Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
1
Application for
Environmental Clearance (u/s 7(ii) of EIA Notification, 2006 &
O.M. dated 19.12.2012 & 07.01.2014)
OF
Naheriya UG Expansion Pench Area, WCL
(One Time Capacity Expansion for incremental production from
0.36 MTPA to 0.54 MTPA within the existing EC ML area of 300.0 ha)
ADDENDUM EIA & EMP
JANUARY - 2016
Prepared by:-
Central Mine Planning & Design Institute Limited (Accreditation as EIA consultant vide NABET No/EIA/01/12/002 Dt.31.01.2012)
CMPDI/Form - I /WCL/2015-16/Dec/23/02
2
Contents
S. No. Particular Description Page
1 Brief of Project Report 01-21
2 EIA/EMP Addendum
3 Chapter-I Anticipated environmental impacts
& Mitigation measures
24-81
4 Chapter-II Environmental Monitoring Programme 82-84
5 Chapter-III Additional Studies 85-90
6 Chapter-IV Project Benefits 91-91
7 Chapter-V Environmental Management Plan 92-93
8 Chapter-VI Disclosure of Consultant Engaged 94-105
ANNEXURES ANNEXURE-I COMPLIANCE REPORT FROM MOEF REGIONAL OFFICE
ANNEXURE-II ATR SUBMITTED TO MOEF ANNEXURE-III ENVIRONMENTAL CLEARANCE OF 0.36 MTPA ANNEXURE-IV MINUTES OF PUBLIC HEARNING ANNEXURE-V STATUS OF CSR ACTIVITY ANNEXURE-VI SCHEME APPROVAL LETTER ANNEXURE-VII SUBSIDENCE REPORT ANNEXURE-VIII TOPO PLAN
1
BRIEF OF PROJECT DETAILS
1. INTRODUCTION
The Naheriya Geological Block forms eastern to north – eastern contiguous part of
Urdhan Block and Thesgora Block “B” of Pench – Kanhan Valley Coalfield, District-
Chhindwara, Madhya Pradesh. Naheriya UG Mine falls under Naheriya Geological Block.
Naheriya UG mine is under Pench administrative area of Western Coalfields Limited. The
area is enclosed by Gunor river and Dhankasa nullah from all the sides except in the
southeastern part. The block is situated about 32 km east of Parasia, the main town in
Pench Valley. Initially Project report has been prepared with target capacity of 0.36 MTY
with an capital investment of Rs. 46.1708 Crores. Naheriya UG mine was operational since
year 2000, obtained Ex-Post –Facto Environmental Clearance vide Lr.No. J- 11015/35/2001-
IA.II(M) dated 15.11.2001 for capacity of about 0.36 MTPA, with land area of 300.0 ha
comprising 206.562 ha of forest land for which forest clearance has been obtained vide
vide letter no F-5/3/2000/10/3 – dated 03.01.2001 and agriculture land
Now it is proposed for production enhancement from 0.36 MTPA to 0.54 MTPA by
deployment of 4 nos. of LHDs additionally in 4 development Panels and 2 depillaring panels
to produce 0.54 MTPA with an additional capital of 8.62 Crores, without increase in land
area. The Scheme for This Environmental Management Plan has been prepared and
approved by WCL dated 12.01.2016 to apply for prior Environmental Clearance for
enhancement under u/s 7(ii) of EIA Notification, 2006 &O.M. dated 19.12.2012 &
07.01.2014.
1.1.2 LOCATION & COMMUNICATION
Naheriya Block named after Naheriya village falls in Pench – Kanhan Valley Coalfield.
It is located in Chhindwara district of Madhya Pradesh. The block is bounded by latitude
22⁰ 16’32” to 22⁰ 12’ 53” and longitude 78⁰ 57’ 58” to 78⁰ 59’ 50” E. it forms a part of SOI
Topo Sheet No 55/J (Scale 1:50,000)
The approach from Parasia to Naheriya Block is via Shivpuri OC Mine on BT weather
road. The mine is also approachable from Amarwada, a Tahsil town on Chhindwara –
Narsinghpur road. The distance between Amarwada and Naheriya is about 35 km and it is
fully black topped road.
The convenient rail head for the block currently used for coal dispatch is EDC siding
which is approximately 37km from Naheriya Block.
1.2 TOPOGRAPHY & DRAINAGE:
The entire area of geological block is occupied by basalt which on differential
erosion has formed rugged terrain comprising of hills and valleys. The maximum elevation is
noticed in the south-eastern part with the contour value of 782 m. In central and south-
eastern part a continuous relatively flat high ground is formed with contour values between
2
760 m to 782 m. In the north-eastern past between boreholes PU- 93 & PU-151, an isolated
ridge is seen with maximum contour value of 756 m. The lowest elevation is seen in the
south-western past around PU-186 & PU-188 where contour value is 700 m.
The drainage in the block is mainly controlled by the perennial Gunor river (together
with Dhankasa nullah) which almost encircle and form the western, norther, southern
(Partly) and eastern boundary of the block. Number of nullahs flow in the block in different
directions guided by local topography and ultimately meet Gunor river.
1.3 DEMAND , MARKETABILITY & JUSTIFICATION
In the view of Vision 2020 of CIL and constant pressure on WCL mines to meet the
increasing demand of non-coking coal for power houses and other bulk consumers from
Western as well as Southern part of country. The existing Naheriya UG project is located in
Pench-Kanhan coalfields of WCL. The justification of this mine for proposed expansion has
been studied in the light of estimated demand for non-coking coal from power sector in
Madhya Pradesh and production forecast from existing, completed and ongoing projects of
WCL. Moreover this mine is in operation and having potential, the reserve of the mine
supports for enhancement, there will be no problem in marketing because existing
customers may continue to lift coal from this mine.
By enhancing the production from 0.36 MT to 0.54 MT will help in reducing the losses from
1169/te to 565/te.
Scheme for enhancement of production in Naheriya UG mine form 0.36 MT to 0.54 MT per
year has been approved with an additional capital of 8.62 Crores by WCL dated 12.01.2016.
Naheriya UG is linked to Power sector and partially fed to MPPGCL Sarni, PTPS Panipath,
UPPGCL Paricha, MSPGCL Bhusaval, MSPGCL Nasik, KTPS Dholpur.
It is, therefore, essential to enhance the production capacity of Naheriya UG to reduce the
gap between the requirement and availability. Keeping this objective in view, Naheriya UG
mine is planned for a target capacity of 0.54 MTPA.
2. REGIONAL GEOLOGY
The mine under consideration has been projected in Naheriya Geological Block.
The detailed exploration in Naheriya Block has been carried out by MECL intermittently
when the borehole sites were approachable and hence, the drilling in the block has spread
over a span of about 5 years from January, 1989 to May, 1994.
The present geological assessment of the proposed mine area is based on the data of 52
boreholes involving a total meterage of 7416.20 m in an area of around 3.00 Sq. km. and
forms a part of Naheriya Geological Block. The density of boreholes works out to 17
boreholes per Sq.km
3
2.1 GEOLOGY OF THE BLOCK
The entire area is covered with the flows of Basalt which on differential erosion has
formed rugged terrain comprising hills and valleys. The general elevation ranges from
706.89 m (PU – 186) to 769.84 (PU-180).
The geological succession in the proposed mine area is as given below in Table 2.1
GEOLOGICAL SUCCESSION
Age Formation Lithology Thickness Range (m)
From To
Sub-recent to
recent
Soil Sandy & Clayey Soil 0.50
(PU-102, 160,
etc.)
5.5
(PU-172)
Up cretaceous
to Eoceone
Deccan Trap with
inter-trappean beds
Flows of Basalt with
beds of clay/ clay –
stone of variaged
colours
23.00 (PU-
160)
103.66
(PU-201)
UNCONFORMITY
Jurassic Jabalpur Gritty sandstones and
clays with jasper
pebbles
1.26
(PU-186)
30.96
(PU-97)
UNCONFORMITY
Permian Motur Clays / Claystones of
brick red, purple and
grey colour with
lenses / bands of
sandstones at places.
9.59 (PU-165) 74.64
(PU-187)
Permian Barakar Sandstones with
kaolinised feldspars,
interbanded with
shales and coal
seams.
9.32
(PU-129)
74.64
(PU-165)
Talchir Fine grained
argillaceous
sandstone and green
shales
0.75 (+)
(PU-188)
2.85 (+)
(PU-186)
2.2 SEQUENCE OF COAL SEAMS
The seams in the block under report have been designated as Seam I (Topmost), II, III, IV
and V (bottom most).
Seam-I occurs in 3 sections: IA, IB, IC designated form top bottom. The Section – IA
is very thin, impersistent and very poorly developed within the block. It has not attained
workable thickness of more than 0.90 m anywhere in the block. Seam – I cannot be
4
considered from exploitation point of view, as such, it has not been considered for mining
in this report.
The Seam – II ranges in thickness from 0.31 m to 3.13 m (Average thickness 2.20 m)
whreas Seam –III ranges in thickness from 0.18 m to 2.34 m (Average of 1.70 m) Both the
seams have a parting of 3 m in whole mine field except at the boundary of the dip side
property, as such, both the seams namely Seams – II & III are to be mined out contiguously
in the rest of the area. Beyond fault F6(N) upto Fault F8 (N), only Seam – II has developed
whereas the thickness of Seam – II is less than 1.2 m and the parting between Seam – II and
Seam – III in this sector [F6(N) & F8 (N)] is by and large less than 3 m. As such, in this area,
only Seam-II will be worked, by driving drifts across Fault F6 (N). From the perusal of seam
folio plan of Seam-II it is clear that the panels 3 & 5 will not be worked, as the coal thickness
in these panels is in between 1.2 m to 1.5 m, which is difficult to work by mechanized
method, as such, their extractable coal reserves have not been considered in the report.
From the perusal of seam folio plan of Seam-III, it appears that the panel Nos. IA, IB, ID, 4 7
and 9 will not be worked by SDL mechanization, as the thickness in these panels is less than
1.5 m. Therefore, the extractable reserves of these panels have not been taken into
consideration.
Seam – IV ranges in thickness from 0.65m to 5.04 m (average 3.25 m) whereas
Seam – V ranges in thickness from 1.19 m to 3.48 m (average 2.45 m). An iso-parting line of
3 m has been drawn on seam folio plans of Seam IV & V. it can be seen that Seam-IV might
be worked in larges area, because of its adequate thickness compared to Seam –V. Panes 1,
2, 3, 5, 6, 8, 8A & 8B might not be worked in Seam –V, as it maintains a parting of less than
3 m with Seam-IV in these panels. Panel-9 might not be worked in Seam-IV, as its thickness
is less as compared to Seam-V and parting between Seams-IV & V is less than 3 m in most of
the area of this panel but it will be worked in Seam-V. Though the extractable reserves of
non-workable panels have not been taken into consideration but their mineability (panel
wise) may be reviewed in consultation with DGMS while actual working of the mine.
The extractable reserves for Seam – II & III will last for 13 years at the target
production of 0.36 Mty, after 13 years, development work in the form of “B & P” panels on
the strike direction will start in the Seams –IV & V. The potential seams being Seam- IV,
where panel development work can be taken up easily, as main trunk roads in the Seam-IV
would have to be driven initially to accommodate trunk belt conveyor for loading of coal
from Seams –II & III.
The gradient of seams varies from 1 in 11 to 1 in 18.
5
TABLE 2.2: SEQUENCE OF COAL SEAMS
S.No Seam No. with
Parting
Thickness Rang (m) Remarks Depth
Range (m) From To
1.
IB 0.12
(PU-163)
0.12
(PU-163)
Not Considered due to
thickness and
deterioration in quality
with the development of
carb.Shale and shale
sand. Average grade is
“F” to “G”.
-
Parting
0.35
(PU-93)
7.320.12
(PU-201)
- -
2.
IC 0.05
(PU-186)
3.43
(PU-180)
Not considered due to
thickness and
deterioration in quality
with the development of
carb.Shale and shale
sand. Average grade is
“E” to “F”.
-
Parting
0.35
(PU-195)
5.30
(PU-200)
- -
3.
II 0.31
(PU-187)
3.13
(PU-93)
General thickness range
is 1.50 m to 2.00 m.
Considered workable.
62.89
to
172.61
Parting
0.37
(PU-93)
6.31
(PU-185)
- -
4.
III 0.18
(PU-201)
2.34
(PU-93)
General thickness range
is 1.50 m to 2.00 m.
Considered workable.
68.14
to
177.95
Parting
3.51
(PU-186)
11.47
(PU-199)
- -
5.
IV 0.65
(PU-165)
5.04
(PU-92)
General thickness range
is 2.50 m to 3.50 m.
Considered workable.
Main Potential Seam.
78.70
to
184.00
Parting
0.77
(PU-203)
8.85
(PU-46)
- -
6.
V 1.19
(PU-46)
3.80
(PU-197)
General thickness range
is 2.00 m to 2.50 m.
Considered workable.
82.14
To
194.00
6
2.3 DESCRIPTION OF FAULT
TABLE 2.3: DESCRIPTION OF FAULTS
S.No Fault No. Trend Throw direction
& Amount (m)
Nature of Fault & Evidence
1. F3 (N) (forms
southern
boundary)
S 80 deg. E- N 80 deg.
W in the eastern part
to S 80 Deg. W – N
80 Deg .E in the
western part.
70 m to 85 m
southerly
Oblique Fault :
Interpreted on the basis of
difference in FRLs of seams on
both sides of fault.
2. F4 (N) Almost E-W on both
the ends to N 70 Deg.
W – S 70 Deg. E
south of PU – 185.
5m to 10 m
northerly ( 5m in
the east, 10 m in
the west)
Oblique Fault:
Interpreted on the basis of
difference in FRLs of seams on
both sides of fault.
3. F5 (N) N 15 Deg. E – S 15
Deg. W
5 m to 10 m
easterly ( 5m in
the northern part
and 10 m in
southern part)
Oblique Fault:
(i) Interpreted on the basis of
difference in FRLS of seams on
both sides of fault.
(ii) Intersected in PU -184 at
134.9 m, causing omission of
seams – IB. IC & II, PU-190 at
84.20 m with omission of Seam
– III (Part), II & IC.
4. F6 (N) Almost EW to N 50
Deg. E – S 50 Deg. W
20 m to 30 m,
northerly ( 20 m
in east and 30 m
in the west)
Strike Oblique Fault :
(i) Interpreted on the basis of
difference in FRLS of seams on
both sides of fault.
(ii) Intersected in PU-200 at
187.20 m depth causing
omission of seams – IV & V.
5. F7 (N) Almost EW to N 65
Deg. E – 65 Deg. W
10 m northerly Strike Oblique Fault :
Interpreted on the basis of
difference in FRLs of seams on
both sides of fault.
6. F7 – F7 N 65 Deg. E – S 65
Deg. W to E-W
20 m to 30 m
southerly
Strike Oblique Fault :
(i)Interpreted on the basis of
difference in FRLs of seams on
both sides of fault.
(ii) Intersected in PU -174& PU-
102 causing omission of seams.
7 F3(TH) (forms
southern
boundary)
N70 Deg. E- S70
Deg.W to N 85 Deg.E
– s 85 Deg.W
15 m southerly Strike Oblique Fault :
(i)Interpreted on the basis of
difference in FRLs of seams on
both sides of fault.
(ii) Intersected in PU -49& at
110 m depth causing omission
of seams – III (part), II, IC & IB.
8 F7(TH) (forms
southern
boundary)
N23 Deg. E-S23
Deg.W to N 45 Deg.E-
S45 Deg. W
10 m easterly Oblique Fault :
Interpreted on the basis of
difference in FRLs of seams on
both sides of fault.
7
2.4 DESCRIPTION OF COAL SEAMS
The immediate roof of Seam – II consists of Arenaceous shale and while the floor
consists of sandstone. The immediate roof of Seam- III consists of shale and sandstone
while the floor consists of Shale/Arenaceous Shale. The immediate roof of Seam - IV
consists of shale/carbonaceous shale. The floor of Seam-IV consists of intercalation of shale
and sandstone while that of Seam-V consists of shale/carbonaceous shale.
The Boreholes: namely PU-205 and PU-206 have been drilled in the “Mining Block”
for determination of Geo-Engineering Data. These rock samples are under investigation.
However, the data of RQD % of the roof of various seems are tabulated in Table-2.3:
DETAILS OF R.Q.D
Particulars Borehole
PU-205 PU-205
Roof Seam – II * 33-48% 37-90 %
Roof Seam – III 56% 53%
Roof Seam – IV 82% 82-91%
Roof Seam – V 72% 63 %
* Roof of Seam – II consists of parting of average thickness of 1.27 m plus average seam
thickness of IC of about 1.3 m.
The depth of cover varies from 63 m (Seam-III) to 194 m (Seam –V).
2.3 QUALITY PARAMETERS
TABLE 2.4: OVERALL QUALITY OF MINE
2.4 GEOLOGICAL COAL RESERVES
The Geological reserves of the Block are 34.259 MT
3. MINE BOUNDARY DELINEATION
The mine is bounded by the following features:
(a) North – Fault F8 (N) and 60 m barrier from Gunor river.
(b) East – 60 m barrier from Dhankasa nullah and Sub- crop of Seam – V.
(c) South – Sub-crop of Seam-V, Fault F3 (N) & Fault F3 (TH).
(d) West – Fault (TH) & 60 m barrier from Gunor river.
NAME OF SEAMS GRADE
SEAM-II (TOP) G6
SEAM-III (Middle - I ) G6 SEAM-III (Middle - II) G6 SEAM-III (Bottom) G6
8
3.1 MINEABLE RESERVES
The Geological reserves of the Block –34.259 MT
Mineable reserves are –32.603 MT
Extractable reserves (thickness 1.5 m and above) – 12.66 MT
Extracted upto 31.03.2015 – 3.33 MT
Remaining Reserves – 8.50 MT
TABLE – 3.1: SEAMWISE DETAILS OF EXTRACTABLE RESERVES
(THICKNESS 1.5 M & ABOVE)
NAME OF SEAM NET EXTRACTABLE
RESERVES (MT)
Seam – II 2.90
Seam – III 1.66
Seam – IV 5.46
Seam – V 2.64
Total 12.66
3.2 TARGET PRODUCTION
It is envisaged that proposed project shall produce 0.54 Mty of coal.
3.3 MINE LIFE
The total life of the mine would be approximately 15.0 years at 100 % achievement
of target.
3.4 PRODUCTION
The production of the mine during the past ten years is as under:-
S.N. YEAR PRODUCTION (Te)
1 2005-06 276145
2 2006-07 256500
3 2007-08 192775
4 2008-09 219735
5 2009 - 10 235583
6 2010-11 253140
7 2011-12 272026
8 2012-13 316368
9 2013-14 284200
10 2014-15 257400
9
3.5 PROJECTED PRODUCTION:-
The projected production for the next ten years is as under:-
S.N. YEAR PRODUCTION (Te)
1 2015-16 400000
2 2016-17 540000
3 2017-18 540000 4 2018-19 540000 5 2019-20 540000 6 2020-21 540000 7 2021-22 540000 8 2022-23 540000 9 2023-24 540000 10 2024-25 540000
4. SELECTION OF MINING METHOD
The mine is being worked by Board and Pillar underground method of working by
development & depillaring is being done by splitting & slicing method in conjunction with
Caving. Coal preparation by solid blasting is being used in the mine. Series of haulages are
used in-bye and out-bye transport of coal for transport of loaded coals tubs. The coal
brought to the surface is dumped in bunker from where trucks are loaded with ROM Coal.
Underground mine working has been done in Seam No. II & III.
Workable horizons:
Only three horizons namely Seam – II,III, IV & V has been considered to be having
workable potentiality.
The scheme for the incremental production form 0.36 MT to 0.54 MT to extract
balance reserves of 8.5 MT for a life of 15 years in Seam - II & Seam - IV by deploying
additional 04 LHDs ( Present 9 LHDs in operation), additional manpower of 120 with
additional budget of 861.998 Lakhs.
10
4.1 SYSTEM PARAMETERS
TABLE : THICKNESS OF COAL & PARTING
4.2 SEQUENCE OF MINING
Initially Seams- II, III, V were worked contiguously. Now the development work in the
seams – II & IV will be taken.
Table- : Phasing of Production
S.No Seam No. with
Parting
Thickness Range (m)
From To
1. IB 0.12
(PU-163)
0.12
(PU-163)
Parting 0.35
(PU-93)
7.320.12
(PU-201)
2. IC 0.05
(PU-186)
3.43
(PU-180)
Parting 0.35
(PU-195)
5.30
(PU-200)
3. II 0.31
(PU-187)
3.13
(PU-93)
Parting 0.37
(PU-93)
6.31
(PU-185)
4. III 0.18
(PU-201)
2.34
(PU-93)
Parting 3.51
(PU-186)
11.47
(PU-199)
5. IV 0.65
(PU-165)
5.04
(PU-92)
Parting 0.77
(PU-203)
8.85
(PU-46)
6. V 1.19
(PU-46)
3.80
(PU-197)
YEAR PRODUCTION (Te)
TPD MTY
I 1334 400000
II 1800 540000
III 1800 540000
IV 1800 540000
11
4.3 MINING SCHEDULE
The proposed Report has been prepared for a targeted capacity of 0.54 Mt per annum.
The parameters of underground mine field and technical conditions of its development
make this target feasible with normal indices namely length, width & depth of the
excavated block, number of coal seams, seam gradient, method of mining, location of
equipment deployment, etc. The proposed calendar programme of excavation in for a
targeted output of 0.54 Mty. is as shown below:-
Calendar Programmed of Excavation
S.N. YEAR PRODUCTION (Te)
1 2015-16 400000
2 2016-17 540000
3 2017-18 540000 4 2018-19 540000 5 2019-20 540000 6 2020-21 540000 7 2021-22 540000 8 2022-23 540000 9 2023-24 540000 10 2024-25 540000
5.0 PUMPING & DRAINAGE
The present make of water of Naheriya mine is 298.0 KLD. The mine water from
intermediate sump is being delivered to maintain sump from where the same is delivered
to the sedimentation tanks on the surface with dimensions (Tank 1- 15.6 x 11 x 2.5 m,
Tank 2 -20 x 10 x 2 m with total capacity of 439 KL) are in operation.
6.0 COAL HANDLING ARRANGEMENT
A simple bunker loading arrangement with screening and weighment facilities have
been envisaged as coal handling arrangement.
The coal is brought to surface by belt conveyor from underground and is transferred
to another 1000 mm wide elevating belt conveyor. The coal is raised to a suitable height
and allowed to pass through a vibratory screen. The screen separates the ROM coal into
steam and slack fractions. These fractions are collected into two separate 100 tonne
overhead bunker loading hoppers. Reciprocating feeder has been provided below the
discharge opening of each hopper.
Customer’s truck will be loaded below these hoppers for further transport.
7.0 WORKSHOP
There is no workshop at Naheriya but there is primary service centre with sufficient civil
infrastructure to cater the maintenance of proposed extra LHD equipments. This primary
12
centre would extend basic engineering support in respect of maintenance and repair of
various Machineries deployed in the mine.
Area workshop at Chandametta shall provide external support to the unit workshop in
the form of major repairs, replacement and overhauling of equipment.
8.0 SOURCE OF POWER
(i) Singodi Sub station is the source of 33 KV power for Naheriya Project.
(ii) 11 KV overhead line is source for Bokai Township of Naheriya UG Project.
8.1 SALIENT FEATURES OF THE EXISTING ELECTRICAL PARAMETERS
Sl.No. PARTICULARS POWER SUPPLY
1 Incoming Power Supply 33 KV
2 Maximum Demand (including Township) 2.1 MVA
3 Specific Power Demand 5.83 MVA / MT
4 Main power transformers 33/11 KV 2x2.0 MVA
5 Specific Electricity Consumption 14.6 KWH / T
6 Specific Power Cost Rs. 57.60 / T
7 Total Capital Investment on Elect. P & M Rs 392.00 Lakhs
8 Specific Capital Investment on Elect. P & M Rs. 108.90 / T
Additional Requirements as per the Approved Scheme
3.3KV Power separately conveyed to SW-5, Seam II by 90 sq.mm power cable form
surface. As the connected load of mine is 2400 KW and is expected to increase for pumping,
installed capacity of the mine is 2.6 MVA which is not sufficient enough to fulfill the power
requirement of fourth district. Required load of the proposed district is 570 KW including
transport and operation hence 1 MVA power transformer is proposed to install 33 KV/3.3
KV at surface sub-station and additional Electric equipments & material required amounting
to additional cost of 2.4852 Crores.
Electrical Equipment & Material Requirement:
Power Transformer 1 Nos 1 MVA 33 KV/3.3 KV
CT 33 KV Rating 30 /30 /5 CTR
PT 33 KV/110V
VCB 33 KV
VCB/OCB 3.3 KV
FLPVCB 3.3 KV
Power Cable (PVC DWA) 3.3 KV Grade 95 Sq.mm
FLPVCB (550 V) 100/ 200/ 300/ AMP
Starter FLP
TSU 315 KVA, 3.3 / 550 V
Drill panel, Machine, Cable
Lighting Transformer 550/110 V, 5 KVA
13
Lighting cable 2 x 4 sq. mm Mining type
Light fitting FLP bell type, 110 V
Telephone Cable
9.0 CIVIL CONSTRUCTION
9.1 CIVIL CONSTRUCTION
11.1.1 Life of the project & specifications
The estimated life of this project is about 15 years. Existing infrastructure such as
Manager’s Office, First Aid Centre, Rest Shelter, Canteen, Lamp Room, Haulage Engine
Shed, Fan House, C.D.S building, workshop, Magazine room etc. will be used.
Existing Bokai Township on non-coal bearing area has 427 quarters and another 78
quarters are to be constructed for a manpower of 1152( including additional man power) .
Enhancement of surface bunker capacity
The mine PR proposed two bunkers 100 te capacity for targeted production of 0.36
MT were constructed and are in operation. Now as the proposed scheme will enhance
production from 0.36 Mt to 0.54 MT and to handle coal at surface it is proposed to install 2
more bunkers of 100 te. capacity at surface with reciprocating feeder, in sequence with
loading on belt to feed coal to proposed bunkers and it is amounting to additional cost as
per the approved scheme is 1.0 Crore.
Ventilation
At present the main ventilator to be installed for Naheriya UG mine is 110 cu.m /
sec. at 100 mm of WG, Surface fan of having specification of 80 to 120 cu,m /sec. At 100 -67
mm WG with a fan motor of 350 HP has been provided in the Project Report.
As per approved scheme, for preparation of district and proper ventilation at least
35 nos. of ventilation stoppings are required and for proper ventilation at the face with
running LHD 04 nos of auxiliary fans are required amounting to total of 0.35 Crores.
Roads & Culvert
Existing approach roads & colony roads will be used.
External Services
External Services viz. Roads, Culverts, Water Supply, and Sewage Disposal etc.
already exist and are maintained at regular intervals.
Material Transport
Direct haulage of 110 KW has been envisaged at the incline Top on surface for
material transport.
14
Additionally as per approved scheme it is proposed to provide Direct haulage of 50
HP x 2 nos complete with all electrical equipments, 10 nos. of Coal tubs and Ms Rails total
amounting to 33.438 Lakhs.
9.2 SERVICE BUILDINGS
Existing service buildings will be used.
Sub-Station
Existing sub-station will be used.
9.3 RESIDENTIAL BUILDING
505 quarters were proposed initially out of which 427 quarters have been
constructed and remaining 78 quarters are to be constructed for a manpower of 1152.
9.4 ROADS AND CULVERTS
Colony Roads and Culverts
Existing colony roads will be utilized, no new roads are proposed.
Roads & Culverts
For transportation of coal existing road will be used. Existing culvert over Gunor
river (about 100 m length and 7.5 m width) will be utilized.
Approach roads
For approaching UG mine existing 2.50 km length of sector road of stratum ‘C’
will be used.
9.5 WATER SUPPLY ARRANGEMENT
The total water requirement for project has been worked out to 444 Kl (Industrial-
98 KL & Domestic – 346 KL). Water demand for project includes water to be supplied for
dust suppression, firefighting, water sprinkling on roads, colony etc.
Source of Water
Water Demand (Industrial) is met from Mine pumped out water of Naheriya UG, for
domestic requirement borewells are in operation at Bhokai Township to meet the
requirement .
15
9.6 SEWAGE DISPOSAL ARRANGEMENT
No waste water is discharged outside mine premises. For colony, each quarter is
provided with septic tank followed by soak pit. Possibility of construction of STP will be
explored during construction of proposed 78 Nos.quarters.
10.0 LAND
The land use pattern of this area is directly controlled by the topography. The
pleateau and valley portions are used for cultivation. The slopes are covered by reserve
forests of moderate to thick density.
The top soil is typical black cotton soil, occurring mostly in the valleys. Thickness of
soil varies from 0.5 m to about 3.0 m. Sub-Soil is dull brown to grey in colour with
dominance of boulders of basalt.
Major crops in this block are maize, jowar, wheat and groundnuts. Major flora in
mine / study area is teak, sal, mahua, tendu together with thorny bushes. Monkey, Fox
etc., represent major fauna in Naheriya study area.
S.No Particulars Area (ha)
AREA FOR UNDERGROUND MINING
A LEASEHOLD AREA 300.0
1. Govt. Forest 196.63
2. Big Trees Forest 8.32
3. Grass Land 5.84
4. Govt. Land under Water 0.67
5. Other Govt. Land 2.90
6. Tenancy Land and Abadi, etc 85.64
B AREA UNDER “ALL RIGHTS” 30.0
1. Non-Forest Land 30.0
Grand Total 330.00
The break-up of the area under “ALL RIGHTS” is as follows.
S.No Particulars Area (ha)
1. Land for mine entries and other infrastructure 5.00
2. Land for approach road to mine and colony 10.00
3. Land for township 15.00
Grand Total 30.00
11.0 COMPENSATION & REHABILITATION
Not Applicable as enhancement of the production from 0.36 MTY to 0.54 MTY
without any change in Land.
16
12.0 MANPOWER
The manpower planning has been estimated and guided by the available norms of
WCL mines. Initially it was planned with 1032 No’s but as on date 1018 No’s of manpower is
employed in the Naheriya UG.
As per the scheme to achieve the target production additional manpower of 120
No's will be provided.
13.0 SAFETY & CONSERVATION
13.1 DEGREE OF GASSINESS
Naheriya UG is placed under Degree – I of gassiness.
13.2 INUNDATION
The Gunor river (perennial) flowing nearby the mine which almost encircle and form
the western, northern, southern (partly) and eastern boundary. Since there is no stream
crossing there is no danger of inundation during monsoon. During rainy season adequate
precautions are taken to prevent dangers due to inundation.
13.3 DUST SUPPRESSION
Dust is generated due to surface transportation of coal from pit head to EDC siding.
For suppression of dust water sprinklers have been provided, optimal loading and covered
transportation by trucks is being done. Avenue plantation of multi-cultural species along
the transportation road, coal stock and railway siding is done.
13.4 FIRE AND SPONTANEOUS HEATING
Spontaneous combustion of coal or other carbonaceous matter may be defined as
the process of self-heating of coal resulting eventually in its combustion without the
application of external heat. Various factors govern the spontaneous heating of coal viz.
Chemical Composition of coal, friability, presence of iron pyrites, depth of the seam,
thickness of the seam, geological disturbances, presence of bands etc.
