58
This project has received funding from the European Union Seventh Framework Programme under grant agreement n° 609349. OPTIMISED DESIGN METHODOLOGIES FOR ENERGY-EFFICIENT BUILDINGS INTEGRATED IN THE NEIGHBOURHOOD ENERGY SYSTEMS eeEmbedded – D4.1 BIM Multi-Model Responsible Authors: Marc Mosch, Jens Kaiser Co-Authors: Francisco Forns-Samso , Romy Guruz, Peter Katranuschkov, Tuomas Laine, Klaus Linhard, Eko Nityantoro, Theodora Pappou, Hervé Pruvost, Thrasos Rekouniotis, Raphael Schär, Kenneth Solvik, Pit Stenzel, Amrita Sukumar, Arne Tøn, Raimund Zellner. Due date: 31.03.2015 Issue date: 31.03.2015 Nature: Other Coordinator: R.J. Scherer, Institute for Construction Informatics, Technische Universität Dresden, Germany

eeEmbedded D4.1 BIM Multi-Modeleeembedded.eu/wp-content/uploads/2015/04/20150331_eeE_D4_1_Fin… · BUILDINGS INTEGRATED IN THE NEIGHBOURHOOD ENERGY SYSTEMS eeEmbedded – D4.1 BIM

  • Upload
    buikiet

  • View
    223

  • Download
    0

Embed Size (px)

Citation preview

This project has received funding from the European Union Seventh Framework Programme

under grant agreement n° 609349.

OPTIMISED DESIGN METHODOLOGIES FOR ENERGY-EFFICIENT

BUILDINGS INTEGRATED IN THE NEIGHBOURHOOD ENERGY SYSTEMS

eeEmbedded – D4.1 BIM Multi-Model

Responsible Authors:

Marc Mosch, Jens Kaiser

Co-Authors:

Francisco Forns-Samso , Romy Guruz, Peter Katranuschkov, Tuomas Laine, Klaus

Linhard, Eko Nityantoro, Theodora Pappou, Hervé Pruvost, Thrasos Rekouniotis,

Raphael Schär, Kenneth Solvik, Pit Stenzel, Amrita Sukumar, Arne Tøn, Raimund Zellner.

Due date: 31.03.2015

Issue date: 31.03.2015

Nature: Other

Coordinator: R.J. Scherer, Institute for Construction Informatics, Technische Universität Dresden, Germany

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 2/58

© eeEmbedded Consortium www.eeEmbedded.eu

Start date of project: 01.10.2013 Duration: 48 months

Organisation name of lead contractor for this deliverable:

Technische Universität Dresden CIB

History

Version

Description Lead Author Date

0.1 Example: Deliverable Structure Mosch, Guruz, Katranuschkov (CIB)

28.10.2014

0.2 Categorization initial input Forns-Samso (GRA), Solvik (DDS), Stenzel (EAS), Tøn (EPM), Mosch (CIB), Guruz (CIB)

14.01.2015

0.2 Classification Introduction Mosch (CIB) 25.02.2015

0.3 Content Categorization Kaiser (IET), Stenzel (EAS), Sukumar (RIB), Pruvost, Mosch (CIB)

26.02.2015

0.4 Input Categorization and Classification

Kaiser (IET), Stenzel (EAS), Sukumar(RIB)

27.02.2015

0.5 Input Categorization and Classification

Kaiser (IET), Stenzel (EAS), Sukumar (RIB)), Pappou, Rekouniotis (SOF), Pruvost, Mosch (CIB)

02.03.2015

0.6 Input Multi Model Nityantoro, Mosch (CIB) 06.03.2015 0.7 Reorganization, Introduction,

Multi Model Mosch (CIB) 09.03.2015

0.8 Additional Categorization Zellner (NEM), Pappou, Rekouniotis (SOF), Solvik (DDS), Forns-Samso (GRA), Mosch (CIB)

10.03.2015

0.9 Revision Zellner (NEM), Solvik (DDS), Stenzel (EAS), Schär (SAR), Rekouniotis (SOF), Tøn (EPM), Forns-Samso (GRA), Mosch (CIB)

18.03.2015

1.0 Revision, Proof Reading Mosch (CIB) 23.03.2015

1.1 Revision, Prefinal Check, Proof Reading

Kaiser (IET), Stenzel (EAS), Schär (SAR), Geißler (BAM), Guruz, Mosch (CIB)

25.03.2015

1.2 Corrections Zellner (NEM), Laine, Forns-Samso (GRA), Pappou, Rekouniotis (SOF), Walser (DDS), Kaiser(IET), Mosch (CIB)

27.03.2015

1.3 Final Revise and Proof Reading Mosch (CIB) 30.03.2015

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 3/58

© eeEmbedded Consortium www.eeEmbedded.eu

Copyright

This report is © eeEmbedded Consortium 2015. Its duplication is restricted to the personal

use within the consortium, the funding agency and the project reviewers. Its duplication is

allowed in its integral form only for anyone's personal use for the purposes of research or

education.

Citation

Mosch, M. & Kaiser J. (2015); eeEmbedded D4.1: BIM Multi-Model, Multi-Physics Models and Management Methods, © eeEmbedded Consortium, Brussels. Acknowledgements

The work presented in this document has been conducted in the context of the seventh

framework programme of the European community project eeEmbedded (n° 609349).

eeEmbedded is a 48 month project that started in October 2013 and is funded by the European

Commission as well as by the industrial partners. Their support is gratefully appreciated. The

partners in the project are Technische Universität Dresden (Germany), Fraunhofer-Gesellschaft

zur Förderung der angewandten Forschung E.V (Germany), NEMETSCHEK Slovensko, S.R.O.

(Slovakia), Data Design System ASA (Norway), RIB Information Technologies AG (Germany), Jotne

EPM Technology AS (Norway), Granlund OY (Finland), SOFISTIK HELLAS AE (Greece), Institute for

applied Building Informatics IABI (Germany), FR. SAUTER AG (Switzerland), Obermeyer Planen +

Beraten (Germany), Centro de Estudios Materiales y Control de Obras S.A. (Spain), STRABAG AG

(Austria) and Koninklijke BAM Group NV (The Netherlands). This report owes to a collaborative

effort of the above organizations.

Project of SEVENTH FRAMEWORK PROGRAMME OF THE EUROPEAN COMMUNITY

Dissemination Level

PU Public X

PP Restricted to other programme participants (including the Commission Services)

RE Restricted to a group specified by the consortium (including the Commission

Services)

CO Confidential, only for members of the consortium (including the Commission

Services)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 4/58

© eeEmbedded Consortium www.eeEmbedded.eu

Abbreviations

BACS Building Automation and Control Systems

BAS Building Automation System

BCF BIM Collaboration Format

BEM Building Energy Modeling

BEPS Building Energy Performance Simulation

BIM Building Information Model

BoQ Bill of Quantities

CAD Computer Aided Design

CBS Cost Breakdown Structure

CFD Computational Fluid Dynamics

COBie Construction Operations Building Information Exchange

DACS District Automation and Control Systems

DGNB Deutsche Gewerkschaft für Nachhaltiges Bauen

DV Decision Value

eeE eeEmbedded

eeBIM Energy-efficient Building Information Model

eeeBIM Energy-efficient embedded Building Information Model

EN European Norm

ERP Enterprise Resource Planning

ES Energy Simulation

ESD Energy System Designer

ESIM Energy System Information Model

FSGIM Facility Smart Grid Information Model

gbXML Green Building Extended Markup Language

HVAC Heating Ventilation and Air Conditioning

IAI International Alliance for Interoperability

ID Identifier

IDF Intermediate Data Format

IDD Input Data Dictionary

IFC Industry Foundation Classes

IGES Initial Graphics Exchange Specification

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 5/58

© eeEmbedded Consortium www.eeEmbedded.eu

ISO International Organization for Standardization

KDP Key Design Parameter

KP Key Point

KPI Key Performance Indicator

LCA Life Cycle Assessment

LCC Life Cycle Costing

LoD Level of Detail

MEP Mechanical, Electrical & Plumbing

MMC Multi-Model Container

m2m Model to model

MVD Model View Definition

MVS Model View Definition

P&ID Piping and Instrumentation Diagram/Drawing

RA Room Automation

SGAM Smart Grid Architecture Model

SPF Step Physical File

SysML Systems Modeling Language

tbd to be defined

TEB Thermal Energy Building Simulation

TES Thermal Energy System Simulation

TMY Typical Meteorological Year

TRY Test Reference Year

UML Unified Modeling Language

VDI Verein Deutscher Ingenieure

VRV Variable Refrigerant Volume

vtk Visualization Toolkit

XMI XML Metadata Interchange

XML Extensible Markup Language

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 6/58

© eeEmbedded Consortium www.eeEmbedded.eu

TABLE OF CONTENTS

Executive Summary __________________________________________________________________ 7

1 The eeE Multi-Model Approach ____________________________________________________ 8

1.1 General Multi-Model Approach _______________________________________________ 8

1.2 Link Model ________________________________________________________________ 8

1.3 Multi-Model Specialisation ___________________________________________________ 8

1.4 Multi-Model Container ______________________________________________________ 9

2 Model Categorisation ___________________________________________________________11

2.1 Organisational Concepts and Models __________________________________________11

2.2 Physical Data Models _______________________________________________________12

2.3 Analysis Information Data Models ____________________________________________13

2.4 Uncertainty Information Models _____________________________________________17

3 Domain Data Model Classification _________________________________________________18

3.1 Architectural Models _______________________________________________________26

3.2 ESIM Models _____________________________________________________________28

3.3 HVAC Models _____________________________________________________________34

3.4 BACS Models _____________________________________________________________36

3.5 FM Models _______________________________________________________________40

3.6 Climate Models ___________________________________________________________42

3.7 Simulation Models _________________________________________________________44

3.8 LCC Models_______________________________________________________________48

3.9 LCA Models ______________________________________________________________50

3.10 Uncertainty Information Models _____________________________________________52

3.11 Decision Making Support Models _____________________________________________54

Conclusions _____________________________________________ Fehler! Textmarke nicht definiert.

References ________________________________________________________________________57

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 7/58

© eeEmbedded Consortium www.eeEmbedded.eu

Executive Summary

The objective of Deliverable 4.1 “BIM Multi-Model, Multi-Physics Models and Management

Methods” is to define the relevant domain models in the eeE context as a baseline for the

interoperability methods and the ontology to be developed in WP5. This includes the

categorisation and the classification of those models as well as a brief recapitulation of the Multi-

Model approach for their exchange.

D4.1 is structured into 4 chapters:

In the first chapter the Multi-Model approach is outlined, followed by a definition of the according Link Model, a discourse about the Multi-Model specialisation as well as the Multi-Model Container.

In the second chapter the categorization of the domain models relevant in the eeE project is elaborated. The categorization is four-part. It partitions the domain models into organisational concepts and models, physical data models, analysis information models and uncertainty information models.

The third chapter features the domain model classification. It is subdivided into one sub-chapter for each domain in the eeE context, namely architectural, ESIM, BACS, HVAC, FM, simulation, LCC, LCA and decision making models. In addition climate and uncertainty information models relevant for analysis related domains (SIM, LCC and LCA) are discussed.

CIB, DDS, EAS, EPM, GRA, IET, IAB, NEM, RIB, SAR and SOF were involved and each of those

partners contributed according to the individual expertise as follows:

The deliverable was led by CIB. The content of this deliverable was elaborated and discussed in

frequent web conferences between all above mentioned partners. CIB was leading discussions

and has contributed in all tasks.

CIB: all tasks, deliverable elaboration, content of chapter 1, input chapters 2 and 3, editing

EAS, RIB, SOF, IET: input chapter 2 and 3

DDS, EPM, GRA, NEM, SAR: input chapter 3

IAB: discussion and advices

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 8/58

© eeEmbedded Consortium www.eeEmbedded.eu

1 The eeE Multi-Model Approach

For the exchange of the domain models categorized and classified in chapters 2 and 3 the so

called Multi-Model approach was chosen. The term Multi-Model describes the combination of

multiple related models from different domains which are in this context referred to as

elementary models. The underlying idea is to combine both engineering and management models

in a single information resource to achieve a closely linked cooperation between the different

domains of the construction industry. The elementary models in the container are interconnected

via one or more link models. The result is a consistent Multi-Model that represents a certain

status of a project. The Multi-Model concept was initially presented in chapter 3.4 of D1.3

(Calleja-Rodriguez & Guruz, 2014). In the following a short recapitulation will be given, which

serves as an introduction to the subsequent deliverables of WP4.

1.1 General Multi-Model Approach

The Multi-Model approach for example presented in (Fuchs & Nityantoro, 2013) and (Scherer &

Schapke, 2014) is based on Multi-Model Containers (MMCs). These containers primarily consist of

elementary models, which can be any kind of either engineering or management models. Those

models are for example represented by IFC files, for the exchange of Building Information Models

(BIM) or by GAEBXML1 (German Joint Committee for Electronics in Construction), a standard for

construction information exchanged during construction bidding, contracting and invoicing as well

as during construction. A Multi-Model Container consists of a 3D building model and calculated

quantities deduced from its elements as well as link models which allow connecting those values

with the elements.

1.2 Link Model

Besides the linking of elementary models as part of the Multi-Model Container so-called Link

Models connect elements of different elementary models via unique identifiers (IDs). The

underlying general concept for the link model which was developed in the Mefisto project will be

used as baseline for interlinking the BIM domain models with other models, like climate and user

behaviour models, BACS and ESIM in the upcoming D4.3.

