Elevator Modernization Case Study

Embed Size (px)

Citation preview

  • 8/19/2019 Elevator Modernization Case Study

    1/22

    Energy-Efficient Elevator Machines

    ThyssenKrupp Elevator Americas

    ThyssenKrupp Elevator AMS

    Energy Monitoring Program

    Technical Analysis Study Report (TASR)

    Level III Analysis

    SUBMITTED BY

    Brad NemethThyssenKrupp Elevator2600 Network Drive, Suite 450Frisco, TX 75034

    CUSTOMER

    Hyatt Place175 Paoakalani AvenueHonolulu, HI 96815

    VERSION: 4.0

  • 8/19/2019 Elevator Modernization Case Study

    2/22

    DISCLAIMER

    This report is not intended to serve as an engineering design document, but is intendedto provide estimated energy-efficiency savings associated with the proposed project.

    The information and recommendation represented in this report have been reviewed for

    their technical accuracy and are believed to be reasonable and correct.

    ThyssenKrupp Elevator AMS is not liable if the projected estimated savings or economics

    are not actually achieved because of varying operating conditions. All savings and

    cost estimates are for informational purposes and are not to be construed as a

    design document or as guarantees. The customer should independently evaluate the

    information presented in this report and in no event will ThyssenKrupp Elevator be held

    liable if the customer fails to achieve a specified amount of energy savings, operation of

    their facilities, or any incidental or consequential damages of any kind in connection withthis report or the installation of the recommended measures.

  • 8/19/2019 Elevator Modernization Case Study

    3/22

    CONTENTS

    SECTION 1: OVERVIEW1.1 Project Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

    SECTION 2: ENERGY BASICS

    2.1 How Elevator Technology Evolved . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

    2.2 How an Elevator Consumes and Regenerates Energy . . . . . . . . . . . . . . . . . . . . 4

    2.3 Electricity Billing Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

      Peak vs. Off-Peak . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

      Power Factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    2.4 Energy-Use Analysis Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    SECTION 3: PROJECT DETAILS

    3.1 Starting Point . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

      The Client . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

      Previously Existing Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

    3.2 Energy-Use Analysis Findings & Recommendations . . . . . . . . . . . . . . . . . . . . . . 8

      Current Energy Consumption Baseline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

      Recommended Energy Reduction Project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

      Estimated Project Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

    3.3 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

      Testing Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11  Energy Performance Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

      Overall Project Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    APPENDIX A  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

  • 8/19/2019 Elevator Modernization Case Study

    4/22

    1

    1.1 Project Summary

    This report provides a case study to demonstrate the key energy-saving components

    of an elevator modernization. Hyatt Place is a 20-story hotel with two high-rise

    elevators installed in 1974. The previously existing elevators were powered by motor

    generators (MG) and DC (direct current) hoist motors controlled by electromechanical

    relay controllers. The project consisted of replacing the DC motors with high-efficiency

    permanent-magnet hoist machines with regenerative drives and previously existing

    relay logic controllers were replaced with ThyssenKrupp TAC 50-04 micro-processor

    controllers. This modernization allowed Hyatt Place to improve elevator reliability and

    ride quality, while reducing electrical consumption of the elevators by 56 percent.

    Overview of Improvement

    PREVIOUSLY EXISTINGEQUIPMENT

    NEW EQUIPMENT

    Machines Geared Gearless

    Hoist Motors 20 HP DC Permanent-magnet motor AC(alternating current)

    Motor Generators 10 kW - 15 HP DC Removed (no longer necessary)

    Controllers Relay Logic ThyssenKrupp TAC 50-04 with smartdestination-based software andregenerative drive technology

    Group Controllers Removed (no longer necessary with theTAC 50-04 advanced communicationalgorithms)

    Lighting Incandescent LED

    Cab Interior Hall Fixtures Dated, worn looking Modern cab and hall fixtures, low-VOC-emitting material

    1. OVERVIEW

  • 8/19/2019 Elevator Modernization Case Study

    5/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 2

    2.1 How Elevator Technology Evolved

    The following definitions and timelines are for the generalized purpose of identifying existing technologies and available alternatives.

    There are multiple generations of hoist motors, hoist machines, drives and controllers available in the industry.

    DRIVES & MOTORS

    Motor Generators (MG) are traditional hoist systems that consist of a DC hoist motor powered from a DC generator.

