158
© ABB Group September 24, 2013 | Slide 1 Lionel Ng, LPBS - Low Voltage Products Welcome To ABB Technical Sharing Session

Electrical Networking, Short Circuit Calculation, Discrimination

Embed Size (px)

DESCRIPTION

All rights reserved by ABB. For knowledge and education use only.

Citation preview

  • ABB Group September 24, 2013 | Slide 1

    Lionel Ng, LPBS - Low Voltage Products

    Welcome To ABB Technical Sharing Session

  • ABB Group September 24, 2013 | Slide 2

    MV & LV Transformer Substations Theory & Short Circuit Calculation

  • Contents

    General information on MV/LV transformer substations Calculation of short-circuit currents Choice of protection and control devices Example of study of a MV/LV network

  • The electrical substations can be divided into public substations

    belong to the electricity utility supply private users in AC single-phase or three-phase current

    (230V and 400V)

    urban type in bricks rural type installed externally directly on the MV pylon

    private substations belong to the user civil users (schools, hospitals, etc.) and industrial users are mostly located in the same rooms of the factory

    General Information MV/LV Transformer Substations

  • Typical structure of a substation where the switching apparatus of

    the utility is installed.

    where the measuring units

    are located

    contains the transformer and

    the MV and LV switching

    apparatus

    General Information MV/LV Transformer Substations

  • Most common management methods

    Substation with a single transformer

    General Information MV/LV Transformer Substations

  • Most common management methods

    Substation with two transformers

    (one as a spare for the other)

    It is possible to use the

    Emax with a wire interlock

    (mechanical interlock)

    between two CBs

    General Information MV/LV Transformer Substations

  • Most common management methods

    two transformers which operate

    in parallel on the same busbar

    General Information MV/LV Transformer Substations

  • two transformers which operate simultaneously on

    two separate half-busbars

    Most common management methods

    General Information MV/LV Transformer Substations

    It is possible to use the

    Emax with a wire interlock

    (mechanical interlock)

    between three CBs

  • MV/LV transformers is the most important part of the transformer substation single transformer for low powers (up to 630kVA - 800kVA) several units in parallel for higher powers (1000kVA - 2500kVA) type of cooling system

    air oil

    most used AN cooling with natural air circulation ONAN cooling with natural oil and air circulation types

    General Information MV/LV Transformer Substations

  • ONAN transformer containing more than 500 kg of oil (> 800kVA)

    General Information MV/LV Transformer Substations

    MV/LV transformers

  • MV/LV transformers one single trafo or two trafos in parallel?

    U U750M

    VA

    400V

    1600kVA

    6% 800kVA

    4%

    800kVA

    4%

    400V

    750M

    VA

    37 kA 55kA

    General Information MV/LV Transformer Substations

  • Management philosophy for the protections L1 trip ensured service continuity

    General Information MV/LV Transformer Substations

  • Management philosophy for the protections ILV1 and CLV trip power supply is maintained to the half-busbar

    trip

    trip

    General Information MV/LV Transformer Substations

  • Management philosophy for the protections IMV1 and ILV1 trip to isolate the trafo affected by the fault ensured service continuity a logic for the disconnection of non-priority loads should be

    foreseen

    General Information MV/LV Transformer Substations

  • Management philosophy for the protections IMV1 trip, ILV1 trip for pulling service continuity of the whole plant a logic for the disconnection of non-priority loads should be

    foreseen

    General Information MV/LV Transformer Substations

  • LV protection devices

    L function protection against

    overload

    General Information MV/LV Transformer Substations

  • S function protection against

    delayed short-circuit

    LV protection devices

    General Information MV/LV Transformer Substations

  • I function protection

    against instantaneous

    short-circuit

    LV protection devices

    General Information MV/LV Transformer Substations

  • G function protection

    against earth-fault

    LV protection devices

    General Information MV/LV Transformer Substations

  • IEC 60909-0 (CEI 11-25) Short-circuit:

    Accidental or intentional conductive path between two or more conductive parts forcing the electric potential differences between

    these conductive parts to be equal or close to zero

    Short-circuit current: Overcurrent resulting from a short-circuit in an electric system

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • Main components involved in a short-circuit calculation Distribution networks Generators Transformers Asynchronous motors Cables