1.3 Multi-Model Specialisation

The metadata of the Multi-Model as well as that of elementary and link models facilitate a

substantive conclusions and offer information about the resources without the necessity to open

all involved files.

This enables the parent use of the data to manage numerous Multi-Models in a construction

project. Within a collaboration management platform, it is possible to specialise a Multi-Model

based on the current task, domain, as well as on the users role.

Metadata is not only a qualitative description of data but also considered to be representative for

the actual models even if they do not exist yet. This concept allows defining tasks in the building

information process by creating so called Multi-Model Templates. These are kind of blueprints –

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 9/58

© eeEmbedded Consortium www.eeEmbedded.eu

containers potentially missing some required elementary models, which are represented by a

metadata-based to-be description.

The expected elementary models might be part of one or several existing Multi-Models. In the

first case the Multi-Model can be reused. In the second case (depicted in Figure 1) the Multi-

models which come into question have to be decomposed, reorganized and merged for the given

task. Assumed not all requested elementary models can be found in existing Multi-Models the

new Multi-Model will again contain only metadata describing the missing elementary model,

which then has to be added in another way.

This combination and merging of Multi-Models will be discussed in more detail in D4.4 under the

general term Multi-Model Manipulation which also includes the transformation, mapping,

structural changing and filtering of models. The later manipulation is then taken up in D4.5.

Figure 1: Multi-Model Specialisation

1.4 Multi-Model Container

The communication between partners in eeE will be based on the idea of Multi-Model Containers

(Figure 2) which is discussed in more depth in the upcoming D4.6. Such a container defines a

structure bundling different kinds of elementary models via link models. Elementary models are

treated as independent information resources with their potentially own application domain, data

schema and data formalization. In this way Multi-Models can be applied on any domain. There are

several ways to realize a Multi-Model Container. It can be either realized as compressed archive

file which contains all models or as a Multi-Model that contains only the links and refers to the

linked resources outside of itself. It could even be realized as a message that contains a link to a

file which again contains links to those link models. Either way the container possesses an (XML-

based) description of its contents. It provides (potentially linked) information about the subjects,

detailing and data format as well as the creators or contributors of each elementary model. With

the help of this so-called metadata Multi-Model templates can be created which allow defining

requirements regarding content and formalization of elementary models of a certain project. In

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 10/58

© eeEmbedded Consortium www.eeEmbedded.eu

principal, Multi-Model Containers contain elementary models from different domains and each

model can be independently processed by participants. Each participant has the opportunity to

create or develop their own elementary models and link it with existing models. This enables

them to recombine the Multi-Models based on their demands as well as based on the

requirements of the project itself.

Figure 2: Multi-Model Container structure based on (Fuchs&Nityantoro, 2013)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 11/58

© eeEmbedded Consortium www.eeEmbedded.eu

2 Model Categorisation

The entire BIM contains several domain models. Some of them are already partially considered in

the BIM-IFC data model. Nevertheless, the consideration of eeE building design in particular the

energetic environment (neighbourhood building energetic infrastructure) introduce many data

models that are up to now not captured by the IFC and should also not be deeply incorporated in

the IFC model. Instead they should be handled as federative interoperable data models. As

foundation for such a data model structure, the data models will at first be categorized according

to the information functionality. As roughly depicted in Fehler! Verweisquelle konnte nicht

gefunden werden., they can be grouped into the categories organizational concepts and models,

physical data models, analysis information models and uncertainty information models. These

categories are presented in the following.

Figure 3: Model categorization

2.1 Organisational Concepts and Models

The organizational concepts and models cover concepts for Key Points, models for energy

operation and facilities management (FM) strategies.

In D2.1 (Guruz et al., 2015a), the new eeE design methodology is introduced. The structured net

of verifiable design checkpoints, the so called Key Points, is specified there. The concepts of Key

Points (see Figure 1Figure 4) are defined in three levels based on building requirements (Key

Points to-be) and are used during the different design phases as milestones in design. In a next

step, the design, simulation and analysis results are aggregated for higher decision making (Key

Points as-is). Furthermore the Key Points are analysed to determine the relations behind them.

Additionally the Key Point structure and main ingredients are introduced and specifications for

the use of Key Points are made. This procedure is necessary to create domain related goals which

are verifiable. Additionally eeE Key Point Taxonomy by classification of the three identified Key

Point Groups: Decision Values (DVs), Key Performance Indicators (KPIs), Key Design Parameters

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 12/58

© eeEmbedded Consortium www.eeEmbedded.eu

(KDPs) is worked out with project related contents. Based on common energy certifications (e.g.

passive house standard, DGNB, Leeds) the detailed description of every Key Point Group is

elaborated and specified as basis for eeE Ontology.

Figure 4: eeE Key Point pyramid (Guruz et al., 2015)

Furthermore, procedures to evaluate requirements and set up key points, procedures to evaluate

design alternatives and procedures for the overall key point methodology are defined. The

sequence of the steps of the Key Point workflow was specified via UML and is divided into four

views/patterns: setup, planners, simulation and decision making. These describe also the

functions of the software components and their integration in the overall eeE system

architecture.

The Key Point based design methodology will apply the existing simulations and analyses tools for

an integrated holistic design system. By this procedure an interoperability design framework is

created that combines a complex multi‐information model and multi‐physics demands. So the

procedure of Key Point controlled design leads to a software framework that combines a

multiplicity of simulations and analyses software.

The models for energy operation (ESIM) will be defined in chapter 3.2 and the upcoming D4.2.

The models which are relevant for ESIM are described in chapter 3.4 (BACS) and chapter 3.3

(HVAC). All necessary information and definitions for FM are elaborated in chapter 3.5 (FM).

2.2 Physical Data Models

Physical data models map construction elements, physical objects like equipment, sensors, energy

system and construction machines, which can be further divided in building internal and building

external objects. This covers elements of architectural and structural data models like BIM as well

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 13/58

© eeEmbedded Consortium www.eeEmbedded.eu

as those of Building Automation and Control Systems (BACS) and those of Heating, Ventilation

and Air Conditioning (HVAC).

In general the physical data model covers physical objects (e.g. building services equipment) as

well as their grouping to systems and sub-systems, e.g. sensor and actuator networks or air

conditioning systems. Besides grouping concepts, composing and decomposing capabilities of

physical objects are supported by the physical data model. A physical chiller object, the energy

generating component of an air conditioning system, can for example be decomposed into the

physical objects evaporator, compressor, condenser and throttle.

Beyond structural data describing principle system characteristics, the physical data model is

providing capabilities to represent the interrelations between real physical objects and systems

like they are and like they should be. To this end each physical object needs a physical interface

description. Using port connection concepts the physical connections of physical objects can be

described in detail. To connect for instance energy generating equipment (e.g. chiller and heat

pump) and energy consuming equipment (e.g. radiator and fan-coil) the physical interface has to

be compatible.

Each physical object or system fulfils a specific task or functionality in the overall building or in its

neighbourhood. Hence, the physical data model provides concepts to describe functionalities of

physical objects. For instance, temperature measurement functionality can be assigned to a

physical temperature sensor object or water storage functionality can be assigned to water

storage tanks.

Manufacturer independent as well as dependent solutions can be covered by the physical data

model. The representation of a physical sensor and actuator network can be both as long as the

physical interface and functionality are identical.

Physical data models cover the following aspects:

System description and grouping of physical objects

Aggregation, composition and decomposition of physical components

Physical interface description using port connection concepts

Function description of physical components

Interrelation between physical objects across domains

Manufacturer information of physical objects

2.3 Analysis Information Data Models

Analysis tools in eeEmbedded concern combined Energy and CFD (Computational Fluid Dynamics)

simulations, in each phase of the building’s design. The data model for combined Energy/CFD

simulations can be linked to a Building Life Cycle Model that could facilitate interoperability

between all stages of the building. Both Energy Simulation (ES) and CFD simulations require a

variety of data from other domains like CAD-MEP systems, simulation tools, and supply data to

LCA and LCC and decision making applications.

The development of interoperable and/or integrated design tools requires the identification of

input and output data requirements for the various domains involved. Data types, relationships

between data, links between types, constraints on relationships, validation checks etc. are

defined for the development of a data model schema for the holistic simulation.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 14/58

© eeEmbedded Consortium www.eeEmbedded.eu

Thermal energy simulation of buildings and systems in the state-of-the-art level is taking into

account a broad range of border conditions like outdoor weather/climate, topology, user

behaviour, internal loads and constructions in the neighbourhood. Most of these main boundary

conditions bring in a unique domain-specific data structure or model.

Figure 5 gives an overview of data models related to energy simulations. Especially of the

following data models which are available on a mature level:

Building geometry o Industry Foundation Classes (IFC, buildingSMART) o Green Building XML (gbXML, developed and maintained by Autodesk)

Weather/climate o Test Reference Year format (TRY, German Weather Service, Germany) o Typical Meteorological Year Format 2 and 3 (TMY2/TMY3, NREL, USA) o International Weather for Energy Calculations format (IWEC, ASHRAE)

Neighbourhood o Various GIS formats o CityGML

Energy Systems o Smart Grid Architecture Model (SGAM) o Facility Smart Grid Information Model (FSGIM)

Construction materials/elements o Not defined yet

Analysis Results o Thermal building energy and system simulation:

No standardisation available o CFD

Plot3D CFD General Notation System (CGNS)/HDF5

Analysis Process Management o Not defined yet, have to be adopted from other domains

Prize/Costs o Not defined yet, have to be adopted from other domains o Core Cross‐Industry‐Invoice (Core CII) ZUGFeRD (Germany)

Figure 5: Overview of analysis data models - part 'energy simulation'. (Legend on the right side, illustration Jens Kaiser)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 15/58

© eeEmbedded Consortium www.eeEmbedded.eu

CFD analysis for energy performance and thermal comfort conditions estimation could be used as

a standalone simulation tool or as a complementary tool to the ES applications. CFD tools can use

results from ES tools such as flow rates and wall temperatures etc. to provide detailed results of

specific building zones. Therefore a natural coupling between these two tools can be seen and

consistency of data models used should be achieved. This state of coupling between CFD and ES

tools means that the majority of the inputs require manual transfer of data as most packages

have independent file formats. A data centric approach would eliminate much of the time wasted

in transferring data between tools during design. The data model for combined ES and CFD

simulations can then be extended into a Building Life Cycle Model that could facilitate

interoperability between all stages of the building. Both ES and CFD simulations require a variety

of data from other domains like CAD-MEP systems, simulation tools, and supply data to decision

making applications and finally LCC and LCA procedures.

The data models required for each alternative CFD simulation, in the context of eeE, concern the

import of the geometrical model, the imposition of suitable boundary conditions and the

generation of the discretised model as pre-processing steps and subsequently the representation/

evaluation of the results as well as their association with the BIM model entities for any future

use.

The geometrical model describes the building envelope as well as the envelopes of the

surrounding buildings for urban design purposes in CityGML or IFC format. Openings’ and glazing

surfaces’ positions are included in the building envelope. The building orientation is also taken

into account. For the case of the detailed design, the thermal envelope is required for each

particular space simulated. The thermal envelope is required in the form of 2nd level space

boundaries in IFC files. The geometric data are created using an IFC compliant 3Dmodeler (e.g.

REVIT, ArchiCAD and AllPlan).

The boundary conditions for CFD simulations refer to climatic data, air flow velocity, turbulence

intensity, solar radiation for a particular data set of a Typical Meteorological Year (TMY) for the

outdoor climate simulation and wall temperatures resulting from ES applications (ESIM),

occupancy data and other thermal loads such as lighting or electromechanical equipment thermal

loads, air supply conditions from HVAC equipment (CAD-MEP IFC4 format) (FSGIM, IFC4) for the

indoor climate simulation. For the latter, the location of supply air inflow (openings, number and

exact location, geometrical characteristics like area, inflow angle to the room) should also be

already defined. Additionally BACS activation also modifies geometrical data and HVAC operation

characteristics (IFC).

After the insertion of the geometrical model and the imposition of the boundary condition the

mesh generation is going to take place. The geometrical characteristics building and the type of

boundary conditions imposed constitute the control parameters for mesh generation.

More specifically, after suitable corrections/healing and refinement the building or the thermal

envelope (2nd level spaces in IFC files with information about materials and surrounding spaces)

are translated to the IGES-format to generate input data for mesh generation software. The

generated mesh is stored in ISO standard file formats such as CGNS (CGNS 2003).

The CFD & thermal results in 3D space concern space distribution and time evolution of

temperature, radiant temperature, air velocities, contaminants’ concentration, relative humidity,

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 16/58

© eeEmbedded Consortium www.eeEmbedded.eu

turbulence intensity, thermal comfort and IAQ KPIs. Geometric and HVAC entities are supported

in IFC. But mesh and CFD data/results do not currently exist and need to be linked to IFC entities.

Distributed results are stored in the vtk format for 3D visualization of the flow field purposes.

Integrated, mean or min/max quantities for each zone could be mapped to an IFC model.

Estimations for U values of the building envelope can be mapped on IFC objects.

