NATIONAL FUND FOR MOHENJODARO C U L T U R E D E P A R T M E N T Pre-monsoon emergency works for prevention of rain damages at Mohenjo-Daro Site started from April, 2013. G O V E R N M E N T O F S I N D H Designed by: Shankar Oad Rajput Prepared by: Ali Hyder, A. Conservator

Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

Embed Size (px)

DESCRIPTION

Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro .Presentation nfm 2013 september, 2013 final. Dr. Neelofer Shaikh. Dr. Michael Jansen and Dr. Kaleemullah Lashari appreciated my Work.So, I am thankfull all of these people.

Citation preview

Page 1: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

C U L T U R E D E P A R T M E N T

Pre-monsoon emergency works for prevention of rain damages at

Mohenjo-Daro Site started from April, 2013.

G O V E R N M E N T O F S I N D H

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Page 2: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Pre-monsoon works identified as follows:-1. De-silting and removal of debris and mud slush out of drainage devices.

2. Renewal of mud capping and resetting of loose bricks.

3. Re-pointing with mud mortar for consolidation of wall cores i.e. grouting of cracks, filling voids in walls, etc. complete.

4. Erection of dry burnt brick masonry buttressing to the leaning walls in order to avoid from collapsing as a temporary measures.

5. Erection of steel shoring (properly designed) to the extremely tilted or out of plane walls in order to stop them from further collapsing.

6. Construction of shallow drains lined with pacca brick masonry.

7. Repair and construction of barriers/mud pushtas in mud brick masonry in order to slow down the speed of rain run off and to divert the flow of rain water towards less sensitive areas.

8. Filling up of cavities and holes of the mud capping of the walls with salt free pure clay obtained from the river Indus, to prevent the rainwater entering into the core of the walls.

9. Recording of gullies with the help of maps and the reinforcement of the same with sundried brick masonry.

Page 3: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Conventions adopted for site works on maps.

Page 4: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator,

Conventions adopted for site works on maps

in SD-Area.

Page 5: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator,

Conventions adopted for site works on maps

in DKG- South Area.

Page 6: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator,

Conventions adopted for site works on maps

in DKG- North Area.

Page 7: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator,

Conventions adopted for site works on maps

in VS-Area.

Page 8: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator,

Conventions adopted for site works on maps

in HR-Area.

Page 9: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

RAIN WATER IS THE MAIN CONTRIBUTOR TO THE WEAR AND DAMAGE OF RUINS AND IT CAN DAMAGE THE STRUCTURES IN SEVERAL WAY; BY WASHING AWAY THE SOIL (EROSION AND SCOURING), • BY MAKING THE SOIL LOOSE, (I.E. WEAKENING THE LOAD BEARING CAPACITY) RESULTING IN TILTING OF WALLS.

Page 10: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

BY DEPOSITING SOILS (SILTING) WHICH MAY OBSTRUCT THE PASSAGE OF WATER

Page 11: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

BY WASHING AWAY ENTIRE SECTIONS OF THE WALLS OR PART OF STRUCTURES

Page 12: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

RAIN WATER CAUSES TUNNELING, GULLIES, FURROWS AND CREVICES

Page 13: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

OBVIOUSLY, THE DESIGN OF PROPER DRAINAGE RELIES ON CAREFUL STUDIES AT SITE. EQUALLY IMPORTANT, THE DRAINAGE PATTERNS AND REQUIREMENTS SHOULD BE OBSERVED DURING RAINY PERIODS, IN ORDER TO OBTAIN A REALISTIC IMPRESSION OF THE HOW, AND HOW MUCH, WATER IS MOVING IN THE VICINITY OF THE STRUCTURES.

Page 14: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

SIDE DRAINS AND SHALLOW DRAINS WHICH COLLECT AND LEAD THE WATER AWAY FROM WALLS.

Page 15: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

How to over come afore mentioned damages of rains:-Measures adopted during this ensuing monsoon season, 2013, according to plan, by constructing barriers, filling voids in capping and to maintain catch-water drains which catch surface water before it reaches the walls, building scour checks, preventing erosion and barriers by slowing down the flow of the water.

Page 16: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

BARRIERS

Page 17: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

BARRIERS

Page 18: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Designing surface drainage which enables the water to flow off out of remains smoothly.

Page 19: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Drainage work in progress (Shallow drain and building scour check)

Page 20: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Constructing scouring checks.

Page 21: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Constructing scouring checks.

Page 22: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Damage and wear to the structures can be reduced if the flow of water is controlled. Minor damages can easily be repaired as part of the regular maintenance provided to the remains and its structures. If the flow of water is not properly managed, the deterioration of the structures will be more serious and occur more rapidly. This will lead to higher maintenance demands. An efficient drainage system is therefore essential to allow water to flow off and away from the walls as quickly as possible. This is achieved by a system consisting of the following components:

Page 23: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 24: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 25: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 26: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 27: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 28: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work in SD Area

Page 29: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work in SD Area

Page 30: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 31: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 32: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 33: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 34: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Maintenance of drainage devices i.e cleaning, removing mud slush, dust dirt, debris and all kinds of rubbish.

Page 35: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Stabilization of endangered part of structures by building dry brunt brick buttressing or steel shoring.

Page 36: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Stabilization of endangered part of structures by building dry brunt brick buttressing.

Page 37: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Stabilization of endangered part of structures by building dry brunt brick buttressing.

Page 38: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Stabilization of endangered part of structures by building dry brunt brick buttressing.

Page 39: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Brushing before application of mud slurry.

Page 40: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud slurry work

Page 41: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud slurry work

Page 42: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud pushta in DKG Area

Page 43: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work in DKG Area

Page 44: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work in DKG Area

Page 45: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work in DKG Area

Page 46: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work in SD Area

Page 47: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Wall base protection either with mud filling or by sundried bricks

Page 48: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Wall base protection either with mud filling or by sundried bricks

Page 49: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud brick flooring DKG-South Area

Page 50: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud brick flooring DKG-South Area

Page 51: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud capping and slurry in Block-29, DKG-North

Page 52: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud capping and slurry in Block-29, DKG-North

Page 53: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud capping in Block-29, DKG-North

Page 54: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud capping and slurry in DKG-North

Page 55: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud capping and slurry in DKG-North

Page 56: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud capping and slurry in DKG-North

Page 57: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Brushing before application of re-pointing in SD Area.

Page 58: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Re-Pointing work at Stupa

Page 59: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Re-Pointing work at Stupa

Page 60: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Re-Pointing work at Stupa

Page 61: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Mud pushta work at Stupa

Page 62: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Resetting work at SD -Area

Page 63: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gaps, voids in mud capping with pure clay in DK area

Page 64: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gaps, voids in mud capping with pure clay in DK area

Page 65: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gaps, voids in mud capping with pure clay in HR area

Page 66: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gullies with mud bricks after rain at DKG-

South -Area

Page 67: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gullies after rain at SD- Area

Page 68: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gullies after rain at SD- Area

Page 69: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

Filling of gullies after rain at SD- Area

Page 70: Emergency Measures adopted before monsoon, during and after rainfall at World Heritage Site of Mohenjodaro during 2013 under National Fund for Mohenjodaro

NATIONAL FUND FOR MOHENJODARO

Designed by: Shankar Oad Rajput

Prepared by: Ali Hyder, A. Conservator

THANKS