To detect fire at an early stage regular monitoring of any sign of fire is being carried
out regularly as per statute.
(1) No person shall deposit heated material or ashes on any opencast working. Also no
person shall light a fire or permit a fire to be lighted in any UG working except by the
permission in writing of the Manager and only for a special purpose specified
therein.
(2) No coal shall be left exposed more than its incubation period to avoid fire in
seam due to spontaneous heating.
17
13.5 EXPLOSION
An explosion is a sudden combustion process of great intensity accompanied by
release of large quantities of heat energy and in which the original gas or solid substance
like coal dust is converted instantaneously into gaseous products. Explosion in Coal mines
are of (a) Fire damp (Methane), (b) Coal dust, or combination of both.
Explosion due to firedamp – Firedamp has been the cause of most of the explosions
in coalmines and in every mine steps are taken to prevent a fire damp explosion. Presence
of firedamp in air between 5.4% and 14.8% forms an explosive mixture. If a suitable source
of ignition is available the mixture results in an explosion.
Precautions taken against fire, heating (as pear CMR) also helps in preventing the
explosion.
Proper ventilation of the mine is the correct method to prevent dangerous built-up
of firedamp. Regular inspection of places where firedamp may accumulate is essential in
addition to proper ventilation.
Adequate provision for self-rescuers has been made in this project to enable
everybody to carry it underground. Stone dust barriers/water through barriers have been
provided as per statute.
Explosion due to coal dust – It has been established that coal dust when suspended
in the air as cloud, is capable of bursting into an explosion and propagate it, even in the
absence of firedamp.
A coal dust explosion can be prevented by:
(i) Reducing the formation of coal dust at the working places and suppressing the same by
water infusion, water spraying and by proper control of shot firing.
(ii) Preventing its spread during transport of coal.
(iii) Rendering coal dust harmless by wetting it with water or mixing with inert stone dust.
(iv) Provision of stone dust barriers or water barriers.
For monitoring the level of dustiness and quality of dust, regular sampling and analysis of
mine dust is being done and precautions are being taken as per statute.
(v) Avoiding accumulation of the methane in underground by proper ventilation and strict
adherence to DGMS guidelines/ Statues.
18
13.6 BLASTING
Special precautions may be taken while performing blasting operations. Solid
blasting is used for coal preparation. All precautions as per statute regarding transport,
handling and use of explosive shall be adhered to.
13.7 ADITIONAL PERMISSION / RELAXATIONS REQUIRED FROM DGMS
• General precautions: - The report has been made confirming to prevailing rules and
regulations in force. However all provisions of Mines' Act, Coal Mines Regulations and
its subordinate legislation may be followed.
• Mine Lighting: - Proper lighting arrangements shall be made in mine
• Exemption regarding provision of manpower: - Necessary exemption regarding
statutory manpower may be taken from DGMS.
• Risk Analysis: - Risk analysis studies shall be done for all critical activities. Also suitable
risk management plan for all critical activities shall be made and implemented.
14.0 ENVIRONMENTAL MANAGEMENT
EMP for Naheriya UG Mine is being prepared for 0.54 MTY Capacity. In the
subsequent paragraphs an attempt has been made to assess the likely environmental
impacts due to proposed mining activities.
To have a close watch on the environmental condition and implementation of the
various measures suggested, a multi - disciplinary approach is essential. At present WCL
headquarter acts as apex body which supervises the activities relating to environment at
project level through the General Manager. General Manager of the area coordinates the
activities of various disciplines in the area to render all necessary assistance at the
implementing level i.e. the project. Area Nodal Officer (Environment) monitors all aspects
of environment on behalf of the General Manager. He also takes suitable steps for
generation of environment data along with its analysis and interpretations.
Sub-Area Manager is responsible for biological reclamation with the assistance of
GM’s office.
For Environment Protection Measures, provision of Rs 6.00 / t of coal production
has been kept.
For Corporate Social Responsibility, provision of Rs 2.00 / t of coal production has
been kept.
15.0 MINE CLOSURE
The mine closure cost will cover the following activities for which a corpus fund will
be created by opening an escrow account with the coal controller organization in
nationalized bank. In case of mines having acid mine drainage, post closure acid mine
drainage management cost shall also be included in the total closure cost. An amount @ Rs
19
1.00 lakes per Ha of the project area will be deposited in this account for final mine closure.
Progressive mine closure will be done with the fund provided in approved report.
The above mentioned rate has been taken from Circular No. 55011-01-2009-CPAM,
Government of India, Ministry of Coal, Dated 27 August 2009 duly updated on 25 April
2012.
The Mine Closure was prepared and approved by WCL Board for Naheriya UG in
2012 taking Total land involvement of the mine as 300 ha and life of the project as 26 years
as on 01.04.2012.
After calculation, financial provision for closure of Naheriya UG Mine was around Rs.
749.83 lakhs (based on July 2012 provision WPI & at the @ Rs 1.0 lakh/ ha).
Escrow account has been opened and fund deposited till date is Rs. 46,24,000.00.
At present, Naheriya UG is proposed for enhancement in capacity from 0.36 MTPA
to 0.54 MTPA without any change in land area. Due to enhancement in production, life of
the project comes down to 15 years.
Mine Closure cost will be reviewed taking into account the total land, change in the
life of project, WPI as on date from website of Office of Economic Adviser, Ministry of
Commerce, Government of India based on these amount to be deposited in escrow account
every year with 5 % escalation will be calculated and deposited.
16.0 PROJECT IMPLEMENTATION SCHEDULE
Table 16.1 PRE AND POST SANCTION ACTIVITIES BEFORE STARTING EXCAVATION
Pre Sanction Activities Post Sanction activities before
starting excavation
Detailed surveying of the area Preparation of budgetary
estimates for construction of
various infrastructural facilities like
Coal Bunkers etc.
Dialogue with MP State Electricity Board to
finalise sources of power supply
Getting various statutory clearances.
Procurement of LHDs and Electrical
equipment. Creating facilities for
Material Transport.
Selection and training of manpower
for the project as per manpower
budget.
Proposal for various scientific
studies.
20
17.0 PROJECT ECONOMICS
Orginally, the Project Report of Naheriya has been approved by CIL Board for
Rs.46.1708 Crores with a target capacity of 0.36 MTPA.
Additional capital requirement for the project works out to Rs 8.62 crores and has
been approved by competent authority on 12.01.2016.
17.1 ADDITIONAL CAPITAL INVESTMENT
The Summarized form of additional Capital investment is given in Table below:
Table 17.1: Additional Capital Investment
S.No Item Amount (Lakhs)
1 Fabrication of Bunkers at Surface 100.00
2 Drinking Water Supply with Water Tank 3.00
3 Pumping (3 nos face pumps) 6.00
4 Ventilation Stoppings etc (35 nos) 35.00
5 Material Transport (1 DH, 10 Coal Tubs etc) 33.438
6 Production ( 4 LHDs, 2 Gate & 1 Trunk Belt) 410.04
7 Surface Power Supply (Power Transformer) 26.00
8 Electrical Equipments 248.52
TOTAL 861.998
17.2 EMS AND WAGES
The EMS calculated to Rs 2334.0 . The cost of salary wages = Rs. 2,80,080 per day.
17.3 SALE PRICE
The selling price of G6 Grade coal with above GCV has been considered as
Rs 2109 /t .
17.4 COST OF PRODUCTION
Total cost of production works out to be Rs 2270.68 per tonne (at 100% of
incremental production)
17.5 PROFIT & LOSS
In the incremental scenario, the overall losses of Nehariya UG mine are proposed to
reduce from Rs.1033.56/t to Rs.299.68/t at 100 % Capacity. In the incremental scenario, the
overall profit and operating profit is estimated to be Rs.762.11/t and 781.83/t respectively.
21
18. CONCLUSION
Proposed Increment by deployment of 4 LHDs and additional capital investment not
only enhances production but also reduce the losses incurred during operation.
*********
22
ENVIRONMENTAL
IMPACT ASSESSMENT (EIA)
&
ENVIRONMENTAL
MANAGEMENT PLAN
(EMP)
23
CHAPTER – I
ANTICIPATED ENVIRONMENTAL IMPACTS
&
MITIGATION MEASURES
24
Brief Description of Present Scenario of Project:
Environment clearance of Naheriya UG (refer Annexure –III) is for 0.36 MTPA rated
capacity in a lease area 300.0 ha, obtained , (vide no – J-11015/35/200/35/200-I A II (M)
date 15.11.2002). The land details are as follows -
Mine Lease Area - 300.0 ha
Agricultural land - 93.438 ha
Govt. land (Forest land) - 206.562 ha
A scheme for Naheriya UG Expansion has been prepared with enhancement in capacity to
0.54 MTPA from earlier 0.36 MTPA. Therefore fresh EC is now being solicited for capacity of
0.54 MTPA for operation of the mine as per following -
Capacity – Expansion from 0. 36 MTPA to 0.54 MTPA
Land area – 300.0 ha
Forest land – 206.562
Resettlement - NIL
Rehabilitation of land losers– NIL
S.No Particulars Area (ha)
AREA FOR UNDERGROUND MINING
A LEASEHOLD AREA 300.0
1. Govt. Forest 196.63
2. Big Trees Forest 8.32
3. Grass Land 5.84
4. Govt. Land under Water 0.67
5. Other Govt. Land 2.90
6. Tenancy Land and Abadi, etc 85.64
B AREA UNDER “ALL RIGHTS” 30.00
1. Non-Forest Land 30.0
Grand Total 330.00
Area under “ALL RIGHTS”
S.No Particulars Area (ha)
1. Land for mine entries and other infrastructure 5.00
2. Land for approach road to mine and colony 10.00
3. Land for township 15.00
Grand Total 30.00
Hence, at present EC for expansion of production capacity from 0.36 MTPA to 0.54 MTPA
in a ML area of 300 ha is solicited under section 7 (ii)
25
LOCATION AND COMMUNICATION:
Naheriya UG is named after Naheriya village which falls in Pench – Kanhan Valley Coalfield.
It is located in Chhindwara district of Madhya Pradesh.
The approach from Parasia to Naheriya Block is via Shivpuri OC Mine on BT weather road.
The mine is also approachable from Amarwada, a Tahsil town on Chhindwara – Narsinghpur
road. The distance between Amarwada and Naheriya is about 35 km and it is fully black
topped road.
The rail head for the mine currently used for coal dispatch is EDC siding which is
approximately 37km from Naheriya UG mine.
Latitude 22⁰ 16’32” to 22⁰ 12’ 53” N
Longitude 78⁰ 57’ 58” to 78⁰ 59’ 50” E
Toposheet No. 55/J (scale 1:50,000)
TOPOGRAPHY AND DRAINAGE:
The entire area of geological block is occupied by basalt which on differential
erosion has formed rugged terrain comprising of hills and valleys. The maximum elevation is
noticed in the south-eastern part with the contour value of 782 m. In central and south-
eastern part a continuous relatively flat high ground is formed with contour values between
760 m to 782 m. In the north-eastern past between boreholes PU- 93 & PU-151, an isolated
ridge is seen with maximum contour value of 756 m. The lowest elevation is seen in the
south-western past around PU-186 & PU-188 where contour value is 700 m.
The drainage in the block is mainly controlled by the perennial Gunor river
(together with Dhankasa nullah) which almost encircle and form the western, norther,
southern (Partly) and eastern boundary of the block. Number of nullahs flow in the block in
different directions guided by local topography and ultimately meet Gunor river.
1.0 IMPACT ASSESSMENT AND MITIGATIVE MEASURES
1.1 AIR POLLUTION IMPACT ASSESSMENT
The impact assessment has been carried out dealing with the following points:
(a) Phase-wise inventory of air pollution emission sources
(b) Impact assessment
a. Phase-wise inventory of air pollution emission sources
The pollution sources are obvious and to assess the impact, the project life is divided
into following time frames:
26
Operation phase
Post-Operational stage
The activities associated with these time frames and having impact on the ambient air
quality along with the pollutants are enumerated in the following sections:
Operational phase
During this phase, activities necessary for mining of coal, its handling and transport are
taken up. Such activities having impact on ambient air quality are detailed below:
(i) Drilling : Dust
(ii) Blasting of coal : Dust and noxious gases
(iii) Handling of coal : Dust and noxious gases
(iv) Movement of vehicles : Dust and noxious fumes
Post-Operational stage
The mine closure cost will cover activities for which a corpus fund has already been
created by opening an escrow account and additional funds considering expansion shall
also be included in the total closure cost. An amount @ Rs 1.00 lakhs per ha of the project
area will be deposited in this account for final mine closure. Progressive mine closure will
be done with the fund provided in approved report.
Modifications in physical and biological reclamation of subsided area, Salvaging and
shifting operation of UG Machineries and other equipment, Clearing of coal and other
materials, restoration of infrastructure area & colony area to the extent possible and
necessary if not useful for other projects, Management of hydrology and hydrogeology,
redeployment of workforce, etc, arrangement & implementation of post-operation
monitoring mainly keeping watch, vigil, etc.
The activities having impact on the ambient air quality are enumerated below:
(i) Movement of vehicles for shifting and salvaging
operation of UG Machineries and other
equipment
: Dust and obnoxious fumes
(ii) Movement of vehicles for clearing of coal and
other materials
: Dust and obnoxious gases
b. Impact assessment
Mining and its related activities create ambient air pollution. The impact of mining on
ambient air quality is highlighted in the following paragraphs:
In an underground, the ambient air quality is influenced due to the presence of PM10,
PM2.5, SO2, NOx, etc., which are generated due to various activities like drilling, blasting
27
and handling related to the project. Further, the ambient air quality is affected marginally
to a varying degree due to the mining activities of other nearby opencast and underground
coalmines of the same coalfield. The concentration of pollutants may vary depending upon
the various micro-meteorological parameters and the seasons of a year.
The baseline ambient air quality data generated for Chinda Mine which is near by site
of Naheriya UG shows that the levels of various pollutants are well within the permissible
limits.
Now, with the proposed expansion in production capacity of the project, there is
likelihood of addition of pollution to the existing concentration level of different attributes
of ambient air. Efforts are being made and will continue to be made by implementation of
proper abatement measures (as detailed out in the approved EIA/EMP) so as to maintain
the quality of ambient air, to the pre – mining level to the extent possible.
In order to assess the likely contribution of pollution due to proposed expansion in
production capacity by 0.54 MTPA, air quality data of the existing mine as well as of the
nearby projects have been considered.
The ambient air quality monitoring as per the existing EC is being carried out at four
locations selected on the basis of topography, wind directions and activity area. The
locations are as follows;-
Ambient Air Quality Monitoring locations :
S.No. Location Details Location Code
1.
2.
3.
4.
SAM Office
Bokai Township
Lamp room
Naheriya Village
PNUA-1
PNUA-2
PNUA-3
PNUA-4
The monitoring of ambient air quality parameters in respect of SPM, RPM, SO2 & Nox is
carried out on fortnightly basis as per Environmental Protection (Amendment) Rule,
2000. The Results of monitoring since quarter ending March 2014 up to September 2015
are given as below :-
28
Environment Laboratory CMPDI, RI IV, Nagpur
Test Report
T - 2969
Test Report No. : RIN/TR/QE-S15/A Date of Issue : 26.10.2015
Name of the Customer: Env.CMPDI, Nagpur Sampling method : IS-5182
Customer letter Ref. No. : �.ेस.4/प.अ./पा.का./15-16
Sample Description : Air sample No. of pages : 2
Test Required : IS-5182 [PM-10(04:1999),NOx (06:2006),SO2 (02:2001)] & TPM*.
AIR QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : SEP. NAME OF THE PROJECT : NAHERIA UG
1. SAM Office
: PNUA-1
( 24 hourly values in µg/m3 ) Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SOx
AUG.2015 11.08.15 - 12.08.15 39 13 7 16 SEP.2015 29.09.15 - 30.09.15 164 114 10 16
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120 2. Bokai Township : PNUA-2
( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SOx
JULY.2015 08.07.15 - 09.07.15 55 26 9 22 JULY.2015 29.07.15 - 30.07.15 89 77 23 20 AUG.2015 24.08.15 - 25.08.15 82 59 7 29 SEP.2015 11.09.15 - 12.09.15 103 62 7 14
PERMISSIBLE LIMIT 200 100 80 80
3. Lamp room / Sub station : PNUA-3
( 24 hourly values in µg/m3 ) Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SOx
JULY.2015 29.07.15 - 30.07.15 63 43 17 31 SEP.2015 29.09.15 - 30.09.15 116 76 9 22
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Naheria Village : PNUA-4
( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SOx
JULY.2015 08.07.15 - 09.07.15 53 44 12 30 JULY.2015 29.07.15 - 30.07.15 72 61 18 26 AUG.2015 11.08.15 - 12.08.15 50 28 6 24 AUG.2015 24.08.15 - 25.08.15 34 21 6 16 SEP.2015 29.09.15 - 30.09.15 129 79 13 11
PERMISSIBLE LIMIT 200 100 80 80
29
Environment Laboratory CMPDI, RI IV, Nagpur
Test Report
T - 2969
Test Report No. : RIN/TR/QE-J15/A Date of Issue : 23.07.2015 Name of the Customer: Env.CMPDI, Nagpur Sampling method : IS-5182
Customer letter Ref. No. : �.ेस.4/प.अ./पा.का./15-16 Sample Description : Air sample No. of pages : 2 Test Required : IS-5182 [PM-10(04:1999),NOx (06:2006),SO2 (02:2001)] & TPM*.
AIR QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : JUNE. NAME OF THE PROJECT : NAHERIA UG
1. SAM Office : PNUA-1
24 hourly values in µg/m3 ) Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX MAY.2015 11.05.15 - 12.05.15 112 53 4 18
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bokai Township : PNUA-2 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 Sox NOX APRIL.2015 08.04.15 - 09.04.15 130 68 9 22 MAY.2015 11.05.15 - 12.05.15 133 35 5 20 MAY.2015 27.05.15 - 28.05.15 331 241 8 31 JUNE.2015 11.06.15 - 12.06.15 36 34 6 22 JUNE.2015 24.06.15 - 25.05.15 66 36 5 19
PERMISSIBLE LIMIT 200 100 80 80
3. Lamp room / Sub station : PNUA-3 ( 24 hourly values in µg/m3 )
Month Dates of Sampling Parameters
From - To TPM PM-10 Sox NOX MAY.2015 11.05.15 - 12.05.15 138 46 5 21 JUNE.2015 11.06.15 - 12.06.15 400 254 7 31
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Naheria Village : PNUA-4
( 24 hourly values in µg/m3) Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX APRIL.2015 25.04.15 - 26.04.15 78 52 6 29 MAY.2015 27.05.15 - 28.05.15 191 75 9 22 JUNE.2015 24.06.15 - 25.05.15 73 19 6 10
PERMISSIBLE LIMIT 200 100 80 80
30
Environment Laboratory CMPDI, RI IV, Nagpur
Test Report
T - 2969
Test Report No. : RIN/TR/QE-M15/A Date of Issue : 15.04.2015 Name of the Customer: Env.CMPDI, Nagpur Sampling method : IS-5182
Customer letter Ref. No. : �.ेस.4/प.अ./पा.का./14-15 Sample Description : Air sample No. of pages : 2 Test Required : IS-5182 [PM-10(04:1999),NOx (06:2006),SO2 (02:2001)] & TPM*.
AIR QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : MAR. NAME OF THE PROJECT : NEHARIYA UG
1. SAM Office
: PNUA-1
( 24 hourly values in µg/m3 )
Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX JAN.2015 28.01.15 - 29.01.15 60 36 11 25 MAR.2015 28.03.15 - 29.03.15 466 251 7 22
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bokai Township : PNUA-2 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 Sox NOX JAN.2015 12.01.15 - 13.01.15 135 78 13 30 FEB.2015 11.02.15 - 12.02.15 64 41 5 22 FEB.2015 25.02.15 - 26.02.15 56 33 11 34 MAR.2015 13.03.15 - 14.03.15 29 27 9 29 MAR.2015 28.03.15 - 29.03.15 69 29 7 15
PERMISSIBLE LIMIT 200 100 80 80
3. Lamp room / Sub station : PNUA-3 ( 24 hourly values in µg/m3 )
Month Dates of Sampling Parameters
From - To TPM PM-10 Sox NOX FEB.2015 11.02.15 - 12.02.15 134 62 5 24 MAR.2015 28.03.15 - 29.03.15 305 210 7 29
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Neharia Village : PNUA-4
( 24 hourly values in µg/m3) Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX FEB.2015 11.02.15 - 12.02.15 35 15 5 15 MAR.2015 28.03.15 - 29.03.15 133 76 7 18
PERMISSIBLE LIMIT 200 100 80 80
31
Environment Laboratory CMPDI, RI IV, Nagpur
Test Report
T - 2969
Test Report No. : RIN/TR/QE-D14/A Date of Issue : 15.01.2015 Name of the Customer: Env.CMPDI, Nagpur Sampling method : IS-5182
Customer letter Ref. No. : �.ेस.4/प.अ./पा.का./14-15 Sample Description : Air sample No. of pages : 2 Test Required : IS-5182 [PM-10(04:1999), NOx (06:2006),SO2 (02:2001)] & TPM*.
AIR QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : DEC. NAME OF THE PROJECT : NEHARIYA UG
1. SAM Office
: PNUA-1
( 24 hourly values in µg/m3 )
Month Dates of Sampling Parameters From - To TPM PM-10 SOx NOX
NOV.2014 13.11.14 - 14.11.14 132 80 4 11 DEC.2014 09.12.14 - 10.12.14 264 229 9 21
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120 2. Bokai Township : PNUA-2
( 24 hourly values in µg/m3) Month Dates of Sampling Parameters
From - To TPM PM-10 Sox NOX OCT.2014 13.10.14 - 14.10.14 90 28 6 20 NOV.2014 13.11.14 - 14.11.14 136 98 3 16 NOV.2014 25.11.14 - 26.11.14 274 129 7 21 DEC.2014 09.12.14 - 10.12.14 159 71 10 23 DEC.2014 24.12.14 - 25.12.14 116 33 2 21
PERMISSIBLE LIMIT 200 100 80 80 3. Lamp room / Sub station : PNUA-3
( 24 hourly values in µg/m3 )
Month Dates of Sampling Parameters From - To TPM PM-10 Sox NOX
NOV.2014 13.11.14 - 14.11.14 224 117 4 24 DEC.2014 24.12.14 - 25.12.14 198 136 2 13
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
32
Environment Laboratory CMPDI, RI IV, Nagpur
Test Report
T - 2969
Test Report No. : RIN/TR/QE-S14/A Date of Issue : 15.10.2014 Name of the Customer: Env.CMPDI, Nagpur Sampling method : IS-5182
Customer letter Ref. No. : �.ेस.4/प.अ./पा.का./14-15 Sample Description : Air sample No. of pages : 2 Test Required : IS-5182 [PM-10(04:1999),NOx (06:2006),SO2 (02:2001)] & TPM*.
AIR QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : SEP. NAME OF THE PROJECT : NEHARIYA UG
1. SAM Office : PNUA-1
( 24 hourly values in µg/m3 ) Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX
JULY.2014 22.07.14 - 23.07.14 68 38 24 10
SEP.2014 10.09.14 - 11.09.14 13 8 21 11
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bokai Township : PNUA-2 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX
JULY.2014 10.07.14 - 11.07.14 308 203 38 13
AUG.2014 26.08.14 - 27.08.14 51 36 18 11
SEP.2014 10.09.14 - 11.09.14 43 11 21 13
SEP.2014 24.09.14 - 25.09.14 252 88 24 13
PERMISSIBLE LIMIT 200 100 80 80
3. Lamp room / Sub station : PNUA-3 ( 24 hourly values in µg/m3 )
Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX JULY.2014 22.07.14 - 23.07.14 36 15 31 11
SEP.2014 10.09.14 - 11.09.14 57 14 29 12
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Neharia Village : PNUA-4 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 SOx NOX AUG.2014 10.08.14 - 11.08.14 95 61 23 9 AUG.2014 26.08.14 - 27.08.14 92 33 11 14
SEP.2014 24.09.14 - 25.09.14 82 67 20 8
PERMISSIBLE LIMIT 200 100 80 80
33
AIR QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : JUNE. NAME OF THE PROJECT : NEHARIYA UG
1. SAM Office : PNUA-1 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SO2
MAY.2014 10.05.14 - 11.05.14 142 78 38 7
JUNE.2014 12.06.14 - 13.06.14 129 59 45 8
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bokai Township : PNUA-2 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SO2
APRIL.2014 04.04.14 - 05.04.14 232 130 4 34
APRIL.2014 24.04.14 - 25.04.14 40 17 5 74
MAY.2014 10.05.14 - 11.05.14 105 50 4 113
JUNE.2014 12.06.14 - 13.06.14 174 65 38 3
PERMISSIBLE LIMIT 200 100 80 80
3. Lamp room / Sub station : PNUA-3
( 24 hourly values in µg/m3) Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SO2
MAY.2014 10.05.14 - 11.05.14 232 139 4 129
JUNE.2014 26.06.14 - 27.06.14 202 132 68 53
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Neharia Village : PNUA-4 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To TPM PM-10 NOX SO2
APRIL.2014 04.04.14 - 05.04.14 237 66 6 47
APRIL.2014 24.04.14 - 25.04.14 36 30 7 59
JUNE.2014 13.06.14 - 14.06.14 99 36 26 9
JUNE.2014 26.06.14 - 27.06.14 296 217 47 36
PERMISSIBLE LIMIT 200 100 80 80
34
AIR QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : MAR. NAME OF THE PROJECT : NEHARIYA UG
1. SAM Office : PNUA-1 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN 2014 10.01.14 11.01.14 104 77 2 47
MAR 2014 12.03.14 13.03.14 46 34 7 22
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
2. Bokai Township : PNUA-2 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN 2014 10.01.14 10.01.14 226 56 3 46
FEB 2014 13.02.14 14.02.14 44 13 4 55
FEB 2014 27.02.14 28.02.14 89 32 5 85
MAR 2014 12.03.14 13.03.14 51 39 6 33
PERMISSIBLE LIMIT 200 100 80 80
3. Lamp room / Sub station : PNUA-3 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN 2014 23.01.14 24.01.14 79 44 3 41
MAR 2014 12.03.14 13.03.14 54 42 9 24
TLV as per Env.(Protection) Amendment Rule 2000 600 300 120 120
4. Neharia Village : PNUA-4 ( 24 hourly values in µg/m3)
Month Dates of Sampling Parameters
From - To SPM PM-10 NOX SO2
JAN 2014 10.01.14 11.01.14 101 47 3 53 JAN 2014 23.01.14 24.01.14 79 44 3 41
MAR 2014 12.03.14 13.03.14 57 48 6 30
PERMISSIBLE LIMIT 200 100 80 80
35
CO MONITORING DATA
( All values are given in µg/m3)
Sl. No.
Monitoring Location Monitoring Date Observed
Value
NAAQ Standards (1
hour)
1. SAM Office 12.03.14 < 114.3 10000
2. Bokai Township
12.03.14 < 114.3 4000
3. Lamp Room / Sub-station
12.03.14 < 114.3 10000
4. Neharia villege 12.03.14 < 114.3 4000 The ambient air quality will have no harmful effect on human being, flora and
fauna, soil quality, surface structures and aesthetic value of the surrounding environment
as suitable mitigative measures will be taken to make the operation eco-friendly.
Further, in order to assess the likely impact of proposed expansion of underground
mine on ambient air, numerical modeling has also been carried out by using FDM Air
Quality Model and is incorporated in subsequent pages. Air quality model is calculated
considering the Meteorological and the Monitoring data of Naheriya UG mine.
The numerical modeling has been carried out by using FDM Air Quality Model and
is incorporated in subsequent pages. Air quality model is calculated considering the
Meteorological datas of the nearby Chinda OC mine and routine monitoring data of
Naheriya UG is used as baseline.
The Naheriya UG mine is proposed for the expansion from 0.36 MTPA to 0.54
MTPA. At present, the average PM10 values (QE June 15 & QE Sept 15) of Naheriya UG
mine at SAM Office is 60 µgm/m3, Naheriya Villageis 47µgm/m3
, Bokai Township is 71
µgm/m3, lamp room is 105 µgm/m3, all are well within permissible limits. The incremental
values due to Naheriya UG 0.54 MTPA by FDM model works out to be at SAM Office is 0.54
µgm/m3, Naheriya Village is 0.14µgm/m3
, Bokai Township is 0.04 µgm/m3, lamp room is 0.46
µgm/m3
, The resultant pollution load ofNaheriya (0.54 MTY) . The increase in pollution due
to enhancement in capacity of this UG mine is insignificant. Hence the values will remain
within permissible limits
The results showing the Iso – pleths both for without and with Control measures
have been attached herewith in subsequent pages along with a Table of the resultant air
quality. It may be seen that the resultant air pollution level will remain well within the
permissible limits with the suggested control measures.
36
AIR QUALITY IMPACT PREDICTION (PM10)
SL.NO.
MONITORING
LOPCATIONS
(AS BASELINE
DATA)
MONITORING
DATA (AS
BASELINE
VALUE)
Incremental
Value
without
Control
Incremental
Value with
Control
Predicted
Value
Without
Control
Predicted
Value
With
Control
Permissible
Value
1 SAM Office 60 0.54 0.27 60.53 60.27 300
2 Bokai Township 71 0.05 0.02 71.04 71.02 100
3 Lamp Room 105 0.46 0.23 105.46 105.23 300
4 Naheriya Village 47 0.14 0.07 47.14 47.07 100
37
AIR QUALITY PREDICTION NAHERIYA UG EXPN.MINE
PM10 WITHOUT CONTROL MEASURES
38
AIR QUALITY PREDICTION NAHERIYA UG EXPN. MINE
PM10 WITH CONTROL MEASURES
39
1.2.1 AIR POLLUTION CONTROL MEASURES
Naheriya UG was commissioned in 1998, the environmental monitoring data
generation has been started on regular basis as per the Env (Protection) Amendment Rule
published Vide Gazette of dated 25.9.2000. In addition to data generation, following
abatement measures are being and will continue to be operated and maintained in order to
suppress the dust and noxious gases generation during the proposed expansion to the
maximum possible extent.
1.2.1 Drilling Operations
Coal Dust is generated during drilling operations, which is confined to UG
Workings and controlled by spraying as per the provisions of Coal Mines Regulation, 1957
and allied DGMS Technical Circulars.
1.2.2 Blasting Operation
In order to minimize the generation of dust during blasting, the following measures will be
adopted:
(a) Blast holes will be properly placed / spaced / positioned.
(b) Hole placing and blast design are looked into as a fresh case every time, by a
competent Blasting Officer who takes into consideration the actual geo-mining
conditions of the site.
(c) Blasting will be done between shifts or during the rest interval when the minimum
number of persons is present around the blast area.
(d) Adaptation of Controlled Blasting Technique as permitted by DGMS.
1.2.3 Loading & Transport
(a) All existing roads have already been Black topped and will be maintained to prevent
the dust formation due to vehicular movement.
(b) Continuous mobile spraying arrangement have been deployed to ensure dust
suppression.
(c) Avoiding overloading of trucks to prevent the spillage and covering of trucks
carrying coal with tarpaulin to avoid slippage.
(d) Minimizing free fall at all the transfer points, and continuous spraying arrangement.
