EMS Picture

  • Upload
    nako83

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/2/2019 EMS Picture

    1/25

    Southern Company Transmission

    Georgia Control Center

  • 8/2/2019 EMS Picture

    2/25

    Eastern Interconnect

    ~700,000 MWs interconnected and

    operated synchronously. Operations and transactions must

    be closely coordinated.

    Ability to lean on others aids thereliability of all participants.

    However, distant events can havewidespread impacts.

    North American Electric Reliability

    Corporation (NERC)

  • 8/2/2019 EMS Picture

    3/25

    Georgia Power Company Transmission

    Transmission Lines

    o 46 kV & 69 kV 3,520 miles

    o 115 kV 5,553 miles

    o 230 kV 2,158 mileso 500 kV 1,100 miles

    Substations

    o 227 Trans. and Gen.

    o 1955 Distribution

    Load Data

    o So. Control Area: 48,000 MW

    o GPC: 29,800 MW

  • 8/2/2019 EMS Picture

    4/25

    Tie Lines and Control Centers

    Tie Lines are thetransmission linesconnecting electricutilities

    There are 53 TieLines that connectSouthern Company toneighboring utilities inthe Southeast

  • 8/2/2019 EMS Picture

    5/25

    Power Coordination Centero System Balancing Authority

    o Reliability Coordinator

    o Monitor Interface Flows

    o Facilitate Transmission Transactions

    Local Transmission Control Centerso Monitor and Control the Transmission System

    o Facilitate Work Requests

    o Local Security

    o Restoration

    Distribution Control Centerso Monitor and Control Distribution Breakers and Feeders

    o Communicate with distribution customers

    Southern Company Operations

  • 8/2/2019 EMS Picture

    6/25

    How Does the GCC Function?

    Floor Operators

    SystemOperators (SO) AreaOperators

    ensure reliabilityand security of thetransmission grid

    in GA

    monitor andcontrol the

    transmission gridin GA in real-time

    Pre-Arrange

    process requests,write safe

    switching orders,communicate with

    personnel

    Security

    study transmissionwork requests to

    ensure the work isdone in a way tokeep grid reliable Support

    Engineersprovide technical

    guidance asneeded

  • 8/2/2019 EMS Picture

    7/25

  • 8/2/2019 EMS Picture

    8/25

    System Operator Desk

    o Perform contingency analysis and security studies

    o Develop operating solutions for identified

    contingencies

    o Monitor system voltage schedule

    o Analyze outages and assist Area desk withrestoration plans

    o Communicate with PCC and external entities

    Desk Responsibilities Continued

  • 8/2/2019 EMS Picture

    9/25

    Other Functions

    Pre-Arrange

    o Coordinate all work requests for facility outages

    1More than 12,000 in 2010

    o Verify feasibility of work requests through SystemSecurity

    o Write accurate and safe switching orders

    o Notify all impacted parties of work requests

    o Compile and distribute the daily work summary

  • 8/2/2019 EMS Picture

    10/25

    Other Functions Continued

    System Security

    o Conduct security studies/perform contingencyanalysis for outage requests

    o Develop necessary operating solutions to facilitatemajor construction projects

    o Coordinate with Transmission Planning group to helpplan to build reliable system

    o

    Conduct annual Summer Operating Study and reportresults

  • 8/2/2019 EMS Picture

    11/25

    Other Functions Continued

    Support Engineers

    o Provide technical support to other GCC groups

    o Collect and distribute data from the field

    o Verify equipment data with field personnel and otheroperating companies

    o Produce and maintain operating procedures (e.g.Blackstart)

    o Fault Data Analysis

  • 8/2/2019 EMS Picture

    12/25

    Operator Tools

    Energy Management System (EMS)o PNA (Power Network Analysis) view real-time data

    from EMS and also perform and build case studies

    o OPNA (Offline PNA) perform studies and N-1

    contingency analysiso EMo (Electronic Monitor) view real-time status to

    get the big picture quickly

    o Dynamic Line Rating

    o Fault Location

  • 8/2/2019 EMS Picture

    13/25

    Operator Tools

    Other Simulation and Viewing Toolso PowerWorld view real-time flows, also big picture

    o PSS/E perform studies and in-depth contingencyanalysis using modified planning model

    o TransMapo GenVarr

    o Situational Awareness

  • 8/2/2019 EMS Picture

    14/25

    EMS Real-time Screenshot Example

    Operator Tools

  • 8/2/2019 EMS Picture

    15/25

    PowerWorld Real-time Screenshot Example

    Software Tools

  • 8/2/2019 EMS Picture

    16/25

  • 8/2/2019 EMS Picture

    17/25

    Reliability Tools

    Weather Forecasts

    Lightning Tracker

    Fault Data Analysis Geographic Information System

    Summer Operating Study

    Sub-Transmission Automation

  • 8/2/2019 EMS Picture

    18/25

    Weather Reports

  • 8/2/2019 EMS Picture

    19/25

  • 8/2/2019 EMS Picture

    20/25

    Determine Location of Lightning Event

    FALLSFault

    AnalysisandLightning

    Location

    System

  • 8/2/2019 EMS Picture

    21/25

  • 8/2/2019 EMS Picture

    22/25

    EMS Real-time Screenshot Example

    Operator Tools

  • 8/2/2019 EMS Picture

    23/25

    Summer Operating Database - Overload

  • 8/2/2019 EMS Picture

    24/25

    Current Issues

    Reliability Standards

    Cyber Security

    Employee Skills and Training Staffing

  • 8/2/2019 EMS Picture

    25/25

    Questions?