    Each component of the network is replaced by its relevant impedance

    U

    Zknet ZcMV ZTR ZcLV

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • The equivalent network is solved according to standard electrotechnical rules (circuits in series / in parallel)

    cLVTRcMVknetn

    kZZZZ3

    UI

    Un

    Zknet

    ZcMV

    ZTR

    ZcLV

    Ik

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • Distribution network it is necessary to know the network short-circuit power

    from 250MVA to 500MVA Un 30kV from 700MVA to 1500MVA Un > 30kV according to IEC 60076-5

    knet

    n

    knet

    2n

    knetI3

    U

    S

    UZ

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • Generators it is necessary to know

    rated apparent power Sn rated voltage Un subtransient reactance xd

    from 10% to 20% smooth rotor (isotropic machines) from 15% to 30% salient pole rotor (anisotropic machines)

    n

    2n

    "d"

    dS

    U

    100

    xX

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • Transformer it is necessary to know

    rated apparent power Sn primary rated voltage voltage U1n secondary rated voltage U2n short-circuit voltage uk%

    from 4% to 8%

    according to IEC 60076-5

    n

    2n2%k

    TRS

    U

    100

    uZ

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • Asynchronous motors In case of short-circuit it functions as a

    generator with a xd from 20% to 25% a current equal to 4-6 times the In can be

    assumed as contribution to the short-circuit

    the minimum criteria for taking into consideration the phenomenon

    (Ik shortcircuit without motor contribution)

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • Example

    USk = 500 MVA UMV= 20 kV

    ZcMV = 0.01

    Sn = 400 kVA

    U= 20/0.4 kV

    uk% = 4 %

    ZcLV = 0.06

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • U Sk = 500 MVA

    UMV= 20 kV Zu = 0.32

    m

    8.0

    10500

    1020

    S

    UZ

    6

    23

    k

    2

    kV20u

    42

    2

    kV20uV400u 102.320000

    400ZZ

    Example

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • UZu = 0.32 m

    62

    2

    kV20cMVV400cMV 10420000

    400ZZ

    ZcMV = 410-3 m

    ZcMV = 0.01

    Example

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • UZu = 0.32 m

    ZcMV = 410-3 m

    Sn = 400 kVA

    U= 20/0.4 kV

    uk% = 4 %

    016.0

    10400

    400

    100

    4

    S

    U

    100

    uZ

    3

    2

    n

    2nLV%k

    T

    ZT = 0.016

    Example

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • UZu = 0.32 m

    ZcMV = 410-3 m

    ZT = 16 m

    ZcLV = 0.61 m ZcLV = 0.61

    m

    Example

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • U Sk = 500 MVA

    UMV= 20 kV Zu = 0.32 m

    ZcMV = 410-3 m

    ZT = 16 m

    ZcLV = 0.61 m

    Un = 400 V

    kA1.14

    ZZZ3

    UI

    TcMVu

    nk

    kA6.13

    ZZZZ3

    UI

    cLVTcMVu

    nk

    Example

    MV/LV Transformer Substations Calculation of Short Circuit Currents

  • ABB Group September 24, 2013 | Slide 34

    MV & LV Transformer Substations General Information about Circuit Breakers

  • Definitions

    Circuit-breaker: a mechanical switching device capable of making,

    carrying and breaking currents under normal circuit conditions and

    also making, carrying for a specified time, and breaking currents

    under specified abnormal circuit conditions such as those of

    overload or short-circuit (IEC 60947-1 def. 2.2.11)

    MV/LV Transformer Substations IEC Standard Definition of Circuit Breakers

  • Definitions

    Moulded case CB: a circuit-breaker having a supporting

    housing of moulding insulating material forming an

    integral part of the circuit-breaker (Isomax / Tmax /

    Formula)

    Air CB: a circuit-breaker in which the contacts open and

    close in air at atmospheric pressure (Emax)

    MV/LV Transformer Substations IEC Standard Definition of Circuit Breakers

  • Definitions

    Current-limiting circuit-breaker: a circuit-breaker with a

    break-time short enough to prevent the short-circuit

    current reaching its peak value (IEC 60947-2 def. 2.3)

    MV/LV Transformer Substations IEC Standard Definition of Circuit Breakers

  • Prospective

    peak value

    Limited

    peak

    value

    Prospective short-

    circuit current Limited short-circuit

    current

    Specific let-through

    energy (I2t)

    I

    t

    MV/LV Transformer Substations Current-Limiting Circuit Breakers

  • Prospecti

    ve peak

    value Limited

    peak

    value

    Prospective short-

    circuit current Limited short-

    circuit current

    Specific let-through

    energy

    I

    t

    I2t

    Icc

    Ip

    Icc

    go

    MV/LV Transformer Substations Current-Limiting Circuit Breakers

  • 1E-2kA 0.1kA 1kA 10kA

    1kA

    10kA

    100kA

    1E3kA

    1E4kA

    1E5kA

    Curva di limitazione

    40 kA

    T2L160 In160 A

    40 kA

    16 kA

    84 kA

    Irms

    Ip

    Prospective

    peak value

    Limited peak

    value

    MV/LV Transformer Substations Current-Limiting Circuit Breakers

  • Generalities about the main electrical parameters Rated operational voltage Ue: the value of voltage which

    determines the application and to which all the other

    parameters are referred to

    Rated uninterrupted current Iu: the value of current which the device is able to carry for an indefinite time. It defines the size

    of the CB

    Rated current In: the value of current which characterizes the protection release installed. Is often related to the rated

    current of the load protected

    MV/LV Transformer Substations Selection of Protective Devices

  • Generalities about the main electrical parameters Rated ultimate short-circuit breaking capacity Icu: it is the

    r.m.s. value of the symmetrical component of the short-circuit

    current which the circuit-breaker is able to break (test cycle O-

    t-CO)

