    The purpose of this procedure is to establish control of

    incoming and outgoing documents at the project site. Tofacilitate expeditious controlled distribution of

    documents, and to ensure that drawings used by

    Construction Field Operations are the current issues or

    latest revisions for implementation.

    This procedure covers the control of incoming and

    outgoing project documents, which includes

    construction drawings, specifications, standardreferences, construction procedures, memorandums,

    instruction letters, communications, correspondences,

    and other applicable documents, during the

    construction of the project, handled by Field

    Engineering Support Group at the project sites.

  • 7/30/2019 END 3 001 Project Documentation

    3/24

    DEFINITIONS

    IFC - Issued for Construction drawings.

    REFERENCES

    EN ISO 9002 : 1994

    4.5 Document and data control

    PROJECT MANAGER

    Has overall management responsibility for the Project

    Construction Operation including the administrative supervision

    of the Field Engineering Support Group. All project

    communications, correspondences, document transmittals are

    passed through for approval and signing of the Project Manager.

  • 7/30/2019 END 3 001 Project Documentation

    4/24

    (continuation)

    PROJECT SITE ENGINEERING MANAGERSUPERINTENDENT or SUPERVISING ENGINEER

    Supervise project documentation works. Determines

    standard distribution procedures and responsible for the

    satisfactory distribution and control of Documents in the

    project site.PROJECT DOCUMENT CONTROLLER

    Receiving, recording, filing, reproduction, distribution,

    updating, protection and return of clients issued project

    documents upon completion of the project in accordance

    with the requirements of the Contract.

    File in controlled manner all identified documents

    collected by Engineering, Materials, Quality Control,

    Project Control, Contracts Departments and from the

    Managers file for retention after completion of the project.

  • 7/30/2019 END 3 001 Project Documentation

    5/24

    (continuation)

    PROJECT DEPARTMENT HEADS

    Responsible for the collection of Project Active Files, for

    documents mentioned in Clause 6.2.9 in their respectivedepartments for archiving.

    Responsible fro the developing, monitoring and control of

    Controlled project documents for any necessary secondary

    distribution within their respective department, referred to in

    Clauses 6.4.2.1. Procedure No. END-3-010, Central

    Documentation Control.

    OVERVIEW

    Field Engineering Support Group shall maintain the project

    work site, copies of all Issued for Construction (IFC) drawings,

    specifications, standard references, construction procedures,

    memorandums, instruction letters, vendors data, instruction

    manuals, contract documents, addenda, communication and

    other applicable correspondences.

  • 7/30/2019 END 3 001 Project Documentation

    6/24

    (continuation)

    RECEIVING, RECORDING, FILING AND DISTRIBUTION

    Project Document Controller acknowledges receipt of

    document from Costumer by signing the incoming transmittal.The documents may consists IFC drawings, specifications and

    other construction documents, stamp date and records in

    Form No. END-4-001B, Project Management Control System

    Engineering Drawing / Document Register (Incoming)

    The register includes the item number, transmittal number of

    Costumer, date received, item description, drawing/referencenumber, sheet number, revision number, print/sepia, number of

    copies, index number, plant/unit area, remarks column for

    additional information. This ensure accurate maintenance of

    master distribution and transmittal status at all times and

    also provide easy identification and quick access to the

    documents. Project Document Controller will reproduce copies for

    distribution and shall distribute the documents to recipient.

    Document Controller will produce Log Book and write on log

    book pages the following information, as formatted below

    (next page).

  • 7/30/2019 END 3 001 Project Documentation

    7/24

    The above format will be used by the Document Controller whenever he

    distribute primary copies of documents at the project site. This is tominimize use of Transmittal Form No. QAD-4-202

    Project Document Controller will distribute the documents to field

    Operations through the office of the respective discipline Field

    Department Heads. The Field Department Heads or his designatedrepresentatives shall indicate his name & signature on the

    Receivers column on the DOCUMENTS LOG BOOK upon receipt of

    the documents. This is to ensure that the documents are not

    issued to the field operation without knowledge.

