53
Electricity in Thailand: current arrangements, impacts, alternatives 2 August, 2006 ERI Chris Greacen www.palangthai.org

Electricity in Thailand: current arrangements, impacts, alternatives 2 August, 2006 ERI Chris Greacen

Embed Size (px)

Citation preview

Electricity in Thailand:current arrangements, impacts,

alternatives

2 August, 2006ERI

Chris Greacenwww.palangthai.org

Will our electricity future look like

this?

…or this?

… or this?

Natural gas

• Used to make 71% of Thailand’s electricity (among highest in world)

• Cleaner than other fossil fuels (especially SOx) but still big CO2 emissions

• Limited domestic supply.• Human rights issues in

pipeline from Burma (Yadana)

LNG terminal

Natural gas• Severe price volatility – linked to crude oil price.• Now around $0.05 to $0.07 / kWh

Coal

• Used to make 14% of Thailand’s electricity

• History of respiratory illnesses from coal smoke – Mae Mot, Lampang

• Acid rain• Worst fuel for global warming• Limited domestic supply• Cheaper (now) than natural gas

($0.04 to $0.06/kWh)• Strong environmental opposition

Big hydro

• Used to make 6% of Thailand’s electricity

• Consensus: no more big dams will be built in Thailand– Limited sites left in Thailand– Strong environmental opposition

• Environmental issues– Inundation– Fish killed– Global warming– Changes in temperature / sediment

loading / flow regime

• Can be cheap– If reasonably close to load centers

Thailand seen from altitude of 450 kilometers

Burma

Sri Nakharin dam reservoir

Khao Laem dam reservoir

Thailand seen from 54 kilometers

Sri Nakharin dam reservoir

Khao Laem dam resettlement• According to a study produced by the World Bank's

Operations Evaluations Department in 1993, 80% of people evicted by the dam "were...dissatisfied with the resettlement outcome", considering themselves "to be worse off than before resettlement".

• "We had to spend all of our compensation for living, and it wasn't enough, actually. The condition of the land here and my previous land is very different...I miss the fertile resources. I could find things for a meal. The thing that I miss most is rice. Rice is my soul. Our ancestors did rice farming for ages. But now I cannot grow rice and have to buy it, which is also very expensive ... If I could ask the officials for one thing, I would like to ask, 'Please can I return to where I was?'" – Panya Kwanprasertwaree, a Karen elder who was forced to

move because of the dam

Nuclear

• Currently not used to make any of Thailand’s electricity

• Cost uncertain– $0.02 to $0.12/kWh

• Environment & security issues– Generates materials that can

be used to make weapons– Thailand has spotty nuclear

safety record already– Waste dangerous for 250,000

years.

Thai Electricity demand is projected to grow

5000

10000

15000

20000

25000

30000

35000

40000

450001992

1994

1996

1998

2000

2002

2004

2006

2008

2010

2012

2014

2016

2018

2020

MW

Peak D

em

and

Jan 04 (MEG)

ACTUAL

What should be done to make sure that there is enough electricity?

• Natural gas interests say:– “Use more gas!” – “It’s clean(er).”

• Coal interests say:– “Use more coal” for fuel diversity– “Clean” coal– “It’s cheaper”

• Hydropower interests say:– “New dams in Lao and Burma!”– Asian Development Bank GMS grid– “Big hydro for poverty reduction!”– “It’s cheap”

• Nuclear advocates say:– “Nuclear energy is part of the ultimate answer”

Industry response…

What should be done to make sure that there is enough electricity?

ADB/World Bank response…

ADB’s Indicative Master Plan on Power Interconnect-ion in the GMS

Civil society response…

1. Fix governance problems• Transparency, accountability, public participation• Remove conflict of interest• Set up empowered, competent regulatory authority

2. More realistic demand projections3. Consider a full range of alternatives in power

development plan including:• Energy savings• Renewable energy• Combined Heat and Power

Fix governance problems: Transparency, accountability, public

participation

Fix governance problems: Remove conflict of interest

• Example: transmission shouldn’t be controlled by the same business that owns generation.

