19
Document Number: EDS 08-0117 Version: 8.0 Date: 30/03/2017 THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE ENGINEERING DESIGN STANDARD EDS 08-0117 INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT Network(s): EPN, LPN, SPN Summary: This standard describes the methods for ensuring the correct introduction of new equipment on the network to ensure the safety and security of personnel and the network. Author: Paul Dyer Date: 30/03/2017 Approver: Paul Williams Date: 02/05/2017 This document forms part of the Company’s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Applicable To UK Power Networks External Asset Management G81 Website Capital Programme UK Power Networks Services Connections Contractors Health & Safety ICPs/IDNOs Legal Meter Operators Network Operations Procurement Strategy & Regulation Technical Training

EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Embed Size (px)

Citation preview

Page 1: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

TH

IS IS

AN

UN

CO

NT

RO

LL

ED

DO

CU

ME

NT

, T

HE

RE

AD

ER

MU

ST

CO

NF

IRM

IT

S V

AL

IDIT

Y B

EF

OR

E U

SE

ENGINEERING DESIGN STANDARD

EDS 08-0117

INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT

Network(s): EPN, LPN, SPN

Summary: This standard describes the methods for ensuring the correct introduction of new equipment on the network to ensure the safety and security of personnel and the network.

Author: Paul Dyer Date: 30/03/2017

Approver: Paul Williams Date: 02/05/2017

This document forms part of the Company’s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue.

Applicable To

UK Power Networks External

☒ Asset Management ☒ G81 Website

☒ Capital Programme ☒ UK Power Networks Services

☒ Connections ☐ Contractors

☐ Health & Safety ☒ ICPs/IDNOs

☐ Legal ☐ Meter Operators

☐ Network Operations

☒ Procurement

☐ Strategy & Regulation

☐ Technical Training

Page 2: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 2 of 19

Revision Record

Version 8.0 Review Date 02/05/2022

Date 30/03/2017 Author Paul Dyer

Reason for update: Updated to incorporate further clarification to the process regarding the approval of third party materials. Document reviewed and review date extended.

What has changed: Update to Section 6.2 to further clarify the process involved with the approval of third party requested materials. Additional Appendix H added to provide an estimate of indicative new material approval costs.

Version 7.0 Review Date 21/02/2018

Date 22/02/2016 Author Paul Williams

Why has the document been updated: Updated to incorporate further clarification to the document to be published on G81.

What has changed: Update to Section 6.1 to clarify the required minimum length of after sales service. Update to Section 6.2 to highlight the basis on which the costs associated with approving new equipment requested by a third party shall be estimated.

Version 6.0 Review Date 23/01/2018

Date 08/09/2015 Author Paul Dyer

Why has the document been updated: Updated to incorporate document to be published on G81.

What has changed: Update to Section 1 (Introduction) referencing G81 website. Update to Section 2 (Scope) adding reference to ‘third parties’. Update to Section 5.1 (Selection) adding reference to ‘internal and external’ customers. Sections 5.5 (Rollout) and 5.6.1 adding reference to manufacturer. Section 6.2 title updated to ‘New Equipment – Proposal by Third Party’.

Row added (Satisfactory customer experience (internal and external) to Appendix A table ‘Desktop Evaluation’.

Version 5.0 Review Date 23/01/2018

Date 23/12/2014 Author Paul Dyer

Why has the document been updated: Periodic review

What has changed: Third party implications introduced into Sections 1 and 2. Section 6 added, and Section 7 check list modified. References to CDL changed to Alfresco. References to Ellipse changed to Asset Register.

Version 4.1 Review Date 18/02/2014

Date 15/09/2011 Author John Lowe

Re-classified to an EDS

Version 4.0 Review Date 18/02/2014

Date 24/08/2010 Author Paul Dyer

Revised and re-branded

Version 3.0 Review Date

Date 12/12/2006 Author Paul Elliott

‘new equipment’ replaced by ‘network equipment’ in section 2

Version 1.0 Review Date

Date 13/10/2006 Author Paul Dyer

Original

Page 3: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 3 of 19

Contents

1 Introduction ............................................................................................................. 4

2 Scope ....................................................................................................................... 4

3 Glossary and Abbreviations ................................................................................... 4

4 Definitions ................................................................................................................ 4

5 Process .................................................................................................................... 5

5.1 Selection ................................................................................................................... 5

5.2 Trial ........................................................................................................................... 5

5.3 Technical Approval .................................................................................................... 6

5.4 Training ..................................................................................................................... 7