The LCC model comprises of Bill of Quantities (BoQ), a structured document, using a hierarchy for

collecting and summarizing values at each level in the structure. The BoQ contains all the works

that have to be priced. For a project, many BoQs can be defined, structure and referenced with

respect to model detailing. The BoQ is connected with the model and the cost codes. Cost codes

are the cost elements such as labour, Plant, Materials and Subcontractor together with their cost,

used for estimating the cost of items and, ultimately, the total cost of a project. Cost Codes are

stored in the Cost Code Catalogue in the Master Project. The Cost Codes from the Master Project

can be used for new projects or new Cost Codes can be added to the new projects file. Each unit

cost is multiplied by the item quantity to arrive at the total cost of the item, which in turn is added

to the cost of all other items to arrive at the grand total for the project. Once Cost Codes are used,

iTWO can analyse the total cost of the project. There is also a price database function, which

facilitates the storage of historical unit rate data for items of Work Item Category (WIC) stored in

the master project. Each item in the WIC can store multiple prices that can then be accessed,

when that item is copied from the master to a project. The prices are linked to a Master

Construction Price Index catalogue. The price database acts as a record of existing project prices

for each work item.

The analysis process management within the analysis information model chain covers both,

(1) the abstract description of an analysis job addressed to analysis software tools, e.g. ‘run a

thermal building simulation covering building x for a one-year period’ and (2) the structure for

transporting results between software applications.

The analysis results model is standardized within the CFD community. However, there is no

standard available for thermal energy building and systems simulation domain. In general a future

standard should cover a definition for (1) single arithmetic values, e.g. KPIs, (2) tuples of

arithmetic values, and (3) string values. The results could be handed over directly between the

applications or indirectly with the help of a link to a specified data source where the results are

available.

In general for lossless back tracking of analysis results the analysis results data model should

provide the structure to keep both, (1) the connection to the object (e. g. a single building, space

or heating radiator or sensor described e.g. within the IFC data model) and (2) the performed

analysis run, both represented by and identifiable by a unique ID.

Regarding the analysis process management data model for doubtless identification of results it is

mandatory to generate unique IDs for each analysis run. In the same way a unique ID has to be

generated for each design variant or design alternative to keep the informational connection

between the objects within the whole workflow.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 17/58

© eeEmbedded Consortium www.eeEmbedded.eu

All of the analysis information data models are closely related to the definition of templates

described within eeE deliverables D1.4 (Solvik et al., 2014) and D2.2. (Zellner & Kaiser, 2015)

2.4 Uncertainty Information Models

In the context of eeE the uncertainty information models can be divided into two kinds of models

namely stochastic and risk models. Those different uncertainty models are meant to be integrated

into the eeeBIM framework on the basis of the Multi-Model method.

The stochastic models provide a mathematical representation of uncertainties related to the

project together with their correlations and their influence on output variables that are expressed

as KPIs. For that purpose the stochastic models express all uncertainties of interest as variables.

The variables defined are of two kinds: static uncertainties (e.g. expressed as probability

distribution) and dynamic uncertainties (e.g. expressed as stochastic process); differentiated

according to their nature and especially their time-dependency. The stochastic models can for

example describe energy consumption using Wiener processes and energy system vulnerability

using Poisson processes. Both stochastic processes are commonly used for that purposes in

engineering. Moreover the stochastic models express uncertainties related to different domains

relying on aspects like costs, building usage and weather as well as energy system characteristics.

As the stochastic models focus on the mathematical description of uncertainty, the role of the risk

models is to represent this uncertainty and its effects on the analysed performances in a more

physical and concrete manner by defining a proper data structure, engineering concepts that

carry the information, their relations to each other and to other models (e.g. ESIM), as well as risk

scenarios. In eeEmbedded WP3 the aim is then to develop an energy risk model related to the

energy system. The energy risk model can be divided in sub-models regarding the performances

of interest and can accordingly be formalized as vulnerability, sustainability and cost risk models.

In the vulnerability model there is more emphasis put on energy system malfunctions and

underperformances that occur over time, identifying critical system behaviour scenarios. The

sustainability model is focused on the energy consumption and CO2 emission over the entire

building life cycle. In the cost risk model resulting cost variations are considered based on the two

previous models, expressing cost values as uncertain parameters.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 18/58

© eeEmbedded Consortium www.eeEmbedded.eu

3 Domain Data Model Classification

Based on the detailed results of D1.2 (Geißler et al., 2014) the model transitions will be presented

in the following for each of the three earlier established use cases. Afterwards state of the art,

user requirements and scope as well as m2m dependencies will be examined for each domain

(and the associated models) individually.

Use Case 1: Urban Design

The first use case (urban design phase, see Figure 6) consists of the following tasks: 1.0 Project set

up, 1.1 Check consistency, 1.2 Create design cubature options,1.3 CFD simulation, 1.4 Create

energy design supply options, 1.5 Energy simulation, 1.6 Life cycle costing, 1.7 Decision Making

Figure 6: Use case 1 - urban design (Geißler et al., 2014)

The project set up task includes the preparation and prioritisation of Decision Values to-be as well

as the analysis of regulatory, site and environmental requirements. Those are translated into Key

Performance Indicators to-be. Furthermore Key Design Parameters to-be (e.g. shape, quality,

quantity) are developed. Correspondingly the task’s input includes requirements for example

from clients, and regulations.

The consistency check task takes all requirements as input and puts out the valid requirements.

The create design cubature options task covers the creation of cubature options, the

development of stories as well as the definition of verticals and architectural zones/spaces. Its

inputs are CityGML files while its outputs are BIM-based (IFC) files.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 19/58

© eeEmbedded Consortium www.eeEmbedded.eu

The CFD simulation task takes the IFC files as input for the creation of stochastic

scenarios/parameterisation, runs simulations, interprets the results and outputs simulation

results. The create energy supply options task takes the IFC files and the simulation results

generated beforehand to create energy supply concepts including

generation/storing/distribution, exchange and energy recovery. Furthermore supply routes and

rules from existing energy infrastructure are considered, interactions with other buildings and/or

energy storage systems are created. A distribution route is developed as well as controller

algorithms to minimize the energy consumption. The task’s output is ESIM (ES+DACS). The specific

definition of which will be proposed in T4.2. In the energy simulation task is fed with IFC + ESIM

to create stochastic scenarios/parameterisation. Simulations are run and the results are

interpreted. The outputs are simulation results which are forwarded to the LCC and the decision

domain. Based on IFC, ESIM and simulation results the life cycle costing task creates stochastic

scenarios/parameterization, preforms Life Cycle Cost Estimation and interprets the results. LCC

results are the final output which is then forwarded to the decision making domain. Building up

on the simulation and LCC results the decision making task balances the advantages and

disadvantages of the elaborated alternatives and prepares a design feedback which culminates in

the output of Decision Values as-is.

The resulting model transitions between the relevant components, presented in D1.5 (Zellner et

al., 2015), are illustrated in Table 1 for the urban design phase.

Table 1: Model transition for use case 1 (urban design phase) with the resprective exchange requirements (ER) according to D1.3 (Calleja-Rodriguez & Guruz, 2014)

1. ARCH Allplan (NEM)

ER 1.1 MMC(IFC4)

ER 1.1 MMC(IFC4)

2. ESIM ESIM GUI

(tbd)

ER 1.3 MMC(IFC4, ESIM, ASCII)

ER 1.3 MMC(IFC4, ESIM, ASCII)

ER 1.2 MMC(IFC4,

ASCII)

6. SIM TRNSYS-TUD

(IET)

ER 1.4 MMC(IFC4, ESIM, ASCII)

ER 1.5 MCC(ASCII/KPI)

ER 1.2 MMC(IFC4,

ASCII)

6. SIM 3DWind

(SOF)

ER 1.4 MMC(IFC4, ESIM, ASCII)

ER 1.5 MMC(ASCII/KPI)

8. LCC iTWO (RIB)

ER 1.6 (1.5) MCC(Cost

results/KPI)

9. DM Navigator

(NEM)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 20/58

© eeEmbedded Consortium www.eeEmbedded.eu

Use Case 2: Early Design

The second use case (early design phase, see Figure 7) consists of the following tasks: 2.0 Project

set up, 2.1 Check consistency, 2.2 Create construction type alternatives, 2.3 Create HVAC type

alternatives, 2.4 Create control strategy alternatives, 2.5 Enrich alternatives with O&M

information, 2.6 Simulation, 2.7 Life Cycle Assessment, 2.8 Life Cycle Cost estimation, 2.9 Decision

Making.

Figure 7: Use case 2 - early design (Geißler et al., 2014)

After the decision in the Urban Design Phase, the project set up task reviews and outputs

Decision Values to-be, Key Performance Indicators to-be as and decomposes the Key Design

Parameters to-be (e.g. shape, quality, quantity) to elements level.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 21/58

© eeEmbedded Consortium www.eeEmbedded.eu

The consistency check task takes all requirements as input and puts out the valid requirements.

In the create construction type alternatives task building shell alternatives (outer walls, windows,

baseplate and roof), layout alternatives, fit-out alternatives (inner walls, floors and ceilings) and

shading alternatives are created and stored in a BIM-based file which is then forwarded.

The create HVAC type alternatives task covers thermal zones identification and definition, loads

calculation as well as the creation of HVAC system type alternatives such as chiller + boiler +

fan coils, air-water heat pump + fan coils, splits, Variable Refrigerant Volume (VRV), etc. taking

into account the type of building, schedules, loads, etc.. It furthermore allows drafting pre-

location and pre-sizing ideas for production equipment such as boiler, terminal units such as fan

coils and distributions systems like fans and pumps, taking into account the loads calculation.

Based on the BIM input (IFC) an ESIM (HVAC) model which will be defined in T4.2 (see

eeEmbedded: Description of Work, 2013) is generated and put out.

The create control strategy alternatives task takes BIM and ESIM (HVAC) as input and puts out

ESIM (BACS). It covers the review of construction type and HVAC type alternatives as well as the

creation of BACS alternatives (sensors, controllers, actuators etc.) based on EN 15232 (DIN EN

15232).

IFC and ESIM (HVAC, BACS) are the input for the enrich alternatives with O&M information task

which includes the checking of maintainability (service lifes, schedules from FM data base), of

cleaning intensity, of accessibility and of flexibility (exchangeability of building components).The

output enriches the input with FM data.

The resulting data are used in the simulation task to create stochastic scenarios, run simulations,

to interpret results and in the end to put out simulation results.

Based on the information generated in the former tasks cost scenarios (stochastics) are prepared

in the Life Cycle Assessment task. Moreover Life Cycle Assessment (LCA) is performed on BIM-

based QTO, simulation results, service life planning and activity category results. Before they are

put out the LCA results are reviewed.

Supplied with BIM, ESIM (HVAC and BACS) and FM information the creation of stochastic

scenarios, the estimation of Life Cycle Cost and the interpretation of the LCC results (which are

the output) take place in the Life Cycle Cost estimation task.

Simulation results plus LCA and LCC results are used in the decision-making task to balance the

advantages and disadvantages of the elaborated alternatives and to prepare the design feedback

in form of Decision Values as-is which are then put out.

The resulting model transitions between the relevant components, presented in D1.5 (Zellner et

al., 2015), are illustrated in

Table 2 for the early design phase.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 22/58

© eeEmbedded Consortium www.eeEmbedded.eu

Table 2: Model transitions for use case 2 (early design phase) with the resprective exchange requirements (ER) according to D1.3 (Calleja-Rodriguez & Guruz, 2014)

1. ARCH

Allplan (NEM)

ER 2.1 MMC(IFC4)

3) HVAC DDS-CAD

MEP (DDS)

ER 2.2 MMC(IFC4,

ESIM)

4. BACS eeBACS Wizard (SAR)

ER 2.3

MMC(IFC4, ESIM)

5. FM Granlund Designer

ER 2.4 MMC(IFC4, FM, ESIM)

ER 2.4 MMC(IFC4, FM, ESIM)

6. SIM TRNSYS-

TUD (IET)

ER 2.5 MMC(IFC4,

ESIM, ASCII)

ER 2.7 Simulation

Results/KPI

6. SIM RIUSKA (GRA)

ER 2.5 MMC(IFC4,

ESIM, ASCII)

ER 2.7 Simulation Results/KPI

7. LCA

iTWO (RIB)

ER 2.6

MMC(IFC4, ESIM,

ASCII, LCC results)

ER 2.7 Simulation Results/KPI

8. LCC

iTWO (RIB)

ER 2.7 Simulation

Results/KPI

9.DM Navigator

(NEM)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 23/58

© eeEmbedded Consortium www.eeEmbedded.eu

Use Case 3: Detailed Design

The third use case (detailed design phase, see Figure 8) consists of the following tasks: 3.0 Project

set up, 3.1 Check consistency, 3.2 Create architecture product alternatives, 3.3 Create HVAC

product alternatives, 3.4 Design sensor and actor network, 3.5 Enrich product alternatives with

operational information, 3.6.a CFD simulation, 3.6.b Energy simulation 3.7 Life Cycle Assessment,

3.8 Life Cycle Cost estimation, 3.9 Decision Making.

Figure 8: Use case 3 - detailed design (Geißler et al., 2014)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 24/58

© eeEmbedded Consortium www.eeEmbedded.eu

After the decision in the Early Design Phase, the project set up task reviews and outputs Decision

Values to-be, Key Performance Indicators to-be and decomposes Key Design Parameters to-be

(e.g. shape, quality, quantity) from elements level into products level.

The consistency check task takes all requirements as input and puts out the valid requirements.