    DC hoist motors were used because a DC motor has a high starting torque and good speed control. An AC induction

    motor turns the DC generator and the generator output is directly connected to the DC hoist motor. This hoist system

    is the least energy efficient.

    Silicon Controlled Rectifiers (SCR) drives are solid-state devices that can rectify AC power to DC power. SCR drives

    represent the next progression from motor generator sets since it became possible to produce DC voltage from an AC

    power line. Two common types of SCR drives are a six-pulse and a 12-pulse. The 12-pulse drives reduce distortion

    problems on power feed lines.

    Pulse Width Modulation (PWM) can be used to control either an AC or DC motor and utilizes several types of power

    transistors. ThyssenKrupp Elevator’s PWM 10k drive provides 10,000 pulses, compared to a 6- or 12-pulse SCR.

    These transistors are switched on and off rapidly in a technique known as Pulse Width Modulation (PWM).

    Variable Voltage Variable Frequency (VVVF) drives eliminate the need for a DC hoist motor and replace it with an AC

    motor. VVVF provides many of the same advantageous characteristics of the DC motor, such as smooth acceleration

    and deceleration and excellent speed control without the issues related to usability of power.

    Regenerative Motors (Regen Motors) produce energy when the motor is in an overhaul condition. In an elevator, this

    occurs when the motor is used to brake a descending unit. Until recently, the electricity generated was sent through

    a series of resisters that dissipated the energy as heat into the machine room. With the introduction of regenerative

    drives, the energy produced can be fed back into the building or power grid. Because the harmonics are purified, there

    is no line loss and 100% of the power that is harnessed is usable.

    Permanent-Magnet Motors have performance advantages over DC excited-synchronous motors and are becoming

    more common in fractional horsepower applications because they are smaller, lighter, more efficient and reliable.

    Large industrial motors originally used wound field or rotor magnets. Permanent-magnets have traditionally been used

    only on smaller motors because of the difficulty in finding a material capable of retaining a high-strength field. Recent

    improvements in material technologies have made it possible to create high-intensity permanent-magnets, allowing

    the development of compact, high-power motors without the extra real estate of field coils and excitation means.

    2. ENERGY BASICS

    OLDEST

    NEWEST

  • 8/19/2019 Elevator Modernization Case Study

    6/22

    3

    Sheave

    Ring Gear

    Motor Shaft

    MACHINERY

    Geared Machine 

    A geared driving machine is one that utilizes a geared-reduction unit between the motor and the drive sheave. The

    main advantage of this design is that a less powerful motor can be used to drive it. A geared system, usually designed

    to run at 350 feet per minute or less (though they can go faster), sacrifices speed to its gearless counterpart. Geared

    systems are often used in slower-moving passenger and freight elevators.

    Gearless Machine A gearless driving machine is a direct-drive system in which there is no reduction gear between the motor and the

    drive (or hoisting) sheave. That is, the drive sheave is connected directly to the motor and brake. Gearless designs are

    used in the world’s tallest structures. They are efficient and used for driving speeds greater than 500 feet per minute.

    CONTROLLERS

    Electromechanical Relays (EMRs) traditionally have been the components of choice for elevator controllers based on

    their price, functional characteristics and availability. EMRs have served effectively in numerous applications, but their

    use of mechanical contacts to switch a load subjects contact points to oxidation and breakdown over the life cycle of

    an elevator unit. EMRs also display bounce, an undesired condition manifested by a short period of pulsed electrical

    current upon mechanical contact, rather than a clean transition from zero to full current.

    A group controller is needed with an electromechanical relay. Group controllers allow individual elevators to

    communicate, or know what each elevator position is relevant to one another, allowing the controllers to determine

    which elevator should answer each hall call. In a group controller, this process is rudimentary – the controller

    determines which elevator should answer the call using a rudimentary process where the direction the person wishes

    to travel is used to determine which elevator should respond to that request.

    Micro-Processors were developed as a result of emergent semiconductor technologies and offer advantages over

    their electromechanical counterparts. Technical parameters to consider when selecting either an EMR or micro-

    processor controller include service life, reliability, isolation voltage, on resistance (RON), output capacity and package

    dimensions. Although each type of relay has its advantages in cost or performance, micro-processor controllershave become the optimal choice in many applications based on their high reliability, long service life, lower power

    consumption and smaller package size/footprint relative to EMRs. Advances in semiconductor manufacturing

    technologies have also reduced the cost gap between the EMR and micro-processor controller, making the micro-

    processor controllers cost effective in a growing number of applications.