(e) Regular cleaning of transportation roads..
(f) Adequate green belt will be developed all along the coal transportation road on both
sides.
(g) Fortnightly monitoring at four stations
40
All the above-mentioned control measures will be continued during the entire life of the
project.
1.2.4 Coal Handling Plant
No crushing & grinding arrangements exist at Naheriya UG mine. Coal is transported
through conveyor to the coal stock yard in the surface.
Some dust gets generated in coal bunkers during its operations like transfer and
conveying. Following abatement measures will be adopted during transportation and
handling.
i) Installation of sprinklers in the coal bunkers and along the conveyor belt for
suppression of dust in such a way that air borne dust is suppressed without adding
much water to the coal.
ii) Minimising the height of coal-fall at transfer points (to reduce dust formation) and,
if necessary, installing dust suppression measures.
iii) Enclosure of the belt conveyor to reduce the generation of dust due to blowing
wind.
iv). Create a green belt of trees on both sides of external belt conveyors and around coal
stocks yard to minimize wind erosion.
Noxious gasses are emitted through exhaust fumes during the operation of diesel /
petrol operated equipment. In order to reduce such emission, regular maintenance of the
diesel / petrol operated vehicles will also be carried out so that the emissions from these
vehicles are under control.
Water sprinkling on coal stock/face, blanketing of exposed surface will be carried
out to avoid spontaneous heating and minimize air pollution.
1.2.5 Ambient Air Quality Monitoring
The ambient air quality monitoring will continue to be carried out on regular basis as
per the Env (Protection) Amendment Rule, 2000 so as to ascertain the likely load of various
air pollutants and thereby suitably modifying the various control measures.
1.2.6 Plantation to Check Air Pollution
Plantation has been under taken in the mine area as mitigatives measure against air
pollution, noise pollution and to increase the aesthetic value. About 5000 nos of plantation
was done in Naheriya UG mine and in Bokhai Township, further plantation will be
developed at suitable places along the road sides, unused land etc to arrest as well as
reduce the rate of dispersion of dust generated due to various mining operations viz. coal
transportation, coal loading. Species to be planted (recommended by Forest Department)
in the area are as follow.
41
a) Ornamental trees viz Gulmohar and fruit trees like Mango, Guava, Jamun and medicinal
plant like Neem etc. will be planted in colony area, schools, dispensary, community
buildings, playground etc.
b) Ornamental shady trees will be planted e.g. around colony along roads and around
industrial buildings etc.
c) The fast growing varieties of trees act as sound barriers whereas Ornamental shady trees
e.g. Subabul, Kikar and Karanj will add to the aesthetic look of the area.
1.3.0 WATER QUALITY
Impact Assessment on Water:- Identification of the sources of water pollution
Likely sources of water pollution from this project along with the type of pollutants are as
follows:
(i) Domestic) wastewater Suspended solids and BOD.
(iii) Wastewater from mine Suspended solids of coal, clay and oil;
(iv) Surface run-off passing through coal
stockpiles
Suspended solids;
(v) Storm water from leasehold area and
built-up area
Suspended solids.
Impact assessment
Mining and its related activities may create water quality problems. The impact of mining at
the project on both surface and ground water sources has been assessed and given below:
(a) Surface water sources
• Deterioration of water quality and pollution of water bodies due to discharge of mine
effluent, if not treated.
• The mine water discharge quality of operating UG project is being monitored regularly
as per Env. (Protection) Amendment Rule, 2000. The analysis of mine effluent from
since March 2014 to September 2015 has been discussed in subsequent paragraphs.
The result indicates that mine pumped out water does not contain any pollution load.
• As such, during the proposed expansion of production in the subject mine the effluent
quality is expected to remain the same because of same hydro geological set up.
• However, due care will be taken to treat the mine water discharge by sedimentation
for the proposed expansion project. As such, possibility of adverse impact on natural
watercourses after mixing is very remote.
As per the condition stipulated in the EC Letter, the quality of mine pumped out
water is being monitored every fortnight as per Environmental Protection
42
(Amendment) Rule, 2000. All the quality parameters are monitored once in year. The
results are placed below:-
Water Quality Monitoring locations :
S.No. Location Details Location Code
1. Mine water discharge - PNUW-1
EFFLUENT WATER QUALITY REPORT NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : SEP.
NAME OF THE PROJECT : NAHERIA UG 1. Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH COD (mg/l) TSS (mg/l) O & G (mg/l)
Below Detection Limit 0.2 4.0 10.0 2.0 JULY.2015 08.07.15 3.93 24 20 <2 JULY.2015 30.07.15 6.07 40 90 <2 AUG.2015 11.08.15 5.33 40 44 <2 AUG.2015 26.08.15 5.43 132 86 <2 SEP.2015 11.09.15 6.44 184 78 <2 SEP.2015 30.09.15 3.18 28 32 <2 TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 250 100 10
DRINKING WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : SEP. NAME OF THE PROJECT : NAHERIA UG Sampling Date : 29.07.15 NAME OF LOCATION : DRINKING WATER FROM GUEST HOUSE
Sl. No Parameters
Test Method Analysis Result
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of alternate source
1 Colour ( Hz ) APHA, 22nd Edition Platinum Cobalt 1 5 15
2 Odour IS 3025 /05:1983, Physical, Qualitative Unobjectionable Unobjectionable Unobjectionable
3 Turbidity (NTU) IS-3025/10:1984 Nephelometric 3 1 5
4 pH Value IS-3025/11:1983 Electrometric 8.19 6.5 to 8.5 No relaxation
5 Total Hardness as CaCO3 -mg/l IS-3025/21:1983 EDTA 116 200 600
6 Iron (as Fe) -mg/l IS-3025/53:2003 AAS-Flame <0.06 0.3 No relaxation
7 Chlorides (as Cl)- mg/l IS-3025/32:1988, Argentometric 86 250 1000
43
Sl. No Parameters
Test Method Analysis Result
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of alternate source
8 Residual Chlorine -mg/l (min.) APHA, 22nd Edition DPD <0.02 0.2 1
9 Fluoride (as F)- mg/l APHA, 22nd Edition SPADNS 0.61 1.0 1.5
10 TDS -mg/l IS-3025/16:1984 Gravimetric 470 500 2000
11 Calcium (as Ca) -mg/l IS-3025/40:1991 EDTA 50 75 200
12 Magnesium (as Mg) -mg/l* IS-3025/40:1991 EDTA 7 30 100
13 Copper as(Cu) -mg/l IS-3025/42:1992 AAS-Flame <0.03 0.05 1.5
14 Manganese as (Mn)- mg/l APHA, 22nd Edition AAS-Flame <0.02 0.1 0.3
15 Sulphate (as SO4) -mg/l APHA, 22nd Edition Turbidity 86 200 400
16 Nitrates (as NO3) - mg/l IS-3025/34:1988 Nesseler’s 8 45 No relaxation
17 Cadmium as (Cd)- mg/l APHA, 22nd Edition AAS-GTA <0.0005 0.003 No relaxation
18 Lead as (Pb) -mg/l APHA, 22nd Edition AAS-GTA <0.005 0.01 No relaxation
19 Selenium (Se) –mg/l* APHA, 22nd Edition AAS-VGA <0.005 0.01 No relaxation
20 Arsenic (Ar)-mg/l* APHA, 22nd Edition AAS-VGA <0.005 0.05 No relaxation
21 Zinc as (Zn) -mg/l IS-3025/49:1994 AAS-Flame 0.132 5 15
22 Total Chromium -mg/l
IS 3025 (Part 52) : 2003 AAS-Flame
0.04 0.05 No relaxation
23 Boron as (B) -mg/l APHA, 22nd Edition Carmine <0.2 0.5 1.0
24 Alkalinity -mg/l IS-3025/23:1986, Titration 50 200 600
25 Nickel-mg/l IS 3025 (Part 54) : 2003, AAS-Flame Method
0.02 0.02 No relaxation
26 Aluminum (Al)-mg/l* APHA, 22nd Edition AAS-VGA <0.03 0.1 0.2
EFFLUENT WATER QUALITY REPORT
NAME OF THE COMPANY : WCL YEAR : 2015
NAME OF THE AREA : PENCH Q.E. : JUNE.
NAME OF THE PROJECT : NAHERIA UG 1. Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH COD (mg/l) TSS (mg/l) O & G (mg/l)
Below Detection Limit 0.2 4.0 10.0 2.0
APRIL.2015 08.04.15 4.04 24 42 <2 APRIL.2015 25.04.15 6.04 40 34 <2 MAY.2015 11.05.15 2.73 16 72 <2 MAY.2015 28.05.15 2.93 20 66 <2 JUNE.2015 12.06.15 2.61 20 70 <2 JUNE.2015 24.06.15 2.84 20 36 <2
TLV as per Env.(Protection) Amendment rule 2000 5.5 - 9.0 250 100 10
44
DRINKING WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : JUNE. NAME OF THE PROJECT : NAHERIA UG Sampling Date : 11.05.15 NAME OF LOCATION : DRINKING WATER FROM GUEST HOUSE
Sl. No Parameters
Test Method Analysis Result
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of alternate source
1 Colour ( Hz ) APHA, 22nd Edition Platinum Cobalt 1 5 15
2 Odour IS 3025 /05:1983, Physical, Qualitative Unobjectionable Unobjectionable Unobjectionable
3 Turbidity (NTU) IS-3025/10:1984 Nephelometric 1 1 5
4 pH Value IS-3025/11:1983 Electrometric 8.13 6.5 to 8.5 No relaxation
5 Total Hardness as CaCO3 -mg/l IS-3025/21:1983 EDTA 100 200 600
6 Iron (as Fe) -mg/l IS-3025/53:2003 AAS-Flame <0.06 0.3 No relaxation
7 Chlorides (as Cl)- mg/l IS-3025/32:1988, Argentometric 76 250 1000
8 Residual Chlorine -mg/l (min.) APHA, 22nd Edition DPD 0.07 0.2 1
9 Fluoride (as F)- mg/l APHA, 22nd Edition SPADNS 2.15 1.0 1.5
10 TDS -mg/l IS-3025/16:1984 Gravimetric 300 500 2000
11 Calcium (as Ca) -mg/l IS-3025/40:1991 EDTA 25.6 75 200
12 Magnesium (as Mg) -mg/l* IS-3025/40:1991 EDTA 9 30 100
13 Copper as(Cu) -mg/l IS-3025/42:1992 AAS-Flame <0.03 0.05 1.5
14 Manganese as (Mn)- mg/l APHA, 22nd Edition AAS-Flame <0.02 0.1 0.3
15 Sulphate (as SO4) -mg/l APHA, 22nd Edition Turbidity 13 200 400
16 Nitrates (as NO3) - mg/l IS-3025/34:1988 Nesseler’s 23 45 No relaxation
17 Cadmium as (Cd)- mg/l APHA, 22nd Edition AAS-GTA <0.0005 0.003 No relaxation
18 Lead as (Pb) -mg/l APHA, 22nd Edition AAS-GTA <0.005 0.01 No relaxation
19 Selenium (Se) –mg/l* APHA, 22nd Edition AAS-VGA <0.005 0.01 No relaxation
20 Arsenic (Ar)-mg/l* APHA, 22nd Edition AAS-VGA <0.005 0.05 No relaxation
21 Zinc as (Zn) -mg/l IS-3025/49:1994 AAS-Flame <0.01 5 15
22 Total Chromium -mg/l
IS 3025 (Part 52) : 2003 AAS-Flame
<0.01 0.05 No relaxation
23 Boron as (B) -mg/l APHA, 22nd Edition Carmine <0.2 0.5 1.0
24 Alkalinity -mg/l IS-3025/23:1986, Titration 96 200 600
45
Sl. No Parameters
Test Method Analysis Result
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of alternate source
25 Nickel-mg/l IS 3025 (Part 54) : 2003, AAS-Flame Method
<0.02 0.02 No relaxation
26 Aluminum (Al)-mg/l* APHA, 22nd Edition AAS-VGA <0.03 0.1 0.2
(BDL- Below Detection Limit)
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : MAR. NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN.2014 10.01.14 6.29 58 <40 <2 JAN.2014 22.01.14 8.02 30 <40 <2
FEB.2014 12.02.14 6.57 30 <40 <2 FEB.2014 26.02.14 5.02 40 <40 <2
MAR.2014 11.03.14 7.56 76 96 <2 MAR.2014 26.03.14 3.36 54 <40 <2
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
46
DRINKING WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. : MAR. NAME OF THE PROJECT : NEHARIYA UG Sampling Date : 12.01.15 NAME OF LOCATION : DRINKING WATER FROM GUEST HOUSE
Sl. No Parameters
Test Method Analysis Result
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of alternate source
1 Colour ( Hz ) APHA, 22nd Edition Platinum Cobalt 1 5 15
2 Odour IS 3025 /05:1983, Physical, Qualitative Unobjectionable Unobjectionable Unobjectionable
3 Turbidity (NTU) IS-3025/10:1984 Nephelometric 1 1 5
4 pH Value IS-3025/11:1983 Electrometric 8.29 6.5 to 8.5 No relaxation
5 Total Hardness as CaCO3 -mg/l IS-3025/21:1983 EDTA 228 200 600
6 Iron (as Fe) -mg/l IS-3025/53:2003 AAS-Flame <0.06 0.3 No relaxation
7 Chlorides (as Cl)- mg/l IS-3025/32:1988, Argentometric 18 250 1000
8 Residual Chlorine -mg/l (min.) APHA, 22nd Edition DPD <0.02 0.2 1
9 Fluoride (as F)- mg/l APHA, 22nd Edition SPADNS 0.75 1.0 1.5
10 TDS -mg/l IS-3025/16:1984 Gravimetric 340 500 2000
11 Calcium (as Ca) -mg/l IS-3025/40:1991 EDTA 32 75 200
12 Magnesium (as Mg) -mg/l* IS-3025/40:1991 EDTA 35.96 30 100
13 Copper as(Cu) -mg/l IS-3025/42:1992 AAS-Flame <0.03 0.05 1.5
14 Manganese as (Mn)- mg/l APHA, 22nd Edition AAS-Flame <0.02 0.1 0.3
15 Sulphate (as SO4) -mg/l APHA, 22nd Edition Turbidity 4.75 200 400
16 Nitrates (as NO3) - mg/l IS-3025/34:1988 Nesseler’s 7.48 45 No relaxation
17 Cadmium as (Cd)- mg/l APHA, 22nd Edition AAS-GTA <0.0005 0.003 No relaxation
18 Lead as (Pb) -mg/l APHA, 22nd Edition AAS-GTA <0.005 0.01 No relaxation
19 Selenium (Se) –mg/l* APHA, 22nd Edition AAS-VGA <0.005 0.01 No relaxation
20 Arsenic (Ar)-mg/l* APHA, 22nd Edition AAS-VGA <0.005 0.05 No relaxation
21 Zinc as (Zn) -mg/l IS-3025/49:1994 AAS-Flame <0.01 5 15
22 Total Chromium -mg/l
IS 3025 (Part 52) : 2003 AAS-Flame
<0.01 0.05 No relaxation
23 Boron as (B) -mg/l APHA, 22nd Edition Carmine <0.2 0.5 1.0
24 Alkalinity -mg/l IS-3025/23:1986, Titration 156 200 600
25 Nickel-mg/l IS 3025 (Part 54) : 2003,
AAS-Flame Method <0.02 0.02 No relaxation
26 Aluminum (Al)-mg/l* APHA, 22nd Edition AAS-VGA <0.03 0.1 0.2
47
EFFLUENT WATER QUALITY REPORT NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : DEC
NAME OF THE PROJECT : NEHARIYA UG 1. Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH COD (mg/l) TSS (mg/l) O & G (mg/l)
OCT.2014 30.10.14 5.88 <40 <25 <2 NOV.2014 13.11.14 5.54 <40 <25 <2 NOV.2014 25.11.14 5.69 <40 64 <2 DEC.2014 09.12.14 6.69 <40 <25 <2 DEC.2014 24.12.14 6.01 <40 <25 <2 TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 250 100 10
EFFLUENT WATER QUALITY MONITORING DATA
NAME OF THE COMPANY : WCL YEAR 2014 NAME OF THE AREA : PENCH Q.E. DEC. NAME OF THE PROJECT : . NEHARIYA UG Sampling Date 13.10.14 Name of the Location : Mine Water Discharge
Sl. No Parameters
Test Method Below Detection
Limit
Standard for discharge
Part A, Schedule VI
Analysis Result Remarks
1 pH Value IS-3025/11:1983 Electrometric 0.2 5.5 to 9.0 4.49
2 Temperature (0C) IS 3025 (Part 9) : 1984, Thermometric 0.5 Te < Ts + 5OC 25OC
3 Colour ( Hz ) APHA, 22nd Edition Platinum Cobalt 1 * 2
4 Odour IS 3025 /05:1983, Physical, Qualitative -- Unobjectionable Unobjectionable
5 TSS –mg/l IS-3025/17:1984 Gravimetric 10 100 42
6 Oil & Grease –mg/l IS-3025/39:1991 Partition Gravimetric 2 10 <2
7 C.O.D. – mg/l APHA, 22nd Edition Closed Reflux 4 250 <40
8 B.O.D. (3 days at 270C)-mg/l IS 3025 (Part 44) : 1993 2 30 2
9 Residual Chlorine -mg/l APHA, 22nd Edition DPD 0.02 1 <0.02
10 Ammonical Nitrogen-mg/l IS 3025 (Part 34) : 1988 0.02 50 0.05
11 Total Kjeldahl Nitrogen-mg/l APHA, 22nd Edition Kjeldahl 1 100 <1
12 Dissolved Phosphate –mg/l APHA, 22nd Edition Molybdovanadate 0.3 5 <0.3
13 Arsenic -mg/l* APHA, 22nd Edition AAS-VGA 0.005 0.2 <0.005
14 Lead -mg/l APHA, 22nd Edition AAS-GTA 0.005 0.1 <0.005
48
Sl. No Parameters
Test Method Below Detection
Limit
Standard for discharge
Part A, Schedule VI
Analysis Result Remarks
15 Hexavalent Chromium -mg/l
APHA, 22nd Edition 1,5-Diphenylcarbohydrazide
0.01 0.1 <0.01
16 Total Chromium -mg/l
IS 3025 (Part 52) : 2003 AAS-Flame
0.06 2 <0.06
17 Copper -mg/l IS-3025/42:1992 AAS-Flame 0.03 3 <0.03
18 Zinc -mg/l IS-3025/49:1994 AAS-Flame 0.01 5 0.011
19 Selenium –mg/l* APHA, 22nd Edition AAS-VGA 0.005 0.05 <0.005
20 Nickel -mg/l IS 3025 (Part 54) : 2003, AAS-Flame Method 0.1 3 <0.1
21 Cadmium - mg/l APHA, 22nd Edition AAS-GTA 0.0005 2 <0.0005
22 Fluoride - mg/l APHA, 22nd Edition SPADNS 0.02 2 1.90
23 Sulphide – mg/l APHA, 22nd Edition Methylene blue 0.005 2 <0.005
24 Iron -mg/l IS-3025/53:2003 AAS-Flame 0.06 3 <0.06
25 Manganese - mg/l IS-3025/59:2006 AAS-Flame 0.02 2 2.25
26 Nitrate Nitrogen - mg/l APHA, 22nd Edition UV-Spectrophotometric 0.5 10 6.0
EFFLUENT WATER QUALITY REPORT NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : SEP
NAME OF THE PROJECT : NEHARIYA UG 1. Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH COD (mg/l) TSS (mg/l) O & G (mg/l)
JULY.2014 10.07.14 6.92 <40 40 <2 JULY.2014 22.07.14 7.35 <40 40 <2 AUG.2014 09.08.14 3.57 <40 40 <2 AUG.2014 25.08.14 5.86 <40 20 <2 SEP.2014 10.09.14 8.70 64 46 <2 SEP.2014 24.09.14 3.98 <40 12 <2 TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 250 100 10
49
EFFLUENT WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : JUN. NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
APRIL.2014 04.04.14 3.23 46 <40 <2 APRIL.2014 24.04.14 5.28 30 <40 <2
MAY.2014 10.05.14 7.78 54 64 <2 MAY.2014 30.05.14 7.72 36 <40 <2
<2 JUNE.2014 12.06.14 7.97 42 <40 <2 JUNE.2014 26.06.14 6.00 58 <40 <2
TLV as per Env.(Protection)
Amendment rule 2000 5.5 - 9.0 100 250 10
DRINKING WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : Pench Q.E. : Jun. NAME OF THE PROJECT : Naheria UG Sampling Date : 30.05.14
Sl. No Parameters
Test Method Analysis Result
Guest House
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of
alternate source
1 Colour ( Hz ) APHA, 22nd Edition Platinum Cobalt < 5 5 15
2 Odour IS 3025 /05:1983, Physical, Qualitative Unobjectionable Unobjectionable Unobjectionable
3 Turbidity (NTU) IS-3025/10:1984 Nephelometric 2 1 5
4 pH Value IS-3025/11:1983 Electrometric 7.78 6.5 to 8.5 No relaxation
5 Alkalinity -mg/l IS-3025/23:1986, Titration 180 200 600
6 Total Hardness as CaCO3 -mg/l
IS-3025/21:1983 EDTA 152 200 600
7 Iron (as Fe) -mg/l IS-3025/53:2003 AAS-Flame <0.06 0.3 No relaxation
8 Chlorides (as Cl)- mg/l IS-3025/32:1988, Argentometric 14 250 1000
9 Residual Chlorine -mg/l (min.)
APHA, 22nd Edition DPD 0.03 0.2 1
10 TDS -mg/l IS-3025/16:1984 Gravimetric 400 500 2000
50
Sl. No Parameters
Test Method Analysis Result
Guest House
Standard ( IS : 10500 : 2012 )
Desirable limit PLV in the absence of
alternate source
11 Calcium (as Ca) -mg/l IS-3025/40:1991 EDTA 25.6 75 200
12 Copper as(Cu) -mg/l IS-3025/42:1992 AAS-Flame <0.03 0.05 1.5
13 Manganese as (Mn)- mg/l APHA, 22nd Edition AAS-Flame <0.02 0.1 0.3
14 Sulphate (as SO4) -mg/l APHA, 22nd Edition Turbidity 8 200 400
15 Nitrates (as NO3) - mg/l IS-3025/34:1988 Nesseler’s 15 45 No relaxation
16 Fluoride (as F)- mg/l APHA, 22nd Edition SPADNS 0.65 1.0 1.5
17 Cadmium as (Cd)- mg/l APHA, 22nd Edition AAS-GTA <0.0005 0.003 No relaxation
18 Lead as (Pb) -mg/l APHA, 22nd Edition AAS-GTA <0.005 0.01 No relaxation
19 Zinc as (Zn) -mg/l IS-3025/49:1994 AAS-Flame <0.01 5 15
20 HexvalentChromium -mg/l*
IS 3025 (Part 52) : 2003
AAS-Flame <0.01 0.05 No relaxation
21 Boron as (B) -mg/l APHA, 22nd Edition Carmine <0.2 0.5 1.0
22 Conductivity Conductivity meter 668 - -
23 Magnesium (as Mg) -mg/l*
IS-3025/40:1991 EDTA 21.47 30 100
24 Nickel-mg/l* IS 3025 (Part 54) : 2003, AAS-Flame method
<0.1 0.02 No relaxation
EFFLUENT WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : PENCH Q.E. : MAR. NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Mine water discharge - PNUW-1
Month Date of Sample Analysis Results collection pH TSS (mg/l) COD (mg/l) O & G (mg/l)
JAN.2014 10.01.14 6.29 58 <40 <2 JAN.2014 22.01.14 8.02 30 <40 <2
FEB.2014 12.02.14 6.57 30 <40 <2
FEB.2014 26.02.14 5.02 40 <40 <2
MAR.2014 11.03.14 7.56 76 96 <2 MAR.2014 26.03.14 3.36 54 <40 <2
TLV as per Env.(Protection) Amendment rule 2000 5.5 - 9.0 100 250 10
51
DRINKING WATER QUALITY MONITORING DATA NAME OF THE COMPANY : WCL YEAR : 2014 NAME OF THE AREA : Pench Q.E. : MAR. NAME OF THE PROJECT : Neheria UG DATE 12.03.14
Name of the Location : Drinking water from Guest House
Sl. No Test Parameters
Standard ( IS : 10500 : 2012 )
Analysis Result
Desirable limit Permissible limit in the absence of alternate source
1 Colour, Hazen unit, Max 2 5 15
2 Odour Unobjectionable Unobjectionable Unobjectionable
3 Turbidity, NTU, Max 2 1 5
4 pH value 7.89 6.5 to 8.5 No relaxation
5 Alkalinity, mg/l, Max 148 200 600
6 Total Hardness (caco3), mg/l, Max 252 200 600
7 Iron, mg/l, Max <0.06 0.3 No relaxation
8 Chlorides, mg/l, Max 18 250 1000
9 Residual Free chlorine, min. 0.03 0.2 1
10 Total Dissolved Solids, mg/l, Max 360 500 2000
11 Calcium, mg/l, Max 75.2 75 200
12 Copper, mg/l, Max <0.03 500 2000
13 Manganese, mg/l, Max <0.02 75 200
14 Sulphate, mg/l, Max 36 500 2000
15 Nitrate, mg/l, Max 13 75 200
16 Fluoride, mg/l, Max 0.68 1.0 1.5
17 Cadmium, mg/l, Max <0.0005 0.003 No relaxation
18 Selenium, mg/l, Max <0.005 0.01 No relaxation
19 Arsenic, mg/l, Max <0.005 0.01 0.05
20 Lead, mg/l, Max <0.005 0.01 No relaxation
21 Zinc, mg/l, Max 0.029 5 15
22 Hexavalent Chromium, mg/l, Max, <0.01 0.05 No relaxation
23 Boron, mg/l, Max <0.02 0.03 0.2
24 Aluminium, mg/l, Max BDL 0.003 No relaxation
25 Conductivity (µS/cm) 555 - -
26 Magnesium, mg/l, Max
11.55 75 200
52
In the proposed Naheriya UG expansion, similar quality of mine effluent can be
expected because of same hydro geological set up.
However, due care will be taken to treat the mine water discharge by sedimentation
for the proposed expansion project and moreover water will be mostly recycled in the mine
for dust suppression. As such, possibility of adverse impact on natural watercourses after
mixing is very remote.
Based on the data collected at similar coal mine, it can be concluded that the impact
due to proposed expansion in mining operation, the adverse impacts on water both surface
as well as ground water will be insignificant.
1.3.1 WATER POLLUTION CONTROL MEASURES
i) Domestic Effluent
Sewage disposal arrangement for quarters of this project has been made. At present
there are 418 Quarters in Bhokai Township, all quarters are provided with individual septic
tank and conventional soak pit arrangement. Before construction of 78 Quarters possibility
of construction of STP will be explored and appropriate decisions will be taken.
ii) Mine Water
In Naheriya 2 No's of surface sedimentation tanks with dimensions
(Tank 1- 15.6 x 11 x 2.5 m, Tank 2 -20 x 10 x 2 m with total capacity of 439 KL) are in
operation. Most of the suspended particles are settled in the sump and the supernatant
water is pumped out. The quality of mine pumped out water is regularly monitored and
from the analysis reports detailed out in previous pages it can be seen that all parameters
are well within the permissible limits. This water is passed through surface settling
channels. The water flowing from it is used in mine mostly and occasionally treated water is
discharged onto agricultural / local nallahs on villagers demand.
1.3.2 HYDROGEOLOGICAL SET- UP:
1.3.2.1 AQUIFIER
The core zone is occupied by Deccan trap. This formation is underlained by Motur
& Barakars in sequence. Weathered and fracture zone of basalt act as shallow aquifer. The
sandstone horizons serve as aquifers and shale/clay acts as aquicludes in Gondwanas
formations while in buffer zone, the sand in soil/weathered rock and the secondary
porosity in Basalts, act as aquifers. The various hydrogeological units developed in the study
area are in the following Table.
53
Type of aquifers in the study area
Sl. No. Type of aquifer
Depth
range
(m)
Core zone Buffer zone
1. Unconfined 0 - 25 Weathered Basalt
Soil and Weathered Basalts
and Metamorphics
2.
Semiconfined/
Confined
Beyond
25
Massive & fracture
Basalt, Sandstone
horizon in Barakars,
Sandstone with
primary & secondary
porosity
Barakar sandstone Basalts
and Metamorphics
The buffer zone is mostly covered by consolidated formations viz. Basalts, Metamorphics
which possess poor/negligible primary porosity and low infiltration factor. Thus, the
groundwater potential is generally moderate to poor in the buffer zone area.
1.3.3 GROUND WATER LEVEL
To collect the representative groundwater levels in the study area, CMPDI,RI-IV has
established a monitoring network with 25 dug wells (hydrograph stations) spread over the
buffer zone (10 km radius from the Nehariya UG). Water level monitoring in these
hydrograph stations has been done as per MoEF guidelines (four times in a year) during the
period June’08 and Nov’15.
The average water levels measured from the area in and around Nehariya U/G mine area
are given below.
Pre monsoon period Core Zone 2.80 m to 6.60 m
Buffer zone 2.00 m to 12.35 m
Post monsoon Core Zone 1.65 m to 6.43 m
Buffer zone 0.70 m to 9.30 m
Water Level and Fluctuation in the Study Area
Period Core zone Period Buffer zone
Max Min Average Max Min Average
2008 5.85 1.30 3.58 2008 7.30 1.55 2.96
2009 3.60 2.30 2.95 2009 2.80 0.10 1.33
2010 5.45 1.85 2010 9.45 0.85 2.75 2011 3.85 1.40 2.63 2011 6.50 0.15 3.46
2012 6.08 2.05 4.55 2012 10.00 1.10 3.63
2013 9.45 0.85 5.34 2013 9.45 1.25 4.93 2014 6.20 0.65 3.98 2014 7.15 0.30 3.15
2015 4.30 1.60 2.95 2015 6.75 0.30 3.50
54
1.3.4 WATER LEVEL TREND
Hydrographs of two permanent observation wells fixed by CMPDI, Regional Institute-IV are
presented in Fig.1& 2 to assess the water level trends from May’06 to Nov’15. Well No (P-
66) situated in the buffer zone (at Tumri Road) shows an increasing water level trend in
both Pre-monsoon as well as Post-Mon season which is shown in Figure -1.
Fig.1
A rising trend in post -monsoon water levels has been also observed at the station Urdhan
(P-60) situated in core zone of Nehariya U/G mine which also indicates that there is
marginal impact on ground water level as shown in Figure-2.
Fig. 2
55
1.3.4.1 GENERAL AQUIFER PARAMETER
No detailed hydrogeological investigations were carried out at Nehariya UG mine. The
observation well drilled by the Central Ground Water Board in Chhindwara district for
Gondwana sandstone aquifer have been considered for this project. The projected
hydraulic parameters of the aquifers in Barakar formation are as follows in table
Aquifer Parameters Of Nehariya Ug Mine
Aquifer Parameters Unit Project for Nehariya
Transmissivity m2/day 20 to 50
Hydraulic conductivity m/day 0.3 to 0.7
Storage coefficient - 3.0 x 10-2 to 5 x 10-4
Specific yield - 0.03 to 0.05 (Assigned)
1.4 GROUND WATER RESOURCES IN THE AREA
1.4.1 GROUND WATER RECHARGE
Rainfall is the main recharge source for groundwater. The study area receives an average
annual rainfall of 1350 mm. Groundwater is also being recharged from other sources such
as return flow from irrigation etc. The replenishable groundwater recharge has been
computed by rainfall-infiltration method of different formations in the area. An area of 10
km radius from the periphery of Nehariya UG is considered as buffer zone. Out of the total
area of 314 sq. km of buffer zone, 99.38 % of the area i.e. about 312.055 sq. km is covered
by Basalt, 0.245 sq. km is covered by Bijori Formation and the remaining 1.7 sq. km is
covered by Metamorphics. The rainfall-infiltration factor for all these 3 formations i.e.
