Name of Work: Power charges during pushkarams. S.No Description Quantity Apr-15 May-15 Jun-15 Ju 1-7 8-15 16-22 23-30 1-7 8-15 16-22 23-31 1-7 8-15 16-22 23-30 1-7 8-15 1 Power Charges Program Progress Construction Program Sheet (Bar Sheet)

Eight Works of Kovvur Municipality of G.P 2015 as on 16-04-2015

Embed Size (px)

DESCRIPTION

Bar charts

Citation preview

ModelConstruction Program Sheet (Bar Sheet)Name of Work:Construction of 300mm dia and 450mm dia section Drain in (Harijana peta) 3rd & 4th Wards in Kovvur Municipality.Kovvur (Town) W.G.Dt Estimated Amount Rs: 27.77 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program84.00 Cum1.8Progress1.82P.C.C (1:4:8)Program85.00 Cum2100Progress21003C.C (1:3:6)Program206.00 CumProgress3R C C M20Program8.00 Cum.22.9Progress4Plastering.Program1740.00 Sqm497.89Progress5SteelProgram1120.00 Kg7.97Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600Progress

Power chargesConstruction Program Sheet (Bar Sheet)Name of Work:Power charges during pushkarams.Kovvur (Town) W.G.Dt Estimated Amount Rs: 10.00 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311Power ChargesProgram1.8Progress1.82Centering And steel fabricationProgram2100.00 Kg2100Progress21003R C C M20Program22.90 Cum.22.9Progress4Laying of Roof slabProgram497.89 Sqm497.89Progress5Brick WorkProgram7.97 Cum7.97Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600Progress

HarijanapetaConstruction Program Sheet (Bar Sheet)Name of Work:Construction of 300mm dia and 450mm dia section Drain in (Harijana peta) 3rd & 4th Wards in Kovvur Municipality.Kovvur (Town) W.G.Dt Estimated Amount Rs: 27.77 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program84.00 Cum1.884.00Progress1.82P.C.C (1:4:8)Program85.00 Cum210085.00Progress3C.C (1:3:6)Program206.00 Cum206.00Progress4R C C M20Program8.00 Cum.8.00Progress5Plastering.Program1740.00 Sqm1740.00Progress6SteelProgram1120.00 Kg1120.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

Old SRMT officeConstruction Program Sheet (Bar Sheet)Name of Work:Construction of CC drain and Providing 170mm thick CC Road to Old SRMT Transport Office Road (Koduri Vari Street) in 7th Ward.Kovvur (Town) W.G.Dt Estimated Amount Rs: 21.84 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program124.50 Cum124.50Progress2P.C.C (1:4:8)Program87.00 Cum87.00Progress3C.C (1:3:6)Program51,10 Cum51.10Progress4M30 concreteProgram210.00 Cum.210.00Progress5Plastering.Program510.00 Sqm510.00Progress6SteelProgram453.00 Kg453.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

IDSMTConstruction Program Sheet (Bar Sheet)Name of Work:Kovvur Municipality Construction of 300 mm cc drain in Satyavathi nagar IDSMT building surroundly area in 20th wardKovvur (Town) W.G.Dt Estimated Amount Rs: 24.10 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program279.50 Cum124.50279.50Progress2P.C.C (1:4:8)Program92.00 Cum87.0092.00Progress3C.C (1:3:6)Program272.00 Cum51.10272.00Progress4M20 concreteProgram9.00 Cum.9.00Progress5Plastering.Program1730.00 Sqm1730.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

KikkaraConstruction Program Sheet (Bar Sheet)Name of Work:Construction of CC drain and providing 170 mm thick cc road in Kikkaravari street and Pachipala vari street in 13th ward.Kovvur (Town) W.G.Dt Estimated Amount Rs: 12.65 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program22.00 Cum124.5022.00Progress2P.C.C (1:4:8)Program64.00 Cum87.0064.00Progress3C.C (1:3:6)Program53.00 Cum51.1053.00Progress4M30 concreteProgram94.00 Cum.96.00Progress5Plastering.Program550.00 Sqm550.00Progress6SteelProgram220.00 Kg220.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

