Enduring Offtake Arrangements including an Off-Peak Interruptible Service. Peter Bolitho. Key drafting points. ‘Bolted-on’ to main proposal Off-peak Interruptible service is simply another product that can be used along side the other exit capacity products. - PowerPoint PPT Presentation

Citation preview

Page 1: Enduring Offtake Arrangements including an Off-Peak Interruptible Service

Enduring Offtake Arrangementsincluding an Off-Peak Interruptible Service

Peter Bolitho

Page 2: Enduring Offtake Arrangements including an Off-Peak Interruptible Service

Page 2Theme Date Department

Key drafting points

‘Bolted-on’ to main proposal Off-peak Interruptible service is simply another product that

can be used along side the other exit capacity products. Off-Peak Interruptible service capacity definition and

booking concept introduced (different to current UNC which relies on defining firm or interruptible status)

Proved too complex and illogical? to have failure to interrupt charges along side overrun charges.

Page 3: Enduring Offtake Arrangements including an Off-Peak Interruptible Service

Page 3Theme Date Department

Key Features

Existing Registered Users can opt (in full or part) to book Off-Peak Interruptible capacity at initialisation of the new regime.

Enduring Capacity can be exchanged for Off-Peak Interruptible Capacity from the relevant capacity reduction date where the appropriate reduction notice has been given.

Otherwise Off-Peak capacity applications/reductions are made on giving [one months] notice.

NGG obliged to make available Off-Peak Interruptible capacity up to the Maximum Supply Point Offtake Rate x 24 less any Enduring Exit Capacity holdings.

The Maximum Supply Point Offtake Rate is the instantaneous rate of offtake (in kW) which NG NTS determines it is feasible to make gas available for offtake. MSPOR may be specified in NExA or connection agreements.

Page 4: Enduring Offtake Arrangements including an Off-Peak Interruptible Service

Page 4Theme Date Department

Key Features 2

Existing entitlement rolls forward on daily basis. Any holdings of Annual, Daily Firm and Daily Interruptible

would reduce the effective Off-Peak Interruptible capacity on any day – Off-Peak interruptible capacity is effectively the ‘swing’ amount.

NG NTS required to publish by 15:00 hours forecast total system demand as a percentage of the 1 in 20 demand.

When forecast is >80% all Off-Peak Interruptible Capacity entitlements shall be withdrawn.

Users may still be able to acquire Daily Firm Capacity or Daily Interruptible Capacity as an alternative.

User obliged to apply for Enduring Capacity in the July application widow at a level not less than the maximum overrun quantity in the last 12 months.

Page 5: Enduring Offtake Arrangements including an Off-Peak Interruptible Service

Page 5Theme Date Department

Release of Off-Peak Interruptible Capacity

Max SPOR x 24Baseline ?

CapacityHolding

Enduring Capacity

Daily capacity (and subsequentannual capacity purchases)

Off-Peak Capacity thatcan be applied for