Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Scott HumePrincipal Technical Leader, EPRI
2018 NETL CO2 Capture Technology Project Review MeetingAugust 14, 2018
Enabling Staged Pressurized Oxy-Combustion (SPOC): Improving Flexibility and
Performance at Reduced CostDE-FE0029087
2© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Acknowledgement and DisclaimerAcknowledgementThis material is based upon work supported by the Department of Energy National Energy Technology Laboratory under cooperative award number DE-FE0029087.
Disclaimer“This presentation was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.”
3© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Agenda
Project Overview
Technology Background
Technical Approach
Progress
Plans for Future Development
Questions
4© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Project Overview
Awarded October 2015, 24 month project$1,167m federal funding, $291,800 cost share (20%)EPRI are leading the project alongside Washington University
in St. Louis, American Air Liquide and Doosan BabcockObjectives:
– Update the design of the novel staged, pressurized oxy-combustion (SPOC) system by OEM review
– Develop flexible design concepts utilizing the SPOC system and advanced oxygen supply strategies
– Validate design tools through pilot plant testing
5© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technology Background – Oxy-Combustion Oxy-combustion technologies typically recycle a portion of the flue gas to reduce the
peak temperatures and increase the resulting gas flow rate, making convective heat transfer easier The fan power needed for flue gas recycle (FGR) increases the overall auxiliary power Atmospheric oxy-combustion necessitates large furnace volumes and cannot utilize fuel
moisture latent heat (low partial pressure of H2O results in low-temperature condensation)
COALO2 FLUE GAS
~80% v/v (d) CO2
STEAM POWER
AIR ASU
FGR
CPU
N2
CO2
Inert Gas Vent
CW
Boiler hardware arrangement similar to conventional air-fired boiler
6© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Compact boiler, enhanced convective heat transfer and lower CO2 compression costs
Technology Background – Oxy-Combustion (cont.)
COAL
O2FLUE GAS~80% v/v (d) CO2
STEAM POWER
AIR ASU CPU
N2
CO2
Inert Gas Vent
Boiler Feedwater
Staged Combustion – most of the oxygen is added to 1st stage but fuel is restricted to deliver appropriate post-combustion temperatures; FGR and gas volume reduced Pressurized Combustion – reduces the size of the combustion system,
eliminates air ingress, allows latent heat from moisture to be recovered at useful temperatures whilst delivering gases to the CPU at elevated pressure, enables easy SOx/NOx removal and restricts radiative heat flux by creating an optically dense medium; FGR is minimized
7© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technology Background – SPOC
What is “Staged Pressurized Oxy-Combustion” (SPOC)?
Burn fuel incrementally to limit peak temperatures and heat flux levelsAbsorb heat sufficiently to allow next stage combustionMinimal need for FGR, hence low fan power requirementsOperating pressure assures fuel moisture latent heat is captured into the steam cycle
Stage 1 Stage 2 Stage 3 Stage 4
FGRCoal FeedingPressurized
Oxygen
Coal
FGR
Hot Wet FGR
Bottom Ash
Bottom Ash
ASUAir
Nitrogen
Main Steam
Main Steam AshAsh
340°C340°C340°C
593°C
Hot Reheat
593°C
Hot Reheat
593°C
Bottom Ash
Main Steam Ash
340°C
Hot Reheat
593°C
Bottom Ash
Main Steam Ash
Hot Reheat
593°C
To Heat Recovery,Particulate Removal and DCC
BFW 290°C
StageI
EVAP
ECO I
FSH I330°C
420°C
Cold Reheat
FRH I
PRH I
PSH I
Saturated Steam
StageII
EVAP
ECO II
FSH II330°C
420°C
Cold Reheat
FRH II
PRH II
PSH IIStage
III EVAP
ECO III
FSH III330°C
420°C
Cold Reheat
FRH III
PRH III
PSH III
Saturated Steam
Saturated Steam
StageIV
EVAP
ECO IV
FSH IV330°C
420°C
Cold Reheat
FRH IV
PRH IV
PSH IV
Saturated Steam
8© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technical ApproachTask Description Sub-tasksTask 2 Concept review and configuration
optimizationDesign BasisBoiler OEM review of prior workDeveloped risk matrix Upgraded OEM boiler performance model for SPOC conditionsConducted heating surface sizing exercise for 550MWe scaleDefine boiler concept design, assess costs