    Rated service short-circuit breaking capacity Ics: it is the r.m.s. value of the symmetrical component of the shortcircuit current

    which the circuit-breaker is able to break (O-t-CO-t-CO)

    T5N400 PR221DS-LS/I In 320

    Icu

    MV/LV Transformer Substations Selection of Protective Devices

  • MV/LV Transformer Substations Selection of Protective Devices

    Ultimate Short-Circuit Breaking Capacity (Icu):

    breaking capacity for which the prescribed conditions

    according to a specified test sequence do not include

    the capability of the CB to carry its rated current

    continuously

    - test sequence: O - 3 min - CO

    - dielectric withstand at 2 x Ue

    - verification of overload release at 2.5 x I1

  • MV/LV Transformer Substations Selection of Protective Devices

    Service Short-Circuit Breaking Capacity (ICS):

    breaking capacity for which the prescribed conditions

    according to a specified test sequence include the

    capability of the CB to carry its rated current continuously

    - test sequence: O - 3 min - CO - 3 min CO (25%-50%-75%-100% of Icu)

    - operational performance capability: (5% of Noperating cycle for operational performance capability- table 8 60947-2)

    - dielectric withstand at 2 x Ue

    - verification of temperature rise at Iu (the temperature doesnt exceed the limits of table 7 60947-2)

    - verification of overload release at 1.45 x I1

  • Generalities about the main electrical parameters Rated short-circuit making capacity Icm: it is the maximum

    prospective peak current which the circuit-breaker must be

    able to make Icm=n x Icu

    T5N400 PR221DS-LS/I In 320

    Icu 36kA Icm 75.6 kA @415V

    MV/LV Transformer Substations Selection of Protective Devices

  • Generalities about the main electrical parameters Rated short-time withstand current Icw: it is the r.m.s. value of

    the alternate current component which the circuit-breaker is

    able to withstand without damages for a determined time,

    preferred values being 1s and 3 s

    Defined for category B only

    MV/LV Transformer Substations Selection of Protective Devices

  • MV/LV Transformer Substations Selection of Protective Devices

  • Generalities about the main electrical parameters Dont forget

    Ue Un Icu or Ics Ik Icm Ip

    Ue, Icu, Ics, Icm?

    MV/LV Transformer Substations Selection of Protective Devices

  • Protection of feeders against overload

    Ib In or I1 Iz

    against short-circuit I2t k2S2

    In

    Iz S

    Ib

    MV/LV Transformer Substations Selection of Protective Devices

  • MV/LV Transformer Substations Selection of Protective Devices

  • MV/LV Transformer Substations Selection of Protective Devices

  • Protection of generators Ingen I1 I3 or I2 2.5-4 x Ingen

    G

    MV/LV Transformer Substations Selection of Protective Devices

  • Protection of transformers InT I1 Upstream CB

    I3 or I2 Iinrush

    MV/LV Transformer Substations Selection of Protective Devices

  • Steps determining the short-circuit

    currents

    choosing the CB setting of the MV overcurrent

    protection setting of the LV overcurrent

    protection

    20kV

    400V

    MV/LV Transformer Substations Example of an MV/LV Network

  • 20kV

    400V

    MV/LV Transformer Substations Example of an MV/LV Network

  • 20kV

    400V

    MV/LV Transformer Substations Example of an MV/LV Network

  • ABB Group September 24, 2013 | Slide 57

    Low voltage selectivity with ABB circuit breakers Selectivity definitions and Standards

  • Definitions and Standards

    Selectivity techniques

    Definitions and Standards

    Back-up protection

    Agenda Low voltage selectivity with ABB circuit breakers

  • Selectivity (or discrimination)

    is a type of coordination of two or

    more protective devices in series.

    Selectivity is done between

    one circuit breaker on the supply side

    and one circuit breaker, or more than

    one, on the load side.

    A is the supply side circuit

    breaker (or upstream)

    B and C are the load side circuit

    breakers (or downstream)

    Introduction What is selectivity?

  • Better selectivity

    FAULT CONTINUITY OF SERVICE DAMAGE REDUCTION

    Fast fault elimination

    Reduce the stress and prevent damage

    Minimize the area and the duration of power loss

    Introduction Protection system philosophy

  • Selective coordination among devices

    is fundamental for economical and technical reasons

    It is studied in order to:

    rapidly identify the area involved in the problem;

    bound the effects of a fault by excluding just the affected zone of the network;

    preserve the continuity of service and good power quality to the sound parts of the network;

    provide a quick and precise identification of the fault to the personnel in charge of maintenance or to management system, in order to restore the service as rapidly as possible;

    achieve a valid compromise between reliability, simplicity and cost effectiveness.