5.5 Rollout ....................................................................................................................... 7

5.6 Documentation .......................................................................................................... 7

5.6.1 Installation ................................................................................................................. 7

5.6.2 Operation .................................................................................................................. 8

5.6.3 Maintenance .............................................................................................................. 8

5.6.4 Dismantlement and Disposal ..................................................................................... 8

6 Approved Status ...................................................................................................... 8

6.1 Previously Approved Equipment ................................................................................ 8

6.2 New Equipment – Proposal by Third Party ................................................................ 9

7 Control Forms .......................................................................................................... 9

7.1 Check List ................................................................................................................. 9

8 References ............................................................................................................... 9

8.1 UK Power Networks Standards ................................................................................. 9

Appendix A - Form A – Manufacturer Approval .............................................................. 10

Appendix B – Form B – Equipment Approval ................................................................. 11

Appendix C – Form C – Factory Assessment ................................................................. 12

Appendix D – Form D – HSS Approval and Final Sign Off ............................................. 15

Appendix E – Process Flow Diagram .............................................................................. 16

Appendix F – Switchgear.................................................................................................. 17

Appendix G - Transformers .............................................................................................. 18

Appendix H – Current Estimated Costs of Approving New Equipment ........................ 19

Page 4: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 4 of 19

1 Introduction

The networks owned by UK Power Networks (UKPN) are of significant size and complexity, and employs hundreds of operational staff and contractors working across a diverse geographical area. It is essential that the introduction of new equipment or technology is carried out in a consistent, controlled, well researched and communicated manner, in order to minimise the effect of change on day to day activities and to ensure that the most suitable equipment is effectively used on the network.

A list of currently approved network equipment is published on the G81 website. This standard takes account of third parties who wish to provide and install equipment to be connected and adopted by UK Power Networks.

2 Scope

This document defines the process to be followed for the introduction of network equipment and technology onto the network. The process is to be followed by UKPN Asset Management staff and third parties seeking to introduce new equipment and technology, and this standard details the formal requirements that shall be complied with. This standard also applies to:

Private Networks where equipment common to UK Power Networks is used;

Third party installers where the equipment is to be adopted by UK Power Networks;

Innovative equipment that is to be trialled on the Networks.

3 Glossary and Abbreviations

Term Definition

CIC Competitions in Connections

ENMAC/Power On UK Power Networks network management system.

UK Power Networks UK Power Networks (Operations) Ltd consists of three electricity distribution networks:

Eastern Power Networks plc (EPN).

London Power Network plc (LPN).

South Eastern Power Networks plc (SPN).

4 Definitions

New plant or equipment – is plant or equipment that is not yet approved or used on the network but whose function is one which is established, and in wide use within UK Power Networks.

A significant modification or alteration to an existing piece of plant or equipment necessitating additional training or technical knowledge would also be classed as new plant or equipment for the purposes of this standard. An example of new plant or equipment would be the introduction of a new type of ring main unit or major change in design or manufacturing location of currently approved equipment.

New technology – refers to a piece of plant or equipment, or a technique or way of working, or both, that is not currently in wide usage within UK Power Networks and which it may be desirable to investigate further for future potential deployment within UK Power Networks.

Page 5: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 5 of 19

5 Process

One of the roles within UKPN Asset Management is to identify new technologies and plant that will allow the company to meet its business objectives. A typical example is new plant to allow for network automation to improve Quality of Supply performance or to meet the demands of our Asset Replacement Programme.

To satisfy legislative requirements, the company must ascertain for itself that an asset is fit for purpose and that it is only operated by trained personnel. This can be achieved through a number of routes principally including:

UK Power Networks Specifications;

ENA Assessment;

BS/EN/IEC Standards;

ENA Technical Specifications;

Considerations of the ‘Designer’ role under CDM;

A robust operator training procedure:

It is also critical that the whole life cycle of the plant is taken into consideration – selection, trial, technical approval, testing, training, rollout, installation, operation, maintenance, dismantlement and disposal, and environmental and safety impact.

The process of selection, trial and technical approval of equipment should be carried out as follows.

5.1 Selection

The initial selection of equipment should be based on current knowledge of the market, the equipment known to be available and its compliance with UK Power Networks technical specifications. This will require an inspection of the equipment, and an assessment of its compliance with UK Power Networks specifications, including associated type test results as appropriate.

The selection shall also take account of the known performance and service history of the equipment using information such as DINS, SOPS NEDERS defect history and references from other internal and external customers.