SrinivasapuramConstruction Program Sheet (Bar Sheet)Name of Work:Construction of 350mm dia section CC Drain in Srinivasapuram in 15th Ward.Kovvur (Town) W.G.Dt Estimated Amount Rs: 18.80 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program156.10 Cum124.50156.10Progress2P.C.C (1:4:8)Program78.10 Cum87.0078.10Progress3C.C (1:3:6)Program223.30 Cum51.10223.30Progress4M20 concreteProgram8.80 Cum.8.80Progress5Plastering.Program1400.00 Sqm1400.00Progress6SteelProgram1100.00 Kg1100.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

Satyavathi nagarConstruction Program Sheet (Bar Sheet)Name of Work:Construction of 450mm dia section CC Drain in Indiramma Colony (Rama krishna Colony) 1st, 2nd and Satyavathi Nagar Main Raods in 20th Ward.Kovvur (Town) W.G.Dt Estimated Amount Rs: 33.10 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program246.00 Cum124.50246.00Progress2P.C.C (1:4:8)Program124.00 Cum87.00124.00Progress3C.C (1:3:6)Program439.00 Cum51.10439.00Progress4M20 concreteProgram16.30 Cum.16.30Progress5Plastering.Program1910.00 Sqm1910.00Progress6SteelProgram1956.00 Kg1956.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

IndirammaConstruction Program Sheet (Bar Sheet)Name of Work:Kovvur Municipality Construction of 300 mm dia section CC drain in Indiramma colony main road north side drain in 20th wardKovvur (Town) W.G.Dt Estimated Amount Rs: 25.33 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program110.00 Cum124.50110.00Progress2P.C.C (1:4:8)Program110.00 Cum87.00110.00Progress3C.C (1:3:6)Program331.00 Cum51.10331.00Progress4M20 concreteProgram9.00 Cum.9.00Progress4Plastering.Program2200.00 Sqm2200.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

colonyConstruction Program Sheet (Bar Sheet)Name of Work:Kovvur Municipality Construction of 300mm dia section CC drain in Indiramma colony 2nd main land south & north sides cross road drains in 20th ward.Kovvur (Town) W.G.Dt Estimated Amount Rs: 39.75 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program110.00 Cum124.50110.00Progress2P.C.C (1:4:8)Program110.00 Cum87.00110.00Progress3C.C (1:3:6)Program331.00 Cum51.10331.00Progress4M20 concreteProgram9.00 Cum.9.00Progress4Plastering.Program2200.00 Sqm2200.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

I.ColomyConstruction Program Sheet (Bar Sheet)Name of Work:Kovvur Municipality Construction of 800 mm size section CC drain satyavathi nagar bye pass road culvert to south hari villu sites existing drain in 20th wardKovvur (Town) W.G.Dt Estimated Amount Rs: 23.16 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program98.00 Cum124.5098.00Progress2P.C.C (1:4:8)Program93.00 Cum87.0093.00Progress3C.C (1:3:6)Program231.00 Cum51.10231.00Progress4M20 concreteProgram9.00 Cum.9.00Progress4Plastering.Program1735.00 Sqm1735.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

PunthaConstruction Program Sheet (Bar Sheet)Name of Work:Providing Junction Improvement Islands at Nandamuru Puntha Pedatalla Puntha Junction, GNT Road Bypass Road Junction and GNT Road Bypass Road Junction (Near Railway Bridge) at 3 Places in Kovvur Municipality.Kovvur (Town) W.G.Dt Estimated Amount Rs: 6.66 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program98.00 Cum124.5098.00Progress2P.C.C (1:4:8)Program93.00 Cum87.0093.00Progress3C.C (1:3:6)Program231.00 Cum51.10231.00Progress4M20 concreteProgram9.00 Cum.9.00Progress4Plastering.Program1735.00 Sqm1735.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