    (continuation)

    ITEM No. ITEM DESCRIPTION REFERENCE No. DATE Distrbt.ORIGINATOR

    Name/Sign

    DATE RECEIVERECEIVER

    Name/Sign

    REMARK

    Form No. END-4-001H

  • 7/30/2019 END 3 001 Project Documentation

    8/24

    (continuation)

    Conflict between drawings, specifications or standards are brought

    to the prompt attention of the Costumer Representatives by the

    Field Engineering Manager / Superintendent or Supervising

    Engineer. The Costumer representative on resolving the conflict

    and shall advise MMG, in writing.

    Sepias and photocopies received from the Costumer

    Representatives are kept for ready reference and reproduction.

    All documents are kept in separate room, neatly filed on sticks or in

    drawing cabinets. Documents shall be filed in a sequencecorresponding to a key index, per discipline, on a respective plant

    area.

    Documents transmitted prior to the effective contract dates are

    likewise handled as provided above.

    Upon Project Completion, all technical data, standards,

    specifications, design, drawings and the like, furnished by theCostumer, shall be returned to the Costumer, if specified in the

    Contract. Alternatively, such documents may be destroyed or

    disposed of in accordance with individual costumer instruction /

    contractual requirement.

  • 7/30/2019 END 3 001 Project Documentation

    9/24

    (continuation)

    PROJECT ACTIVE FILES

    (Form No. END-4-001C) for archiving shall be maintained in a

    secured environment at the Dammam warehouse or DMSYard. The period of retention may vary in accordance with

    contractual warranty periods, but shall not be less than two

    (2) years following the project completion date. An

    indeterminate retention period may be required in relation to

    unresolved claims.

    Documents to be considered for archiving may include but

    are not restricted to the following:

    MATERIAL FILES

    Includes Material receiving report, Requisition Slip, PurchaseOrder, Over/Short Damage Report, Weekly Material Check

    Report, Costumer Supplied Material Receiving Report, materials

    status log. And etc..

  • 7/30/2019 END 3 001 Project Documentation

    10/24

    (continuation)

    ENGINEERING FILES

    Includes Site Query, Work Estimates, As-Built drawings, Field Work

    Directives, Change Notice, Avoid Verbal Orders, letters on claims,

    Change request, Calculations, specifications, standard drawings,

    and etc

    QUALITY CONTROL FILES

    Includes Inspection and Test Reports, Certification Dossiers,Control Procedures, Welding Report and etc

    PROJECT CONTROL FILES

    Includes Foreman Daily Progress Report, Daily Report to Costumer,

    Weekly Report, Monthly Narrative Report, Construction Schedules

    (All Construction Schedules, S-Curve, CPM, manpower & EquipmentHistograms developed from start to the last phase of the project)

    Change Order Settlement, Progress Report, Billing, Timesheets and

    etc

  • 7/30/2019 END 3 001 Project Documentation

    11/24

    (continuation)

    CONTRACT FILES

    o Includes Field Work Directives, Change Orders, Settlement of

    Change Orders, Subcontractor Contract and Job Specifications.

    PROJECT MANAGER SECRETARY FILES

    o Includes incoming and outgoing letter, Facsimiles, Memos,

    Minutes of meeting and etc..

    OTHER COMMUNICATION AND CORRESPONDENCES

    o Which are vital to unresolved Change Orders or Claims and

    reference information beneficial to any unexpected

    requirements.

    o Respective Project Department Head shall collect all the above

    respective documents in their custody and make corresponding

    records using Form No. END-4-001C (Project Active FileRecord). This files shalll be sequence in the storage boxes in

    accordance with the indices and label (END-4-010U) place on

    the side of the box with the corresponding box number, then

    transmit the record to the Project Document Controller who will

    prepare the transmittal for archiving.

  • 7/30/2019 END 3 001 Project Documentation

    12/24

    (continuation)

    o For large volume of Project Active Files, documents

    storage boxes shall be placed inside a conex vancontainer, properly identified or marked for

    identification of a Project Name, Contract Number

    and date delivered for archive. The conex van container

    shall be stored at Dammam Maintenance Shop (DMS)

    storage yard.o Project Document Controller shall prepare the Master

    List of the Project Active File and a copy forwarded to

    Central Documentation Control Section for record

    control.

    o Field Engineering to co-ordinate with ProjectWarehouse who will in turn take-over the

    responsibility for transporting the Conex Van

    containing the Project Active Files to DMS,

  • 7/30/2019 END 3 001 Project Documentation

    13/24

    (continuation)

    SUPERSEDED DOCUMENTS

    Project Document Controller will stamp SUPERSEDED mark on

    superseded drawings and/or documents, and update the ProjectManagement Control System (Form No. END-4-001B)

    Project Document Controller reproduce a copy of the current issue

    or latest revision drawing or documents and distribute to recipient.

