Upload
consumeractiongroup
View
186
Download
0
Tags:
Embed Size (px)
Citation preview
Challenges in the Tamil Nadu Electricity Sector
Agenda
• Historical Overview• Current situation in Tamil Nadu• Challenges in the Electricity Sector
• Generation• Transmission• Distribution
• Institutional
The Past –1990’s
1990 - 2003• 1990’s- State electricity boards in a mess –
• lack of electricity generation, power cuts, no investments in critical areas.
• GoI recognized the seriousness of the situation& passed the Electricity Act in 2003• Allowing private sector participation in all areas
of the electricity sector…• It was hoped this would change the situation and
energize the electricity sector!
Tamil Nadu 2012
Unfortunately…
• Despite the reforms…• Electricity supply has not kept with Electricity
Consumption• Scheduled power cut 1 hour in Chennai• Unscheduled power cut 8-10 hours in other
parts of Tamil Nadu• Agricultural and Industrial production affected• Affecting daily lives
The Future…?
The Blame Game…
Tamil Nadu Electricity Sector
Tamil Nadu Electricity Sector was Previously a single entity – Tamil Nadu Electricity Board (TNEB)
TNEB
Disaggregated into …
Generation DistributionTransmission
HELPLESS CONSUMERS
TANGEDCO AND TANTRANSCO
Regulator - TNERC
Challenges in the Electricity Sector
•Demand: 12,000 MW
•Supply: 8000 MW
•Shortage: 4000 MW
Electricity Generation
Environmental Clearance
• Udangudi TPS (2 x 800 MW)
• Cheyyur project
Land Acquisition
BHEL’s projects in TNe.g. Vallur Thermal Power Project North Chennai Thermal Power Station
Water linkage
Tamil Nadu naturally water deficit state
Fuel linkage• Shortage of coal production
- Coal India Limited (CIL) • High cost of imported coal• Getting Right of Way
Delays & Costs overrun
• e,g, Cheyyur Power Plant
• BHEL
Transmission
•Inadequate evacuation facilities – no 400 KV transmission lines to evacuate generated capacity
•Projected T & D losses are 18.5%
•Scope of future generation projects is therefore hampered
Challenges
Transmission Congestion
• Lack of transmission capacity
• Limit the quantum of power
• E.g. Gujarat Urja Videsh Nigam Ltd. (GVNL)
Grid Stability • Consumption and overdrawal causes grid instability
• Wind, Tangedco
Distribution
Operational Costs
• Loss Rs. 200 crores everyday
• Depends on loans for paying salaries etc.
• Loses 95 paisa per unit on 3029 MU
Subsidised power
1. Agricultural sector subsidy
- Rs.250/HP/annum but now it is Rs.1750/HP/annum with a hike of about 589%
2. Hut Sector - Unmetered
Total Accumulated Loss Rs. 45,000 crores
Theft
Non-Existent Meters for Agricultural Sector And Huts
• 32,83,987 Nos.• large number of meters non-functional
• Manpower Shortage
• Lack quality and Technical knowledge
Institutional factors...
Institutional Contd…
Who will be our Saviours?????
Finally…
Nothing will change unless…Consumers demand quality service from utility
providersBy forcing the political setup to improve
electricity systems And making Tangedco accountable & Regulator
independent.