    Main purposes of coordination Selectivity purpose

  • The definition of selectivity

    Trip selectivity (for overcurrent) is a coordination between the operating characteristics of two or more overcurrent protection

    devices, so that, when an overcurrent within established limits

    occurs, the device destined to operate within those limits trips

    whereas the others do not trip

    IEC 60947-1 Standard: Low voltage equipment

    Part 1: General rules for low voltage equipment

    Standards definition Selectivity

    IEC 60947-1

    def. 2.5.23

  • In occurrence of a fault

    (an overload or a short circuit)

    if selectivity is provided

    only the downstream circuit

    breaker opens.

    Overcurrent selectivity Example

  • All the system is out of service!

    In occurrence of a fault

    (an overload or a short circuit)

    if selectivity is not provided

    both the upstream and the

    downstream circuit breakers

    could open

    Overcurrent selectivity Example

  • A and B connected in series:

    partial selectivity and total selectivity.

    Standards definition Partial and total selectivity

    IEC 60947-2

    def. 2.17.2 - 2.17.3

  • Partial selectivity is an overcurrent selectivity where, in the presence of two protection devices against overcurrent in series,

    the load side protection device carries out the protection up to a

    given level of overcurrent, without making the other device trip.

    B opens only according to fault current

    lower than a certain current value;

    values equal or greater than Is

    will give the trip of both A and B.

    Is is the ultimate

    selectivity

    value!

    Is = ImA

    Standards definition Partial selectivity

  • Only B trips for every current value

    lower or equal to the maximum

    short-circuit current.

    Total selectivity is an overcurrent selectivity where, in the presence of two protection devices against overcurrent in series,

    the load side protection device carries out the protection without

    making the other device trip.

    B A

    Is = Ik

    Standards definition Total selectivity

  • Upstream circuit breaker A

    T4N 250 PR221DS In = 250 (Icu = 36kA)

    Downstream circuit breaker B

    S 294 C100 (Icu = 15kA)

    Standards definition Partial and total selectivity

  • Overload zone

    Thermal protection

    L protection

    Short-circuit zone

    Magnetic protection

    S, D, I and EF protections

    Time-current selectivity

    Current, time, energy, zone,

    directional, zone directional selectivity

    Selectivity analysis Time-current curves

  • Real currents circulating through the circuit breakers

    I> A

    B I> I> I>

    A

    B

    I>

    I>

    I>

    I> I>

    A

    B

    I>

    I>

    IA = IB

    IA IB

    tA

    tB

    tA

    tB

    IA IB IA=IB

    tA

    tB

    IA = IB + Iloads

    IA = (IB + Iloads) / 2

    Selectivity analysis Real currents

  • ABB Group, BU Breakers and Switches September 24, 2013 | Slide 71

    Definitions and Standards

    Selectivity techniques Selectivity techniques

    Back-up protection

    Agenda Low voltage selectivity with ABB circuit breakers

  • ABB Group, BU Breakers and Switches September 24, 2013 | Slide 72

    Current selectivity

    Time selectivity

    Energy selectivity

    Zone (logical) selectivity

    Introduction Selectivity techniques

  • The ultimate selectivity value

    is equal to the instantaneous trip threshold

    of the upstream protection device

    Other methods are needed to have a total

    selectivity

    A B

    ImB ImA

    Current selectivity: closer to the power supply

    the fault point is, higher the fault current is

    In order to guarantee selectivity,

    the protections must be set to different

    values of current thresholds

    Ultimate

    selectivity

    value

    1kA

    3kA

    tB

    tA

    tA

    Current selectivity Base concept

  • A

    B

    Here the selectivity is a total selectivity,

    because it is guaranteed up to the maximum

    value of the short-circuit current, 1kA.

    Circuit breaker A will be set to a value which does not

    trip for faults which occur on the load side of B.

    (I3Amin >1kA)

    Circuit breaker B will be set to trip for faults which

    occur on its load side (I3Bmax < 1kA)

    0.1kA 1kA 10kA

    10-2s

    10-1s

    1s

    10s

    102s

    103s

    104s

    3kA

    Is Is = I3Amin

    Current selectivity Example

  • Plus

    Easy to be realized

    Economic

    Instantaneous

    Minus

    Selectivity is often only partial

    Current thresholds rise very quickly

    CURRENT SELECTIVITY

    Current selectivity Plus and minus

  • Time selectivity is based on a trip delay of the upstream

    circuit breaker, so to let to the downstream protection the

    time suitable to trip

    B A

    Setting strategy:

    progressively increase the

    trip delays getting closer to

    the power supply source

    On the supply side

    the S function is required

    Time selectivity Base concept

  • 0.1kA 10kA 100kA

    10-2s

    10-1s

    1s

    10s

    102s

    103s

    104s

    1kA

    The ultimate selectivity value is:

