.6 17,802 2,060 33 68 10 680 0.12 250 930 4.8 190 9% AHU-1

205 Learn dis/off/testing/computer 4,318 8.6 37,135 2,000 5 20 10 200 0.12 520 720 5.8 120 6% AHU-1

206 Corridor 4,603 8.6 39,586 1,200 0 0 0 0 0.06 280 280 0.8 350 29% AHU-1

207 Social Studies/Language 3,561 8.6 30,625 5,280 34 120 10 1200 0.12 430 1,630 0.8 2,040 39% AHU-1

208 Language/Fine Art 2,417 8.6 20,786 3,930 33 80 10 800 0.12 290 1,090 0.8 1,360 35% AHU-1

209 Language 3,195 8.6 27,477 2,565 25 80 10 800 0.12 380 1,180 0.8 1,480 58% AHU-1

210 Library 5,288 8.6 45,477 4,210 25 130 5 650 0.06 320 970 8.8 110 3% AHU-1

211 Conference room 624 8.6 5,366 260 16 10 5 50 0.06 40 90 6.8 10 4% AHU-1

212 Corridor 4,721 8.6 40,601 735 0 0 0 0 0.06 280 280 7.8 40 5% AHU-1

123 Conference Room 376 9 3,384 560 27 10 5 50 0.06 20 70 0.8 90 16% AHU-2

124 Recp/Off/Nurse/Exam 1,200 9 10,800 1,200 13 15 5 75 0.06 70 145 0.8 180 15% AHU-2

130 Boys/Girls dressing rooms 1,131 9 10,179 1,170 11 12 5 60 0.06 70 130 0.8 160 14% AHU-2

131 Band 1,056 20.6 21,754 2,165 28 30 10 300 0.06 60 360 0.8 450 21% AHU-2

132 Choral/Band offices/storage 1,860 9 16,740 1,070 16 30 10 300 0.06 110 410 0.8 510 48% AHU-2

133 Choir 1,288 18 23,184 2,285 23 30 10 300 0.06 80 380 0.8 480 21% AHU-2

143 Drama Classroom 900 9 8,100 690 33 30 10 300 0.06 50 350 0.8 440 64% AHU-2

213 Crafts 1,537 8.6 13,218 1,370 20 30 10 300 0.18 280 580 8.8 70 5% AHU-2

215 Media graphics/Photo lab 3,170 9 28,530 1,820 5 15 10 150 0.12 380 530 10.8 50 3% AHU-2

216 Control room 594 8.6 5,108 1,000 7 4 5 20 0.06 40 60 11.8 10 1% AHU-2

134 Stage 1,647 47.2 77,762 4,000 7 12 5 60 0.06 100 160 0.8 200 5% AHU-3

135 Auditorium 4,544 47.2 214,477 13,380 77 350 5 1750 0.06 270 2,020 0.8 2,530 19% AHU-3

101 Gymnasiums/Storage/Wght rm 13,068 28.8 376,358 36,000 38 500 7.5 3750 0.06 780 4,530 0.8 5,660 16% AHU-4

102 PE/Coaches/Training/Dressing 2,280 9 20,520 2,180 2 5 5 25 0.06 140 165 0.8 210 10% AHU-5

103 Boys/Girls Locker rooms 3,164 9 28,476 5,520 6 20 5 100 0.06 190 290 0.8 360 7% AHU-5

104 Ski/Classrooms/PE Storage 1,290 9 11,610 1,100 19 25 10 250 0.12 150 400 0.8 500 45% AHU-5

130A Screen Room 823 10 8,225 1,000 18 15 5 75 0.06 50 125 0.8 160 16% FCU-1

2009 IMC MINIMUM OUTSIDE AIR CALCULATIONS

From 2009 IMC Table 403.3

Number of Occ People Rate Area Rate

Job Name: North Pole High SchoolJob Number:

Date: 30-Apr-12

Zone Zone Area Ceil Ht Room Zone SA OA Zone Zone OA Current Primary Zone

No. Description Sf Ft Vol cf Cfm Density Total cfm/per cfm cfm/sf cfm Vbz Eff (Ez) Voz Design OA Fract Served

Az V Vpz #/1000 sf Pz Rp Ra Vbz Ez Voz OSA Zp By

2009 IMC MINIMUM OUTSIDE AIR CALCULATIONS

From 2009 IMC Table 403.3

Number of Occ People Rate Area Rate

106 Wood shop 2,634 9 23,706 3,000 15 40 10 400 0.18 470 870 0.8 1,090 36% FCU-2

108 Auto shop 3,157 9 28,413 4,500 13 40 10 400 0.18 570 970 0.8 1,210 27% FCU-3

109 Metal shop 3,234 0 0 4,300 12 40 10 400 0.18 580 980 0.8 1,230 29% FCU-4

110 Drivers Ed/Agriculuture lab 3,552 0 0 2,100 11 40 10 400 0.12 430 830 0.8 1,040 50% FCU-5

111 Agriculuture class/storage/off 1,323 9 11,907 1,380 26 35 10 350 0.12 160 510 0.8 640 46% FCU-5

105 Boiler rm/Storage/Recv/Wkrm 2,646 9 23,814 1,635 0 0 0 0 0.06 160 160 0.8 200 12% V-4

136 Vestibule 504 8 4,032 1,100 0 0 0 0 0.06 30 30 0.8 40 4% VCH

137 Vestibule 184 8 1,472 550 0 0 0 0 0.06 10 10 0.8 10 2% VCH

138 Vestibule 64 8 512 550 0 0 0 0 0.06 0 0 0.8 0 0% VCH

139 Vestibule 80 8 640 550 0 0 0 0 0.06 0 0 0.8 0 0% VCH

140 Vestibule 80 8 640 550 0 0 0 0 0.06 0 0 0.8 0 0% VCH

141 Vestibule 162 8 1,296 550 0 0 0 0 0.06 10 10 0.8 10 2% VCH

142 Vestibule 64 8 512 550 0 0 0 0 0.06 0 0 0.8 0 0% VCH

112 Green house 1,158 0 0 10,840 9 10 0 0 0.06 70 70 0.8 90 1% VF-1,-2

141,956 179,440 23,265 13,440 38,260 0

Job Name: North Pole High SchoolJob Number:

Date: 30-Apr-12

Zone Zone Area Ceil Ht Room Zone SA OA Zone Zone OA Current Primary Zone

No. Description Sf Ft Vol cf Cfm Density Total cfm/per cfm cfm/sf cfm Vbz Eff (Ez) Voz Design OA Fract Served

Az V Vpz #/1000 sf Pz Rp Ra Vbz Ez Voz OSA Zp By

2009 IMC MINIMUM OUTSIDE AIR CALCULATIONS

From 2009 IMC Table 403.3

Number of Occ People Rate Area Rate

Area Primary Tot Tot Diversity Total Uncrtd Max Vent Total OA Design Design OA OA Avg CO2

TAG SERVES Served Air People People of People OA OSA Zp Eff OSA Percent OSA OSA Cfm/Per Cfm/Sf Met Setting

SF Cfm Zone Pz Sys Ps D Voz Vou % Ev Vot % Ros Rate

AHU-1 Classrooms 83,186 70,775 1,565 600 38% 20,640 7,913 58% 0.50 15,826 22% n/a n/a 10 0.19 1.2 1,200

AHU-2 Music 13,112 13,330 206 180 87% 2,440 2,132 64% 0.50 4,264 32% n/a n/a 21 0.33 1.2 700

AHU-3 Auditorium 6,191 17,380 362 360 99% 2,730 2,715 19% 0.90 3,017 17% n/a n/a 8 0.49 1.2 1,400

AHU-4 Gym/Weight Room 13,068 36,000 500 500 100% 5,660 5,660 16% 0.90 6,289 17% n/a n/a 13 0.48 2.0 1,500

AHU-5 Locker Rooms 4,454 6,620 45 45 100% 860 860 45% 0.60 1,433 22% n/a n/a 32 0.32 1.2 600

120,011 144,105 0 0 0 0

Based on 2009 IMC

Az Area of the zone (sq ft) ASHRAE 62.1, 2007 Appendix A-2:

Pz Zone population Table A-A Typical Met Levels For Activities

Rp Outdoor air required per person (Table 6.1) MET ACTIVITY

Ra Outdoor air required per unit area (Table 6.1) 1.0 Seated, quiet

Vbz The design outdoor airflow in the breathing zone ( people factor plus area factor in accordance with Table 6.1) 1.0 Reading and Writing, seated

Voz The design outdoor airflow supplied to the zone ( Vbc/Ez) 1.1 Typing

Vou Uncorrected outdoor intake (sum of all zones served by the ahu times the occupanct diversity D) 1.2 Filing, Seated

Vot Design outdoor intake flow ( Vou/Ev) 1.4 Filing, Standing

Ez Zone air distribution effectiveness in accordance with Table 403.3.1.2 2.0 Walking, at 0.89m/s

Ev System ventilation efficency ( Per table 403.2.2.3.2) 2-3 House Cleaning

Short Term Conditions 3-4 Exercise

If the peak occupancy will be of short duration, the design may be based on the average condtions over a time period T.

T Averaging time period , min ( 3v/Vbz)

V Volume of the zone , cu ft

CO2 Calculations

Cru - C0 = 1,000,000 x Nb x M / Ros Calculates rise in CO2 concentration if all supplied outdoor air is consumed.

Cs-C0 = Zs x 0 + (1-Zs) x (Cru - C0) Calculates target SA CO2 concentration (above ambient) based on previous calculation.

Cru = CO2 concentration in recirculated air if all outdoor air supplied to the building is used.

C0 = CO2 concentration outdoors.

Nb = CO2 generation rate per person at base metabolic rate. Default = 0.0091 CFM/Person (0.0043 L/s per person).

M = Relative metabolic rate in met units. Default is sedentary person = 1.2 mets, ASHRAE standard 62.1-2007, Appendix C.

400 Ambient CO2 Concentration

10% Safety Factor

0.0091 CO2 Generation Rate

Ros = OA Dilution Per Person (Vot / Population Served)

Motor Upgrades Feasiblity Analysis

Blended Electrical Cost $0.177

Maximum Acceptable Payback 5 Years

Ratio of BHP to Motor HP 75%

Estimated Annual Hours of Operation 3700

Exist Est Replace if Proposed Required Proposed Required Required Proposed Required

Motor Brake Motor Eff New Existing Energy Energy An Energy Motor Simple

Hp Hp Is Less Motor Energy Consump Savings Savings Instalation Payback

Than Eff Cons KWh KWH KWH $ Costs Yrs

1 0.75 68.0% 85.5% 3,042 2,420 621 110$ 550$ 5.0

1.5 1.13 72.4% 86.5% 4,289 3,588 701 124$ 620$ 5.0

2 1.50 74.9% 86.5% 5,525 4,785 740 131$ 655$ 5.0

3 2.25 79.9% 89.5% 7,772 6,936 836 148$ 740$ 5.0

5 3.75 83.3% 89.5% 12,414 11,560 853 151$ 755$ 5.0

7.5 5.63 85.2% 91.0% 18,207 17,055 1,153 204$ 1,020$ 5.0

10 7.50 86.3% 91.7% 23,979 22,566 1,412 250$ 1,250$ 5.0

15 11.25 88.1% 93.0% 35,240 33,376 1,864 330$ 1,650$ 5.0

20 15.00 88.3% 93.0% 46,874 44,501 2,373 420$ 2,100$ 5.0

25 18.75 88.5% 93.6% 58,457 55,270 3,186 564$ 2,820$ 5.0

30 22.50 89.7% 94.1% 69,192 65,972 3,220 570$ 2,850$ 5.0

40 30.00 90.2% 94.1% 91,804 87,962 3,842 680$ 3,400$ 5.0

50 37.50 90.8% 94.5% 114,007 109,488 4,520 800$ 4,000$ 5.0

60 45.00 91.4% 95.0% 135,846 130,694 5,153 912$ 4,560$ 5.0

75 56.25 91.3% 95.0% 169,989 163,367 6,621 1,172$ 5,860$ 5.0

100 75 91.9% 95.4% 225,249 216,910 8,339 1,476$ 7,380$ 5.0

Main Building Fan Systems

Motor Upgrades Feasiblity Analysis

Blended Electrical Cost $0.177

Maximum Acceptable Payback 5 Years

Ratio of BHP to Motor HP 75%

Estimated Annual Hours of Operation 5270

Exist Est Replace if Proposed Required Proposed Required Required Proposed Required

