EDP Renewables Canada Ltd. 1320B – 396 11 Avenue SW
Calgary, Alberta T2R 0C5 Toll-free: 1-844-624-0330
www.sharphillswindfarm.com www.edpr.com
January 14, 2019
EDP Renewables Canada Ltd. 1320B – 396 11 Avenue SW Calgary, Alberta T2R 0C5 RE: Sharp Hills Wind Farm
Dear Stakeholder,
Thank you for your ongoing interest in the Sharp Hills Wind Farm (Project). In December 2018, we provided Project updates, including further information on the wind farm layout and number of turbines. As a result of detailed engineering studies, EDP Renewables Canada Ltd. (EDPR) has now updated some parts of the collector system layout.
The locations of the turbines, meteorological towers, access roads, O&M building, substation and laydown yard have not changed. The total Project size will remain at 298.2 megawatts (MW). The Project will continue to have two phases, Sharp Hills I and II:
• Sharp Hills I will continue to move forward with 59 turbines (247.8 MW). • Sharp Hills II will continue to move forward with 12 turbines (50.4 MW).
Accompanying this letter are two documents that provide more detailed information about the proposed Project modifications and EDPR’s participant involvement program:
• Project Infrastructure and Noise Map, which shows the location of the updated collector system layout. The noise impact assessment results are shown on the same map and are the same as those shown in the December 2018 Project Specific Information Package (PSIP).
• Alberta Utilities Commission Brochure, Public involvement in a proposed utility development.
The Shadow Flicker Map has not been included as these results have not changed since the December 2018 PSIP. Visual simulations remain available on our website at www.sharphillswindfarm.com.
We will continue to engage with the community, landowners, and local government over the coming weeks, and we look forward to receiving your feedback about the Project and these changes.
EDP Renewables Canada Ltd. 1320B – 396 11 Avenue SW
Calgary, Alberta T2R 0C5 Toll-free: 1-844-624-0330
www.sharphillswindfarm.com www.edpr.com
Electronic Communications
Many stakeholders have requested regular electronic notifications on the Project updates and progress. As a result, we have set up a service on the Sharp Hills website under the section titled “Sharp Hills Mailing List”. Click the “Sign Up” button to access an online form to provide your consent to EDPR sending electronic communications. Please provide your contact information in this online form (e-mail address, mailing address and phone number).
Within this form you can elect to sign-up for one or both the following services on our Project website:
1. Construction Updates - join the e-mail list for regular updates, including construction activities and potential traffic impacts.
2. Community Newsletters - occasional industry, company and project updates, and future consultation materials.
Contact us
For additional information on the Project, please visit our website at www.sharphillswindfarm.com. If you have questions or comments, please contact us directly at 1-844-624-0330 or [email protected].
Kind regards,
Ryan O’Connor Project Manager, EDP Renewables Canada Ltd. Email: [email protected]
!
!
!P
d
!P
!P
d
dR
d
!P !P
d
d
dR
dR
!P
!P
!P
d
!P
d
!P
d
!P
&,&, &, &,&,
&,
&,&,
!P
XY
Y
XY
d
6
GF
GF
GF
88
8
8
8
88 88
88
8
88 8
8
88
888 8 88
8
8
8
8
88
8
8
8888
8
8
888
8
8
8
8
8
888
8888888
88
8
8
88888
8
8
888
8
8
88
8
88
8
8
8
88
88
8
8
8
8
8
8
88
8
8
8
8
8
88
8
88
8
8
8
8
8
8
8
88
8
8
8
8
8
888
!O
!O
!O!O
!O
!O
!O
!O
!O!O
!O
!O
!O
!O
!O
!O
!O
!O
!O
"S
!C
"/
! ! !!
!!
!
!!
!!
!!
! !!
!!
!!
!!
!
!
! !
!!
!
!
!!
!
!
!
!
!!
!!
!!
! !
!
!
!!
!!
!!
!
!?!?
!? !? !(!( !( !(
!?!?
!?
!?!?
!?
!(!(
!(
!(
!(
!?