    With a micro-processor controller installed, group controllers are no longer needed. In the TAC 50-04 controller, TKE

    exclusive algorithms provide advanced intelligence to dispatch elevators with improved efficiency. Factors such as

    weight, direction and length of travel are all incorporated into the controller calculations. This provides the enhanced

    performance as well as eliminating the need for a passive controller and its associated wiring—further reducing overal

    environmental impacts.

    Previously Existing Geared Machine

    OLDEST

    OLDER

    NEWEST

    NEWEST

  • 8/19/2019 Elevator Modernization Case Study

    7/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 4

    2.2 How an Elevator Consumes and Regenerates Energy

    When an electric motor accelerates or maintains velocity, it consumes energy. But when this same electric motor brakes or decelerates

    a body in motion, the motor becomes a generator of energy. This energy has traditionally been considered a nuisance,

    but with the invention of integrated regenerative drives, this “waste” energy is sent back into the electrical grid.

    Power is consumed in a traction elevator first, by the

    gravitational pull on ascending cabs that are heavier than thedescending counterweight and second, by the gravitational

    pull on ascending counterweights when they are heavier than

    descending elevator cabs.

    Power is generated in a traction elevator first, by the

    gravitational pull on descending cabs that are heavier thanthe ascending counterweight and second, by the gravitational

    pull on descending counterweights when they are heavier than

    ascending elevator cabs.

    In the case of power generation, the mechanical energy of the

    descending car or counterweight causes the elevator motor to

    function as a generator (or re-generator) of electricity.

    The elevator also produces electricity when the motor works as

    a braking system to decelerate. Conventional elevator systems

    dissipate this untapped electricity as waste heat, routing itthrough electrical resistors in the elevator shaft or machine

    room, using essentially the same principle as an electric toaster.

    This waste heat is not only inefficient, but can raise the ambient

    temperatures in elevator machine rooms and often require

    additional cooling.

    CONSUMING ENERGY GENERATING ENERGY

    Cab Weight > Counterweight Cab Weight < CounterweightCab Weight < Counterweight Cab Weight > Counterweight

  • 8/19/2019 Elevator Modernization Case Study

    8/22

    5

    2.3 Electricity Billing Factors

    PEAK VS. OFF-PEAK

    Power consumption is typically represented by kilowatts or kW.

    Utility and power distribution companies typically charge by kW,

    however, different rates apply to the time of use – peak demandusage versus off-peak usage.

    POWER FACTOR

    Another element in understanding energy use and distribution

    is the power factor or, in simple terms, how much effort it takes

    to push electricity through a building or power grid. The power

    factor indicates how efficiently a building accepts and uses

    electricity.

    Power Factor = Active power/Apparent power = kW/kVA

      = Active power/(Active Power + Reactive Power)

    = kW/(kW + kVAr)

    Higher kVAr indicates low power factor and vice versa. In

    electrical terms kW, kVA, and kVAr are vectors and must be

    summed.

    kVA

    kVAr

    kW

    2.4 Energy-Use Analysis Options

    Audits can provide baseline data and recommendations for how

    to best manage upgrades of elevator components in order to

    improve energy efficiency. An organization can often receive tax

    incentives or rebates from utility companies if i t can significantlyreduce energy consumption. Not all energy audits are the same

    and it is helpful to understand the various levels of audits that are

    performed.

    An energy audit is the key to a systematic approach to decision-

    making regarding energy conservation. The primary function

    of this energy audit is to identify all of the energy streams in an

    elevator system in order to balance total energy input with energy

    use. The four main objectives of an elevator energy audit are as

    follows:

    1. To establish an energy-consumption baseline

    2. To quantify energy usage according to its discrete functions

    (e.g. machine, lighting, standby)

    3. To validate pre- and post-elevator modernization

    4. To identify existing energy-cost reduction opportunities

    Elevator energy audits vary in depth, depending on the potential

    for energy and cost reductions at a specific site and the project

    parameters set by the client.

    Though a recognized standard for auditing elevator energyefficiency does not specifically exist, ASHRAE (American Society

    of Heating, Refrigerating and Air-Conditioning Engineers)

    is recognized as an industry standard for energy audits.