    All superseded drawings and documents are segregated from the

    current issues files by the corresponding field discipline

    responsible Field Supervisor or Foreman using the drawings or

    documents. Superseded drawings or documents are either being

    kept by field operation for further reference or are returned to the

    Project Document Controller for safe keeping, where appropriate.

    Superseded drawings and documents are filed in separate cabinet

    for later reference, if demanded.

    A Computer database or appropriate computer program is

    implemented by Field Engineering Support Group where the

    contract requires the application of a computerized program for

    handling documents and for ensuring accurate maintenance of

    master distribution status.

    S O CO O O SS O C CO O

  • 7/30/2019 END 3 001 Project Documentation

    14/24

    DISTRIBUTION AND CONTROL OF ISSUED PROJECT CONTROLLED

    DOCUMENT USED BY FIELD OPERATION DEPARTMENTS

    Field Discipline Department Heads or his designated

    representative shall allocate Control Copy Number for identified

    secondary distribution Controlled Copy Holders within his

    department. Control Copy Number for secondary distributioncopy holder shall be prefix to the Primary Controlled Copy Holder

    Control Number, Below are examples of assigning control

    numbers, which will vary per discipline, types of drawings of

    documents, Department Heads shall assign appropriate control

    number.

    Example1

    PQAM-4CR01-QCP-03/01

    PQAM = Project Quality Assurance Manual

    4CR01-QCP = Manual Number

    O3 = Primary Controlled Copy Holder No. 3

    O3/O1 = Secondary Distribution Controlled Copy

    Holder No. 1

    ( ti ti )

  • 7/30/2019 END 3 001 Project Documentation

    15/24

    (continuation)

    Example2

    PD-ISO-03/01

    PD =

    Piping Drawing (changes with discipline)

    ISO =

    Isometric (changes with type drawing)

    O3 =

    Primary Controlled Copy Holder No. 3

    O3/O1 =

    Control No. of Number One Secondary

    Distribution Controlled Copy Holder

    Note : All piping isometric drawings covered by the above Control Numberwill be change in Form No. END-4-001G

    Accomplished Form No. END-4-001G and outgoing documents log bookwill be used when distributing it to Secondary Controlled CopyHolder together with all covered drawings and/or documents.

    ( ti ti )

  • 7/30/2019 END 3 001 Project Documentation

    16/24

    (continuation)

    Field Discipline Department Heads or his designated

    representative shall register in Form No, END-4-001G Field

    Operation Secondary Controlled Documents Register (Incoming/

    Outgoing) all controlled documents requiring secondary

    distribution. Registration of documents and/or drawings dataincludes names of primary & secondary copy holders controlled

    copy holders number, document or drawings reference details,

    issue dates, and etc.. Copies of documents and/or drawings shall

    be stamped Controlled Copy (sample below) in red ink and the

    Copy Holder Name, Number & Date, written on the space

    provided thereof.

    After secondary distribution of drawings, documents and specifications to fieldoperation retrieval of these documents, drawings and specifications areresponsibility of construction operation or designated person who will issued thesecondary copy.

    MOHAMMAD AL-MOJIL GROUPCONTROLLED COPY

    COPY HOLDER NAME : _____________

    COPY NO. : _____________________

    DATE ISSUE : ____________________

    Sample Stamp

    ( ti ti )

  • 7/30/2019 END 3 001 Project Documentation

    17/24

    (continuation)

    Upon completion of the project. Secondary Copy Holders of

    controlled documents shall return all issued controlled copies to

    their respective Department Heads or Designated Representative.

    Subsequent steps to be undertaken by the Designated

    Representative, refer to Clause 6.2.8 & 6.2.10 for proper dispositionof project document. Also refer Procedure END-3-010 in conjunction

    to procedure END-3-001 for other related document control

    information.