5.2 Trial

Once the equipment has passed the initial validation stage a trial of the product can be initiated. The purpose of the trial is to assess the suitability of the equipment for wide scale usage within UK Power Networks. The suitability should be assessed not only by the equipment’s continued compliance with UK Power Networks technical specifications, but also by taking into consideration information and comments obtained from operational staff as to the suitability of the equipment.

Page 6: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 6 of 19

The form of the trial must be planned so as to be able to assess:

The impact of the equipment on the operation of the network;

The impact on, and compatibility with, associated equipment and buildings (e.g. substation design, cable joints and terminations);

Practicality of installation and commissioning, including ergonomic aspects and CDM requirements;

Operational compliance with Distribution Safety Rules;

Ergonomic aspects of operation including risks of operator error;

Assessment of maintenance requirements, and outage constraints for replacement of major components and availability of spare parts:

A template is to be produced that allows this equipment to be added as an equipment type in the Asset Register where applicable;

If applicable, symbols are to be added to PowerOn or (Enmac):

It will not generally be required to commission equipment onto the network as part of a trial. Practical considerations will determine whether the trial takes place within the UK Power Networks footprint, on a site elsewhere or at the factory.

The following considerations must be taken into account when planning a trial.

Impact of the trial on day to day operation of the network;

Written assessment by regarding safety of the equipment;

Exposure of equipment to wide cross section of design and field staff – those that will ultimately be responsible for installing, commissioning, operating, maintaining, decommissioning and disposing of the equipment;

Exposure of equipment to operational staff from differing geographical areas:

The whole life cycle of the equipment from ‘cradle to grave’ must be carefully considered and documented.

At this stage it is necessary to evaluate the trial and decide whether:

It is appropriate to proceed;

To return to the initial stage requesting that the manufacturer make modifications to the equipment;

To reject the equipment as being unsuitable:

5.3 Technical Approval

Technical approval can only be given once it is determined that the equipment is suitable for usage on the network. Technical approval is granted by the UKPN Director of Asset Management in the following circumstances:

It has been established that the equipment complies with UK Power Networks Technical Specifications;

A written assessment confirming suitability regarding safety of installation and operation;

A suitable and thorough trial has been carried out and documented;

Learning points from a trial have been fully implemented;

A detailed roll-out plan is documented and in place;

A suitable training package is provided if required;

Commissioning, Operations and Maintenance Manual provided if required:

Page 7: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 7 of 19

Equipment is formally approved when an UKPN Equipment Approval Standard is signed by the Director (or his delegated authority) of UKPN Asset Management and placed on the UK Power Networks Document Library.

5.4 Training

Training must be carried out before rollout but not so far in advance that the value of the training is reduced. The training of equipment must be carried out in a well planned, organised and resourced manner.

UKPN Asset Management will assist HSS&TT, in conjunction with Procurement and Logistics (where appropriate), to:

Ensure that suitable training packages are produced;

Identify which areas of the business require training and to what level the training is required;

Use key contacts within business areas to agree geographical areas where training is required, the format of training and some indication of the number of participants;

Engage the Training Centre to organise and deliver training in conjunction with key business contacts. Technical support should be provided by UKPN Asset Management if required;

Ensure availability of equipment required for training;

Communicate the training dates clearly, using appropriate media – e.g. posters, email, Team Briefs:

5.5 Rollout

The successful rollout of new equipment is a multi-departmental task requiring UKPN Logistics, Procurement, Asset Management, the manufacturer and the end user to work closely together to an agreed implementation plan.

The implementation plan owner shall be agreed in advance of rollout and shall publish an agreed plan which has been approved by all interested parties.

Rollout of equipment shall not commence until:

Equipment is formally approved and a UKPN Equipment Approval Standard Document issued.

Required Asset Register templates have been created (refer to EOP 12-0213);

Any changes or addition to control system symbols have been made;

Suitable and sufficient training has been carried out in the associated geographical area and business.

5.6 Documentation

5.6.1 Installation

Installation and Commissioning procedures shall be provided by UKPN Asset Management and the manufacturer prior to the introduction of new equipment.

Additional training for installation and Commissioning Engineers will be carried out at the training stage of the introduction if practicable. It may be possible for the training of installation and commissioning procedure to be carried out at the initial rollout and installation and commissioning of the first units.

Page 8: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 8 of 19

5.6.2 Operation

Manuals detailing the operation of equipment will be made available on the UKPN Document Library (Alfresco). Operation of equipment will also be trained to appropriate staff. This may be through a formal training session with evaluation or a familiarisation session. The appropriate level of training required will be considered during the training phase of the introduction.