    ThyssenKrupp Elevator has adopted the ASHRAE standards for

    the energy audits of elevators.

    ThyssenKrupp Elevator provides Level I, II, and III audits

    depending upon building needs. In order to qualify for tax

    incentives and rebates from utility companies, an organization

    must get a Level II or III audit.

    Completing an energy audit of a facility provides an organization

    with customized Energy Conservation Measures (ECM’s) designed

    to ensure significant energy savings as well as CO2 emission

    reductions.

    Power factor is the ratio of true power or watts to apparent power

    or volt amps, so the theoretical best value for a power factor

    is one (on a scale of zero to one). In an electric power system,

    a load with a low power factor draws more current than a load

    with a high power factor for the same amount of useful power

    transferred. The higher currents increase the energy lost in the

    distribution system and require larger wires and other equipment.

    Because of the costs of larger equipment and wasted energy,

    electrical utilities will usually charge a higher cost to industrial or

    commercial customers where there is a low power factor.

  • 8/19/2019 Elevator Modernization Case Study

    9/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 6

    ASHRAE LEVEL I 

    WALK-THROUGH ANALYSIS/

    PRELIMINARY AUDIT

    The most basic audit is a Level I audit. It is

    also referred to as a simple audit, screening

    audit or walk-through audit. It involvesminimal interviews with site personnel,

    a brief review of elevator equipment and

    other operating data and a walk-through

    of the facility. Auditors will identify areas

    of significant energy waste or inefficiency.

    The data compiled is then used for the

    preliminary energy-use analysis and a

    report detailing potential energy savings.

    This level of detail is adequate to estimate

    energy-efficiency projects.

    Services:

    • Brief survey of the building

    • Savings analysis of energy conservation

    measures (ECMs)

    • Identification of potential capital

    improvements meriting further

    consideration

    ThyssenKrupp Elevator provides an online

    tool for estimating energy consumption that

    is based upon operating parameters andtraffic patterns of both real and simulated

    buildings1. With a minimal amount of

    input, the energy can be predicted based

    on several assumptions that emulate

    conditions consistent with building type,

    use and traffic patterns. This energy

    calculator estimates the baseline energy

    consumption and predicts potential energy

    savings from modernization.

    The calculations and parameters usedin ThyssenKrupp’s energy calculator

    are modeled after actual-use data

    within our test facility. It is periodically

    cross-referenced with actual energy

    measurements from on-site metering

    during the pre- and post-audits of similar

    elevator modernizations.

    ASHRAE LEVEL II 

    ENERGY SURVEY AND ANALYSIS

    A Level II audit includes the preliminary

    ASHRAE Level I analysis, but also includes

    more detailed building energy usage.

    Onsite monitoring of the elevator machineduty cycle affords better estimates for

    machine run time versus idle time, which

    helps to identify lighting and energy use

    patterns. Understanding these energy

    patterns enables better management of

    energy use.

    Average wait times (waiting for an

    elevator), average transport times and

    traffic patterns are determined. This

    information is then used to either optimizethe elevator characteristics (when

    technology permits) or suggest overlay

    systems, such as smart destination-based

    software to improve tenant satisfaction.

    Services:

    • More extensive building survey (over

    many days)

    • Breakdown of energy use by machine,

    drive, generators, lights, transformers,

    exhaust fans, heaters and cooling units• Savings and cost analysis of all energy

    conservation measures

    • Identification of potential rebate

    programs offered through utility and

    transmission companies

    ASHRAE LEVEL III 

    DETAILED ANALYSIS OF CAPITAL

    INTENSIVE MODIFICATIONS

    A Level III audit is also known as a

    comprehensive audit, detailed audit or

    technical analysis audit. This audit focuseson potential capital-intensive projects and

    involves more detailed field-data gathering

    and a more rigorous engineering analysis.

    It provides detailed project energy usage

    and savings calculations with a high level

    of confidence.

    A Level III audit measures the energy

    consumption analysis on the existing

    elevator equipment. Existing utility data is

    supplemented with sub-metering of majorenergy consuming systems.

