WCCUSD Bond ProgramConstruction Update
Edward Downer Elementary School Playfield RenovationStatus Update
10/14/14
Construction Manager: Gabriel Fortich (SGI)
Inspector of Record: Man Wah Cheng
Architect of Record: BCA Architects
General Contractor: Maggiora & Ghilotti, Inc.
Edward Downer Elementary SchoolPlayfield Renovation
Project
Project Team
Fine grading to commence 10/20/14 -11/24/14
Sod Installation to commence on 10/27/14 – 10/31/14
Irrigation booster pump 11/6/14 – 11/13/14
Field complete 11/15/14
Edward Downer Elementary SchoolPlayfield Renovation
PROJECT SUMMARY
Edward Downer Elementary SchoolPlayfield Renovation
Project
Project Summary
Project Duration: 180 (Calendar
Days)
Notice To Proceed Date: May 19, 2014
Completion Date: Nov 15, 2014
Percent Complete: 90%
Base Contract Amount: $563,226.00
Change Order to date: .1%
Edward Downer Elementary SchoolPlayfield Renovation
Project
General Information
Edward Downer Elementary SchoolPlayfield Renovation
Project
Graded Site
Edward Downer Elementary SchoolPlayfield Renovation
Project
Landscape Planting