In the create architecture product alternatives task the layout is detailed and material supplier

options are created and stored in a BIM-based file which is then forwarded.

The create HVAC product alternatives task covers final selection and sizing according to

manufactures products as well as the location of production equipment, terminal units and

distribution system. Furthermore it captures final sizing of the distribution system (ducts, pipes,

fans, valves, pumps, heat exchangers etc.). Based on the BIM input (IFC) an ESIM (HVAC) model

which will be defined in T4.2 is generated and put out.

The design sensor and actor network task takes BIM and ESIM (HVAC) as input and puts out ESIM

(BACS). It covers the design of the sensor and actor network (e. g. sensors, actor and controller

placement).

IFC and ESIM (HVAC, BACS) are the input for the enrich product alternatives with operational

information task which includes the checking of maintainability (service lifes, schedules from FM

data base), of cleaning intensity, of accessibility and of flexibility (exchangeability of building

components).The output enriches the input with FM data.

The resulting data are used in the CFD simulation task to create stochastic scenarios, run

simulations, to interpret results and in the end to put out CFD simulation results.

The resulting data are used in the energy simulation task to prepare and run simulations,

interpret the energy simulation results and put them out.

Based on the information generated in the former tasks cost scenarios (stochastics) are prepared

in the Life Cycle Assessment task. Moreover Life Cycle Assessment (LCA) is performed. The LCA

results are reviewed before they are finally put out.

Supplied with BIM, ESIM (HVAC and BACS) and FM information the creation of stochastic

scenarios/parameterisation, the estimation of Life Cycle Cost and the interpretation of the LCC

results (which are the output) take place in the Life Cycle Cost estimation task.

Simulation results plus LCA and LCC results are used in the decision-making task to balance the

advantages and disadvantages of the elaborated alternatives and to prepare the design feedback

in form of Decision Values as-is which are then put out.

The resulting model transitions between the relevant components, presented in D1.5 (Zellner et

al., 2015), are illustrated in Table 3 for the detailed design phase.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 25/58

© eeEmbedded Consortium www.eeEmbedded.eu

Table 3: Model transition for use case 3 (detailed design phase) with the resprective exchange requirements (ER) according to D1.3 (Calleja-Rodriguez & Guruz, 2014)

1. ARCH Allplan (NEM)

ER 3.1 MMC(IFC4)

3. HVAC DDS-CAD

MEP (DDS)

ER 3.2 MMC (IFC4,

ESIM)

4. BACS DDS-CAD

MEP (DDS)

ER 3.3 MMC (IFC4,

ESIM)

5. FM Granlund Designer

ER 3.4 MMC (IFC4, ESIM, FM)

ER 3.4 MMC (IFC4, ESIM, FM)

6. SIM

TRNSYS-TUD (IET)

ER 3.5 MMC (IFC4, ESIM, FM,

ASCII)

ER 3.7

Simulation results/KPI

6. SIM 3DThermal CFD(SOF)

ER 3.5

MMC (IFC4, ESIM, FM,

ASCII)

ER 3.7 Simulation results/KPI

7. LCA

iTWO (RIB)

ER 3.6 MMC (IFC4, ESIM, FM, ASCII, LCC

results)

ER 3.7 Simulation results/KPI

8. LCA

iTWO (RIB)

ER 3.7

Simulation results/KPI

9. DM Navigator

(NEM)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 26/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.1 Architectural Models

Architectural models are virtual 3D volume models enhanced by alphanumeric data. They are

created by architects, designers or planers via Computer Aided Design (CAD) software. All

graphical elements of these models are representations of construction elements and spaces or

zones. They are classified by construction types, like walls, doors, windows, ceilings and others, to

enable controlled data handling, object recognition and object filtering. In order to obtain a

complete Architectural BIM Model, building geometry and object alphanumerical information are

required.

3.1.1 State-of-the-Art

The result of the architectural domain work is represented by a BIM Model, generated and

designed in a CAD system. There are several such systems available on the market. To better

integrate them in the planning workaround, all popular CAD manufacturers implemented

standard interfaces like IFC, to exchange their BIM data with other applications. Nonetheless, it is

important to mention at this point that the Level of Detail (LoD) and the architectural model

completeness vary from CAD system to CAD system, but depend mainly on the user inputs and

detailing work.

A smooth interdisciplinary working methodology requires (1) an interface standardization of the

BIM data structure to enable loss-free information exchange between different IT Tools, which

are used by the planers in the entire planning process, and (2) the inclusion of a minimum set

of useful information from each domain to provide sufficient input for the next working steps.

In order to fulfil the first requirement, the open standard IFC description was developed by the IAI

(International Alliance for Interoperability) as a neutral and open specification for BIM. All major

manufacturers integrated the current IFC2x3 interface into their CAD application. The new and

improved syntax IFC4 is already defined, but not broadly realized.

BIM data quality and information level provided by a CAD System do not exclusively depend on

the application capabilities itself, but also on the information which the user added into the BIM

model. The level of information added into the Architectural Model can therefore verify from

designer to designer.

3.1.2 End user requirements

End-user requirements related to the Architectural Model cover basically (1) the geometrical

model completeness including (2) the existence of alphanumerical object data, and (3) the BIM

model data quality. In addition, data readiness and standard interfaces are demanded to enable

smooth and loss-free data exchange between all domains defined in the eeE use case scenarios.

On the one hand, in the eeE project the KDPs to-be need to be checked against the real model

geometry, expressed in KDP as-is.

On the other hand, design of buildings e.g. indoor environmental comfort should be permanently

controlled via given KPIs to-be, and simulation results KPIs as-is. To support this process

appropriate simulation and analysis tools and viewers are required.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 27/58

© eeEmbedded Consortium www.eeEmbedded.eu

As experience shows, creating BIM models can be very time consuming, especially if a high LoD is

desired. A reduction of those modelling efforts is desirable but necessitates a large scale of

automatic CAD functionalities as well as adequate object libraries, which contain all required

object information.

In the early design process, most of the construction details are unknown. Construction material

selection and architectural details are usually elaborated iteratively, supported stepwise through

the energy, and cost analysis.

The eeE project improves the design process with the preparation of CAD project setups and

ensures that the CAD environment conditions are optimized according to the building

requirements. In other words, the CAD project setup will be prepared before starting the work,

enhanced by an additional templates library, to enable the architect to design the building in the

right direction. This could involve for instance the provision of certain wall, windows, façade and

other construction templates that need to be used, in order to reach the required building

performance values.

The use of templates leads to automatic detailing of CAD objects. This reduces the modelling

effort and provides all alphanumerical parameters to determine exact quantities, as well as to

execute energy and cost simulations.

3.1.3 eeE Scope and Extensions

In order to optimize and steer the design process in the right direction, several improvements are

proposed for the creation of architectural models in the following:

To enable a smooth exchange of geometry and building information between IT Tools and BIM

servers in the entire design process the standardization of CAD data interfaces is striven.

Therefore IFC2x3 or IFC4 format defined by the BuildingSmart will be supported.

The Allplan BIM CAD interoperability to third party products supported by the bim+ platform will

be improved. Nemetschek’s web based BIM platform bim+ hosts and administrates BIM models

and supports collaboration topics in the Planning, Construction and Facility Management

processes. The integration of third party tools into the bim + platform is necessary to enable best

workflow.

It is furthermore aspired to support BIM processes via BCF RESTful services. This enhancement

will enable simultaneous communication between planners and decision makers, regardless of

their location.

Another scope is the development of an “ease of use” Navigator. This mmNavigator will be a

front-end application which supports experts as well as non-experts in taking design decisions.

BIM Server extensions (EDMmodelServer and bim+ Server) will be developed to support different

scenarios in a decentralized network, for instance data upload and download services.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 28/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.1.4 m2m dependencies in the eeE use cases

The transmission of the architectural models through all eeE domains is realized with the standard

IFC interface. This interface is already supported by many software companies, above all by the

most popular CAD providers.

The project communication and data transmission will be supported by the use of BCF2 (BIM

Collaboration Format, version 2).

3.2 ESIM Models

The Energy System Information Model (ESIM) covers a data structure to describe all major

systems, subsystems and components of energy systems and related data and objects including

HVAC and BACS objects. Figure 9 provides an overview of core information objects within the

ESIM.

Figure 9: Core objects within the ESIM (draft version, (Zellner & Kaiser. 2015))

3.2.1 State-of-the-Art

Currently there is no single model available which covers all aspects of energy systems in buildings

and the neighbourhood from scratch. Various existing models already cover certain aspects and

provide data structures for enhancement or adaption to cover information which are not

originally part of the model content. Certain examples for available models and standards are

listed below assigned to their domains:

Architecture/HVAC/BACS design domain o IFC2x3 model, IFC4 model (ISO 16739)

HVAC design domain o Piping and instrumentation diagram (P&ID) (ISO 10628 and ISO 14617)

BACS design domain o EN15232 o ISO 16484 o VDI 3813 o Modelica model o BACnet (ISO 16484-5), KNX (ISO/IEC 14543-3)

Thermal Building Energy and System Simulation domain o Modelica model o Energy Plus data model (IDD, IDF) o Green Building XML (gbXML)

Smart Grid domain

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 29/58

© eeEmbedded Consortium www.eeEmbedded.eu

o Facility Smart Grid Information Model (FSGIM) UML o Smart Grid Architecture Model (SGAM) SysML

ESIM is going to be newly developed in T4.2. However, there are already existing data structures

covering ES and HVAC as well as BACS related information. The following provides an overview on

existing data structures or standards respectively.

IFC Model IFC2x3, IFC4

The Industry Foundation Classes, an international standard for the exchange of BIM data, are

providing a generic data schema that covers among others architectural, building service and

structural elements. Since IFC4 schema specification the data structure provides enhanced

capabilities for the modelling of building service systems. System modelling using e.g. port

connection concepts is available. Serialized IFC models are provided either in STEP physical file

format (SPF) or as ifcXML file. IFC also covers a wide range of generic HVAC type devices,

instances and attributes to match a specific product. The IFC4 schema model is improved in

several aspects, both in content and exchange: It enhances the capability of the IFC specification

in its main architectural, building service and structural elements with new geometric, parametric

and other features. It furthermore enables numerous new BIM workflows – including 4D and 5D

model exchanges, product libraries, BIM to GIS interoperability, enhanced thermal simulations

and sustainability assessments. The improvement of space boundaries and the introduction of

additional spatial zones and external spaces (against ground, water, air) as well as the

descriptiveness of shading devices can be used for energy and other performance analysis. In

addition to the EXPRESS schema, the ifcXML4 schema is fully integrated into the IFC4

specification. The additional full integration of the new mvdXML technology easily enables the

definition of data validation services for IFC4 data submissions.

Since IFC4 schema specification the data structure provides enhanced capabilities in modelling

building automation and control systems and their components.

Note that although the partners up to now committed to IFC4 it still has to be checked at the

beginning of the implementation phase if IFC4 can be used spanning across all components or if

partially fall back solutions involving IFC2x3 have to be found.

Piping and instrumentation diagram (ISO 10628 and ISO 14617)

The piping and instrumentation diagram (P&ID) is a common schematic representation in the

process industry which shows the piping of the process flow together with the installed

equipment (e.g. vessels, fans and pumps) and instrumentation (e.g. sensors and controller). The

international standards ISO 10628 - Diagrams for the chemical and petrochemical industry and

ISO 14617 - Graphical symbols for diagrams provide the appropriated symbol definitions (ISO

10628, ISO 14617).

BACnet (ISO 16484-5), KNX (ISO/IEC 14543-3)

Common ISO standards to interface building control devices used to control HVAC and Electro

installations systems. Special designed and proprietary software access these standard protocols

to program BACS devices with the intension of controlling its connected HVAC product and

systems to act as required in the physical constructed building. In theory, the HVAC domain

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 30/58

© eeEmbedded Consortium www.eeEmbedded.eu

experts can set BACS generic controlling data according to ES results to optimize the HVAC

systems in the model.

EN 15232

This European Standard EN 15232 provides a structured list of control, building automation and

technical building management functions which have an impact on the energy performance of

buildings and the technical building system (EN 15232). Using BAC Efficiency Classes (A, B, C, and

D) of building automation and technical building management functions the required building

energy performance can be achieved. The EN 15232 provides a promising basis for a functional

description of building automation and control system which can be covered by BACS models.

ISO 16484

The international standard ISO 16484 provides a guideline for integrated planning and operation

of building automation and control systems. The standard defines BACS hardware, BACS functions

and a data communication protocol (BACnet) (ISO 16484).

VDI 3813

The German guideline VDI 3813 applies to room control applications in the field of building

services. The guideline is defining room automation (RA) functions which are grouped into

different function groups (sensor functions, actuator functions, operator and display functions,

application functions, management functions, and service and diagnosis functions). Each RA

function can be seen as a black box including an interface description (VDI3813).

Modelica Model

Modelica is a standardized, object-oriented, equation based language to conveniently model

complex physical systems containing, e.g., mechanical, electrical, electronic, hydraulic, thermal,

control, electric power or process-oriented subcomponents. Modelica models are behavioural

models which provide capabilities to describe major systems, subsystem and components of the

energy system (Modelica, 2015). There are a numerous open source Modelica libraries available,

containing building services system models, e.g. Modelica Buildings Library and Green Building

Library. Enhanced state chart modelling capabilities are provided since Modelica 3.3 specification,

enabling the description of simple and extensive control strategies (Modelica, 2015).