    Services:

    • Attention to capital-intensive projects

    • More detailed field analysis

    • In-depth discussions with utility

    companies

    • Submittal of rebate application,

    subsequent follow-up

    • Pre- and post-energy consumption

    metrics with a high level of accuracy

    1ThyssenKrupp’s energy calculator is available at: http://www.thyssenkruppelevator.com/energy%20calculator/energy.aspx

  • 8/19/2019 Elevator Modernization Case Study

    10/22

    7

    PASSENGERCAR #1

    PASSENGERCAR #2

    Stops 19 19

    Capacity (lbs) 2500 2500

    Speed (fpm) 350 350

    Average CarLoad

    300 lbs 300 lbs

    OperatingHours*

    10 hours/day5 days/week52 weeks/year

    10 hours/day5 days/week52 weeks/year

    Estimated DutyCycle*

    35% 35%

    *Operating hours and estimated duty

    cycle data are not available for this

    project. Both elevators were out of service

    because the entire building was already

    under renovation when the elevator

    modernization began.

    3.1 Starting Point

    THE CLIENT

    Hyatt Hotels Corp. expanded its presence in Hawaii with the conversion of the Ocean

    Resort Hotel Waikiki into the Hyatt Place Waikiki Beach. The 451-room hotel, which is

    located at the Diamond Head end of Waikiki, was being renovated and repositioned to

    become a 425-room Hyatt Place when the elevator modernization project began.

    The Hyatt wanted improved ride performance, improved dispatching, energy efficiency,

    increased dependability and an interior cab face lift. Without a costly replacement of

    the entire elevator, the Hyatt wanted to make a 30-year-old elevator look, ride and

    perform like a brand new elevator.

    PREVIOUSLY EXISTINGEQUIPMENT

    EQUIPMENT CONDITION

    Machines Geared Geared machines were originally usedbecause they require a less powerful motorto drive it, but any time mechanical energyis transferred from a motor shaft through aseries of gears, there is inherent energy loss.

    Hoist Motors 20 HP DC A DC hoist motor was originally installed forhigh starting torque and good speed control.

    Motor Generators 10 kW - 15 HP DC An AC induction motor was required to turnthe DC generator, which powered the DChoist motor.

    Controllers Relay Logic Electromechanical relay controllersrelied upon magnetism between metalcontacts, which means that the mechanicalcomponents wore out over time and tooklonger to operate.

    Lighting Incandescent Incandescent bulbs, which weretechnologically advanced at the time ofconstruction, are now well known to be theleast energy-efficient option for lighting.

    Cab Interior HallFixtures

    Dated, worn looking 30 years of wear and tear made the elevatorcomponents appear unreliable and in need

    of maintenance.Elevator Code Not up to code Elevator would stop during a power outage,

    leaving passengers stranded until powerwas restored.

    PREVIOUSLY EXISTING EQUIPMENT

    Year Built: 1974

    Number of Floors: 20

    Number of Elevators: 2

    Line Voltage: 208V

    3. PROJECT DETAILS

  • 8/19/2019 Elevator Modernization Case Study

    11/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 8

    3.2 Energy Use Analysis Findings & Recommendations

    ThyssenKrupp Elevator provided a Level III energy audit for the Hyatt.

    CURRENT ENERGY CONSUMPTION BASELINE

    Since the elevator modernization project began after the building renovation was alreadyunderway, the duty cycle and traffic patterns of the previously existing elevators could

    not be captured for this study. The figures below are estimates for one run (empty

    elevator sent from the bottom to the top floor and then back down).

    Energy Consumption Baseline

    Lighting 0.72 kWh

    Controller* 1.33 kWh

    Motor 0.13 kW/run

    RECOMMENDED ENERGY REDUCTION PROJECT

    As a result of the Level III energy audit, ThyssenKrupp Elevator recommended that

    the DC motors be replaced with high-efficiency permanent-magnet hoist machines.

    The permanent-magnet motor will increase energy efficiency because high-intensity

    permanent-magnets are used instead of drawing from an external electrical source.

    Permanent-Magnet Motor

    DC Motor

    *Included all standby power excluding hoist motion.

  • 8/19/2019 Elevator Modernization Case Study

    12/22

    9

    The audit findings also recommended installing regenerative drives to feed the

    energy produced directly back into the building. Previously existing controllers were

    recommended to be replaced with ThyssenKrupp TAC 50-04 micro-processor controllers

    in order to improve ride dispatching, improve energy efficiency, reduce noise and

    provide precision acceleration/deceleration and leverage accuracy. ThyssenKrupp

    was also able to offer a gearless option for these elevators, which until recently was

    unavailable in elevators operating at speeds below 350 fpm. ThyssenKrupp is the only

    company currently offering the 2:1 roping that is required to accommodate the more

    energy-efficient gearless motor.

