Elevator Installation, Window Replacement,
HVAC, Sprinklers, Block wall skimcoating
(resident rooms & 1st through 4th floor resident corridors).
New resident room lighting, Resident room door replacement, Patio reconstruction, &
ADA compliant hardware.
Before June 2, 2008 Demolition in progress.
June 30,2008 Patio construction in progress.
LOBBY BEFORE…
Elevator shaft cut in at lobby. (Former mailbox location). June 30, 2008
LOBBY NOW…June 2 – June 30Lobby and front desk receive massive demolition to prepare for location of new elevator, mailboxes, front desk reconfigure & more...
HD Office demo continues.June 30, 2008
Front Desk Demo. June 2, 2008
Lobby demo. June 2, 2008Lobby & HD Office demo. June 2, 2008
And the basement sees action too!
FITNESS ROOMwalls come downto make way forelevator shaft.
COMPUTER LAB
NOW…
COMPUTER LAB
BEFORE…
STUDY LOUNGE BEFORE…
STUDY LOUNGE NOW…
June 2, 2008
June 2, 2008
June 2, 2008
Resident Rooms In Progress…
Sprinkler system & heater placement in progress.
June 2 - 30, 2008
Skimcoating of block walls on 4W begins. What a change!
Painting of walls, door frames, new wood door install, casework, windows and new lights to follow. June 30, 2008
Arrival of New Windows!
June 30, 2008
Resident floor corridors in progress…
4W corridor shows skimcoating in progress. Painting of walls, door frames and install of new wood doors to follow.
June 30, 2008
View of cut-in elevator shaft & access panel from 4th floor.(Former 440 resident room.)
June 30, 2008
Tectum & ceiling tile removed to prepare for skimcoating, texturing and painting of ceilings and walls.
June 2 -30, 2008