    OUTGOING DOCUMENTS

    (To Client, Subcontractor & other Parties)Project Document Controller will register in PROJECT TRANSMITTAL

    CONTROL LOG (Form No. END-4-001D, Rev 1, 27 Feb. 1996) all

    outgoing document forwarded to Client, Subcontractor or other

    parties. The Project Transmittal Control Log includes the Item

    Number, Transmittal Number, Date Issued, Issued to (recipient

    name), signature of receiving person and description or remarks arenoted in the space provided for particulars. This is to ensure that all

    outgoing documents issued to Client, subcontractors and other

    parties are fully documented and controlled.

  • 7/30/2019 END 3 001 Project Documentation

    18/24

    START

    PROJECT SITE ENGINEERING

    PROJECT DOCUMENTATION

    CONTROL

    (END-3-001)

    PROJECT DOCUMENT CONTROLLER

    AKNOWLEDGE RECEIPT

    OF DOCUMENT

    FROM COSTUMER

    STAMP DATE OF ISSUE

    RECORD IN REGISTER

    (END-4-001B)

    PROJECT DOCUMENT CONTROLLER

    REPRODUCE SECONDARY

    COPIES AND DISTRIBUTE

    (END-4-001H)

    PROJECT DOCUMENT CONTROLLER

    PROJECT

    ACTIVE FILES

    (COMPLETED PROJECTS)

    PROJECT DOCUMENT CONTROLLER

    ORIGINAL PROJECT DOCUMENTS

    ISSUED BY

    COSTUMERS

    SUPERSEDED DRAWINGS /

    DOCUMENTS IS REPLACED

    WITH CURRENT ISSUES

    PROJECT DOCUMENT CONTROLLER

    FILE ORIGINAL DOCUMENT

    IN ORDER / MAINTAIN IN

    SECURED ROOM/CABINET

    PROJECT DEPARTMENT HEADS

    COLLECT / RECORD / FILE IN

    STORAGE BOX

    (END-4-001C)

    PROJECT DOCUMENT CONTROLLER

    PREPARES

    TRANSMITTAL

    MASTER LIST

    COORDINATE WAREHOUSE FOR

    TRANSPORT ARCHIVE BOXES

    TO STORAGE WAREHOUSE/YARD

    PROJECT DOCUMENT CONTROLLER

    PROJECT DOCUMENT CONTROLLERPROJECT DOCUMENT CONTROLLER

    A1END

  • 7/30/2019 END 3 001 Project Documentation

    19/24

    PROCEDURE FOR PROJECT DOCUMENTATION CONTROL

    ACKNOWLEDGE RECEIPT OF DOCUMENT / RECORDING

    Project Document Controller will acknowledge receipt of documents

    from Costumer by signing the incoming Costumer generated

    Transmittal. The documents may consist of IFC drawings,

    specifications and other construction documents. He will stamp date

    and record on Form END-4-001B Document Register (Incoming)

    REPRODUCTION / DISTRIBUTIONReproduce secondary copies for distribution. Distribute secondary

    controlled reproduced copies to Field Operations / Recipients

    through the office of the respective discipline Field Department

    Heads.

    FILING

    File all original documents in secure room, neatly retained on sticks

    or in drawing cabinets, in orderly sequence corresponding to a key

    index, discipline and plant areas.

    ( ti ti )

  • 7/30/2019 END 3 001 Project Documentation

    20/24

    (continuation)

    SUPERSEDED DRAWINGS / DOCUMENTS

    Reproduce secondary copies of the current issue or latest revision

    drawing and or documents for distribution. Remove superseded

    drawings / documents from the file and replace with the current issues.

    Distribute secondary controlled copies to Field Operation / Recipients

    through the office of the respective discipline. Field Department Heads.

    The distribution shall be controlled in accordance with PFE (05)

    Control of Technical Literature used Form No. END-4-001H (Outgoing

    Document Log Book) to record distribution.

    Stamp SUPERSEDED mark on all superseded drawings and /or

    documents and update the Engineering Drawing / Document Register

    (Form No. END-4-001B)

    File all superseded original drawings and documents in a separate

    cabinet in orderly sequence corresponding to a key index., discipline or

    plant areas for future reference, or whenever demanded.

    All superseded secondary copies of drawings / documents issued tofield Operations (FO) should be removed from the latest issue files by

    the corresponding field discipline responsible Field Supervisor or

    Foreman and destroyed.