Energy Plus Data Model (IDD/IDF)

Energy Plus is a software application which provides functionalities for energy analysis and

thermal load simulation. The software takes into consideration the building geometry, user

behaviour and energy related systems. For the description of systems, a proprietary data model is

used and named as IDD/IDF format (IDD/IDF, 2015)

Green Building XML (gbXML)

The Green Building XML (gbXML) provides an open schema for exchanging BIM data. The data

structure is specialized in transferring building properties from BIM-CAD applications to

engineering analysis tools (gbXML, 2015).

Facility Smart Grid Information Model (FSGIM) UML

The FSGIM data structure facilitates an abstract representation of the energy consuming,

producing, and storage systems. It provides concept of modelling the energy characteristics of the

equipment and detailed information about systems (e.g. HVAC, lighting, security, facility

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 31/58

© eeEmbedded Consortium www.eeEmbedded.eu

management systems, and industrial automation systems) inside the facility. The FSGIM is

specified using Unified Modeling Language (UML) (FSGIM, 2015).

Smart Grid Architecture Model (SGAM) SysML

The Smart Grid Architecture Model developed by Siemens AG (Siemens, 2012) targets the

modelling of a smart grid architecture of intelligent electrical power grid covering technical,

functional, communication-related and informational aspects. The model contains data structures

of all major sub-domains of (electrical) energy systems (including generation, transmission,

distribution and facilities) relevant for the hand-over to end-users, see Figure 10. Because of the

focus on the electrical energy domain this model has to be extended to cover thermodynamic

facilities like heating and cooling systems. The SGAM is formulated with the help of SysML (SGAM,

2015).

Figure 10: Schema introducing the SGAM (SGAM, 2015)

3.2.2 End user requirements

In general an energy system related data model is intended to support the design team within the

design process elaborating, shaping and fine-tuning appropriate concepts for energy systems

related to the building and the building site taking into account the boundary conditions provided

by the neighbourhood.

The conceptual design of the energy system is one of the main tasks within the Urban Design

phase. Within the Early Design phase the energy systems will get more detailed and adapted on

the progress of the architectural design of the building.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 32/58

© eeEmbedded Consortium www.eeEmbedded.eu

In usual cases the energy system of a building or a neighbourhood is formed by a set of different

systems, subsystems and components. Reflecting the modularized concept of the system

engineering approach energy systems are formed by several main subsystems.

Figure 11 shows major subsystems of the energy systems containing (1) heat generation devices,

(2) heat storage, (3) heat distribution system covering heat circuits, (4) a controller device but also

the (5) consumption block.

The mentioned objects can be aggregated by function into several modules or blocks. Within a

system engineering approach typical systems configurations and setups are identifiable as a pre-

step for generalized and formalized abstraction. The outcomes of this analysis are transferred into

templates which could cover almost complete energy systems, subsystems or single components

as pre-defined modules for typical design cases. The eeE templates covering energy system data

will be structured in compliance with the introduction given in the chapters of this document.

Figure 11: Simplified example schema of energy system. Please note that not all required components and information flows of the ESIM are indicated (Zellner & Kaiser. 2015).

3.2.3 eeE Scope and Extensions

ESIM is a newly developed data structure that covers information related to the energy system (as

mentioned above: major system, subsystem and components of the energy system). Due to

strong interdependencies between energy system (building internal or external), HVAC system as

well as automation and control system, it is aimed that ESIM covers and includes BACS and HVAC

data structures as well.

Furthermore it is intended to follow a Multi-Model approach. Hence, the ESIM data structure will

include existing data structures as mentioned above and newly specified data structures. The new

specified data structures will close the gap of existing standards and will ensure an integrated

information space.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 33/58

© eeEmbedded Consortium www.eeEmbedded.eu

The scope of ESIM will be explained in detail within D4.2. More detailed information about

templates used regarding to energy systems is provided within D2.3 (Guruz et al., 2015b).

3.2.4 m2m dependencies in the eeE use cases

As mentioned above ESIM benefits from the Multi-Model approach within eeE. Currently ESIM

should be based on UML or SysML data structures stored within an XML-based file format,

potentially the XML Metadata Interchange (XMI) format.

There is no specific software application named ‘Energy System Designer’ (ESD) as editor for

energy systems within the DOW. Because of the early development status of ESIM and the affinity

of the current approach to UML/SysML existing editors could be used. NEM evinced interest for a

further implementation depending on the expected functionality of the editor. Due to that early

stage of development the m2m dependencies could be expressed as follows – in spite of further

specification later on in the project run: (1) The BIM-CAD Application ALLPLAN provided by

Nemetschek – which possibly contains a software module, providing functions similar to Energy

System Designer (ESD) – delivers information in the IFC format and potentially the data format of

the ESIM model (e.g. SysML) covering all design phases. (2) The Energy System Designer (ESD) –

possibly a SysML editor – generates the ESIM related data following the SysML data standard

covering all design phases with focus on the urban design phase. (3) The HVAC engineering

software application DDS CAD delivers especially HVAC related data, using the IFC standard and

the ESIM data structure, covering the early and detailed design phase. (4) The BACS design

software application Sauter eeBACS Wizard developed by Sauter AG delivers especially BACS

related data, using the IFC standard and the ESIM data structure within the early and detailed

design phase. (5) Downstream of the authoring tools ALLPLAN, DDS-CAD, ESD and Sauter eeBACS

Wizard the analysis tools (energy simulation SIM, life cycle cost analysis LCC and life cycle

assessment LCA) have to extract all the data out of IFC und ESIM data models covering

information of all design domains.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 34/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.3 HVAC Models

3.3.1 State-of-the-Art

HVAC devices and systems are designed and maintained by DDS-CAD BIM native model. At

present time software vendors provide functionality in native models to build a sustainable

model, from early phase generic product into detailed specific product and system design. The

HVAC designer interacts with other actors in different domains in the project and strongly

depends on a trustworthy flow of information. Data exchange processes between model domains

still depend on human knowledge although various Open BIM exchange models exist for different

purposes to assist the interaction between the model domains. Open BIM is a universal approach

to the collaborative design, realization and operation of buildings based on open standards and

workflows. Open BIM is an initiative of buildingSMART and several leading software vendors using

the open buildingSMART data model. In the following, the before mentioned exchange models

are listed:

Architecture/HVAC design domain o IFC2x3 model, IFC4 model (ISO 16739)

BACS/HVAC design domain o IFC2x3 model, IFC4 model (ISO 16739) o BACnet(ISO 16484-5), KNX (ISO/IEC 14543-3)

Building Energy and System Simulation domain o Green Building XML (gbXML) o IFC2x3 model, IFC4 model (ISO 16739)

The data structures and standards which already cover some HVAC aspects are introduced in

subchapter 3.2.1.

3.3.2 End user requirements

The vision is to enable the user to build a BIM HVAC system «As built» completely energy

optimized with integrated Building Automation and Control System (BACS). The eeEmbedded

target is to improve interoperability between actors in the different modelling phases of Building

Services domains with focus on energy analysis, using Open BIM. IFC4 supports the required HVAC

data needed to build a sustainable HVAC model in a building environment. State of the art is

mainly user driven and process and knowledge exchange oriented, instead of software assisted

data exchange. HVAC end users expect related model domains to exchange data and keep models

sustainable throughout all phases to meet the spaces climate and energy requirements.

Improved interoperability between actors is needed in the different modelling phases of Building

Services domains with focus on energy analysis, IFC4 usage and MVD (Model View Definition)

improvement as well as access to common templates, open libraries, products and materials. (i.e.

IFC Libraries and extensions)

3.3.3 eeE Scope and Extension

Stronger interoperability between domains is mandatory to achieve a sustainable HVAC model

during the BIM planning phases. Actors and domains are required to be familiar with the process

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 35/58

© eeEmbedded Consortium www.eeEmbedded.eu

and the date exchange format. BuildingSMART covers the format with IFC schema (as model),

various exchange views with MVD and the need for a common BIM communication platform with

BCF. The Scope and extension regarding the HVAC domain context of eeE is to improve HVAC

design and provide energy efficient buildings using Open BIM (IFC4) in the planning process.

3.3.4 m2m dependencies in the eeE use cases

Energy optimized HVAC solutions are designed in the HVAC domain. During the BACS design, the

model is enriched with BACS information adapted to the HVAC design. During a later LoD phase,

the HVAC model is checked and adapted to the chosen BACS solution. In the detailed design

phase, the chosen BACS and HVAC solutions are together placed for an optimal behaviour.

Architecture/HVAC design domain

One of the main and early phase factors in HVAC model build up is to establish the building spaces

need for ventilation, heating and cooling. What system is to be used, what sizing is needed to

provide required air exchange and space temperature. A building energy analyses is needed to be

done to provide a complete picture that covers all neighbourhood-spaces, including building

surface against air and soil, location, angle, shadows, space type, usage, occupancy rate, seasons,

etc. User comfort also covers noise reduction and the HVAC system’s ability to exchange air in

spaces. Analyses will often include sound, pressure, flow rate calculations and second level space

boundary to calculate heating and cooling load.

BACS/HVAC design domain

Energy optimization is an important part of the more detailed HVAC model build-up, selecting

HVAC products that in turn cover control strategies for energy management tuned by the

integrated BACS. Common accessible open product libraries and common templates to meet the

project and process requirement are preferred (i.e. IFC Libraries and extensions).

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 36/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.4 BACS Models

The BACS Model covers a data structure to describe all major systems, subsystems and

components of the building automation and control system. The BACS model comprises

information of all products and engineering services for automatic controls, monitoring and

optimization, for operation, human intervention and management to achieve energy-efficient,

economical and safe operation of building services.

The BACS model domain covers the whole automation pyramid in Figure 12. In detail, the BACS

model can be divided in Management Level (supervision of the building automation with a global

building controller), Automation Level (plant automation e.g. air handling unit according to

EN15232 with its main control functionality and interactions) and Field Level (Sensors and

actuators with its specific control).

Figure 12: Automation Pyramid Layer

The mentioned examples above refer to the automation pyramid for a building. However, the

automation pyramid also holds for districts. On district level the BACS model covers control

strategies for energy management, e.g. control of energy demand and energy supply. Figure 13

illustrates the relation between building level and district level of the BACS model. The BACS

model on district level can be seen as DACS model. However, it is part of the ESIM model domain

too.

Figure 13: Relation among DACS and BACS based on an illustration from (Solvik et al., 2014)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 37/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.4.1 State-of-the-Art

Currently there is no single model or standard available which covers all aspects of building

automation and control systems. Various models still exist which cover certain aspects and

provide data structures to enhance or adapt the models to cover information which are not

originally part of the model content. Certain examples for available models/standards are listed

below:

Architecture/Building Services design domain o IFC4 model SPF

HVAC design domain o Piping and instrumentation diagram (P&ID) (ISO 10628 and ISO 14617)

BACS design domain o EN 15232 o ISO 16484 o VDI 3813/3814 o Modelica model o KNX o BACnet

The BACS model in combination with the ESIM model is going to be newly developed in WP4.

However, there are already existing data structures covering some aspects of building automation

and control system related information. Those data structures and standards were introduced in

subchapter 3.2.1.

3.4.2 End user requirements

In general a building automation system related data model is intended to support the design

team within the design process elaborating, shaping and fine-tuning of appropriate control

strategies for operating the district energy system and technical building systems in an energy

efficient way while taking into account the building users comfort conditions.

The elaboration of basic control strategies for conceptual design of the district energy system is

one of the main tasks within the Urban Design phase. Within the Early Design phase the control

strategies related to the technical building systems and the user comfort will get more detailed

and adapted on the progress of the architectural and HVAC design of the building. In the Detailed

Design phase the functional control strategies are mapped to manufacture dependent BACS

equipment and the optimized placement of the sensors and network is elaborated.

From end-user point of view the BACS model covers information to facilitate (1) design of multiple

automation and control system configurations managing energy demand and supply while

maintaining user comfort, (2) specification of BACS function that generates multiple alternatives

and solutions based on EN 15232 that can be used later on in simulations, and (3) import of

products characteristics from data base and catalogues for BACS components (actuators, sensors

and controller).

3.4.3 eeE Scope and Extensions

In general the scope of the BACS model is to provide a data structure that allows to describe

software, hardware and service aspects according to the BACS definition illustrated in Figure 14.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 38/58

© eeEmbedded Consortium www.eeEmbedded.eu

BACS models are aimed to provide structural, functional and physical information of the building

automation and control system.

Figure 14: BACS model - eeE Scope (based on Frost & Sullivan, 2010)

The integration in the eeeBIM data model domain and especially the integration in the ESIM

information space form the main scope of the BACS model in eeE. Therefore the elaboration of an

appropriated BACS model concept and the integration in the ESIM and eeeBIM data model

domain is aimed. For this purpose, existing data structures and standards, mentioned above, will

be taken into consideration and potential information gaps will be defined. To overcome these

gaps the BACS model information space will be extended.

The following aspects have to be covered by the BACS data structure:

System and component description

Interface description (physical and functional interface)

Identifier description (physical and virtual data points)

Functional description (BACS and RA functions)

Manufacturer information

LCC/LCA information

A further aspect regarding the BACS model forms the generic BACS template concept. The

integration of BACS knowledge templates into the BACS data model domain has to be in line with

the aimed BACS concept.