Fix governance problems: regulatory authority

• Independent– Able to think for itself

• Competent in working for public interest– Public wants reliable, affordable energy without

environmental impacts

• Empowered– Has authority to enforce the rules

Customer Efficiency

Central Generation

Centralized utilityCentralized utility(EGAT)(EGAT)

Decentralized utilityDecentralized utility(A better way)(A better way)

RemoteLoads

Wind

PV

Genset

Fuel Cell

Battery

Customers

Central Generation

21

More realistic demand projections

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

19

92

19

94

19

96

19

98

20

00

20

02

20

04

20

06

20

08

20

10

20

12

20

14

20

16

20

18

20

20

MW

Pe

ak

De

ma

nd

Jun-93

Dec-94

Oct-95

Apr-96 (High)

Oct 96 (Base)

Jun 97 (Low)

Sep 97 (Very Low)

Sep 98 (RER)

Sep 98 (MER)

Sep 98 (LER)

(Feb-01)

(Aug-02)

Jan 04 (MEG)

Apr 06 Base

ACTUAL

Alternative (04)

Jun-93

Dec-94

Oct-95

Apr-96 (High)

Oct 96 (Base)

Jun 97 (Low)

Sep 97 (Very Low)

Sep 98 (RER)

Sep 98 (MER)

Sep 98 (LER)

(Feb-01)

(Aug-02)

Jan 04 (MEG)

Apr 06 Base

ACTUAL

Alternative (04)

•Official Thai Jan 04 forecast overestimated 2006 peak demand by 1674 MW.•Lao NT2 = 995 MW

Power Development Plan(Planned installed capacity = peak demand + 15% reserve)

Options that need to be included

Options that need to be included

• Saving energy

Options that need to be included

• Saving energy

• Renewable energy

Options that need to be included

• Saving energy

• Renewable energy

• Combined heat and power (CHP)

Customer Efficiency

Central Generation

Centralized utilityCentralized utility(EGAT)(EGAT)

Decentralized utilityDecentralized utility(A better way)(A better way)

RemoteLoads

Wind

PV

Genset

Fuel Cell

Battery

Customers

Central Generation

28

Saving electricity is cheaper than generating it…

Source: The World Bank (1993)

2.12.6

4.04.9 5.0 5.1 5.2 5.5

8.2

-

2.0

4.0

6.0

8.0

10.0

DSM Hydro fromLaos

Gascombined

cycle

Lignite withFGD

Low-sulphurcoal w/o

FGD

Low-sulphur fuel

oil w/oFGD

LNG Low-sulphur

coal withFGD

Nuclear

Type of Power Plant

Co

st

of

En

erg

y (

US

ce

nts

/kW

H)

Demand Side Management (saving electricity)

Saving Energy : big potential in Thailand

• 2000 to 3000 MW: “Achievable and cost effective Demand Side Management (DSM)” in 1991 (Utility study)

Saving energySaving energy in the house: in the house: Using overhangs, trees to keep Using overhangs, trees to keep

house coolhouse cool

ที่��มา : Australian Greenhouse Office (2003)

South

Saving Energy in a typical pumping system

Source: Presentation by Ministry of Energy at Energy Strategy Workshop chaired by Prime Minister Thaksin Shinawatra. 28 August 2003

Community micro-hydro

• Mae Kam Pong village, Chiang Mai

• 1x40 kW; 2x20 kW

• Community cooperative

40 kW micro-hydro generator at Mae Kam Pong

Biogas from Pig Farms

Reduces air and water pollution

Produces fertilizer

Produces electricity

Biogas from Pig Farms

• 8 x 70 kW generators

Korat Waste to Energy - biogas

• Uses waste water from cassava to make methane

• Produces gas for all factory heat (30 MW thermal) + 3 MW of electricity

Korat Waste to Energy - biogas

• 3 x 1 MW gas generators

Rice husk fired power plant

• 9.8 MW• Roi Et province

Wind power

• Hundreds of kW to 5 MW per turbine

• Now over 15,000 MW in Germany

• Denmark gets >17% electricity from wind

• Power costs in Thailand: 4 to 6 baht/kWh

www.windpower.org

Wind Energy Wind Energy Potential MapPotential Map

Average speed Average speed 4.4 - 6.44.4 - 6.4 m/sec m/sec

Power Potential 1,600 MW

50 kW

400 W(Not to scale)

3 kW

10 kW10 kW

Solar electricity – off-grid

• 25,000 baht per household system

• 120 watts• Electricity

for 2 lights + TV

DEEP CY CLEEBB 125

3K THAI STORAGE BATTERY PUBLIC COMPANY LIMITED

3KDEEP CY CLE

EBB 1253K THAI STORAGE BATTERY PUBLIC COMPANY LIMITED

3KDEEP CY CLE

EBB 1253K THAI STORAGE BATTERY PUBLIC COMPANY LIMITED

3KDEEP CY CLE

EBB 1253K THAI STORAGE BATTERY PUBLIC COMPANY LIMITED

3KDEEP CY CLE

EBB 1253K THAI STORAGE BATTERY PUBLIC COMPANY LIMITED

3K

SH-1210M

เครื่��องควบคมการื่ปรื่ะจุแบตเตอรื่��และแปลงกรื่ะแสไฟฟ�าส�าหรื่�บรื่ะบบพล�งงานแสงอาทิ�ตย์!

