Elevating the Quality of Life in the District. Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE –

Embed Size (px)

Citation preview

Page 1: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

Page 2: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY

TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE – AUGUST 2015 TO APRIL 2016 TIMELINE – EASTER BREAK 2016 TIMELINE – APRIL 2016 TO JULY 2016

ACCESS & FLOW Foundation to Grade Building Permit Building Permit

NEXT STEPS 18th Nov. to 2nd Dec. Activities two week look ahead. Construction Images in Courtyard Construction Milestone Frequently Asked Questions.

Q & A

Elevating the Quality of Life in the District

Page 3: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

RULES OF THE ROAD RESPECT EACH OTHER

CELLPHONES OFF OR ON VIBRATE

Q&A WILL BE TAKEN AT THE END OF THE PRESENTATION

Page 4: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

SITE VIEW

Page 5: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

COURTYARD

AFTER RENOVATION AFTER RENOVATIONBEFORE RENOVATION

BEFORE RENOVATION

Page 6: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

MEDIA CENTERAFTER RENOVATIONBEFORE RENOVATION

Page 7: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

BEFORE RENOVATION AFTER RENOVATION

SOUTH ELEVATION

Page 8: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

AFTER RENOVATIONBEFORE RENOVATION

REAR ELEVATION

Page 9: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

BEFORE RENOVATION AFTER RENOVATION

MAIN ENTRANCE

Page 10: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

SECTIONS

Page 11: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

COURTYARD

Page 12: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

FIVE STOPS ELEVATOR

Page 13: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – JUNE 2013 TO JULY 2015

Page 14: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

GROUND FLOOR PLAN

SECOND FLOOR PLAN

FIRST FLOOR PLAN

Page 15: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – AUGUST 2015 TO APRIL 2016

Page 16: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

SITE VIEW

Page 17: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

GROUND FLOOR PLAN

SECOND FLOOR PLAN

FIRST FLOOR PLAN

TIMELINE AUGUST 2015 – APRIL 2016

UNDER CONSTRUCTIONEGRESS DURING

CONSTRUCTION

LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

Page 18: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – EASTER BREAK 2016

Page 19: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

TIMELINE EASTER BREAK 2016

UNDER CONSTRUCTION

LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

Page 20: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – APRIL 2016 TO JULY 2016

Page 21: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

SITE VIEW

Page 22: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

GROUND FLOOR PLAN

SECOND FLOOR PLAN

FIRST FLOOR PLAN

TIMELINE APRIL 2016 – JULY 2016

UNDER CONSTRUCTIONEGRESS DURING

CONSTRUCTION

LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

Page 23: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

SITE VIEW

TWO CREPE MYRTLE TREES WILL BE RELOCATED

1

2

Page 24: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Excavation & Demo in Courtyard

Page 25: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Excavation & Demo in Courtyard

Page 26: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Excavation & Demo in Courtyard

Page 27: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Installation of Foundation System & Elevator Pit in Courtyard

Page 28: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Erection of Structural Steel in Cafeteria & Roof of 1956 Building

Page 29: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the District

SITE VIEW

TWO CREPE MYRTLE TREES WILL BE RELOCATED

1

2

Page 30: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Infiltration System Impact Crepe Myrtle Trees in Images

Page 31: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

CONSTRUCTION MILESTONE COMMENCEMENT OF CONCRETE WORK; OCTOBER

COMMENCEMENT OF ELEVATOR SHAFT; NOVEMBER

COMMENCEMENT OF COURTYARD STRUCTURAL STEEL; DECEMBER

Page 32: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Shepherd ES Logoin Courtyard

Page 33: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Frequently Asked Questions

1. Will the asphalt area on theplayground be repaired or replaced?Answer:- The asphalt will be repaired.

2. The Mural on the concrete wall will not be impacted by the construction Activities.

Page 34: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

NEXT STEPS TWO WEEK LOOK AHEAD EXCAVATION IN COURTYARD

FORMING & INSTALLATION OF FOUNDATION SYSTEM IN COURTYARD

ERECTION OF STRUCTURAL STEEL IN THE 1956 BUILDING

Page 35: Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –

Kenneth DiggsDGS Associate Director

DGS Government Affairs & [email protected]