5
Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New resident room lighting, Resident room door replacement, Patio reconstruction, & ADA compliant hardware. Before June 2, 2008 Demolition in progress. June 30,2008 Patio construction in progress.

Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New

Embed Size (px)

Citation preview

Page 1: Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New

Elevator Installation, Window Replacement,

HVAC, Sprinklers, Block wall skimcoating

(resident rooms & 1st through 4th floor resident corridors).

New resident room lighting, Resident room door replacement, Patio reconstruction, &

ADA compliant hardware.

Before June 2, 2008 Demolition in progress.

June 30,2008 Patio construction in progress.

Page 2: Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New

LOBBY BEFORE…

Elevator shaft cut in at lobby. (Former mailbox location). June 30, 2008

LOBBY NOW…June 2 – June 30Lobby and front desk receive massive demolition to prepare for location of new elevator, mailboxes, front desk reconfigure & more...

HD Office demo continues.June 30, 2008

Front Desk Demo. June 2, 2008

Lobby demo. June 2, 2008Lobby & HD Office demo. June 2, 2008

Page 3: Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New

And the basement sees action too!

FITNESS ROOMwalls come downto make way forelevator shaft.

COMPUTER LAB

NOW…

COMPUTER LAB

BEFORE…

STUDY LOUNGE BEFORE…

STUDY LOUNGE NOW…

June 2, 2008

June 2, 2008

June 2, 2008

Page 4: Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New

Resident Rooms In Progress…

Sprinkler system & heater placement in progress.

June 2 - 30, 2008

Skimcoating of block walls on 4W begins. What a change!

Painting of walls, door frames, new wood door install, casework, windows and new lights to follow. June 30, 2008

Arrival of New Windows!

June 30, 2008

Page 5: Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New

Resident floor corridors in progress…

4W corridor shows skimcoating in progress. Painting of walls, door frames and install of new wood doors to follow.

June 30, 2008

View of cut-in elevator shaft & access panel from 4th floor.(Former 440 resident room.)

June 30, 2008

Tectum & ceiling tile removed to prepare for skimcoating, texturing and painting of ceilings and walls.

June 2 -30, 2008