    Is = IcwA (if function I = OFF)

    Is = I3minA (if function I = ON)

    Ik

    A will be set with the current threshold I2

    adjusted so as not to create trip overlapping

    and with a trip time t2 adjusted so that

    B always clears the fault before A

    B will be set with an instantaneous trip

    against short-circuit

    B

    I2

    t2

    Is

    Time selectivity Example

  • 0.1kA 10kA 100kA

    10-2s

    10-1s

    1s

    10s

    102s

    103s

    104s

    1kA

    The network must withstand high values of

    let-through energy!

    If there are many hierarchical levels, the

    progressive delays could be significant!

    Ik

    Which is the problem of time selectivity?

    In the case of fault occurring at the busbars,

    circuit breaker A takes a delayed trip time t2

    B

    t2

    Time selectivity Example

  • Plus

    Economic solution

    Easy to be realized

    Minus

    TIME SELECTIVITY

    Time selectivity Plus and minus

    Quick rise of setting levels

    High values of let-through energy

  • Energy selectivity is based on the current-

    limiting characteristics of some circuit breakers

    A

    B

    0.1kA 1kA 10kA

    10-2s

    10-1s

    1s

    10s

    102s

    103s

    104s

    Current-limiting circuit breaker

    has an extremely fast trip time,

    short enough to prevent the

    current from reaching its peak The ultimate current

    selectivity values

    is given by the

    manufacturer

    (Coordination tables)

    Energy selectivity Base concept

  • 1kA 10kA 0.1kA 10-2s

    10-1s

    1s

    10s

    102s

    103s

    104s

    Circuit breaker A conditions:

    I3=OFF

    S as for time selectivity

    A

    B

    Is = 20kA

    Energy selectivity Example

  • PLUS

    MINUS

    ENERGY SELECTIVITY

    Energy selectivity Plus and minus

    High selectivity values

    Reduced tripping times

    Low stress and network disturbance

    Increasing of circuit breakers size

  • Zone selectivity is an evolution of the time

    selectivity, obtained by means of a electrical

    interlock between devices

    The circuit breaker which detects a fault

    communicates this to the one on the supply side,

    sending a locking signal

    Fault

    locking

    signal

    Only the downstream circuit breaker opens,

    with no need to increase the intentional time

    delay

    Zone selectivity Base concept

  • A Does Not Open

    B Does Not Open

    C Opens

    A

    B

    C

    Zo

    ne 1

    Z

    on

    e 2

    Z

    on

    e 3

    Zone selectivity Example

  • Is up to 100kA for Tmax

    Is up to Icw for Emax

    It is possible to obtain zone selectivity between Tmax and Emax

    Zo

    ne

    1

    Zo

    ne

    2

    Zo

    ne

    3

    Zone selectivity needs:

    a shielded twisted pair cable

    an external source of 24V

    dedicated trip units

    PR223EF for Tmax T4, T5 and T6

    PR332/P for Tmax T7 and T8

    PR122/P and PR123/P for Emax

    PR332/P and PR333/P for X1

    Zone selectivity Specifications

  • PLUS

    MINUS

    ZONE SELECTIVITY

    Zone selectivity Plus and minus

    Trip times reduced

    Low thermal and dynamic stress

    High number of hierarchical levels

    Can be made between same size circuit breakers

    Cost and complexity of the installation

    Additional wiring and components

  • ABB Group, BU Breakers and Switches September 24, 2013 | Slide 87

    Definitions and Standards

    Selectivity techniques

    Back-up protection Back-up protection

    Agenda Low voltage selectivity with ABB circuit breakers

  • Back-up protection (or cascading)

    is a type of coordination of two protective

    devices in series which is done in electrical

    installations where continuous operation is

    not an essential requirement.

    Back-up protection What is back-up protection?

    Back-up protection

    excludes the use

    of selectivity!!!

  • The definition of back-up is given by the

    Back-up is a coordination of two overcurrent protective devices in series, where the protective device on the supply

    side, with or without the assistance of the other protective

    device, trips first in order to prevents any excessive stress on

    downstream devices.