    PREVIOUSLY EXISTINGEQUIPMENT

    RECOMMENDED EQUIPMENT

    Machines Geared Gearless

    Hoist Motors 20 HP DC Permanent-magnet motor AC

    Motor Generators 10 kW - 15 HP DC Removed (no longer necessary)

    Controllers Relay Logic ThyssenKrupp TAC 50-04 with smartdestination-based software

    Lighting Incandescent LED

    Cab Interior Hall Fixtures Dated, worn looking Modern cab and hall fixtures, low-VOC-emitting material

    Elevator Code Not up to code Up to code according to equipmentdesign safety compliance and life-safetycompliance standards

  • 8/19/2019 Elevator Modernization Case Study

    13/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 10

    ESTIMATED PROJECT RESULTS

    It was estimated that electricity use will result in a 48 percent reduction in electricity costs. Estimates of project electricity savings were

    made by utilizing ThyssenKrupp Elevator’s Energy-Cost Analysis:

    Previously Existing Drive Type MG

    New Drive Type VVVF Regen

    PREVIOUSLY EXISTINGEQUIPMENT

    NEWEQUIPMENT

    Application Type Geared Gearless

    Speed (fpm) 350 350

    Capacity (lbs) 2500 2500

    CWT% (if applicable) 45% 50%

    Net Travel (ft) 200 200

    Roping (if applicable) 1:1 2:1

    # of Cars in Group 2 2

    Transformer No Yes

    Local Electrical Cost $0.10000 per kW-h

    Elevator operating hours per day 10 hours

    Elevator operating days per week 5 days

    Elevator operating weeks per year 52 weeks

    Average load in car 300 lbs

    % running duty cycle 35%

    Include Power Factor No

    Application Data Variable Parameters

    ANNUAL COST SAVINGS

    PER UNIT

    $543PER GROUP

    $1,086PERCENTAGE

    48%

    $500 $1,000 $1,500 $2,000 $2,500

    ANNUAL COST

    PER GROUP$2,258

    PER GROUP$1,172

    PER UNIT$1,129

    PER UNIT$586

    MGVVVF

    $0

  • 8/19/2019 Elevator Modernization Case Study

    14/22

    11

    3.3 Results

    TESTING PROCEDURES

    ELITEpro energy-data loggers were used during controlled test runs to measure the

    previously existing motor generators against the new permanent-magnet hoist system.

    The elevators being tested were servicing the same elevator bank and same number offloors. Elevators were sent from the bottom to the top floor and then back down with a

    variety of loads and no intermediate stops. Data was logged at the same sampling rates

    for both elevators and measurements of the kVAr and average kW were taken for both

    the MG and the new permanent-magnet machines. A review of the data verified that no

    anomalies or events skewed the data or introduced uncommon patterns.

    ENERGY PERFORMANCE RESULTS

    The energy use logged during the test runs is shown below. The permanent-magnet

    motor outperformed the MG in all five test runs. The permanent-magnet motor consumed

    45 percent to 70 percent less energy than the MG, depending upon the elevator load.

    The controller standby energy use was 55.9 percent less with the new TAC 50-04 micro-

    processor controller, and the new LED lighting contributed to an 85.9 percent reduction in

    lighting energy use.

    3.32 Incandescent Lighting vs. LED Lighting per run

    PREVIOUSLY EXISTINGEQUIPMENT

    NEWEQUIPMENT

    LESS ENERGY USED

    Lighting 0.724 kWh 0.102 kWh 85.9%

    3.31 Relay Logic Controller vs. TAC 50-04 Controller

    PREVIOUSLY EXISTINGEQUIPMENT

    NEWEQUIPMENT

    LESS ENERGY USED

    Controller Standby 1.332 kWh 0.588 kWh 55.9%

  • 8/19/2019 Elevator Modernization Case Study

    15/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 12

    3.33 Motor Generator vs. Permanent-Magnet Motor

    Average kW per run, 0 lbs (no load)

    PM MG

    0.05867 0.13367

      56.1%

    -10

    -5

    0

    5

    10

    15

    20

    25

         K     W

    Average kW with 0 lbs

    One Cycle (kWh)