Motor Brake Motor Eff New Existing Energy Energy Energy Motor Simple

Hp Hp Is Less Motor Energy Consump Savings Savings Instalation Payback

Than Eff Cons KWh KWH KWH $ Costs Yrs

1 0.75 72.4% 85.5% 4,069 3,447 621 110$ 550$ 5.0

1.5 1.13 76.1% 86.5% 5,812 5,111 701 124$ 620$ 5.0

2 1.50 78.0% 86.5% 7,555 6,815 740 131$ 655$ 5.0

3 2.25 82.5% 89.5% 10,716 9,879 836 148$ 740$ 5.0

5 3.75 85.1% 89.5% 17,319 16,466 853 151$ 755$ 5.0

7.5 5.63 86.9% 91.0% 25,444 24,292 1,153 204$ 1,020$ 5.0

10 7.50 87.8% 91.7% 33,554 32,142 1,412 250$ 1,250$ 5.0

15 11.25 89.5% 93.0% 49,403 47,538 1,864 330$ 1,650$ 5.0

20 15.00 89.6% 93.0% 65,757 63,385 2,373 420$ 2,100$ 5.0

25 18.75 90.0% 93.6% 81,909 78,723 3,186 564$ 2,820$ 5.0

30 22.50 91.0% 94.1% 97,186 93,965 3,220 570$ 2,850$ 5.0

40 30.00 91.3% 94.1% 129,129 125,287 3,842 680$ 3,400$ 5.0

50 37.50 91.8% 94.5% 160,466 155,946 4,520 800$ 4,000$ 5.0

60 45.00 92.4% 95.0% 191,303 186,150 5,153 912$ 4,560$ 5.0

75 56.25 92.4% 95.0% 239,309 232,688 6,621 1,172$ 5,860$ 5.0

100 75 92.9% 95.4% 317,289 308,950 8,339 1,476$ 7,380$ 5.0

Perimeter Pump Systems

Motor Upgrades Feasiblity Analysis

Blended Electrical Cost $0.177

Maximum Acceptable Payback 5 Years

Ratio of BHP to Motor HP 75%

Estimated Annual Hours of Operation 3200

Exist Est Replace if Proposed Required Proposed Required Required Proposed Required

Motor Brake Motor Eff New Existing Energy Energy Energy Motor Simple

Hp Hp Is Less Motor Energy Consump Savings Savings Instalation Payback

Than Eff Cons KWh KWH KWH $ Costs Yrs

1 0.75 65.9% 85.5% 2,715 2,093 621 110$ 550$ 5.0

1.5 1.13 70.6% 86.5% 3,804 3,103 701 124$ 620$ 5.0

2 1.50 73.4% 86.5% 4,878 4,138 740 131$ 655$ 5.0

3 2.25 78.6% 89.5% 6,835 5,999 836 148$ 740$ 5.0

5 3.75 82.5% 89.5% 10,851 9,998 853 151$ 755$ 5.0

7.5 5.63 84.4% 91.0% 15,903 14,750 1,153 204$ 1,020$ 5.0

10 7.50 85.5% 91.7% 20,929 19,517 1,412 250$ 1,250$ 5.0

15 11.25 87.4% 93.0% 30,730 28,866 1,864 330$ 1,650$ 5.0

20 15.00 87.6% 93.0% 40,861 38,488 2,373 420$ 2,100$ 5.0

25 18.75 87.8% 93.6% 50,988 47,801 3,186 564$ 2,820$ 5.0

30 22.50 89.1% 94.1% 60,277 57,057 3,220 570$ 2,850$ 5.0

40 30.00 89.6% 94.1% 79,917 76,076 3,842 680$ 3,400$ 5.0

50 37.50 90.2% 94.5% 99,212 94,692 4,520 800$ 4,000$ 5.0

60 45.00 90.9% 95.0% 118,185 113,032 5,153 912$ 4,560$ 5.0

75 56.25 90.7% 95.0% 147,912 141,291 6,621 1,172$ 5,860$ 5.0

100 75 91.3% 95.4% 195,936 187,597 8,339 1,476$ 7,380$ 5.0

Heating Coil Pump Systems

APPENDIX E – SYSTEM DIAGRAMS

HEATING WATER SYSTEM

HEATING WATER SYSTEM DIAGAMS M1.1

VAV SYSTEMS

VAV SYSTEMS M1.2

TWO SPEED SYSTEMS

TWO SPEED SYSTEMS M1.3

HEAT RECOVERY SYSTEM

HEAT RECOVERY SYSTEM M1.4

APPENDIX F – EQUIPMENT SCHEDULES

AHFC ENERGY AUDITS - EXISTING EQUIPMENT SCHEDULES

BOILER SCHEDULE - NORTH POLE HIGH SCHOOLMARK TYPE BOILER CAP CAP OIL EST BURNER

MODEL INPUT OUPUT CAP EFF MODEL

# MBH MBH GPH % #

B-1 BUILDING HEATING CAST IRON P-1086 2,520 2,040 18.0 81.0%

B-2 BUILDING HEATING CAST IRON P-1086 2,520 2,040 18.0 81.0%

B-3 BUILDING HEATING CAST IRON P-1086 2,520 2,040 18.0 81.0%

NOTES:

FAN SCHEDULE - NORTH POLE HIGH SCHOOLMARK FAN AIR MIN TSP CAPACITY MOTOR MOTOR

MANUF FLOW OSA IN CONTROL SIZE EFF

CFM CFM H20 HP

AHU-1 PACE 65,200 4-1/4 VSD 75 N/A

AHU-2 PACE 13,500 3 -1/2 IN VANES 15 N/A

AHU-3 PACE 17,400 1-3/4 2 SPD 10/2 N/A 2 MOTOR DRIVE

AHU-4 GYM PACE 36,000 2-1/4 2 SPD 20/5 90.1% 2 MOTOR DRIVE

AHU-5 LOCKER ROOM PACE 8,800 N/A 2-1/4 2 SPD 5/1 N/A 2 MOTOR DRIVE

REF-1 AHU-1 RET/EXH PACE 56,000 N/A 5/8 VSD 15 N/A

REF-2 AHU-2 RET/EXH PACE 11,700 N/A 5/8 CV 3 N/A

REF-3 AHU-3 RET/EXH PACE 17,400 N/A 1/2 2 SPD 7.5/1 N/A 2 MOTOR DRIVE

REF-4 AHU-4 RET/EXH PACE 36,000 N/A 1/2 2 SPD 3 N/A

FCU-1 SCREEN ROOM PACE 1,500 1-1/4 CV 1-1/2 N/A

FCU-2 WOOD SHOP PACE 3,600 1 CV 2 80.0%

FCU-3 AUTO SHOP PACE 4,500 1-1/4 CV 2 80.0%

FCU-4 METAL SHOP PACE 4,300 1 CV 1-1/2 N/A

FCU-5 VOC SHOP PACE 4,300 1 CV 1-1/2 N/A

FCU-7 KITCHEN MAKE UP PACE 4,000 1-1/4 CV 3 N/A

FCU-8 TOILET EXHAUST PACE 4,800 1-3/4 CV 5 N/A

FCU-9 LOCKER EXHAUST PACE 8,500 1-3/4 2 SPD 5/1 N/A 2 MOTOR DRIVE

FCU-10 AUTO SHOP EXHAUST PACE 3,500 N/A 1-1/4 CV 2 N/A

NOTES:

GOULD

GOULD E PLUS

GOULD E PLUS

GOULD E PLUS

GOULD E PLUS

GOULD

REMARKS

REMARKS

MOTOR MANUFACTURER

N/A

N/A

N/A

GOULD E PLUS

GOULD

LINCOLN

LINCOLN

LINCOLN

LINCOLN

GOULD E PLUS

BALDOR

BALDOR

SERVES

SERVES

AUDITORIUM

MAIN BUILDING

MUSIC/ART

BURNER

MANUF

BOILER

MANUF

WEIL McCLAIN

WEIL McCLAIN

WEIL McCLAIN

GORDON PIATT

GORDON PIATT

GORDON PIATT

RS Consulting - Mechanical Engineering - 2400 NW 80th St #178 Seattle, WA 98117

AHFC ENERGY AUDITS - EXISTING EQUIPMENT SCHEDULES

PUMP SCHEDULE -NORTH POLE HIGH SCHOOLMARK PUMP PUMP PUMP PUMP PUMP CAPACITY MOTOR MOTOR REMARKS

MANUF TYP MODEL FLOW HEAD CONTROL SIZE EFF

# GPM FT H20 HP

CP1A B & G INLINE HD3 100 6 CV 1/2

CP1B BOILER CIRC B & G INLINE HD3 100 6 CV 1/2

CP1C BOILER CIRC B & G INLINE HD3 100 6 CV 1/2

CP2A HEATING WATER DIST B & G END SUCT 3E-10-BF 285 95 CV 15.0 91.7%

CP2B HEATING WATER DIST B & G END SUCT 3E-10-BF 285 95 CV 15.0 91.7%

CP3 COIL PUMP - AHU-1 B & G INLINE SERIES 60 60 12 CV 1/2 N/A

CP4 COIL PUMP - AHU-2 B & G INLINE SERIES 60 12 10 CV 1/4 N/A

CP5 COIL PUMP - AHU-3 B & G INLINE SERIES 60 38 12 CV 1/4 N/A

CP6 COIL PUMP - AHU-4 B & G INLINE SERIES 60 45 12 CV 1/3 N/A

CP7 COIL PUMP - AHU-5 B & G INLINE SERIES 60 30 30 CV 3/4 N/A

CP8 LOCKER EXH HEAT REC B & G INLINE SERIES 80 50 58 CV 2.0 N/A

CP9 COIL PUMP - FCU-2 B & G INLINE SERIES 60 10 12 CV 1/6 N/A

CP10 COIL PUMP - FCU-3 B & G INLINE SERIES 60 40 35 CV 1.0 N/A

CP11 SHOP HEAT RECOVERY B & G INLINE SERIES 60 30 50 CV 1.0 N/A

CP12 COIL PUMP - FCU-4 B & G INLINE SERIES 60 10 12 CV 1/6 N/A

CP13 COIL PUMP - FCU-5 B & G INLINE SERIES 60 10 12 CV 1/6 N/A

CP15 B & G INLINE SERIES 60 40 38 CV 1.0 91.0% REDUNDANT

CP16 B & G INLINE SERIES 60 40 45 CV 1.0 91.0%

CP18 RADIANT SLAB B & G INLINE SERIES 60 18 52 CV 1.0 91.0% REDUNDANT

CP22 LOCKER ROOM TERM UN B & G INLINE SERIES 60 24 38 CV 3/4 N/A

CP23 MUSIC TERM UNITS B & G INLINE SERIES 60 25 32 CV 3/4 N/A

CP24 CLASSRM TERM UNITS B & G INLINE SERIES 60 36 42 CV 1.0 N/A

CP25 SHOP TERM UNITS B & G INLINE SERIES 60 44 36 CV 1.0 N/A

NOTES:

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

SERVES

BOILER CIRC

COIL PUMP - FCU-7

TOILET EXH HT REC

BELL AND GOSSET

MOTOR

MANUF

N/A

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

N/A

N/A

GOULD E-PLUS

GOULD E-PLUS

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

BELL AND GOSSET

RS Consulting - Mechanical Engineering - 2400 NW 80th St #178 Seattle, WA 98117

APPENDIX G – TRACE 700 INPUT

Bldg: North Pole High SchoolZone Zone Floor Roof Total Floor Ceiling Plenum Grs Wall Window # Occ Design Design

Number Name Area Area Perimeter to Floor Height Ht Area Area of per Total Watts Total Loads System Airflow Cfm

Sf Sf Lgth, Ft Ht Ft Ft Ft Sf Sf People 1000 sf Watts Per SF Watts Watt/Sf Cfm SF

101 Gymnasiums/Storage/Wght rm 13,068 13,068 251 28.8 28.8 0.0 7,229 0 500 38 14,375 1.1 1568 0.12 AHU-4 36,000 2.75

Building Input Form - Trace 700

Lights (Existing) Misc Loads

101 Gymnasiums/Storage/Wght rm 13,068 13,068 251 28.8 28.8 0.0 7,229 0 500 38 14,375 1.1 1568 0.12 AHU-4 36,000 2.75

102 PE/Coaches/Training/Dressing 2,280 2,280 0 13.6 9.0 4.6 0 0 5 2 2,508 1.1 570 0.25 AHU-5 2,180 0.96

103 Boys/Girls Locker rooms 3,164 3,164 0 13.6 9.0 4.6 0 0 20 6 3,480 1.1 791 0.25 AHU-5 5,520 1.74

104 Ski/Classrooms/PE Storage 1,290 1,290 44 13.6 9.0 4.6 598 36 25 19 1,419 1.1 968 0.75 AHU-5 1,100 0.85

105 Boiler rm/Storage/Recv/Wkrm 2,646 2,646 111 26.0 9.0 17.0 2,886 24 0 0 2,911 1.1 5292 2.00 V-4 1,635 0.62

106 Wood shop 2,634 2,634 0 13.6 9.0 4.6 0 0 40 15 2,897 1.1 1976 0.75 FCU-2 3,000 1.14

107 Elect Switchgear/Emer Generator 600 600 14 13.6 9.0 4.6 190 0 0 0 660 1.1 150 0.25 UH 0.00

108 Auto shop 3,157 3,157 42 13.6 0.0 13.6 571 0 40 13 3,473 1.1 2368 0.75 FCU-3 4,500 1.43

109 Metal shop 3,234 3,234 43 16.8 0.0 16.8 722 0 40 12 3,557 1.1 2426 0.75 FCU-4 4,300 1.33109 Metal shop 3,234 3,234 43 16.8 0.0 16.8 722 0 40 12 3,557 1.1 2426 0.75 FCU-4 4,300 1.33

