Tank
Operations
Contract
1
EFCOG Supply Chain
Quality Task Team
Conference Call December 2014
Vince Grosso
Supply Chain Quality Chair
Tank
Operations
Contract
2
Overview
1. Upcoming Conferences / Workshops
2 . Industry / Suppl ier Issues
3 . In ter face Update
4 . Pro ject Updates
5 . Audi t Update
6 . Old / New Business
7 . D iscussion & Close Out
Tank
Operations
Contract
3
JSEP Access
• Any issues with access or use?
• In order to use MASL you will need an entrust account
• Does everyone have an entrust account?
– If not, contact your IT department
• Questions or problems, contact:
– Vince Grosso - [email protected]
– Bill Wingfield - [email protected]
Tank
Operations
Contract
4
Upcoming Conferences / Workshops
January - March 2015
Date Conference Title Location Website
January 26-30, 2015
Boiler, Pressure Vessel and Piping Technologies MasterClass Series (Texas)
Houston, Texas
https://www.asme.org/wwwasmeorg/media/ResourceFiles/Shop/Courses/ASMETrainingDevelopment/Webpage-MC-Series-BPV-Jan-2015.pdf
February 2-5, 2015
NQA-1 Lead Auditor Training - Charlotte
Charlotte, NC https://www.asme.org/products/courses/asme-nqa1-lead-auditor-training
March 15-19, 2015
Waste Management (WM) Conference 2015
Phoenix, AZ http://www.wmsym.org/
Tank
Operations
Contract
5
Upcoming Conferences / Workshops
April - June 2015
Date Conference Title Location Website
April 21-23, 2015
ASME NQA-1 Spring 2015 Meeting
Charlotte, NC http://calendar.asme.org/EventDetail.cfm?EventID=29686
April 26-May 1, 2015
Boiler, Pressure Vessel and Piping Technologies MasterClass Series (Colorado)
Colorado Springs, Colorado
https://www.asme.org/wwwasmeorg/media/ResourceFiles/Shop/Courses/ASMETrainingDevelopment/Webpage-MC-Series-Apr-2015.pdf
May 15-18, 2015
NQA-1 Lead Auditor Training - London, ENG
London, ENG https://www.asme.org/products/courses/asme-nqa1-lead-auditor-training
May 19-21, 2015
GIDEP New User Training Clinic - Tysons Corner, VA
Best Western Golden Sails Hotel in Long Beach, CA
http://www.gidep.org/events/clinic/clinic.htm
Tank
Operations
Contract
6
Industry Supplier Issues / Feedback
• Feedback from October meeting / Commercial Grade
Dedication Handbook Project
• Packaging Specialties Inc (PSI) Update
• Transition of Los Alamos site legacy environmental cleanup
work from NNSA to EM
• Request for Proposal for support services at the Oak Ridge
Transuranic Waste Processing Center (TWPC) estimated
contract value $100 Million - $300 Million
• JSEP Audit of Flanders
• Mueller Standard Copper Tube may not fully meet ASTM
dimensional requirements*
• AMO – NOI*
• EM Business Opportunities
• Others?
Tank
Operations
Contract
7
Mueller Standard Copper Tube
• Mueller Standard Copper Tube may not fully meet ASTM
dimensional requirements.
• Standard Tube will be provided unless Certified Tube is
clearly defined on the Purchase Order.
• When specified at order placement, Mueller Copper Tube
can supply Certified Tube to meet all requirements of the
current applicable ASTM specification, at an additional
cost.
• May affect copper tubing that is ink stamped as B88,
B280, B306, or B819 unless special purchasing
arrangements are made.
Tank
Operations
Contract
8
AMO – NOI
• The Advanced Manufacturing Office (AMO) posted a Notice
of Intent (NOI) entitled “Clean Energy Manufacturing
Innovation Institute on Smart Manufacturing: Advanced
Sensors, Controls, Platforms and Modeling for
Manufacturing.”
• Energy Department will lead this competition and addressing
gaps in the development of smart manufacturing technology
• Seeks to develop, demonstrate, and transition to industry
advanced sensing, instrumentation, monitoring, control, and
process optimization using both advanced hardware and
software platforms, as well as modeling and simulation
technologies, for industrial automation
• Emerging opportunity across U.S. manufacturing firms
Tank
Operations
Contract
9
EM Hosts Business Opportunity Forum
• There was a public forum on EM’s procurement process,
certification of cost and pricing data, & business opportunities
in the legacy nuclear cleanup program
• EM is expanding the use of fixed-priced procurements
• Previous EM fixed price/rate contracts have been used in
Oak Ridge, Tenn.; Moab, Utah; and Hanford, Washington
• Upcoming procurements include: analytical laboratory
services at Hanford’s 222-S lab; infrastructure support in
Paducah, Ky., and Portsmouth, Ohio; and the management
and operations of the Transuranic Waste Processing Center
in Oak Ridge
• EM’s Office of Acquisition and Project Management plans to
host the forum approximately each quarter
Tank
Operations
Contract
10
Interface Representative(s) Update
• EPWOG - Kronvall / Weaver
• Supply Chain Management Center - Biagioli
• Packaging Management Committee - Natali / Hawk
• EFCOG QE Task Team - Thompson
• EFCOG SQA Task Team - Williams
• ICPT - Bass
• NNSA
• EM
• Office of Science
• HSS
• Others??