Task 3 System integration with steam cycle
Model NETL baseline case B12AAssess heat recovery opportunitiesAuxiliary power of SPOC system
Task 4 Turndown and flexibility Options for enhanced turndownOxygen supply flexibility
Task 5 Combustor performance testing Upgrade pilot plant for target pressure operationCarry out full load and part load testing to recommended conditions
Task 6 Economics CAPEX assessment, OPEX and LCOE
9© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Progress: Project Schedule Task 2 – SPOC concept review (complete) Tasks 3, 4 & 5 – Integration, flexibility and testing (ongoing) Task 6 – Economics (to be initiated)
Boiler design activity minor delay due to workshop scheduling
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Task 1.0: Project Management and Planning 11/1/2016 10/31/2018 Subtask 1.1: Project and Risk Management 11/1/2016 10/31/2018 M1 Subtask 1.2: Financial Reporting 11/1/2016 10/31/2018 Q Q Q Q Q Q Q Subtask 1.3: Project Reporting 11/1/2016 10/31/2018 K, M2 K, M2 Subtask 1.4: Technology Transfer/Exchange 11/1/2016 10/31/2018 Q Q Q Q Q Q QTask 2.0: Concept Review and Configuration Optimization 3/1/2017 3/31/2018 Subtask 2.1: Design Basis Development 3/1/2017 4/31/2017 M3 M3 Subtask 2.2: SPOC Boiler Concept Review 4/1/2017 8/31/2017 S Subtask 2.3: Definition of Optimized Arrangement for 550-MWe Scale 6/1/2017 3/31/2018 M4 M4Task 3.0: Detailed Integration of SPOC with the Steam Cycle 10/1/2017 8/31/2018 Subtask 3.1: Steam Generator Performance 10/1/2017 3/31/2018 Subtask 3.2: CFD Modeling 12/1/2017 5/31/2018 Subtask 3.3: Steam Turbine Performance 3/1/2018 7/31/2018 Subtask 3.4: Oxygen Supply Energy Requirements 5/1/2018 8/31/2018Task 4.0: Turndown and Flexibility 1/1/2018 5/31/2018 Subtask 4.1: Steam Generator Turndown 1/1/2018 5/31/2018 Subtask 4.2: Steam Generator Performance 1/1/2018 5/31/2018 Subtask 4.3: Oxygen Supply Flexibility 1/1/2018 5/31/2018 S, M5 S, M5Task 5.0: Combustor Performance Testing 12/1/2016 9/30/2018 Subtask 5.1: Retrofit of 100-kWth Pressurized Oxy-Combustor 12/1/2016 4/30/2018 M6,D Subtask 5.2: Experimental Determination of Combustion Domains 5/1/2018 3/31/2018 Subtask 5.3: Measurement of Heat Flux, Composition, and Temperatures 8/1/2017 9/30/2018Task 6.0: Economics 5/1/2018 10/31/2018 Subtask 6.1: SPOC System Total Overnight Capital 5/1/2018 7/31/2018 Subtask 6.2: ASU Overnight Capital 7/1/2018 9/30/2018 Subtask 6.3: COE Assessment 9/1/2018 10/31/2018 F, M7
Task Name Start Date End Date 2016 2017 2018 2019
FY 2017 FY 2018 FY 2019
10© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 – OEM Concept Review The previously developed SPOC boiler concept
was reviewed against OEM boiler design requirements
Areas of particular focus were: Layout Vessel Arrangement and Sizing Burner Design Fuel Selection and Fuel Handling Particulate Removal Ash Management and Ash Handling
Risk matrix developed (with potential mitigations)
11© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 – Risk Mitigation
Revised design:– Combustor vessel with steam cooled walls
and no heating surface in the gas path– Transition to upward flowing ‘convective’
sections – allowing for ash and slag management
– Cross flow heat transfer, substantial heat transfer surface
A workshop was held to develop the concept further
12© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 – Original SPOC Concept
Each stage has unique
performance requirements
A B D F H
C E G I
J
K
42% O2 29% O2 20% O2 15% O2
52 kg/s
100% O2
23 kg/s
100% O2
23 kg/s
100% O2
23.6 kg/s
100% O2
150 kg/s
19% O2
192 kg/s
12% O2
234 kg/s
7% O2
277 kg/s
3% O2
79 kg/s
3% O2
19.3 kg/s
100% Fuel
19.3 kg/s
100% Fuel
19.3 kg/s
100% Fuel
19.3 kg/s
100% Fuel
L
A B C D E F G H I J K
Total Flow (kg/s) 121.6 52 150 23 192 23 234 23.6 277 79 198
[O2] (% v.) 100 100 17 100 10 100 6 100 3 3 3
[CO2] (% v.) 0 0 48 0 52 0 54 0 56 56 56
[H2O] (% v.) 0 0 35 0 38 0 40 0 41 41 41
13© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 – Revised SPOC ArrangementA
B E H K
C F I L
D G J
M1 M2 M3
N
O
30% O278 kg/s
3% O2
30 kg/s
100% O2
30 kg/s
100% O2
30 kg/s
100% O2
30 kg/s
100% O2
78 kg/s
3% O2
78 kg/s
3% O2
78 kg/s
3% O2