110 Drivers Ed/Agriculuture lab 3,552 3,552 149 16.8 0.0 16.8 2,503 0 40 11 3,907 1.1 2664 0.75 FCU-5 2,100 0.59

111 Agriculuture class/storage/off 1,323 1,323 13 13.6 9.0 4.6 177 0 35 26 1,455 1.1 992 0.75 FCU-5 1,380 1.04

112 Green house 1,158 1,158 118 16.8 0.0 16.8 1,982 0 10 9 1,274 1.1 290 0.25 VF-1,-2 10,840 9.36

113 Business/Typing 1,513 90 13.6 9.0 4.6 1,224 96 50 33 1,664 1.1 1135 0.75 AHU-1 2,600 1.72

114 Drivers Ed/Simulator 1,472 0 13.6 9.0 4.6 0 0 20 14 1,619 1.1 1104 0.75 AHU-1 1,620 1.10

115 Power/mech/elect lab/auto 1,501 0 13.6 9.0 4.6 0 0 12 8 1,651 1.1 1126 0.75 AHU-1 1,220 0.81

116 Corridor 6,842 0 13.6 10.0 3.6 0 0 0 0 7,526 1.1 1711 0.25 AHU-1 1,200 0.18

117 Voc Ed/Din/Living/Drafting class 2,444 14 13.6 9.0 4.6 190 36 80 33 2,688 1.1 1833 0.75 AHU-1 2,770 1.13117 Voc Ed/Din/Living/Drafting class 2,444 14 13.6 9.0 4.6 190 36 80 33 2,688 1.1 1833 0.75 AHU-1 2,770 1.13

118 Home economics 2,652 105 13.6 9.0 4.6 1,428 132 80 30 2,917 1.1 1989 0.75 AHU-1 4,680 1.76

119 Biology 1,300 83 13.6 9.0 4.6 1,129 96 40 31 1,430 1.1 975 0.75 AHU-1 2,210 1.70

120 Biology/Earth Science/Chem stg 2,968 103 13.6 9.0 4.6 1,401 156 80 27 3,265 1.1 2226 0.75 AHU-1 3,500 1.18

121 Bio/Earth Sci/Earth Phys/Chem 4,336 0 13.6 9.0 4.6 0 0 120 28 4,770 1.1 3252 0.75 AHU-1 5,000 1.15

122 Biology/Animal and Plant 1,278 65 13.6 9.0 4.6 884 48 35 27 1,406 1.1 959 0.75 AHU-1 1,980 1.55

123 Conference Room 376 52 13.6 9.0 4.6 707 36 10 27 414 1.1 94 0.25 AHU-2 560 1.49

124 Recp/Off/Nurse/Exam 1,200 34 13.6 9.0 4.6 462 48 15 13 1,320 1.1 300 0.25 AHU-2 1,200 1.00

125 Corridor 4,020 0 13.6 9.0 4.6 0 0 0 0 4,422 1.1 1005 0.25 AHU-1 1,200 0.30

126 Recp/Sec/Princ/VP/Offices 1,680 0 13.6 9.0 4.6 0 0 15 9 1,848 1.1 1260 0.75 AHU-1 830 0.49

127 Kitchen/Food Strg/Dish wash 1,976 0 13.6 9.0 4.6 0 0 10 5 2,174 1.1 1482 0.75 AHU-1 1,050 0.53

128 Commons 8,819 0 13.6 9.0 4.6 0 0 250 28 9,701 1.1 6614 0.75 AHU-1 5,500 0.62

129 Faculty Lounge/Fac Prep 2,352 0 13.6 9.0 4.6 0 0 25 11 2,587 1.1 2940 1.25 AHU-1 2,425 1.03

130 Boys/Girls dressing rooms 1,131 0 13.6 9.0 4.6 0 0 12 11 1,244 1.1 848 0.75 AHU-2 1,170 1.03

130A Screen Room 823 0 14.6 10.0 4.6 560 0 15 18 905 1.1 617 0.75 FCU-1 1,000 1.22

131 Band 1,056 1,056 25 22.4 20.6 1.8 560 0 30 28 1,162 1.1 792 0.75 AHU-2 2,165 2.05

132 Choral/Band offices/storage 1,860 31 13.6 9.0 4.6 422 0 30 16 2,046 1.1 1395 0.75 AHU-2 1,070 0.58

133 Choir 1,288 1,288 84 22.6 18.0 4.6 1,898 0 30 23 1,417 1.1 966 0.75 AHU-2 2,285 1.77133 Choir 1,288 1,288 84 22.6 18.0 4.6 1,898 0 30 23 1,417 1.1 966 0.75 AHU-2 2,285 1.77

134 Stage 1,647 2,470 126 55.1 47.2 7.9 6,943 0 12 7 1,812 1.1 3295 2.00 AHU-3 4,000 2.43

135 Auditorium 4,544 3,950 54 55.1 47.2 7.9 2,975 0 350 77 4,998 1.1 3408 0.75 AHU-3 13,380 2.94

136 Vestibule 504 36 9.4 8.0 1.4 338 0 0 0 554 1.1 0 0.00 VCH 1,100 2.18

137 Vestibule 184 8 9.4 8.0 1.4 75 0 0 0 202 1.1 0 0.00 VCH 550 2.99

138 Vestibule 64 8 9.4 8.0 1.4 75 0 0 0 70 1.1 0 0.00 VCH 550 8.59

139 Vestibule 80 8 9.4 8.0 1.4 75 0 0 0 88 1.1 0 0.00 VCH 550 6.88

140 Vestibule 80 10 9.4 8.0 1.4 94 0 0 0 88 1.1 0 0.00 VCH 550 6.88

141 Vestibule 162 14 9.4 8.0 1.4 132 0 0 0 178 1.1 0 0.00 VCH 550 3.40141 Vestibule 162 14 9.4 8.0 1.4 132 0 0 0 178 1.1 0 0.00 VCH 550 3.40

142 Vestibule 64 8 9.4 8.0 1.4 75 0 0 0 70 1.1 0 0.00 VCH 550 8.59

143 Drama Classroom 900 0 13.6 9.0 4.6 0 0 30 33 990 1.1 0 0.00 AHU-2 690 0.77

201 Mechanical rms/MW restrms 5,420 5,420 67 14.0 8.6 5.4 938 0 0 0 5,962 1.1 4065 0.75 VCH 0.00

202 Math 3,618 3,618 164 14.0 8.6 5.4 2,296 216 120 33 3,980 1.1 2714 0.75 AHU-1 5,500 1.52

203 Social Studies 3,618 3,618 106 14.0 8.6 5.4 1,484 96 120 33 3,980 1.1 2714 0.75 AHU-1 5,250 1.45

204 Math/Computer/Prep 2,070 2,070 0 14.0 8.6 5.4 0 0 68 33 2,277 1.1 1553 0.75 AHU-1 2,060 1.00

205 Learn dis/off/testing/computer 4,318 4,318 0 14.0 8.6 5.4 0 0 20 5 4,750 1.1 3239 0.75 AHU-1 2,000 0.46

Bldg: North Pole High SchoolZone Zone Floor Roof Total Floor Ceiling Plenum Grs Wall Window # Occ Design Design

Number Name Area Area Perimeter to Floor Height Ht Area Area of per Total Watts Total Loads System Airflow Cfm

Sf Sf Lgth, Ft Ht Ft Ft Ft Sf Sf People 1000 sf Watts Per SF Watts Watt/Sf Cfm SF

Building Input Form - Trace 700

Lights (Existing) Misc Loads

206 Corridor 4,603 4,603 70 14.0 8.6 5.4 980 0 0 0 5,063 1.1 3452 0.75 AHU-1 1,200 0.26206 Corridor 4,603 4,603 70 14.0 8.6 5.4 980 0 0 0 5,063 1.1 3452 0.75 AHU-1 1,200 0.26

207 Social Studies/Language 3,561 3,561 132 14.0 8.6 5.4 1,848 192 120 34 3,917 1.1 2671 0.75 AHU-1 5,280 1.48

208 Language/Fine Art 2,417 2,417 120 14.0 8.6 5.4 1,680 108 80 33 2,659 1.1 1813 0.75 AHU-1 3,930 1.63

209 Language 3,195 3,195 0 14.0 8.6 5.4 0 0 80 25 3,515 1.1 2396 0.75 AHU-1 2,565 0.80

210 Library 5,288 5,288 80 14.0 8.6 5.4 1,120 0 130 25 5,817 1.1 3966 0.75 AHU-1 4,210 0.80

211 Conference room 624 624 18 14.0 8.6 5.4 252 0 10 16 686 1.1 468 0.75 AHU-1 260 0.42

212 Corridor 4,721 4,721 20 14.0 8.6 5.4 280 0 0 0 5,193 1.1 3541 0.75 AHU-1 735 0.16

213 Crafts 1,537 1,537 55 14.0 8.6 5.4 770 24 30 20 1,691 1.1 1153 0.75 AHU-2 1,370 0.89

214 Mech rooms 1,553 1,553 133 14.0 14.0 1,862 0 0 0 1,708 1.1 1165 0.75 AHU-2 0.00214 Mech rooms 1,553 1,553 133 14.0 14.0 1,862 0 0 0 1,708 1.1 1165 0.75 AHU-2 0.00

215 Media graphics/Photo lab 3,170 3,170 104 14.0 9.0 5.0 1,456 0 15 5 3,487 1.1 2378 0.75 AHU-2 1,820 0.57

216 Control room 594 594 75 14.0 8.6 5.4 1,050 0 4 7 653 1.1 149 0.25 AHU-2 1,000 1.68

149,529 97,177 2,887 54,524 1,344 2,903 164,482 1.1 98,811 0.66 179,440

Percent Windows 2% 33% Diversity

AIR HANDLING UNITS Total Student Enrollment 946

TAG SERVES AREA CFM CFM/SF SCHEDULEDTAG SERVES AREA CFM CFM/SF SCHEDULED

AHU-1 CLASSROOMS 83,186 70,775 0.85 65200

AHU-2 MUSIC 14,665 13,330 0.91 13500

AHU-3 AUDITORIUM 6,191 17,380 2.81 17400

AHU-4 GYM 13,068 36,000 2.75 36000

AHU-5 LOCKERS 6,734 8,800 1.31 8800

FCU-1 SCREEN ROOM 823 1,000 1.22

FCU-2 WOOD SHOP 2,634 3,000 1.14

FCU-3 AUTO SHOP 3,157 4,500 1.43

FCU-4 METAL SHOP 3,234 4,300 1.33

FCU-5 SHOP 4,875 3,480 0.71

CH-1 VESTIBULES 1,138 4,400 3.87

OTHER OTHER 10,227 10,227

149,932 177,192 1.18

Bldg: North Pole High School Wall Direction: North = 0, East = 90, South = 180, West =270

Zone Zone

Number Name Wall Gross Wall Wall Glass Glass Wall Wall Gross Wall Wall Glass Glass Wall Wall Gross Wall Wall Glass Glass Wall

Length Ft Sq Ft Type Area Type Direction Length Ft Sq Ft Type Area Type Direction Length Ft Sq Ft Type Area Type Direction

101 Gymnasiums/Storage/Wght rm 133 3830 2 0 100 2880 2 270 18 518 2 90

102 PE/Coaches/Training/Dressing 0 0 0

103 Boys/Girls Locker rooms 0 0 0

104 Ski/Classrooms/PE Storage 3 41 1 0 41 558 1 36 1 270 0

105 Boiler rm/Storage/Recv/Wkrm 44 1144 1 270 64 1664 1 24 1 180 3 78 1 90

106 Wood shop 0 0 0

107 Elect Switchgear/Emer Generator 14 190 1 270 0 0

108 Auto shop 42 571 1 270 0 0

109 Metal shop 43 722 1 270 0 0

110 Drivers Ed/Agriculuture lab 58 974 1 270 25 420 1 0 66 1109 1 180

111 Agriculuture class/storage/off 13 177 1 90 0 0

112 Green house 14 235 1 270 52 874 1 180 52 874 1 90

113 Business/Typing 37 503 1 48 1 180 53 721 1 48 1 90 0

114 Drivers Ed/Simulator 0 0 0

115 Power/mech/elect lab/auto 0 0 0

116 Corridor 0 0 0

117 Voc Ed/Din/Living/Drafting class 14 190 1 36 1 180 0 0

118 Home economics 52 707 1 84 1 180 53 721 1 48 1 90 0

119 Biology 26 354 1 48 1 180 53 721 1 48 1 90 4 54 1 270

120 Biology/Earth Science/Chem stg 74 1006 1 144 1 180 29 394 1 12 1 90 0

121 Bio/Earth Sci/Earth Phys/Chem 0 0 0

122 Biology/Animal and Plant 55 748 1 48 1 90 10 136 1 0 0

123 Conference Room 10 136 1 180 25 340 1 12 1 90 17 231 1 24 1 0

124 Recp/Off/Nurse/Exam 34 462 1 48 1 0 0 0

125 Corridor 0 0 0

126 Recp/Sec/Princ/VP/Offices 0 0 0

127 Kitchen/Food Strg/Dish wash 0 0 0

128 Commons 0 0 0

129 Faculty Lounge/Fac Prep 0 0 0

130 Boys/Girls dressing rooms 0 0 0

130A Screen Room

131 Band 25 560 1 90 0 0

132 Choral/Band offices/storage 31 422 1 90 0 0

133 Choir 24 542 1 90 57 1288 1 0 3 68 1 270

134 Stage 3 165 1 90 96 5290 1 1 27 1488 1 270

135 Auditorium 54 0 1 270 0 0

136 Vestibule 36 338 1 0 0 0

137 Vestibule 8 75 1 270 0 0

138 Vestibule 8 75 1 180 0 0

139 Vestibule 8 75 1 180 0 0

140 Vestibule 10 94 1 180 0 0

141 Vestibule 14 132 1 90 0 0

142 Vestibule 8 75 1 0 0 0

143 Drama Classroom 0 0 0

201 Mechanical rms/MW restrms 21 294 1 0 46 644 1 90 0

202 Math 82 1148 1 144 1 180 82 1148 1 72 1 90 0

203 Social Studies 52 728 1 12 1 90 54 756 1 84 1 180 0

204 Math/Computer/Prep 0 0 0

205 Learn dis/off/testing/computer 0 0 0

206 Corridor 14 196 1 270 38 532 1 180 18 252 1 0

207 Social Studies/Language 53 742 1 48 1 90 79 1106 1 144 1 180 0

208 Language/Fine Art 94 1316 1 60 1 90 26 364 1 48 1 0 0

209 Language 0 0 0

210 Library 26 364 1 270 27 378 1 270 27 378 1 180

211 Conference room 18 252 1 0 0 0

212 Corridor 20 280 1 0 0 0

213 Crafts 55 770 1 24 1 0 0 0

214 Mech rooms 56 784 1 0 30 420 1 90 47 658 1 180

215 Media graphics/Photo lab 64 896 1 270 40 560 1 0 0

216 Control room 9 126 1 270 66 924 1 0 0

Wall 1 Wall 2 Wall 3

Building Input Form - Trace 700 - Wall Data

Library Members

Schedules

FB School Misc Loads Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 11 a.m. 100.0