5.6.3 Maintenance

Procedures detailing the maintenance of equipment will be made available on the UKPN Document Library (Alfresco), and where appropriate, included as a section of the UKPN Maintenance Manual. Appropriate consideration to the maintenance requirements of a piece of equipment will be a key consideration at the trial stage of the introduction.

If considered advantageous for the whole life cycle of the product, a decision may be made to increase the quality of the product beyond the minimum for compliance with the technical specification. An example of this might be the application of enhanced paint finishes for plant.

5.6.4 Dismantlement and Disposal

A procedure for the future dismantlement and disposal of the equipment shall be considered during the trial of the equipment. This will ensure that the equipment can be safely and cost effectively disposed of taking into account appropriate Safety, Health, Environmental and Cost considerations.

6 Approved Status

6.1 Previously Approved Equipment

A UKPN Engineering Approval Standard document for equipment that is approved will be placed on the UKPN document library (Alfresco) and if necessary the external G81 website.

Equipment that is no longer purchased by UK Power Networks for contractual reasons remains technically approved, unless the reasons for not purchasing are because of poor performance, a change in the specification of the equipment, or a change in the UK Power Networks specification for that type of equipment.

Previously approved equipment will remain as approved for third parties to install onto the network for adoption by UK Power Networks with the following conditions:

The equipment is identical to that previously approved;

The equipment is manufactured in the same factory;

Spare parts will continue to be available for a minimum of 10 years;

The ENA Notice of Conformity is still valid

The UK Power Networks specification has not changed.

Page 9: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 9 of 19

6.2 New Equipment – Proposal by Third Party

If a third party installer wishes to install non approved equipment for adoption by UK Power Networks, the approval methodology as described in this document will apply.

On approach the UKPN Competition in Connections Team, will request that the Technical Sourcing and Standards Team within UKPN Asset Management will provide them with a detailed estimate of the costs and timescale involved with approving a new piece of equipment.

This will be based on the actual cost of the work, including the working time, travel and accommodation required, with no additional on-costs.

This will be sent to the third party for review and acceptance prior to the work being started.

The CiC Team will then raise an internal SAP Service Order for the cost to be allocated too, at the end of the process the third party will be invoiced for the full cost of the tasks undertaken.

"An order to UK Power Networks for the estimated cost will be required before the initial assessment can commence.

Details of the approximate guide to the current cost of approving a particular item of equipment (i.e. Cable, Switchgear, Transformers, etc.) can be found in Appendix H. This appendix will be reviewed regularly to ensure the costs are as accurate as possible.

7 Control Forms

These are listed in Appendix A.

A separate pack is available comprising the forms for completion.

When completed, these will be filed on the server in the appropriate manufacturer file.

7.1 Check List

Date complete

1 Operational staff consulted

2 Field trials complete

3 Form A completed – Manufacturer approval

4 Form B completed – Equipment approval

5 Form C completed – Factory approval

6 Form D Completed –and final approval

7 Training plan complete

8 Roll out plan complete

8 References

8.1 UK Power Networks Standards

EDS 06-0014 Secondary Substation Earthing Design

Page 10: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 10 of 19

Appendix A - Form A – Manufacturer Approval

Manufacturer

Address

Country

Equipment

Equipment type

Date

Desktop Evaluation

Previous supply to UK Power Networks

Supply to other UK Power Networks Group Companies

Supplier to others DNO’s

Reference list supplied

Failure rates

Types of defects

Record of on time deliveries

Back up service

Facilities in UK

Satisfactory YES/NO

Satisfactory customer experience (internal and external)

Factory Inspection

Factory inspected

Location

Date

Staff visiting

Quality system inspected

Environmental aspects

Attach inspection report

Satisfactory YES/NO

Form completed by:

Name Signature Position Date

Page 11: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 11 of 19

Appendix B – Form B – Equipment Approval

Manufacturer

Address

Country

Equipment

Equipment type

Date

Desktop Evaluation Actions

Compliance with IEC standards

Compliance with ENA TS

Compliance with UK Power Networks specification

Defects in service

Latent defects

Check with NEDERS

Operational Evaluation Actions

Operability

Installation assessment

Safety

Maintenance requirement

Spares availability

Service back up

Form Completed by:

Name Signature Position Date

Page 12: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 12 of 19

Appendix C – Form C – Factory Assessment

Manufacturer

Place

Country

Date of visit

Staff visiting

Key Staff at Factory

Tabulated Assessment

Note: This form may be enhanced as necessary to suit the individual factory being assessed.

