Embedded Systems: Testing
Combinational Logic
Main issues in testing embedded systems hardware:
The world is ANALOG, not digital; even in designing combinational logic, we need to take analog effects into account
Software doesn’t change but hardware does:--different manufacturers of the same component--different batches from the same manufacturer--environmental effects--aging--noise
main areas of concern:--signal levels (“0”, “1”—min, typical, and max values; fan-in, fan-out)--timing—rise & fall times; propagation delay; hazards and race conditions--how to deal with effects of unwanted resistance, capacitance, induction
Testing combinational circuits
Fault-unsatisfactory condition or state; can be constant, intermittent, or transient; can be static or dynamic
Error: static; inherent in system; most can be caught
Failure: undesired dynamic event occurring at a specific time—typically random—often occurs from breakage or age; cannot all be designed away
Physical faults: one-fault model
Logical faults:
Structural—from interconnections
Functional: within a component
Structural faults:
Stuck-at model: (a single fault model)
s-a-1; s-a-0; may be because circuit is open or there is a short
fig_02_39
Testing combinational circuits: s-a-0 fault
fig_02_40
Modeling s-a-0 fault:
fig_02_41
S-a-1 fault
fig_02_42
Modeling s-a-1 fault:
fig_02_43
Open circuit fault; appears as a s-a-0 fault
fig_02_49 fig_02_50
Functional faults:
Example: hazards, race conditions
Two possible methods:
A: consider devices to be delay-free, add spike generator
B: add delay elements on paths
Method A Method B
As frequencies increase, eliminating hazards through good design is even more important
The above examples refer to physical faults or performance faults
These are less common in FPGAs.
Our main concern here is with SPECIFICATION and DESIGN/IMPLEMENTTION faults—these are similar to software problems
The main source of error is “human error”
And software testing strategies are applicable
Testing for: Storage Elements;
Finite State Machines;
Sequential Logic
fig_03_30, 03_31, 03_32, 03_33
Johnson counter (2-bit): shift register + feedback input; often used in embedded applications; states for a Gray code; thus states can be decoded using combinational logic; there will not be any race conditions or hazards
fig_03_343-stage Johnson counter:
--Output is Gray sequence—no decoding spikes
--not all 23 (2n) states are legal—period is 2n (here 2*3=6)
--unused states are illegal; must prevent circuit from ever going into these states
Making actual working circuits:
Must consider--timing in latches and flip-flops--clock distribution--how to test sequential circuits (with n flip-
flops, there are potentially 2n states, a large number; access to individual flipflops for testing must also be carefully planned)
fig_03_36, 03_37
Timing in latches and flip-flops:
Setup time: how long must inputs be present and stable before gate or clock changes state?
Hold time: how long must input remain stable after the gate or clock has changed state?
Metastable oscillations can occur if timing is not correctSetup and hold times for a
gated latch enabled by a logical 1 on the gate
fig_03_38
Example: positive edge triggered FF; 50% point of each signal
fig_03_39, 03-40
Propagation delay: minimum, typical, maximum values--with respect to causative edge of clock:
Latch: must also specify delay when gate is enabled:
fig_03_41, 03_42
Timing margins: example: increasing frequency for 2-stage Johnson counter –output from either FF is 00110011….
assume tPDLH = 5-16ns
tPDLH =7-18ns
tsu = 16ns
Case 1: L to H transition of QA
Clock period = tPDLH + tsu + slack0 tPDLH + tsu
If tPDLH is max,
Frequency Fmax = 1/ [5 + 16)* 10-9]sec = 48MHz
If it is min, Fmax = 31.3 MHz
Case 2: H to L transition:
Similar calculations give Fmax = 43.5 MHz or 29.4 MHz
Conclusion: Fmax cannot be larger than 29.4 MHz to get correct behavior
Clocks and clock distribution:
--frequency and frequency range
--rise times and fall times
--stability
--precision
fig_03_43
Clocks and clock distribution:
Lower frequency than input; can use divider circuit above
Higher frequncy: can use phase locked loop:
fig_03_44
Selecting portion of clock: rate multiplier
fig_03_46
Note: delays can accumulate
fig_03_47
Clock design and distribution:
Need precision
Need to decide on number of phases
Distribution: need to be careful about delays
Example: H-tree / buffers
fig_03_48
Testing:
Scan path is basic tool
fig_03_56
Testing fsms:
Real-world fsms are weakly connected, i.e., we can’t get from any state S1 to any state S2 (but we could if we treat the transition diagram as an UNDIRECTED graph)
Strongly connected: we can get from a state S initial to any state Sj; sequence of inputs which permits this is called a transfer sequence
Homing sequence: produce a unique destination state after it is applied
Inputs:
I test = Ihoming + Itransfer
Finding a fault: requires a
Distinguishing sequence
Example:
Strongly connected Weakly connected
fig_03_57
Basic testing setup:
fig_03_58
fig_03_59
Example: machine specified by table below
Successor tree
fig_03_63
Example: recognize 1010
fig_03_65
Scan path
fig_03_66
Standardized boundary scan architecture
Architecture and unit under test
Testing:
General Requirements
DFT
Multilevel Testing--
System, Black Box, White Box Tests
Testing--General Requirements
Testing--general requirements:
•thorough
•ongoing
•DEVELOPED WITH DESIGN (DFT--design for test)note: this implies that several LEVELS of testing will be carried out
•efficient
Good, Bad, and Successful Tests
•good test: has a high probability of finding an error
•("bad test": not likely to find anything new)
•successful test: finds a new error
Most Effective Testing Is Independent
most effective testing:
by an "independent” third party
Question: what does this imply about your team testing strategy for the quarter project?
How Thoroughly Can We Test?
how thoroughly can we test?
example:
VLSI chip
200 inputs
2000 flipflops (one-bit memory cells)
# exhaustive tests?
What is the overall time to test if we can do1 test / msec? 1 test / sec?testsec?
Design for Testability (DFT)
Design for Testability (DFT)--what makes component "testable"?
operability: few bugs, incremental test
observability: you can see the results of the test
controllability: you can control state + input to test
decomposability: you can decompose into smaller problems and test each separately
simplicity: you choose the “simplest solution that will work”
stability: same test will give same results each time
understandability: you understand component, inputs, and outputs
Testing strategies
testing strategies:
verification--functions correctly implemented
validation--we are implementing the correct functions (according to requirements)
Spiral design/testing strategy
A general design/testing strategy can be described as a "spiral”:requirements design codesystem test module,integ. tests unit test (system) (black (white
box) box)
when is testing complete?One model:"logarithmic Poisson model”
f(t)=(1/p)ln(I0pt+1)
f(t) = cumulative expected failures at time tI0 = failures per time unit at beginning of testingp = reduction rate in failure intensity
START
END
Requirements, Specs/System Tests
Design/Integration Tests
Implement/Unit Tests
Design/Module Tests
Types of testing
Types of testing:
white box--"internals” (also called "glass box")
black box—modules and their "interfaces” (also called "behavioral")
system--”functionality” (can be based on specs, use cases)
(application-specific)
Good testing strategy
steps in good test strategy:
•quantified requirements
•test objectives explicit
•user requirements clear
•use "rapid cycle testing"
•build self-testing software
•filter errors by technical reviews
•review test cases and strategy formally also
•continually improve testing process
Black box testing guidelines
General guidelines:
test BOUNDARIES
test output also
choose "orthogonal” cases if possible