11 a.m. noon 80.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 5 p.m. 30.0

5 p.m. Midnight 0.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 11 a.m. 100.0

11 a.m. noon 80.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 5 p.m. 30.0

5 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 5.0

8 a.m. 3 p.m. 5.0

3 p.m. 5 p.m. 5.0

5 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 7 of 31Dataset Name: NP High School.trc

Library Members

Schedules

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 11 a.m. 100.0

11 a.m. noon 80.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 5 p.m. 30.0

5 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight Midnight 0.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 8 of 31Dataset Name: NP High School.trc

Library Members

Schedules

Lights - Middle School gym Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 7 p.m. 100.0

7 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 3 p.m. 10.0

3 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 7 p.m. 100.0

7 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight Midnight 0.0

fb school vest tstat Simulation type: Reduced year

Start time End time Setpoint °FJanuary - December Cooling design to Sunday Thermostat

Midnight Midnight 70.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 9 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB School Vent Simulation type: Reduced year

Start time End time PercentageJanuary - June Weekday Utilization

Midnight 8 a.m. 0.0

8 a.m. 9 a.m. 50.0

9 a.m. 5 p.m. 100.0

5 p.m. Midnight 0.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 100.0

Start time End time PercentageJuly - August Weekday Utilization

Midnight 10 a.m. 0.0

10 a.m. 3 p.m. 100.0

3 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 8 a.m. 0.0

8 a.m. 9 a.m. 50.0

9 a.m. 5 p.m. 100.0

5 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 10 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB School Lights Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight 7 a.m. 0.0

7 a.m. 9 a.m. 50.0

9 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. Midnight 0.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 9 a.m. 50.0

9 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 20.0

8 a.m. 3 p.m. 50.0

3 p.m. 5 p.m. 20.0

5 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 9 a.m. 50.0

9 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 11 of 31Dataset Name: NP High School.trc

Library Members

Schedules

Midnight Midnight 0.0

fb school clg tstat Simulation type: Reduced year

Start time End time Setpoint °FJanuary - May Cooling design to Weekday Thermostat

Midnight 9 a.m. 95.0

9 a.m. 4 p.m. 80.0

4 p.m. Midnight 95.0

Start time End time Setpoint °FSeptember - December Cooling design to Weekday Thermostat

Midnight 9 a.m. 95.0

9 a.m. 4 p.m. 80.0

4 p.m. Midnight 95.0

Start time End time Setpoint °FJune - August Cooling design to Weekday Thermostat

Midnight 7 a.m. 95.0

7 a.m. 6 p.m. 95.0

6 p.m. Midnight 95.0

Start time End time Setpoint °FJanuary - December Saturday to Sunday Thermostat

Midnight 9 a.m. 95.0

8 a.m. 5 p.m. 75.0

4 p.m. Midnight 95.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 12 of 31Dataset Name: NP High School.trc

Library Members

Schedules

People - Middle School gym Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. 7 p.m. 20.0

7 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 3 p.m. 10.0

3 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 50.0

8 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. 7 p.m. 20.0

7 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight Midnight 0.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 13 of 31Dataset Name: NP High School.trc

Library Members

Schedules

Vent - Middle School kitchen Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 6 a.m. 0.0

6 a.m. 7 a.m. 10.0

7 a.m. 8 a.m. 80.0

8 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. 6 p.m. 10.0

6 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 6 a.m. 0.0

6 a.m. 8 a.m. 10.0

8 a.m. 3 p.m. 50.0

3 p.m. 5 p.m. 10.0

5 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 6 a.m. 0.0

6 a.m. 7 a.m. 10.0

7 a.m. 8 a.m. 80.0

8 a.m. 3 p.m. 100.0

3 p.m. 5 p.m. 50.0

5 p.m. 6 p.m. 10.0

6 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight 6 a.m. 0.0

6 a.m. 5 p.m. 30.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 14 of 31Dataset Name: NP High School.trc

Library Members

Schedules

5 p.m. Midnight 0.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 100.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 15 of 31Dataset Name: NP High School.trc

Library Members

Schedules

fb school htg tstat Simulation type: Reduced year

Start time End time Setpoint °FJanuary - May Cooling design to Weekday Thermostat

Midnight 5 a.m. 65.0

5 a.m. 6 a.m. 66.0

6 a.m. 7 a.m. 67.0

7 a.m. 8 a.m. 68.0

8 a.m. 9 a.m. 69.0

9 a.m. 5 p.m. 70.0

5 p.m. Midnight 65.0

Start time End time Setpoint °FSeptember - December Cooling design to Weekday Thermostat

Midnight 5 a.m. 65.0

5 a.m. 6 a.m. 66.0

6 a.m. 7 a.m. 67.0

7 a.m. 8 a.m. 68.0

8 a.m. 9 a.m. 69.0

9 a.m. 5 p.m. 70.0

5 p.m. Midnight 65.0

Start time End time Setpoint °FJune - August Cooling design to Weekday Thermostat

Midnight 7 a.m. 65.0

7 a.m. 6 p.m. 65.0

6 p.m. Midnight 65.0

Start time End time Setpoint °FJanuary - December Saturday to Sunday Thermostat

Midnight 7 a.m. 65.0

7 a.m. 8 a.m. 65.0

8 a.m. 5 p.m. 65.0

5 p.m. 6 p.m. 65.0

6 p.m. Midnight 65.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 16 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB School Parking Lot Lights Simulation type: Reduced year

Start time End time PercentageJanuary - March Cooling design to Sunday Utilization

Midnight 9 a.m. 100.0

9 a.m. 4 p.m. 0.0

4 p.m. Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight 7 a.m. 100.0

7 a.m. 6 p.m. 0.0

6 p.m. Midnight 100.0

Start time End time PercentageApril - September Cooling design to Sunday Utilization

Midnight 5 a.m. 100.0

5 a.m. 8 p.m. 0.0

8 p.m. Midnight 100.0

Start time End time PercentageOctober - December Cooling design to Sunday Utilization

Midnight 8 a.m. 100.0

8 a.m. 6 p.m. 0.0

6 p.m. Midnight 100.0

FB School Vestibule Infiltration Simulation type: Reduced year

Start time End time PercentageHeating Design Utilization

Midnight Midnight 100.0

Start time End time PercentageJanuary - December Cooling design to Sunday Utilization

Midnight 8 a.m. 75.0

8 a.m. 5 p.m. 100.0

5 p.m. Midnight 75.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 17 of 31Dataset Name: NP High School.trc

Library Members

Schedules

Cooling Only (Design) Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design to Sunday Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Available (100%) Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design to Sunday Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 100.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 18 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB People Common Areas Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 8 a.m. 0.0

8 a.m. 10 a.m. 100.0

10 a.m. noon 25.0

noon 1 p.m. 100.0

1 p.m. 3 p.m. 25.0

3 p.m. 4 p.m. 100.0

4 p.m. 5 p.m. 25.0

5 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 10 a.m. 0.0

10 a.m. 3 p.m. 25.0

3 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 8 a.m. 0.0

8 a.m. 10 a.m. 100.0

10 a.m. noon 25.0

noon 1 p.m. 100.0

1 p.m. 3 p.m. 25.0

3 p.m. 4 p.m. 100.0

4 p.m. 5 p.m. 25.0

5 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 19 of 31Dataset Name: NP High School.trc

Library Members

Schedules

Midnight Midnight 0.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 20 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB People Classroom Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 20.0

8 a.m. 9 a.m. 50.0

9 a.m. noon 100.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 4 p.m. 50.0

4 p.m. 5 p.m. 20.0

5 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 10 a.m. 0.0

8 a.m. 3 p.m. 30.0

2 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 7 a.m. 0.0

7 a.m. 8 a.m. 20.0

8 a.m. 9 a.m. 50.0

9 a.m. noon 100.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 4 p.m. 50.0

4 p.m. 5 p.m. 20.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 21 of 31Dataset Name: NP High School.trc

Library Members

Schedules

5 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight Midnight 0.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 22 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB Dom Hot Water Simulation type: Reduced year

Start time End time PercentageJanuary - May Cooling design to Weekday Utilization

Midnight 7 a.m. 5.0

7 a.m. 8 a.m. 50.0

8 a.m. 11 a.m. 100.0

11 a.m. noon 80.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 5 p.m. 30.0

5 p.m. Midnight 5.0

Start time End time PercentageJanuary - May Saturday Utilization

Midnight Midnight 5.0

Start time End time PercentageJanuary - May Sunday Utilization

Midnight Midnight 5.0

Start time End time PercentageJune - August Cooling design to Weekday Utilization

Midnight 7 a.m. 5.0

7 a.m. 8 a.m. 10.0

8 a.m. 3 p.m. 30.0

3 p.m. 5 p.m. 10.0

5 p.m. Midnight 5.0

Start time End time PercentageJune - August Saturday Utilization

Midnight Midnight 5.0

Start time End time PercentageJune - August Sunday Utilization

Midnight Midnight 5.0

Start time End time PercentageSeptember - December Cooling design to Weekday Utilization

Midnight 7 a.m. 5.0

7 a.m. 8 a.m. 50.0

8 a.m. 11 a.m. 100.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 23 of 31Dataset Name: NP High School.trc

Library Members

Schedules

11 a.m. noon 80.0

noon 1 p.m. 20.0

1 p.m. 3 p.m. 100.0

3 p.m. 5 p.m. 30.0

5 p.m. Midnight 5.0

Start time End time PercentageSeptember - December Saturday Utilization

Midnight Midnight 5.0

Start time End time PercentageSeptember - December Sunday Utilization

Midnight Midnight 5.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Off (0%) Simulation type: Reduced year

Start time End time StatusJanuary - December Cooling design to Sunday Equipment operation

Midnight Midnight Off

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 24 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB People Office Simulation type: Reduced year

Start time End time PercentageJanuary - December Cooling design Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 0.0

Start time End time PercentageJanuary - May Weekday Utilization

Midnight 8 a.m. 0.0

8 a.m. 9 a.m. 50.0

9 a.m. 3 p.m. 100.0

3 p.m. 4 p.m. 50.0

4 p.m. 5 p.m. 20.0

5 p.m. Midnight 0.0

Start time End time PercentageJune - August Weekday Utilization

Midnight 10 a.m. 0.0

10 a.m. 2 p.m. 30.0

2 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Weekday Utilization

Midnight 8 a.m. 0.0

8 a.m. 9 a.m. 50.0

9 a.m. 3 p.m. 100.0

3 p.m. 4 p.m. 50.0

4 p.m. 5 p.m. 20.0

5 p.m. Midnight 0.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight Midnight 0.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 25 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB School Infiltration Simulation type: Reduced year

Start time End time PercentageJanuary - May Cooling design to Weekday Utilization

Midnight 8 a.m. 100.0

8 a.m. 4 p.m. 25.0

4 p.m. Midnight 100.0

Start time End time PercentageJanuary - May Saturday Utilization

Midnight Midnight 100.0

Start time End time PercentageJanuary - May Sunday Utilization

Midnight Midnight 100.0

Start time End time PercentageJune - August Cooling design to Weekday Utilization

Midnight Midnight 100.0

Start time End time PercentageJune - August Saturday Utilization

Midnight Midnight 100.0

Start time End time PercentageJune - August Sunday Utilization

Midnight Midnight 100.0

Start time End time PercentageSeptember - December Cooling design to Weekday Utilization

Midnight 8 a.m. 100.0

8 a.m. 4 p.m. 25.0

4 p.m. Midnight 100.0

Start time End time PercentageSeptember - December Saturday Utilization

Midnight Midnight 100.0

Start time End time PercentageSeptember - December Sunday Utilization

Midnight Midnight 100.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 100.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 26 of 31Dataset Name: NP High School.trc

Library Members

Schedules

FB Fan Middle School Simulation type: Reduced year

Start time End time PercentageJanuary - May Cooling design to Weekday Utilization