    IEC 60947-1 Standard: Low voltage equipment

    Part 1: General rules for low voltage equipment

    Back-up protection Standards definition

    IEC 60947-1

    def. 2.5.24

  • Back-up is used by those who need

    to contain the plant costs

    The use of a current-limiting circuit

    breaker on the supply side

    permits the installation of lower performance

    circuit breakers on the load side

    Both the continuity of service and the selectivity are sacrificed

    Back-up protection Base concept

  • T4L 250

    T1N 160 T1N 160 T1N 160

    Ik = 100 kA

    T4L 250 T4L 250 T4L 250 Icu = 120kA

    Icu = 36kA

    Icu (T4L+T1N) = 100kA

    Back-up protection Application example

  • Back-up protection tables

  • T4L 250

    T1N 160 T1N 160 T1N 160

    Ik = 100kA

    Icu (T4L+T1N) = 100kA

    Ik = 100kA

    A

    B C D

    Back-up protection Application example

    General power supply

    is always lost

  • Plus

    Economic solution

    Quick tripping times

    Minus

    No selectivity

    Low power quality

    BACK-UP PROTECTION

    Back-up protection Plus and minus

  • Incoming = T5H 630A (70kA

    rating) Outgoing = T3N 160A

    (36kA rating)

    Results: The co-ordination

    resulted in a conditional short-

    circuit of 65kA for the T3 mccb!

    The discrimination is up to 20kA.

    Example of Selectivity

    Iz

    T5H 630A 70kA

    T3N 160A 36kA

    65kA

    ~

  • Example of Selectivity

    Discrimination

  • Example of Selectivity

    Back-Up

  • T5H 70kA

    T3N 36kA

    Example of Selectivity Meaning of Selectivity Value

    T3N 36kA

    T5H 70kA

    Y is 20kA

    Fault level at Y is 20kA

  • T3N 36kA

    T5H 70kA

    T5H

    T3N 20kA

    Example of Selectivity Meaning of Selectivity Value

  • 5kA

    T5H T3N

    5kA fault ON Trip

    T3N 36kA

    T5H 70kA

    Example of Selectivity Meaning of Selectivity Value

  • T5H T3N

    5kA fault ON Trip

    10kA fault ON Trip

    10kA

    T3N 36kA

    T5H 70kA

    Example of Selectivity Meaning of Selectivity Value

  • T3N 36kA

    20kA

    T5H 70kA T5H T3N

    5kA fault ON Trip

    10kA fault ON Trip

    20kA fault Trip Trip

    Example of Selectivity Meaning of Selectivity Value

  • T3N 36kA 36kA

    T5H 70kA T5H T3N

    5kA fault ON Trip

    10kA fault ON Trip

    20kA fault Trip Trip

    36kA fault Trip Trip

    Example of Selectivity Meaning of Selectivity Value

  • T3N 65kA

    T5H 70kA T5H T3N

    5kA fault ON Trip

    10kA fault ON Trip

    20kA fault Trip Trip

    36kA fault Trip Trip

    65kA fault Trip Trip

    36kA

    Example of Selectivity Meaning of Selectivity Value

  • Motor co-ordination ABB offers co-ordination tables

    MV/LV Transformer Substations Selection of Protective & Control Devices

  • Co-ordination between CBs and switch-disconnectors

    T2S160

    T1D160

    400V

    MV/LV Transformer Substations Selection of Protective & Control Devices

  • ABB Group September 24, 2013 | Slide 107

    DOC Electrical Installation Calculation and Dimensioning

  • Contents

    Introduction Aim of the application Target users Products managed How it works Features Support Tools ABB Software Desktop Assistance How to obtain the software

  • ABB Group September 24, 2013 | Slide 109

    DOC Introduction

  • Aim of the application

    DOC is the software for Electrical Installations Calculation

    and Dimensioning

    Draw single-line diagrams

    Perform electrical calculation according to the

    Standards

    Choose the correct switching and protecting devices

    (MV and lv devices)

    Set the trip units and check for discrimination

    Prepare a complete project documentation

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Target user

    DOC is complete and precise, but smart and flexible and

    can be used from everyone interested in calculating

    electrical installation or part of them

    Consultants

    Electrical Engineers

    Panel builders

    Installers

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    DOC allows and the selection of a wide range of ABB

    Products

    Medium Voltage products

    Low Voltage products

    Motors

    Transformers

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Air Circuit- Breakers

    New Emax

    Emax

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Molded Case Circuit Breakers

    Tmax

    Isomax

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Miniature Circuit Breakers

    System PRO M

    System PRO M Compact

    S800

    Smissline

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    RCCBs

    System PRO M

    System PRO M Compact

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Fuses

    OFAX

    OFASB

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Switch Fuses

    E930

    OESA

    OS

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Disconnectors

    New Emax MS

    Emax MS

    Tmax D

    Isomax D

    OT

    OETL

    E200

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Contactors

    A

    AF

    EN

    ESB

    E250

    E259

    E260

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Manual Motor Starter

    MS116, MS325, MS450, MS495, MS496

    MO325, MO450, MO495, MO496 , MO497

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Low Voltage Products

    Thermal Overload

    TAxxDU, ExxDU

    UMC-22

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Medium Voltage Products

    Circuit breaker

    Secondary distribution SF6 and Vacuum up to 24kV 630A 16kA

    Primary distribution SF6 and Vacuum up to 36kV 3150A 50kA

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Medium Voltage Products

    Circuit breaker

    REF542Plus/DK

    PR521/DK

    PR521/P (50-51)

