El Rio Watercourse Master Plan. City of Avondale Council Meeting August 5, 2013. EL Rio Watercourse Master Plan. Purpose - Adopt a Resolution Authorizing an IGA: Maricopa County (Flood Control), Buckeye, and Goodyear Cost Sharing, Planning, Analysis, and Preparation. - PowerPoint PPT Presentation
Citation preview
El Rio Watercourse El Rio Watercourse Master PlanMaster Plan
City of Avondale Council City of Avondale Council Meeting August 5, 2013Meeting August 5, 2013
EL Rio Watercourse Master Plan
• Purpose - Adopt a Resolution• Authorizing an IGA: Maricopa County (Flood
Control), Buckeye, and Goodyear• Cost Sharing, Planning, Analysis, and
Preparation
El Rio WatercourseEl Rio WatercourseMaster Plan Overview/RefresherMaster Plan Overview/Refresher
• March 2006 – Plan DevelopedBenefitsOpportunitiesImpact to Flood Control
• 2007 MOU Endorsed by Partners
Goals of the IGAGoals of the IGA
• Identify and Define Plan ResponsibilitiesCost SharingPlanningAnalysis Preparation• Initial Term – Five (5) Years or Completion• Consultant – Detailed Design
Partner Responsibilities
•Avondale - Lead Administration
•Buckeye – Project Oversight and Administration
•All Others – Various Responsibilities
All Participating Partners•Develop Goals and Objectives•Identify and Develop Projects •Develop Cost Estimates•Promote Public Awareness •Identify Sources of Funding•Inventory and Resource Management•Pay All Invoices Within 30 Days•Provide Comments/Input as Required
Lead Administrative Agency - Avondale
•Contract Administration
•Plan Payments
•Include Partners Consultant SelectionScopingPlan Meetings and Information Gathering
Lead Oversight and Coordinating Agency - Buckeye
•Oversight and Coordination of Consultant Services
•Public Input As Required
•Monthly Progress Reports
•Plan Submittals
•Include Partners in Project Management
Potential Growth Opportunities
•Promote Awareness
•Interpretive Trails and Overlooks
•Signs and Way Finding
•Funding Sources
•Inventory and Resource Management
•Local, State, and Federal Coordination
Budgetary Impacts•Plan Cost – Not to Exceed $200,000•1/4 Equal Shares / $50,000 Each•Appropriation Transfer Required•Staff Request: Approval of $200,000 Appropriations TransferFrom Project 320-1046-Improvement District-Unformed.
RecommendationRecommendation
Approve Transfer of Funds
Adopt Resolution Authorizing IGA Between Maricopa
County (Flood Control), Town of Buckeye, and City of Goodyear
El Rio Watercourse Implementation and Management Plan