Midnight 6 a.m. 0.0

6 a.m. 5 p.m. 100.0

5 p.m. Midnight 0.0

Start time End time PercentageHeating Design Utilization

Midnight Midnight 100.0

Start time End time PercentageJanuary - December Saturday to Sunday Utilization

Midnight 11 a.m. 0.0

11 a.m. 2 p.m. 0.0

2 p.m. Midnight 0.0

Start time End time PercentageJune - August Cooling design to Weekday Utilization

Midnight 10 a.m. 0.0

10 a.m. 2 p.m. 100.0

2 p.m. Midnight 0.0

Start time End time PercentageSeptember - December Cooling design to Weekday Utilization

Midnight 6 a.m. 0.0

6 a.m. 5 p.m. 100.0

5 p.m. Midnight 0.0

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 27 of 31Dataset Name: NP High School.trc

Library Members

Utility Rates

Fairbanks Oil and Elect Rates

Min Charge Start period

End periodMin demand

Fuel adjustment

kWh/kW flag

On peak

Electric demand Rate Cutoff

No

0

0.00

0

January

December

0Customer charge

10.790$

Min Charge Start period

End periodMin demand

Fuel adjustment

kWh/kW flag

On peak

Oil Rate Cutoff

No

0

0

0

January

December

0Customer charge

2.430$

Min Charge Start period

End periodMin demand

Fuel adjustment

kWh/kW flag

On peak

Electric consumption Rate Cutoff

No

0

30.00

0

January

December

0Customer charge

0.160$

Base Utilities

Domestic Hot Water Load

Domestic Hot WaterAvailable (100%)

100.00 MbhProcess hot water load

CommentsScheduleEnergy TypeHourly demandEnteringLeaving

°F°F

70.00120.00

Parking lot lights

Parking lot lights

0.10 kWElectricity

CommentsScheduleEnergy TypeHourly demandEnteringLeaving

°F°F

TRACE® 700 v6.2.7Project Name: North Pole High School

Page 28 of 31Dataset Name: NP High School.trc

APPENDIX H – TRACE 700 OUPUT

Total Building Consumption

ElectricityStand-alone Base Utilities

ElectricityReceptacles - Conditioned

ElectricityFans - Conditioned

ElectricityPumps

Oil

Space Heating Electricity

ElectricityLighting - Conditioned

Alt-3 Variable Speed PumpingAlt-2 VSD on AHU-2 and RET-2* Alt-1 Existing Systems

Energy10^6 Btu/yr

Proposed/ Base%

PeakkBtuh

Energy10^6 Btu/yr

Proposed/ Base%

PeakkBtuh

Energy10^6 Btu/yr

Proposed/ Base%

PeakkBtuh

1,090.9 10 593 1,090.9 100 593 1,090.9 100 593

649.7 6 111 649.7 100 111 672.6 104 111

5,998.4 54 7,319 5,998.4 100 7,319 5,998.4 100 7,195

621.6 6 91 621.6 100 91 194.8 31 64

1,402.7 13 584 1,356.0 97 577 1,356.0 97 577

350.1 3 256 350.1 100 256 350.1 100 256

914.3 8 205 914.3 100 205 914.3 100 205

11,027.7 10,981.0 10,577.1

Energy Cost Budget / PRM SummaryBy RS Consulting

Project Name: North Pole High School

Weather Data: Eielson AFB, AlaskaCity: North Pole AK

February 17, 2012Date:

Note: The percentage displayed for the "Proposed/ Base %"column of the base case is actually the percentage of thetotal energy consumption.

* Denotes the base alternative for the ECB study.

Total

Oil

Electricity

Alt-3 Variable Speed PumpingAlt-2 VSD on AHU-2 and RET-2* Alt-1 Existing Systems

Energy10^6 Btu/yr

Cost/yr$/yr

Energy10^6 Btu/yr

Cost/yr$/yr

Energy10^6 Btu/yr

Cost/yr$/yr

5,029.3 294,943 4,982.6 292,478 4,578.7 271,876

5,998.4 145,760 5,998.4 145,760 5,998.4 145,760

11,028 440,703 10,981 438,238 10,577 417,636

Total

Alt-3 Variable Speed PumpingAlt-2 VSD on AHU-2 and RET-2* Alt-1 Existing Systems

Number of hours heating load not metNumber of hours cooling load not met

00

00

00

North Pole High School

Dataset Name:

Project Name:

Energy Cost Budget Report Page 1 of 1

TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012

NP High School.trc

MONTHLY ENERGY CONSUMPTION

By RS Consulting

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalUtility

------- Monthly Energy Consumption -------

Alternative: 1 Existing Systems

Electric

1,473,572146,093141,341142,355116,66179,35275,77477,028126,455120,415152,943137,759157,394On-Pk Cons. (kWh)

476452453453453448448447453455476475470On-Pk Demand (kW)

Oil

59,9848,5397,0945,5202,4251,1481,1141,0982,6723,7047,4438,46010,766Cons. (therms)

BuildingSource

Floor Area

70,589

137,005

ft2

Btu/(ft2-year)

156,224

CO2SO2NOX

Energy Consumption Environmental Impact Analysis

76,537,672 lbm/year

78,944 gm/year

249,439 gm/year

Btu/(ft2-year)

Alternative: 2 VSD on AHU-2 and RET-2

Electric

1,459,902144,922140,168141,237115,57778,31574,76475,961125,199119,388151,744136,592156,035On-Pk Cons. (kWh)

473450451451451446446445451452473473468On-Pk Demand (kW)

Oil

59,9848,5397,0945,5202,4251,1481,1141,0982,6723,7047,4438,46010,766Cons. (therms)

BuildingSource

Floor Area

70,290

136,109

ft2

Btu/(ft2-year)

156,224

CO2SO2NOX

Energy Consumption Environmental Impact Analysis

75,827,632 lbm/year

78,212 gm/year

247,125 gm/year

Btu/(ft2-year)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 2 Monthly Energy Consumption report Page 1 of 2

MONTHLY ENERGY CONSUMPTION

By RS Consulting

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalUtility

------- Monthly Energy Consumption -------

Alternative: 3 Variable Speed Pumping

Electric

1,341,553134,869130,303130,905105,87368,54564,97766,504115,119109,261141,320127,612146,264On-Pk Cons. (kWh)

462437437437438433433433438439460462457On-Pk Demand (kW)

Oil

59,9848,5397,0945,5202,4251,1481,1141,0982,6723,7047,4438,46010,766Cons. (therms)

BuildingSource

Floor Area

67,705

128,352

ft2

Btu/(ft2-year)

156,224

CO2SO2NOX

Energy Consumption Environmental Impact Analysis

69,680,592 lbm/year

71,872 gm/year

227,092 gm/year

Btu/(ft2-year)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 3 Monthly Energy Consumption report Page 2 of 2

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 1 Existing Systems

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Lights28,352.8 34,000.8 29,903.4 32,672.0 13,250.8 12,459.4 13,812.8 29,903.4 32,672.0 31,232.2 319,617.031,343.2 30,014.3Electric (kWh)

173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7Peak (kW)

Misc. Ld10,119.5 12,250.0 10,652.1 11,717.3 825.2 750.2 862.7 10,652.1 11,717.3 11,184.7 102,568.011,184.7 10,652.1Electric (kWh)

75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0Peak (kW)

Energy Recovery Parasitics0.3 0.4 0.3 0.4 0.2 0.1 0.2 0.3 0.4 0.3 3.50.3 0.3Electric (kWh)

Cooling Coil Condensate0.0 0.0 0.0 0.0 0.0 0.6 0.7 0.0 0.2 0.0 1.60.0 0.0Recoverable Water (1000gal)

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Peak (1000gal/Hr)

Bsu 1: Parking lot lights28,560.0 31,620.0 16,200.0 16,740.0 16,200.0 16,740.0 16,740.0 16,200.0 26,040.0 25,200.0 267,900.031,620.0 26,040.0Electric (kWh)

60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0Peak (kW)

Bsu 2: Domestic Hot Water Load1,431.0 1,701.0 1,512.0 1,641.6 700.2 676.8 728.1 1,512.0 1,641.6 1,571.4 16,220.71,582.2 1,522.8Proc. Hot Water (therms)

9.0 9.0 9.0 9.0 9.0 2.7 2.7 2.7 9.0 9.0 9.0 9.0 9.0Peak (therms/Hr)

Cpl 1: No Cooling [Sum of dsn coil capacities=307.5 tons]

Hpl 1: Main Building Heating [Sum of dsn coil capacities=6,760 mbh]

Boiler - 001 [Nominal Capacity/F.L.Rate=6,760 mbh / 80.48 Therms] (Heating Equipment)7,228.2 6,393.5 3,240.8 2,463.0 1,097.8 1,113.9 1,147.5 2,264.7 4,861.0 6,053.5 52,218.59,126.8 7,227.8Oil (therms)

55.6 50.1 42.0 22.1 15.4 4.6 4.6 4.6 16.4 30.3 37.2 43.9 55.6Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)1,567.3 1,735.3 1,679.3 1,735.3 1,679.3 1,735.3 1,735.3 1,679.3 1,735.3 1,679.3 20,431.31,735.3 1,735.3Electric (kWh)

2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)4,543.0 5,029.7 4,867.5 5,029.7 4,867.5 5,029.8 5,029.7 4,867.5 5,029.8 4,867.5 59,221.25,029.7 5,029.7Electric (kWh)

6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8Peak (kW)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 1 Equipment Energy Consumption report page 1 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 1 Existing Systems

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Hpl 1: Main Building Heating [Sum of dsn coil capacities=6,760 mbh]

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)336.0 372.0 360.0 372.0 360.0 372.0 372.0 360.0 372.0 360.0 4,380.0372.0 372.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)5,101.8 5,648.4 5,466.2 5,648.4 5,466.2 5,648.4 5,648.4 5,466.2 5,648.4 5,466.2 66,505.35,648.4 5,648.4Electric (kWh)

7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6Peak (kW)

Heating water circ pump (Misc Accessory Equipment)9,926.4 10,990.0 10,635.5 10,990.0 10,635.5 10,990.0 10,990.0 10,635.5 10,990.0 10,635.5 129,398.210,990.0 10,990.0Electric (kWh)

14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8Peak (kW)

Hpl 2: Perimeter Heating [Sum of dsn coil capacities=1,991 mbh]

Boiler - 002 [Nominal Capacity/F.L.Rate=1,991 mbh / 23.71 Therms] (Heating Equipment)329.0 405.5 261.4 123.5 0.0 0.0 0.0 103.6 283.0 391.8 2,688.7391.2 399.7Oil (therms)

9.2 7.6 5.6 3.0 1.9 0.0 0.0 0.0 1.9 3.5 5.5 6.9 9.2Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)251.5 368.2 271.4 174.5 0.0 0.0 0.0 144.3 269.3 281.7 2,336.5284.4 291.3Electric (kWh)

0.7 0.7 0.7 0.7 0.7 0.0 0.0 0.0 0.7 0.7 0.7 0.7 0.7Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)728.8 1,067.4 786.6 505.8 0.0 0.0 0.0 418.2 780.6 816.5 6,772.6824.4 844.3Electric (kWh)

2.0 2.0 2.0 2.0 2.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0Peak (kW)

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)183.0 268.0 197.5 127.0 0.0 0.0 0.0 105.0 196.0 205.0 1,700.5207.0 212.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)818.5 1,198.7 883.3 568.0 0.0 0.0 0.0 469.6 876.6 916.9 7,605.6925.8 948.2Electric (kWh)

2.2 2.2 2.2 2.2 2.2 0.0 0.0 0.0 2.2 2.2 2.2 2.2 2.2Peak (kW)

Heating water circ pump (Misc Accessory Equipment)502.9 736.5 542.7 349.0 0.0 0.0 0.0 288.6 538.6 563.4 4,673.1568.9 582.6Electric (kWh)

1.4 1.4 1.4 1.4 1.4 0.0 0.0 0.0 1.4 1.4 1.4 1.4 1.4Peak (kW)

Hpl 3: Glycol System [Sum of dsn coil capacities=5,820 mbh]

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 1 Equipment Energy Consumption report page 2 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 1 Existing Systems

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Hpl 3: Glycol System [Sum of dsn coil capacities=5,820 mbh]

Boiler - 003 [Nominal Capacity/F.L.Rate=5,820 mbh / 69.29 Therms] (Heating Equipment)902.8 643.6 202.2 85.1 0.0 0.0 0.0 57.0 376.3 649.1 5,076.31,248.4 911.9Oil (therms)

8.4 7.1 5.6 2.2 1.0 0.0 0.0 0.0 1.1 3.5 4.6 5.9 8.4Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)937.8 785.1 425.7 273.1 0.0 0.0 0.0 172.7 799.2 887.6 6,899.61,325.3 1,293.2Electric (kWh)

2.0 2.0 2.0 2.0 2.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)2,718.1 2,275.8 1,233.9 791.6 0.0 0.0 0.0 500.6 2,316.5 2,572.6 19,998.83,841.5 3,748.3Electric (kWh)

5.8 5.8 5.8 5.8 5.8 0.0 0.0 0.0 5.8 5.8 5.8 5.8 5.8Peak (kW)

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)233.5 195.5 106.0 68.0 0.0 0.0 0.0 43.0 199.0 221.0 1,718.0330.0 322.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)3,052.4 2,555.7 1,385.7 888.9 0.0 0.0 0.0 562.1 2,601.4 2,889.0 22,458.74,313.9 4,209.4Electric (kWh)