เป"ด / ป"ดปล�$กไ ฟฟ�ากรื่ะแสสล�บ220 โ วลต์� 50 เฮิ�รต์ซ์�

แบต์เต์อร�� แผงร�บพล�งงานแสงอาที่�ต์ย์�

ไ ฟฟ�ากระแสสล�บ220 โ วลต์� 50 เฮิ�รต์ซ์�

FORTHSOLAR PRODUCT

สาย์ดิ�น

NL

แผงพล�งงานแสงอาทิ�ตย์!

ปานกลาง

ต��า

โหลด / เก�นพ�ก�ดโหลด

เต'ม

สภาวะการื่ทิ�า งาน

สภาวะแบตเตอรื่��

ปรื่ะจุแบตเตอรื่��

SH-1210M

เครื่��องควบคมการื่ปรื่ะจุแบตเตอรื่��และแปลงกรื่ะแสไฟฟ�าส�าหรื่�บรื่ะบบพล�งงานแสงอาทิ�ตย์!

เป"ด / ป"ดปล�$กไ ฟฟ�ากรื่ะแสสล�บ220 โ วลต์� 50 เฮิ�รต์ซ์�

แบต์เต์อร�� แผงร�บพล�งงานแสงอาที่�ต์ย์�

ไ ฟฟ�ากระแสสล�บ220 โ วลต์� 50 เฮิ�รต์ซ์�

FORTHSOLAR PRODUCT

FORTHFORTHSOLAR PRODUCT

สาย์ดิ�น

NL

แผงพล�งงานแสงอาทิ�ตย์!

ปานกลาง

ต��า

โหลด / เก�นพ�ก�ดโหลด

เต'ม

สภาวะการื่ทิ�า งาน

สภาวะแบตเตอรื่��

ปรื่ะจุแบตเตอรื่��

ปานกลาง

ต��า

โหลด / เก�นพ�ก�ดโหลด

เต'ม

สภาวะการื่ทิ�า งาน

สภาวะแบตเตอรื่��

ปรื่ะจุแบตเตอรื่��

HaCo

HaCo

10A

~ON

HaCo

HaCo

10A

~~ON

Grid connected solar electricity

• Baht 250 to 350 per watt

• VSPP program

• Baht 9 to 15 per kWh (compare to baht 2.5 per kWh from PEA)

shop.altenergystore.com

3 kW grid-connect solar electricity at EPPO office in Bangkok

Cost of renewable energy is sometimes higher than conventional

1.36 1.45 2.02 1.57 1.76

9.07

3.98

0.50

1

2

3

4

5

6

7

8

9

10

ก!าซ์ ถ่#านหิ�น น%&าม�นเต์า ชี�วมวล พล�งน%&า(เล(ก) แสงอาที่�ต์ย์� พล�งลม DSM

Pro

duct

ion

cost

(ba

ht/k

Wh)

gas coal Smallhydro

biomass solar wind Energy efficiency

Renewable energy accounts for very little of Thailands’ installed generating capacity

พล�งน%&าก!าซ์ ธรรมชีาต์�น%&าม�นเต์าดิ�เซ์ ลล�กไ นต์�ถ่#านหิ�นน%า เข้+าพล�งงานหิม,นเว�ย์นสาย์ส#งเชี-� อมไ ที่ย์-มาเลเซ์�ย์

Source: EGAT (2003). Power Development Plan

Natural gas

lignite

Big hydro

Fuel oil

0.6% grid-connected renewables

TOTAL: 26,000 MW

Imported coal

Combined Heat and Power

(CHP)… also called

“cogeneration”

CHP potential in Thailand

–8610 MW cogen installed as of 2001

–At least 3,000 MW of additional cogen had applied and have not been accepted.

Summary of alternatives

• Energy saving 2000 to 3000 MW

• Renewables > 3000 MW

• Cogeneration > 3000 MW

• Total peak load in Thailand (2006): around 21,064 MW

Civil society response…

1. Fix governance problems• Transparency, accountability, public participation• Remove conflict of interest• Set up empowered, competent regulatory authority

2. More realistic demand projections3. Consider a full range of alternatives in power

development plan including:• Energy savings• Renewable energy• Combined Heat and Power

Thank you

For more information, please contact [email protected]