Tank
Operations
Contract
11
Project Update (Supply Chain Contacts)
Task: SC-12-01
Project Manager: Cathy Nesser
• Action: Develop a comprehensive Supply Chain Quality Site,
Site contact, and Departmental list of Subject Matter Experts
from across the complex. The list should include National
Laboratories, NNSA, EM, and Science. Determine if the list is
to be controlled (through the supplier evaluation tool) or
publicly available (through a website or other means)
A. Phase 1 - QA Manager / Subject Matter Expert
B. Phase 2 - Engineering and Procurement Management
C. Phase 3 - This becomes a living document to ensure all
DOE sites have the opportunity to participate
Tank
Operations
Contract
12
Project Update (Non-NQA-1 Suppliers)
Task: SC-12-03
New Project Manager: TBD
Action: Work with Engineering Practices Work Group to
evaluate the feasibility of developing a standard set of
criteria for Commercial Grade Surveys and Suppliers
for Non-NQA-1 suppliers.
• Status Update:
Tank
Operations
Contract
13
Project Update (JSEP / MASL Integration)
Task: SC-12-04
Project Manager: Vince Grosso
• Action: Utilize a single tool for supplier quality
data.(MASL / JSEP Integration)
• Status Update:
Tank
Operations
Contract
14
Project Update (Supplier Base Increase)
Task: SC-12-08
Project Managers: Cathy Nesser (WIPP) & Bill Wingfield
(LANL)
Team Members: Leesa Brownell (KCP), Rich Brown (Y-12)
Action: Determine ways to grow the supplier base to support
upcoming Engineer, Procure, Construct Projects
– How can the Supplier Base be increased
Status Update:
• Still looking for a Project Manager
• Focus will be on growing supplier base
• Sponsor is EM-43
• Preparation for future projects
– NNSA & EM
Tank
Operations
Contract
15
Project Update (Packaging)
Task: SC-12-09
Project Manager: Vince Grosso & Ashok Kapoor
Team: DOE, NNSA, & Contractors
• Action: QA in DOT Type A Procurement Specifications for
the Complex.
– Work with the PMC to develop Procurement Specifications
and reduce quality assurance related issues concerning
commonly used DOT Type A containers (drums and boxes)
for packaging and transportation of solid and/or liquid
radioactive materials and waste complex-wide
Status Update:
Tank
Operations
Contract
16
Project Update (Packaging)
1. Joint EFCOG / PMC-QA Packaging CGD Team (M.
Bowers)
– Update
2. Joint EFCOG / PMC-QA Packaging Graded
Approach Team (R. Natali)
– Update
Tank
Operations
Contract
17
Project Update (Evaluation Program Plan)
Task: SC-14-01
Project Manager: Joe Fulghum (SRNS)
Team: Bill Wingfield (LANL), Leesa Brownell (KCP)
• Action: Revise the existing JSEP program plan and MASL
program plan to be an integrated JSEP-MASL Program
Plan and guidance document as part of the JSEP-MASL
integration process.
Status Update:
Tank
Operations
Contract
18
Project Update (CGD Handbook Training)
Task: SC-14-02
Project Manager: Cynthia Williams
Team: TBD
• Action: Evaluate / modify existing Commercial Grade
Dedication training in conjunction with the new DOE CGD
Handbook to provide consistent application of NQA-1
2008/2009a requirements.
Status Update:
Tank
Operations
Contract
19
Project Update (CGD Handbook)
Task: SC-14-02
Project Manager: TBD
Team: See Next Slide
• Action: Provide a DOE / NNSA Commercial Grade
Dedication Handbook with examples that clarify the
programmatic controls for consistent application of NQA-1
2008/2009a requirements.