Basalt, Bijori and Metamorphic has been considered to be 8% (GEC report-1997). The
groundwater balance computation for this study area of 314 sq. km has been done as per
GEC -1997 norms and is furnished below:
Recharge in Buffer Zone by Rainfall Infiltration Method
Description of items Quantity
1. Area Bijori – 0.245 sq. km
Basalt- 312.055 sq.km
Metamorphic- 1.7 sq.km
2. Normal Rainfall during
a. Monsoon season in mm (June to Oct)
b. Non-monsoon season in mm (Nov to
May)
c. Non-monsoon season rainfall as a
percentage of normal annual rainfall
(Yes if > 10%, No if < 10%)
1350 mm
Negligible
No, it is <10%. Therefore Recharge during
56
non-monsoon is not considered.
3. Rainfall infiltration factor Bijori – 8%
Basalt – 8 %
Metamorphics- 8%
4. Rainfall recharge in Buffer zone by rainfall
infiltration factor method
a. Monsoon season (MCM)
[ (1) * (2a) * (3) ]
i) Bijori – 0.026 [0.245*1.35*0.08]
ii) Basalt – 33.70 [312.055*1.35*0.08]
iii)Metamorphics- 0.183 [1.7*1.35*0.08]
Gross Rainfall Recharge 33.909 MCM
Recharge in Buffer Zone by Water Level Fluctuation Method
Description of items Quantity
1. Area Bijori – 0.245 sq. km
Metamorphic- 1.7 sq.km
Basalt- 312.055 sq.km
2. Water table Fluctuation Bijori- 3.4
Metamorphics- 3.45
Basalt- 3.5
3. Specific Yield Bijori- 0.02
Metamorphic- 0.012
Basalt- 0.02
4. Change in groundwater
storage
[ (1) * (2) * (3) ]
Bijori–0.016 MCM
Metamorphic-0.070 MCM Basalt- 21.84 MCM
5. Gross Rainfall Recharge 21.93 MCM
As recommended in GEC Report 1997, the rainfall recharge during monsoon season is
estimated after comparing results from by calibrating results from Water table Fluctuation
Method and Rainfall Infiltration Factor Method, given in Table below:
Calibration of Ground Water Recharge in Buffer Zone
Description of items Quantity
1. Rainfall Recharge during monsoon season in Buffer Zone
a. By Water Table Fluctuation Method
b. By Rainfall Infiltration Factor Method
21.93 MCM
33.909 MCM
2. Difference between (1a) and (1b) expressed as a percentage of (1b), ‘PD’
{(1a) – (1b)}
[ ------------------ * 100 ]
(1b)
-35.32 %
3. Rainfall Recharge in the Buffer Zone during monsoon season after
57
considering the ‘PD’
[ = (1a) if ‘PD’ is between -20 and +20%
= 0.8 * (1b) if ‘PD’ is less than -20% = 0.8 * 33.67=26.93
= 1.20 * (1b) if ‘PD’ is greater than +20% ]
27.13 MCM
1.4.2 NET GROUNDWATER AVAILABILITY
The Net annual ground water availability of 27.37 million cubic meters have been estimated
for the study area (buffer zone), given in Table
Net Groundwater Availability in Buffer Zone
Description of items Quantity
1. Rainfall Recharge in Buffer Zone
a. During Monsoon season
b. During Non-monsoon season (10% of 1a)
c. Annual [ (1a) + (1b) ]
27.13 MCM
2.71 MCM
29.84 MCM
2. Recharge from ‘Other Sources’
Return flow from Irrigation [ 20 % of Irrigation Draft ]
Return flow from Excess mine water [ 20% as a seepage
factor ]
Total
0.41 MCM
0.16 MCM
0.57 MCM
3. Total Annual Groundwater Recharge
[ (1c) + (2) ]
30.41 MCM
4. Unaccounted annual natural discharge
a. [ 0.05 * (3) ] if rainfall recharge during monsoon
season computed by ‘Water table Fluctuation
Method’
b. [ 0.10 * (3) ] if rainfall recharge during monsoon
season computed by ‘Rainfall Infiltration factor
Method’
30.41*0.10=3.04 MCM
5. Net Annual Groundwater Availability in Buffer Zone
[ (3) – (4) ]
27.37 MCM
1.4.3 GROUND WATER DRAFT
The groundwater withdrawal is generally for irrigation, domestic and industrial requirement
and is quantified as under.
The irrigation draft (40000 l/Ha/day) of the buffer zone of this block of 426.88 Ha has been
considered for ground water irrigation (120 days) and was estimated as 2.04 million cubic
meters. Gross Groundwater Draft for ‘All Uses’ is furnished in Table given below-
58
Gross Groundwater Draft for ‘All Uses’
Sl No. Purpose No./Area Water consumption
per capita
Total qty. of
withdrawal (MCM)
1.
a) Domestic
(Human Population)
for 365 days
b) Domestic
(Animals) )(20% of
human population)
for 365 days
77080 Nos.
20000 Nos.
70 lit/day
20 lit/day
[77080*70*365]=
1.97
[20000 *20*365]=
0.15
2.
Irrigation (for 120
days)
426.88 ha.
40000 lit/ha/day
2.04
3.
Mine pumping 3 nos 0.78
Total : 4.94
1.4.4 GROUND WATER BALANCE
i) Gross groundwater recharge : 30.41 MCM
ii) Natural discharge to drains & other
losses (Approx.10% of item (i)) : 3.04 MCM
iii) Net annual groundwater availability : 27.37 MCM
iv) Annual groundwater draft for all uses : 4.94 MCM
v) Groundwater balance (Item iii-iv) : 22.43 MCM
Ground water balance flow diagram is shown below.
59
GROUND WATER BALANCE OF NAHERIYA UG EXPN. MINE BUFFER ZONE (All values in MCM)
QUANTITY OF WATER FALLING OVER THE AREA OF 314 sq.km. FROM RAINFALL
OF 1.15 m
Actual Evapotranspiration
Surface run-off
RAINFALL RECHARGE 21.67
RECHARGE FROM OTHER SOURCES 0.43
Infiltration
GROSS RECHARGE 22.10
Metamorphics & Basalts 6%
NET ANNUAL GROUND WATER AVAILABILITY- 19.89
90 % NATURAL DISCHARGE AND THERS LOSSES 2.21
PRESENT DOMESTIC-1.51
INDUSTRIAL NIL
IRRIGATION 1.72
EXISTING MINE PUMPING -0.20
TOTAL DRAFT 4.18
GROUND WATER BALANCE / AVAILABILITY 15.71
10 %
Addition Subtraction
361.10
60
1.4.5 STAGE OF GROUND WATER DEVELOPMENT
Description of items Buffer Zone
1. Stage of Groundwater Development
a. Net Groundwater Availability
b. Annual Gross Groundwater Draft
c. Annual Groundwater Balance
d. Stage of Groundwater Development
[ {(1b) / (1a)} * 100 ]
27.37 MCM
4.94 MCM
22.43 MCM
18.04 %
The present stage of ground water development in and around the project is about 18.04 %
which can be categorized as "Safe" zone with less than 70% value.
1.4.6 GROUND WATER QUALITY
The groundwater quality in the area is being monitored regularly (once in a year) by CMPDI,
an ISO-9001 company and the results indicate the groundwater quality in the area is potable
and does not contain any toxic elements. Generally, the water quality is slightly alkaline in
nature with pH value of 7.01 to 7.41 of potable quality with low to medium concentration of
total dissolved solids (TDS) i.e. 240 mg/l to1120 mg/l which is under permissible limit for
drinking as per BIS 10500:2012. Normally, the coal mining activity does not induce any
unwanted chemical or elements into the groundwater affecting the water chemistry except
for total suspended solids (TSS); hence no serious pollutant is observed in the mine
discharged water.
The mine water will be discharged onto surface after passing through the sumps and
sedimentation tanks. Hence, no quality degradation of mine water is anticipated.
1.4.7 MINE DRAINAGE / PUMPING
The mining area is mainly covered by Moturs and Barakar below the Basalts. The semi-
consolidated Gondwana are mostly stratified formations underlying the basalts. The permeable
beds (Sandstone horizons) of Barakars act as individual hydrogeological units and develop multi-
aquifer system. As such under these circumstances, the groundwater flow / velocity along the
bedding planes is higher than across the plane. It is imperative that horizontal hydraulic
conductivity is many folds higher than the vertical hydraulic conductivity.
The roof conditions vary from moderately cemented sandstones to thin shale or sandy
shale and clay materials, Weak strata in the immediate roof sages into the opening with fracturing
61
and bed separation whereas a strong roof holds the strata in place. When sagging in the formation
occurs, the water from the overlying zones flows into the underlying voids at rates defined by the
fracture size and water bearing properties of the rock formation. The in-flow is generally high if
cracks propagate into shallow formation, while it is marginal when cracks are confined
In Naheriya U/G, the formations overlying the working Seam are mainly composed of shale,
variegated clay and thus are having very low permeability.
Based on the Darcy’s law (i.e. Q= KIA), the groundwater inflow from different mine galleries were
predicted.
Mine inflow Prediction (Nehariya U/G):
S No. Roof Area
(Seepage Area) (m2)
(A)
Permeability
m/d
(K)
Hydraulic gradient
(I)
Mine inflow
(m3/day)
(Q)
1. 2752000 0.01 1.5x10-2 412.80
The groundwater inflow computation has been done by utilizing the above
mentioned aquifer and mine parameters. The groundwater inflow to the mine has
been estimated to be around 412.80 m3/day.
1.4.8 RADIUS OF MINE INFLUENCE AREA
The mining area of Nehariya U/G is generally covered by thick Basalts followed by
thick Motur formation. Coal is encountered in Barakar Formation which lies below Motur
Formation. Motur Formation generally consisting of variegated clay and fine grained
sansdstone have high porosity but very less conductivity. Hence because of this, it act as
very poor groundwater potential aquifer. In most of the cases, water seepage takes place
from the roof of the galleries and its influence terminates at the boundary between Moturs
and Barakars. It has been observed that in Pench, Kanhan and Pathakhera coalfields that
fractures does not propagate to the surface and ground water seepage occurs only where a
sustainable water bearing zone is hydraulically connected to the immediate roof of the
Underground mine. There is no lateral ground water movement within the coal seam and
the small openings in the roof have only localized impact. Thus, as long as the vertical
permeability of the overburden remains low, as long as the main roof is not fractured
significant drainage and cone of depression will be limited to immediate aquifer above the
working coal seam only. In the above unconfined aquifers, separated from the mine by
unaffected Motur Formation, effects of mining are diffused.
62
1.5 IMPACT OF MINING ON WATER REGIME
The mining activity creates dis-equilibrium in environmental scenario of the area and
disturbs the groundwater conditions/regime in particular. The impact on water regime due
to mining activity can be broadly classified as under:
i) Impact on topography & soil
ii) Impact on surface water and quality
iii) Impact on groundwater & quality
A brief description/out-line on these aspects is given below:
1.5.1 IMPACT ON TOPOGRAPHY AND SOIL
In general, a local change in ground topography occurs due to open cast mining
operations such as open pit, embankments, dumps of overburden and coal. But as Nehariya
U/G is an underground mine, no such major topographical changes will takes place except
some minor changes restricted to site of mine opening. As a result, there would be no or
marginal change in the drainage and surface run-off. The external dumping will be very less
as compared to dumping associated with open cast mining. Hence there will be pretty less
silting on soils and local drains thereby marginal change in drainage of the area. Further the
fine dust particles of coal arising due to coal transportation may adversely affect the
porosity of soils.
Within the core zone area, underground workings may lead to development of
cracks and loosening of soil and thereby changing physical and textural properties of
soil/formations. This mine-induced process increases the rate of infiltration and recharge.
It may be appropriate to high light the fact that temporary groundwater loss/deficit
created during active mining stage would be compensated by these different means in the
post mining stage so that the initial groundwater levels are regained to normalcy at the
earliest for the utility of the area.
1.5.2 IMPACT ON SURFACE WATER AND ITS QUALITY
As mentioned earlier, there would be minor change in the ground topography and
infiltration capacity/rate of soil/formation due to mining operations resulting in some local
change in drainage pattern and surface run-off in core zone. It is established that high
infiltration zone would serve as good media for high groundwater recharge and reduces the
surface run-off considerably in the core zone. In view of this, the mine has to handle more
water in the monsoon besides the additional contribution from the surface run-off from the
catchment area. As such the surface run-off contribution to the natural drains from the
mining area would be reduced / minimum thereby some minor change is expected in
hydrologic regime of the river system.
63
1.5.3 IMPACT ON GROUND WATER AND ITS QUALITY
Mining is associated with groundwater problems, particularly when it is below water
table. The impact of mining on groundwater is dependent mainly on mine and aquifer
parameters, groundwater recharge-discharge process etc. In the underground mining, the
unconfined aquifer gets little affected whereas the semi-confined aquifers are more
affected due to continuous gravity drainage from the aquifer just above coal seam. As such,
during the caving basically the water level is to be depressed / depleted above the working
seam depth in which case large scale mine water pumping will be done. Consequently the
mine dewatering would drain out some area around the mine with decline in groundwater
levels of aquifer just above coal seam. However, these mine induced effects are temporary
and likely to be recovered after some time of mine closure.
Groundwater inflow and mine influence area have been estimated and the
groundwater monitoring would be undertaken as corrective measure to avoid adverse
effects. The mine discharge after passing through sedimentation pond / tank would be
discharged onto land/natural drains with earthen check dam at suitable locations so that the
groundwater gets additional recharge by the return flow. The artificial recharge by water
conservation structures in mine influence area proper may not be a viable solution because
of the reason that recharged water would drain to the mine at a faster rate due to the steep
hydraulic gradients resulted in during mining activity. As mentioned earlier the mine impact
may be for temporary period during mine life and the area would regain the
normalcy/benefits in many ways by appropriate reclamation measures during post-mining
period. However, the water shortage in the mine influence area would be supplemented
from the treated mine water discharge for both domestic & irrigation use of affected
villages if any. Hydrogeological regime may change in case of induced blasting of Basalt
formation for caving purposes. In this case detail Hydrogeological study is required as this
will be the first mine to be caved by blasting.
AUGMENTATION OF GROUNDWATER RECHARGE POTENTIAL
As a part of environmental protection, the project has been adopting all possible
measures to increase the ground water recharge potential in the influenced and nearby
areas.
1.6 AFFORESTATION AND PLANTATION
To improve the environment and greenery in the area, WCL has taken up
plantation on a larger scale in the coal mining area. Physical reclamation is the first stage
of reclamation in which geometrical shapes of the dumps are made suitable for biological
reclamation and make it stable and safe. Biological reclamation involves growing of
grasses and trees that can check the soil erosion from the dump. The improvement in
vegetation cover has a direct bearing on augmentation of ground water recharge.
64
1.7 RAIN WATER HARVESTING AND ARTIFICIAL RECHARGE
Coal mining is the major industrial activity in the area. Ground water pumping is an
integral part of coal mining. Besides this, groundwater utilization is mainly for domestic and
irrigation use in the study area.
To minimize the impact of mining on ground water system, the project/mine
authority has been adopting all possible measure to increase the ground water recharge
potential.
The stage of ground water development in the buffer zone (10 km from the
periphery of the core zone) of Nehariya U/G comes to about 18.04%.
However, artificial recharge may be done for more use of ground water for irrigation
augmentation in the study area when the source of water is easily available for recharging.
The artificial recharge by water conservation structures in the outside mine influence
areas will check water level lowering. But within the mine influence area it may not be a
viable solution because of the reason that recharged water would drain into the mine at a
faster rate due to the steep hydraulic gradients resulted in the mining activity.
However, additional artificial recharge will be taken up for improving the quality of
ground water.
The impact on ground water level is being minimized by artificial recharge by
spreading of pumped out water, creation and filling of ponds with mine water and
construction of rainwater harvesting structure.
In the monsoon season the garland drain channels the surface run-off from the
different mines area without any contamination and is accumulated in mine sump and being
utilized for different purposes.
Roof-top rainwater Harvesting has already been taken up in the project area using
the administrative buildings. Rainwater Harvesting and artificial recharge will also take place
through abandoned dug-wells and final voids of old mines for increasing ground water
potential and check water level lowering.
After mine closure, void of opencast and underground workings will be waterlogged.
This will help in maintaining the water table in the surrounding areas and may become a
source of water supply to the community.
Creation of awareness among workers and local peoples about rain water Harvesting
and artificial recharge will be given priority. This aspect is usually covered during the
Environmental Week celebrated every year (5th to 12th June).
Efforts are being made to construct more recharge structures (i.e. ponds/tanks) at suitable
sites in the nearby affected villages.
65
1.8 CONSERVATION MEASURES:-
• The mine discharge will be utilized to meet the mine’s domestic, dust
suppression, firefighting and other industrial water needs.
• After the cessation of mining, with copious rainfall and abundant
groundwater recharge, the water levels will recoup and attain normalcy.
Thus, the impact of mining on groundwater system may be considered as a
temporary phenomenon. The old mine workings also behave as water pools
and improves the resource availability in the area.
• The construction of surface tanks and settling tanks/deepening of existing
low-lying area in the local villages would enhance the water availability in the
nearby villages. Utilization of mine water for irrigation use will also enhance
the ground water recharge potential through artificial recharge in the area.
Thereby, in post-mining condition, the recharge and source potential in core
zone will be much higher than the existing.
• The discharged mine water would be available for the local people to utilize
in irrigation and domestic use. Thereby the mine water will be a resource for
many of the local villagers.
1.9 FUTURE STRATEGY
• To create the water source and to increase ground water recharge, under
community development, tanks/ponds/dugwells will be constructed in
the nearby villages.
• Increase vegetative cover by plantation in the mine areas. This will
contain the surface runoff and increase the ground water recharge.
• Monitoring of water quality of mine water discharge, local river/nala and
domestic water (dug well/hand pumps) will be continued under routine
monitoring.
• On analyzing the field data if any area receiving the maximum impact,
suitable controls measures will be adopted by the project authorities.
1.10 NOISE QUALITY
In order to assess the existing ambient noise level in the surrounding of project site
corresponding to pre-mining scenario, baseline noise level data was generated & details
were given in approved EIA/EMP. All the values were found well within the permissible limit.
Proposed expansion mine would be associated with following activities that may
generate noise during operation:
66
(a) Drilling
(b) Blasting
(c) Heavy underground machinery operation
(d) Loading & unloading
(e) Operation of CHP / Workshop
The following are some of the important activities responsible for high noise level
generation, with their expected noise levels:
All mining activities i.e. drilling, blasting, shoveling, dozing and dumping are
associated with high noise level [about 100 dB(A)].
Operation underground machinery contributes to noise levels. The noise level are in
range of 80 – 100 dB(A). Noise levels have been found to be related to engine capacity.
ACCEPTABLE INDUSTRIAL NOISE LEVEL
As per Env. (Protection) Amendment Rules, 2000 the ambient air quality standards
in respect of noise in industrial, commercial, residential and silence zones area as follows:
Sl. No. Category of area Limits [dB(A)]
Day time (6.00 AM to 10.00 PM )
Night time (10.00 PM to 6.00 AM )
1. Industrial 75 70
2. Commercial 65 55
3. Residential 55 45
4. Silence zone 50 40
Assessment of the degree of harmful workplace noise is done by comparing the
values measured at workplace to the permissible limit adopted by statutory bodies like
DGMS.
The Director General of Mines Safety vide their circular no. DG (Tech.)/18 of 1975 has
prescribed the permissible limit for noise level as 90 dB(A), for the workers engaged in
mining occupation likely to be exposed to in an 8 hour shift period with unprotected ear.
The following table shows the maximum permissible noise exposure levels, as per American
Standards, for the industrial workers.
67
To assess the likely contribution from proposed expansion project, the ambient noise level
of operating mines of the same area has been taken into consideration. It is observed that
noise level recorded near Near Fan house PNUN-1 & near colony PNUN-2 (Fan houses are
major source of noise in UG mines) are well within the permissible limit.
NOISE LEVEL DATA NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. :SEP. NAME OF THE PROJECT : NAHERIA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A) collection Day Time Night Time
JULY.2015 08.07.15 71.6 71.4 JULY.2015 30.07.15 68.7 66.3 AUG.2015 11.08.15 70.9 69.9 AUG.2015 25.08.15 69.6 67.2 SEP.2015 12.09.15 70.8 70.6 SEP.2015 28.09.15 69.4 68.1 Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A) collection Day Time Night Time
JULY.2015 08.07.15 42.5 41.4 JULY.2015 30.07.15 44.7 41.9 AUG.2015 11.08.15 43.5 42.9 AUG.2015 25.08.15 44.5 41.2 SEP.2015 12.09.15 42.7 42.4 SEP.2015 28.09.15 44.9 42.4 Noise Level Standard as per Env.
(Protection) Amendment rule 2000 55 45
Exposure time (Hrs./day) Noise level [dB(A)]
8 90
6 92
4 95
3 97
2 100
1.5 102
1 105
0.5 108
0.25 or less 115
EXPOSURE TO PULSE OR IMPACT NOISE SHOULD NOT EXCEED 140 dB(A)
68
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2015 NAME OF THE AREA : PENCH Q.E. :JUNE NAME OF THE PROJECT : NAHERIA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A) collection Day Time Night Time
APRIL.2015 09.04.15 70.6 70.2 APRIL.2015 25.04.15 69.8 69.2 MAY.2015 11.05.15 70.1 66.1 MAY.2015 27.05.15 69.2 68.6 JUNE.2015 11.06.15 70.2 70.0 JUNE.2015 25.06.15 70.4 70.2 Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A) collection Day Time Night Time
APRIL.2015 09.04.15 42.2 42.0 APRIL.2015 25.04.15 44.1 42.2 MAY.2015 11.05.15 50.6 40.1 MAY.2015 27.05.15 45.1 41.9 JUNE.2015 11.06.15 45.4 42.2 JUNE.2015 25.06.15 42.7 42.4 Noise Level Standard as per Env.
(Protection) Amendment rule 2000 55 45
69
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2015
NAME OF THE AREA : PENCH Q.E. :MAR.
NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
JAN.2015 12.01.15 69.4 68.2
JAN.2015 29.01.15 71.4 65.8
FEB.2015 11.02.15 68.7 68.3
FEB.2015 26.02.15 70.4 66.3
MAR.2015 14.03.15 68.5 68.1
MAR.2015 28.03.15 69.4 68.1
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
JAN.2015 12.01.15 43.4 43.3
JAN.2015 29.01.15 38.9 36.5
FEB.2015 11.02.15 43.3 42.5
FEB.2015 26.02.15 42.5 41.8
MAR.2015 14.03.15 43.5 43.1
MAR.2015 28.03.15 45.1 43.2
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 55 45
70
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2014
NAME OF THE AREA : PENCH Q.E. :DEC
NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
OCT.2014 13.10.14 68.2 67.9
OCT.2014 30.10.14 67.7 66.5
NOV.2014 13.11.14 69.6 68.7
NOV.2014 25.11.14 69.4 69.1
DEC.2014 09.12.14 70.2 69.2
DEC.2014 17.12.14 69.2 70.4
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
OCT.2014 13.10.14 43.9 42.1
OCT.2014 30.10.14 41.4 41.2
NOV.2014 13.11.14 43.2 42.1
NOV.2014 25.11.14 44.5 43.2
DEC.2014 09.12.14 43.7 42.4
DEC.2014 17.12.14 44.6 43.7
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 55 45
71
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2014
NAME OF THE AREA : PENCH Q.E. :SEP
NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
JULY.2014 10.07.14 66.4 70.0
JULY.2014 24.07.14 69.2 70.3
AUG.2014 11.08.14 67.3 70.0
AUG.2014 26.08.14 70.4 69.2
SEP.2014 10.09.14 70.4 66.5
SEP.2014 25.09.14 68.7 68.5
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
JULY.2014 10.07.14 42.3 43.0
JULY.2014 24.07.14 41.3 40.4
AUG.2014 11.08.14 41.2 42.5
AUG.2014 26.08.14 43.3 42.3
SEP.2014 10.09.14 50.2 40.7
SEP.2014 25.09.14 43.3 43.0
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 55 45
72
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2014
NAME OF THE AREA : PENCH Q.E. : JUNE.
NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
APRIL.2014 05.04.14 67.5 67.2
APRIL.2014 25.04.14 68.6 64.1
MAY.2014 11.05.14 70.2 67.4
MAY.2014 30.05.14 71.2 69.3
JUNE.2014 13.06.14 69.2 66.4
JUNE.2014 27.06.14 68.7 68.3
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A) collection Day Time Night Time
APRIL.2014 05.04.14 43.7 43.3 APRIL.2014 25.04.14 38.6 35.8 MAY.2014 11.05.14 39.7 36.7 MAY.2014 30.05.14 42.4 42.2 JUNE.2014 13.06.14 42.1 41.1 JUNE.2014 27.06.14 42.8 42.6
Permissible Limit 55 45
73
NOISE LEVEL DATA
NAME OF THE COMPANY : WCL YEAR : 2014
NAME OF THE AREA : PENCH Q.E. : MAR.
NAME OF THE PROJECT : NEHARIYA UG
Name of the Location : Fan house - PNUN-1
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
JAN. 2014 09.01.14 69.9 70.7
JAN. 2014 23.01.14 69.5 70.4
FEB. 2014 13.02.14 69.6 70.4
FEB. 2014 26.02.14 69.4 69.9
MAR.2014 12.03.14 68.2 68.0
MAR.2014 26.03.14 69.9 68.9
Noise Level Standard as per Env.
(Protection) Amendment rule 2000 75 70
Name of the Location : Colony - PNUN-2
Month Date of Data Noise Level in dB(A)
collection Day Time Night Time
JAN. 2014 09.01.14 43.5 41.0
JAN. 2014 23.01.14 43.7 44.5
FEB. 2014 13.02.14 42.6 41.7
FEB. 2014 26.02.14 42.2 41.1
MAR.2014 12.03.14 42.9 42.2
MAR.2014 26.03.14 42.5 41.7
Permissible Limit 55 45
The noise levels encountered during routine monitoring at mine have been shown in
above paragraphs which indicate that noise levels are well within the permissible limits.
Hence, it can be predicted that the values will remain within the permissible limits for the
proposed Naheriya UG Expansion mine (Enhancement from 0.36MTPA to 0.54 MTPA) with
the control measures in place.
1.10.1 NOISE POLLUTION CONTROL MEASURES
Monitoring of the noise control will be carried out on regular basis as per the Env
(Protection) Amendment Rule 2000. While planning for an effective noise attenuation
measures, the concept of source, path and receiver has been considered.
74
(A) Noise Control at Source
There are two areas where the noise generation can be checked at source.
(i) Proper Design
Since the generation of noise can be reduced by reducing the vibration amplitude,
the area of vibrating part and frequency of vibration will be taken care that all loose contact
between metal parts avoided.
Shock absorbing pads will be fixed in the foundation of vibrating equipment /
machines. In case of aerodynamic noise producing sources, mufflers will be provided with
the machines.
(ii) Proper Maintenance
All machines and equipment will be properly maintained. Sound muffler system and
bearing lubricating system etc. of equipment will be kept in proper condition.
Noise control in Transmission Path
The measures are to be taken for controls of noise along the transmission path have
been put in following two categories:
(i) Air borne path
(ii) Ground borne path
(i) Air Borne Path
The control in air – borne path has been planned in a number of ways as:
(a) The Fan house, screen house etc., which are source of high level noise generation
are to be enclosed.
(b) Planting of furrows of trees along the thick foliage around the compound and wall of
workshop and other industrial buildings. This will reduce the spread of noise. It can
be also used as an acoustic enclosure to reduce ambient noise.
(ii) Ground Borne Path
It has been proposed to provide vibration isolators in the form of vibration absorbing pads
placed at the base of vibrating equipment.
(C) Noise Control at Receiver End
Even after adopting above measures, if desired noise level is not achieved at receiver
end, in that case, following measures are suggested:
(a) The workers exposed to high noise level are provided with earplugs.
(b) Provision of enclosed booths at the worksite to protect worker from noisy
environment.
(c) Exposure control – This consists of rotation of working personnel so that the work
assignment in the intense noise area is for a limited period of time.
(d) Periodical medical examination of all workmen once in five years.
(e) Training and retraining of all workmen as per statute.
75
Control Of Ground Vibration
In the proposed Naheriya UG Expansion, blasting will be carried out in UG workings as per
the provisions of Coal Mines Regulation, 1957. Steps will be taken to ensure that the effect
of ground vibration due to drilling & blasting is negligible.
1.11 Land Reclamation measures
The earth’s crust is subject to two main natural forces – vertical and lateral
compression. In most natural conditions, these forces may be considered to be in
equilibrium unless disturbed by natural phenomena or man-induced disturbance of strata
equilibrium.
Underground mining being a man-induced disturbance, creates a void which may cause the
overlying overburden to subside or to move vertically and laterally into excavated space.
Thus, the subsidence may be defined as the lowering of strata including surface due to
underground excavations. These movements of overlying strata will continue until the
bulking of the rock material has closed the space or the compressive forces have been
placed again into a state of equilibrium.
Factors affecting Subsidence:
When the underground coal mining is employed, the stresses in the overburden
strata above and on the floor strata below the opening will re-adjust and be subject to
strata movement and deformation. Generally, within a certain limit above the excavated
opening the strata breaks, this is called caving zone. Above the caving zone and within a
certain height, there are numerous fractures parallel or perpendicular to the bedding plane,
which is the fractured zone. The strata between the fractured zone and the surface deform
continuously and are called the continuously deformed zone. Every point on the surface
moves towards center of the excavated opening and forms a surface subsidence basin. This
process is called strata movement. If this process refers to the surface, then it is called
surface movement. The characteristics and severity of the strata and surface movements
are mainly dependent on the following factors:
i) Thickness of the seams.
ii) Percentage of extraction.
i) Depth of panel.
ii) Width of panel.
iii) Dip of the seam.
iv) Method of working.
v) Nature of Goaf Support, caving or stowing.
vi) Nature of Overlying Strata.
vii) Geological disturbances.
viii) Surface topography, etc.
76
Within the movement basin, the displacement that causes lengthening in horizontal
strain (tensile strain) can be managed by controlling some of the above factors, viz.
Percentage of extraction, width of panel, method of working, nature of goaf support.
Moreover, the interval between extraction of two seams play an important role in multi-
seam working, the overlying strata will tend to consolidate with rains and become stable for
lower seam workings (in case the extraction of panels in lower seam is delayed by 1 – 3
years with respect to extraction in upper seam). In order to assess the quantum of
subsidence, different formulae are in prevalence for different areas of coalfields, specific on
consideration of above factors. However, the most relevant data will be information about
subsidence behavior from adjacent mines; if anywhere the composition of super –
incumbent strata and other parameters of coal seams are identical.