6.5 6.5 6.5 6.5 6.5 0.0 0.0 0.0 6.5 6.5 6.5 6.5 6.5Peak (kW)

Heating water circ pump (Misc Accessory Equipment)2,500.7 2,093.7 1,135.2 728.3 0.0 0.0 0.0 460.5 2,131.2 2,366.8 18,398.93,534.1 3,448.5Electric (kWh)

5.4 5.4 5.4 5.4 5.4 0.0 0.0 0.0 5.4 5.4 5.4 5.4 5.4Peak (kW)

Sys 1: AHU-1 Main Building VAV

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=34,485 cfm / 35.83 kW] (Main Clg Fan)5,972.7 6,882.4 5,834.2 6,420.3 4,678.0 4,151.3 4,972.1 5,824.9 6,574.4 6,399.4 70,587.06,603.1 6,274.2Electric (kWh)

31.0 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=2,800 cfm / 1.32 kW] (Room Exhaust Fan)231.5 285.5 264.7 298.5 116.3 105.7 121.6 270.7 280.7 261.8 2,728.8246.9 244.9Electric (kWh)

1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3Peak (kW)

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=38,140 cfm / 23.31 kW] (Main Return Fan)2,286.8 2,651.2 2,242.0 2,615.2 2,313.3 1,988.4 2,263.4 2,316.7 2,510.7 2,457.1 28,582.82,530.2 2,407.7Electric (kWh)

16.1 18.5 18.5 18.5 18.5 19.2 19.0 18.5 18.5 18.5 18.5 18.5 19.2Peak (kW)

Sys 2: AHU-4 Gym System

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 1 Equipment Energy Consumption report page 3 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 1 Existing Systems

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Sys 2: AHU-4 Gym System

FC Centrifugal const vol [DsnAirflow/F.L.Rate=36,000 cfm / 25.68 kW] (Main Clg Fan)7,883.8 7,601.3 5,855.0 6,265.9 2,638.0 2,355.0 2,732.7 5,598.2 6,548.4 7,858.1 72,798.89,167.8 8,294.6Electric (kWh)

25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=38,100 cfm / 13.59 kW] (Main Return Fan)3,952.4 3,848.2 2,996.8 3,330.2 1,588.2 1,397.7 1,529.5 2,939.5 3,312.9 3,972.6 37,624.04,587.4 4,168.7Electric (kWh)

13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6Peak (kW)

Sys 3: AHU-6 Shops

FC Centrifugal const vol [DsnAirflow/F.L.Rate=26,420 cfm / 23.56 kW] (Main Clg Fan)4,956.7 5,376.2 4,619.5 5,153.1 2,590.3 2,313.7 2,677.4 4,687.2 5,503.0 5,425.8 55,280.66,480.4 5,497.2Electric (kWh)

23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=11,800 cfm / 5.57 kW] (Room Exhaust Fan)139.6 177.0 160.7 264.4 264.7 217.6 227.4 230.7 167.7 161.6 2,313.3152.5 149.3Electric (kWh)

1.0 1.0 1.0 1.0 2.1 4.9 4.7 4.7 2.3 1.0 1.0 1.0 4.9Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=26,420 cfm / 16.49 kW] (System Exhaust Fan)136.2 193.7 216.5 352.0 394.0 303.6 373.8 308.6 176.0 158.5 2,907.5148.5 145.9Electric (kWh)

1.0 1.3 1.7 2.1 2.9 5.8 6.4 6.7 3.4 1.6 1.0 1.0 6.7Peak (kW)

Sys 4: CH Vestibules

FC Centrifugal const vol [DsnAirflow/F.L.Rate=5,100 cfm / 0.48 kW] (Main Htg Fan)10.5 16.3 10.8 6.3 0.0 0.0 0.0 5.2 10.7 14.1 98.111.4 12.9Electric (kWh)

0.3 0.3 0.2 0.1 0.1 0.0 0.0 0.0 0.1 0.2 0.2 0.3 0.3Peak (kW)

Sys 5: AHU-2 Music

AF Centrifugal vav/inlet v [DsnAirflow/F.L.Rate=6,827 cfm / 7.34 kW] (Main Clg Fan)1,808.2 1,985.3 1,665.9 1,797.1 951.1 893.2 1,007.6 1,625.2 1,891.1 1,869.5 19,414.52,055.2 1,865.0Electric (kWh)

7.2 7.3 7.3 7.3 7.3 7.3 7.3 7.3 7.3 7.3 7.3 7.3 7.3Peak (kW)

AF Centrifugal vav/inlet v [DsnAirflow/F.L.Rate=7,418 cfm / 5.85 kW] (Main Return Fan)1,305.9 1,475.3 1,285.3 1,567.9 1,095.4 982.2 978.9 1,362.8 1,399.6 1,392.7 15,689.01,482.5 1,360.6Electric (kWh)

5.6 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8Peak (kW)

Sys 6: AHU-3 Auditorium

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 1 Equipment Energy Consumption report page 4 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 1 Existing Systems

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Sys 6: AHU-3 Auditorium

FC Centrifugal const vol [DsnAirflow/F.L.Rate=9,190 cfm / 6.56 kW] (Main Clg Fan)3,947.2 4,242.6 4,080.6 4,158.0 3,803.2 4,113.3 3,909.6 4,040.6 4,279.1 4,233.2 49,588.74,390.6 4,390.6Electric (kWh)

6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=9,503 cfm / 3.39 kW] (Main Return Fan)1,975.2 2,128.4 2,050.6 2,108.5 1,941.8 2,089.6 1,979.2 2,041.3 2,145.3 2,123.1 24,977.22,195.8 2,198.5Electric (kWh)

3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4Peak (kW)

Sys 7: AHU-7 - Kitchen

FC Centrifugal const vol [DsnAirflow/F.L.Rate=4,000 cfm / 3.57 kW] (Main Clg Fan)501.5 590.6 516.5 573.5 326.4 263.9 329.6 520.0 580.7 554.3 5,824.1539.3 527.9Electric (kWh)

2.9 3.6 2.9 3.6 3.6 2.9 2.9 3.5 3.6 3.6 3.6 3.6 3.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=5,000 cfm / 3.30 kW] (Room Exhaust Fan)509.1 620.6 551.3 622.6 243.7 172.9 245.0 562.7 596.6 566.1 5,782.8555.2 537.1Electric (kWh)

3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=4,000 cfm / 2.85 kW] (System Exhaust Fan)0.0 0.0 0.0 0.0 0.0 0.0 17.6 0.0 0.0 0.0 17.60.0 0.0Electric (kWh)

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.9Peak (kW)

Sys 8: AHU-5 Locker Rooms

FC Centrifugal const vol [DsnAirflow/F.L.Rate=8,800 cfm / 6.28 kW] (Main Clg Fan)1,663.7 1,619.6 1,277.4 1,422.9 681.7 605.0 701.0 1,294.2 1,408.5 1,494.0 15,876.82,120.7 1,588.1Electric (kWh)

6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=6,000 cfm / 2.83 kW] (Room Exhaust Fan)23.8 32.0 30.3 71.8 66.7 54.5 53.5 62.1 30.0 29.2 505.425.6 26.0Electric (kWh)

0.2 0.2 0.2 0.2 0.5 2.3 1.6 1.4 0.6 0.2 0.2 0.2 2.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=8,800 cfm / 2.35 kW] (System Exhaust Fan)20.0 26.3 24.4 47.9 51.1 41.6 41.6 41.6 26.4 24.0 388.321.7 21.7Electric (kWh)

0.2 0.2 0.2 0.2 0.3 0.6 0.6 0.7 0.4 0.2 0.2 0.2 0.7Peak (kW)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 1 Equipment Energy Consumption report page 5 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 2 VSD on AHU-2 and RET-2

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Lights28,352.8 34,000.8 29,903.4 32,672.0 13,250.8 12,459.4 13,812.8 29,903.4 32,672.0 31,232.2 319,617.031,343.2 30,014.3Electric (kWh)

173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7Peak (kW)

Misc. Ld10,119.5 12,250.0 10,652.1 11,717.3 825.2 750.2 862.7 10,652.1 11,717.3 11,184.7 102,568.011,184.7 10,652.1Electric (kWh)

75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0Peak (kW)

Energy Recovery Parasitics0.3 0.4 0.3 0.4 0.2 0.1 0.2 0.3 0.4 0.3 3.50.3 0.3Electric (kWh)

Cooling Coil Condensate0.0 0.0 0.0 0.0 0.0 0.6 0.7 0.0 0.2 0.0 1.60.0 0.0Recoverable Water (1000gal)

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Peak (1000gal/Hr)

Bsu 1: Parking lot lights28,560.0 31,620.0 16,200.0 16,740.0 16,200.0 16,740.0 16,740.0 16,200.0 26,040.0 25,200.0 267,900.031,620.0 26,040.0Electric (kWh)

60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0Peak (kW)

Bsu 2: Domestic Hot Water Load1,431.0 1,701.0 1,512.0 1,641.6 700.2 676.8 728.1 1,512.0 1,641.6 1,571.4 16,220.71,582.2 1,522.8Proc. Hot Water (therms)

9.0 9.0 9.0 9.0 9.0 2.7 2.7 2.7 9.0 9.0 9.0 9.0 9.0Peak (therms/Hr)

Cpl 1: No Cooling [Sum of dsn coil capacities=307.5 tons]

Hpl 1: Main Building Heating [Sum of dsn coil capacities=6,760 mbh]

Boiler - 001 [Nominal Capacity/F.L.Rate=6,760 mbh / 80.48 Therms] (Heating Equipment)7,228.2 6,393.5 3,240.8 2,463.0 1,097.8 1,113.9 1,147.5 2,264.7 4,861.0 6,053.5 52,218.59,126.8 7,227.8Oil (therms)

55.6 50.1 42.0 22.1 15.4 4.6 4.6 4.6 16.4 30.3 37.2 43.9 55.6Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)1,567.3 1,735.3 1,679.3 1,735.3 1,679.3 1,735.3 1,735.3 1,679.3 1,735.3 1,679.3 20,431.31,735.3 1,735.3Electric (kWh)

2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3 2.3Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)4,543.0 5,029.7 4,867.5 5,029.7 4,867.5 5,029.8 5,029.7 4,867.5 5,029.8 4,867.5 59,221.25,029.7 5,029.7Electric (kWh)

6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8 6.8Peak (kW)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 2 Equipment Energy Consumption report page 6 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 2 VSD on AHU-2 and RET-2

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Hpl 1: Main Building Heating [Sum of dsn coil capacities=6,760 mbh]

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)336.0 372.0 360.0 372.0 360.0 372.0 372.0 360.0 372.0 360.0 4,380.0372.0 372.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)5,101.8 5,648.4 5,466.2 5,648.4 5,466.2 5,648.4 5,648.4 5,466.2 5,648.4 5,466.2 66,505.35,648.4 5,648.4Electric (kWh)

7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6 7.6Peak (kW)

Heating water circ pump (Misc Accessory Equipment)9,926.4 10,990.0 10,635.5 10,990.0 10,635.5 10,990.0 10,990.0 10,635.5 10,990.0 10,635.5 129,398.210,990.0 10,990.0Electric (kWh)

14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8 14.8Peak (kW)

Hpl 2: Perimeter Heating [Sum of dsn coil capacities=1,991 mbh]

Boiler - 002 [Nominal Capacity/F.L.Rate=1,991 mbh / 23.71 Therms] (Heating Equipment)329.0 405.5 261.4 123.5 0.0 0.0 0.0 103.6 283.0 391.8 2,688.7391.2 399.7Oil (therms)

9.2 7.6 5.6 3.0 1.9 0.0 0.0 0.0 1.9 3.5 5.5 6.9 9.2Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)251.5 368.2 271.4 174.5 0.0 0.0 0.0 144.3 269.3 281.7 2,336.5284.4 291.3Electric (kWh)

0.7 0.7 0.7 0.7 0.7 0.0 0.0 0.0 0.7 0.7 0.7 0.7 0.7Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)728.8 1,067.4 786.6 505.8 0.0 0.0 0.0 418.2 780.6 816.5 6,772.6824.4 844.3Electric (kWh)

2.0 2.0 2.0 2.0 2.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0Peak (kW)

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)183.0 268.0 197.5 127.0 0.0 0.0 0.0 105.0 196.0 205.0 1,700.5207.0 212.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)818.5 1,198.7 883.3 568.0 0.0 0.0 0.0 469.6 876.6 916.9 7,605.6925.8 948.2Electric (kWh)

2.2 2.2 2.2 2.2 2.2 0.0 0.0 0.0 2.2 2.2 2.2 2.2 2.2Peak (kW)

Heating water circ pump (Misc Accessory Equipment)502.9 736.5 542.7 349.0 0.0 0.0 0.0 288.6 538.6 563.4 4,673.1568.9 582.6Electric (kWh)

1.4 1.4 1.4 1.4 1.4 0.0 0.0 0.0 1.4 1.4 1.4 1.4 1.4Peak (kW)

Hpl 3: Glycol System [Sum of dsn coil capacities=5,820 mbh]

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 2 Equipment Energy Consumption report page 7 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 2 VSD on AHU-2 and RET-2

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Hpl 3: Glycol System [Sum of dsn coil capacities=5,820 mbh]

Boiler - 003 [Nominal Capacity/F.L.Rate=5,820 mbh / 69.29 Therms] (Heating Equipment)902.8 643.6 202.2 85.1 0.0 0.0 0.0 57.0 376.3 649.1 5,076.31,248.4 911.9Oil (therms)

