34
Energie Saguenay Project Update and Preliminary Consultation Results June 3, 2015

Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Energie Saguenay Project Update and

Preliminary Consultation ResultsJune 3, 2015

Page 2: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Meeting Agenda

2

Time (pm)

Activity

7:00 Energie Saguenay Project update and results of the preliminary consultation process

7:30 Questions and discussions with participants

8:00 Break

8:15

Presentation of the consultation approach and Advisory Committee’s proposal for the natural gas liquefaction complex

8:30 Questions and discussions with participants

8:45 Advisory Committee registrations

9:00 Meeting Closure

Page 3: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Meeting Objectives

1. Provide an update of the Energie Saguenay

Project

2. Share the results of the preliminary consultation

3. Gather participant concerns and answer questions

4. Present the validated consultation approach

proposal, including the formation of the Advisory

Committee on the Natural Gas Liquefaction

Complex

3

Page 4: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Ethics

1. Being respectful in all aspects

2. Giving voice to all participants

3. Avoiding cross-fires

4. Trusting the process in place

4

Page 5: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

ÉNERGIE SAGUENAY PROJECT UPDATE AND

PRRLIMINARY CONSULTATION RESULTS

JUNE 3, 2015

Page 6: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Liquefaction, storage, and transshipment-export complex

– Port Saguenay site

– Project worth $7.5 billion (CAD)

– Yearly operational budget of $2.7 billion

– Yearly LNG production of 11 million metric tons

– Construction 2018 / Commissioning 2021

Project Summary

6

Page 7: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Project Features

3

• LNG liquefaction and storage facility:

– Hydropower-driven process

– 2 or 3 liquefaction trains

– 2 or 3 LNG tanks (maximum storage capacity of

400,000 m3)

• Loading dock (single vessel)

– 3 or 4 vessels per week

• New 650 km pipeline developed and managed by

an expert partner

• New ≈40 km hydropower line

Page 8: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Competitive investment and operations

spending:

– Natural gas surplus in Western Canada

– Location allowing access to world markets

– Low GHG emissions

– Northern climate improves process

effectiveness by 10-15%

– Lower capital costs than other similar projects

due to existing port infrastructures (Port

Saguenay and region)

– Qualified workforce

A World-Class Project

8

Page 9: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Economic Benefits for Saguenay and Quebec

9

• Large-scale project in Quebec:

• Job creation:

• 4,000 during construction

• 800 for operations, including 300 full-time jobs on site

• Business opportunities for regional organizations

• Reinforcement of existing gas supply

infrastructures in Quebec

• Gas supply source for regions

• Alternative energy source for enterprises

• Development of a new LNG sector

Page 10: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Community-Inclusive Project Development

Processus de participation avec les parties prenantes et les Premières Nations

Site rehabilitation

10

+

Social and environmental

assessment Construction Phase

Commissioning

Operations

Stakeholder and First Nation participation process

Page 11: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Major Milestones

Steps taken since June 2014

11

Preliminary studies and partnerships

Regulatory and environmental processes

Community relations

Page 12: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Preliminary Studies and Partnerships

• Confirmation of the Project’s technical and

commercial viability

• Capital expenditure (CAPEX) validation

• Preliminary technical studies

– Hydropower supply

– New gas pipeline

12

Page 13: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Preliminary Studies and Partnerships

• Preliminary discussions with potential

natural gas suppliers

• Preliminary contacts with European and

Asian markets

• Preliminary discussions with major

investors

• $12 million plus invested to date

13

Page 14: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Regulatory and Environmental Processes

• LNG export permit application with the

National Energy Board

• Preparation of the Project Notice

(description) for provincial and federal

authorities

• Base line studies of the site in preparation

of the impact study

14

Page 15: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Building Community Relations

• Preliminary consultation with regional

communities and First Nations

• Project Office / Headquarter established in

Saguenay

• Interactive Website and social media

platforms

15

Page 16: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

A PROJECT TO DEVELOP WITH THE COMMUNITY

PRELIMINARY CONSULTATION RESULTS

Page 17: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés. 17

Results of the Preliminary Consultation

• Consultation objectives and

stages

• Activities conducted

• Results:

– Issues and concerns associated with

the Project are gathered

– Consultation process validated by

communities

• Next steps

Page 18: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Phase I

Start dialogue

• Objective:

• Describe the Project and discuss it with communities

Phase II

Preliminary consultation framework

• Objective:

• Determine the terms of the preliminary consultation program and hear public concerns

Phase III

Implement preliminary consultation

• Objectives:

• Collect ideas, visions, needs and concerns from communities

• Validate the impacts and mitigating/optimizing actions

Phase IV

Validate, plan, and monitor

• Objectives:

• Validate the integration of concerns

• Plan the collaborative action programs

18

June 2014November 2014 to May

2015Fall 2015 to end 2016 2017

Consultation Process Objectives and Stages

Develop the Project with the community with public involvement from the start

Page 19: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés. 19

• Press conference

• 10 information meetings

(Phase I)

Start the dialogue

June 2014

• Over 25 meetings

• Over 150 persons and stakeholders met

• Present project and consultation process

• Validate minutes

• Discuss with First Nations

(Phase II)

Preliminary consultation framework, Sept. 2014 to

May 2015

• Identify issues and concerns

• Frequency

• Sensitivity

Analysis of comments

Completed Actions

Page 20: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

First Nations

20

• Committee formed involving

representatives from the

Mashteuiatsh, Essipit, and

Pessamit Innu communities

• Five discussion meetings held

• Collaboration Agreement signed

between GNL Quebec and the

three communities (26 May

2015)

Page 21: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

We hear all issues and concerns associated

with the Project

21

Page 22: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Issues Identified from Preliminary Consultation

22

Issues Key Concerns

Economic benefitsInvolvement of local businesses, prioritization of regional labor force, project investors

Marine transportationIncrease in marine traffic, share with other users, Marine Park, aquatic fauna

Visual integrationIntegration with landscape, share with tourism activities, noise, odors, light

Environmental impactGHG emissions, agricultural land, land ecosystems, shale gas, and site rehabilitation

Health & Safety Public and workers health risks (inhalation, fires, spills)

Construction Nuisances from construction

Page 23: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Discussion Period

23

Page 24: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Consultation process

validated by

communities

24

Page 25: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Proposed Consultation Process

• Advisory Committee on issues associated

with the natural gas liquefaction complex

• Advisory Committee on issues associated

with marine transportation

• Work groups on Project’s major issues

• Launch of a community liaison office

• Open-door days on Project notice and

impact study

25

Propriété de GNL Québec. Tous droits réservés

Page 26: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés. 26

Consultation Process - Suggestions and

Comments

Community Relations

Respect the community and follow up on concerns

Involve organizations and stakeholders early in Project development

Assess impacts based on life-cycle approach and sustainable development analysis

Involve concerned and interested people

Page 27: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Consultation Process - Suggestions and

Comments

27

Advisory Committees

Integrate intergenerational aspects into the consultation approach

Actively involve communities to foster the development of regional LNG expertise

Collaborate with community stakeholders

Marine Transportation Committee to consider that the zone of influence extends to Escoumins

Page 28: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

VALIDATED CONSULTATION PROCESS

Page 29: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Consultation Process Framework

29

Propriété de GNL Québec. Tous droits réservés

Advisory Commitee on the Natural GasLiquefaction Complex

Objective:Discuss issues and concerns associated with the liquefaction complex at Port Saguenay

Proposed composition:• Facilitator• GNL Québec• Representative:

• Municipalities• Citizens• First Nations• Tourism associations• Environmental groups• Socioeconomic groups

Advisory Commitee on MarineTransportation

Objective:Discuss issues and concerns associated with Marine transportation

Proposed composition:• Facilitator• GNL Québec• Representative:

• Municipalities• Citizens• First Nations• Tourism associations• Environmental groups• Socioeconomic groups• Marine security groups

Work Groups on Project’sMajor Issues

Objective:• Discuss major issues in details with

stakeholders• Gather information and point of

view of experts

Composition according to the subject:• Experts ans scientists, etc. • Stakeholders

Page 30: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Advisory Committee on the Natural Gas

Liquefaction Complex

The Committee’s specific objectives are:

1. Establish clear and transparent communications between GNL Quebec and stakeholders

2. Discuss Project progress and the results of studies

3. Encourage stakeholders to express their concerns regarding the Project

4. Take concerns into consideration in Project development

5. Make sure mitigating actions and commitments are followed up

30

Page 31: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Proposed composition - Advisory Committee on

the Natural Gas Liquefaction Complex

31

SUGGESTED CATEGORIES NUMBER

Citizens 4

Environmental groups 2

Municipalities and municipal organizations 2

Tourism and sector users 2

Training and educational institutions 1

Socioeconomic organizations 2

Youth representative 1

Fire safety 1

First Nation representative 1

Total 16

Page 32: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Workgroups

The makeup of a workgroup includes resource persons

and/or experts who can analyze the specific issues

identified by the Committee and elaborate

recommendations.

32

Examples of workgroups

Local employmentMarine biologySustainable development LNG Complex safetyLandscape integration/visual impact

Page 33: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

• Committee startup meeting and

elaboration of the work plan

• Inauguration of the Saguenay office

• Preliminary meetings and formation of the

Marine Transportation Committee

33

Next Consultation Stages

Page 34: Energie Saguenay Project Update and Preliminary ......2015/06/01  · Project 2. Share the results of the preliminary consultation 3. Gather participant concerns and answer questions

Propriété de GNL Québec. Tous droits réservés.

Discussion Period

34