Land
In Naheriya UG Expn. Project, 300.0 Ha of land is envisaged for mine working (area
below which underground mining is being carried out).
The total requirement for land for inclines, mine infrastructure, surface buildings, roads and
colony has been assessed to be 30 ha.
Land under All Rights (as per PR) :
S.No Particulars Area (ha)
1. Land for mine entries and other infrastructure 5.00
2. Land for approach road to mine and colony 10.00
3. Land for township 15.00
Total 30.00
Entire land is tenancy land and is outside the mine lease area.
Land under Mining Rights :
1. Govt. Forest 196.63
2. Big Trees Forest 8.32
3. Grass Land 5.84
4. Govt. Land under Water 0.67
5. Other Govt. Land 2.90
6. Tenancy Land and Abadi, etc 85.64
Total 300.00
Below this 300 ha of land, underground mining is being carried out.
In the approved EIA/EMP, Physico-chemical properties of three soil samples were
collected in agricultural and barren land of the nearby areas were found to be clay in nature
and suitable for vegetative growth with suitable amendments.
SUBSIDENCE PREDICTION
As study has been carried out to predict the amount of subsidence and its impact on
surface topography at Naheriya UG mine.
77
The detailed report on subsidence prediction has been enclosed as Annexure- VII
The summary of subsidence prediction report prepared for Naheriya UG during March 1997
is placed below :
The surface over the proposed mining area comprises of 2.37 sq.km. of forest land
and 0.63 sq.km agriculture land. The general elevation of the surface ranges from 700 m to
782 m, i.e difference of elevation is 82 m. For such elevation, the maximum predicted
subsidence of 4.345 m will not extensively affect the drainage pattern in the area. However,
drainage will be affected at several places due to formation of pools and cracks which need
to be filled up to achieve original drainage pattern.
Even after leaving 60 m barrier from panel to Gunor river and Dhankasa nullah , it is
found that extent of subsidence influence is reaching inside the river at some place and
therefore, extraction in some of the panels has been suggested to be limited so that
subsidence does not affect the river.
Presently, HFL as flowing 720 m surface contour which does not affect the villages,
but after subsidence surrounding of Naheriya Dhana village get lowered than 720 m and
making it island. Therefore, to maintain this village link form surface, the extraction in panel
- 3 towards village has been suggested to be restricted.
Further to the above, as per the recent stipulation of MoEF on workinf of
underground mines below forest cover with caving, a study has also been carried to assess
the likely strain values and resultant crack width which are given a below:
Latest Stipulations
Recently, the MoEF & CC vide its letter dated 27.03.2000 has issued the guidelines
stipulating thath the maximum tensile strain of 20 mm/m and thereby the surface cracks of
width of about 200 - 300 mm is to be permitted in forest areas. This is based onthe
assumption that the negligible damage is caused to the standing trees if the tensile strain is
limited to 20 mm/m. In actual practice, trees have been found to be safe even at higher
tensile strain. Till sufficient data is generated the above guidelines have been considered in
the planning of Naheriya UG Project.
Subsidence Prediction at Naheriya UG (Below Forest)
In the Naheriya UG Project, about 70 % of the surface land ( i.e. 204.95 Ha out of 300
Ha ) is covered under forest. The coal extraction is being carried out by caving.
The likely maximum subsidence and strain prediction for Naheriya UG Mine ( below
forest area ) after extraction of Seam - II & III ( contiguous seam ) are as given below :
TABLE-1
78
All the strain values are within the stipulated limit.
The extraction in Panel - 4, 6 and 8 in lower seams i.e. IV & V shall be delayed by 3
years after extraction in upper seams i.e. II & III so that the extraction in the above panels in
lower seam starts below the stable / stablilized goaf.
Maximum subsidence, slop and tensile strain after extraction of II, III, IV & V ( IV & V
are contiguous) are as given below:
TABLE-2
All the strain values are within the stipulated limit.
Panel Likely Max.
Subsidence
(mm)
Likely Slope G
(mm /m)
Likely Max.
Tensile Strain
(+) E (mm /m)
IA 832 11.83 5.88
IB 831 21.68 10.70
1 1106 40.26 19.79
2 1450 39.45 19.45
3 710 17.16 6.49
5 640 13.58 6.74
5A 750 15.92 7.90
7 850 18.89 9.44
9 980 17.09 8.46
4 1160 17.85 8.92
6 1656 38.72 19.17
8 1797 39.86 19.76
Panel Likely Max.
Subsidence
(mm)
Likely Slope G
(mm /m)
Likely Max.
Tensile Strain
(+) E (mm /m)
IA 2292 28.65 13.33
IB 3023 35.99 17.99
1 3070 37.21 18.81
2 3298 39.98 19.99
3 1742 24.54 12.27
5 2189 35.31 17.65
5A 2160 37.89 18.95
7 1995 39.90 19.95
9 1795 20.51 10.26
4 3809 35.39 17.70
6 3444 33.67 16.83
8 3544 27.89 13.94
8A 1160 18.86 9.43
79
With this amount of subsidence and strain, the width of surface cracks likely to occur
in the forest area will be about 200-300mm.
As such, it may be concluded that the strain values and crack width over the forest
area are within the stipulated limit. As such, anticipated damage to the forest due to
underground mining with caving at Naheriya UG will be almost negligible.
1.12 During Mining Land Use Pattern:-
In the proposed Naheriya UG Expansion there is enhancement in the production and
no change in the land area. Land area is 300 ha (MLA) as per approved EC. land use pattern
during expansion of mining operation is as follows:-
S.No Particulars Area (ha)
AREA FOR UNDERGROUND MINING
A LEASEHOLD AREA 300.0
1. Govt. Forest 196.63
2. Big Trees Forest 8.32
3. Grass Land 5.84
4. Govt. Land under Water 0.67
5. Other Govt. Land 2.90
6. Tenancy Land and Abadi, etc 85.64
B AREA UNDER “ALL RIGHTS” 30.00
1. Non-Forest Land 30.0
Grand Total 330.00
Area under “ALL RIGHTS”
S.No Particulars Area (ha)
1. Land for mine entries and other infrastructure 5.00
2. Land for approach road to mine and colony 10.00
3. Land for township 15.00
Grand Total 30.00
80
1.13 Occupational Health Issues
WCL has full-fledged medical set up in all areas to check up and monitor all the
Occupational diseases endangering the health of its precious workforce. The periodical
medical Examination for all workmen is compulsory as per Statute. It is carried out once in
every five years for each and every worker and proper records are maintained and
submitted to Directorate General of Mines Safety as it is a statutory requirement.
In case of workers, above 50 years of age and employed in underground mine, this periodical
medical examination is carried out every two and half yearly interval. In Pench Area, under
whose administrative control, the mine under consideration is being worked is no exception. All
the statutory obligations under the Occupational health are strictly followed.
Present set up of Occupational Health Services At WCL:
WCL is having Occupational health committee at the corporate (HQ) level as well as at the
unit (Area /Project level).
At corporate level, the committee consists of the following: -
• Chief General Manager (Safety)
• Chief of Medical Services
• Periodical Medical Examination (PME) Incharge of HQ.
The committee scrutinizes the report of the area every quarter.
At Unit level, the committee consists of the following: -
• General Manager (Operations)
• Area Medical Officer
• Area Safety Officer
• Periodical Medical Examination (PME) Incharge of Area.
The above committee takes the review at area level every month.
In suitable cases, as per the recommendation of the Apex Medical Board, the change of job
is also suggested and implemented accordingly.
In addition, the Welfare Board of WCL time to time makes visits to different area hospitals &
PME Centres so as take stock of the ground realities.
81
CHAPTER- II
ENVIRONMENTAL MONITORING PROGRAMME
2.0 ENVIRONMENTAL MONITORING –
The environmental monitoring programme is already being carried out at four stations
and will be continued as per details given below: -
S
N
Items Parameters Frequency No. of Stations
1 Ambient Air
Quality
Monitoring
PM10, PM2.5, SO2,
Nox, CO & Fugitive
dust
Every Fortnight as per
EPA, Rule 2000
4
2 Water
Quality
Monitoring
1) 4 Parameters viz. p
H, Total Suspended
Solids (TSS), Chemical
Oxygen Demand
(COD) & Oil and
Grease.
2) 35 Parameters
Every Fortnight
Once in a Year
3
3 Noise
Quality
Monitoring
Noise Levels Every Fortnight 3
4 Environment
al Statement
Annual
5 Ground
Water Level
Monitoring
& Quality
Water Level & Quality
Parameters.
Water Level – Quarterly.
Water Quality – Yearly.
In Buffer
Zone
Villages.
6 Compliance
Report of EC
Conditions
All conditions both
Specific & General
30th
September &
31st
March
Not
Applicable
82
2.1 MONITORING ORGANISATION
To have a close watch on the environmental condition and implementation of the various
measures suggested, a multi-disciplinary approach is essential for formation of Environment
Management Cell / Department.
WCL, has an Environment Deptt. headed by General Manager (Env.) at its HQs. The
department provides necessary support which is required for environmental management
of various mining projects under the jurisdiction of the company.
(a) At area level, Chief General Manager of the area co- ordinates the activities of
various disciplines in the area to render all necessary assistance at the
implementing level i.e. the Project level.
(b) Nodal Officer (Environment) of the area monitors all aspects of environment on
behalf of the Chief General Manager. He will also take suitable steps for
generation of environmental data along with CMPDI team for its analysis and
interpretations.
The work of plantation will be implemented through State Forest Deptt..
(c) At project level, Project Officer shall primarily be responsible for land resource
management. He shall also be responsible for biological reclamation as per
directives of GM (Env.), WCL ( Hqr).
2.2 FUNCTIONS OF THE ENVIRONMENT MANAGEMENT CELL / DEPARTMENT
� To integrate environmental factors into business decisions.
� To prepare time bound action plan for implementation of various provisions of
Environment Management Plan, maintain a record of it and submit six monthly
report to GM (Env.).
� To monitor in compliance with environmental regulations.
� Continual improvement in environmental performance.
� To follow proper documentation and monitoring procedures, for developing
better environmental management systems at the mine.
� To ensure systematic and routine housekeeping to reduce generation of
pollution inside the mine.
� To develop and maintain green belt in and around the mine.
83
� To keep up with regulatory requirements and arrange for the necessary
certificates or consents viz. air and water.
� To submit environmental statement to SPCB within stipulated time.
ORGANISATION CHART
Sl.
No.
Measures/Actions Agency
1. Environment Pollution 1 Chief General Manager, Pench Area 2 Area Nodal Officer, (Environment), Pench Area
3 Project Officer Naheriya UG Mine
4 Staff Officer(Civil), Pench Area
5 Environmental Cell (WCL H.Q.)
2. Environment Monitoring 1 Chief General Manager, Pench Area
2 Staff Officer (Civil) , Pench Area
3 Area Nodal Officer (Environment), Pench Area.
4 Project Officer, Naheriya UG Mine
5 Environment Cell of WCL Headquarters
6 Environment Deptt. of CMPDI, RI-IV
3. Land Reclamation 1 Project Officer, Naheriya UG Mine
2 Area Nodal Officer (Environment), Pench Area
3 Environmental Supervisor
84
CHAPTER- III
ADDITIONAL STUDIES
3.0 INTRODUCTION:
Mining is a hazardous industry. There is risk to life and property associated with various
mining and allied activities of the project. As such a detailed study has been carried out
covering identification and assessment of risk, and recommendation of measures to prevent
damage to life and property against such risks. They are discussed below & this is an
application under section 7(ii) vide MOEF O.M dated 19.12.2012 & 07.01.2014
3.1 PUBLIC CONSULTATION
As discussed earlier, in this proposal, it is submitted that the project is envisaged for
enhancement in capacity only from 0.36 MTPA to 0.54 MTPA (with existing EC ML area of
300.0 ha) as per O.M dated 07.01.2014.
Public Hearing had been completed on 11.09.2001 before obtaining the existing EC dated
15.11.2002 for 0.36 MTPA. Now this expansion proposal is submitted fulfilling the
requirement of O.M. dated 19.12.2012 & 07.01.2014. The minutes of the above Public
Hearing for the proposed Naheriya UG Expansion project is attached as annexure - IV
3.2 DISASTER MANAGEMENT PLAN
The project report has been drawn in confirmity with the prevailing statutory provisions as
per Mines Act 1952 CMR 1957 applicable for safety in UG Mines. However, all statutory
rules, regulations, applicable laws etc. and statutory requirement related to Govt. licences,
workers compensation, Insurance, etc. including minimum wage act for workers employed
will be adhered to. All the regulations & schedules of coal mines Regulations 1957 relating
to UG mining have to be adhered to and implemented in order to maintain day to day safety
precautions as per statute.
GENERAL:
The disaster management plan is essential to guard against and mitigate the consequences
of major accidents. The term " major accident " means an unexpected and sudden
occurrence of event from abnormal developments in course of one's industrial activity
leading to a serious danger, public or environment, whether immediate or delayed, inside or
outside the installation involving one or more hazardous substance.
Keeping in view the three basic principles i.e. prevention, preparedness (both pro-active and
reactive) and mitigation of effect through rescue, recovery, relief and rehabilitation; a
comprehensive blue print of disaster management plan (DMP) has been made for Naheriya
UG incorporating the following.
Identification and assessment of risks
Recommendation of measures to prevent damage to life and property against such risks.
85
As such, a detailed study has been carried out covering identification and assessment of risk
so as to suggest measures to be taken to prevent unfortunate damage to the life and
property against such expected risks. They are as follows.
Spontaneous heating/Underground mine fire
Explosion
Inundation
Subsidence
3.2.3 SPONTANEOUS HEATING OF COAL
Spontaneous combustion of coal or other carbonaceous matter may be defined as the
process of self-heating of coal resulting eventually in its combustion without the application
of external heat. Various factors govern the spontaneous heating of coal viz. Chemical
Composition of coal, friability, presence of iron pyrites, depth of the seam, thickness of the
seam, geological disturbances, presence of bands etc.
To detect fire at an early stage regular monitoring of any sign of fire is being carried out
regularly as per statute.
3.2.4 ROOF CONTROL
For efficient roof control, as far as possible steel supports in the form of steel props,
bars, roof bolts etc., have been proposed. In order to determine the support requirement
vis -a-vis the strata condition, rock masss rating of the roof strata must be determined for all
the seams. The mine management shall prepare systematic support rules on the basis of
findings of rock mass rating and get the same approved by DGMS before adopting the same
for implementation in the mine. The S.S.R for depillaring should be framed on the basis of
RMR and as per the experience of mines where depillaring by LDHs is in practice.
In contiguous seams, the panel barries should be maintained in vertical coincidience.
Since the parting between Seams - II & III is less than 9 m, it will entail columnization
of coal pillars. Therefore, it is necessary to develop Seams - II & III by superimposing the
galleries as well as pillars. This will hold good for Seams - IV & V also. Wherever parting
between them in 3 m or more, both the seams will be worked as contiguous sections. While
depillaring, precautions have to be taken to maintain the depillaring operation in "Upper
seam" in vertical coincidence of " Lower seam". Regular test holes are to be drilled to
confirm the parting between "Upper" and "Lower" Sections i.e. between Seams - II & III and
Seams - IV & V respectively. Since main trunk roads have been planned in Seam-II & IV,
where the parting between these two seams varies from 9m to 14 m. Though the parting
between them is more than 9 m, it may be necessary to develop Seams - II & IV by
superimposing the galleries as well as pillars.This will facilitate the transportation of coal
form upper seams to lower seams by dropping through staple pit. Superimposition will also
help better strata control in the main trunk roads of Seams - II & IV. All the precautions that
have been laid in Coal Mines Regulations, 1957 under the Mines Act, 1952 have to be
followed during simultaneous extraction of both the sections.
86
3.2.5 EXPLOSION
An explosion is a sudden combustion process of great intensity accompanied by
release of large quantities of heat energy and in which the original gas or solid substance
like coal dust is converted instantaneously into gaseous products. Explosion in Coal mines
are of (a) Fire damp (Methane), (b) Coal dust, or combination of both.
Explosion due to firedamp – Firedamp has been the cause of most of the explosions
in coalmines and in every mine steps are taken to prevent a fire damp explosion. Presence
of firedamp in air between 5.4% and 14.8% forms an explosive mixture. If a suitable source
of ignition is available the mixture results in an explosion.
Precautions taken against fire, heating (as pear CMR) also helps in preventing the
explosion.
Proper ventilation of the mine is the correct method to prevent dangerous built-up
of firedamp. Regular inspection of places where fire damp may accumulate is essential in
addition to proper ventilation.
Adequate provision for self-rescuers has been made in this project to enable
everybody to carry it underground. Stone dust barriers/water through barriers have been
provided as per statute.
Explosion due to coal dust – It has been established that coal dust when suspended
in the air as cloud, is capable of bursting into an explosion and propagate it, even in the
absence of firedamp.
A coal dust explosion can be prevented by:
(i) Reducing the formation of coal dust at the working places and suppressing the same by
water infusion, water spraying and by proper control of shot firing.
(ii) Preventing its spread during transport of coal.
(iii) Rendering coal dust harmless by wetting it with water or mixing with inert stone dust.
(iv) Provision of stone dust barriers or water barriers.
For monitoring the level of dustiness and quality of dust, regular sampling and analysis of
mine dust is being done and precautions are being taken as per statute.
(v) Avoiding accumulation of the methane in underground by proper ventilation and strict
adherence to DGMS guidelines/ Statues.
87
3.2.6 INNUNDATION:
Precautionary Measures: -
Any place in a seam approaching a fault passing through the seam, which may contain
accumulation of water, adequate precautions should be taken against such eruption of
water.
i) All boreholes drilled from the surface should be correlated & plotted on the workings &
other plans accurately & boreholes should plugged with cement to prevent inflow of
water through such boreholes.
ii) A careful assessment of the danger of inundation from surface should be made before
the onset of every rainy season & adequate precautions against such dangers should be
clearly laid down & implemented.
iii) During rainy season, blockage of river, jore, nallah or stream may occasionally occur in
the up-stream. It is, therefore, necessary to keep a constant watch on the upstream of
river or nallah & take suitable precautions.
3.2.7 SUBSIDENCE
Land degradation due to cracks developed after subsidence, can lead to (i) increased
percolation of water from surface to underground in certain cases; (ii) passage of air
through open cracks which may lead to spontaneous heating or fire underground; (iii)
damage of vegetative growth on surface.
In order to prevent accidents due to above mentioned causes, the following
measures are suggested:
Around depillaring area, co-related on surface protective bunds and garland drains
should be laid so that the minimum water from surface enters through subsided area to the
underground workings. Sufficient pumping arrangement will be made to deal with any
eventuality. Since sufficient coal barrier will be left taking into consideration the extent of
subsidence likely to occur, there is no chance of inundation.
The surface cracks should be filled up by using concrete shale, clay or such other
suitable material depending on the nature of cracks.
Depressed portions should be levelled up using clay or other suitable material.
Proper support of galleries and junctions is very essential in the proposed mine, not
only for safety of the workman but also for safety of the surface features and the mine
itself. Any pot holing in the area lying below HFL of the river can lead to inundation of the
mine. It is because of these reasons that regular support system in the form of roof
bolting/roof stitching has been suggested. Sufficient numbers of roof bolting machines have
been provided for this purpose.
88
Before starting depillaring operations, a systematic support rule is framed on the
basis of experience of depillaring by SDLs. This SSR is then introduced after taking approval
of DGMS.
3.2.8 TRAINING
The personnel directly responsible for handling emergencies are given training for
making them better equipped for discharging their responsibilities. Coal Industry has set up
a number of training institutes for imparting training to its employees. The training
improves safety awareness among the workers and trains them to carry out their
assignments safely.
3.2.9 MEDICAL AID
In Pench Area a fully equipped hospital with qualified medical practitioners & other
equipments etc. is running very efficiently. Therefore, any medical emergencies can be
attended without any problem.
3.2.10 COMMUNICATION SYSTEM
Efficient communication system based on VHF system has been provided for the
project. This allows proper communication link between various work centers and helps in
preventing accidents as well in taking early action.
3.2.11 SAFETY AWARENESS
To create safety awareness and impart education on safe practices, the following
steps are being taken:
Holding annual safety weeks.
Imparting basic and refresher training to new and old employees respectively.
PREVENTIVE MEASURES:
i) Adequate ventilation to dilute any possible emission of fire damps is of paramount
importance, for this purpose suitable high capacity fans have been provided.
ii) Suppression of dust at the source by water spraying at different places in Underground.
iii) Proper statutory precautions are taken in the use of the explosives.
iv) Use of fire resisting materials, and flameproof equipment for ventilation of mine
workings.
v) No combustion materials are being used in the construction of, or in connection with, any
shaft lining, or any room housing any machinery/apparatus below ground.
89
vi) In case of every fan (other than an auxiliary fan), installed below ground, the coal or
other carbonaceous materials exposed in the sides, roof and floor, shall be covered with
masonry or other adequate protection against fire, for a distance of not less than 5 m in
every direction from the face.
vii) No coal, shale or other carbonaceous material would be left / slacked below ground.
Where removal of fallen coal out of the mine is not practicable, the area would be
effectively sealed off.
3.2.12 CONCLUSIONS:
Following conclusions may be drawn from the above discussion:
(a) Coal mining is associated with a number of hazards.
(b) These hazards can be identified and assessed, which has been done for this project.
(c) Preventive measures against identified risks have been provided in this report
(d) With adoption of such protective measures, the operation of the mine would be safe.
90
CHAPTER – IV
PROJECT BENEFITS
4.0 PROJECT BENEFITS
The benefits of the project can be summarized as below:-
- The physical infrastructure in the area has already been improved substantially by
following ways:-
Development of road thereby improving the communication.
Improvement in Power, Telephone (including Mobile) facility.
Improvement in Health Care facility & Educational facility.
Improvement in Market / Trade & Business.
- The social infrastructure by way of cultural mixing of people of other states with local
community glorifying “UNITY IN DIVERSITY”.
- Substantial employment in the project & indirect employment for business & trading,
contractor, transportation, vehicle contractor, nursery development.
WCL as a responsible corporate organization in Central India is playing a significant role in
developing the region around its mines in the States of Madhya Pradesh & Maharashtra.
WCL takes up various infrastructural development works in the surrounding area covering
the felt needs of the local community and the various works undertaken under CSR
activities.
In addition to the details detailed out earlier, various other works done by WCL is also given
in earlier chapter Different CSR work taken up by the area during 2010 to 2014 is given is
given in Annexure V.
91
CHAPTER - V
ENVIRONMENT MANAGEMENT PLAN
5.0 GENERAL
Monitoring of the environment and implementation of various protective measures
discussed in the report forms an important part of EMP. In the earlier chapters the causes
of various pollutions along with the preventive and mitigating measures have been
discussed. In this chapter description of the administrative aspects of ensuring that
mitigative measures are implemented and their effectiveness monitored, after approval of
the EIA is being discussed.
5.1 MONITORING ORGANISATION
To have a close watch on the environmental condition and implementation of the various
measures suggested, a multi-disciplinary approach is essential.
(a) WCL headquarters acts as an apex body which supervises the activities relating to
environment at project level through the General Manager.
(b) Area General Manager of the area coordinates the activities of various disciplines in the
area to render all necessary assistance at the implementing level i.e. the Project. Area Nodal
Officer (Environment) monitors all aspects of environment on behalf of the General
Manager. He also takes suitable steps for generation of environment data along with its
analysis and interpretations.
As far as plantation is concerned, it is being got done through State Forest Development
Corporation, who are expert for such works.
(c) Sub Area Manager is responsible for mechanical reclamation of the area. He is also
responsible for biological reclamation with the assistance of AGM's office.
ORGANISATION FOR ENVIRONMENT MANAGEMENT
SN Measures/Actions Agency
1. Environmental Control 1 Area General Manager, Pench Area
2 Nodal Officer, (Environment), Pench Area
3 Sub Area Manager, Naheriya UG.
4 Staff Officer (Civil), Pench Area
5 Environmental Cell (WCL H.Q.)
2. Environmental
Monitoring
1 Area General Manager, Pench Area
2 Staff Officer (Civil), Pench Area
3 Nodal Officer (Environment), Pench Area
4 Sub Area Manager, Naheriya UG
92
5 Environment Cell of WCL Headquarters
6 Environmental Laboratory of CMPDI, RI-IV
3. Reclamation 1 Sub Area Manager Naheriya UG
2 Nodal Officer (Environment), Pench Area
3 Environmental Supervisor
4 Horticulturist
5.2 ENVIRONMENTAL COST PROJECTION
The expenditure incurred on environmental protection measures including afforestation has
been detailed out as below ;-
(in Rs. Lakh)
S.No Capital Cost Annual recurring cost
Existing Proposed Existing Proposed
1. Pollution Control
( Sedimentation Pond, ETP,
Fixed type sprinklers, Mobile
water sprinkler, etc)
8.00 10.00
3.00
2. Pollution Monitoring ----
----
8.00 Will be carried
out from Revenue
head
3. Installation of fixed type
sprinklers / rain guns etc. for
dust control (including water
reservoir, pump, pipeline
etc.)
5.0 ---- 1.0
4. Occupational Health ---- ---- ---- In-built in the project
5. Plantation
3.00
Will be carried
out from Revenue
head
6. Digital Mapping for land use/
Vegetation cover map ---
8.00*
Total 13.0 10.0 23.00
* once in three years
Revenue cost of Rs. 6/t of coal production has been provisioned for Environmental activities.
93
CHAPTER-VI
DISCLOSURE OF CONSULTANTS ENGAGED
6.1 Name of Consultant
Central Mine Planning & Design Institute Limited. Briefly, it is called as ‘CMPDI’. It is an ISO
9001 Company.
Its registered corporate office is situated at Gondwana Place, Kanke Road, Ranchi – 834008,
a capital city of Jharkhand State. It operates through seven strategically located Regional
Institutes over six states territories of India. Details of all seven Institutes including its
corporate office are given as in Table-6.1.
Table-6.1
S
N
Offices Addresses Tel/Fax
Postal E-Mail Website
1 Corporate Gondwana
Place, Kanke
Road,
Ranchi-
834008,
Jharkhand
,
o.in
http://www.
cmpdi.co.in
+916512230483,22
30116
/+916512231447,
2232249
2 Regional
Institute-I
West End, GT
Road,
asansole –
713301,
West Bengal
- - +913412253504/
+913412250935
3 Regional
Institute-II
Koyla
Bhawan,
Koyla Nagar,
Dhanbad-
826005,
Jharkhand
+913262230850,22
30789/
+913262265575
4 Regional
Institute-
III
Gondwana
Place, Kanke
Road,
Ranchi-
834008,
Jharkhand
+916512231506/
+916512231501
5 Regional
Institute-
IV
Kasturba
Nagar,
Jaripatka-
440014
http://www.
cmpdi.co.in
+917122642134/
+917122643231
94
6 Regional
Institute-
V
SECL
Complex,
Seepat Road,
Bilaspur,
Chhatisgarh.
+917752246482/
+917752246481
7 Regional
Institute-
VI
CWS Colony,
P.O. Jayant
Colliery,
Sidhi-
486890, M.P.
+917805222329,
222172/
+917805222330
8 Regional
Institute-
VII
Griha Nirman
Bhawan,
Sachiwalaya
Marg, Unit 3,
Bhubaneshw
ar-751001,
Orissa
+916742394357,
2394760/
+916742395128
All the above Regional Institutes are dedicated to render services to seven subsidiaries of
the CIL AS follows:
Table-6.2
Sl. No. Institutes Dedicated to
1 Regional Institute-I Eastern Coalfields Ltd. (ECL)
2 Regional Institute-II Bharat Coking Coal Ltd. (BCCL)
3 Regional Institute-III Central Coalfields Ltd. (CCL)
4 Regional Institute-IV Western Coalfields Ltd. (WCL)
5 Regional Institute-V South Eastern Coalfields Ltd. (SECL)
6 Regional Institute-VI Northern Coalfields Ltd. (NCL)
7 Regional Institute-VII Mahanadi Coalfields Ltd. (MCL)
Hqrs. Ranchi is committed to render services to NEC & Non-CIL clients and specialized
assignments for both CIL & Non-CIL clients.
6.2 Brief Resume of the Consultants:
6.2.1 Establishment Background:
The company was formerly known as Coal Mines Authority Limited. And, the Central Mine
Planning & Design Institute Limited (herein after called as CMPDI) is a planning & design
division of Coal India Limited (herein after called as CIL) as per Memorandum of Association
of the company. The CIL is a holding company since November 01, 1975, and the CMPDIL is
one of its subsidiaries since then. It is under Ministry of Coal, Government of India.
95
6.2.2 Strength & Resources
a) Manpower:
CMPDI has more than 800 multidisciplinary technical executive professionals who combine
innovation and initiative to deliver faster and effective solutions in planning,
implementation and management of projects.
b) Resources:
CMPDI is equipped with modern laboratory facilities for undertaking various analytical
works to supplement its services. It has well equipped network of six environmental
laboratories located in various coalfields to regularly monitor air, water and noise
parameters. The central unit at Ranchi is accredited with Central Pollution Board, New Delhi.
Besides its own strength, CMPDI has access to the vast resources with its principal, CIL,
India’s largest coal producer and a Maharatna Company.
6.2.3 Recognition:
CMPDI is recognized as preferred consultant by India and overseas clients, United Nation
agencies and international financial institutions and the company is registered with
• World Bank
• Asian Development Bank
• African Development Bank
• United Nations Development Programme
6.2.4 Main Functional Area:
The main functional area of the CMPDI is to provide adequate and up-to-date planning,
design and technological supports to the CIL and its coal producing subsidiaries to enable
them to produce the planned quantity of coal efficiently and economically with due
attention to safety, conservation, quality and environment. In addition to these, CMPDI also
provides necessary consultancy for clients outside the CIL in India and abroad. The Quality
Management System of CMPDI, Ranchi is certified under international standard – ISO-2000
by BVQI (UK). Services covered under are as follows:
• Consultancy in Mineral Exploration and Environmental Management.
• Planning & Design in Mining, Civil & Architectural Engineering, Coal Preparation &
Utilization, Electrical & Mechanical Engineering, Mining Electronics, Geomatics and
Mine Construction.
• Laboratory testing facilities for the above
• Technical & Management Training in Mineral & Mining Sector
6.3 Nature of consultancy rendered:
96
CMPDI has been offering services in the fields enumerated in Table – 6.3
Table – 6.3
Sl. No. Services Offered
1 Exploration & Resource Evaluation
2 Mine Planning & Design Services
3 Infrastructures Engineering
4 Environmental Services
5 Beneficiation Services
6 Management Services
7 Specialized Services
8 Laboratory Services
9 ITC in Mining
10 Research & Development
6.3.1 Exploration & Resource Evaluation:
New generation exploration technology coupled with skilled manpower has made CMPDI a
twenty first century leader in mineral exploration, deposit modeling, resource evaluation,
resource management, mining geology, hydro-geological & geophysical studies,
engineering, geological investigations etc. Services rendered under this head are described
in brief in Table- hereinafter.
Table-6.3.1
Sl.No. Sub-heads of
Services
Services Rendered in
1 Geological
Support for
mining
• Production support or mine development
drilling and prediction of faults and pinch / wash
outs.