3.4.4 m2m dependencies in the eeE use cases

There are strong dependencies to ESIM models and HVAC models from BACS model point of view.

ESIM (see section 3.2) covers a data structure to describe all major systems, subsystems and

components of energy systems and related data and objects including HVAC and BACS objects. In

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 39/58

© eeEmbedded Consortium www.eeEmbedded.eu

addition there are strong m2m dependencies among IFC4 models and BACS models as well. The

IFC4 model provides the physical representation (object geometry) and placement of the BACS

equipment inside the building.

Due to the early stage of development the m2m dependencies could be expressed as follows – in

spite of further specification later on in the project run.

In the Early Design conceptual BACS solutions are designed and elaborated by means of the

Sauter eeBACS Wizard. The Sauter eeBACS Wizard uses Architectural model (IFC4) and HVAC

model (IFC4), which provide results of the previous design steps carried out in the Architectural

and HVAC domain. The different BACS solutions are provided later on in an ESIM data structure,

which comprises the BACS model. In these early design steps the different control strategies,

described in BACS model, are interlinked to spatial structure elements (e.g. in case of room

automation) or to HVAC system types (e.g. in case of plant automation) contained in the IFC

model. Both, IFC model and BACS model form the basis for simulation and analysis tasks in Early

Design phase.

In the Detailed Design phase the physical representation of BACS equipment, fulfilling a specific

functionality, is added and the corresponding placement is done in the Architectural model (IFC4).

Further detailed control strategies for single HVAC components are elaborated. In general the

BACS model is used to carry a more detailed description of the BACS equipment, these include: (1)

BACS functional description, including interface and identifier specifications, (2) energetic

properties and behaviour, and (3) an integrated system view. In summery there exist strong

dependencies to Architectural and HVAC model (both IFC4) and ESIM model, whereas the latter

includes the BACS model data structure.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 40/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.5 FM Models

The Facility Management (FM) model on the whole supports all core parts of facility

management: communication, emergency preparedness and business continuity, environmental

stewardship and sustainability, finance and business, human factors, leadership and strategy,

operations and maintenance, project management, quality, real estate and property management

as well as technology.

One scope of eeE is to bring FM competence and information to support the analysis of FM

already during design. So it does not include the parts, which only support management of the

facility, when it is already built and taken into use. As a consequence FM models, which mainly

support the information hand-over to FM, such as COBie, are not included in the scope of eeE FM

models. On the other hand, a part of the information which supports operation and maintenance

of the building also allows analysis of FM during design.

3.5.1 State-of-the-Art

Model based FM applications are already available for space management, maintenance manual,

monitoring of energy consumption and environmental impacts, maintenance budgeting, long-

term planning, etc. Maintenance manual applications, utilizing models either on a restricted basis

or more widely, are available for management of technical data, service requests, contracts,

documents, various maintenance tasks and maintenance history.

The majority of current FM systems utilizes legacy data models. If building data is included, it is

typically included as vectorized drawings together with attributed data. Only few use open

standards like IFC.

Model-based analysis of FM during design is neither theoretically planned nor practically

implemented. Granlund Designer currently manages central HVAC equipment data and has

proprietary import/export links to chart level models of the HVAC system. Currently Granlund

Designer supports only design and contracting of HVAC and electrical systems and has no links to

FM information.

The FM modules for EDMmodelServer provide real integration with BIM models in IFC2x3, and

also utilize IFC2x3 for data storage of FM data, with some minor extensions.

3.5.2 End user requirements

FM module in Granlund Designer is used to link HVAC components to FM templates (service life,

maintenance need). Within the eeE scope and referring to eeE use cases, the end user

requirements sums up to: “As a user I want to enrich the data model with necessary FM data so I

can calculate maintenance costs.”

The input data required are taken from BIM. Within the eeE use cases only HVAC BIM for FM is

relevant. Each HVAC equipment object is linked to FM template based on the equipment type

definition. The attributes in the FM templates for each object type are amongst others the

expected life time and the service need (service program, spare parts).

The enriched data model is exported to be utilized by LCC to calculate FM cost as part of the life

cycle cost and by LCA to calculate environmental impact of the replaced HVAC components.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 41/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.5.3 eeE Scope and Extensions

The FM model is developed based on data structures that cover FM related information and is

linked to the HVAC model. The needed eeE extensions must ensure interoperability between

HVAC design and facilities management. This means identification and agreement on the

information and actual data sets needed for FM data exchange, and formulation of this

agreement as “FM exchange requirements”. This includes identification of IFC constructs needed:

zones, areas, volumes, spaces etc. To achieve necessary information exchange compatibility, the

IFC4 standard has to be supported. Finally, the FM data handling requires to link HVAC

components to FM templates, and to provide mapping of the FM templates to the actual data

sets defined for the exchange.

3.5.4 m2m dependencies in the eeE use cases

The FM tool will have the following dependencies: The Granlund Designer will receive its input

data in IFC4 format, primarily HVAC from DDS CAD. The extent of data will be defined as ERs

and/or MVDs as appropriate. FM data provided by Granlund Designer will be consumed by

LCC/LCA analysis tools. Information here will also be carried by IFC4 format, when applicable, and

defined as ERs and/or MVDs as appropriate.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 42/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.6 Climate Models

Energy analysis needs weather (atmospheric conditions over a short period of time) and climate

data (atmospheric behaviour over relative long period of time).

Climate data are used for building energy simulations, energy demand estimation, building and ES

design evaluations of different scenarios, long term building and system energy performance.

The need for appropriate climatic data for long term prediction of the annual energy performance

of buildings (e.g. thermal comfort conditions, heating and cooling loads) has led to the

development of the so called Test Reference Years (TRYs) a term mainly used in Europe or Typical

Meteorological Years (TMYs) a term mainly used in the USA.

Building simulation software requires comprehensive TRYs which are commonly composed of

hourly values for a one year period (12 typical meteorological months) rather than extreme

conditions of actual (measured) weather data. TRY data represent a year of typical climatic

conditions for a location, preserving the main local weather characteristics, for example, typical

cold or hot conditions, but consistent with the local long term averages. However, TRYs should

not be used to predict weather for a particular period of time.

A comprehensive overview of various weather data sets and methodologies is available in

(Crawley, 1998) and (Forejt et al., 2006).

For building energy analysis based on transient simulations the consideration of well-chosen

weather/climate data sets is essential to generate results which intend to be close to the real

world behaviour of the building and the existing energy systems. Due to the ability of the used

simulation models and the addressed LoD the following climate elements have to be part of the

weather/climate data set:

Global solar radiation on a horizontal surface

Diffuse solar radiation on a horizontal surface

Air temperature

Air humidity

Wind speed

Wind direction

Precipitation

3.6.1 State-of-the-Art

A weather profile is a continuous time series with a fixed hourly time step. Several standard

formats exist to catalogue weather data that have emerged over the years. Such weather profiles

can be obtained for many European locations. The most common weather data formats used for

energy calculation and simulation are:

Test Reference Year (TRY)

Typical Meteorological Year (TMY2)

Weather Year for Energy Calculation (WYEC2)

International Weather for Energy Calculations (IWEC)

Actual historic weather data (AHW)

Non reference years (NRY)

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 43/58

© eeEmbedded Consortium www.eeEmbedded.eu

Some simulation software vendors recommend using TMY2 or WYEC2 weather profiles. However,

not all energy calculation and simulation software depend on the standard formats for weather

data, but rather use their own proprietary formats. Such weather profiles can be constructed

from available historic weather data or by filtering and transforming standard profiles, provided

they contain all the necessary data.

The Test Reference Year format TRY provided by the German Weather Service ‘Deutscher

Wetterdienst DWD’ covers 15 locations/climate regions within Germany. The last update was

delivered in 2011. The data sets are available on hourly basis and contain three different data

sets: (1) normal average year, (2) hot year and (3) cold year.

The Typical Meteorological Year Format version 3 called TMY3 provided by the ‘National

Renewable Energy Laboratory (NREL)’ of the United States is available on hourly basis and the

current version was updated in 2015. The data sets are available for 1.020 locations within USA

and representing typical weather conditions.

The International Weather for Energy Calculations format IWEC provided by ASHRAE includes

data sets for 3.012 locations outside USA and Canada on hourly basis extracted out of the

Integrated Surface Hourly (ISH) data base maintained by the National Climatic Data Center (NCDC)

of the USA. This data sets cover weather information of up to 25 years.

The data are delivered on hourly basis for minimum one year. Certain commercial providers

deliver data sets on sub-hourly basis. For example “Metronome” application provides reliable

estimation of hourly weather data (e.g. solar radiation, temperature and other meteorological

parameters), based on over 8300 weather stations worldwide.

For long term analysis the climate change will be considered with the help of a drift factor used in

conjunction with the climate elements when analysing upcoming periods.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 44/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.7 Simulation Models

The simulation model for the whole building energy performance evaluation and assessment,

through all building design phases, involves many individual simulation models for each

simulation tool used. Building performance and behaviour aspects, like thermal efficiency

assessment and HVAC performance optimization, CFD analysis and thermal comfort criteria

fulfilment and interior lighting and acoustics simulation require a multitude of domain specific

models all linked to the BIM as a base of the whole building design. Heterogeneous multi-level

models are utilized across different engineering disciplines. In addition to the support of different

levels of detail users have also need to combine optimization computation and model uncertainty

assessment into their simulation experiments.

Following the definition of transient thermal simulation approaches according to VDI6020:2001

Blatt 1 (VDI 6020, 2001) two main classes of simulation models are identifiable: (1) thermal and

energy simulation of buildings (TEB), and (2) thermal and energy simulation of systems (TES).

Thermal building energy simulations (TEB), mentioned first, cover an analysis of the thermal

reaction of the building and/or certain spaces on transient inputs, especially taking into account

the outdoor climate, the user behaviour and the related set points for indoor temperature.

Depending on the used simulation models, the LoD modelling of the building itself and the

transient influences, this kind of analysis delivers results regarding spaces or parts of spaces and

the thermal behaviour of the building construction elements.

The second approach called ‘Thermal Energy System Simulation (TES)’ is based on or includes TEB

but also includes the behavioural models of HVAC and BACS systems and components. Both kinds

of analysis are working with simulation steps of maximum one hour or explicit lower time steps till

to seconds, depending on the question which has to be answered. They are strongly influenced by

the LoD of the used simulation models. In addition to the thermal behaviour of building and

spaces, detailed results describing the operation of the HVAC components and the energy system

are delivered.

CFD simulations are carried out for TEB and TES simulation coupled with Energy Simulations in

order to obtain the detailed indoor climate, e.g. for the optimal design of the building envelope,

the prediction of thermal comfort conditions, the evaluation of the HVAC performance, the

optimization of HVAC systems (size of diffusers and location in the zone) and the design of natural

ventilation.

3.7.1 State-of-the-Art

Various Building Energy Modeling (BEM) tools and interfaces have been developed for the energy

simulations of the whole building embedded in its environment and taking into account transient

conditions. Most of them are based on the ESP-r, Energy Plus, DOE-2, BLAST and TRNSYS

simulation engines that use a multi-zone approach considering one calculation node per zone for

air temperature determination. The most advanced tools include models for moisture conditions

of the indoor air, models for solar radiation gains, photovoltaic systems and renewable energy

sources use. Several alternative architectural designs are evaluated according to building energy

consumption cost dimension and results are incorporated to the lifecycle cost model to reach an

optimum trade-off between energy and cost resulting in an optimum design.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 45/58

© eeEmbedded Consortium www.eeEmbedded.eu

The BEM tools are used for: (1) thermal load simulation, for determining sizing of equipment such

as fans, chillers, boilers, etc. and (2) for energy analysis to determine thermal comfort conditions

and evaluating the energy cost of the building over longer periods of time (for an already

calculated HVAC system) and providing data for detailed analysis of some particular spaces via

CFD simulations.

Despite the existence of an increasing number of BIM models that are linked to energy

performance simulation models and the existence of models that are linked to BIM authoring

tools (CAD) within proprietary environments, there are still limitations to the current BIM tools for

energy analysis in terms of interoperability and quality of the results [Bazjanac, 2011]. The IFC

HVAC schema is currently widely used for HVAC information exchange between building ES tools.

Additional data exchange between ES tools usually requires proprietary data formats.

Typical ES data models are stand-alone, usually in the form of plain text files with poor or non-

existent interfaces for data exchange. In fact, there is no official standard for the simulation

domain. Existing simulation tools (E+, DOE-2, IES, etc.) fail to take advantage of standard data

exchange tools that are available for data in the XML or IFC format. More recent exchange

models, such as gbXML, enable the exchange of concepts previously defined in BDL and IDD using

XML (gbXML, 2010).

For CAD/BIM and ES interoperability the IFC model needs to be extensively pre-processed and

appropriate energy specific model views have to be derived that need to be enriched with

incomplete or missing domain specific information (e.g. thermal properties, occupancy and

operational schedules) to comply with the building model used by the Building Energy

Performance Simulation tools (BEPS) (Gudnason et al., 2015). Data enrichment platforms have

been previously demonstrated, for example in COBie (East et al., 2012) – an intermediary model

for “as built/operated” information in downstream FM exchange, by Simergy (See et al., 2011)

together with SimModel (O’Donnell et al., 2011) – a BIM based integration platform for whole

building energy performance simulation. The more generic Multi-Model framework for energy

enhanced BIM (Liebich et al., 2011) was developed in the EU project HESMOS and the platform

ontology, eeBIMOnto (Kadolsky et. al., 2014), in the EU project ISES.

