EIS Progress Report
Steering Committee MeetingDecember 3, 2008
04/19/23 1
Major Milestones AchievedSeptember - October 2008
Planned milestones Results
Acquisition of EIS hardware •Board approved the purchase 7/7/2008. •Purchase Order issued 7/31/2008. •Equipment arrived the week of 9/15/2008.
Acquisition of EIS implementation services
•Completed the selection process 6/4/2008. •Submitted for Board approval 9/8/2008
Hardware and software installed •Technical Architecture Document 9/15/08 •Banner Pre-install validation 9/22/08•Banner Seed Install 9/29/08 •System status verified by SunGard 10/26/08
04/19/23 2
Major Milestones AchievedNovember 2008
Planned Milestones ResultsIdentity Management planning •Single sign on study and recommendation 11/5/08.
•Deployment strategy 11/5/08.
Luminis Portal platform install • Portal hardware operational 11/7/08.
Finance Business Process Analysis •Business process analysis of the old and new 11/11/08. •Change strategy recommendation 11/11/08.
HR Training Kick Off •Training of HR users on Banner system. 11/11/08.
Luminis Parallel Deployment •Fault tolerant architecture installed 11/14/08
Luminis Content Planning sessionTown Hall Meeting (Foothill / De Anza)
•Deployment recommendation of Luminis portal content 11/18/08
04/19/23 3
Major Events AheadDecember 2008
Planned activities Dates •Expected results
Student Business process Analysis 12/1/08 •Business process analysis between the old and new•Change strategy recommendation
Finance Technical training 12/1/08 •ETS internal technical team training•Maintenance of Finance module
HR Training 12/8/08 •HR Foundation basic training•Employment administration
Financial Aid Business Process Analysis 12/8/08 •Business process analysis between the old and new•Change recommendation
Report Strategy –ODS (Operational Data Store) planning call
12/15/08 •Planning the installation of ODS reporting environment in January 2009•Introduction to team leads of ODS
Purchasing training 12/15/08 •Purchasing training on Banner purchasing module
Oracle training 12/15/08 •ETS technical team training
Disaster Recovery RFP 12/16/2008 •11/11– Invitation to Bid release•12/16 – Bid response deadline
04/19/23 4
Major Events AheadJanuary 2009
Planned activities Dates •Expected results
Oracle training 1/12/09 •Oracle database access language training•ETS technical team•Acquire capability to write query language
Student Implementation Planning 1/19/09 •Student module implementation planning•Project team task layout and planning
Luminis Data Integration 1/19/09 •Lumins core Banner module data integration
HR training 1/26/09 •Benefits, deductions, tax administration training•Understanding of functionalities of Banner HR module
Luminis Organizational Planning 1/26/09 •Luminis deployment role and task assignments•Roll out task plan for Luminis module
Data Warehouse installation TBD •Installation of Banner ODS and Enterprise Data Warehouse.
Disaster Recovery Board agenda 1/20/09 •Outcome of the selection of DR RFP
04/19/23 5
Project Progression Chart Started
In Progress Q3 Finished Sep Oct Nov Dec J an Feb Mar Apr May J un J ul Aug Sep Oct Nov Dec J an Feb Mar Apr May J un J ul Aug Sep Oct Nov Actual Planned
1 Software Installation 7/21/08 12/5/082 Business Process Analysis 9/15/08 12/29/08
3 Identify and Access Mgmt 10/13/08 6/17/094 Integrations/Interfaces 10/6/08 1/31/115 Integration Assessment 10/6/08 12/9/086 Luminis IV - Finance Users 9/3/08 7/17/097 Banner Finance - Phase 1 10/10/08 7/16/098 Banner Finance Phase 2 -
budget8/17/09 2/1/10
9 Human Resources 10/21/08 1/19/1010 Banner Student -Admission 10/6/08 3/2/10
11 Banner -Financial Aid 10/6/08 3/2/1012 Banner Advancement 1/18/10 1/24/1113 Banner Document
Management8/10/09 4/15/10
14 Banner Operational Data Store
11/17/08 4/20/10
15 Banner Data Warehouse 11/17/08 4/20/1016 DegreeWorks 6/8/10 1/17/11
Go Live Date Planned Activities In ProgressCompleted
2008 2009 2010Q4 Q1 Q2 Q3 Q4 Q2 Q3 Q4Q1
04/19/23 6
Project budgetCurrent budget vs expenditure as of 11/30/2008
Project Item Budget amount Expenditure Balance
Banner/Oracle Implementation 3 years
6.6M 6.3M +0.3M
EIS Hardware 1.0M 1.1M -0.1M
Backfill 1.7M 0 1.7M
Start up cost year 2/3 1.3M 0 1.3M
Project Contingency 1.2M 0 1.2M
Total 11.8M 7.4M 4.4M
04/19/23 7
SunGard project implementation hours
As of 11/30/2008Task Hours used Hours planned % of total completed
Project Management 822.5 920 / 4,400* 89 / 18.6
Review and validate proposed environment
80.0 80.0 100.0
Banner Installation 179.0 189.0 95.0
HR consulting 92.5 1,036.0 8.0
Finance consulting 36.0 1,045.0 3.5
Luminis 231.0 740.0 31.0
Business Process Analysis 294.5 640.0 45.0
Other tasks 492.0 9,478.0 5.1
Total hours 2,227.5 17,608.0 12.7
Implementation consulting hours for 3 years based on Sungard RFP 1152 proposed hours* 1st year allocated hours / three years total hours04/19/23 8
Questions