• Delineation of roof / floor and dirt bands
2 Drilling • Coring-Diamond rotary drills up to a capacity of
1280 m depth
• Non-coring-Direct rotary and DTH drills for
geophysical logging, hydro-geological
investigations, dewatering, etc.
3 Deposit
modeling
Using geo-statistical and geological software packages
including MINEX and in-house developed
CEMPGEODOC and SASLINT software
4 Resource Deposits of coal, lignite, manganese, iron ore
97
Evaluation (magnetite and hematite), phosphorite, coal bed
methane etc.
5 Resource
Management
• Strategic planning for future exploration
depending upon market demand.
• Updating of reserve / resource of individual
blocks or coalfields.
6 Hydro-
geological
studies
• Systematic ground water investigations.
• Mining hydro-geological studies
7 Geo-
engineering
works
Determination of strength properties of rocks and coal
and RQD (Rock Quality Designation) to assess strength
characteristics of strata
8 Master
planning for
assessment of
resource
potential with
respect to
CBM, globally
an emerging
environment
friendly
alternate
energy source.
• Creation of data packages of potential CBM
blocks.
• Resource evaluation of CBM / CMM / AMM.
• Formulation of policy guidelines for harnessing
CBM resources.
• Implementation of CIL-ONGC Consortium’s
venture in developing CBM in coalfields.
To provide quality services, CMPDI is effectively utilizing technology like remote sensing,
combination drilling (coring and non-coring), multi-probe geophysical borehole logging,
seismic refraction survey etc.
CMPDI has already undertaken over 500 integrated exploration projects in varying
geological and terrain conditions.
6.3.2 Mine Planning & Design Services:
CMPDI is a premier consultant in open pit and underground mine planning & design in coal,
lignite and other minerals. It has prepared more than 950 mining project reports with
individual capacity up to 35 Million ton per annum. CMPDI uses advance software like
MINEX for resource modeling, mine planning and scheduling of open cast and underground
mine projects. It has helped its subsidiaries to achieve unprecedented growth from open
cast mines in their organizations. Its experience in mechanized underground mining
technology spans exploitation of coal seams from 1.00 m to 20 m thickness, at different
gradients from flat to 750, with soft to extremely hard coal, liable to spontaneous heating
and gassiness and under varying roof strata conditions. Services offered to are manifold and
are enumerated briefly in Table-6.3.2.
98
Table-6.3.2
Sl. No. Services Offered
1 Master planning of coalfield
2 Perspective planning
3 Conceptual engineering studies
4 Techno-economic feasibility studies
5 Detailed project reports
6 Detailed engineering with working drawings
7 Mine ventilation & transport planning
8 Operational planning
9 Mining plans for mining lease
10 Mine capacity assessment
11 Performance analysis of equipment
12 Prediction of surface subsidence through numerical modeling
software
13 Geophysical logging, Seismic survey, Resistivity Survey.
6.3.3 Infrastructure Engineering:
CMPDI provides engineering logistic or support services for development of infrastructure. It
has developed multi-disciplinary engineering skills for implementing projects of various
complexities. In particular, it has offered complete planning & design services for
architectural planning, civil, structural, electrical and mechanical engineering in various
projects. A few of them are enumerated in Table-6.3.3.
Table – 6.3.3
Sl. No. Services Offered
1 Planning of large capacity, high speed bulk material handling plants
2 Turnkey execution of coal handling plants
3 Planning of high voltage sub-stations
4 Planning of workshops of various types and capacities
5 Township planning including roads, water supply, water supply
system, drainage, Water / sewerage treatment plants and detailed
planning and design of all township infrastructure
6 Site selection of pit head thermal power plants based on remote
sensing data
7 Rail corridor alignment through remote sensing
8 Techno-economic feasibility study of captive power plants based on
pulverized coal and FBC technology
99
6.3.4 Environmental Services:
CMPDI holds a position of eminence in the field of environmental planning, impact
assessment, management and environmental engineering in coal and other sectors. It is the
nodal agency for co-ordination and monitoring of ongoing environmental up-gradation
schemes sanctioned by Ministry of Coal and Mines under the head “Environmental
Measures and Subsidence Control”. It undertakes technical scrutiny of new proposals, visits
to project sites and disbursement of funds to the implementing agencies.
A few of the new areas in which CMPDI has diversified are environmental and hydro-
geological studies for disposal of fly ash, development of air quality model, bio-treatment of
industrial effluents, carrying capacity base development planning, watershed modeling and
rain water harvesting. Services offered with respect to environmental quality monitoring,
engineering, management and planning are briefly given in Table-6.3.4.
100
Table-6.3.4
6.3.5 Beneficiation Services:
CMPDI specializes in planning, design and construction of new washeries and modification
of existing washeries for coal and mineral beneficiation. Services with respect to
beneficiation offered to are given in Table-6.3.5.
Sl. No. Sub-heads of Services Services rendered
1 Environmental Monitoring • Air quality
• Water quality
• Noise level
• Soil quality
• Micro-meteorological studies
• Stack monitoring
2 Environmental Engineering • Industrial/ Municipal effluent
treatment and recycling
plants
• Hazardous waste disposal site
engineering
• Municipal effluent disposal
site engineering
3 Natural resource management • Land use planning
• Rain water harvesting
• Watershed management
plans
4 Regional planning • Regional environment
management plans
• Regional environment status
plans
5 Environment assessment plans Environment assessment plans
6 Special studies • Review of existing mining and
environment policies,
legislations, standards and
mechanisms for monitoring
compliance, institutional
strengthening for regulatory
and counterpart institutions.
• Study of environmental
problems and action plan for
restoration of environmental
quality.
• Mine closure planning
101
Table-6.3.5
Sl. No. Services Offered to for
1 Planning of coal and mineral beneficiation plants
2 Preparation of feasibility / project reports including macro level
analysis, washability studies, environmental impact assessment and
techno-economic analysis.
3 Technical studies, performance evaluation and operation and
maintenance related consultancy for existing washeries.
6.3.6 Management Services:
Management services enumerated in Table-6.3.6 have been offered by CMPDI to different
organizations or bodies.
Table-6.3.6
Sl. No. Sub-heads of Services Services rendered for
1 Coal Investment
promotion Services
Assistance to Government of India in identification
and assessment of coal mining properties for
investments through private sector participation.
2 Quality Management
Services
Consultancy for implementation, certification and
maintenance of ISO 9001 Quality Management
System and its industry specific translations, ISO
14001 Environment Management System and
OHSAS 18001 Occupational Health and Safety
Assurance System.
3 Human Resource Services Creating knowledge and skill based workforce,
CMPDI through its Staff Training College (STC)
imparts training to its clients’ personnel. Under
UNDP, CMPDI has trained professionals from
Nigeria, Sultanate of Oman and North Korea.
Through its STC it has organized training
programmes under five major categories such as (i)
Technical, (ii) Managerial, (iii) Computer
application, (iv) Quality Skills, (v) Quality System,
etc. It has also organized and conducted off-
campus training programmes with respect to
Quality System at various subsidiaries of CIL.
CMPDI diversified into management system consultancy in 1998. While continuing to
provide consultancy for ISO 9000 Quality Management System (QMS) and ISO 14000
Environmental Management System (EMS), it made forays into consultancy for ISO 17025
(Testing and calibrating laboratories) under consultancy scope as:
• Creation of Management system
102
• Providing training support
• Implementation, certification and post certification support
6.3.7 Specialized Services:
With a view to catering to specific requirements of clients, CMPDI has been providing field
oriented specialized services to its clients. Descript services rendered under this category
have been remote sensing, terrestrial survey, blasting, ventilation design & gas assessment
in underground mines, energy audit and non-destructive testing. Main services rendered are
described in brief in Table-6.3.7.
Table-6.3.7
Sl. No. Sub-heads of Services Services rendered in
1 Geomatics Geomatic services in mining sector ranging from
topographical survey, baseline data generation
and monitoring of land use / land cover for
environmental management, water resource
survey and coal mine fire mapping. It has also
imparted expertise services in the field of remote
sensing applications, terrain mapping, co-relation
survey for underground mines, GPS / GIS survey,
cartography and digital image processing.
2 Blasting Carrying out controlled blasting and ground
vibration study, vibration monitoring,
fragmentation improvement studies, random
sampling & testing of explosives and accessories
and performance evaluation of new explosives
with sophisticated testing equipment, in both coal
and non-coal sectors.
3 Non-destructive Testing
(NDT)
Services for non-destructive testing of
components of machinery, installations and other
structural elements have been provided at site
during periodic maintenance to avoid accidental
failure.
4 Ventilation and Gas Survey CMPDI has been offering services for ventilation
monitoring, planning & design of ventilation
system including gas assessment and testing for
underground mines.
5 Energy Audit CMPDI is empanelled as an accredited energy
auditor with Govt. of West Bengal and Petroleum
Conservation Research Association (PCRA) under
Ministry of Petroleum and Natural Gas, Govt. of
India. Over 130 reports on electrical and diesel
energy conservation have been prepared.
6 Inspection services CMPDI has been rendering pre-dispatch third
party inspection services for plants and equipment
at the manufacturers’ workstations for materials
103
procured by its clients.
7 Captive power plants Reports on optimum utilization, conceptual notes
and tender documents
6.3.8 Laboratory Services:
CMPDI has well equipped laboratories for carrying out investigations and analysis for geo-
chemical, petrography coal washability and geo-mechanical properties.
For coal and lignite characterization, CMPDI has laboratories with highly skilled manpower
and state of art equipment. The data generated by these laboratories form basis of
characterization and grading of coal in exploration, mine feasibility reports, washery design
and downstream utilization. Brief description of Laboratory Services rendered by CMPDI is
given in Table-6.3.8.
Table-6.3.8
Sl. No. Sub-heads of Services Services rendered in
1 Geo-chemical Laboratory CMPDI has been rendering services like geo-chemical
analysis like proximate & ultimate analysis, GCV
determination of coal and lignite and other special
test through microprocessor based automatic
calorimeter and analyzer.
2 Petrographic Laboratory CMPDI has been carrying out evaluation for hydro
carbons, oil shales and coal bed methane for coal
coke and source rock through sophisticated
microscopes, identifying mineral phases in coal, rocks
and metal through X-Ray diffractometer, and micro-
area analysis and cleat studies for CBM through
Scanning Electron Microscope accredited by
International Committee for Coal and Organic
Petrology (ICCP).
3 Mining Laboratory CMPDI has been determining physico-mechanical
properties of rocks for design inputs for mine
planning and other technical services and undertaking
testing of roof supports and building materials for
design support systems for underground workings.
4 Washery Laboratory CMPDI has been determining washability
characteristics of coarse, small and fine coal and
shattering & pulverized characteristics of coal for
assistance in planning and design of coal beneficiation
plants.
5 Captive power plants Reports on optimum utilization, conceptual notes and
tender documents
104
6.3.9 IT Services in Mining:
CMPDI has been gearing up itself fully to meet challenges of IT sector requisite for mining
industries as per IT implementation scheme with a view to revolutionizing mining industry
and mining operations in coming years. IT services provided by CMPDI have been tabulated
in Table-6.3.9.
Table-6.3.9
Sl. No. Services Offered to for
1 Mine communication and mine safety systems
2 Establishing internet and internet facilities
3 Real time fleet management system for large OC mines using GIS &
GPS.
4 Land information system using enterprise GIS.
6.3.10 R & D Services:
The Research & Development activities in coal and lignite are being administered through
the Scientific Advisory Committee (SSRC) with Secretary (Coal) as its Chairman. The
committee is entrusted with the task of planning, budgeting and overseeing the
implementation of R & D programme in coal and lignite sector and also for application of
research findings. And, CMPDI is the Nodal Agency to co-ordinate S & T / R & D activities in
coal and lignite sectors and assist SSRC in areas mentioned herein after.
CMPDI applied research and development in the field of mining, beneficiation, utilization,
environment, exploration, etc. serving as nodal agency for all S & T schemes funded by
Ministry of Coal and R & D schemes funded by R & D Board of CIL (constituted in August
1995).
Field oriented research projects including transfer and absorption of new technology
concerning main areas of coal research have been as follows:
• Production, productivity and safety.
• Coal beneficiation and utilization.
• Environment and Ecology.
**************************
105
Check – list
Name of the Company :- Western Coalfields Limited (WCL)
Project :- NAHERIYA UG EXPN.
S.NO Particulars Details
I. BASIC PROJECT DETAILS
1 Name of the project: NAHERIYA UG Expn.
2 Name of the Company, Address,
Telephone No. & E- mail
Western Coalfields Limited(WCL)
Coal Estate, Civil Lines, Nagpur – 440001.
Tel. 0712- 2510151 {General Manager (Env)}
e- mail – [email protected]
3 Latitude and Longitude of the project Latitude : 22016’32’’ to 22012’53’’ N
Longitude : 78057’58’’ to 78
059’30’’ E
4 If a Joint Venture, the names &
addresses of the JV partners including
their share
No
5 Details of coal linkage Thermal power plants of MPPGCL and &
Miscellaneous consumers
6 Whether the project is in the Critically
Polluted Area (CPA):
NO
7 Cost of the Project Originally as per PR - 46.1708 Crores and
additional capital (approved in Scheme) of 8.62
Crores . Total 54.79078 Crores.
8 Employment generated/to be
generated
Required Manpower for the project is 1138 (
1018 existing manpower + 120 additional man
power) Nos.(From Internal)
Indirect – Approximately 100 (contractual &
misc. Works related to Mining operations & Coal
transportation)
9 Benefits of the project This project will bridge the gap(to the extent of
the peak production capacity of the project)
between demand & supply of non – coking coal
for power houses & other bulk consumers of
Northern as well as Southern part of the country.
10 Whether new or expansion project
If Expansion
Expansion
i) From …… MT to …..MT 0.36 MTPA to 0.54 MTPA
ii) What is the % of expansion 50 %
106
S.NO Particulars Details
11 If for expansion, whether the
application is under 7(ii) of the EIA
Notification, 2006.
Yes.
Application is as per OM dated 19.12.12 &
07.01.14
12 If expansion, please indicate the
number and date of the certified
Compliance Report of Regional Office
of the MOEF
Submitted vide letter No.
3-24/2007(ENV)/1287 dated 18.11.2015 by
Regional Office, MoEF&CC, Bhopal .
13 No. and Date of the TOR/and revised
TOR,ifany, letter issued by the MoEF
(if this is a case for EC)
NOT APPLICABLE
14 No. and Date of the EC and the
revised EC letter issued by the
MoEF(if this is a case for
reconsideration(s) being sought by
the proponent)
No.
This proposal is for expansion in production
capacity u/s 7(ii) of EIA Notification 2006 beyond
the EC capacity sanctioned vide letter
J-11015/35/2001-IA.II(M) dated 15.11.2001 in
terms of the O.M. dated 19.12.2012 &
07.01.2014.
15 If the project was considered in EAC,
Pl. give dates of the meeting (s).
NOT APPLICABLE
16 Type of Mine: ( Open
cast/Underground/mixed)
Underground
17 Capacity of mine applied for 0.54 MTPA
Expansion from 0.36 MTPA to 0.54 MTPA
18 ML Area 300.0 ha
a) As per Block Allotment 3.00 sq.km (Naheriya Goeological Block)
b) As per approved Mine Plan Total Land Area – 330.0 ha ( Mine Lease Area -
300 Ha + All rights area - 30.0 Ha)
19 Date of approval of mine plan, mine
closure plan, status& date
Scheme approval for expansion approved on
12/01/2016 by WCL
20 Date of Board’s approval: Scheme approval by WCL on 12/01/2016
21 Date of Ground water clearance: Not Applicable. As it is not falling in critical area
as per CGWA
22 Date of Mine Closure approval 28.01.2013
23 Any river/Nallah flowing adjacent to
the proposed mine. If yes, please
indicate
Gunor river, Dhankasa nallah.
II. TECHNICAL DETAILS
24 Geological Reserve:
107
S.NO Particulars Details
i. Total geological reserve
34.259 Mt
ii. Mineable reserve
32.603 Mt
iii. Extractable reserve
12.66 Mt
iv. Percent (%) of extraction
38 %
v. Range of ground water level
Core Zone Pre -2.80 m to 6.60 m
Post -1.65 m to 6.43 m
Buffer Zone Pre - 2.00 m to 12.35 m
Post -0.70 m to 9.30 m
vi. Total estimated water
requirement:
444 KLD
25 Details of Seams:
i) No. of Seams Five
ii) Thickness of Seams to be
worked on
Seam II - 0.31m to 3.31m
Seam IV - 0.65 m to 5.04 m
iii) Grade of Coal GCV –(4420-5142) Kcal/kg
iv) Stripping Ratio > 1:19
v) Category of gaseousness Degree 1
vi) Average Gradient 1:11 to 1:18
vii) Maximum thickness of Seams S.No seam Thickness (m)
Min Max
1 V 1.19 3.31
2 IV 0.65 5.04
3 III 0.18 2.34
4 II 0.31 3.13
5 I C 0.05 3.43
6 I B 0.12 0.12
26 Method of Mining Underground mining with LHDs
27 Life of Mine 15 years
28 Whether ambient air quality seasonal
data has been documented. If so,
from which season to which season
and whether the results are within
the prescribed limits.
Yes. The mine is in operation. Fortnightly
environmental monitoring as per Existing EC is
carried out. Q.E. Sep 15 - Most of the time it is
within limits.
108
S.NO Particulars Details
29 Whether the certificate of compliance
of earlier EC from MoEF Regional
Office has been obtained, if the
proposal is for expansion.
Yes.
Submitted vide letter No.
3-24/2007(ENV)/1287 dated 18.11.2015 by
Regional Office, MoEF&CC, Bhopal.
30 Details of O.B.
i) External OB Dumps Not Applicable Since it is a underground mine.
ii) No. of Dumps
iii) Area
iv) Height
v) Quantity
vi) Year of Backfilling
31 Details of Internal Dumps Not Applicable
i) No. of Internal Dumps
ii) Area
iii) Height
iv) Quantity
32 Details of Final Mine Void Not Applicable
i) Area
ii) Depth
33 Details of Quarry Not Applicable
i. Total quarry area :
ii. Backfilled quarry area of …..ha shall
be reclaimed with plantation
iii. A void of ….. ha at a depth of …… m
which is proposed to be converted
into a water
body
34 Land Usage
i) Pre-mining Total Area - 330 Ha
Total Mine Lease area - 300 Ha
Forest Land - 206.562 Ha
Agriculture Land - 93.438
Area under All rights (Non forest) - 30Ha
ii) Post Mining
109
S.NO Particulars Details
iii) Core Area As given above
Details of Forest Issues
i) Total Forest Area involved (in ha)
for mining
206.562 Ha
ii) Status of Forest Clearance Forest Clearance obtained vide letter no
8-37/2000-FC dated 11.04.2001
iii) Is there any National Park, eco –
sensitive Zone within 10 km radius? If
so, give the details
No
iv) If the project is within 10 KM of
radius of the wild life sanctuary,
whether the wild life Management
Plan has been prepared and
approved. If so, pl give the status,
date of approval with the budgetary
provision.
No
v. Extent of forest land in the project
(including safety zone and all types of
forest land)
(in ha)
Forest Land - 198.20 Ha
Big Tree Forest - 8.32 Ha
v. Total forest land for which Stage-1
FC is available (give area in ha),
provide breakup
of this area in following format:
Area (in Ha) Stage-1 FC
issued vide
letter no. &
date
Validity
period of
FC
206.562 Ha Forest Clearance
was accorded
vide no.8-
37/2000-FC dated
11.04.2001
11.04.2031
( 30 Years)
vi. Balance forest land for which
Stage-1 FC is not available (give area
in ha)
Not applicable
vii. Details of wild life issues involved,
if any. If so, whether Wild Life
management plan
has been prepared and pl. indicate
the status.
Not applicable
35 Costs of the Project
i) Total Capital Cost Rs. 8.62 Crores (Additional)
ii) Cost of Production Rs 2270.68 per tonne(at 100%)
iii) Sale Price Rs. 1971 /t (Power Sector)
iv) CSR Cost Rs. 2.00 per tone
v) R&R Cost Not Involved Hence Nil Cost
vi) No. of PAFs Not Involved Hence Nil Cost
110
S.NO Particulars Details
vii) Environmental Management
Cost
Revenue @ Rs 6.00 per tonne
36 Details of Transportation of Coal
I) In Pit Through Conveyor belt from incline to Coal
bunkers and to Stock yard
II) Surface to Siding By Tippers
III) Siding to Loading By Pay Loaders
37 Details of reclamation
a. Total Afforestation plan shall be
implemented covering an area of:
………. Ha at the end of mining. This
will include:
9 Ha includes Road, Township, around
infrastructure
i. Reclaimed external OB dump ( in ha)
:
NA
ii. internal dump (in Mcum), NA
iii. Green belt ( in ha) (Out of Total 330 ha Area, 30 Ha is under All
Rights, Plantation will be done at 09 ha Area. i.e.,
30% of All Rights Area)
iv. Density of tree plantation ( in no of
plants)
At 2500 plants per ha
v. void ( in ha) at a depth of ( in m
)which is proposed to be converted
into water body
NA
vi. Others in ha (such as excavation
area along ML boundary, along roads
and infrastructure, embankment area
and in township located outside the
lease etc).
S.N Particulars Total Area(ha)
1 Roads &
infrastructure, open
places (approx.)
9.0
III. LEGAL ISSUES
38 Pl give details, if the proposal is under
any investigation
Not Applicable
39 Any court cases pending. If so, please
provide a list with details as annexure.
Not Applicable
40 Any violation cases pending. If so,
please provide a list with details as
annexure
Not Applicable
41 Give details of actual coal production
vis-à-vis sanctioned capacity since the
inception of
mine in following format :
Year EC
sanctioned
capacity
(MTPA)
Actual
production
(MTPA)
Excess
production
beyond the
EC sanctioned
capacity
2000-01 0.36 Mt 0.0311 Mt No 2001-02 0.36 Mt 0.117 Mt No
111
S.NO Particulars Details
2002-03 0.36 Mt 0.163 Mt No 2003-04 0.36 Mt 0.195 Mt No 2004-05 0.36 Mt 0.264 Mt No 2005-06 0.36 Mt 0.276 Mt No 2006-07 0.36 Mt 0.256 Mt No 2007-08 0.36 Mt 0.192 Mt No 2008-09 0.36 Mt 0.219 Mt No 2009-10 0.36 Mt 0.235 Mt No 2010-11 0.36 Mt 0.253 Mt No 2011-12 0.36 Mt 0.272 Mt No 2012-13 0.36 Mt 0.316 Mt No 2013-14 0.36 Mt 0.284 Mt No 2014-15 0.36 Mt 0.258 Mt No
IV. PUBLIC HEARING
42 Date and Place of public hearing: Held on 11.09.2001 at District Collectorate,
Chhindwara for the existing EC dated 15.11.2002.
43 Issues raised during Public Hearing 1. Regular monitoring of pollution levels in
Ambient Air, Mine Discharge, and Noise level.
2. Plantation along the road, siding and in open
Places and maintainence
Already covered in the existing EC.
V. CONSULTANT
44 Name of the consultant who prepared
the EIA/EMP report
Central Mine Planning and Design Institute Ltd.
(CMPDIL)
45 Whether the consultant has been
accredited by the QCI and NABL as
per the MoEF OM dated 2nd
December,2009
Yes
VI. IMG of Ministry of Coal:
46 Whether the project was considered
by the IMG of Ministry of Coal for any
irregularities. If so the no. and date of
the show cause notice and the
response of the MoC.
No
112
ANNEXURES ANNEXURE-I COMPLIANCE REPORT FROM MOEF REGIONAL OFFICE
ANNEXURE-II ATR SUBMITTED TO MOEF ANNEXURE-III ENVIRONMENTAL CLEARANCE OF 0.36 MTPA ANNEXURE-IV MINUTES OF PUBLIC HEARNING ANNEXURE-V STATUS OF CSR ACTIVITY ANNEXURE-VI SCHEME APPROVAL LETTER ANNEXURE-VII SUBSIDENCE REPORT ANNEXURE-VIII TOPO PLAN
113
114
115
116
117
118
119
120
121
Nehariya UG Mine Sub:- Action Taken Report against the Certificate of Compliance issued by Regional Office, MoEFF&CC, Bhopal vide letter 3-24/2007(ENV)/1287
dated 18/11/2015
Ref:-ECLetter No. J-11015/35/200/35/2001-I A II (M) date 15.11.2002
A. SPECIFIC CONDITIONS
S.
N
Conditions Observation of MoEF&CC Action Taken Report
1. The action plan for eco-
development measures
around the Project area
including welfare measures for
the local community should be
prepared and submitted to the
Ministry within 3 months.
These measures would be in
addition to measures
proposed in the EMP and such
measures to be undertaken
should be at least 1%of the
project cost of 46.17 crores.
PA submitted that the following
measures for the local community and
eco-development has been taken up as
Eco-Development Measures:-
1. 5000 nos. of plants have been
planted at Naheriya Complex. Nos.
of plantations has been done in
Bokai colony along both sides of the
road.
Welfare Measures:-
1. 6 nos. of Bore well / Hand Pumps
have been provided for the local
community.
2. A Stop Dam has been constructed at
GurulluNalah.
3. A Community Development Hall has
been constructed for the
recreational purposes of villagers.
4. Vocational Training has been
provided to the local youth, who are
thereafter absorbed as contractual
workers.
5. Metalled road has been constructed
The various eco-development works undertaken in the
neighbouring villages since 2003-04 to cater for
a). Improving drinking water facilities.
b). Improving roads & bridges
c). Providing assistance for community benefits
d). Assistance to education.
Total year – wise expenditure on eco-development measures
around the Project Area incurred since 2003-04 is as follows:-
Year Activity Village Expenditure
2003-04 1. Tree Plantation Bhokai 195000.00
2004-05 1. 100 m CC road Bhokai 155000.00
2005-06 1. Well
construction
Naheriya 108000.00
2. Well
Construction
Bhokai 90000.00
2006-07 1. Well
Construction
Tumdi 99000.00
2007-08 1. Stop dam Naheriya 297340.00
2. Hand-pump (4
Nos.)
Bhokai 159156.00
122
in Naheriya market to ensure safety
of villagers.
It is observed that the action plan
has not been submitted within the
time limit as such no details
headwise/year wise all expenditures
are submitted within time limit.
Not Complied.
3. 1 no. of Well (4.5
m dia and 10.5 m
depth)
Naheriya 99993.25
2008-09 1. Class Room Naheriya 279638.00
2. Community
Center
353940.00
3. Hand pump 34352.00
4. Cremation shed Bhokai 160189.00
5. G.I. Pipe line
laying
Jhurrey to
Bhokai
258300.00
2009-10 1. C.C.Road Bhokai 267703.00
2010-11 1. Boundary wall
along the cremation
shed
Bhokai 133450.00
2. 100m long / 250
mm dia pipe line
with motor
Naheriya 349000.00
3. 200 m WBM
approach road
Cremation
Place to
Jhurre Mall
Village
318000.00
2011-12 1. C.C. Road Bhokai 298000.00
2. Play ground Jhurre 194528.00
3. 1 no. of Hand-
Pump
Urdhan 19000.00
123
4. 2 nos. of Hand-
Pump
Jhurre
(Middle
School)
194000.00
5. Black Topping of
1 Km road
Jhurre village
to main basti
412000.00
6. 100 m CC road JhurreBasti
ward 3
209000.00
7. 100 m CC road Urdhan 209000.00
8. 200m CC road
and Culvert
Tumdi 469000.00
9. 400 m CC road Tumdi 1023000.00
10. 1 Km long water
pipe line and a
switch room
Bhokai 556000.00
11. Stop Dam at
Gurulla Nallah
230000.00
2012-13 1. 2 nos. of
classrooms for
school building
Rahiwada 685000.00
2. Community Hall Sajwa 721500.00
3. 100 m CC road Nutan –
Chikli Block
257000.00
4. 100 m CC road Rahiwada 311400.00
5. Culvert on river Urdhan
Dhana
584000.00
124
6. CC road
construction and
bridge repair work
Bhokai 894000.00
2013-14 1. Vocational
Training has been
provided to the local
youth
Departmenta
lly done.
2. Regular Cleaning
of wells
2014-15 1. Vocational
Training has been
provided to the local
youth
Departmenta
lly done.
2. Regular cleaning
of wells
TOTAL 10624489.25
As seen from the above the total cost on eco-development
incurred so far is 2.30% (the condition stipulates at least 1%).
It is further submitted that such eco-development works will
continue to be undertaken in the balance years also as per the felt
need of the neighboring population.
9. ETP should be installed in
township for treatment of
domestic wastes.
PA submitted that at present there are
418 Quarters in Bhokai Township, out
of which occupied Quarters are 200.
Another 78 Quarters are to be
constructed. All the residential are
provided with individual septic tank and
conventional soak pit arrangement.
Proposed construction of 78 Quarters,
In the Bokai Township, there are 418 quarters having individual
septic tank with proper designed soak pit.
The effluent from the quarters are being collected through pipes,
manhole chambers and treated in two stage as per the provision
of “ IS : 2470 (Part – 1& 2 )-1985 ‘Code of practice for design and
construction of septic tanks&secondary treatment and disposal
of septic tank effluent”
125
STP will be explored and appropriate
decisions will be taken. No ETP installed
in township for treatment of domestic
wastes.
Not Complied.
The philosophy of treatment is given below:-
• Septic tank offers a preliminary treatment of sewage prior to
final disposal. Sewage is held in these tanks for some
prescribed period during which time the suspended solids
present in the storage settle down. The settled sludge and the
supernatant liquor undergo anaerobic digestion. The digestion
results in appreciable reduction in the volume of sludge and
reduction in organic matter in the liquid.
• METHODS OF TREATMENT AND DISPOSAL OF EFFLUENT
The following methods of disposal are described in this Code:
� a) Soil absorption system,
• We have adopted the one of the universally accepted
methods.
• Soil Absorption Systems — After collecting necessary
information like soil type, percolation test and position and
nature of outfall ditches, wells, tanks or smallstreams in
the vicinityetc., the soak pit has been designed and
constructed as per the provision of “ CODE OF PRACTICE
FORINSTALLATION OF SEPTIC TANKSPART 2 SECONDARY
TREATMENT AND DISPOSALOF SEPTIC TANK EFFLUENT”
In view of the above, we have complied as per the
guidelines of IS – Codes 2470 – (Part- 1 &2 ) -1985.
126
B. GENERAL CONDITIONS.
S.N Conditions Observation of MoEF&CC Action Taken Report 13. The funds earmarked for
environmental protection
measures should be kept in
separate account and should
not be diverted for any other
purpose. Year wise
expenditure should be
reported to the Regional
Office of the ministry located
at Bhopal.
There is a separated account for the
funds earmarked for environmental
protection measures and is being
utilized and recorded for the said
purpose only. It is observed that the
details have not been submitted and
no details head wise/year wise for all
expenditures are to be submitted.
Not Complied.
