EGLINTON CROSSTOWN CONSTRUCTION UPDATE
CENTRAL OPEN HOUSE | MARCH 23, 2020
WELCOME
Our Central Open House will feature the following stations:
• Chaplin
• Avenue
• Eglinton
• Mount Pleasant
• and Leaside
2
EGLINTON CROSSTOWN LRT PROJECT
• A 19-kilometre route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface in east • 15 underground stations and 10 surface stops • A maintenance and storage facility • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
PROJECT PROGRESS
Maintenance and Storage Facility complete
12 vehicles received
50% of track installed
Mining complete at Laird and Oakwood stations
Deep excavation underway or complete at all stations
2019 PROJECT HIGHLIGHTS
FIRST LIGHT RAIL VEHICLE ON MAINLINE
7
8
9
TTC STATION UNDERPINNING
CHAPLIN STATION RENDERINGS
MAIN ENTRANCE SECONDARY ENTRANCE
PLATFORM TERTIARY ENTRANCE
CHAPLIN STATION: WHAT TO EXPECT
Year What to Expect
2019 Milestones • All station roof pours completed
Remaining Work for 2020
• Deep excavation and concrete works • Intersection closure for traffic bridge removal
• Traffic configuration changes • Installation of structural steel and panels at entrances
CHAPLIN STATION PROGRESS PHOTOS
DEEP EXCAVATION BENEATH THE STATION ROOF
MAIN ENTRANCE/DEEP EXCAVATION
AVENUE STATION RENDERINGS
Station Features Accessible main entrance
Covered & uncovered bicycle parking
Retail space in main entrance??
SECONDARY ENTRANCE
MAIN ENTRANCE
MAIN ENTRANCE INTERIOR
AERIAL VIEW
AVENUE STATION MINING PROGRESS
AVENUE STATION: WHAT TO EXPECT
Year What to Expect
2019 Milestone • Completion of final lining between the main and secondary entrances.
Remaining Work for 2020
• Completion of mining excavation in summer 2020. • Completion of concrete works at entrances.
• Completion of final lining works, including installation waterproofing,
rebar and formwork.
• Begin installation of structural steel and panels at entrances. • Begin implementation of Eglinton Connects.
AVENUE STATION PROGRESS PHOTOS
FINAL LINING WORKS FINAL LINING WORKS
EGLINTON STATION RENDERINGS
Station Features Accessible main entrance
Covered & uncovered bicycle parking
Retail space in main entrance??
LOBBY
PLATFORM
TTC SERVICE BUILDING (BERWICK AVE)
MAIN ENTRANCE
EGLINTON STATION: WHAT TO EXPECT
Year What to Expect
2019 Milestone • All pedestrian crosswalks open at Yonge Street and Eglinton Avenue
• TTC underpinning work started
Remaining Work for 2020
• Deep excavation
• Removal of tunnel boring machines
• TTC station underpinning • Construction of the south ventilation building at Berwick Avenue
• Construction of the north tunnel ventilation shaft
EGLINTON STATION PROGRESS PHOTOS
MAIN ENTRANCE DEEP EXCAVATION
MOUNT PLEASANT STATION RENDERINGS
MAIN ENTRANCE SECONDARY ENTRANCE
CONCOURSE PLATFORM
MOUNT PLEASANT STATION: WHAT TO EXPECT
Year What to Expect
2019 Milestone • Completion of shallow excavation and roof construction.
Remaining Work for 2020
• Deep excavation beneath the station roof and entrances.
• Reinstatement of utilities. • Concrete works which will form the walls of the station and entrances.
MOUNT PLEASANT STATION PROGRESS PHOTOS
MAIN ENTRANCE EXAVATION DEEP EXCAVATION SECONDARY ENTRANCE
LEASIDE STATION RENDERINGS
MAIN ENTRANCE PLATFORM
LOBBY SECONDARY ENTRANCE
LEASIDE STATION: WHAT TO EXPECT
Year What to Expect
2019 Milestone
• Completion of road decking • Completion of shallow excavation • Supported 1200mm watermain
Remaining Work for 2020
• Deep excavation, hauling, concrete works and material deliveries will continue on the surface through 2020.
• Periodic additional lane closures may be required to facilitate deliveries,
dewatering and concrete works. • Permanent works will continue into late 2020, including waterproofing,
formwork, rebar installation and concrete works. Concrete structure expected to be complete late 2020.
LEASIDE STATION PROGRESS PHOTOS
MAIN ENTRANCE SECONDARY ENTRANCE
SYSTEMS AND TRACK RENDERINGS
TRACTION POWER SUBSTATION 10 OVERHEAD CATENARY
SYSTEM
SYSTEMS AND TRACK: WHAT TO EXPECT
Year What to Expect
Remaining Work for 2020
• Track installation from Mount Dennis Station to Cedarvale Station and from Leaside Station to Kennedy Station
• Installation of traction power cables from Mount Dennis Station to
Cedarvale Station and from Laird Station to Kennedy Station • Tunnel lighting installation from West Portal to Chaplin Station and
from Mount Pleasant Station to Science Center Station
• Overhead Catenary System (OCS) installation from West Portal to Chaplin Station, Mount Pleasant Station to Science Center Station, and from Wynford Dr to Kennedy Station
• Traction power systems at Mount Dennis Station and Keelesdale Station will be operational
• Begin installation of major electrical equipment, including Supervisory Control and Data Acquisition (SCADA) cabinets and panels, communications infrastructure, field end devices, radio towers, signaling and train control infrastructure, and tunnel ventilation fans
SYSTEMS AND TRACK PROGRESS PHOTOS
OVERHEAD CATENARY SYSTEM AT WEST GUIDEWAY
TRACTION POWER SUB STATION 10 DELIVERY
COMMUNITY BENEFITS & INVESTMENT
• The Eglinton Crosstown LRT Project contractually requires the constructor, Crosslinx Transit Solutions Constructors (CTSC), to embed community benefits in their work, including ensuring that local communities and historically disadvantaged groups benefit directly from the province’s $5.3 billion investment
• We are committed to making the pathway to Professional, Administrative and
Technical (PAT) roles in the construction industry more accessible to people facing barriers to employment
• CTS has hired 152 people in PAT roles to date, as well as 133 apprentices and
journey persons from historically disadvantage and equity seeking groups
• We are committed to supporting small and medium sized businesses along the Eglinton corridor, businesses impacted by our construction, and social enterprises that create employment and training opportunities for people who face systemic barriers to employment
• CTS has spent $587,175.14 on social enterprises and more than $6 million at local businesses
31
THANK YOU!
• ?