3.7.2 End user requirements

End-users and especially non energy experts (like architects) require the seamless integration of

ES tools of escalating LoD and a decision making support in accordance to KPIs or user defined

energy performance criteria concerning the operation lifecycle of buildings.

Therefore a system, which organizes the data flow in a unified model, enabling effective exchange

of data is required. The final goal is to simplify and automate the information exchange processes

among different tools, and develop enabling technologies and platforms to facilitate and establish

an integrated system around a BIM-centred simulation matrix with multiple tools and users.

With all the above considerations and limitations in mind, the simulation domain requires an

interoperable data model that facilitates:

Data exchange between existing simulation tools

Bi-directional exchange of data within eeeBIM thus enabling seamless workflow

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 46/58

© eeEmbedded Consortium www.eeEmbedded.eu

Use of templates as another key feature that empowers users and allows them to leverage pre-configured data sets and configurations, thus expediting simulation model development.

Easy generation of design alternatives for optimization purposes.

3.7.3 eeE Scope and Extensions

A consistent data model (ESIM) across all aspects of the building simulation process and the

building lifecycle is required, thus preventing information loss. The model accounts for new

simulation tool architectures, existing and future systems, components and features. In addition,

it should be a multi-representation model that enables integrated geometric and MEP simulation

configuration data.

The eeEmbedded simulation data model intends to incorporate a number of features to address

current domain weaknesses (as highlighted in the State Of the Art subsection), a set of

requirements for a shared simulations model and is easily extensible to account for future domain

advances. It ensures interoperable exchange of simulation data within the simulation domain and

most importantly across an entire building project. The unique design enables interoperable data

exchange and uses a number of features to do so. These are:

Mappings to/from existing domain models

Property set definitions (for using an extended set of data types.)

Object type definitions

Model topology for energy systems

Templates with, where possible, reference to lower level data contained in libraries Representation of context and outputs upon user’s request

Analysis tools have to be integrated to the eeeBIM system and have to be linked with the data

provided by Architectural, ESIM (energy system), BACS and HVAC and FM data structures. They

also should provide suitable representation of output results to support decision making for

optimized building solutions.

3.7.4 m2m dependencies in the eeE use cases

Energy performance and thermal comfort simulation tools (TRNSYS for ES and CFD for urban

design and thermal comfort performance) require (1) building elements, 2nd level space

boundaries, products and materials (via IFC4 and/or XML files), (2) weather data (TRY or WDV), (3)

occupancy data and heating/cooling set point temperature(gbXML), (4) HVAC equipment data

produced with DDS-CAD MEP design tool (IFC2X3, IFC4, gbXML), (5) BACS equipment (IFC4), (6)

Type of analysis and Decision making parameters (job matrix, see chapter 3.5. Simulation

Management Services of D1.5) and (7) design alternatives.

CFD and ES tools use different space discretization and time scale. ES provides CFD analysis with

all the required boundary conditions for the detailed simulation of a subsystem of the building (or

even the whole building). ES results are mapped on IFC objects and are consequently translated to

boundary conditions on the space boundaries of the building or thermal envelope surrounding

the flow domain. HVAC systems (via ESIM model) are also included into the CFD model. CFD

simulation requires location, geometry and flow rate (m3/h) of the HVAC air suppliers, as well as

the air properties (in the psychrometric diagram) needed for the efficient

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 47/58

© eeEmbedded Consortium www.eeEmbedded.eu

ventilation/cooling/heating of the space. These data are provided by the HVAC manufacturers and

could stand as templates in the ESIM data model.

CFD simulations could provide more accurate U-values to ES tools for material assemblies of the

building.

Usually CFD detailed simulations are carried out for specific cases selected among design

alternatives obtained by ES on a yearly basis (i.e. worst case scenario or design that could not be

covered by ES, such as displacement or natural ventilation). The alternative approach is to couple

ES and CFD applications directly and exchange the convective heat transfer information between

the two programs.

All the data generated during CFD analysis are linked back to IFC Models. Mesh and CFD results do

not currently exist and will need to be developed as entities of the ESIM data model.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 48/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.8 LCC Models

The life cycle cost model is based on design-to-cost methodology considering the complex states

of different cost spread over the entire life of the system. The Cost-Code Catalogue is

fundamental and classifies different cost components and their relationships. The Cost Codes

Catalogue has a dual purpose. It forms the Cost Breakdown Structure (CBS) for the estimate.

Additionally, any branch of it can be used directly in the estimate or an assembly to hold a cost,

either with a fixed unit rate or with a floating unit rate. A hierarchical cost profile is used at each

level subsequently with the cost break down structure framework.

3.8.1 State-of-the-Art

The LCC model is supported by using iTWO modules, such as element planning, BoQ, cost

estimation, cost catalogues, object model, activity model, and scheduling to finally obtain the

desired output. The LCC model is structured using the data provided by architectural design, ES,

HVACS and by BACS. The file formats currently supported are CPI, IFC (IFC2x3, IFC4), DWG and

XML.

3.8.2 End user requirements

In order to obtain the desired Life Cycle Cost output, the user has to be enabled to match and link

the parametric design to the LCC templates. Furthermore the model has to provide the

opportunity to create miscellaneous cost catalogues, including all costs, which arise in the whole

life cycle of a building. This cost catalogue consists of information such as labour, equipment,

maintenance, operational planning, etc. The user also should have the possibility to import actual

costs from XML- or CSV files. Moreover the user needs to be able to generate remaining costs

from existing data. These costs need to be integrated with projected costs in the LCC cost

breakdown structure to provide a time-dependent analysis of a projects whole life cycle cost

process. These multiple processes have to be performed in parallel. Furthermore, the LCC model

has to support project phasing in the different use cases. Controlling functions and structures

have to be created, which provide flexible methods for the clients to manage and understand the

project. And users should be able to assign activities or BoQ elements to controlling units.

3.8.3 eeE Scope and Extensions

The LCC model will be developed based on data structure that covers information related to the

total cost involved in the life cycle of a building. To estimate the entire life cycle of a building, this

model must be linked with the data provided by the Architectural, ESIM, BACS and HVAC, FM data

structures.

Thus, it is the scope with the perspective of cost analysis to evaluate the exploratory part of data

from energy, HVAC, BACS and FM stimulation. Hence, results from these model domains on each

use case will enable decision-making from cost realization perspective. The LCC tool will enhance

decision-making and financial planning by facilitating decision makers to select the most

economical infrastructure

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 49/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.8.4 m2m dependencies in the eeE use cases

Currently the LCC model is described as XML-based file format stored in an SQL database. The

m2m dependencies in eeE use cases can be defined as follows: The data model of Allplan as

IFC4 file is required for the calculation of all costs which arise in the entire life cycle of a building.

Any other information that are essential to evaluate the LCC must be provided as schematized

XML file in order to evaluate the results of each corresponding domain. This includes, for instance,

all evaluations of the HVAC, BACS and FM domain. The resulting outcomes are forwarded to the

decision-making domain as XML-based files.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 50/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.9 LCA Models

The life cycle assessment model is based on design-to-environmental methodology considering

the different material and potential impacts associated over the entire life of the building. The

commodity catalogue is used to store material estimation codes. The advantage of using

commodities as material in LCA models is to set wastage factors, link commodities to ERP

database, carry out material quotation, comparisons and specifies material details like densities to

calculate the potential environmental impact. Commodities are arranged hierarchically. LCC and

LCA analysis in an early design phase are used to perform a risk assessment. Thus, evaluating

economic and environmental design decisions allows developing more sustainable urban areas.

3.9.1 State-of-the-Art

The LCA model is supported by using iTWO modules such as element planning, BoQ, material

estimation, commodity catalogue, and currency catalogue concerned with the assignments

management of the LCC model. The LCA model is structured using the data provided from

architectural design, energy system, HVAC system, building automation and control system. The

file formats currently supported are CPI, IFC (IFC2x3, IFC4), DWG and XML.

3.9.2 End user requirements

In order to obtain the desired Life Cycle assessment, the user has to be enabled to match and link

the parametric design to the LCA templates. Furthermore the model has to provide the

opportunity to create new commodity groups, subgroup including all material specifications,

which can arise in the whole life cycle of a building. Commodities are referenced to cost codes to

estimate the required cost associated with the project to carry out LCC. Thus, LCA estimates the

environmental factor associated with the building and further linked to estimate the cost due to

these impacts on the project. This cost catalogue consists of information such as material

specification, density, unit of measurement, etc. The user has to get the possibility to import

commodity libraries from excel or import and export in XML files. The commodities can be

mapped to a resource so that the estimated detail can be passed to schedule. Moreover, the LCA

model needs to support project phasing in the Early Design and in the Detailed Design use cases.

3.9.3 eeE Scope and Extensions

The LCA model will be developed based on data structure that covers information related to the

material involved in the life cycle of a building. To estimate the entire life cycle of a building, this

model will be linked with the data provided by the Architectural, ESIM (energy system), BACS,

HVAC and FM data structures.

For eeE scope with the perspective of LCA, data are strongly dependent on ESIM, HVAC; BACS and

FM stimulation data. Thus, results from these model domains on each use case will enable

decision-making for material specification and detailing.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 51/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.9.4 m2m dependencies in the eeE use cases

Currently the LCA model is described as XML-based file format and stored in an SQL database. The

m2m dependencies in eeE use cases can be defined as follows: The data model of Allplan as an

IFC4 file is required for the calculation of any ecological impacts which arise in the entire life cycle

of a building. Any other information that is essential to calculate LCA must be provided as

schematized XML file in order to evaluate the results of each corresponding domain. These

include, for instance, all evaluations of the HVAC, BACS and FM Domain. The resulting outcomes

will be forwarded to the decision making domain in XML files as well.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 52/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.10 Uncertainty Information Models

3.10.1 State-of-the-Art

There exists a variety of concepts about risk in general. In some approaches, risks are associated

with negative events and disadvantageous consequences only. For others it is defined as an error

in a process. Risk can be defined and assessed in terms of fatalities and injuries, in terms of

reliability of a system, in terms of sample of a population or even in terms of the likely effects on a

project. All these points of view are valid regarding the domain they reflect (Smith, Merna, &

Jobling, 2006). The ISO 31000:2009 standard defines risk as the 'effect of uncertainty on

objectives'. In this definition, uncertainties can be both negative and positive impacts on

objectives.

The standard and the common professional practice define four essential steps to be executed as

part of the risk management procedure. These are: (1) risk identification, (2) risk analysis, (3) risk

treatment planning and (4) risk monitoring. Even if such a methodology is quite precise and well

formalized there exists no concrete standard for risk data modelling and risk assessment.

Modelling risk can be done in different ways, in a specific proprietary form by software vendors

(@Risk, Frontline Solvers, Oracle’s Crystal Ball, R, etc.) or user defined by end users utilising

common tools not dedicated for risk modelling. In view of that, even if the developments in

eeEmbedded will rely on existing methods, new specific approaches for stochastic and risk

modelling shall be developed. As an example one substantial source of innovation comes from the

expected interrelationship between Multi-Model BIM and risk.

3.10.2 End user requirements

To allow for reliable energy efficient building design and especially the design of complex energy

systems with highly dynamic control systems there is a need for taking into consideration

uncertainty that evolve over the life cycle of the project. Uncertainty is inherent because of the

strong dynamic energetic environment of the building in which building usage, climate, costs,

system characteristics, components wear, the energy market, etc. change and fluctuate over time.

To support the designer in managing this uncertainty it is necessary first of all to identify relevant

stochastic variables and related risks that have impact on the building performances over its life

cycle. In view of that, the stochastic information has to be modelled in a suitable and generic

manner in order to interlink it with BIM and to process it in a BIM-based risk management

procedure. Based on such models the designer shall be able to derive the risk level of its design

solutions and more precisely how uncertain the performances are over time and how much they

could deviate from the legal and end user tolerances. Moreover alternative design solutions that

reduce risk shall be implemented. For that purpose the designer shall rely on specific expert

knowledge.

3.10.3 eeE Scope and Extensions

In order to fulfil the end user requirements mentioned above, it is expected in eeE to develop

dedicated stochastic and risk models related to the specific aspects of vulnerability, sustainability

and cost. More precisely the stochastic nature of the building will be considered in the forecasting

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 53/58

© eeEmbedded Consortium www.eeEmbedded.eu

of building energy demand, CO2 emission, energy system malfunction and underperformance as

well as life cycle costs that include investment, maintenance, operation, demolition costs and the

return of investment. Related stochastic models as well as three specific energy risk models

namely vulnerability risk, sustainability risk and cost risk models are the backbone for performing

risk analyses. Those analyses are based on adapted simulation methods that allow for the

computation of specific risk indicators. On one side it requires the extension of existing simulation

methods or the creation of new ones on the basis of the stochastic models. On the other side it

requires also the integration of the energy risk models in the eeeBIM Multi-Model framework. As

a result risk prognoses can be made on the basis of Multi-Models providing enough

interoperability between risk models and simulation tools like TRNSYS or R.

3.10.4 m2m dependencies in the eeE use cases

There exist strong m2m dependencies among risk model and energy system information model

(ESIM). The conceptual design of different energy system alternatives is one of the main tasks

within the Urban Design phase, whereas the winning alternative will get more detailed in the

Early Design phase. By means of defining relations among risk model and systems, subsystems

and components of the energy systems, described in the ESIM data structure, an appropriated

analysis of the design alternatives can be performed already in early design stages.