Total Year wise and head wise expenditure:
Year
wise
Activity/Particulars Expenditure
2003-04 1. Tree Plantation 195000.00
2. Consent fees to MPPCB 200000.00
2004-05 1. 100 m CC road 155000.00
2. Consent fees to MPPCB 200000.00
2005-06 1. Well construction 108000.00
2. Well Construction 90000.00
3. Consent fees to MPPCB 160000.00
2006-07 1. Well Construction 99000.00
2. Consent fees to MPPCB 160000.00
2007-08 1. Stop dam 297340.00
2. Hand-pump (4 Nos.) 159156.00
3. 1 no. of Well (4.5 m dia and 10.5 m
depth)
99993.25
4. Consent fees to MPPCB 160000.00
2008-09 1. Class Room 279638.00
2. Community Center 353940.00
3. Hand pump 34352.00
4. Cremation shed 160189.00
5. G.I. Pipe line laying 258300.00
6. Consent fees to MPPCB 160000.00
127
2009-10 1.TRANSPORT ROAD 518373.00
2.RR Drain 333638.00
3. Consent fees to MPPCB 160000.00
2010-11 1. Boundary wall along the cremation
shed
133450.00
2. 100m long / 250 mm dia pipe line with
motor
349000.00
3. 200 m WBM approach road 318000.00
4. Consent fees to MPPCB 160000.00
2011-12 1. C.C. Road 298000.00
2. Play ground 194528.00
3. 1 no. of Hand-Pump 19000.00
4. 2 nos. of Hand-Pump 194000.00
5. Black Topping of 1 Km road 412000.00
6. 100 m CC road 209000.00
7. 100 m CC road 209000.00
8. 200m CC road and Culvert 469000.00
9. 400 m CC road 1023000.00
10.1 Km long water pipe line and a switch
room
556000.00
11.Stop Dam at Gurulla Nallah 230000.00
12. Consent fees to MPPCB 160000.00
2012-13 1. 2 nos. of classrooms for school building 685000.00
128
2. Community Hall 721500.00
3. 100 m CC road 257000.00
4. 100 m CC road 311400.00
5. Culvert on river 584000.00
6. CC road construction and bridge repair
work
894000.00
7. Consent fees to MPPCB 160000.00
2013-14 1.Water sprinkling for dust suppression. 159088.00
2. Consent fees to MPPCB 160000.00
2014-15 Water Sprinkling for dust suppression. 883662.00
2. Consent fees to MPPCB 160000.00
2015-16 1. Consent fees to MPPCB 160000.00
Total 14091547.25
18. The Project Authorities
should advertise in at least
two local newspapers widely
circulated around the project.
One of which shall be in
vernacular language of the
locality concerned within
seven days of issue of the
clearance letter informing
that the project has clearance
Letter is available with the
SPCB and may also be seen at
Advertisement in two local
newspapers published inKranti Chakra
Parasia on 01.12.2002 and Nava
Bharat Jabalpur on 27.11.2002 which
is beyond seven days of issue of EC.
Not Complied.
EC date of letter 15.11.2002. The publication was made on 27.11.2002
i.e. delay of additional 5 days with respect to date of letter may kindly
be condoned considering the issue and receipt.
129
the website of the MOEF.
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
WCL'S MONTHLY CSR ACTIVITIES PROGRESS REPORT FOR THE MONTH OF NOVEMBER 2015 - 16 (PROVISIONAL) SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME
DISTRICT Activities
Within 25
Kms/Beyond
25 Kms
Exp. In
15 -16
(Fig Rs. In
Lakhs)
SWACHH BHARAT ABHIYAN (CONSTRUCTION OF TOILETS)
5 Swachh Bharat Abhiyan (Construction of Toilets) SVA Pench Various Villages Chhindwara
Within/Beyond 25 Km 30.85
Total :- 30.85
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
HEALTH CARE 1 Hiring of Mobile Medical Van HCMMV Pench Various Villages Chhindwara Within 25 km 4.03 2 Village Medical camps HCVMC Pench Various Villages Chhindwara Within 25 km 0.26 TOTAL :- 4.29
INFRASTRUCTURE SUPPORRT (CONSTRUCTION / REPAIRS/EXTENTION) 1
Construction of Compound Wall in football ground at Daniyalson UM vidyalay CHW
INFBW Pench Shivpur Chhindwara Within 25 km 25.79
2 Const.of Boundari wall for khedapati mandir ward no 17 at parasiya
INFBW Pench Kundala Kala Chhindwara Within 25 km 4.31
3 Construction of Boundary wall at Bagalamukhi Mandir Jatajhapar
INFBW Pench Patha Chhindwara Within 25 km 1.31
4 const.of choupal at gayatri mandir Shivpuri INFCBT/CPL Pench Kohka Chhindwara Within 25 km 1.08 5 const.of choupal at sai mandir Shivpuri INFCBT/CPL Pench Khanswada Chhindwara Within 25 km 1.06
6 const.of choupal at near mata mandir panchayt Khajari antu.
INFCBT/CPL Pench Bhamada Chhindwara Within 25 km 1.10
7 const.of choupal at Bijagora INFCBT/CPL Pench Chandmeta Chhindwara Within 25 km 1.10 8 const.of choupal at Mata mandir at Apatara INFCBT/CPL Pench Shivpuri Chhindwara Within 25 km 1.10 9 const.of choupal at choupan tekadi,panchyayt INFCBT/CPL Pench Khairanji Chhindwara Within 25 km 1.10
170
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
Dabak
10 Construction of Chabutra at Garha Tola Parasiya Village
INFCBT/CPL Pench Garha Tola Chhindwara Beyond 25 Km 0.49
11 Construction of Chabutra at karapatha Village INFCBT/CPL Pench Karapatha Chhindwara Beyond 25 Km 0.49
12 Construction of Community Building at Bhamori Village
INFCH Pench Mankadeyikala Chhindwara Within 25 km 3.41
13 Const.of community building at Hirwadi, gram panchyat chandameta-kala
INFCH Pench Mankadeyikala Chhindwara Within 25 km 5.50
14 Construction of Community Building at Pounar Village
INFCH Pench Pounari Chhindwara Beyond 25 Km 8.24
15 Fencing of Masahanghat near Bhujliya Nalah,Eklehara
INFCMT Pench Parasia Chhindwara Within 25 km 1.84
16 Construction of Puliya at Barsa Grampanchayat, Ghogari
INFDM/BDG Pench Khajari Chhindwara Within 25 km 2.39
17 const.of pulliya at Sawaldhana INFDM/BDG Pench Hirwadi Chhindwara Within 25 km 5.50 18 const.of pulliya at Pendonala , Kohka INFDM/BDG Pench Kachram Chhindwara Within 25 km 5.81
19 Construction of Pulliya at nera PWD rest house, Gram khapa, Harrai
INFDM/BDG Pench Haraai Chhindwara Beyond 25 Km 5.50
20 Construction of 200 Mtr. Cement Drainage at Lahegdua
INFDRN Pench Lahegdua (Tamiya
Block) Chhindwara Beyond 25 Km 4.34
21 Providing and laying Paver blocks at Barkuhi Masjid
INFOW Pench Bijagora Chhindwara Within 25 km 5.58
22 Construction of Swagat/Pravesh Dwar at Khanswada
INFOW Pench Laminiya Chhindwara Within 25 km 2.15
23 Development of Indira Gandhi Stadium at Chhindwara City ,MP
INFOW Pench Madai Chhindwara Within 25 km 18.47
24 Development and fencing of inner(Hockey)ground of Danielson college
INFOW Pench Chhindwara City Chhindwara Beyond 25 Km 1.32
25 Const.of 100 Mtr.cement concrete road at ward no.10,kundali kala near hanuman mandir
INFRDCC Pench Apatara Chhindwara Within 25 km 3.47
26 Construcdtion of 100 Mtr C.C road near Bhujliya Nalah upto Mashanghat
INFRDCC Pench Shivpuri Chhindwara Within 25 km 3.55
171
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
27 Const.of 100 Mtr.cement concrete road at ward no.2,patha
INFRDCC Pench Malpipariya Chhindwara Within 25 km 3.51
28 Const.of 100 Mtr.cement concrete road at Mankadeyikala
INFRDCC Pench Bararia Chhindwara Within 25 km 3.69
29 Const.of 100 Mtr.cement concrete road at Tumdi INFRDCC Pench Khedapati Chhindwara Within 25 km 3.47
30 Const.of 100 Mtr.cement concrete road at Chandmeta Masjid
INFRDCC Pench Choupan Tekadi Chhindwara Within 25 km -0.91
31 Const.of 100 Mtr.cement concrete road at Khairychietu
INFRDCC Pench Thisgoura Chhindwara Within 25 km 3.63
32 Const.of 100 Mtr.cement concrete road at Gayagohan-semardhana,gram panchayt Satnur
INFRDCC Pench Darbai Chhindwara Within 25 km 3.47
33 Const.of 100 Mtr.cement concrete road at Mankadeyi-khurd
INFRDCC Pench Khairychitu Chhindwara Within 25 km 3.47
34 Const.of 100 Mtr.cement concrete road at Zubrebasti ward no 2,panchayt zubremal
INFRDCC Pench Sahapani Chhindwara Within 25 km 3.54
35 Const.of 100 Mtr.cement concrete road at Tanda,gram panchayt Baghbadhiya
INFRDCC Pench Gayagohan semardhana
Chhindwara Within 25 km 3.56
36 Const.of 100 Mtr.cement concrete road at Baddi,panchayat Lohari-Bandari
INFRDCC Pench Zubrebasti Chhindwara Within 25 km 3.47
37 Const.of 100 Mtr.cement concrete road at Ghagartalai,gram panchayt Talpipariya
INFRDCC Pench Nehariya Chhindwara Within 25 km 3.47
38 Construction of 100 Mtr Cement Concrete road at Palani Village,
INFRDCC Pench Palani Chhindwara Beyond 25 Km 3.38
39 Construction of 100 Mtr. Cement Concrete road at Simariya Village
INFRDCC Pench Simariya Chhindwara Beyond 25 Km 3.41
40 Construction of 200 Mtr Cement Concrete road at Umri Village(100 Mtr done)
INFRDCC Pench Umri Chhindwara Beyond 25 Km 3.42
41 Connstruction of 200 Mtr Cement Concrete road at Chinda Village
INFRDCC Pench Chinda Chhindwara Beyond 25 Km 3.44
42 Construction of 200 Mtr Cement Concrete road at Gval Mohalla,
INFRDCC Pench Gval Mohalla Chhindwara Beyond 25 Km 3.39
43 Construction of 200 Mtr Cement Concrete road INFRDCC Pench Balidhana Chhindwara Beyond 25 Km 3.40
172
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
at Balidhana Village
44 Construction of 100 Mtr. Cement Concrete road at Pounari Village
INFRDCC Pench Pounari Chhindwara Beyond 25 Km 3.41
45 Construction of 100 mtr cement concrete road at Hatoda.
INFRDCC Pench Hatoda Chhindwara Beyond 25 Km 3.41
46 200 Mtr. Cement Concrete Road at Rajadi Pipla INFRDCC Pench Rajadi Pipla
(Sausar Block) Chhindwara Beyond 25 Km 4.39
47 300 Mtr. Cement Concrete Road at Gram Navegaon Udasi
INFRDCC Pench Navegaon Udasi
(Mohkhed Block) Chhindwara Beyond 25 Km 5.03
48 200 Mtr CC road at Navegaon Udasi INFRDCC Pench Navegaon Udasi
(Mohkhed Block) Chhindwara Beyond 25 Km 5.05
49 100 Mtr. Cement Concrete Road at Gaidhane House to Mata Mandir
INFRDCC Pench Mohkhed
(Mohkhed Block) Chhindwara Beyond 25 Km 2.75
50 200 Mtr. Cement Concrete Road at Tansra, G.P Tansramal
INFRDCC Pench Tansra (Mohkhed
Block) Chhindwara Beyond 25 Km 7.63
51 200 Mtr. Cement Concrete Road from Main road to High School in Ner Gram
INFRDCC Pench Ner (Chhindwara
Block) Chhindwara Beyond 25 Km 4.96
52 100 Mtr. Cement Concrete Road from Sukiyara House to Rambhrosh House at Kuhiya
INFRDCC Pench Kuhiya
(Chhindwara Block)
Chhindwara Beyond 25 Km 2.75
53 100 Mtr. Cement Concrete Road from Hariprasad Viswakarma House to Bazar Chouk at Kuhiya
INFRDCC Pench Kuhiya
(Chhindwara Block)
Chhindwara Beyond 25 Km 2.75
54 100 Mtr. Cement Concrete Road at Ajaniya Gram
INFRDCC Pench Ajaniya
(Chhindwara Block)
Chhindwara Beyond 25 Km 2.75
55 200 Mtr. Cement Concrete Road at Khapa Khurd Gram
INFRDCC Pench Khapa Khurd
(Tamiya Block) Chhindwara Beyond 25 Km 5.08
56 200 Mtr. Cement Concrete Road at Gram Tamiya
INFRDCC Pench Tamiya (Tamiya
Block) Chhindwara Beyond 25 Km 4.97
57 100 Mtr. Cement Concrete Road at Mendki INFRDCC Pench Mendki (Harrai
Block) Chhindwara Beyond 25 Km 2.75
173
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
58 100 Mtr. Cement Concrete Road at Banjara Tola
INFRDCC Pench Banjara Tola
(Harrai Block) Chhindwara Beyond 25 Km 4.99
59 100 Mtr. Cement Concrete Road at Muarkala INFRDCC Pench Muarkala (Harrai
Block) Chhindwara Beyond 25 Km 5.02
60 100 Mtr. Cement Concrete Road at Matiya INFRDCC Pench Matiya (Harrai
Block) Chhindwara Beyond 25 Km 2.75
61 100 Mtr. Cement Concrete Road at Sejwada INFRDCC Pench Sejwada (Harrai
Block) Chhindwara Beyond 25 Km 2.75
62 100 Mtr. Cement Concrete Road at Karapata INFRDCC Pench Karapata (Harrai
Block) Chhindwara Beyond 25 Km 2.75
63 100 Mtr. Cement Concrete Road at Baratmari INFRDCC Pench Baratmari (Harrai
Block) Chhindwara Beyond 25 Km 2.75
64 200 Mtr. Cement Concrete Road to Adiwasi Gram Dhana Road
INFRDCC Pench Adiwasi Gram
Dhana (Sausar Block)
Chhindwara Beyond 25 Km 5.03
65 300 Mtr. Cement Concrete Road at Kadaiya INFRDCC Pench Kadaiya (Sausar
Block) Chhindwara Beyond 25 Km 5.07
66 150 Mtr. Cement Concrete Road at Bilanda Gram
INFRDCC Pench Bilinda (Chourai
Block) Chhindwara Beyond 25 Km 4.95
67 100 Mtr. Cement Concrete Road at Samaswada Gram
INFRDCC Pench Samaswada
(Chourai Block) Chhindwara Beyond 25 Km 5.03
68 100 Mtr. Cement Concrete Road at Moghar gaon INFRDCC Pench Moghargaon
(Chourai Block) Chhindwara Beyond 25 Km 4.94
69 100 Mtr. Cement Concrete Road at Gohargaon INFRDCC Pench Gohargaon
(Chourai Block) Chhindwara Beyond 25 Km 4.96
70 100 Mtr. Cement Concrete Road at Ghogri Gram INFRDCC Pench Ghogri
(Amarwada Block) Chhindwara Beyond 25 Km 4.99
71 100 Mtr. Cement Concrete Road at Diwangaon Basti
INFRDCC Pench Diwangaon
(Amarwada Block) Chhindwara Beyond 25 Km 4.95
72 100 Mtr. Cement Concrete Road at Bajrang Dhana Gram
INFRDCC Pench Bajrang Dhana
(Amarwada Block) Chhindwara Beyond 25 Km 4.92
73 100 Mtr. Cement Concrete Road at Semrapura INFRDCC Pench Semrapura Chhindwara Beyond 25 Km 4.95
174
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
Gram (Amarwada Block)
74 100 Mtr. Cement Concrete Road at Dungaria Raiyat
INFRDCC Pench Dungariya Raiyat
(Amarwada Block) Chhindwara Beyond 25 Km 5.02
75 const.of rang manch at Musadevi INFRGM Pench Mahavirdhana Chhindwara Within 25 km 0.88
76 const.of rang manch at Jhurremal Hanuman Mandir
INFRGM Pench Newton Chhindwara Within 25 km 1.65
77 const.of rang manch at Darbai Bajrang Mandir INFRGM Pench Barkuhi Chhindwara Within 25 km 1.65 78 const.of rang manch at Shiv Puri High School INFRGM Pench Eklehara Chhindwara Within 25 km 1.52
79 const.of rang manch at Durga Mandir ,Bazar Chowk Parasia
INFRGM Pench Parasia Chhindwara Within 25 km 1.65
80 const.of rang manch at Khairanji, panchyat Harai INFRGM Pench Haranbhata Chhindwara Within 25 km 1.79
81 const.of rang manch at nagadev chowk, panchyat Mankadeyikala
INFRGM Pench Barsa Chhindwara Within 25 km 1.62
82 const.of rang manch at Bhamada INFRGM Pench Nagalwadi Chhindwara Within 25 km 1.55
83 const.of rang manch at Kachram,panchyat Bijakwada
INFRGM Pench Deoridhana Chhindwara Within 25 km 1.44
84 const.of rang manch at Laminiya, panchyat Sindarai guryyathar
INFRGM Pench Tigara Chhindwara Within 25 km 1.65
85 const.of rang manch at Madae INFRGM Pench Jatajhapar Chhindwara Within 25 km 1.77
86 const.of rang manch at Nehariya,panchayat uradhan
INFRGM Pench Chhindwara City Chhindwara Within 25 km 1.27
87 const.of rang manch at khedapati mandir Mandala
INFRGM Pench Bhamori Chhindwara Within 25 km 1.65
88 const.of rang manch at Thisgoura,panchayat Tendukheda
INFRGM Pench Barkui Chhindwara Within 25 km 1.65
89 const.of rang manch at Lohari-bandari INFRGM Pench Chhindwara City Chhindwara Within 25 km 1.65 90 Const.of rangmunch at Dhamodi Durga Mandir INFRGM Pench Various Villages Chhindwara Within 25 km 1.51
91 Construction of Stage (Rangmanch) at Tinsai Village
INFRGM Pench Tinsai Chhindwara Beyond 25 Km 1.62
92 Construction of Stage ( Rangmanch )at Chinda school Dhana
INFRGM Pench Chinda Chhindwara Beyond 25 Km 1.71
93 Construction of Stage at Pounari Village INFRGM Pench Pounari Chhindwara Beyond 25 Km 1.57
175
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
94 Construction of community hall at Village Sonapur, Block Amarwada of Pench Area
INFCH Pench Sonapur Chhindwara Beyond 25 Km 7.18
95 Construction of community hall at Village Swami-Sallaiya Block Harrai of Pench Area
INFCH Pench Swami sallaiya Chhindwara Beyond 25 Km 1.47
96 Construction of community hall at Village Jamunia, Block Harrai of Pench Area
INFCH Pench Jamunia Chhindwara Beyond 25 Km 6.89
97 Construction of community hall at Village Nandanwadi of Ammarwada Block Pench Area
INFCH Pench Nandanwadi Chhindwara Beyond 25 Km 7.27
98 Construction of Cement Concrete Road 600 Mtrs from Mohan Colliery to Hinglaj Main road. Village Ambada
INFRDCC Pench Ambada Chhindwara Within 25 km 1.99
99 Const. of Rang Manch under CSR at Village Pati Pathara, Ghogartola (Dharmi) and Gorpani of Harrai Block under Pench Area (4th Call)
INFRGM Pench Pati, Pathara,
Ghogartola(Dharmi) & Gorpani
Chhindwara Beyond 25 Km 3.27
100 Construction of Manch at village Chikhlibala, Chandan Gaon, Dungaria Raiat And Ghugarla Kala of Amarwada Block of Pench Area Parasia
INFRGM Pench
Chikhibala,Chandan Gaon, Dungaria Raiat & Ghugarla
Kala
Chhindwara Beyond 25 Km 0.12
TOTAL :- 362.30
101 MISCELLENIOUS 102 Recovery of Advance Payment of NBCC MISC Pench Hatoda Chhindwara Beyond 25 Km -26.00
TOTAL :- -26.00
SPORTS AND CULTURAL 103
Construction of Compound Wall to Play ground at Mehalon
SCOW Pench Mehalon Chhindwara Beyond 25 Km 10.95
TOTAL :- 10.95
WATER SUPPLY AND DRINKING WATER 104 Bor handpump 1 nos. at Bijagora WSHP Pench Various Villages Chhindwara Within 25 km 1.00 105 Bor handpump 2 nos. at mahavir WSHP Pench Various Villages Chhindwara Within 25 km 2.05
176
WCL'S CSR ACTIVITIES AT A GLANCE 2014 - 15 SL NO CSR ACTIVITIES WORK CODE AREA VILLAGE
NAME DISTRICT Activities
Within 25 Kms/Beyond
25 Kms
EXP. INCURRED
2014-15(Fig. in Rs Lakhs)
dhana,panchyayt Umareth 106 Provision of bor or hand pump at Hatoda WSHP Pench Hatoda Chhindwara Beyond 25 Km 2.15
TOTAL :- 5.20
GRAND TOTAL :- 356.74
WCL'S CSR ACTIVITIES AT A GLANCE 2013 - 14 SL NO
CSR ACTIVITIES WORK CODE AREA
VILLAGE NAME
DISTRICT
Activities Within 25
Kms/Beyond 25 Kms
EXP.INCURRED IN 13-
14(Fig.in Rs Lakhs)
HEALTH CARE 1 Mobile medical camp HCMMV Pench Crusader Chhindwara Within 25 Km 5.87
2 Medical Camps HCVMC Pench Jhurremal
Hanuman Mandir Chhindwara Within 25 Km 0.48
TOTAL :- 6.35
INFRASTRUCTURE SUPPORRT (CONSTRUCTION / REPAIRS/EXTENTION) 3
Construction of Boundary wall at Bagalamukhi Mandir Jatajhapar
INFBW Pench Patha Chhindwara Within 25 Km 1.92
4 Construction of Community Building at Bhamori Village
INFCH Pench Mankadeyikala Chhindwara Within 25 Km 4.73
5 Construction of Puliya at Barsa Grampanchayat, Ghogari
INFDAM/BDG
Pench Khajari Chhindwara Within 25 Km 3.49
6 Development and fencing of inner(Hockey)ground of Danielson college
INFOW Pench Danielson college Chhindwara Beyond 25 Km 11.73
7 Const.of 100 Mtr.cement concrete road at nagalwadi ward no 20 ,Jaganadhoh
INFRDCC Pench Sawaldhana Chhindwara Within 25 Km 3.62
177
WCL'S CSR ACTIVITIES AT A GLANCE 2013 - 14 SL NO
CSR ACTIVITIES WORK CODE AREA
VILLAGE NAME
DISTRICT
Activities Within 25
Kms/Beyond 25 Kms
EXP.INCURRED IN 13-
14(Fig.in Rs Lakhs)
8 Const.of 100 Mtr.cement concrete road at Gularkhapa,gram panchayt Nimkuhi
INFRDCC Pench Gourpani Chhindwara Within 25 Km 3.62
9 Const.of 100 Mtr.cement concrete road at ward no .3 Newton
INFRDCC Pench Khaswada Chhindwara Within 25 Km 3.66
10 Const.of 100 Mtr.cement concrete road at Bijagora INFRDCC Pench Tanda Chhindwara Within 25 Km 3.58 11 Const.of 100 Mtr.cement concrete road at Khaswada INFRDCC Pench Mankadeyi-Khurd Chhindwara Within 25 Km 3.57
12 Construction of 100 Mtr. Cement Concrete road at Ward No. 2, Main road Shanta Kutty house, Barkui Grampanchayat
INFRDCC Pench Bijagora Chhindwara Within 25 Km 3.51
13 Const.of 100 Mtr.cement concrete road at Haranbhata INFRDCC Pench Lohari-Bandari Chhindwara Within 25 Km 3.64
14 Const.of 100 Mtr.cement concrete road at High School Marg Bararia
INFRDCC Pench Tumdi Chhindwara Within 25 Km 3.67
15 Const.of 50 Mtr.cement concrete road at Tigara INFRDCC Pench Baddi Chhindwara Within 25 Km 1.77
16 Construction of 100 Mtr. Cement Concrete road at Ward No. 10, Barkui Grampanchayat
INFRDCC Pench Bijagora Chhindwara Within 25 Km 3.52
17 Const.of 100 Mtr.cement concrete road at Malpipariya,gram panchayt Apatara
INFRDCC Pench Ghagartalai Chhindwara Within 25 Km 3.65
18 Const.of 100 Mtr.cement concrete road at mandali(chakkidhana),panchyat Mandala
INFRDCC Pench Mandali Chhindwara Within 25 Km 3.60
19 const.of rang manch at Musadevi INFRGM Pench Mahavirdhana Chhindwara Within 25 Km 2.09
20 Construction of community hall at Lahgadua block Chhindwara under CSR at Pench Area
INFCH Pench Lahgadua Chhindwara Within 25 Km 1.87
21 Construction of community hall at Sarra Village Block Chhindwara under CSR at Pench Area
INFCH Pench Sarra Chhindwara Within 25 Km 4.59
22 Construction of community hall at Village Mandan Garh, Block Amarwada of Pench Area
INFCH Pench MandanGarh Chhindwara Beyond 25 Km 7.56
23 Construction of community hall at Village Swami-Sallaiya Block Harrai of Pench Area
INFCH Pench Swami sallaiya Chhindwara Beyond 25 Km 5.66
24 Construction of cremation Shed/place at Batkakhapa Village under Harri Block under CSR at Pench Area
INFCMT Pench Batkakhapa Chhindwara Beyond 25 Km 1.56
25 Construction of cremation place at Rangeen Khapa under Chhinwada Block.
INFCMT Pench Rangeen Khapa Chhindwara Beyond 25 Km 1.75
178
WCL'S CSR ACTIVITIES AT A GLANCE 2013 - 14 SL NO
CSR ACTIVITIES WORK CODE AREA
VILLAGE NAME
DISTRICT
Activities Within 25
Kms/Beyond 25 Kms
EXP.INCURRED IN 13-
14(Fig.in Rs Lakhs)
26 Construction of 200 metre drain at Chhindwara from the house of Gangai Budhdhu to the house of Sukhram under CSR of Pench Area
INFDRN Pench Chhindwara Chhindwara Beyond 25 Km 1.75
27 Construction of 100 meter cement concrete road at Indira Awas of Chhindwara Block of Pench Area
INFRDCC Pench Indira Awas Chhindwara Within 25 Km 2.30
28 Construction of 100 meter cement concrete road at Barahhira of Amarwada Block of Pench Area
INFRDCC Pench Barahhira Chhindwara Beyond 25 Km 0.68
29 Construction of 100 mtr. cement concrete road at Pipriyamanu of Amarwada Block at Pench Area
INFRDCC Pench Pipriyamanu Chhindwara Beyond 25 Km 0.55
30 Construction of 100 meter cement concrete road at Jhirlinga of Chhindwara Block of Pench Area
INFRDCC Pench Jhirlinga Chhindwara Beyond 25 Km 0.10
31 Construction of 100 meter cement concrete road at Berban of Amarwada Block of Pench Area
INFRDCC Pench Berban Chhindwara Beyond 25 Km 2.87
32 Construction of 100 metre cement concrete road at Bamhanwada Village of Amarawada Block of Pench Area
INFRDCC Pench Bamhanwada Chhindwara Beyond 25 Km 3.12
33 Construction of 100 mtr. cement concrete road at Gadawara Village of Amarawada block of Pench Area.
INFRDCC Pench Gadawara Chhindwara Beyond 25 Km 3.11
34 Construction of 100 Mtr. cement concrete road at village Baghi of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Baghi Chhindwara Beyond 25 Km 3.12
35 Construction of Cement Concrete Road 425 Mtrs at Village Ambada.
INFRDCC Pench Ambada Chhindwara Within 25 Km 10.23
36 Construction of Cement Concrete Road 600 Mtrs from Mohan Colliery to Hinglaj Main road. Village Ambada
INFRDCC Pench Ambada Chhindwara Within 25 Km 14.14
37 Construction of Cement Concrete Road 600 Mtrs. & 150 Mtrs Ward no. 5,12,13,14, &20 at Grampanchayata Rawanwara Block parasia
INFRDCC Pench Rawanwara Ward No. 5,12,13,14,&
15 Chhindwara Within 25 Km 22.13
38 Construction of 350 Mtr Cement Concrete Road at Ward no. 14 Sanjay Rai House to Old Rly Station at
INFRDCC Pench Barkui Ward no.