Parameter Comments Rating

Factory

Location

General layout

Access for plant

Distance from public transport and access for personnel

General cleanliness

Design

Ability to design standard products

Ability to design “specials”

Innovative designs

Flexibility of design process

Drawing system (CAD etc.)

Drawing storage system

Design storage system

Knowledge of design staff

Design staff knowledge of English

The product

Methods of manufacture

Materials

Page 13: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 13 of 19

Tabulated Assessment

Note: This form may be enhanced as necessary to suit the individual factory being assessed.

Parameter Comments Rating

Quality system for sub suppliers

Testing

Facilities of test area

Ability to perform required tests

Quality system

Rating Score Description

1 Very poor – unacceptable

2 Poor

3 Average

4 Good

5 Exceptional

Page 14: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 14 of 19

Main Statistics

Factory Information

Factory location

Description of factory

No. of Employees in factory

Total Area of factory

Area of production plant

Sales Markets Domestic

Export

Maximum unit size produced

Maximum voltage produced

Failures in service

Manufacturing Design Process

Manufacturing Production Process

Materials handling

Test facilities

Installation and Service

Quality And Environment

General Comments

Risks Comment Methods of Mitigation

Page 15: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 15 of 19

Appendix D – Form D – HSS Approval and Final Sign Off

Manufacturer

Address

Country

Equipment

Equipment type

Date

HSS Approval

Compliance with UK Power Networks safety rules

Compliance with UK Power Networks Environmental requirements

Training Requirements

Equipment available for training

Form completed by:

Name Signature Position Date

Final Approval of Equipment:

Name Signature Position Date

Page 16: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 16 of 19

Appendix E – Process Flow Diagram

Identify need from

NAMP or

Business

Identify critical

issues to ensure

there are no

‘showstoppers’

Assess Supplier, Factory and ProductProcurement

involvement

Technical

compliance - type

test

Operation &

Safety - human

factors.

Assess training

needs

User feedback

Decide on

introduction

e.g. small batch

Produce training

materials

Training and full-

scale introduction

New

technology –

R & D

Yes

No

Set up project

Everything

OK?

Yes

NoSeek new supplier

or product

Request from

customer installerYes

Page 17: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 17 of 19

Appendix F – Switchgear

Request to consider new equipment

ENA Notice of Conformity?

Yes

Reject requestNo

IEC

ISO

ANSI

Type tests & literature available?

No

Other UK users?

Yes

No

Consultant to review and report

Yes

Meet suppliers Tests valid?

Yes

Yes

Yes

Plant inspection

No

Plant complies with UKPN operational

requirements?

No

Factory inspection

Yes

Satisfactory inspection?

No

Accept equipment implementation using

EDS 08-0117

Yes

SWITCHGEAR

Designed, manufactured and

tested to recognised standards?

Page 18: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 18 of 19

Appendix G - Transformers

Request to consider new transformer

UKPN standard ratings requested?

Yes

Reject requestNo

IEC

ISO

ANSI

No

Yes

Factory inspection satisfactory?

Yes

Approve schedules

Yes

No

No

Factory acceptance tests

Approve transformer

Transformers

Designed, manufactured and

tested to recognised standards?

Query why standard ratings not requested

Other UK users?Response

satisfactory?YesContact other users No

Design Review

Page 19: EDS 08-0117 Introduction of New Technology and …library.ukpowernetworks.co.uk/library/asset/d453b327-dbbc-4624-9a...INTRODUCTION OF NEW TECHNOLOGY AND EQUIPMENT ... Departure from

Introduction of New Technology and Equipment Document Number: EDS 08-0117

Version: 8.0

Date: 30/03/2017

© UK Power Networks 2017 All rights reserved 19 of 19

Appendix H – Current Estimated Costs of Approving New Equipment

The table below shows the current high level estimated cost of approving a particular type of new equipment. The list is for indicative purposes only and does not necessarily reflect the actual cost that would be charged to a third party.

Plant Description Estimated Cost of Approval

LV Service Cables £3,000

LV Mains Cables £3,500

11kV Cables £6,000

33kV Cables £8,500

132kV Cables £11,000

Distribution Transformers £7,500

Ring Main Units (6.6 or 11kV) £12,500

11kV or 33kV Panel Switchgear £25,000

Grid or Primary Transformer £20,000

132kV GIS Switchgear £40,000