131 kg/s
3% O2
131 kg/s
3% O2
131 kg/s
3% O2
131 kg/s
3% O2
30% O2 30% O2 30% O2
P
19.3 kg/s
100% Fuel
19.3 kg/s
100% Fuel
19.3 kg/s
100% Fuel19.3 kg/s
100% Fuel
53 kg/s
3% O2
53 kg/s
3% O2
53 kg/s
3% O2213 kg/s
3% O2
A B C D E F G H I J K L M1 M2 M3 N O
Total Flow (kg/s) 122 30.4 131 77.8 30.4 131 77.8 30.4 131 77.8 30.4 131 53.2 53.2 53.2 53.2 213
[O2] (% v.) 100 100 3 3 100 3 3 100 3 3 100 3 3 3 3 3 3
[CO2] (% v.) 0 0 56 56 0 56 56 0 56 56 0 56 56 56 56 56 56
[H2O] (% v.) 0 0 41 41 0 41 41 0 41 41 0 41 41 41 41 41 41
Identical Stages - lower development
costs
14© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
0
500
0 10 20 30 40 50 60
Q(k
w/m
2 )
x(m)
Task 2 – Combustion – Long conical design PRB coal; 385MW; 30%/70% of O2/CO2; Particle size: 40% 1.6~2.0 mm, 60% 10~200 μm.
Temperature contour (°C)
Total surface heat flux (kW/m2)
Complex furnace tube geometry needed in upper sections
Drawing to scale
3.8
m
15© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
0
500
0 10 20 30 40 50 60
Q(k
w/m
2 )
x(m)0
500
0 10 20 30 40 50 60
Q(k
w/m
2 )
x(m)
2.3 – Combustion – Revised design Same conditions as previous case except particle size is 50% 1.4~1.8 mm, 50% 10~200 μm
Temperature contour (°C)
Total surface heat flux (kW/m2)
Simplified SPOC for reduced capital costs and lower peak heat flux
Drawing to scale
3.8
m
16© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 – 550MWe Design
Aim to reduce construction costsSingle boiler design across all stagesModular and ground transportable Sequential gas bed conceptHot FGR ensures stage 1 identical to subsequent stagesSteam/water equally shared across all stages
– Mass flux / geometry / tube selection– Cage design, accommodation of headers/supplies/risers
Identical furnace and boiler stages reduces cost and complexity
17© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
COMBUSTOR MODULE
CONVECTIVE MODULE
PSH
FRH
FSH
SSH
PRH
ECO
‘WATERWALLS’ (Circular
Membrane)
Steam Cooled Cage (Box section)
Task 2 – Module Design
Two pressure vessels needed for a single SPOC ‘stage’Combustor module cooled
with evaporative surface due to high incident heat fluxDirection change at base to
aid furnace ash dropoutConvective pass headers
contained within PV cavities (minimize penetrations)
18© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 –Combustor Module Concept
Sized based on WUSTL combustion performance predictionsEvaporator based on once-through,
vertical tube membrane wall arrangementTop and bottom sections refractory
lined
19© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 2 –Convective Module ConceptMembrane walls,
square profile Internal sub-headersPlenum at base to
assist ash dropout Inert CO2 gas added
to cool pressure vessel In-situ cleaning
20© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 3 – Integration with steam cycle
NETL baseline case S12A modeledAssessment of heat recovery available34 MWth available at sufficient
temperature for HP feedwater bypass136 MWth available at lower
temperatures from DCC/acid gas removal columnCorrosion resistant materials needed
due to high acid dew point at pressureLow temperature heat available sufficient to eliminate LP feedwater heaters
21© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 4 – FlexibilityStage Bypass Potential
– at reduced firing rates on proceeding stages, full bypass of subsequent stages is possible with Concept 3 arrangement
– NFPA-85 compliance, purge flow before stage restart Increased FGR at low load
– Improved convective/radiative balancingAir Separation Unit
– Storage of air inventory to allow MAC ‘deferment’– Reduced LOx storage, maintain 8 hour startup oxygen
supplyStaged system delivers high turndown potential
22© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – WUSTL Pressurized Combustion Facility
Multiple load cases planned for numerical model validation
• Pressures up to 15 barg• Thermal input up to 100 kW• Solid and gaseous fuel testing capability• Full view of near-burner (flame) region
• Diagnostics include: Temperature profile High Speed Camera Heat Flux Particle / gas sampling and ELPI, CEM Laser transmission for soot/ash measurement Fourier-transform infrared spectroscopy (FTIR)