14 Chhindwara Within 25 Km 7.55
179
WCL'S CSR ACTIVITIES AT A GLANCE 2013 - 14 SL NO
CSR ACTIVITIES WORK CODE AREA
VILLAGE NAME
DISTRICT
Activities Within 25
Kms/Beyond 25 Kms
EXP.INCURRED IN 13-
14(Fig.in Rs Lakhs)
Barkui
39 Constrtuction of 425 Cement Concrete road from Chandametta Kabristhan to Newton By Pass road under CSR at Pench Area
INFRDCC Pench Chandamenta Chhindwara Within 25 Km 9.63
40 Construction of 100 cement concrete road each at village Bansuri Kala, Burena Chatti and Karer of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Basurikala,Burena
Chatti, Karer Chhindwara Beyond 25 Km 0.35
41 Construction of 100 mtr. cement concrete road at each village Kachanara and Khantara of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Kachanara, Khantara
Chhindwara Beyond 25 Km 6.14
42 Construction of 100 Mtrcement concrete road each at village Tinasi, Charu Dhana and Khirda (Harrai Block) under CSR at Pench Area Parasia
INFRDCC Pench Tinasi, Charu
Dhana & Khirda Chhindwara Beyond 25 Km 9.25
43 Construction of 100 Mtr cement concrete road each at village Madai, Bargi and Bani of (Harrai Block) under CSR at Pench Area Parasia
INFRDCC Pench Madai,Bargi,&Ban
i Chhindwara Beyond 25 Km 9.40
44 Construction of Rang Manch at Chandan Gaon Housing Board Colony of Chhindwara against CSR Activity of Pench Area” (Retender)
INFRGM Pench Chandangaon Chhindwara Within 25 Km 1.73
45 Construction of Rang Manch at Barabone ( Rajdhana) village of Harrai Block Parasia
INFRGM Pench Barabone (Rajdhana
Chhindwara Beyond 25 Km 0.27
46 Construction of Rang Manch under CSR at village Dhokhera Harrai Block of Pench Area Parasia
INFRGM Pench Dhokhera Chhindwara Beyond 25 Km 1.79
47 Construction of Rang Manch at village Pipariya Ghumani, Bandra, Kubai and Ghabai of Amarwada Block of Pench Area Parasia
INFRGM Pench Pipariya, Ghumani, Bandram Kubai &
Ghabai Chhindwara Beyond 25 Km 0.86
48 Construction of Manch at village Jhungawara, Dulara, Barahdhana and Chargaon of Amarwada Block of Pench Area Parasia
INFRGM Pench
Jhungawara, Dulara,
Barahdhana & Chargaon
Chhindwara Beyond 25 Km 4.06
49 Construction of Manch at village Babutola, Seja and Dhada of Amarada Block of Pench Area Parasia
INFRGM Pench Babutola, Seja &
Dhada Chhindwara Beyond 25 Km 2.20
180
WCL'S CSR ACTIVITIES AT A GLANCE 2013 - 14 SL NO
CSR ACTIVITIES WORK CODE AREA
VILLAGE NAME
DISTRICT
Activities Within 25
Kms/Beyond 25 Kms
EXP.INCURRED IN 13-
14(Fig.in Rs Lakhs)
50 Construction of Rangh Manch at village Babai, Gadachota, Diwangaon of Amarwada Block of Pench Area Parasia
INFRGM Pench Babai,
Gadachota,Chimou,
Chhindwara Beyond 25 Km 1.99
51
Construction of Rang Manch under CSR at village Hadai, Ojhal dhana (Kareli) and Chilak Harrai Block of Pench Area Parasia INFRGM Pench
Hadai, Ojhal Dhana, & Chilak
Chhindwara Beyond 25 Km 2.17
52 Const. of Rang Manch under CSR at Village , Dendu, Chorasi, Dungaria of Harrai Block under Pench Area INFRGM Pench
dendu, Chorasi, Dungaria
Chhindwara Beyond 25 Km 3.65
53
Construction of Rang Manch under CSR at Village Barsalia (Mahulkuhi), Nabalpur (Haranbhata), Bhond (Khotapani) and Siajhiri (Kokarpani) of Harrai Block under Pench Area
INFRGM Pench Barsalia, Nabalpur, Bhond & Siajhiri
Chhindwara Beyond 25 Km 6.19
54 Const. of Rang Manch under CSR at Village Pati Pathara, Ghogartola (Dharmi) and Gorpani of Harrai Block under Pench Area
INFRGM Pench Pati, Pathara,
Ghogartola(Dharmi) & Gorpani
Chhindwara Beyond 25 Km 3.16
55 Construction of Manch at village Tednimal and Bhajia of Amarwada Block of Pench Area Parasia
INFRGM Pench Tednimal &Bhajia Chhindwara Beyond 25 Km 3.65
56
Const. of Rang Manch under CSR at Village Tuipani (Partapur), Gadagad (Mudia) Tendu Khera (Patania), Bhaisakala (Paradbhata) of Harrai Block under Pench Area
INFRGM Pench
Tuipani, Tendukhera
,Gadagad,Bhaisakala
Chhindwara Beyond 25 Km 3.69
57 Construction of Manch at village Mohalibharat, Chui, Badela khami and Kekra of Amarwada Block of Pench Area Parasia
INFRGM Pench Mohalibharat,Chui,
Badela Khami & Kekra
Chhindwara Beyond 25 Km 6.96
58 Const. of Rang Manch under CSR at Village Digdahar, Nikahi, Pandu and Balusar (Chilak) of Harrai Block under Pench Area
INFRGM Pench Digdhar, Nikahi,
Pandu & Balusar(Chilak)
Chhindwara Beyond 25 Km 6.78
59 Const. of Rang Manch under CSR at village surala, Khapa, Khirkatala (Basuriakala) and Jhanda (Kokanpat) of Harari Block under Pench Area
INFRGM Pench Surala, Khapa, Khirkatala &
Jhanda Chhindwara Beyond 25 Km 6.76
181
WCL'S CSR ACTIVITIES AT A GLANCE 2013 - 14 SL NO
CSR ACTIVITIES WORK CODE AREA
VILLAGE NAME
DISTRICT
Activities Within 25
Kms/Beyond 25 Kms
EXP.INCURRED IN 13-
14(Fig.in Rs Lakhs)
(Retender)
60 Construction of Manch at village Chikhlibala, Chandan Gaon, Dungaria Raiat And Ghugarla Kala of Amarwada Block of Pench Area Parasia
INFRGM Pench
Chikhibala,Chandan Gaon, Dungaria Raiat & Ghugarla
Kala
Chhindwara Beyond 25 Km 6.94
TOTAL :- 257.63
MISCELLENIOUS 61 Advance to NBCC MISC Pench
Jhurremal Hanuman Mandir
Chhindwara Within 25 Km 50.75
TOTAL :- 50.75 GRAND TOTAL :- 314.73
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs)
EDUCATION 1
Const. Of 2 no. Class room for school building at Rahiwada village
EDNCR Pench Rahiwada Chhindwara Within 25 Km 6.85
TOTAL :- 6.85
HEALTH CARE
2 Construction of culvert on the river at Urdhan Dhana village under Nehariya Sub Area
INF CVT/ RP Pench Urdhan Dhana
Chhindwara Within 25 Km 5.84
3 Construction of hume pipe culvert in between Chandametta to INF CVT/ RP Pench Bhamori Chhindwara Within 25 Km 2.82
182
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs) Bhamori road under CSR work, Pench Area
4 Const. Of 200 meter boundary wall for Sports field at Chhawadi kala.
INFBW Pench Chhawadi
Kala Chhindwara Within 25 Km 4.91
5 Const. Of Community hall at Sonapapari village INFCH Pench Sonapapri Chhindwara Within 25 Km 6.19 6 Const. Of community hall at Ridhora Village INFCH Pench Righora Chhindwara Within 25 Km 5.17 7 Const. of waiting hall at cremation place at EDC INFCMT Pench EDC Chhindwara Within 25 Km 2.45 8 Const. Of cement concret pavement at Umarhar village INFOW Pench Umarhar Chhindwara Within 25 Km 11.99 9 Const. Of 100 mtr. CC road at Dighawani INFRDCC Pench Dighawani Chhindwara Within 25 Km 3.07 10 Const. Of 100 mtr. CC road at Baghbardia village INFRDCC Pench Baghbardia Chhindwara Within 25 Km 2.98 11 Const. Of 100 mtr. CC road at Sahpani village INFRDCC Pench Sahpani Chhindwara Within 25 Km 0.13 12 Const. Of 150 mtr. CC road at Darbai village INFRDCC Pench Darbai Chhindwara Within 25 Km 3.54 13 Const. Of 100 mtr. CC road at Tendukheda village. INFRDCC Pench Tendukheda Chhindwara Within 25 Km 3.12 14 Const. Of 100 mtr. CC road at Marai village INFRDCC Pench Marai Chhindwara Within 25 Km 2.90
15 Const. Of CC road Ward No. 6 to Nagar Palika School.Parasia
INFRDCC Pench Parasia Chhindwara Within 25 Km 5.19
16 Const. Of CC road Ward No.11 Newton Chikhli INFRDCC Pench Newton Chikhli
Chhindwara Within 25 Km 5.00
17 Const, of 200 mtr. CC road from the house of Kundan to the house of Ibrahim, Eklehra. Ward No. 6
INFRDCC Pench Eklehra Chhindwara Within 25 Km 0.12
18 Const.of 100 mtr. CC road at Bhajipani, Parasia. INFRDCC Pench Bhajipani Chhindwara Within 25 Km 3.15
19 Construction of cement concrete road under CSR for Ridhora Village under Pench Area.
INFRDCC Pench Ridhora Chhindwara Within 25 Km 5.46
20 Construction of 100 mtrs cement concrete road at Chhitri Village under CSR. Pench Area
INFRDCC Pench Chhitri Chhindwara Within 25 Km 3.21
21 Const. Of C.C. Road railway track to Mata Mandir ward no.17
INFRDCC Pench Ward No. 17 Chhindwara Within 25 Km 9.46
22 Const. Of 200 meter C.C. Road at ward no.3 main road to Hanuman Mandir Ambara
INFRDCC Pench Ambara Chhindwara Within 25 Km 4.35
23 Construction of cement concrete road at Bhamori Village under CSR head Pench Area
INFRDCC Pench Bhamori Chhindwara Within 25 Km 4.98
24 Construction of 60 mtr. cement concrete road at Newton by INFRDCC Pench Jatachapper Chhindwara Within 25 Km 2.26
183
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs) pass road at Jatachapper under CSR work at Pench Area
25 Construction of cement concrete road from PWD main road Chandametta to Ravishankar Vishwakarma ward no.5 at Newton, Pench Area
INFRDCC Pench Vishwakarma Ward No. 5
Chhindwara Within 25 Km 2.60
26 Construction of cement concrete road from the house of Shri Ganesh to Shri Sanjay Dehariya ward no. 2 at Newton under CSR at Pench Area Parasia
INFRDCC Pench Newton Ward
No. 2 Chhindwara Within 25 Km 4.28
27 Construction of 100 mtrs cement concrete road at Shivpuri Village under Shivpuri Sub Area
INFRDCC Pench Shivpur Chhindwara Within 25 Km 2.73
28 Tarring of approch road at Sirgora village INFRDWBM Pench Sirgora Chhindwara Within 25 Km 6.32
29 Const. Of C.C Road Newton Jatachhapa by pass road with protection wall at Newton under CSR at Pench Area.
INFRDWBM Pench Newton Chhindwara Within 25 Km 3.21
30 Construction of Chabutra at Karaghat Chota Village Chhindwara Blockunder CSR Activity of Pench Area.
INFCBT/CPL Pench Karaghat
Chota Chhindwara Within 25 Km 0.86
31 Construction of Chabutra at Thuniya Bhand Village Chhindwara Block under CSR Activity of Pench Area
INFCBT/CPL Pench Thuniya Bhand
Chhindwara Within 25 Km 0.84
32 Construction of Chabutra at Matkuli Village Chhindwara Block under CSR Activity of Pench Area
INFCBT/CPL Pench Matkuli Chhindwara Within 25 Km 0.84
33 Construction of Chabutra at Village Matkuli Chhindwara Block under CSR Activity of Pench Area
INFCBT/CPL Pench Matkuli Chhindwara Beyond 25 Km 0.93
34 Construction of community hall at Lahgadua block Chhindwara under CSR at Pench Area
INFCH Pench Lahgadua Chhindwara Within 25 Km 5.37
35 Construction of community hall at Sarra Village Block Chhindwara under CSR at Pench Area
INFCH Pench Sarra Chhindwara Within 25 Km 3.81
36 Construction of community hall at Village Bargi Block Harrai of Pench Area
INFCH Pench Bargi Chhindwara Beyond 25 Km 7.24
37 Construction of community hall at Village SAJWA, Block Amarwada of Pench Area
INFCH Pench Sajwa Chhindwara Beyond 25 Km 7.22
38 Construction of community hall at Village Mandan Garh, Block Amarwada of Pench Area
INFCH Pench MandanGarh Chhindwara Beyond 25 Km 1.83
39 Providing barbed wire fencing for Mokhsdham at Harrai INFCMT Pench Harrai Chhindwara Beyond 25 Km 2.28
184
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs) block under CSR at Pench Area.
40 Construction of Drain at Sonpur of Chhindwara Block under CSR Activity Pench Area
INFDRN Pench Sonpur Chhindwara Within 25 Km 2.22
41 Construction of Drain at Karaboh of Chhindwara Block under CSR Activity Pench Area
INFDRN Pench Karaboh Chhindwara Within 25 Km 2.22
42 Construction of drain at Malhanwara Bharia Mohalla of Chhindwara block under CSR at Pench Area
INFDRN Pench Malhanwara
Bharia Chhindwara Within 25 Km 1.90
43 Construction of Drain at Jhanda of Chhindwara under CSR at Pench Area.
INFDRN Pench Jhanda Chhindwara Within 25 Km 1.41
44 Construction of drain from the house of Shri Sadan to house of Shri Prakash Sahu at Imlikhera Sadan at Chhindwara under CSR at Pench Area
INFDRN Pench Imlikhera
Sada Chhindwara Within 25 Km 2.65
45 Construction of drain at Soma dhana at Chhindwara Block under CSR Activity of Pench Area
INFDRN Pench Soma Dhana Chhindwara Within 25 Km 2.37
46 Construction of 100 metre cement concrete road at Thuniya Udana Village of Chhindwara Block of Pench Area
INFRDCC Pench Thuniya Udana
Chhindwara Within 25 Km 2.28
47 Construction of 100 metre cement concrete road at Poama Village of Chhindwara Block of Pench Area
INFRDCC Pench Poama Chhindwara Within 25 Km 2.36
48 Construction of 100 metre cement concrete road at Partala Village of Chhindwara Block of Pench Area
INFRDCC Pench Partala Chhindwara Within 25 Km 2.36
49 Construction of 100 metre cement concrete road at Bhanadei Village of Chhindwara Block of Pench Area
INFRDCC Pench Bhanadei Chhindwara Within 25 Km 2.47
50 Construction of 100 metre cement concrete road at Bhaisadand Village of Chhindwara Block of Pench Area
INFRDCC Pench Bhaisadand Chhindwara Within 25 Km 2.40
51 Construction of 100 metre cement concrete road at Khapabhat Village of Chhindwara Block of Pench Area
INFRDCC Pench Khapabhat Chhindwara Within 25 Km 3.02
52 Construction of 100 metre cement concrete road at Sonakhar Village of Chhindwara Block of Pench Area
INFRDCC Pench Sonakhar Chhindwara Within 25 Km 2.34
53 Construction of 100 metre cement concrete road at each Village Saraswada, Boriya, Atarwada (under CSR) of
INFRDCC Pench Saraswada,B
oriya, Chhindwara Within 25 Km 6.91
185
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs) Chhindwara Block at Pench Area Atarwada
54 Construction of 100 metre cement concrete road at each village Khairibhopal, Seonipranmoti, Lohar dhana, & Moyadeyi of Chhindwara Block at Pench Area
INFRDCC Pench
Khairibhopal, Seonipranmoti,Lohardhana,
Moyadevi
Chhindwara Within 25 Km 9.77
55 Construction of 100 C.C. road under CSR at Noniakarbal village of Chhindwara Block
INFRDCC Pench Noniakarbal Chhindwara Within 25 Km 4.70
56 Construction of cement concrete road at Bangaon and Chandangaon (200 meters length each) under CSR at Pench Area
INFRDCC Pench Bangaon, Chandangaon
Chhindwara Within 25 Km 12.69
57 Construction of 100 mtr. cement concrete road under CSR from the house of Moti to Shri Mahesh at Meghaseoni of Chhindwara block at Pench Area
INFRDCC Pench Meghaseoni Chhindwara Within 25 Km 3.21
58 Construction of 100 metre cement concrete road at Kukrajagat at Chhindwara under CSR head of Pench Area
INFRDCC Pench Kukrajagat Chhindwara Within 25 Km 2.60
59 Construction of 100 meter cement concrete road at Sarna Village of Chhindwara Block of Pench Area
INFRDCC Pench Sarna Chhindwara Within 25 Km 2.34
60 Construction of 100 metre Cement concrete Road at Kotalbarri Village of Chhindwara Block of Pench Area
INFRDCC Pench Kotalbarri Chhindwara Within 25 Km 2.31
61 Construction of 100 metre cement concrete road at Ramgadi of Chhindwara Block of Pench Area
INFRDCC Pench Ramgadi Chhindwara Beyond 25 Km 2.43
62 Construction of 100 meter cement concrete road at Medkital of Chhindwara Block of Pench Area
INFRDCC Pench Medkital Chhindwara Beyond 25 Km 2.47
63 Construction of 100 metre cement concrete road at Singodi Village of Amarawada Block of Pench Area
INFRDCC Pench Singodi Chhindwara Beyond 25 Km 2.31
64 Construction of 100 mtr. cement concrete road at Ghogri Village of Amarawada block of Pench Area.
INFRDCC Pench Ghogri Chhindwara Beyond 25 Km 3.12
65 Construction of 100 mtr. cement concrete road at Lakhanwada Village of Amarawada block of Pench Area.
INFRDCC Pench Lakhanwada Chhindwara Beyond 25 Km 2.93
66 Construction of 100 mtr. cement concrete road at Khamihira Village of Amarawada block of Pench Area.
INFRDCC Pench Khamihira Chhindwara Beyond 25 Km 3.03
186
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs)
67 Construction of 100 mtr. cement concrete road at Pataniya Village of Amarawada block of Pench Area.
INFRDCC Pench Pataniya Chhindwara Beyond 25 Km 3.11
68 Construction of 100 mtr. cement concrete road at Rahiwara Village of Amarawada block of Pench Area.
INFRDCC Pench Rahiwara Chhindwara Beyond 25 Km 2.78
69 Construction of 100 mtr. cement concrete road at Kharibhutai Village of Chhindwara block of Pench Area.
INFRDCC Pench Kharibhutai Chhindwara Beyond 25 Km 3.11
70 Construction of 100 mtr. cement concrete road at Bineki Village of Amarawada block of Pench Area.
INFRDCC Pench Beniki Chhindwara Beyond 25 Km 2.87
71 Construction of 100 mtr. cement concrete road at Ponar Village of Amarawada block of Pench Area.
INFRDCC Pench Ponar Chhindwara Beyond 25 Km 2.56
72 Construction of 100 mtr. cement concrete road at Bakamukama Village of Amarawada block of Pench Area.
INFRDCC Pench Bakamukama Chhindwara Beyond 25 Km 2.52
73 Construction of 100 mtr. cement concrete road at Chuyi Village of Amarawada block of Pench Area.
INFRDCC Pench Chuyi Chhindwara Beyond 25 Km 2.90
74 Construction of 100 mtr. cement concrete road at Jamuniya Village of Chhindwara block of Pench Area.
INFRDCC Pench Jamuniya Chhindwara Beyond 25 Km 3.13
75 Construction of 100 mtr. cement concrete road at Marahi Village of Chhindwara block of Pench Area.
INFRDCC Pench Marahi Chhindwara Beyond 25 Km 3.06
76 Construction of 100 mtr. cement concrete road at Sihora Village of Chhindwara block of Pench Area.
INFRDCC Pench Sihora Chhindwara Beyond 25 Km 3.12
77 Construction of 100 meter cement concrete road at Karahdol of Amarwada Block of Pench Area.
INFRDCC Pench Karahdol Chhindwara Beyond 25 Km 2.95
78 Construction of 100 meter cement concrete road at Rani Khakra Chourai of Amarwada Block of Pench Area
INFRDCC Pench Rani Khakra Chhindwara Beyond 25 Km 2.97
79 Construction of 100 metre cement concrete road at Chaniyakala of Chhindwara Block of Pench Area
INFRDCC Pench Chaniyakala Chhindwara Beyond 25 Km 3.13
80 Construction of 100 meter cement concrete road at Rani Kamath of Amarwada Block of Pench Area
INFRDCC Pench Rani Kamath Chhindwara Beyond 25 Km 3.12
81 Construction of 100 meter cement concrete road at Jamuniya Bhura of Amarwada block of Pench Area
INFRDCC Pench Jamuniya
Bhura Chhindwara Beyond 25 Km 3.16
82 Construction of 100 meter cement concrete road at Gadathana INFRDCC Pench Gadathana Chhindwara Beyond 25 Km 3.06
187
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs) of Amarwada Block of Pench Area
83 Construction of 100 meter cement concrete road at Pipriya Virsa of Chhindwara Block of Pench Area
INFRDCC Pench Pipriya Virsa Chhindwara Beyond 25 Km 3.03
84 Construction of 100 meter cement concrete road at Khapa Mithekha of Chhindwara Block of Pench Area
INFRDCC Pench Khapa
Mithekha Chhindwara Beyond 25 Km 3.05
85 Construction of 100 meter cement concrete road at Kosmi of Amarwada Block of Pench Area
INFRDCC Pench Kosmi Chhindwara Beyond 25 Km 3.14
86 Construction of 100 metre cement concrete road at Mohali Bharat Village of Amarawada Block of Pench Area
INFRDCC Pench Mohali Bharat
Chhindwara Beyond 25 Km 3.01
87 Construction of 100 Mtr cement concrete road at village Batkakhapa of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Batkakhapa Chhindwara Beyond 25 Km 3.12
88 Construction of 100 metre cement concrete road at each Village MORKHA & BICHHUA of Pench Area Harrai Block
INFRDCC Pench Morkha & Bichhua
Chhindwara Beyond 25 Km 6.23
89 Construction of 100 Mtr cement concrete road at village Bhamori of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Bhamori Chhindwara Beyond 25 Km 3.16
90 Construction of 100 mtr. cement concrete road at Markawada of Amarwada Block under CSR at Pench Area
INFRDCC Pench Markawada Chhindwara Beyond 25 Km 3.14
91 Construction of 100 mtr. cement concrete road at Lahgadua of Amarwada Block of Pench Area
INFRDCC Pench Lahgadua Chhindwara Beyond 25 Km 2.93
92 Construction of 100 meter cement concrete road at Ghughrla Khurd of Amarwada Block of Pench Area
INFRDCC Pench Ghughrla
Khurd Chhindwara Beyond 25 Km 3.05
93 Construction of 100 meter cement concrete road at Lakdie Jamodi of Chhindwara Block of Pench Area
INFRDCC Pench Lakdie Jamodi
Chhindwara Beyond 25 Km 1.59
94 Construction of 100 meter cement concrete road at Lakdie Jamodi of Chhindwara Block of Pench Area
INFRDCC Pench Lakdie Jamodi
Chhindwara Beyond 25 Km 1.59
95 Construction of 100 Mtr cement concrete road at village Nandram Dhana, Titori and Ghorawari (Harrai Block) under CSR at Pench Area Parasia
INFRDCC Pench Nandram
Dhana,Titori, Ghorawari
Chhindwara Beyond 25 Km 9.39
96 Construction of 100 cement concrete road at village Ankhawadi, Kamtha and Karaghat (Harrai Block) under CSR at Pench Area Parasia
INFRDCC Pench Ankhawadi, Kamtha & Karaghat
Chhindwara Beyond 25 Km 9.47
188
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs)
97 Construction of 100 cement concrete road at village Sajwa, Karai and Papda (Harrai Block) under CSR at Pench Area Parasia
INFRDCC Pench Sajwa, Karai
& Papda Chhindwara Beyond 25 Km 9.37
98 Construction of 100 meter cement concrete road at Sakarwada of Amarwada Block of Pench Area
INFRDCC Pench Sakarwada Chhindwara Beyond 25 Km 2.97
99 Construction of 100 meter cement concrete road at Bhajipani of Amarwada Block of Pench Area.
INFRDCC Pench Bhajipani Chhindwara Beyond 25 Km 2.94
100 Construction of 100 meter cement concrete road at Putarra of Amarwada Block of Pench Area
INFRDCC Pench Putarra Chhindwara Beyond 25 Km 2.93
101 Construction of 100 meter cement concrete road at Richheda of Amarwada Block of Pench Area
INFRDCC Pench Richheda Chhindwara Beyond 25 Km 3.16
102 Construction of 100 meter cement concrete road at Barahhira of Amarwada Block of Pench Area
INFRDCC Pench Barahhira Chhindwara Beyond 25 Km 1.88
103 Construction of 100 mtr. cement concrete road at Pipriyamanu of Amarwada Block at Pench Area
INFRDCC Pench Pipriyamanu Chhindwara Beyond 25 Km 2.57
104 Construction of 100 mtr. Cement concrete road at village Dhobighat Visarjan Harrai under CSR at Pench Area.
INFRDCC Pench Dhobighat Visarjan
Chhindwara Beyond 25 Km 3.14
105 Construction of 100 meter cement concrete road at Chargaon Pralahad of Chhindwara Block of Pench Area
INFRDCC Pench Chargaon Pralahad
Chhindwara Beyond 25 Km 2.35
106 Construction of 100 metre cement concrete road at Gangiwara of Chhindwara Block of Pench Area
INFRDCC Pench Gangiwara Chhindwara Beyond 25 Km 2.37
107 Construction of 100 meter cement concrete Road at Nayegaon of Chhindwara Block of Pench Area
INFRDCC Pench Nayegaon Chhindwara Beyond 25 Km 2.95
108 Construction of 100 Mtr cement concrete road each at village Singodi Dhadhra and Bhaira of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Singodi ,Dhadra, Bhaira
Chhindwara Beyond 25 Km 9.40
109 Construction of 100 Mtr. cement concrete road each at village Dharmi, Kohpani and Karer of (Harrai Block) under CSR at Pench Area Parasia
INFRDCC Pench Dharmi,Kohp
ani, Karer Chhindwara Beyond 25 Km 9.38
110 Construction of 100 meter cement concrete road at Pipriya Bharti of Amarwada Block of Pench Area
INFRDCC Pench Pipriya Bharti Chhindwara Beyond 25 Km 3.04
189
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs)
111 Construction of 100 meter cement concrete road at Ghuriya of Amarwada Block of Pench Area
INFRDCC Pench Ghuriya Chhindwara Beyond 25 Km 3.04
112 Construction of 100 cement concrete road each at village Bansuri Kala, Burena Chatti and Karer of Harrai Block under CSR at Pench Area Parasia
INFRDCC Pench Basurikala,Burena Chatti,
Karer Chhindwara Beyond 25 Km 8.87
113 Construction of 100 meter cement concrete road at Dhodakuhi of Amarwada Block of Pench Area
INFRDCC Pench Dhodakuhi Chhindwara Beyond 25 Km 3.14
114 Construction of 100 meter cement concrete road at Jhirlinga of Chhindwara Block of Pench Area
INFRDCC Pench Jhirlinga Chhindwara Beyond 25 Km 3.00
115 Construction of 100 meter cement concrete road at Patharkati of Amarwada Block of Pench Area
INFRDCC Pench Patharkati Chhindwara Beyond 25 Km 3.12
116 Construction of 100 meter cement concrete road at Chaneri of Amarwada Block of Pench Area
INFRDCC Pench Chaneri Chhindwara Beyond 25 Km 3.05
117 Construction of 100 meter cement concrete road at Bhurkum of Amarwada Block of Pench Area
INFRDCC Pench Bhurkum Chhindwara Beyond 25 Km 3.14
118 Construction of 100 mtr. cement concrete road at Dhaturiya Village of Amarwada block of Pench Area.
INFRDCC Pench Dhaturiya Chhindwara Beyond 25 Km 3.12
119 Construction of 100 Mtr Cement Concrete road 100 Mtrs at Ward No. 12 Neuton Chickli Block-Parasia
INFRDCC Pench Newton
Chickli Ward no. 12
Chhindwara Beyond 25 Km 2.57
120 Construction of Rang Manch at Bangaon village of Chhindwara Blockagainst CSR Activity of Pench Area
INFRGM Pench Bangaon Chhindwara Within 25 Km 1.69
121 Construction of 3 No.Rang Manch under CSR at village Dorli, Piparia Chata and Deori (piparpani) Harrai Block of Pench Area Parasia
INFRGM Pench Dorli, Piparia
Chata & Deori
Chhindwara Within 25 Km 4.66
122 Construction of Rang Manch at Barabone ( Rajdhana) village of Harrai Block Parasia
INFRGM Pench Barabone (Rajdhana
Chhindwara Beyond 25 Km 1.42
123 Construction of Manch at village Kopakhera, Khamraadku, Simriya and Jhagraboh of Amarwada Block of Pench Area Parasia
INFRGM Pench
Kopakhera,Khamradku, Simriya & Jhagraboh
Chhindwara Beyond 25 Km 6.65
190
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs)
124 Construction of Manch at village Rangpur, Umariya, Charankhapa and Baheriya of Amarwada Block of Pench Area Parasia
INFRGM Pench
Rangpur, Umariya,
Charankhapa & Baheriya
Chhindwara Beyond 25 Km 6.75
125 Construction of Rang Manch at village Pipariya Ghumani, Bandra, Kubai and Ghabai of Amarwada Block of Pench Area Parasia
INFRGM Pench
Pipariya, Ghumani Bandram Kubai & Ghabai
Chhindwara Beyond 25 Km 6.19
126 Construction of Manch at village Jhungawara, Dulara, Barahdhana and Chargaon of Amarwada Block of Pench Area Parasia
INFRGM Pench
Jhungawara, Dulara,
Barahdhana & Chargaon
Chhindwara Beyond 25 Km 2.49
127 Construction of Manch at village Babutola, Seja and Dhada of Amarada Block of Pench Area Parasia
INFRGM Pench Babutola,
Seja & Dhada Chhindwara Beyond 25 Km 2.74
128 Construction of Rangh Manch at village Babai, Gadachota, Chimoua and Diwangaon of Amarwada Block of Pench Area Parasia
INFRGM Pench
Babai, Gadachota,C
himou, Diwangaon
Chhindwara Beyond 25 Km 2.67
129
Construction of Rang Manch under CSR at village Hadai, Ojhal dhana (Kareli) and Chilak Harrai Block of Pench Area Parasia
INFRGM Pench Hadai, Ojhal
Dhana, & Chilak
Chhindwara Beyond 25 Km 2.86
130 Const. of Rang Manch under CSR at Village Nagdamela, Dendu, Chorasi, Dungaria of Harrai Block under Pench Area INFRGM Pench
Nagdamela, dendu,
Chorasi, Dungaria
Chhindwara Beyond 25 Km 1.46
131 Construction of Rang Manch under CSR at village Dhokhera Harrai Block of Pench Area Parasia
INFRGM Pench Dhokhera Chhindwara Beyond 25 Km 0.25
132 Const. of Rang Manch under CSR at Village Tuipani (Partapur), Gadagad (Mudia) Tendu Khera (Patania),
INFRGM Pench Tuipani,
Tendukhera Chhindwara Beyond 25 Km 2.92
191
WCL'S CSR ACTIVITIES AT A GLANCE 2012 - 13 SL NO NAME OF CSR ACTIVITY CODE Area VILLAGE
NAME District ACTIVITIES
WITHIN /BEYOND 25
Kms.
EXP. INCURRED IN 2012-13(Fig.in
Rs Lakhs) Bhaisakala (Paradbhata) of Harrai Block under Pench Area ,Gadagad,Bha
isakala TOTAL :- 477.17
MISCELLENIOUS 133 Expenditure for Welfare Plan Tribal MISC Pench MandanGarh Chhindwara Within 25 Km 0.10 TOTAL :- 0.10
WATER SUPPLY AND DRINKING WATER
134 100 Mtr. depth hand pump at Jhurrey gram ward No. 5 WSHP Pench Jhurrey Chhindwara Within 25 Km 0.19 135 100 Mtr. depth hand pump at Shivpuri cremation site WSHP Pench Shivpuri Chhindwara Within 25 Km 0.21 136 100 Mtr. Depth hand pump at Urdhan gram.2. Nos. WSHP Pench Urdhan Chhindwara Within 25 Km 0.41
137 Drilling of 125 mm nominal dia. Bore bole 100 mtr. Depth for hand pump at Mokha dham Gandhi Chowk Harrai under CSR
WS BW/SP/TW
Pench Mokha Dham Chhindwara Beyond 25 Km 0.91
138 Drilling of 125 mm nominal dia. Bore bole 100 mtr. Depth for hand pump at Pipariya Chata Harrai block under CSR
WS BW/SP/TW
Pench Pipariya Chata
Chhindwara Beyond 25 Km 0.96
139 Drilling of 125 mm nominal dia. Bore bole 100 mtr. Depth for hand pump at Kotbarra Harrai block under CSR
WS BW/SP/TW
Pench Kotberra Chhindwara Beyond 25 Km 0.96
140 Drilling of 125 mm nominal dia. Bore bole 100 mtr. Depth for hand pump at Choti basoriya Harrai block under CSR
WS BW/SP/TW
Pench Choti
Basoriya Chhindwara Beyond 25 Km 0.91
141 Drilling of 125 mm nominal dia. Bore bole 100 mtr. Depth for hand pump at Chotar tola at Harrai block under CSR
WS BW/SP/TW
Pench Chotal Tola Chhindwara Beyond 25 Km 0.99
TOTAL :- 5.54 GRAND TOTAL :- 489.66
192
TOPO PLAN
193