!(!(
!(
!
!
!
!
!
!?
!ProposedSubstation
GrassyIslandLake
Berry Lake
Currant Lake
Misty Lake
SPECIAL AREA NO. 3SPECIAL AREA NO. 4
Tp.33 Rg.4Tp.33 Rg.6
Tp.32 Rg.4
Tp.31 Rg.5
Tp.32 Rg.5
Tp.31 Rg.6
Tp.32 Rg.6
Tp.33 Rg.5
NEW BRIGDEN
SEDALIA
HWY 41
HWY 886
Township Road 340A
Township Road 312
Rang
e Roa
d 42
Rang
e Roa
d 35
Township Road 310
Rang
e Roa
d 40
Township Road 332
Rang
e Roa
d 54
Township Road 330
Township Road 341
Rang
e Roa
d 50
Township Road 320
Rang
e Roa
d 60
Range
Road
64A
TownshipRoad 323
Rang
e Roa
d 62
Rang
e Roa
d 53
Township Road 322
Township Road 340
Rang
e Roa
d 55
Rang
e Roa
d 61
Township Road 335
Township Road 311
Rang
e Roa
d 45
Met 2
Met 1
Met 3
16
14
13
15
40dB
40 d
B
40dB
40dB
40
dB
40 d
B
4 0 d
B
40 dB
40dB
40dB
40 dB
40dB
40 dB
40dB
40 dB 40 dB4 0d B
4 0 dB
40 dB
40 dB
6566
6970
7576 77
78 79 80
86STW_4
71 7273 74
81 82 83 8485
87 88 89
1 23 4
5 6 7
8 9
10 1112 13
14 15 1617 18
1920
21 2223
24 2526
3233 34
2728 29
3031
40
42 43 44
49 50 51 5253A54A
5657 58
59 6061 62 63 64
90 91
92
94
STW_1
93A
6
8
12
3.24
9
7
5.15.2
11
12.2
10
3.1
12.1
Operations& MaintenanceFacility
ATCO
Elec
tric 2
40kV
(9L4
6)
²
LegendProposed Turbine Locations (71)! Phase 1
!( Phase 2
!? Removed TurbineCurrent Project BoundaryNon-Project Land
!O Visual Representation PointsLand Use!C Operations & Maintenance Facility"/ Proposed Laydown Yard Location
"S Proposed Substation LocationProposed Meteorological TowersGF Phase 1GF Phase 2
8 Participating House
8 Non-Participating HouseOil & Gas Facility Type!P Compressor Station
d Crude Oil Multiwell Proration Battery
d Crude Oil Single-Well Battery
dR Field Meter Station
6 Gas Gathering System
Y Gas Plant Acid Gas Flaring
XY Gas Plant Sweet
d Gas Single-Well Battery
&, Pumping Well
40 dBA Noise ContoursPotential Overhead Collector SystemProposed Turbine Access RoadsProposed Underground Collector SystemProposed Collector System Additionssince December 2018 PSIP2km Notification ZoneSpecial Areas 3 & 4Visual Simulation Photo Orientation & Extent
Transmission Line VoltageExisting 240kV (Single Circuit)Numbered HighwaysMunicipal RoadsHydrographyClass 3 - 5 WaterbodiesTownship
0 2.5 5 7.5 101.25Kilometres
"
"
"
"
UV886UV899
UV12
UV13
UV9
UV41UV884
UV872
CORONATION
OYEN
PROVOST
CONSORT
SHARP HILLS WIND FARMProject Infrastructure and Noise Map for 298.2 MW Wind Farm
Author: Solas Energy Consulting Inc. Date / Time: 15 January 2019 / 05:04 PM Version: REV .6 Datum: North American 1983 Projection: NAD 1983 UTM Zone 12N Scale: 1:110,000 Sources: EDPR, ESRI, AER, Ventyx, AltaLIS, RWDI.
NotesTurbine labels with "STW" refer to those turbines thatare "Subject to Waiver" from adjoining non-projectlandowners.The Project boundary is not representative of theentire leased land base.