• Ability to test multiple burners Two types of burner configurations tested
burnernozzle
quartz section
23© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – WUSTL Pressurized Combustion Facility
Multiple load cases planned for numerical model validation
• Pressures up to 15 barg• Thermal input up to 100 kW• Solid and gaseous fuel testing capability• Full view of near-burner (flame) region
• Diagnostics include: Temperature profile High Speed Camera Heat Flux Particle / gas sampling and ELPI, CEM Laser transmission for soot/ash measurement Fourier-transform infrared spectroscopy (FTIR)
• Ability to test multiple burners Two types of burner configurations tested
burnernozzle
quartz section
24© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – WUSTL Pressurized Combustion Facility
Multiple load cases planned for numerical model validation
• Pressures up to 15 barg• Thermal input up to 100 kW• Solid and gaseous fuel testing capability• Full view of near-burner (flame) region
• Diagnostics include: Temperature profile High Speed Camera Heat Flux Particle / gas sampling and ELPI, CEM Laser transmission for soot/ash measurement Fourier-transform infrared spectroscopy (FTIR)
• Ability to test multiple burners Two types of burner configurations tested
burnernozzle
quartz section
Camera
Cooling Coils
Lights
Sample Tubeignitor
laser output on 2-D
translationstage
25© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Firing experience and validation
Qualitative agreement between experiments and simulations achieved in terms of flame shape and flow field
Coal-O2/CO2
Experiments from 1 bar to 15 bar conducted at WUSTL
show similar characteristics.
HS Camera VideoVideo LES Simulation
Quartz wall
26© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Firing experience and validation
Qualitative agreement between experiments and simulations achieved in terms of flame shape and flow field
Coal-O2/CO2
Experiments from 1 bar to 15 bar conducted at WUSTL
show similar characteristics.
HS Camera VideoVideo LES Simulation
Quartz wall
27© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Firing experience and validation
Qualitative agreement between experiments and simulations achieved in terms of flame shape and flow field
Coal-O2/CO2
Experiments from 1 bar to 15 bar conducted at WUSTL
show similar characteristics.
HS Camera VideoVideo LES Simulation
Quartz wall
28© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Firing experience and validation
Qualitative agreement between experiments and simulations achieved in terms of flame shape and flow field
Coal-O2/CO2
Experiments from 1 bar to 15 bar conducted at WUSTL
show similar characteristics.
HS Camera VideoVideo LES Simulation
Quartz wall
29© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Firing experience and validation
Qualitative agreement between experiments and simulations achieved in terms of flame shape and flow field
Coal-O2/CO2
Experiments from 1 bar to 15 bar conducted at WUSTL
show similar characteristics.
HS Camera VideoVideo LES Simulation
Quartz wall
30© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Firing experience and validation
Qualitative agreement between experiments and simulations achieved in terms of flame shape and flow field
Coal-O2/CO2
Experiments from 1 bar to 15 bar conducted at WUSTL
show similar characteristics.
HS Camera VideoVideo LES Simulation
Quartz wall
31© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Task 5 – Operation: 100% coal combustion at 15 bar
Results used to validate CFD models for full scale application
• Stable flame without methane support
• No CO and soot emission detected
• Complete burnout with 3% oxygen concentration
Full Load (100 kWth) Part Load (50 kWth) Ash analysis
32© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Plans for future development
Validation of modeling from test resultsReduction of ASU auxiliary power and
thermal integrationFlexibility opportunities for oxygen supplyCost analysis of 550MW concept design
33© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Questions
34© 2018 Electric Power Research Institute, Inc. All rights reserved.© 2015 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of ElectricityTogether…Shaping the Future of Electricity