    ( ti ti )

  • 7/30/2019 END 3 001 Project Documentation

    21/24

    (continuation)

    ORIGINAL PROJECT DRAWINGS / DOCUMENT ISSUED BY COSTUMER

    Upon project completion, all original copies of documents furnished by

    the Costumer during the life of the project shall be returned to the

    Costumer. If specified in the Contract. Alternately, such documents may

    be destroyed or disposed of in accordance with the individual costumer

    instruction / contractual requirement.

    PROJECT ACTIVE FILES

    Project Active Files on completed project considered for archive may

    include, but not limited to the following:

    Material Files

    Engineering Files

    Quality Control Files

    Contract Files

    Project Managers Files

    Other Internal / external correspondences & communications.

    (continuation)

  • 7/30/2019 END 3 001 Project Documentation

    22/24

    (continuation)

    Respective Project Department Heads (PD) shall collect all the above

    respective documents in their custody and make corresponding records

    using Form END-4-001C Project Active File Record and shall file in

    orderly manner in storage boxes in accordance with the corresponding

    box number.

    Endorse respective Project Active Files records to project Document

    Controller who will prepare the transmittal for archiving.

    Project Document Controller prepares the Transmittal and master list

    address to Central Documentation Section in Dammam for record

    control and advise for the archiving at MMG Central Archive. For large

    volume of Project Active Files, documents storage boxes shall beplaced inside container van, properly identified or marked for

    identification of Project Name, Contract Number and date delivered for

    archive. The container van shall be stored at Dammam Central

    Warehouse (DMS) storage yard.

    Field Engineering shall coordinate with Project Warehouse who will in

    turn take-over the responsibility for transporting the container vancontaining th Project Active Files to DMS storage yard. Copy of the

    Document Master List is also retain inside the Container van.

    CWD transport the boxes to Dammam warehouse archive room or the

    Container Van with the Project Active Files to DMS storage yard.

  • 7/30/2019 END 3 001 Project Documentation

    23/24

    Mohammad Al-Mojil Group

    Project Active File Control

    Flow Chart

    MATERIAL DEPARTMENT ENGINEERING DEPARTMENTQUALITY CONTROL

    DEPARTMENTPROJECT CONTROLS

    DEPARTMENT CONTRACTS DEPARTMENTPROJECT MANAGERS FILES

    SECRETARY

    MATERIAL RECEIVING REPORT,REQUISITION SUP, PURCHASED

    ORDERS,MATERIAL STATUSLOG OVERSHORT/DAMAGE

    REPORT, ETC.

    START

    SITE QUERY, WORK ESTIMATESAS BUILT DRAWINGS, CHANGE

    NOTICE CHANGE REQUEST,LETTER ON CLAIMS,CALCULATION, ETC..

    INSPECTION & TEST REPORTS,CERTIFICATION DOSSIERS,

    CONTROL PROCEDURES,WELDING REPORT, ETC

    MANPOWER & EQUIPMENTRECORDS, DAILY REPORT,

    MONTHLY NARRATIVE REPORT,CONSTRUCTION SCHEDULE,

    ETC

    FIELD WORK DIRECTIVES,CHANGE ORDERS, SETTLEMENT

    OF CO. SUBCONTRACTORCONTRACT & JOB

    SPECIFICATIONS, ETC

    INCOMING & OUTGOINGLETTERS, FACSIMILES, MEMOS,MINUTES OF MEETINGS, ETC..

    COLLECT IDENTIFIEDDOCUMENTS FOR RETENTION,PUT IN DOC BOXES, LABEL AND

    FORWARD TO PROJECTDOCUMENT CONTROLLER

    RECEIVE, CHECK, RECORD ANDPREPARE TRANSMITTAL (QAD-

    4-202) ADDRESSED TO CDCSECTION, DAMMAM

    MATERIAL RECEIVINGCOORDINATE WITH CDC

    DOCUMENT CONTROLLER FORSPECIFIC DOCUMENT ARCHIVE

    LOCATION OR STORAGEWAREHOUSE PRIOR DISPATCH

    TO DAMMAM

    PROJECT DEPARTMENT

    HEADS

    PROJECT DOCUMENTSCONTROLLER

    PROJECT DOCUMENTS

    CONTROLLER

    TRANSMIT DOCUMENTS TODAMMAM OR TO SPECIFIED

    LOCATION UPONCONFIRMATION BY CDC

    DOCUMENT CONTROLLER

    END

    END-4-001C / END-4-010U

    PROJECT DOCUMENTS

    CONTROLLER