Status Update:
• K/O meeting in December
• Next meeting 1/7/14 at 11 AM EST
• Need a Project Manager
Tank
Operations
Contract
20
Project Update (CGD Handbook)
Team
Sponsors: Debbie Rosano (AU-33) / Duli Agarwal (AU-33)
Team: Dennis Weaver (EPWOG) Marshall Bullock (EPWOG) Stephen O’Connor (SRR)
Karen Lesko (SRR) Dave Shugars (SRR) Cynthia Williams (SRNS)
Joe Fulghum (SRNS) Jon Allen (SRNS) Don Zinter (WRPS)
Mike Tipps (WRPS) Vince Grosso (WRPS) Jim Henry (Y-12)
Dean Shipley (Y-12) Rick Chester (Y-12) Bob Bailey (Y-12)
Alexis Hundertmark (AU-33) Bob Thompson (ICP) Jim Cudmore (ICP)
Bill Kerley (LANL) Dan Tepley (LANL) Laura Valdez (Pantex)
Gary Sooter (Pantex) Darlene Johnson (NNSS) Scott Spencer (CHPRC)
David Willford (BNI) Michael D. Mohundro (CB&I) Mark Maier (MOX)
John Wisniewski (MOX) Amy Ecclesine (LBNL) Steve Chalk (RL)
Tank
Operations
Contract
21
Audit Opportunities Update
(As of December 2014)
Tank
Operations
Contract
22
Audit Scheduling – Jan - Jun 2015
Supplier Website Lead
URS, Princeton, NJ (J57) http://www.urscorp.com/About_URS/index.php
TBD
GE-Hitachi Nuclear Energy Americas LLC, Canonsburg, PA (J35)
http://www.ge-energy.com/products_and_services/products/nuclear_energy/index.jsp
TBD
Consolidated Power Supply, Birmingham, AL (J34) http://www.consolidatedpower.com/
TBD
Skolnik, Chicago, IL (J30) http://www.skolnik.com/ TBD
Nuclear Logistics Inc., Fort Worth, TX (J25) http://www.nuclearlogistics.com/company
TBD
Nuclear Filter Technology (NFT), Golden, CO (J24) http://nuclearfilter.com/nucfil/ Hendrickson
Tank
Operations
Contract
23
Audit Scheduling – Jul - Dec 2015
Supplier Website Lead
Applied Technical Services, Marietta, GA (J114) http://www.atslab.com/ TBD
Babcock and Wilcox (B&W) Nuclear Operations Group, Inc., Lynchburg, VA (J17)
http://www.babcock.com/about/business_units/nuclear_operations_group/
TBD
Canberra Inc., Meriden, CT (J4) http://www.canberra.com/ C. Nesser
Tank
Operations
Contract
24
Audit Opportunities Update
• Any near team site needs?
Tank
Operations
Contract
25
Supply Chain Quality Webex Calls
2015 Supply Chain Quality Webex / Conference Call Schedule
Date EST CST MST PST
Jan 15 2015 11 AM 10 AM 9 AM 8 AM
Feb 19 2015 11 AM 10 AM 9 AM 8 AM
Mar 19 2015 11 AM 10 AM 9 AM 8 AM
Apr 16 2015 11 AM 10 AM 9 AM 8 AM
May 21 2015 11 AM 10 AM 9 AM 8 AM
Jun 18 2015 11 AM 10 AM 9 AM 8 AM
Jul 16 2015 11 AM 10 AM 9 AM 8 AM
Aug 20 2015 11 AM 10 AM 9 AM 8 AM
Sep 17 2015 11 AM 10 AM 9 AM 8 AM
Oct 15 2015 11 AM 10 AM 9 AM 8 AM
Nov 19 2015 11 AM 10 AM 9 AM 8 AM
Dec 17 2015 11 AM 10 AM 9 AM 8 AM
Tank
Operations
Contract
26
EFCOG Meeting
• Next QA/ISM Meeting Plan – (TBD) May, 2015
– Day 1 - TBD
• (EM QA Corporate Board Meeting)
• EFCOG Leadership Meeting Day
– Day 2 - TBD
• Morning – Joint & Working Group Session
• Afternoon – Subgroup and task group meetings
– Day 3 - TBD
• Supply Chain Quality Working Day
– Day 4 - TBD
• QA / Packaging Working Teams
• JSEP / MASL Integration Team
• CGD Handbook Team
Tank
Operations
Contract
27
EFCOG Meeting
Quality Assurance Work Activities
• Develop guidance on software management - modeling
graded approach and commercial grade dedication
• MASL/JSEP integration, Commercial Grade Surveys,
Supplier development, QA guidance for packaging
specifications (DOT Type A containers), CGD Handbook
• Establish guidance on developing key processes using the
graded approach
• Finalize NQA-1 Basic Interpretation White Paper
• Working Group on EM Corporate Board Task 1 –
Incorporation of OCRWM into NQA-1
• Working Group on EM Corporate Board Task 2 – QA
Resources
Tank
Operations
Contract
28
Old Business
• Any Other Old or New Business to Discuss?
Tank
Operations
Contract
29
Retirement Announcement
• Dean Shipley – Y-12
– Thanks for all your help and support
– Enjoy!
Tank
Operations
Contract
30
Open Discussion & Close Out
Tank
Operations
Contract
31
Next Webinar/Call & Close Out
• Next Webinar/Call:
– 1/15/15
• 11:00 AM EST
• 10:00 AM CST
• 09:00 AM MST
• 08:00 AM PST