    PR521/P (50-51-51N)

    REF542Plus

    REF610

    REJ525

    PR512/P (50-51)

    PR512/P (50-51-50N-51N)

    PR512/PD

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Medium Voltage Products

    Disconnectors

    SHS2/A

    SHS2/I

    SHS2/IB

    SHS2/IF

    SHS2/N-I

    Earth Disconnectors

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Medium Voltage Products

    Switch Disconnectors

    SHS2/T1

    SHS2/T1M

    SHS2/T2

    SHS2/T2F

    SHS2/T2M

    SHS2/T2MF

    SHS2/N-T1

    SHS2/N-T1M

    SHS2/N-T2

    SHS2/N-T2F

    SHS2/N-T2M

    SHS2/N-T2MF

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Medium Voltage Products

    General Purpose Fuses

    CEF 7.2kV 200A

    CEF 12kV 125A

    CEF 17.5kV 100A

    CEF 24kV 80A

    Motor Fuses

    CEM 7.2kV 315A

    CEM 12kV 100A

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Medium Voltage Products

    Cables

    Sized according to

    the ABB

    XLPE Cable Systems

    Users Guide"

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Product managed

    Other Products

    Motors

    M2xxx

    M3xxx

    Transformers

    Oil Distribution Transformers

    RESIBLOC

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • How it works DOC How it Works

  • Features - Professional and Light Profiles

    DOC can be used with 2 different profiles

    Depending on the user needs and skills it can be recommended to use

    the Light Profile which hides the advanced and complex features

    DOC Light is for ...

    ... first time, unskilled DOC users

    ... installers panel builders

    who need a simple tool to draw

    and verify small networks

    DOC Professional is for ...

    ... skilled DOC users

    ... customers working on industrial

    applications

    ... engineering companies

    OEMs looking for a powerful

    calculation and design tool

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Single line diagram drawing

    Different layout available:

    Blank Page

    More flexible

    Allows representing rings and meshes

    Main project data available beside the objects

    Column Page

    Faster and easier drawing

    Main project data available in the grid

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Single line diagram drawing

    Different ways to draw the symbols:

    By Single Objects

    More flexible

    Allows representing rings and meshes

    By Macros

    Faster and easier drawing

    Note: it is possible to use Single Objects

    and Macros independently from the layout

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Single line diagram drawing

    When using the Column layout, Objects are numbered by Page &

    Column

    All the object in the same feeder have the same number

    I.e: Page =1, Column=3 leads to QF1.3+ WC1.3 +L1.3

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Single line diagram drawing

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    It is possible to draw one scheme on more than one page

    Use the Add Sheet and Change layout commands to prepare new empty

    pages

    Use the Cross References to connect two objects

    Use the Previous/Next Sheet commands to turn the pages

  • Features - Plant General Properties Window

    This window is shown when starting a new project. Set all the options

    carefully to spare time when drawing and calculating the electrical

    installation

    Main options: Power supply definition

    Voltage level

    Default distribution system

    Default number of phases

    Method for SC calculations

    Method for cable sizing

    Options for addressing the device

    selection

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Suggested Workflow

    A toolbar on the right side of the working area suggests the preferred

    way to develop a project with DOC

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    MV diagram drawing

    LV diagram drawing

    Calculation and automatic project dimensioning

    Protection and discrimination verification thru the curves

    Auxiliaries scheme drawing

    Switchboard configuration

    Printouts

  • Features - MV Diagram Drawing

    The Medium Voltage section of the project can be drawn by the Macros

    of the typical units of the Unimix switchboard or by Objects for more

    flexibility

    To pass to the Low Voltage section it is necessary to use the

    transformers (when a low voltage section is not needed, the drawing

    can be completed with MV Loads or Motors)

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Lv Diagram Drawing

    The Low Voltage section of the project can be drawn by the Macros or

    by Objects for more flexibility

    The Macros available represents the most common Objects

    combinations; not available combinations can be realized using the

    Objects

    1 Macro = 1 Feeder = Many

    single objects

    I.e.: CB+Cable+Load

    I.e.: Fuse+Cable+Load

    Faster drawing

    Pop-up window

    When drawing a feeder it is

    possible to insert the main

    data making the drawing phase faster

    Power Supply

    Switchboard Arrival

    Sub-Switchboard

    Interlock graphical representation

    Feeders

    Motor Coordination

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features - Calculation and automatic dimensioning

    Load-Flow

    DOC can calculate the current distribution, the voltage profile

    and the voltage drop profile in load condition considering:

    Section with different number of phases

    Unbalanced loads (automatic balance is optional)