Bleaching PowderConstruction Program Sheet (Bar Sheet)Name of Work:Temporary Water Supply facilities and Required Bleaching Powder, Liquid Chlorine Alum, Chlorine Tablets and Lime in Pushkara ghats and Temporary Bus Stand Near Railway Station, pilgrim Shed in Kovvur Municipality.Kovvur (Town) W.G.Dt Estimated Amount Rs: 9.46 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311Temporary Water Supply facilities and Required Bleaching Powder, Liquid Chlorine Alum, Chlorine Tablets and Lime in Pushkara ghats and Temporary Bus Stand Near Railway Station, pilgrim Shed.Program124.50Progress2P.C.C (1:4:8)Program124.00 Cum87.00124.00Progress3C.C (1:3:6)Program439.00 Cum51.10439.00Progress4M20 concreteProgram16.30 Cum.16.30Progress5Plastering.Program1910.00 Sqm1910.00Progress6SteelProgram1956.00 Kg1956.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

H.D.P.EConstruction Program Sheet (Bar Sheet)Name of Work:Providing Water Supply 225mm dia HDPE pipe line from Bores to Sump connecting line at Head Water Works near box culvert and 110 mm dia HDPE pipe lien at Rajeev colony crossing Box culvert in Kovvur Municipality (Rectification of Leakages and Atending urgent Repair works).Kovvur (Town) W.G.Dt Estimated Amount Rs: 9.995 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311Providing Water Supply 225mm dia HDPE pipe line from Bores to Sump connecting line at Head Water Works near box culvert and 110 mm dia HDPE pipe lien at Rajeev colony crossing Box culvert in Kovvur Municipality (Rectification of Leakages and Atending urgent Repair works).Program124.50Progress2P.C.C (1:4:8)Program110.00 Cum87.00110.00Progress3C.C (1:3:6)Program331.00 Cum51.10331.00Progress4M20 concreteProgram9.00 Cum.9.00Progress4Plastering.Program2200.00 Sqm2200.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

Nandamuru PunthaConstruction Program Sheet (Bar Sheet)Name of Work:Construction of CC Drain and Providing 150mm thick CC Road from Nandamuru Puntha Road North Side Road Door No: 4-2-65/3 to 4-5-16/17 in 21st Ward.Kovvur (Town) W.G.Dt Estimated Amount Rs: 3.72 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program98.00 Cum124.5098.00Progress2P.C.C (1:4:8)Program93.00 Cum87.0093.00Progress3C.C (1:3:6)Program231.00 Cum51.10231.00Progress4M20 concreteProgram9.00 Cum.9.00Progress4Plastering.Program1735.00 Sqm1735.00Progress6SteelProgram1260.00 Kg1260.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress

Factory Guest HouseConstruction Program Sheet (Bar Sheet)Name of Work:Construction of 300mm dia section CC Drain in Electrical Revenue Office Road, Factory Guest House West Side & Transformer Street in 10th Ward .Kovvur (Town) W.G.Dt Estimated Amount Rs: 4.30 LakhsS.NoDescriptionQuantityMar-15Apr-15May-15Jun-15Jul-151-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311-78-1516-2223-301-78-1516-2223-311San bed/Quarry rubbish/stone dust.Program22.00 Cum124.5022.00Progress2P.C.C (1:4:8)Program64.00 Cum87.0064.00Progress3C.C (1:3:6)Program53.00 Cum51.1053.00Progress4M30 concreteProgram94.00 Cum.96.00Progress5Plastering.Program550.00 Sqm550.00Progress6SteelProgram220.00 Kg220.00Progress6Plastering & Other FinishingsProgram242.00 Sqm242.00Progress7Electrification & Water SupplyProgram-ProgressFIRST FLOOR8R C C ColumnsProgress4.77Cum4.77Program9Centering And steel fabricationProgress5.62 MT5.62Program10Laying of Roof slabProgram380.33 Sqm380.33Progress11Brick WorkProgram96.74 Cum96.74Progress12Doors & WindowsProgram46.64 Sqm46.64Progress13Plastering & Other FinishingsProgram1359.1 Sqm1359.10Progress14Electrification & Water SupplyProgramProgress15PaintingProgram1600 Sqm1600ProgressProgress