    COMBINED - MG vs PM

     

    PM MG

    0.05233 0.11666

      55.1%

    -10

    -5

    0

    5

    10

    15

    20

    25

         K     W

    Average kW with 320 lbs

    One Cycle (kWh)

    COMBINED - MG vs PM

     

    3.34 Motor Generator vs. Permanent-Magnet Motor

    Average kW per run, 320 lbs

    Motor Generator

    Motor Generator

    Permanent-Magnet Moto

    Permanent-Magnet Moto

    MG = Motor Generator GearedMachine

    PM = Permanent-Magnet MotorGearless Machine

    MG = Motor Generator GearedMachine

    PM = Permanent-Magnet MotorGearless Machine

  • 8/19/2019 Elevator Modernization Case Study

    16/22

    13

    3.35 Motor Generator vs. Permanent-Magnet Motor

    Average kW per run, 640 lbs

    3.36 Motor Generator vs. Permanent-Magnet Motor

    Average kW per run, 960 lbs

    PM MG

    0.04667 0.10033

      53.5%

    -10

    -5

    0

    5

    10

    15

    20

    25

         K     W

    Average kW with 640 lbs

    One Cycle (kWh)

    COMBINED - MG vs PM

    PM MG

    0.046 0.08433

      45.5%

    -10

    -5

    0

    5

    10

    15

    20

    25

         K     W

    Average kW with 960 lbs

    One Cycle (kWh)

    COMBINED - MG vs PM

     

    Motor Generator

    Motor Generator

    Permanent-Magnet Moto

    Permanent-Magnet Moto

    MG = Motor Generator GearedMachinePM = Permanent-Magnet Motor

    Gearless Machine

    MG = Motor Generator GearedMachine

    PM = Permanent-Magnet MotorGearless Machine

  • 8/19/2019 Elevator Modernization Case Study

    17/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 14

    3.38 Generator vs. Permanent-Magnet Motor

    Average kVAr per run, 0 lbs (no load)

    3.37 Motor Generator vs. Permanent-Magnet Motor

    Average kW per run, 2500 lbs

    PM MG

    0.061 0.20433

      70.1%

    -10

    -5

    0

    5

    10

    15

    20

    25

         K     W

    Average kW with 2500 lbs

    One Cycle (kWh)

    COMBINED - MG vs PM

    -1

    2

    3

    5

    7

    9

           k       V       A     r

    Average kVAr with 0 lbs

    COMBINED - MG vs PM

    The kVAr measurements reveal yet another way that the modernized equipment can improve the energy efficiency of the building.

    The lower kVAr measurement for the new equipment indicates that the new equipment accepts and uses electricity more efficiently.

    This is because a lower kVAr indicates a higher power factor, that could result in lower electricity costs in cases where the local

    utility company considers the power factor in commercial billing calculations. The data shows that the new permanent-magnet

    drive increases the power factor by 8 to 44 percent depending on motor loading conditions, which could generate an additional 10

    percent in cost savings.

    Motor GeneratorPermanent-Magnet Motor

    Motor GeneratorPermanent-Magnet Moto

    MG = Motor Generator GearedMachinePM = Permanent-Magnet Motor

    Gearless Machine

    MG = Motor Generator GearedMachine

    PM = Permanent-Magnet MotorGearless Machine

  • 8/19/2019 Elevator Modernization Case Study

    18/22

    15

    OVERALL PROJECT RESULTS

    Two factors in the Hyatt modernization project diminished the

    actual energy cost savings. Typical 1970’s construction in this

    location utilized 208 line voltage, therefore a transformer was

    required in order to bring the line voltage up to industry standards.

    Energy required to run the transformer diminishes the net energyreduction by about 10 percent. Also, if the local utility company’s

    billing calculations utilized an adjusted rate due to lower power

    factor, then the Hyatt can realize an additional 10 percent reduction

    in energy costs. In any case, it is anticipated that this building will

    notice a 50 to 60 percent reduction in energy consumption under

    normal operating conditions.

    In addition to the reduction in energy use, the cycle time, or the

    time it takes to go from the bottom to the top floor and then back

    down has improved by 8 seconds (22 percent) with the new

    permanent-magnet hoist system. This is due to two main factors– (1) the previously existing MG hoist system could not operate at

    the specified 350 fpm due to performance issues, and (2) the new,

    solid-state controller allows for improved speed over the traditional

    mechanical switches and relays. This improvement in dispatching,

    ride time, ride performance and reliability results in improved guest

    satisfaction in the newly renovated facility.