    Transformer Voltage Regulator

    Cable dimensioning

    Presence of meshes

    More distribution systems

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Cable dimensioning

    Given the power required by the loads and the motors, DOC is

    able to size the cables in an iterative process bringing to the

    section optimization and the current profile calculation

    DOC implements several calculation methods

    IEC 60364

    CEI 64-8 Italian standard

    VDE 298 German standard

    NFC 15-100 French standard

    UNE 20460 Spanish standard

    IEC 60092 (for naval installation)

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Features - Calculation and automatic dimensioning

  • Short Circuit

    DOC can calculate the maximum and minimum short

    circuit currents, with or without the motor contribution,

    for symmetrical and non-symmetrical faults, for different

    times

    DOC implements several calculation methods

    IEC 60909 LV\MV network, AC, 50-60Hz

    IEC 60363 Naval

    NFC 15-100 French national standard

    Symmetrical components method

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Features - Calculation and automatic dimensioning

    ABB SACE A Division of ABB S.p.A., MK-TO, 2009 June

  • Configuration Management

    In DOC it is possible to simulate different

    scenarios for the electrical

    installation defining the

    open/closed position for

    the switching and

    protecting devices

    The calculation are

    performed in the worst

    condition

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Features - Calculation and automatic dimensioning

  • Devices Selection

    The calculation leads to an automatic proposal for all

    the devices drawn in the scheme

    When more than one product is technically suitable,

    DOC proposes the basic one

    It is possible to change the solution proposed by DOC

    and to lock the user choice thanks to the padlocks

    present in all the selection windows

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Features - Calculation and automatic dimensioning

  • DOC gives the possibility to perform the temperature rise-

    assessment according to IEC 60890 in a early stage of the

    installation design

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Features - Calculation and automatic dimensioning

  • Features - Curves

    With DOC it is possible to manage

    Time-current diagrams for the devices present in the scheme

    Set the thermomagnetic and electronic trip units

    Realize discrimination studies involving MV and LV devices

    Verify the cable protection

    1E-2kA 0.1kA 1kA 10kA 100kA

    1E-2s

    0.1s

    1s

    10s

    100s

    1E3s

    1E4s

    Time-Current curve LLL

    -QF2, HD4/UniMix-R 24.06.12 P230, REF542Plus/DK

    -TM1

    -QF5, E4S 4000 PR121-LI 4000A

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Features Switchboard configuration

    With DOC it is now possible to configure switchboard:

    By using a Wizar configuration: three steps guide procedure to create a

    switchboard.

    By using a toolbar on the left side of working area:

    Insert and move column, Kit and device

    Tracking busbar system and temperature rise assessment

    Layer management (door, panel and plate layer, show hide busbars)

    Modify switchboard dimension

    Smart commands (switchboard table, labels, accessories)

  • Features - Project documentation

    Different reports sections allows the creation of a unique file

    documenting the project

    The report sections can be added/removed according to the needs

    Calculation hypothesis

    Short circuit calculations

    Cable Protections

    MV / LV devices list and settings

    Export in MS Excel is available

    The report language can be different from the current language

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Support Tools DOC Support Tools

  • ABB Software Desktop

    ABB Software Desktop (ASD)

    ASD is automatically installed with the first installed software

    ASD functionalities:

    Allows to run the software

    Manage the language

    Registration

    Software upgrade

    Contact Software Support

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • ABB Group September 24, 2013 | Slide 152

    ABB Software Desktop

    Registration Visit www.bol.it.abb.com

    Click on Profile Management

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Starting on a New

    Project The Single Line Diagram

  • ABB Group September 24, 2013 | Slide 153

    ABB Software Desktop

    Registration Click on New User

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Starting on a New

    Project The Single Line Diagram

  • ABB Group September 24, 2013 | Slide 154

    ABB Software Desktop

    Registration Click on Subscribe

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Starting on a New

    Project The Single Line Diagram

  • ABB Software Desktop

    Registration

    After registering via internet ,

    you will receive immediately

    an e-mail with ID and PSW

    to access the Upgrade

    Service

    Use them to check for

    available Upgrades before

    starting using the Software

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • Upgrade DOC via internet

    ABB Software Desktop

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

    Use The Automatic Upgrade

    Service allows you to

    maintain the software

    aligned to the latest

    improvements delivered

    from ABB SACE them to

    check for available

    Upgrades before starting

    using the Software

  • Assistance

    How to contact us Software support

    Ask the ABB SACE Software Assistance for any question you may

    have regarding the software tools

    Email

    [email protected]

    Call Center

    +39 035 395 570

    On line

    http://www.bol.it.abb.com

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software

  • How to obtain the software

    Refer to the ABB Local Sales Organization for a free copy of the

    software

    Introduction Aim of the application

    Target users

    Product managed

    How it works Features

    Support Tools ASD

    Assistance

    How to obtain the

    software