8.4 7.1 5.6 2.2 1.0 0.0 0.0 0.0 1.1 3.5 4.6 5.9 8.4Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)937.8 785.1 425.7 273.1 0.0 0.0 0.0 172.7 799.2 887.6 6,899.61,325.3 1,293.2Electric (kWh)

2.0 2.0 2.0 2.0 2.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)2,718.1 2,275.8 1,233.9 791.6 0.0 0.0 0.0 500.6 2,316.5 2,572.6 19,998.83,841.5 3,748.3Electric (kWh)

5.8 5.8 5.8 5.8 5.8 0.0 0.0 0.0 5.8 5.8 5.8 5.8 5.8Peak (kW)

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)233.5 195.5 106.0 68.0 0.0 0.0 0.0 43.0 199.0 221.0 1,718.0330.0 322.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)3,052.4 2,555.7 1,385.7 888.9 0.0 0.0 0.0 562.1 2,601.4 2,889.0 22,458.74,313.9 4,209.4Electric (kWh)

6.5 6.5 6.5 6.5 6.5 0.0 0.0 0.0 6.5 6.5 6.5 6.5 6.5Peak (kW)

Heating water circ pump (Misc Accessory Equipment)2,500.7 2,093.7 1,135.2 728.3 0.0 0.0 0.0 460.5 2,131.2 2,366.8 18,398.93,534.1 3,448.5Electric (kWh)

5.4 5.4 5.4 5.4 5.4 0.0 0.0 0.0 5.4 5.4 5.4 5.4 5.4Peak (kW)

Sys 1: AHU-1 Main Building VAV

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=34,485 cfm / 35.83 kW] (Main Clg Fan)5,972.7 6,882.4 5,834.2 6,420.3 4,678.0 4,151.3 4,972.1 5,824.9 6,574.4 6,399.4 70,587.06,603.1 6,274.2Electric (kWh)

31.0 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=2,800 cfm / 1.32 kW] (Room Exhaust Fan)231.5 285.5 264.7 298.5 116.3 105.7 121.6 270.7 280.7 261.8 2,728.8246.9 244.9Electric (kWh)

1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3Peak (kW)

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=38,140 cfm / 23.31 kW] (Main Return Fan)2,286.8 2,651.2 2,242.0 2,615.2 2,313.3 1,988.4 2,263.4 2,316.7 2,510.7 2,457.1 28,582.82,530.2 2,407.7Electric (kWh)

16.1 18.5 18.5 18.5 18.5 19.2 19.0 18.5 18.5 18.5 18.5 18.5 19.2Peak (kW)

Sys 2: AHU-4 Gym System

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 2 Equipment Energy Consumption report page 8 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 2 VSD on AHU-2 and RET-2

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Sys 2: AHU-4 Gym System

FC Centrifugal const vol [DsnAirflow/F.L.Rate=36,000 cfm / 25.68 kW] (Main Clg Fan)7,883.8 7,601.3 5,855.0 6,265.9 2,638.0 2,355.0 2,732.7 5,598.2 6,548.4 7,858.1 72,798.89,167.8 8,294.6Electric (kWh)

25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=38,100 cfm / 13.59 kW] (Main Return Fan)3,952.4 3,848.2 2,996.8 3,330.2 1,588.2 1,397.7 1,529.5 2,939.5 3,312.9 3,972.6 37,624.04,587.4 4,168.7Electric (kWh)

13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6Peak (kW)

Sys 3: AHU-6 Shops

FC Centrifugal const vol [DsnAirflow/F.L.Rate=26,420 cfm / 23.56 kW] (Main Clg Fan)4,956.7 5,376.2 4,619.5 5,153.1 2,590.3 2,313.7 2,677.4 4,687.2 5,503.0 5,425.8 55,280.66,480.4 5,497.2Electric (kWh)

23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=11,800 cfm / 5.57 kW] (Room Exhaust Fan)139.6 177.0 160.7 264.4 264.7 217.6 227.4 230.7 167.7 161.6 2,313.3152.5 149.3Electric (kWh)

1.0 1.0 1.0 1.0 2.1 4.9 4.7 4.7 2.3 1.0 1.0 1.0 4.9Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=26,420 cfm / 16.49 kW] (System Exhaust Fan)136.2 193.7 216.5 352.0 394.0 303.6 373.8 308.6 176.0 158.5 2,907.5148.5 145.9Electric (kWh)

1.0 1.3 1.7 2.1 2.9 5.8 6.4 6.7 3.4 1.6 1.0 1.0 6.7Peak (kW)

Sys 4: CH Vestibules

FC Centrifugal const vol [DsnAirflow/F.L.Rate=5,100 cfm / 0.48 kW] (Main Htg Fan)10.5 16.3 10.8 6.3 0.0 0.0 0.0 5.2 10.7 14.1 98.111.4 12.9Electric (kWh)

0.3 0.3 0.2 0.1 0.1 0.0 0.0 0.0 0.1 0.2 0.2 0.3 0.3Peak (kW)

Sys 5: AHU-2 Music

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=6,827 cfm / 6.26 kW] (Main Clg Fan)1,199.1 1,385.7 1,175.4 1,266.1 560.5 503.2 563.6 1,150.8 1,333.6 1,282.2 13,027.61,343.4 1,264.1Electric (kWh)

6.1 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3Peak (kW)

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=7,418 cfm / 4.99 kW] (Main Return Fan)747.8 875.9 748.7 842.9 418.3 362.2 385.5 752.8 838.6 807.0 8,405.7835.3 790.6Electric (kWh)

4.7 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0Peak (kW)

Sys 6: AHU-3 Auditorium

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 2 Equipment Energy Consumption report page 9 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 2 VSD on AHU-2 and RET-2

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Sys 6: AHU-3 Auditorium

FC Centrifugal const vol [DsnAirflow/F.L.Rate=9,190 cfm / 6.56 kW] (Main Clg Fan)3,947.2 4,242.6 4,080.6 4,158.0 3,803.2 4,113.3 3,909.6 4,040.6 4,279.1 4,233.2 49,588.74,390.6 4,390.6Electric (kWh)

6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=9,503 cfm / 3.39 kW] (Main Return Fan)1,975.2 2,128.4 2,050.6 2,108.5 1,941.8 2,089.6 1,979.2 2,041.3 2,145.3 2,123.1 24,977.22,195.8 2,198.5Electric (kWh)

3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4Peak (kW)

Sys 7: AHU-7 - Kitchen

FC Centrifugal const vol [DsnAirflow/F.L.Rate=4,000 cfm / 3.57 kW] (Main Clg Fan)501.5 590.6 516.5 573.5 326.4 263.9 329.6 520.0 580.7 554.3 5,824.1539.3 527.9Electric (kWh)

2.9 3.6 2.9 3.6 3.6 2.9 2.9 3.5 3.6 3.6 3.6 3.6 3.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=5,000 cfm / 3.30 kW] (Room Exhaust Fan)509.1 620.6 551.3 622.6 243.7 172.9 245.0 562.7 596.6 566.1 5,782.8555.2 537.1Electric (kWh)

3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=4,000 cfm / 2.85 kW] (System Exhaust Fan)0.0 0.0 0.0 0.0 0.0 0.0 17.6 0.0 0.0 0.0 17.60.0 0.0Electric (kWh)

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.9Peak (kW)

Sys 8: AHU-5 Locker Rooms

FC Centrifugal const vol [DsnAirflow/F.L.Rate=8,800 cfm / 6.28 kW] (Main Clg Fan)1,663.7 1,619.6 1,277.4 1,422.9 681.7 605.0 701.0 1,294.2 1,408.5 1,494.0 15,876.82,120.7 1,588.1Electric (kWh)

6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=6,000 cfm / 2.83 kW] (Room Exhaust Fan)23.8 32.0 30.3 71.8 66.7 54.5 53.5 62.1 30.0 29.2 505.425.6 26.0Electric (kWh)

0.2 0.2 0.2 0.2 0.5 2.3 1.6 1.4 0.6 0.2 0.2 0.2 2.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=8,800 cfm / 2.35 kW] (System Exhaust Fan)20.0 26.3 24.4 47.9 51.1 41.6 41.6 41.6 26.4 24.0 388.321.7 21.7Electric (kWh)

0.2 0.2 0.2 0.2 0.3 0.6 0.6 0.7 0.4 0.2 0.2 0.2 0.7Peak (kW)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 2 Equipment Energy Consumption report page 10 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 3 Variable Speed Pumping

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Lights28,352.8 34,000.8 29,903.4 32,672.0 13,250.8 12,459.4 13,812.8 29,903.4 32,672.0 31,232.2 319,617.031,343.2 30,014.3Electric (kWh)

173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7 173.7Peak (kW)

Misc. Ld10,119.5 12,250.0 10,652.1 11,717.3 825.2 750.2 862.7 10,652.1 11,717.3 11,184.7 102,568.011,184.7 10,652.1Electric (kWh)

75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0 75.0Peak (kW)

Energy Recovery Parasitics0.3 0.4 0.3 0.4 0.2 0.1 0.2 0.3 0.4 0.3 3.50.3 0.3Electric (kWh)

Cooling Coil Condensate0.0 0.0 0.0 0.0 0.0 0.6 0.7 0.0 0.2 0.0 1.60.0 0.0Recoverable Water (1000gal)

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Peak (1000gal/Hr)

Bsu 1: Parking lot lights28,560.0 31,620.0 16,200.0 16,740.0 16,200.0 16,740.0 16,740.0 16,200.0 26,040.0 25,200.0 267,900.031,620.0 26,040.0Electric (kWh)

60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0 60.0Peak (kW)

Bsu 2: Domestic Hot Water Load1,431.0 1,701.0 1,512.0 1,641.6 700.2 676.8 728.1 1,512.0 1,641.6 1,571.4 16,220.71,582.2 1,522.8Proc. Hot Water (therms)

9.0 9.0 9.0 9.0 9.0 2.7 2.7 2.7 9.0 9.0 9.0 9.0 9.0Peak (therms/Hr)

Cpl 1: No Cooling [Sum of dsn coil capacities=307.5 tons]

Hpl 1: Main Building Heating [Sum of dsn coil capacities=7,349 mbh]

Boiler - 001 [Nominal Capacity/F.L.Rate=7,349 mbh / 87.50 Therms] (Heating Equipment)7,270.5 6,418.0 3,246.8 2,463.0 1,097.8 1,113.9 1,147.5 2,264.7 4,877.5 6,081.8 52,449.59,198.0 7,270.2Oil (therms)

56.0 50.5 42.3 22.3 15.4 4.6 4.6 4.6 16.4 30.5 37.5 44.3 56.0Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)1,704.0 1,886.5 1,825.7 1,886.5 1,825.7 1,886.5 1,886.5 1,825.7 1,886.5 1,825.7 22,212.21,886.5 1,886.5Electric (kWh)

2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)4,939.0 5,468.1 5,291.8 5,468.2 5,291.8 5,468.2 5,468.1 5,291.8 5,468.2 5,291.8 64,383.05,468.2 5,468.2Electric (kWh)

7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4 7.4Peak (kW)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 3 Equipment Energy Consumption report page 11 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 3 Variable Speed Pumping

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Hpl 1: Main Building Heating [Sum of dsn coil capacities=7,349 mbh]

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)336.0 372.0 360.0 372.0 360.0 372.0 372.0 360.0 372.0 360.0 4,380.0372.0 372.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)5,546.5 6,140.7 5,942.7 6,140.7 5,942.6 6,140.7 6,140.7 5,942.7 6,140.7 5,942.7 72,302.26,140.7 6,140.7Electric (kWh)

8.3 8.3 8.3 8.3 8.3 8.3 8.3 8.3 8.3 8.3 8.3 8.3 8.3Peak (kW)

Variable Volume Heating Water Pump (Misc Accessory Equipment)650.3 481.3 196.9 300.4 131.7 121.2 137.8 275.7 305.8 485.7 4,639.0907.8 644.5Electric (kWh)

7.5 5.9 3.4 1.8 1.8 0.6 0.6 0.6 1.8 1.9 3.0 4.6 7.5Peak (kW)

Hpl 2: Perimeter Heating [Sum of dsn coil capacities=1,402 mbh]

Boiler - 002 [Nominal Capacity/F.L.Rate=1,402 mbh / 16.69 Therms] (Heating Equipment)286.7 381.1 255.4 123.5 0.0 0.0 0.0 103.6 266.5 363.5 2,457.7320.1 357.2Oil (therms)

7.6 6.8 5.1 3.0 1.9 0.0 0.0 0.0 1.9 3.2 5.0 6.3 7.6Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)177.0 259.3 191.1 122.9 0.0 0.0 0.0 101.6 189.6 198.3 1,645.1200.3 205.1Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)513.2 751.5 553.8 356.1 0.0 0.0 0.0 294.4 549.6 574.9 4,768.5580.5 594.5Electric (kWh)

1.4 1.4 1.4 1.4 1.4 0.0 0.0 0.0 1.4 1.4 1.4 1.4 1.4Peak (kW)

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)183.0 268.0 197.5 127.0 0.0 0.0 0.0 105.0 196.0 205.0 1,700.5207.0 212.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)576.3 844.0 622.0 399.9 0.0 0.0 0.0 330.7 617.2 645.6 5,355.0651.9 667.6Electric (kWh)