Following a template-based design, multiple energy concepts can be elaborated, as mentioned in

chapter 4.5, in a modularized and schematic way. Therefore the integration of risk models into

the design templates is advisable. By doing that e.g. a design template describing a components

of the energy system provides detailed information about energy, vulnerability or cost risks.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 54/58

© eeEmbedded Consortium www.eeEmbedded.eu

3.11 Decision Making Support Models

The decision making support model or system combines the results obtained from simulation

models, ESIM, LCC, LCA models in an attempt to support the decision making process that aims to

meet intended target values and determine different alternatives on the basis of the best possible

solution(s). For instance, energy simulations produce a very large number of design solutions and

the user needs powerful visualization tools that can be easily customized in order to facilitate the

decision making process. The visualization tool is comprehensive and enables intuitive reasoning

for decision makers to analyse the simulation results, investigate the effects of the variables

taking into account different KPIs and assess the impact on different alternatives. The graphical

representation uses advanced techniques for the visualization to best represent the results.

3.11.1 State of the Art

Currently there is no application that functions as a decision support system and that is able to

visualize results from different simulations containing data related to energy, costs, sustainability

in a single application.

3.11.2 End user requirements

In general terms the decision makers, end-users, facility manager and designers need a decision

support system that is able to combine different results from different simulations to best support

the decision making process in form of KPIs. In addition, based on weighted preference by the

users for the different KPIs, the user can also have the possibility to obtain a Decision Value. For

instance, the DV could be a passive house, Deutsche Gewerkschaft für Nachhaltiges Bauen

(DGNB) certification, Leadership in Energy and Environmental Design (LEED certification or a

building with a return of investment of 5%. The DVs may vary depending on the targets for the

building and the performance of their systems. In principle, a DV is determined by weighting

different Key Performance Indicators (KPIs) obtained from different simulations performed during

the design phase. KPIs specify a performance during operations that could be related to final

energy need, thermal comfort or lifecycle costs. These values are influenced by Key Design

Parameters (KDPs). These parameters are related to spaces or elements/systems, some of those

are constraints and some of them are variables, the constraints have to be checked in the design

authoring tool. Some examples of Key Design Parameters include for instance:

Architectural: shape of the building, size of the zones, clear height, width, depth of the

room etc.

HVAC: operating requirements, heating, cooling, electricity type, product quality, service

lives, etc.

An illustration of the decision making model is presented in Figure 15 that shows the relationship

between DVs, KPIs and KDPs.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 55/58

© eeEmbedded Consortium www.eeEmbedded.eu

Figure 15: Graphical representation of Key Design Parameters, Key Performance Indicators and Decision Values (Guruz et al., 2015)

Some of more detailed user requirements include the ability to prepare charts and get simulation

results from BIM server or ontology. The decision support tool, called Multi-KP, prepares a

ranking of alternatives based on KPIs and forwards it to the Multi-Model navigator. The Multi-KPI

tool presents the key performance indicators on basis of simulations, LCC and LCA processed data.

In addition, the user has the option to visualize KPI data and compare different KPIs between

configurations and between versions of alternatives. The end user must commit to a type of chart

as well as to the DV to be shown by a mean factor.

3.11.3 eeE Scope and Extensions

In eeE the decision support tool will support decision makers, designers and facility managers to

select the result KPIs from different simulation models via their graphical representations. The

tool will not only cover energy aspects but also costs and sustainability. The calculation of DVs and

the additional graphical representation is one of the main aspects of the development of the

decision support tool in the eeE project context.

3.11.4 m2m dependencies

The decision support tool will use simulation results from ESIM, LCC and LCA to visualize the result

KPI, utilising advanced visualization techniques. The results are sent as annotated CSV file to the

Multi-KPI server. The Multi-KP tool could work as a service aside the Multi-Model Navigator or be

embedded in the application.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 56/58

© eeEmbedded Consortium www.eeEmbedded.eu

Outlook

In D4.2 the energy system concept will be elaborated within the urban design phase based on the

user requirements, the energy related neighbourhood and the resulted architectural draft. The

Energy System Information Model (ESIM) describes all parts of the energy system and subsystem

including parts and aspects of HVAC and BACS components. It contains also links to architectural

objects, HVAC, BACS components because those are modelled within IFC. The structure of the

ESIM follows the modularized concept of energy systems.

In D4.3 the general concept for the Link Model which was developed in the Mefisto project will be

used as baseline for interlinking the BIM domain models and eeeBIM models, like climate and

user behaviour models, BACS and ESIM. The eeBIM methodology which was developed in the

HESMOS project will be applied as a starting point. The different kinds of links will be identified

based on the information identified in this deliverable and in D4.2. The related different types of

relations and relationship objects will be developed and the requirements for the link attributes

and the transformation and mapping functions will be defined.

D4.4 is dedicated to the Multi-Model Manipulation. This deliverable will therefore give an

overview of the manipulation types and the environments they are executed in, that are for

example data models, repositories and servers. The manipulation will be realized via manipulation

services. They support the use cases presented in WP1 and will be listed and linked to the use

cases accordingly. D4.4 will also cover the according software implementation and its

documentation.

In D4.5 the filtering of Multi-Models will be covered in detail. Filtering is needed in nearly any kind

of model management and information handling, for example to prepare the BIM for the link

models. To link external non-BIM model data with BIM elements, the necessary BIM elements

have to be filtered first from the BIM. A modularized filtering approach will be used based on the

filter toolbox developed in the Mefisto project, which will be further extended and adapted for

eeE. The modules will be structured in 3 layers: meta data layer, semantic data layer and end-user

query layer. The modularisation allows re-using and adjusting the filter modules to the three

identified generic use cases. This existing filter toolbox will be extended in D4.4 by new ee-

functionalities, ee-query modules and the modules needed for the new ESIM and BACS semantic

model and the BACS data format.

D4.5 will address the Multi-Model Container, an approach for the exchange of interlinked data

from different AEC domains. The Multi-Model Container combines different domain models as so

called elementary models and link models and allows connecting construction elements from the

BIM model with other models, elements or files. Although the term container suggests it, the

elementary models and the link models are not necessarily encapsulated in such a container but

can remain in their respective model repositories, bound together by respective meta data

(tentatively planned to be implemented in RDF format). In this context, container is a rather

abstract term describing its enveloping functionality. Another possibility is a combination of both

approaches where for example some models are contained while others are stored on a server. In

D4.5 the definite architecture and software implementation of the Multi-Model Container in the

eeE context will be presented.

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 57/58

© eeEmbedded Consortium www.eeEmbedded.eu

References

Bazjanac V., Maile T., O'Donnell J., Rose C., Marzovic N. (2011); Data Environments and processing in semi-automated simulation with EnergyPlus, Proceedings of the CIB W78-W102 2011: International Conference –Sophia Antipolis, France, (2011) 26-28 October.

Calleja-Rodriguez G. & Guruz R. (2014); eeEmbedded Deliverable D1.3: Interoperability and collaboration requirements © eeEmbedded Consortium, Brussels.

Crawley D. B. (1998); Which Weather Data Should You Use for Energy Simulations of Commercial Buildings?, ASHRAE Transactions, Vol. 104, Pt. 2, pp. 498?515.

DIN EN 15232 - Energy performance of buildings – Impact of Building Automation, Controls and Building Management. German version FprEN 15232:2011.

DIN EN ISO 16484 - Building automation and control systems (BACS) -- Part 3: Functions.

East B., Carrasquillo-Mangual M.(2012); The COBie Guide: a commentary to the NBIMS-US COBie standard, Available from http://projects.buildingsmartalliance.org/files/?artifact_id=4994.

eeEmbedded 2013-17, EU FP7 Project No. 609349. eeEmbedded [online], http://www.eeEmbedded.eu.

eeEmbedded: Description of Work, EU Project eeEmbedded, Grant No. 609349, Version 2013-06-13, Brussels.

eu.bac – Certifying Energy Efficiency of Building Automation and Control Systems, a first delivery and during the lifetime – Part 4: Specification of Key Performance Indicators.

Forejt L., Hensen J. L. M., Drkal F. & Barankova P. (2006); Weather data around the world for the design of field hospital HVAC, Proc. 17th Int. Air Conditioning and Ventilation Conference, Prague, CZ.

Frost & Sullivan (2010); European Building Automation Systems Market -Paving the Way for Smart and Energy Efficient Buildings.

FSGIM (2015); Facility Smart Grid Information Model [online], https://osr.ashrae.org/Public%20Review%20Draft%20Standards%20Lib/ASHRAE%20201%20APR%20Draft.pdf

Fuchs S. & Nityantoro E. (2013); BIM-Management von Multimodellen, Dresden: Technische Universität Dresden, Institut für Bauinformatik

gbXML (2014). Open Green Building XML. Available from: <www.gbxml.org>.

gbXML (2015). Open Green Building XML Schema: a Building Information Modeling Solution for Our Green World [online], http://gbxml.org

Geißler M.-C., Guruz R., van Woudenberg W. (2014); eeEmbedded Deliverable D1.1: Vision and requirements for a KPI-based holistic multi-disciplinary design, © eeEmbedded Consortium, Brussels.

Geißler M. C., Guruz R., van Woudenberg, W. (2014); eeEmbedded Deliverable D1.2: Use case scenarios and requirements specification, © eeEmbedded Consortium, Brussels.

Gudnason G., Katranuschkov P., Scherer R.J. & Balaras C.A., (2015); Framework for sharing and re-use of domain data in whole building energy simulation, ECPPM 2014, eWork and eBusiness in Architecture, Engineering and Construction – Martens, Mahdavi & Scherer (Eds), pp.495-202

D4.1 BIM Multi-Model, Multi-Physics Models and Management Methods

Version 1.3

Page 58/58

© eeEmbedded Consortium www.eeEmbedded.eu

Guruz R., Calleja G. & Geißler M.-C. (2015); eeEmbedded D2.1: Holistic multi-disciplinary KPI-based design framework, © eeEmbedded Consortium, Brussels.

Guruz R., Calleja G. & Geißler M.-C. (2015); eeEmbedded Deliverable D2.3: Holistic KPI based design methodology © eeEmbedded Consortium, Brussels.

IDD/IDF (2015); Energy Plus – Input-Output Reference [online], http://apps1.eere.energy.gov/buildings/energyplus/pdfs/inputoutputreference.pdf

ISO 10628: Diagrams for the chemical and petrochemical industry.

ISO 14617: Graphical symbols for diagrams.

Kadolsky M., Katranuschkov P., Dolenc M., Baumgärtel K., Klinc R. & Gudnason G. (2014); ISES Deliverable D3.1: Ontology specification, © ISES Consortium, Brussels.

Liebich T., Stuhlmacher K., Katranuschkov P., Guruz R.,Nisbet, N., Kaiser J., Hensel B., Zellner R., Laine T., Geißler M.-C. (2011); HESMOS Deliverable D2.1: “BIM Enhancement Specification2, © HESMOS Consortium, Brussels.

Modelica (2015); Introduction of OPENMODELICA [online], https://www.openmodelica.org/

O’Donnell J., See R., Rose C., Maile T., Bazjanac V. and Haves P. (2011); SimModel: A Domain Data Model for Whole Building Energy Simulation. In Proceedings of the 12th Conference of International Building Performance Simulation Association, Sydney, Australia, 14–16 November.

Scherer R. J. & Schapke S.-E. (eds.)(2014); Informationssysteme im Bauwesen – Modelle, Methoden und Prozesse (information Systems in Building Construction – Models, Methods and Processes), Springer Vieweg, DOI 10.1007/978-3-642-40883-0, 609 p.

See R., Haves P., Sreekanthan P., O’Donnell J., Basarkar M. and Settlemyre K. (2011); Development of a User Interface for the ENERGYPLUS™ Whole Building Energy Simulation Program. In Proceedings of the 12th Conference of International Building Performance Simulation Association, Sydney, Australia, 14–16 November.

Siemens AG (2012); Siemens entwickelt europäisches Architekturmodell für Smart Grids [online], http://www.siemens.com/press/de/pressemitteilungen/?press=/de/pressemitteilungen/2012/infrastructure-cities/smart-grid/icsg201205018.htm

Smith N., Merna T. & Jobling P. (2006); Managing risk in construction projects. Blackwell Publishing.

Solvik K., Kaiser J., Geißler M.-C., Stenzel P., (2014); eeEmbedded D1.4: Requirements for knowledge-based design support and templates, © eeEmbedded Consortium, Brussels.

SysML (2015); SysML Open Source Specification Project [online], http://sysml.org

VDI 3813 – Part 2 2011. Building automation and control systems (BACS) - Room control functions (RA functions). VDI, Beuth Verlag, Berlin.

VDI 6020 – Blatt 1 2001-05. Requirements on methods of calculation to thermal and energy

simulation of buildings and plants - Buildings. VDI, Beuth Verlag, Berlin.

Zellner R., Kaiser J. (2015); eeEmbedded Deliverable D2.2: Templates for fast semi-automatic detailing, © eeEmbedded Consortium, Brussels.

Zellner R., Guruz R., Mosch M., Katranuschkov P., Tøn A. & Kaiser J. (2015); eeEmbedded Deliverable D1.5: System Architecture of the virtual holistic design lab and office © eeEmbedded Consortium, Brussels.