    Several factors contributed to improved ride performance after

    the modernization process was complete. First, vibration in the

    elevator was significantly decreased. Vibration is defined as a

    variation with time of the magnitude of acceleration, when themagnitude is alternately greater and smaller than a reference

    level. Within a moving elevator, vibration is caused by surfaces

    and a component vibrating strongly enough to turn them into

    a secondary sound source. This vibration is generated by an

    elevator moving through the shaft and changes in intensity

    during the acceleration, full speed and deceleration elements of

    each elevator ride. Apart from this vibration, elevator passengers

    are also generally subjected to a high frequency vibration

    generated by a primary source vibration through the rotating

    drive machinery which is transmitted into the elevator car by the

    suspension ropes. The rotating components transmitting vibrationare classified as motors, sheaves, rollers, bearings and gears

    which all have differing levels of frequency generation which,

    at high rotating speeds, should be dynamically balanced to

    reduce unwanted vibration. The ThyssenKrupp Elevator exclusive

    geared to gearless conversion improved ride performance to an

    industry record of 9 to 12 m-g*. Most elevators utilizing gearedmachines are unable to limit vibration below 15 to 20 m-g. Ride

    performance has also improved because the elevators can now

    level themselves more precisely at the stopping point of each

    floor. This is a common issue for aging elevators, and with

    these modernizations, the leveling along with acceleration and

    deceleration issues were remedied.

    The previously existing machines were noisy and took up a

    large amount of space, making it difficult to plan where the

    machine rooms were placed in relation to the guest rooms. The

    new equipment reduces the noise in the machine room, thusimproving guest satisfaction in the adjacent hotel rooms. The

    required amount of space in the room itself was also reduced by

    approximately 12 percent, thus providing greater flexibility for

    the architects that designed the renovated hotel. The previously

    existing equipment also used carbon brushes that contributed to

    dust in the machine room. The modernization project eliminated

    the carbon dust associated with carbon brushes, reduced the

    frequency with which the air filters needed to be replaced and

    improved indoor air quality.

    The new elevators are also fit with ThyssenKrupp’s signature ULEnvironment listed cab interiors. UL Environment verified that

    the materials used in the modernization process were low-VOC-

    emitting material compliant with the stringent indoor air quality

    standard established by California’s Section 01350 (CA 01350). A

    new backup, uninterrupted power supply (UPS) was also installed,

    enabling passengers to safely exit the elevator in the event of a

    power outage.

    Overall, the modernization of the elevator cab and hall fixtures

    mean the elevators provide a more peaceful, reliable and safe

    ride for the guests and significant savings on energy costs for thebuilding owner.

    *Acceleration is normally expressed in terms of milli-g (m-g) or one

    thousandth of a “g” (.001 g)

  • 8/19/2019 Elevator Modernization Case Study

    19/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 16

    Modernized Elevator at Hyatt Place Waikiki Beach

    Image is a not an exact representation of an elevator product.

    Gearless Permanent-Magnet Motorwith VVVF Drive

    Counterweight

    2:1 Roping

  • 8/19/2019 Elevator Modernization Case Study

    20/22

    17

    APPENDIX A: PICTURES OF PREVIOUSLY EXISTING EQUIPMENT AND NEW EQUIPMENT

    Previously Existing Equipment

    Heater bank for waste-energy dissipation Relay logic controllerMechanical floor position controller

    Motor generator Geared machine

  • 8/19/2019 Elevator Modernization Case Study

    21/22

    // Technical Analysis Study Report // ThyssenKrupp Elevator // 18

    TAC 50-04 controller Governor

    New Equipment

    PM Hoist Machine

  • 8/19/2019 Elevator Modernization Case Study

    22/22

    ThyssenKrupp Elevator

    P.O. Box 2177, Memphis, TN 38101

    Phone (877) 230-0303

    thyssenkruppelevator.com

    All illustrations and specifications are based on information in effect at time of

    publication approval. ThyssenKrupp Elevator reserves the right to change specifications

    or design and to discontinue items without prior notice or obligation. Copyright © 2011

    ThyssenKrupp Elevator Corporation.