1.6 1.6 1.6 1.6 1.6 0.0 0.0 0.0 1.6 1.6 1.6 1.6 1.6Peak (kW)

Heating water circ pump (Misc Accessory Equipment)354.1 518.6 382.1 245.7 0.0 0.0 0.0 203.2 379.2 396.7 3,290.3400.5 410.2Electric (kWh)

1.0 1.0 1.0 1.0 1.0 0.0 0.0 0.0 1.0 1.0 1.0 1.0 1.0Peak (kW)

Hpl 3: Glycol System [Sum of dsn coil capacities=5,820 mbh]

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 3 Equipment Energy Consumption report page 12 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 3 Variable Speed Pumping

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Hpl 3: Glycol System [Sum of dsn coil capacities=5,820 mbh]

Boiler - 003 [Nominal Capacity/F.L.Rate=5,820 mbh / 69.29 Therms] (Heating Equipment)902.8 643.6 202.2 85.1 0.0 0.0 0.0 57.0 376.3 649.1 5,076.31,248.4 911.9Oil (therms)

8.4 7.1 5.6 2.2 1.0 0.0 0.0 0.0 1.1 3.5 4.6 5.9 8.4Peak (therms/Hr)

Heating water circ pump (Misc Accessory Equipment)937.8 785.1 425.7 273.1 0.0 0.0 0.0 172.7 799.2 887.6 6,899.61,325.3 1,293.2Electric (kWh)

2.0 2.0 2.0 2.0 2.0 0.0 0.0 0.0 2.0 2.0 2.0 2.0 2.0Peak (kW)

Boiler forced draft fan (Misc Accessory Equipment)2,718.1 2,275.8 1,233.9 791.6 0.0 0.0 0.0 500.6 2,316.5 2,572.6 19,998.83,841.5 3,748.3Electric (kWh)

5.8 5.8 5.8 5.8 5.8 0.0 0.0 0.0 5.8 5.8 5.8 5.8 5.8Peak (kW)

Cntl panel & interlocks - 0.5 KW (Misc Accessory Equipment)233.5 195.5 106.0 68.0 0.0 0.0 0.0 43.0 199.0 221.0 1,718.0330.0 322.0Electric (kWh)

0.5 0.5 0.5 0.5 0.5 0.0 0.0 0.0 0.5 0.5 0.5 0.5 0.5Peak (kW)

Fuel oil circulation pump (Misc Accessory Equipment)3,052.4 2,555.7 1,385.7 888.9 0.0 0.0 0.0 562.1 2,601.4 2,889.0 22,458.74,313.9 4,209.4Electric (kWh)

6.5 6.5 6.5 6.5 6.5 0.0 0.0 0.0 6.5 6.5 6.5 6.5 6.5Peak (kW)

Heating water circ pump (Misc Accessory Equipment)2,500.7 2,093.7 1,135.2 728.3 0.0 0.0 0.0 460.5 2,131.2 2,366.8 18,398.93,534.1 3,448.5Electric (kWh)

5.4 5.4 5.4 5.4 5.4 0.0 0.0 0.0 5.4 5.4 5.4 5.4 5.4Peak (kW)

Sys 1: AHU-1 Main Building VAV

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=34,485 cfm / 35.83 kW] (Main Clg Fan)5,972.7 6,882.4 5,834.2 6,420.3 4,678.0 4,151.3 4,972.1 5,824.9 6,574.4 6,399.4 70,587.06,603.1 6,274.2Electric (kWh)

31.0 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8 35.8Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=2,800 cfm / 1.32 kW] (Room Exhaust Fan)231.5 285.5 264.7 298.5 116.3 105.7 121.6 270.7 280.7 261.8 2,728.8246.9 244.9Electric (kWh)

1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3Peak (kW)

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=38,140 cfm / 23.31 kW] (Main Return Fan)2,286.8 2,651.2 2,242.0 2,615.2 2,313.3 1,988.4 2,263.4 2,316.7 2,510.7 2,457.1 28,582.82,530.2 2,407.7Electric (kWh)

16.1 18.5 18.5 18.5 18.5 19.2 19.0 18.5 18.5 18.5 18.5 18.5 19.2Peak (kW)

Sys 2: AHU-4 Gym System

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 3 Equipment Energy Consumption report page 13 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 3 Variable Speed Pumping

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Sys 2: AHU-4 Gym System

FC Centrifugal const vol [DsnAirflow/F.L.Rate=36,000 cfm / 25.68 kW] (Main Clg Fan)7,883.8 7,601.3 5,855.0 6,265.9 2,638.0 2,355.0 2,732.7 5,598.2 6,548.4 7,858.1 72,798.89,167.8 8,294.6Electric (kWh)

25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7 25.7Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=38,100 cfm / 13.59 kW] (Main Return Fan)3,952.4 3,848.2 2,996.8 3,330.2 1,588.2 1,397.7 1,529.5 2,939.5 3,312.9 3,972.6 37,624.04,587.4 4,168.7Electric (kWh)

13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6 13.6Peak (kW)

Sys 3: AHU-6 Shops

FC Centrifugal const vol [DsnAirflow/F.L.Rate=26,420 cfm / 23.56 kW] (Main Clg Fan)4,956.7 5,376.2 4,619.5 5,153.1 2,590.3 2,313.7 2,677.4 4,687.2 5,503.0 5,425.8 55,280.66,480.4 5,497.2Electric (kWh)

23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6 23.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=11,800 cfm / 5.57 kW] (Room Exhaust Fan)139.6 177.0 160.7 264.4 264.7 217.6 227.4 230.7 167.7 161.6 2,313.3152.5 149.3Electric (kWh)

1.0 1.0 1.0 1.0 2.1 4.9 4.7 4.7 2.3 1.0 1.0 1.0 4.9Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=26,420 cfm / 16.49 kW] (System Exhaust Fan)136.2 193.7 216.5 352.0 394.0 303.6 373.8 308.6 176.0 158.5 2,907.5148.5 145.9Electric (kWh)

1.0 1.3 1.7 2.1 2.9 5.8 6.4 6.7 3.4 1.6 1.0 1.0 6.7Peak (kW)

Sys 4: CH Vestibules

FC Centrifugal const vol [DsnAirflow/F.L.Rate=5,100 cfm / 0.48 kW] (Main Htg Fan)10.5 16.3 10.8 6.3 0.0 0.0 0.0 5.2 10.7 14.1 98.111.4 12.9Electric (kWh)

0.3 0.3 0.2 0.1 0.1 0.0 0.0 0.0 0.1 0.2 0.2 0.3 0.3Peak (kW)

Sys 5: AHU-2 Music

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=6,827 cfm / 6.26 kW] (Main Clg Fan)1,199.1 1,385.7 1,175.4 1,266.1 560.5 503.2 563.6 1,150.8 1,333.6 1,282.2 13,027.61,343.4 1,264.1Electric (kWh)

6.1 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3Peak (kW)

AF w/VFD Crit Zn Reset [DsnAirflow/F.L.Rate=7,418 cfm / 4.99 kW] (Main Return Fan)747.8 875.9 748.7 842.9 418.3 362.2 385.5 752.8 838.6 807.0 8,405.7835.3 790.6Electric (kWh)

4.7 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0Peak (kW)

Sys 6: AHU-3 Auditorium

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 3 Equipment Energy Consumption report page 14 of 15

EQUIPMENT ENERGY CONSUMPTIONBy RS Consulting

Alternative: 3 Variable Speed Pumping

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TotalEquipment - Utility

------- Monthly Consumption -------

Sys 6: AHU-3 Auditorium

FC Centrifugal const vol [DsnAirflow/F.L.Rate=9,190 cfm / 6.56 kW] (Main Clg Fan)3,947.2 4,242.6 4,080.6 4,158.0 3,803.2 4,113.3 3,909.6 4,040.6 4,279.1 4,233.2 49,588.74,390.6 4,390.6Electric (kWh)

6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6 6.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=9,503 cfm / 3.39 kW] (Main Return Fan)1,975.2 2,128.4 2,050.6 2,108.5 1,941.8 2,089.6 1,979.2 2,041.3 2,145.3 2,123.1 24,977.22,195.8 2,198.5Electric (kWh)

3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4Peak (kW)

Sys 7: AHU-7 - Kitchen

FC Centrifugal const vol [DsnAirflow/F.L.Rate=4,000 cfm / 3.57 kW] (Main Clg Fan)501.5 590.6 516.5 573.5 326.4 263.9 329.6 520.0 580.7 554.3 5,824.1539.3 527.9Electric (kWh)

2.9 3.6 2.9 3.6 3.6 2.9 2.9 3.5 3.6 3.6 3.6 3.6 3.6Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=5,000 cfm / 3.30 kW] (Room Exhaust Fan)509.1 620.6 551.3 622.6 243.7 172.9 245.0 562.7 596.6 566.1 5,782.8555.2 537.1Electric (kWh)

3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3 3.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=4,000 cfm / 2.85 kW] (System Exhaust Fan)0.0 0.0 0.0 0.0 0.0 0.0 17.6 0.0 0.0 0.0 17.60.0 0.0Electric (kWh)

0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.9 0.0 0.0 0.0 0.0 0.9Peak (kW)

Sys 8: AHU-5 Locker Rooms

FC Centrifugal const vol [DsnAirflow/F.L.Rate=8,800 cfm / 6.28 kW] (Main Clg Fan)1,663.7 1,619.6 1,277.4 1,422.9 681.7 605.0 701.0 1,294.2 1,408.5 1,494.0 15,876.82,120.7 1,588.1Electric (kWh)

6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3 6.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=6,000 cfm / 2.83 kW] (Room Exhaust Fan)23.8 32.0 30.3 71.8 66.7 54.5 53.5 62.1 30.0 29.2 505.425.6 26.0Electric (kWh)

0.2 0.2 0.2 0.2 0.5 2.3 1.6 1.4 0.6 0.2 0.2 0.2 2.3Peak (kW)

FC Centrifugal const vol [DsnAirflow/F.L.Rate=8,800 cfm / 2.35 kW] (System Exhaust Fan)20.0 26.3 24.4 47.9 51.1 41.6 41.6 41.6 26.4 24.0 388.321.7 21.7Electric (kWh)

0.2 0.2 0.2 0.2 0.3 0.6 0.6 0.7 0.4 0.2 0.2 0.2 0.7Peak (kW)

Project Name: TRACE® 700 v6.2.7 calculated at 04:08 PM on 02/17/2012North Pole High School

Dataset Name: NP High School.trc Alternative - 3 Equipment Energy Consumption report page 15 of 15

APPENDIX I – TREND LOG INFORMATION

34.7%

20.0%

25.0%

30.0%

35.0%

40.0%

20

40

60

80

100

OAT

RAT

MAT

OA %

North Pole High School - AHU-1 Trend Logsfor Friday Jan 13th, 2012

Percent Outside Air

Return Air Temp

Mixed Air Temp

12.9%

5.8%

0.0%

5.0%

10.0%

15.0%

-40

-20

0

20

05

:00

05

:30

06

:00

06

:30

07

:00

07

:30

08

:00

08

:30

09

:00

09

:30

10

:00

10

:30

11

:00

11

:30

12

:00

12

:30

13

:00

13

:30

14

:00

14

:30

15

:00

15

:30

16

:00

16

:30

17

:00

17

:30

18

:00

18

:30

19

:00

19

:30

20

:00

20

:30

21

:00

21

:30

22

:00

OA %

This Should Be Zero

80%

100%

120%

140%

60

70

80

90

100

110

120

130

140

150

160

170

180

190

200

OSA

HWS

HWR

total

North Pole HS - Boiler Plant - Jan 12 Through Jan 14

AHU OSA Dampers Open Boiler Plant Capacity

0%

20%

40%

60%

-50

-40

-30

-20

-10

0

10

20

30

40

50

60

21

:50

22

:50

23

:50

00

:50

01

:50

02

:50

03

:50

04

:50

05

:50

06

:50

07

:50

08

:50

09

:50

10

:50

11

:50

12

:50

13

:50

14

:50

15

:50

16

:50

17

:50

18

:50

19

:50

20

:50

21

:50

22

:50

23

:50

00

:50

01

:50

02

:50

03

:50

04

:50

05

:50

06

:50

07

:50

08

:50

09

:50

10

:50

11

:50

12

:50

13

:50

14

:50

15

:50

-10

0

10

20

2000

2500

3000

3500

4000

Sys Mbh

OSA

Poly. (Sys Mbh)

North Pole High Schoool - Heating Load For Tuesday Jan 17thBased on Heating Water Supply and Return Temperatures Assuming Constant Flow

-40

-30

-20

0

500

1000

1500

00

:00

00

:30

01

:00

01

:30

02

:00

02

:30

03

:00

03

:30

04

:00

04

:30

05

:00

05

:30

06

:00

06

:30

07

:00

07

:30

08

:00

08

:30

09

:00

09

:30

10

:00

10

:30

11

:00

11

:30

12

:00

12

:30

13

:00

13

:30

14

:00

14

:30

15

:00

15

:30

16

:00

16

:30

17

:00

17

:30

18

:00

18

:30

8

10

12

14

16

18

170

175

180

185

North Pole HS Boiler Plant - Jan 14th - All Boilers Enabled

Delta T

Heating Water Supply Temp

0

2

4

6

155

160

165

Heating Water Return Temp

APPENDIX J – FLOOR PLANS